Vous êtes sur la page 1sur 3

Site Formation Works For 132KV Substation at HKUST

Internal Progress Meeting -18.1.2010

Date : 18 January 2010


Present : Yee Hop
Jackin Jim (JJ) M. M. Chui (MMC) Derrick Leung (DL)
C. Wong (祥哥 ) C.W.Li (CWL) K.H.Lai (KHL) Y.F.Shum (發哥)
Franky Chan (蕃茄)
Absent :

NOTES: Action

1. Notes of Last Meeting


No comment was raised on the notes of the last meeting

2. Weather Record
( 0 day) weather affected day was recorded last week

3. Resources

3.1 Labour Resources

Direct Subcontractor
Foreman Lab/Rigger Operato Others Foreman Lab/Rigger. Operato Welder
r r
Bored Pile 1 6 2 2
Work

Prebored 1 3 2 2
H-Pile
Work

Soil Nail 0 0 0 0
Work

Excavation 1
Work

General 4
work
Total 4 1 2 9 4 4

3.2 Plant Resources

Direct Subcontractor

Bored Pile Work Air Welding Crawler oscillator- RCD- 1set


compressor – machine – crane – 2nos 2 sets
1nos 2no
Grab – 2 nos Chisel – 2
nos

Prebored H-Pile Crawler DHP40 Welding


Work crane – 1nos drilling rig machine –
– 1no 2no
Air
compressor –
2nos

Soil Nail Work 1 Air Drilling Grout Pump


compressor – machine – – 1set
1no 2nos

Excavation Work Excavator- Waste


2nos water
chemical
Plant-
1no

4. Programme

4.1 MMC proposed the contract commencement date to be on 30 KHL


April 2008. KHL had to liase with CLP to confirm the date as
well as the mobilization work of the containers to site.
4.2 JJ reminded KHL to submit the Organization Chart, Safety Plan, KHL
Environmental Plan, QA Plan, Master Programme, Submission
Schedule, etc. to CLP as soon as possible.

5. Progress

5.1 KH stated that Bridge Inspection Vehicle (BIV) would be used for KHL
the inspection work at side of Jetty Deck with fenders, and the
inspection would be started on 19May 2008.
5.2 KH expressed that the fabrication work of the scaffold platform at KHL
Approach Bridge had been started at the Sheung Shui Workshop.
The anticipated date for the erection work at CLP would be on 26
May 2008.
5.3 JJ expressed that the painting work at Jetty could be done by KHL/ JP
subcontractor, and reminded KHL and JP to prepare the
subcontract document for the painting work.
5.4 JJ reminded KHL and JP to submit the payment application to KHL/JP
Hip Hing by end of May 2008. as the contract work had been
started on 30April2008.
5.5 KHL expressed that he was still liaising with Eddie Hui and CF KHL
Chow for the method statement of the pile wrapping work, and it
was still not finalized. JJ reminded KHL to speed up the work.
5.6 MMC stated that Mr. C.M.Chan and Mr. Y.F.Shum would be MMC
assigned for this project in next week.
coppy to:- All present & absent

Vous aimerez peut-être aussi