Académique Documents
Professionnel Documents
Culture Documents
SOME PRE-GROUTING
PRE GROUTING HOLES BEING DRILLED TO prevent
water inflow in THE NEXT THREE or FOUR ROUNDS OF
TUNNEL ADVANCE
PRE-GROUTING TO
REDUCE FUTURE
CONCRETE USE
....AND CURING
PROBLEMS
SKETCHES OF WHY
PRE-GROUTING IS
NEEDED MAINLY
IF TUNNELS
(AND STATIONS) ARE
NOT DEEP AND
THEREFORE
IN WEATHERED,
PERMEABLE,,
LESS STABLE
ROCK MASSES !
10
11
12
13
14
15
16
17% of zero flow stages means 1.8 conducting joints per test lengthon average
17
19
20
k = e2/12
K1 = e2/12 x e/S
e (6LS x 10-8)1/3
The equation e (6LS x 10-8)1/3 looks like this for typical S-values of 0.5 to 3.0m
Obviously it is difficult to inject cement particles into e.g. < 0.1 Lugeon rock masses
unless E ( the physical joint aperture ) >> e ( the hydraulic aperture )
22
i e PG >> PW = 1 MPa
i.e.
In Norway we use final grouting pressures in the range 5 to 10 MPa
(50 to 100 bars), when pre-injecting ahead of tunnels, successively
reducing the w/c ratio. The grouts are stable (little shrinkage or water
separation).
BUT FIRST WE MUST INVESTIGATE IF WE NEED HIGH PRESSURE
GROUTING what p
physical
y
apertures
p
do we have??
23
Can be done on core from ahead of the face, or in the tunnel close to the face
25
26
JRC value ranges derived from tilt tests and direct shear tests
CONVERSION BETWEEN (e) and (E) USING JRC0 (100mm scale)
27
THE (approx
(approx.)) LIMITS FOR INJECTION of ULTRAFINE,
ULTRAFINE MICRO and industrial cement
28
29
30
Even this is possible (all 3 cements can be injected) due to E>e, and
maybe due to use of high injection pressure causing deformation
31
32
ONE, or perhaps
ONE
h
TWO SETS ARE INJECTED..
INJECTED
BUT THE ROCK MASS IS STILL WET!
33
H d
Hydraulic
li aperture
t
changes
h
34
35
BUT. a false idea of permeability will be given with too high water pressure testing
37
Note that E can be almost doubled from 30 to 60m now OK for ULTRAFINE?
38
The difference between E and e in a UDEC-BB model (Makurat, 1988: Oslo Tunnel)
39
easiest to grout)
YELLOW (OK)GREENBLUE
needs higher pressure or finer micro/ultrafine
40
41
42
43
45
46
47
Logarithmic pressure decay with radial, laminar or turbulent flow (e.g. Cruz, 1979)
48
49
WHAT HAPPENS WITH TOO LOW PRESSURE, TOO TIGHT JOINTS, TOO
LARGE CEMENT PARTICLES..AND UNSTABLE GROUTS
THAT BLEED WATER?
50
WATER-SICK
WATER SICK ROCK
ROCK......MORE
MORE WATER AFTER PRE
PRE-GROUTING
GROUTING, THAN BEFORE !
NOTE DRY ROCK BEHIND JUMBO ((ALREADY PREGROUTED)SEE SEVERAL EXAMPLES THAT FOLLOW
52
58
59
60
61
IPT multilti
probemulti-hole
measure
ment of
grouting
(Quadros
and
d
Correa
Filho,
Filho
1995)
62
64
65
SOME OF THE
EMPIRICAL
EQUATIONS
RELATING
Q-value and
rock mass
property estimates
((allll seen iin earlier
li
lectures)
66
67
68
69
70
71
CONSEQUENCES OF
PRE INJECTION
PRE-INJECTION
ON COST.....
IF EFFECTIVE
Q-VALUE
CAN BE INCREASED
TRY TO ELIMINATE
MOST OF THE LOW
Q-VALUE ROCK
Q
i.e. Q< 1
THEN GET LOWER
COST BECAUSE OF
LESS PROBLEMS
WITH CONSTRUCTION
72
Line 4, screen 4
11 kg/m (mean 134 kg/hole,12m long holes using 13 holes in arch only)
(pressure 10- 60 bars, mean 32 bars
AREA OF TUNNEL per 12 m grout fan 12.D x 12.10 x 180 m2
1,735 kg/180m2 = 9.6 kg/m2 (THIS IS LOW, BUT SEE FIGURE FOR GNEISS
(assumed 6 m cylinder of grout gives 1.6
1 6 l/
l/m3 ...typical for tight gneiss, granite)
----------------------------------------------------------------------------------------------------------------- 74
75
kg/m3
litres/m3
gneiss
11.0 to 16.5
1.8-2,8
1.7-2.6
granite
12.0 to 52
2.0-8.7
1.8-8.3
phyllite
26
4.3
4.1
rhomb porphyry
28 to (99)
4 7 (16 5)
4.7-(16.5)
4 5 (15 7)
4.5-(15.7)
syenite (dike)
30 to (186)
5.0-(31)
4.7-(28.7)
fracture zone
19 to 50
3.1-8.3
2.9-7.7
Rock type
77
78
79