10.

Chapter 10
The nature of planning and
control

10.1

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.2

Planning and control

Planning is deciding

what activities should take place in the


operation
when they should take place
what resources should be allocated to them

Control is

understanding what is actually happening in


the operation
deciding whether there is a significant deviation
from what should be happening

(if there is deviation) changing resources in order


to affect the operations activities.

10.2

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.3

Long-term planning and control


Uses aggregated demand forecasts
Determines resources in aggregated form

PLANNING

Days/weeks/months

Time horizon

Months/years

Significance of planning and control

Objectives set in largely financial terms

Medium-term planning and control


Uses partially disaggregated demand forecasts
Determines resources and contingencies
Objectives set in both financial and operations
terms

Hours/days

Short-term planning and control

10.3

CONTROL

Uses totally disaggregated forecasts or


actual demand
Makes interventions to resources to correct
deviations from plans
Ad hoc consideration of operations objectives.
Slack, Chambers and Johnston, Operations Management, 6th Edition,
Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.4

Dependent and independent demand


Dependent demand

Independent demand

e.g. input tire store in


automobile plant

e.g. tire-fitting service

Demand for tires is


governed by the number
of automobiles planned
to be made

Demand for tires is governed


by the type of car arriving, the
fluctuations in the number of
cars arriving and how many
tires need replacing.

For every automobile


that are planned to be
made, five tires will be
needed

Demand for tires is


largely governed by
random factors.

Independent demand is uncertain.


Dependent demand is certain.
10.4

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.5

Total Throughput Time: Demand Time (P:D ratios)


Customer
orders
Obtain resources

Produce product/service

Deliver to customer

Produce to stock
D

Part produce to order


D

Produce to order
P

Resource to order
D
P

Allow time for


resourcing

10.5

Allow time
for creation

Allow time
for delivery

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.6

The activities of planning and control


How much
to do?

When to
do things?

Scheduling

Sequencing
In what
order to do
things?

10.6

Loading

Monitoring
and control
Are activities
going to plan?

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.7

Loading The reduction of time available for valuable


operating time

Maximum available time


Valuable operating
time
Quality
losses

10.7

Not worked
(planned)
Slow
Not worked
Set-up
and
running Equipment
(unplanned)
changeovers
Breakdown
equipment
idling
failure

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.8

Finite and infinite loading


Finite loading limits the loading on each centre to their capacities, even if it means that jobs will be
late.
Infinite loading allows the loading on each centre to exceed their capacities to ensure that jobs will
not be late.

Hospitals Surgeries
Aircraft - baggage
Specialist car dealers

10.8

Emergency dept
Fast food center
Bank

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.9

The activities of planning and control


How much
to do?

Loading

Monitoring
and control
Are activities
going to plan?

10.9

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.10

A simple model of control

Input

Operation or
process

Intervention
Plans

Output

Monitor

Compare
/ replan

10.10

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.11

Pull and push philosophies of planning and control

Push control

Pull control

10.11

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.12

The activities of planning and control


How much
to do?

Loading

Sequencing
In what
order to do
things?

10.12

Monitoring
and control
Are activities
going to plan?

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.13

Sequencing Priority
1. Physical Constraints
- construction of a house, changeover time of machine, dye color

2. Customer Priority
- BIG DOG
3. Due date
- ensure that product is delivered to customer on time
- improves delivery reliability and average delivery speed
- not optimal in terms of productivity
- better flexibility

10.13

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.14

Sequencing rules
1. FCFS - First Come, First Served: or FIFO
Jobs are processed in the order in which they arrive at a machine / work center

2. SPT - Shortest Processing Time


According to processing time at a machine or work center, shortest job first.

3. DD - Due Date
Jobs are processed according to due date, earliest due date first.

4. CR - critical ratio
Jobs are processed according to smallest ratio of time remaining until due date to
processing time remaining.

5. S/O - slack per operation


Jobs are processed according to average slack time (time until due date minus
remaining time to process).
Compute by dividing slack time by number of remaining operations including the current one.

6. Rush emergency: Emergency or Preferred Customers first


Others -------LIFO, longest operation time (LOT)
10.14

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.15

Johnsons Rule
Sequencing n jobs through 2 workstations
Objectives
minimize the processing time for sequencing a group of jobs through two work centres.
minimize the total idle times on the machines.
minimize the flow time from the beginning of the first job until the finish of the last job.
Conditions
Job time(including setup and processing) must be known and constant for each job at each
work center.
Job times must be independent of the job sequence.
All jobs must follow the same two-setup work sequence.
Job priorities cannot be used.

Algorithm
1. Find the job with minimum Pij
2. If j = 1 (machine 1) this job becomes the first job
3. If j = 2 (machine 2) this job becomes the last job
4. Remove assigned job from the list and repeat (break ties at random)

10.15

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

Johnsons Rule Example

10.16

Algorithm
1. Find the job with minimum Pij
2. If j = 1 (machine 1) this job becomes the first job
3. If j = 2 (machine 2) this job becomes the last job
4. Remove assigned job from the list and repeat (break ties at random)

Min Pij = P21 = 1

now eliminate job 2

Min Pij = P41 = 2


Min Pij = p12 =3
Min Pij = p32

now eliminate job 4


since j = 2 now job 1 goes to last

The Sequence: {2,4,5,3,1}

10.16

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.17

10.17

Johnsons Rule Example

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.18

The activities of planning and control


How much
to do?

When to
do things?

Scheduling

Sequencing
In what
order to do
things?

10.18

Loading

Monitoring
and control
Are activities
going to plan?

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.19

Ait Traffic Control


1. What does planning and control mean to air traffic controllers?
2. What are the differing problems faced by TRACON, tower and ground
controllers?
3. What sequencing rules do you think the tower controllers use?

10.19

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.20

Ait Traffic Control

1. What does planning and control mean to air traffic controllers?

PLANNING
1. Route planning
Drawing of the invisible corridors in the sky through which the planes are channeled
- planning of how these invisible corridors are changed to cope with different weather
conditions.

2. Emergency planning
Setting out procedures for emergency situations, such as emergency landings.
- predetermined routines not only on what happens to the plane subject to the emergency,
but also to the other traffic in the air space and on the ground during the emergency.
3. Rough capacity planning
Airlines run to schedules and therefore it is possible to forecast the expected number of
planes arriving in the air space at any particular time.
- possible to forecast at a certain point in air space when the shift of responsibility occurs
- tower controllers, ground controllers and TRACON controllers or others

10.20

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.21

Ait Traffic Control


1. What does planning and control mean to air traffic controllers?

CONTROL
-

Emphasis on monitoring.

- Where is my aircraft at any point in time.


Any loss of information means loss of control.
What should be happening (where the aircraft should be) against what is actually
happening (where the aircraft actually is).
Approach not per plan impacts all the other aircraft in the air space at the time.
Adjust the instructions given to the aircraft in order to take account of each others
position or deviation from position.

10.21

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.22

Ait Traffic Control

2. What are the differing problems faced by TRACON, tower and ground
controllers?

A. TRACON controllers
1. Keep aircraft apart while they are in a particular sector.
Closely monitor the position, direction and speed of each aircraft
and predict their relative positions over time. (Computer assistance for
proximity)
2. Handovers between different sectors.
Necessary for 1 controller to have charge of all aircraft in his or her
air space because it is the position of the aircraft relative to each other which
is important.
Consequence of doing this - must be a handover between sectors.
- Potentially a major failure point.
Any failure to understand that responsibility has been passed on, or loss of
monitoring, could be disastrous here.

10.22

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.23

Ait Traffic Control

2. What are the differing problems faced by TRACON, tower and ground
controllers?

Tower controllers
1. Capacity.
Major bottleneck = airport itself.
schedule and control the passage of planes into and out of the airport.
(shoot the gap) Reduce time between take off and landing increase
capacity ------RISK???
2. Variation between aircraft
The gap between planes taking-off or landing is a function of size because
of the wake turbulence.
Analogous to changeover times.

10.23

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.24

Ait Traffic Control

2. What are the differing problems faced by TRACON, tower and ground
controllers?

Ground controllers
- seems the least dangerous of the three areas,
several accidents due to aircraft straying onto the runway.
Ground control, - safety and efficiency
Avoid bottleneck move aircraft swiftly but pay attention to
surroundings.

10.24

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010

10.25

Ait Traffic Control


3. What sequencing rules do you think the tower controllers use?
Probably shift between various rules
A. Normal situations
Common due date - prioritizing landing slots according to the aircraft schedules
FIFO (orderly queuing) - likely to be adopted by the controllers.
B. Non-normal situations
- Customer priority
e.g. short on fuel, emergency landing, hijacking etc
Will change when safety is an issue

10.25

Slack, Chambers and Johnston, Operations Management, 6th Edition,


Nigel Slack, Stuart Chambers, and Robert Johnston 2010