Name of the Project/s

M/s. Indus Ferrotech Ltd. At D-3,DCompany Name,


3/1& D-3/2
,Kagal-Hatkanangale Five Star
Address,
industrial
City,Area,Dist-kolhapur
State - PinCode
( Maharashtra)India.

S. No in the Schedule

8 (a)

Proposed capacity/area/length/tonnge to be
handled/command area/lease area/number
of wells to be drilled

Total Plot Area of the Project: 62,491 Sq. mt.

New/Expansion/Modernization

New

Existing capacity/Area etc.

Total Plot Area: 62,491 Sq. mt.


Built up Area: - 24381.66 Sq.mt.

B Category Project

Category of Project i.e. A or B

Does it attract the general condition? If Yes Not Applicable


please Specify.

Does it attract the specific condition? If yes Not Applicable


please specify.

Location

Kagal-Hatkanangale
Five star
MIDC
xxx (specify
if MIDC)

Plot/survey/Khasra No

D-3,D-3/1&
D-3/2
, Five Star M.I.D.C
288/4
xxx survey No

Village

District

Talandage
Khed
yyy
Hatkanangale
jjjKhed
Kolhapur
zzz Pune

State

Maharashtra

Tehsil

10

Nearest railway station/airport along with Kolhapur Railway junction (30 km SW)
distance in kms

11

(25 Km) & 9Km From


the
Nearest town, city, District Headquarters Kolhapur
yyyy
National Highway 4 (Mumbai Banglore)
along with distance in

12

Village panchyats Zilla Parishad, municipal D-3, D-3/1& D-3/2, Kagal-Hatkanangale


aaa, bbb, ccc, ddd with phone numbers
corporation, Local body (Complete postal Five Star industrial Area, Kolhapur.
addresses with telephone nos. to be given)

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 1

Form I &IA and Consolidated statement


Not Applicable

24

Forest land involved (hectares)

25

Whether there is any litigation pending Not Applicable


against the project and/or land in which the
project is propose to be set up?
(a)Name of the Court.
(b)Case No.
(c) Orders /Directions of the court, if any
and its relevance with the proposed Project.

Screening Category
(II)

8(a) to sub category B

Activity

1. Construction, operation or decommissioning of the Project involving actions, which will


cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
Yes Details thereof (with approximate quantities / rates, wherever
Sr. Information/Checklist
/
possible) with source of information data
No.
confirmation
No
1.1
Permanent
or No No change in Land Use
temporary charge in
land use, land cover or
topography including
increase in intensity of
land use (with respect
to local land use plan)
1.2
Clearance of existing No Land is leveled.
land, vegetation and
No demolition of building involved.
building?
No cutting of trees.
1.3

Creation of new land


uses?

No

--

1.4

Yes

Geotechnical Investigation is already conducted.

1.5

Pre-construction
investigation e.g. bore
houses, soil testing?
Construction works?

Yes

1.6

Demolition works?

No

62% construction work done out of 24,381.66 Sq.mt sanctioned


built up area.
There is no demolition work.

1.7

Temporary sites used


for construction works
or housing of
construction workers?
Above ground
building, structures or
earthworks including
linear structures, cut

No

No residential workers or labor camp.

1.8

Yes Above ground building, structures and Excavation work only for
the construction of footings & area grading.

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 3

Form I &IA and Consolidated statement


Sr.
No.

Information/Checklist
confirmation

Yes
/
No

Details thereof (with approximate quantities / rates, wherever


possible) with source of information data

No

--

1.10

and fill or excavations


Underground works
including mining or
Tunneling?
Reclamation works?

No.

--

1.11

Dredging?

No

--

1.12

Offshore structures?

No

--

1.13

Production and
manufacturing
processes?

Yes

1.14

Facilities for storage of


goods or materials?
Facilities for treatment
or disposal of solid
waste or liquid
effluents?

Yes

Company proposed production capacity Fettling, Machining,


painting of jobs (1, 00,000 nos.) & surface treatment (Mn
Phosphating(surface treatement),Electroless nickel plating =5000
nos/m),
Goods and Material is stored in proper storage facility.

Yes

A) During Construction

1.9

1.15

phase:
Non Hazardous waste generated from the construction is reused
predominantly for filling and compaction of site. Empty gunny
bags are returned to suppliers. Scrap Mild steels bars/ general
mild steel items to send back for rerolling.
There is no labor camp. The day workers are served by regular
existing sewage treatment plant.
Hazardous waste was not generated during construction phase
B) During Operation Phase:
Total solid waste: 166 kg/day
Biodegradable waste: 116 kg/day. (will be handled over to
authorized vendors for disposal)
Non-biodegradable waste: 50 kg/day. will be handed over to
authorized contractors.
Use of dried STP sludge as manure.

Non Hazardous Waste :


Sr. Type
No.
1
Griding
/Fettling
powder
2.
Griding
wheel
3.
Shot
blasting
dust
4.
CI boring
/MS
Turning

Quantity
25

UoM

Disposal

MT/M

Sale

nos.

Sale

25

MT/M

Sale

300

MT/M

Sale

2000

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 4

Form I &IA and Consolidated statement


Sr.
No.

Information/Checklist
confirmation

Yes
/
No

Details thereof (with approximate quantities / rates, wherever


possible) with source of information data

Hazardous waste Details :


Sr. Item no. Type of
Quantity
No. as per
waste
HW
Schedule
1.
21.1
Paint
30MT/A
sludge
2.
5.2
Hand
3.7MT/A
gloves,oil
soked
rags/cotton
5.1
Used
15 KL/A
3
oil/spent
oil
4
33.3
Discarded
6000
containers
nos/A
5
12.2
Alkali
1.44MT/A
residue
6
14.1
Nitrite
7MT/A
containing
sludge
7
12.3
Spaint
3.6MT/A
bath
sludge
8
12.5
Phosphate
6.2MT/A
sludge

Disposal

CHWTSDF
CHWTSDF

Authorised
reprocesser/recycler
CHWTSDF
CHWTSDF
CHWTSDF

CHWTSDF

CHWTSDF

Sewage:
Sewage generation : 24 m3/day
Capacity of STP (CMD): 25 m3/day
STP Technology: MBR
Effluent:
Effluent generation: 18 m3/day
Capacity of ETP (CMD): 4 m3/Hr
Capital Cost: Rs 80 Lakh
O & M Cost: Rs 11 Lakh / Year
1.16

1.17

1.18

Facilities for long term


housing of operational
workers?
New road, rail, or sea
traffic during
construction or
operation?
New road, rail, air
waterborne or other
transport infrastructure
including
new
or

No

No

No

xxx
Site is already in Kagal-Hatkanangale
Five star MIDC; all
transportation facility is easily available.

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 5

Form I &IA and Consolidated statement


Sr.
No.

1.19

1.20

1.21

1.22
1.23

Information/Checklist
confirmation
altered routes and
stations, ports, airports
etc?
Closure or diversion of
existing
transport
routes or infrastructure
leading to changes in
traffic Movements?
New or diverted
transmission lines or
pipelines?
Impoundment,
damming, culverting,
realignment or other
change o the hydrology
of watercourses or
aquifers?
Stream crossings?
Abstraction or transfers
of water from ground
or surface waters?

Yes
/
No

Details thereof (with approximate quantities / rates, wherever


possible) with source of information data

No

No Diversion or closer of existing transport routes or any other


infrastructures to changes.

No

No

No
No

For Construction: MIDC


During this proposed construction period we may need
Water 20 KLD. Total consumption will be within consented
quantity.
For Operational Phase: MIDC
Daily fresh water requirement = 47 m3/day
Recycled water reused = 40 m3/day
One time water requirement 87 m3/day

1.24

1.25

1.26

1.27

Changes in water
bodies or the land
surface affecting
drainage or runoff?
Transport of personnel
or materials for
construction, operation
or decommissioning?

Long-term dismantling
or decommissioning or
restoration works?
Ongoing activity
during
decommissioning
which could have an
impact on the
environment?

No

Yes

(Source of water is MIDC)


Water drains of appropriate capacity will be designed.

No

Transportation of Raw material and final product


Mainly, will be by road. Within factory premises, all
Raw material will be safely transported by carboys
Thorough trolleys.
The movement of vehicular traffic would be restricted
to only during receipt of materials and dispatches of
Materials. Hence the impact due to noise pollution will
be occasional. Precautions will be taken to reduce the impact of
the vehicular movement by trying to avoid the vehicular trips
during peak hours.
--

No

--

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 6

Form I &IA and Consolidated statement


Sr.
No.

Information/Checklist
confirmation

1.28

Influx of people to an
area in either
temporarily or
permanently?
Introduction of alien
species?
Loss of native species
or genetic diversity?
Any other actions?

1.29
1.30
1.31
2.

Sr.
No.
2.1
2.2

Yes
/
No
Yes

Details thereof (with approximate quantities / rates, wherever


possible) with source of information data
Total Manpower is on project site 665 nos. including contract
workers and staff.

No

--

No

--

No

--

Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or ion short
supply):

Information/Checklist confirmation
Land especially undeveloped or
agricultural land (ha)
Water (expected source & competing
users) unit : KLD

No

Details thereof (with approximate


quantities / rates, wherever possible) with
source of information data
--

Yes

During Construction Phase :

Yes /
No

During this small construction period we


may need water 20 KLD. Consumption will
be within consented quantity.
During Operational Phase -

Total Daily Water Requirement: 87 m3/ day.


Fresh water intake :
For Domestic : 13 m3/ day.
For Processing: 23 m3/ day.
For Gardening : 34 m3/ day.

2.3
2.4

Minerals (MT)
Construction material stone,
aggregates, and / soil (expected source
MT)

No
Yes

2.5

Forests and timber (source MT)

No

2.6

Energy including electricity and fuels


(source, competing users) Unit: fuel

(When sewage Treatment Plants is run in the


full-fledged condition treated water will be
reused for Gardening. So that extra load on
the MIDC water supply system is reduced)
-For proposed Building structures, estimated
Construction material like Cement, Sand,
Grits, Bricks, Steel, etc. shall be purchased
from the local vendors.
Recycled shuttering & Carpentry kind of
material will be used for Proposed structures
During Operational Phase -

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 7

Form I &IA and Consolidated statement


Sr.
No.

Information/Checklist confirmation

Yes /
No

(MT), energy (MW)

2.7

Any other natural resources (use


appropriate standard units)

No

Details thereof (with approximate


quantities / rates, wherever possible) with
source of information data
Source: MSEDC
Connected
Load

2.5 MVA

Maximum
Demand

1 MVA

DG Set

1.5 MVA

--

3.
Use, storage, transport, handling or production of substances or materials, which would be
harmful to human health or the environment or raise concern about actual or perceived risks to
human health.
Sr.
No.

Information/Checklist confirmation

Yes /
No

3.1

Use of substances or materials, which are


hazardous (as per MSIHC rules) to human
health or the environment (flora, fauna, and
water supplies)

Yes

3.2

Changes in occurrence of disease or affect


disease vectors (e.g. insect or water borne
diseases)
Affect the welfare of people e.g. by
changing living conditions?
Vulnerable groups of people who could be
affected by the project e.g. hospital
patients, children, the elderly etc.,
Any other causes

No

3.3
3.4

3.5

4.
Sr.
No.
4.1
4.2

Details thereof (with approximate


quantities / rates, wherever possible)
with source of information data
Construction :
Minimum amount of waste will be
generated during construction which
will be confined within existing
building structure
Operational Phase :
Hazardous waste generated from
Production process will be send to
CHWTSDF.

No

Construction only for short


duration with small number of
Workers.
Positive effect in the Socio economic
conditions.
--

No

--

No

Production of solid wastes during construction or operation or decommissioning


(MT/month)
Information/Checkli Yes / Details thereof (with approximate quantities / rates,
st confirmation
No
wherever possible) with source of information data
Spoil, overburden or Yes The Top soil will be used for gardening and other for refilling
mine wastes
the plinth.
Municipal
waste Yes Construction Phase :
There is no labor camp. The day workers waste will be taken
(domestic and or
care of in the existing premises.
commercial wastes)

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 8

Form I &IA and Consolidated statement


Sr.
No.

Information/Checkli
st confirmation

Yes /
No

4.3

Hazardous wastes (as


per Hazardous waste
Management Rules)

Yes

4.4

Other
industrial
process wastes

Yes

Details thereof (with approximate quantities / rates,


wherever possible) with source of information data
Operation Phase:
Sr. Type
Quantity UoM
Disposal
No.
1.

Griding
/Fettling
powder

25

MT/M

Sale

2.

Griding
wheel

2000

nos.

Sale

3.

Shot
blasting
dust

25

MT/M

Sale

4.

CI boring
/MS
Turning

300

MT/M

Sale

Construction Phase:
Hazardous waste was not generated from the construction
phase.

Sr. Item no.


No.
as per
1.
21.1

Type of
waste
Paint
sludge

30MT/A

CHWTSDF

2.

Hand
gloves,oil
soked
Used
oil/spent
oil
Discarded
containers

3.7MT/A

CHWTSDF

15 KL/A

Authorised
reprocesser/recycler

1.44MT/A CHWTSDF

5.2
5.1

3
4

33.3

12.2

Alkali
residue

14.1

12.3

Nitrite
containing
sludge
Spaint

Quantity

6000
nos/A

Disposal

CHWTSDF

7MT/A

CHWTSDF

3.6MT/A

CHWTSDF

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 9

Form I &IA and Consolidated statement


Sr.
No.

Information/Checkli
st confirmation

Yes /
No

Details thereof (with approximate quantities / rates,


wherever possible) with source of information data
bath
sludge
8

4.5
4.6

4.7

4.8
4.9
4.10
4.11

12.5

Phosphate
sludge

6.2MT/A

CHWTSDF

Surplus product
Sewage sludge or
other sludge from
effluent treatment.
Construction
or
demolition wastes.

No
Yes

Redundant machinery
or equipment.
Contaminated soils or
other materials.
Agriculture wastes.
Other solid wastes.

No

Only construction wastes. Solid waste would be


mainly due to excavation in the form of rubble and
Soil. This soil and rubble will be reused for leveling
of project site.
--

No

--

No
No

---

Yes

-Dried sludge from STP will be used as manure for the plants.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)


Sr.
No.

Information/Checklist
confirmation

Yes /
No

5.1

Emissions from combustion of fossil


fuels from stationary or mobile
sources

Yes

5.2

Emissions from production processes

Yes

5.3

Emissions from materials handling


including storage or transport

5.4

Emissions
from
activities including
equipment

construction
plant and

Yes /
Marg
inal

5.5

Dust or odours from handling of


materials including construction
materials, sewage and waste

Yes

Yes

Details thereof (with approximate quantities


/ rates, wherever possible) with source of
information data
D.G. Sets will be provided only in case of
power failures during operational phase. The
Pollutants like SO2 that may arise from
emissions from D.G. Sets will be discharged
through vent of proper height.
Nominal emissions are expected from process
plant while operation, as and When operated.
Approval of CTE & CTO will be taken from
MPCB
For pollution control, we will provide the
scrubber.
The earth moving machineries and dumpers
will be used. Pollution under control ( PUC)
will be ensured .Proper and safe storage as per
the regulation shall be practiced & certificates
are made mandatory
Nominal emissions expected from earth
moving machineries and dumpers .Pollution
under control (PUC) certificates are Made
mandatory.
Water sprinkling on ground and new
construction will be done at regular intervals to
reduce spreading of dust particles.
Dust levels are expected during the
construction phase. Proper measures such as
sprinkling of water on the ground and new
Construction will be done at regular intervals

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 10

Form I &IA and Consolidated statement


Information/Checklist
confirmation

Yes /
No

No
No

5.8

Emissions from incineration of waste


Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
Emissions from any other sources

Details thereof (with approximate quantities


/ rates, wherever possible) with source of
information data
to reduce the Spreading of the dust particles.
Sewage: - It shall be treated in Sewage
treatment Plant.
Effluent: It Shall be treated in Effluent
treatment Plant.
Waste:- Waste is segregated as per category
and disposed off as per Hazardous Waste
(Management, Handling and Transboundry
Movement) Rules, 2008
---

No

--

6.

Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr.
No.

5.6
5.7

Sr.
No.

Information/Checklist
confirmation

Yes / No

6.1

From operation of equipment e.g.


engines, ventilation plant, crushers.

Yes but
negligible

6.2
6.3
6.4

From industrial or similar processes.


From construction or demolition.
From blasting or piling.

No
No
No

6.5

From construction or operational


traffic.

Yes

Details thereof (with approximate


quantities / rates, wherever possible)
with source of information data
1. No additional DG set, No Crusher is
planned for construction. No construction
will be undertaken in the night.Use of
equipment generating Noise less than 75
dB (A) in day time.
2. Noise generating constructional
activities would be carried out only during
day time.
3. Installation, use and maintenance of
mufflers on equipment would be ensured.
4. Workers working near noise
construction machinery would be supplied
with necessary Personnel protective
Equipments like ear muffs/ear plugs etc. as
per requirement.
-There is no demolition activity.
No blasting will be undertaken.
During Construction phase:
There will be transport of materials for
construction work. Precautions will be
taken to reduce the impact of the vehicular
movement such as vehicular trips will not
be at peak traffic hours.
Operation Phase :
The vehicular parking shall be restricted
only in the adequate parking area provided,
which would help in reducing noise and air
pollution
due
toVehicular
movement. The project proponent has

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 11

Form I &IA and Consolidated statement

6.6
6.7

From lighting or cooling systems.


From any other sources.

No
No

proposed good tree plantation which will


also help to reduce the noise level and
enhance air quality.
---

7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:
Sr.
No.
7.1

Information/Checklist confirmation
From handling, storage, use or spillage
of hazardous materials.

Yes /
No
No

Details thereof (with approximate


quantities / rates, wherever possible)
with source of information data
Hazardous wastes like Paints sludge as per
Hazardous Waste (Management, Handling
and Transboundry Movement) Rules,2008.
Well equipped Fire fighting system shall
be installed. Risk assessment and disaster
management plan shall be prepared.
Formation of Safety Department under
Safety Officer to take care of Occupation,
Hazard & Hygiene.

7.2

7.3

From discharge of sewage or other


effluents to water or the land (expected
mode and place of discharge).
By deposition of pollutants emitted to
air into the land or into water.

No

Treated sewage will be reused for


gardening within the premises.

No

Dust will be generated during construction


phase from earthworks and movement of
vehicles. Appropriate fugitive dust control
measures, including water sprinkling of
exposed areas and dust covers for trucks,
will be provided to minimize any impacts.

7.4
7.5

From any other sources.


Is there a risk of long term build up of
pollutants in the environment from
these sources?

No
No

---

8. Risk of accidents during construction or operation of the Project, which could affect human
health or the environment
Sr.
No.
8.1

Information/Checklist confirmation
From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances

Yes /
No
No

Details
thereof
(with
approximate
quantities / rates, wherever possible) with
source of information data
Blasting is not allowed so risk of explosion
does not exist. Fire Fighting system is
operational to control any fire hazard.
Secondary containments are provided for all
liquids spillages. Hazardous wastes generated
will be disposed off as per The Hazardous

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 12

Form I &IA and Consolidated statement


Waste (Management, Handling and
Transboundry Movement) Rules, 2008.
8.2
8.3

From any other causes.


Could the project be affected by
natural disasters causing environmental
damage (e.g. floods, earthquakes,
landslides, cloudburst)?

9.

Factors which should be considered (such as consequential development) which could lead
to environmental effected or the potential for cumulative impacts with other existing or
planned activities in the locality

Sr.
No.
9.1

Information/Checklist
confirmation

No
No

Yes / No

Lead to development of supporting,


lities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.:
Supporting infrastructure
(roads, power supply, waste or
waste water treatment etc)

No

-There is no history of such a disaster in the


area under reference. However, drains will
be designed of appropriate size. Structures
will be designed as per the Seismic zone
requirements.

Details
thereof
(with
approximate
quantities / rates, wherever possible) with
source of information data

Power, water, roads, wastes disposal


approvals are granted by as per State
Government rules hence no impact would be
observed for below mentioned

Housing development
Extractive industries
Supply industries

9.2

9.3

Other
Lead to after-use of the site, which
could have an impact on the
environment
Set a precedent for later
developments

9.4

Have cumulative effects due to


proximity to other existing or
planned projects with similar
effects

(III)

Environmental Sensitivity

Sr.
No.
1

Information/Checklist
confirmation
Areas protected under international

No

--

No

The additional proposed Structures are to


support storage activities. Like, receiving of
materials, dispatch.

No

The additional proposed Structures are to


support storage activities. Like, receiving of
materials, dispatch.

Name/
Identity
No

Aerial distance (within 15 km.)


Proposed project location boundary
--

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 13

Form I &IA and Consolidated statement

Sr.
No.

4
5
6

7
8
9

10

11

12

(IV).

Information/Checklist
confirmation
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
Areas which are important or
sensitive for ecological reasons
Wetlands, watercourses other water
bodies, costal zone, biospheres,
mounting, forests
Areas used by protected, important
or sensitive species of flora or
fauna for breeding, nesting,
foraging, resting, over wintering,
migration
Inland,
costal,
marine
or
underground waters
State, national boundaries
Routes or facilities used by the
public for access to recreation or
other tourist, pilgrim areas
Defence installations
Densely populated or built-up area
Areas occupied by sensitive manmade land uses (hospitals, schools,
places of worship, community
facilities)
Areas containing important, high
quality or scarce resources (ground
water resources, surface resources,
forestry, agriculture, fisheries,
tourism, minerals)
Areas already subjected to pollution
or environmental damage. (those
where existing legal environmental
standards are exceeded)
Areas susceptible to natural hazard
which could cause the project to
preset environmental problems
(earthquakes,
subsidence,
landslides, erosion, flooding
or extreme or adverse climatic
conditions)

Name/
Identity

Aerial distance (within 15 km.)


Proposed project location boundary

Yes

There is Panchaganga
River
at 15 km SE
a xxx from yyy
km distance
direction from site.

No

--

No

--

No
Yes

-State Highway No. 4- Mumbai Bangalore


within 9 Km.

No
No
Yes

-NA
As industry is located in MIDC Area all
infrastructure facilities are available.
.

No

--

No

--

No

--

Proposed Terms of Reference for EIA studies:

Not Applicable.

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 14

Form I &IA and Consolidated statement

Form IA
APPENDIX II
(See paragraph 6)
FORM-1 A (only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed environmental management plan
& monitoring programme)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1. Will the existing land use get significantly altered from the project that is not consistent with
the surroundings? (Proposed land use must conform to the approved Master Plan /
Development Plan of the area. Change of land use if any and the statutory approval from the
competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features
of the proposed site (within 500 meters) and (iii) The site (indicating levels & contours) to
appropriate scales. If not available attach only conceptual plans.

Land Use Pattern:


The project falls within Kagal-Hatkanangale MIDC. The site is situated at D-3, D-3/1, D-3/2,
Kagal-Hatkanangle Five Star Industrial area, Dist-Kolhapur (Maharashtra) INDIA.
The project is an Industrial construction activity for manufacturing of Fettling, Shot blasting, Painting, &
machining Casting of ancillaries for tractors and farm equipments automotives and Engineering products.
The additional proposed structures are to support Storage activities like, receiving of materials, Separate
Storage and dispatch.

Agriculture / Livestock:
There is no agricultural activity in the vicinity of the proposed area. Industry is located in Kagal
Hatkanangale five star MIDC.
Please refer the enclosed maps showing the following:
(i) Google Image
(ii) Layout of the site

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 15

Form I &IA and Consolidated statement


1.2.

List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.
I.

PROJECT DETAILS :

a. Name & Location: M/s. Indus Ferrotech Ltd.


A. Plot History:
This project is located at D-3, D-3/1, D-3/2, Kagal-Hatkanangle Five Star Industrial area, DistKolhapur (Maharashtra) INDIA, having plot area 62,491.00 Sq. mt.

The Built-up area of the Project is 24,381.66 Sq.mt. Now we are applying for Obtaining
Environmental Clearance for the industrial construction project under 8(a) category of schedule.

b. Area Statement:

No. Description

Area Sq. Mt.

a.

Total Plot Area:

62,491

b.

Built-up area approved by MIDC

24,381.66

c. Parking Statement:
As an Industry is in Kagal-Hatkanangale five star MIDC, Management has provided transportation Pick
and drop facility to their staff. so required parking area (6300.68 m2) is provided for bus, cars & two
wheelers.
d. Occupancy
665 nos. of staff including Contract and permanent.
a. Water Consumption: (Domestic and flushing requirement)
1. During Construction Phase: MIDC Source
From MIDC: 20 KLD
2.

During Operation Phase:

Total Water requirement of the project is:


Sr.
No.

Description

Quantity of water required


m3/day

Source of water supply

a.
b.

Domestic
Gardening

13 m3/day
34 m3/day

MIDC
MIDC

Processing

23 m3/day

MIDC

Total

87 m3/day

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 16

Form I &IA and Consolidated statement


f. Sewage Generation:
Sewage:

Sewage generation : 24 m3/day

Capacity of STP (CMD): 25 m3/day

STP Technology: MBR

Effluent:
Effluent generation: 18 m3/day

Capacity of ETP (CMD): 4 m3/Hr

g. Solid Wastes:
During Construction phase:
The total quantities of solid waste generated will be210 MT in the project; it will be disposed off
through existing authorized and local contractor.
During Operation Phase:
Total solid waste: 166 kg/day
Biodegradable waste: 116 kg/day. (will be handled over to authorized vendors for disposal)
Non-biodegradable waste: 50 kg/day. will be handed over to authorized contractors.
Use of dried STP sludge as manure.
Non Hazardous Waste
Sr. Type
No.

Quantity

UoM

1.

Griding /Fettling powder

25

MT/M

Sale

2.

Griding wheel

2000

nos.

Sale

3.

Shot blasting dust

25

MT/M

Sale

4.

CI boring /MS Turning

300

MT/M

Sale

Disposal

Hazardous waste Details:


Sr. Item no.
No.
as per

Type of waste

Quantity

Disposal

HW
Schedule

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 17

Form I &IA and Consolidated statement


1.

21.1

Paint sludge

30MT/A

CHWTSDF

2.

5.2

Hand gloves,oil soked rags/cotton

3.7MT/A

CHWTSDF

5.1

Used oil/spent oil

15 KL/A

Authorised
reprocesser/recycler

33.3

Discarded containers

6000 nos/A

CHWTSDF

12.2

Alkali residue

1.44MT/A

CHWTSDF

14.1

Nitrite containing sludge

7MT/A

CHWTSDF

12.3

Spaint bath sludge

3.6MT/A

CHWTSDF

12.5

Phosphate sludge

6.2MT/A

CHWTSDF

h.

Power requirement:
For Construction Phase:
During Construction Phase Source: MSEDC

During Operational Phase


Source: MSEDC
Sr. No. Details
1.
Connected Load
2.
Maximum Demand
3.
D.G set

1.3.

Unit
2.5 MVA
1.0 MVA
1.5 MVA

What are the likely impacts of the proposed activity on the existing facilities adjacent to
the proposed site? (Such as open spaces, community facilities, details of the existing landuse,
disturbance to the local ecology).
No impact on adjacent facilities due to proposed development. All required pollution control
equipments in the proposed facility to control liquid, solid and air pollutant parameters.

1.4

Will there be any significant land disturbance resulting in erosion, subsidence & instability?
(Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc. may be given).
No significant land disturbance as the site is flat land. As per the Seismic Zoning Map of India,
Kolhapur
aaa region falls under Zone-II. Stability Certificate, as per prevalent IS Code will be
obtained for these buildings from registered Consulting Structural Engineer considering the
seismic forces and wind forces etc.

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 18

Form I &IA and Consolidated statement


1.5

Will the proposal involve alteration of natural drainage systems? (Give details on a contour
map showing the natural drainage near the proposed project site)
For building structure there will not be any alteration in existing natural drainage systems.

1.6.

What are the quantities of earthwork involved in the construction activity-cutting, filling,
reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc.)
Excavation in the form of rubble and soil. Part of this soil and rubble will be used
for back filling and remaining material will be disposed within the site.

1.7

Give details regarding water supply, waste handling etc during the construction period.
During Construction Phase Approximate 20 KLD water is required for proposed construction during construction phase.
Water will be utilized from existing source and it will be well within consented quantity.
Sewage will be treated in Sewage treatment plant and reused for gardening/horticulture. And it
will well within demand.

Non Hazardous waste generated from the construction is reused predominantly for filling and
compaction of site.

Will the low lying areas and wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity)
1.8

There is no low laying area and wetlands are available in the existing site which is going to be
affected due to the project

Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the
construction labour and the means of disposal)
1.9

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 19

Form I &IA and Consolidated statement


Excavated material will be generated as mentioned below; same would be used within premises
for land leveling.
Nominal dust level is expected during the construction phase. Proper measures such as sprinkling
of water on the ground and new construction will be done at regular intervals to reduce the
spreading of the dust particles.

Wastes generated by Construction laborBiodegradable garbage = 20m3 /day


Non-biodegradable garbage = NIL
Total : 20 m3 /day
The total quantities of Non-biodegradable waste generated in the project will be disposed off
through existing authorized contractor.

2.
2.1.

WATER ENVIRONMENT
Give the total quantity of water requirement for the proposed project with the breakup of
requirements for various uses. How will the water requirement be met? State the sources
& quantities and furnish a water balance statement.

Water Requirement & Sources

For Construction : From MIDC


MIDC: 20 KLD (depending upon the activity).
During Operational Phase Total Water Requirement. :
For Domestic

: 13 m3/ day.

For Gardening : 34m3/ day.


For processing : 23 m3/ day
Total Water Requirement: 87 m3 /day.
(When sewage Treatment Plants will run in the full-fledged condition treated water is reused for
flushing, paint shop & gardening. So that extra load on the MIDC water supply system will be
reduced)

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 20

Form I &IA and Consolidated statement


Net water Demand from local water supply body will be 47 m3 /day only.

Sr.
No.
1

Water demand for fire fighting is one time and occasional. Therefore water requirement for fire
fighting has not been considered while calculating daily water requirement.

Description

Input
M3/day

Loss
M3/day

Domestic

13.00

7.2

Reason for
Loss

Effluent
M3/day

Remark

22.8

Domestic
Effluent

Loss

-------

Consumption
2

Flushing

17

Loss

Gardening

34

Process

23

5.9

Processing

17.1

Industrial
Effluent

TOTAL

87

13.1

-------

39.9

-------

NIL

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 21

Form I &IA and Consolidated statement

Water Balance daily Requirement

M/s. Indus Ferrotech Ltd. At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur.

Page 22

Vous aimerez peut-être aussi