Académique Documents
Professionnel Documents
Culture Documents
907m
A)
B)
Input Data
Design Chainage
Skew Angle
Catchment Area ,A
Proposed span details
=
=
=
=
=
=
=
184.907
0
3.000
1
0
0
1.20
346.189
Empirical Formula
Description
Dicken's
Ryve's
19.000
3.000
43.311
10.000
3.000
20.801
By Rational Method
Area of catchment, A
Length of longest stream, L
The fall in level between source and bridge site, H
Average grade-source to site (in percent)
R
=
=
=
=
=
=
50 year 24 hour point rainfall
16
cm
3.000
2.257
15
(H/L)*100
tc
=
=
=
=
=
Time of concentration
0.9 x L / (M 0.1 x S 0.2)
Where,
1.349
hr.
L in miles and M in sq miles
Areal Reduction Factor (for tc=1.349 hr and area=3 sq km)
0.85
(From Table under Para 2.1.1 of B
and Flood Wing Report No. RBF Runoff Coefficient
0.415 x (R x F)0.2
0.70
=
=
=
tc hr. ratio
1 hr. ratio
=
=
R50(24)
R50(1)
70 mm
R50(tc)
=
=
=
=
=
K x R50(1)
=
=
0.560
1.000
39.2
mm
50 year rainfall intensity (mm/hr) lasting for tc hr. duration
R50(tc)/tc
29.061
mm/hr.
0.278 x C I A
16.952
m3/sec
Longitudinal Section
346.700
346.650
346.600
346.550
Column M
Linear (Column M)
346.500
346.450
346.400
346.350
100
110
120
130
140
150
160
170
180
190
200
D)
=
=
0.003200
0.055
Discharge by
Dicken's formula
Ryve's formula
Rational Method
Design Discharge as per above methods
DPR Discharge
Maximum Discharge
=
=
=
=
=
=
43.311
20.801
16.952
31.201
31.201
31.201
cumecs
cumecs
cumecs
cumecs
cumecs
cumecs
HFL Calculation
Design Discharge
31.201
cumecs
349.000
348.500
348.000
347.500
347.000
346.500
346.000
345.500
0.000
2.000
4.000
6.000
Column D
8.000
10.000
Column E
12.000
14.000
16.000
Distance (m)
RL of Existing
GL (m)
RL of Modified
GL (m)
HFL (m)
Area, a
(sqm)
Wetted Perimeter,p
(m)
0.000
2.696
7.190
11.930
14.000
348.834
348.290
346.491
346.650
347.969
347.500
346.620
346.648
348.129
347.969
348.788
348.788
348.788
348.788
348.788
4.658
9.679
6.633
1.529
2.836
4.494
4.966
2.076
An1=
22.500
14.372
22.500 m2
1.446 m
14.372 m
1.566 m
31.201 m3/sec
346.620 m
E)
Afflux calculations
Design Discharge
Area of C/S at bridge location
Velocity of Water V=Q/A
HFL
Bed Level
Effective Linear waterway provided (no of spans *length of each span
(i.e c/c of bearings))-(no. of piers * width of pier)-(Abutment width)
=
=
=
=
=
31.201
22.500
1.387
348.788
346.620
L provided
18.800
=
=
26.812
348.788
2.599
=
=
51.977
0.600
Area after construction,An1* (An1* calculated from RLs which we have considered in
between the Extream edges of the bridge cross section taken from the topo survey)
22.500
48.858
0.639
0.005
348.792
Regime width
HFL (Without Afflux)
4.8 x Q^0.5
F)
i.
1.758
3.517
1.27 x Dsm
For Abutments
=
2.233
Flood with seismic combination
For considering load combination of flood and seismic load together with other appropriate combinations given elsewhere
, the maximum scour depth given above may be reduced by 0.9
The maximum scour depth may be adopted as
0.9 x 1.27 x Dsm
For Abutments
=
2.010
Normal Scour level
For abutment
=
346.555
For Pier
=
345.271
H.
=
=
1.750
350.542
m
km
degree
km2
20.000 m
0.000 m
m
m
m
km2
km
m
=
1.158
1.402
0.009
0.665
Mile2
Mile
Mile
and M in sq miles
- 4 of Bridges and
Depth, d (m)
2.168
2.140
0.659
0.819
1.446
Cumecs
Sq.m
m/sec
m
m
m
m
m
m
sq m
m/s
sq m
sq m
m/s
m
m
be designed
cumecs
(As per cl.703.1.1 of IRC:78-2000)
m
From Geotech report
m
m
m
m
m
m
m
m
Annexure-1
Chaung Name
Proposed chainage
Skew Angle
Twaose chaung
519+906
0
km
Degree
Sl No
(1)
1
2
3
4
5
6
7
8
9
10
11
12
13
SUM
(*)
Reduced
Distance
Reduced
Length of
Starting From
Level of
Each Segment
Bridge Site
River Bed
(Li) (km)
(Point of Study)
(m)
(km)
(2)
0.00
1.599
4.068
5.359
7.529
8.448
9.197
14.221
15.695
17.012
21.479
23.105
23.965
(3)
280
290
300
310
320
330
340
400
410
420
440
460
470
(4)
1.60
2.47
1.29
2.17
0.92
0.75
5.02
1.47
1.32
4.47
1.63
0.86
23.97
=
=
=
=
7.042*[(tp)^(0.559)]
11.18
11.00
say
Time from start of rise to the peak of unit hydrograph
Tm
=
=
Peak discharge of Unit Hydrograph
Qp
=
=
say
tp + tr/2
2.8
qp * A
57.87
58.00
Estimated parameter of Unitgraph in step-2 were plotted to scale. The plotted points were jo
The discharge ordinates of unitgraph at ti=tr=1 hr interval were summed up and compared w
runoff as calculated below
Time (in hrs)
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
4.25
4.50
4.75
5.00
5.25
5.50
5.75
6.00
6.25
1-hr Synthetic
U.G. ordinates
0.00
1.00
2.00
3.00
5.00
7.00
10.00
12.00
20.00
29.00
43.50
50.00
58.00
50.00
43.50
35.00
31.00
29.00
24.00
22.00
19.00
17.00
15.00
13.50
12.50
11.50
70.00
Qp
60.00
50.00
75% Qp
40.00
W75
30.00
W50
50% of
Qp
20.00
10.00
0.00
0
10.50
9.50
8.50
7.50
6.50
5.50
4.00
3.00
2.00
1.25
0.75
0.50
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.00
156.38
Sum(Qi)
=
=
cumecs
(A*d)/(tr*0.36)
156.59
1.1 * tp
2.53
3.00
Duration (hrs)
Distribution
coefficient
Storm
Rainfall
(cm)
Hourly Rainfall
Increament
(cm)
1
2
3
0.77
0.93
1.00
8.60
10.39
11.17
8.60
1.79
0.78
Note: Design loss rate in this zone is recommended as 0.5 cm/hr as per part 3.6 of flood estim
Narmadha -Tapi sub zone -3b (revised)
Step : - 7 Estimation of base flow
=
=
0.05
2.8186
cumec/sq.km
cumecs
For the estimation of the peak discharge the effective rainfall units were re-arranged aga
maximum effective rainfall was placed against the maximum U.G. ordinates, the next lower
the the next lower value of U.G. ordinates and so on as shown below:
Total
Base Flow
100-yr peak flood
U.G. Ordinates
(cumec)
1-hr
effective
rainfall
(cm)
Direct Runoff
(cumecs)
58.00
50.00
50.00
8.10
1.29
0.28
469.94
64.38
14.10
=
=
=
548.42
2.82
551.24
Annexure-1
=
=
56.37
23.80
sq km
km
10.64
=
km
Height
Above
Datum*
(Di)=Differe (Di-1 + Di) Li x (Di-1 +
nce Between
Di) (m*km)
(m)
the Datum
Line and its
R.L (m)
(5)
10.00
20.00
30.00
40.00
50.00
60.00
120.00
130.00
140.00
160.00
180.00
190.00
(6)
10.00
30.00
50.00
70.00
90.00
110.00
180.00
250.00
270.00
300.00
340.00
370.00
(7)
15.99
74.07
64.55
151.90
82.71
82.39
904.32
368.50
355.59
1340.10
552.84
318.20
4311.16
i x (Di-1 + Di))]/L2
m/km
ydrograph
[LLc / (S)^0.5]^(0.302)
hrs
hrs
[tp]^(-0.753)
cumecs per sq km
[qp]^(-0.976)
hrs
[qp]^(-0.792)
hrs
charge ordinate
[qp]^(-0.781)
hrs
charge ordinate
[qp]^(-0.641)
hrs
[(tp)^(0.559)]
hrs
hrs
hrs
cumecs
cumecs
Qp
75% Qp
W75
W50
50% of
Qp
Column C
10
11
12
13
cumecs
hrs
hrs
=
=
=
24.00
0.49
11.76
=
=
0.950
11.17
cm
(From Plate-10)
(from Fig-10)
cm
(From Fig 12 (a) or 12 (b))
cm
n of Rainfall Excess
Design Loss
Rate (cm/hr)
Rainfall
Excess
(cms)
0.5
0.5
0.5
8.10
1.29
0.28
cumecs
cumecs
cumecs
Input Data
Chaung Name
Design Chainage
Skew Angle
Catchment Area ,A
Existing/Proposed span details
Pier /internal wall width
Abutment /External wall width
A)
Empirical Formula
Description
Dicken's
Ryve's
12.000
56.372
246.876
8.500
56.372
124.967
Longitudinal Section
272.500
272.000
f(x) = - 0.0032805958x + 271.909224505
271.500
271.000
270.500
Column I
270.000
Linear (Co
269.500
269.000
268.500
268.000
0
100
200
300
400
500
600
700
800
Discharge by
SUH Method
Dicken's formula
Ryve's formula
Design Discharge
Maximum Discharge
=
=
=
=
=
HFL Calculation
Design Discharge
276.000
275.000
274.000
273.000
272.000
271.000
270.000
269.000
268.000
0.000
10.000
20.000
30.000
Column D
Column E
Distance (m)
RL of Existing
GL (m)
RL of Modified
GL (m)
0.000
5.126
10.324
14.629
20.585
24.112
39.835
43.277
48.070
54.293
55.000
274.654
274.316
273.327
272.042
271.635
270.882
270.968
271.696
272.271
272.740
274.800
274.654
274.316
273.327
272.042
271.635
270.882
270.968
271.696
272.271
272.740
274.800
40.000
Afflux calculations
Design Discharge
Area of C/S at bridge location
Velocity of Water V=Q/A
118.918 m2
2.318 m
51.848 m
2.294 m
216.017 m3/sec
270.882 m
50.000
60.000
Regime width
HFL (Without Afflux)
4.8 x Q^0.5
H.
I.
Recommendation
Design Discharge, Q
Design Affluxed HFL
Average Velocity, Vn2
Required vertical clearance
Minimu soffit level required
00
=
=
=
Twaose chaung
519+906 Km
0 degree
=
=
=
=
56.37 Km2
3
18.000 m
1.5 m
1.75 m
Column I
Linear (Column I)
800
0.0033
Cum
RD (m)
0
136
253
326
433
605
717
Avg bed
level
@ C/S (m)
272.185
271.015
270.941
270.925
270.903
269.710
269.583
551.238
246.876
124.967
339.454
339.454
cumecs
cumecs
cumecs
cumecs
cumecs
From Annexure-1
000
339.454
50.000
HFL (m)
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
An1=
cumecs
60.000
Area, a
(sqm)
Wetted
Depth, d (m)
Perimeter,p (m)
2.296
6.796
14.441
10.597
52.486
10.089
10.926
10.938
0.349
118.918
5.291
4.493
5.970
3.606
15.723
3.518
4.827
6.241
2.178
51.848
0.936
2.221
2.628
3.381
3.295
2.567
1.992
1.523
=
=
=
216.017
118.918
1.817
2.318
Cumecs
Sq.m
m/sec
274.263
270.882
m
m
L provided
49.250
=
=
70.548
274.263
m
m
2.318
=
=
118.918
1.817
sq m
m/s
we have considered in
from the topo survey)
118.918
sq m
of abutment*depth
duct two times of
103.851
sq m
2.080
m/s
0.062
274.325
section)
=
=
=
=
=
=
=
1.750 m
276.075 m
216.017
274.325
2.080
0.9
275.225
cumecs
m
m/sec
m
m