Vous êtes sur la page 1sur 40

Hydrological calculations for Bridge at Chainage 184.

907m

A)

B)

Input Data
Design Chainage
Skew Angle
Catchment Area ,A
Proposed span details

=
=
=
=

Pier /internal wall width


Abutment /External wall width
Bed level

=
=
=

184.907
0
3.000
1
0
0
1.20
346.189

Empirical Formula
Description

Dicken's

Ryve's

Value of C adopted in the present case


Catchment area (M) (Sq Km)
Discharge, Q (Cumecs)

19.000
3.000
43.311

10.000
3.000
20.801

(From Article-4 of IRC:SP:13-2004)

By Rational Method
Area of catchment, A
Length of longest stream, L
The fall in level between source and bridge site, H
Average grade-source to site (in percent)
R

=
=

=
=
=
=
50 year 24 hour point rainfall
16
cm

3.000
2.257
15
(H/L)*100

tc

=
=
=
=
=

Time of concentration
0.9 x L / (M 0.1 x S 0.2)
Where,
1.349
hr.
L in miles and M in sq miles
Areal Reduction Factor (for tc=1.349 hr and area=3 sq km)
0.85
(From Table under Para 2.1.1 of B
and Flood Wing Report No. RBF Runoff Coefficient
0.415 x (R x F)0.2
0.70

=
=
=

tc hr. ratio
1 hr. ratio

=
=

R50(24)

R50(1)

70 mm

R50(tc)

=
=
=
=
=

K x R50(1)

Design Flood Discharge ,


Q

=
=

0.560
1.000

(For Zone-3 from Figure - 4 of Bridges and


Flood Wing Report No. RBF - 16)

tc hr. ratio / 1 hr. ratio


0.56
16
cm

(For Subzone-3h from Figure - 3.7 : Krishna and Penner Basin o


Flood Wing Report No. RBF - 16)

39.2
mm
50 year rainfall intensity (mm/hr) lasting for tc hr. duration
R50(tc)/tc
29.061

mm/hr.

0.278 x C I A
16.952

m3/sec

Longitudinal Section

346.700

346.650

346.600

f(x) = - 0.00353x + 346.964

346.550
Column M
Linear (Column M)

346.500

346.450

346.400

346.350
100

110

120

130

140

150

160

170

180

190

200

D)

Average Bed Slope of River, S


Manning's Coefficient,n

=
=

0.003200
0.055

Discharge by
Dicken's formula
Ryve's formula
Rational Method
Design Discharge as per above methods
DPR Discharge
Maximum Discharge

=
=
=
=
=
=

43.311
20.801
16.952
31.201
31.201
31.201

cumecs
cumecs
cumecs
cumecs
cumecs
cumecs

HFL Calculation
Design Discharge

31.201

cumecs

(Rugosity Co- efficient,n table 5.1 of IRC:SP:13

349.000
348.500
348.000
347.500
347.000
346.500
346.000
345.500
0.000

2.000

4.000

6.000
Column D

8.000

10.000
Column E

12.000

14.000

16.000

Check: It should not be more tha


(Cl. 6.2.1, IRC:SP:13-2004)

Distance (m)

RL of Existing
GL (m)

RL of Modified
GL (m)

HFL (m)

Area, a
(sqm)

Wetted Perimeter,p
(m)

0.000
2.696
7.190
11.930
14.000

348.834
348.290
346.491
346.650
347.969

347.500
346.620
346.648
348.129
347.969

348.788
348.788
348.788
348.788
348.788

4.658
9.679
6.633
1.529

2.836
4.494
4.966
2.076

An1=

22.500

14.372

C/S area of stream ,An1 =


Average depth
(i.e davg considered with in the entire
cross section), d avg=
Wetted perimeter P =
Hydraulic Radius, (r=An1/P) =
Discharge (Q) =
Lowest Bed Level

22.500 m2
1.446 m
14.372 m
1.566 m
31.201 m3/sec
346.620 m

E)

Afflux calculations
Design Discharge
Area of C/S at bridge location
Velocity of Water V=Q/A
HFL
Bed Level
Effective Linear waterway provided (no of spans *length of each span
(i.e c/c of bearings))-(no. of piers * width of pier)-(Abutment width)

=
=
=
=
=

31.201
22.500
1.387
348.788
346.620

L provided

18.800

=
=

26.812
348.788

Average depth of flow at bridge cross section (d avg)


( i.e davg considered b/w the Extream edges of the bridge cross section)

2.599

Area before construction, An1


Average velocity prior to construction, Vn1=Q/An1

=
=

51.977
0.600

Area after construction,An1* (An1* calculated from RLs which we have considered in
between the Extream edges of the bridge cross section taken from the topo survey)

22.500

48.858

0.639

0.005

348.792

Regime width
HFL (Without Afflux)

4.8 x Q^0.5

Net C/S area of flow under bridge,


An2=(An1-(no. of piers*width of piers * depth (d avg))-(width of abutment*depth (davg))), An1
calculated as mentioned above so we have to deduct two times of abutment thickness
Average Velocity after construction, Vn2= Q/An2
Afflux due to construction (by Molesworth Formula),
h= [(Vn1^2)/17.88+0.015] [ (An1/An2)^2-1]
Design HFL

F)
i.

Scour Depth calculations


Normal scour depth
Dsm = 1.34 x (Db2/ksf)1/3

(As per article-9 of SP:13-2004)

Dsm is the normal ( mean) depth of scour below HFL in m


Db is the discharge in cumec per m width of effective waterway
ksf is the silt factor for sample of bed material
Ksf = 1.76 x (dm) 0.5

(cl.703.2.2 of IRC :78-2000)

dm is the weighted mean diameter of bed material in mm


According to Clause 703.1.1 IRC:78-2000 To provide for an adequate margin of safety, the scour for foundation shall be designed
for larger discharge over the discharge obtained (IRC:5)
Design discharge is increased in percnetage depending upon the catchment area
Actual Discharge calculated
=
31.201
Increase in design discharge for scour depth calculation
=
30%
Discharge per m width of the Linear water way Db
=
2.16
Silt factor for the bed material ksf
=
2.060
ii.

Normal scour depth, Dsm

1.758

Maximum scour depth


Clause 703.3 of IRC:78-2000
Flood without seismic combination
The maximum scour depth may be adopted as
2 x Dsm
For Box

3.517

1.27 x Dsm
For Abutments
=
2.233
Flood with seismic combination
For considering load combination of flood and seismic load together with other appropriate combinations given elsewhere
, the maximum scour depth given above may be reduced by 0.9
The maximum scour depth may be adopted as
0.9 x 1.27 x Dsm
For Abutments
=
2.010
Normal Scour level
For abutment
=
346.555
For Pier
=
345.271

H.

Check for free board


Free board is the difference between HFL and road formation level
Free board required (Cl.107.1 of IRC :5-1998)
Min FRL required for New bridge

=
=

1.750
350.542

m
km
degree
km2
20.000 m
0.000 m
m
m
m

km2
km
m
=

1.158
1.402
0.009
0.665

Mile2
Mile
Mile

and M in sq miles

e under Para 2.1.1 of Bridges


Wing Report No. RBF - 16)

- 4 of Bridges and

and Penner Basin of Bridges and

table 5.1 of IRC:SP:13-2004)

hould not be more than 1.5*next max. Discharge


IRC:SP:13-2004)

Depth, d (m)
2.168
2.140
0.659
0.819

1.446

Cumecs
Sq.m
m/sec
m
m
m
m
m
m
sq m
m/s
sq m

sq m

m/s
m
m

be designed

cumecs
(As per cl.703.1.1 of IRC:78-2000)
m
From Geotech report
m

m
m

m
m
m

m
m

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

Annexure-1
Chaung Name
Proposed chainage
Skew Angle

Twaose chaung
519+906
0

km
Degree

(1) By Unit Hydrograph Method


Step : - 1 Determination of Physiographic Parameter
Area, A
Length of longest stream, L
Length of main stream from bridge gauging site to a point nearest to
centriod of the stream basin along stream course, Lc

Sl No

Equivalent stream slope

(1)
1
2
3
4
5
6
7
8
9
10
11
12
13
SUM

(*)

Reduced
Distance
Reduced
Length of
Starting From
Level of
Each Segment
Bridge Site
River Bed
(Li) (km)
(Point of Study)
(m)
(km)

(2)
0.00
1.599
4.068
5.359
7.529
8.448
9.197
14.221
15.695
17.012
21.479
23.105
23.965

(3)
280
290
300
310
320
330
340
400
410
420
440
460
470

(4)
1.60
2.47
1.29
2.17
0.92
0.75
5.02
1.47
1.32
4.47
1.63
0.86
23.97

Reduced level of river bed at the point of study, i.e. 280m

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
S

=
=

[Sum(Li x (Di-1 + Di))]/L2


7.51

Step : - 2 Determination of Synthetic (1-hr) Unitgraph Parameterrs


Time from the center of Unit rainfall duration to the peak of Unit Hydrograph
tp
=
0.583*[LLc / (S)^0.5]^(0.302)
=
2.287
say
2.30
Peak discharge of hydrograph per unit area
qp
=
1.914*[tp]^(-0.753)
=
1.027
Width of U. G. measured at 50% maximum discharge ordinate
W50
=
1.849*[qp]^(-0.976)
=
1.80
Width of U. G. measured at 75% maximum discharge ordinate
W75
=
0.955*[qp]^(-0.792)
=
0.94
Width of the rising side of U. G. measured at 50% of maximum discharge ordinate
WR50
=
0.738*[qp]^(-0.781)
=
0.72
Width of the rising side of U. G. measured at 75% of maximum discharge ordinate
WR75
=
0.438*[qp]^(-0.641)
=
0.43

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

Base width of Unit Hydrograph


TB

=
=

7.042*[(tp)^(0.559)]
11.18
11.00

say
Time from start of rise to the peak of unit hydrograph
Tm
=
=
Peak discharge of Unit Hydrograph
Qp
=
=
say

tp + tr/2
2.8
qp * A
57.87
58.00

Step : - 3 Drawing of Synthetic Unitgraph

Estimated parameter of Unitgraph in step-2 were plotted to scale. The plotted points were jo
The discharge ordinates of unitgraph at ti=tr=1 hr interval were summed up and compared w
runoff as calculated below
Time (in hrs)
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
4.25
4.50
4.75
5.00
5.25
5.50
5.75
6.00
6.25

1-hr Synthetic
U.G. ordinates
0.00
1.00
2.00
3.00
5.00
7.00
10.00
12.00
20.00
29.00
43.50
50.00
58.00
50.00
43.50
35.00
31.00
29.00
24.00
22.00
19.00
17.00
15.00
13.50
12.50
11.50

70.00

Qp
60.00

50.00

75% Qp

40.00

W75
30.00

W50

50% of
Qp

20.00

10.00

0.00
0

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
6.50
6.75
7.00
7.25
7.50
7.75
8.00
8.25
8.50
8.75
9.00
9.25
9.50
9.75
10.00
10.25
10.50
10.75
11.00
11.25
11.50
11.75
12.00
Sum

10.50
9.50
8.50
7.50
6.50
5.50
4.00
3.00
2.00
1.25
0.75
0.50
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.00
156.38

Sum(Qi)

=
=

cumecs
(A*d)/(tr*0.36)
156.59

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
Since Eq-1 = Eq-2, so unitgraph drawn is in order
Step : - 4 Estimation of design storm duration
The design storm duration
TD
=
=
Say

1.1 * tp
2.53
3.00

Step : - 5 Estimation of point rainfall and areal rainfall


100-yr, 24-hr rainfall
Ratio of 3-hr rainfall to 24-hr rainfall
So, 100-yr 3-hr point rainfall
Areal reduction factor corresponding to area 56.372sq km and TD=3 hrs
So, 100-yr 3-hr areal rainfall
Step : - 6 Time distribution of Areal Rainfall and Calculation of Rainfall Excess
This 100-yr 3-hrs areal rainfall is distributed as below (from Annexure-4.3)

Duration (hrs)

Distribution
coefficient

Storm
Rainfall
(cm)

Hourly Rainfall
Increament
(cm)

1
2
3

0.77
0.93
1.00

8.60
10.39
11.17

8.60
1.79
0.78

Note: Design loss rate in this zone is recommended as 0.5 cm/hr as per part 3.6 of flood estim
Narmadha -Tapi sub zone -3b (revised)
Step : - 7 Estimation of base flow

The design base flow


Adopting a design base flow of 0.05 cumec per sq.km.recommended for this zone (from para 3
for lower Narmada and Tapi subzone-3(b)-(revised)))
Total base flow
design base flow
Qb

=
=

0.05
2.8186

cumec/sq.km
cumecs

Step : - 8 Estimation of 100-yr Flood Peak

For the estimation of the peak discharge the effective rainfall units were re-arranged aga
maximum effective rainfall was placed against the maximum U.G. ordinates, the next lower
the the next lower value of U.G. ordinates and so on as shown below:

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

Total
Base Flow
100-yr peak flood

U.G. Ordinates
(cumec)

1-hr
effective
rainfall
(cm)

Direct Runoff
(cumecs)

58.00
50.00
50.00

8.10
1.29
0.28

469.94
64.38
14.10

=
=
=

548.42
2.82
551.24

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

Annexure-1

=
=

56.37
23.80

sq km
km

10.64
=

km

Height
Above
Datum*
(Di)=Differe (Di-1 + Di) Li x (Di-1 +
nce Between
Di) (m*km)
(m)
the Datum
Line and its
R.L (m)
(5)
10.00
20.00
30.00
40.00
50.00
60.00
120.00
130.00
140.00
160.00
180.00
190.00

(6)
10.00
30.00
50.00
70.00
90.00
110.00
180.00
250.00
270.00
300.00
340.00
370.00

point of study, i.e. 280m

(7)
15.99
74.07
64.55
151.90
82.71
82.39
904.32
368.50
355.59
1340.10
552.84
318.20
4311.16

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

i x (Di-1 + Di))]/L2
m/km

ydrograph
[LLc / (S)^0.5]^(0.302)
hrs
hrs

[tp]^(-0.753)
cumecs per sq km

[qp]^(-0.976)
hrs

[qp]^(-0.792)
hrs

charge ordinate
[qp]^(-0.781)
hrs

charge ordinate
[qp]^(-0.641)
hrs

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

[(tp)^(0.559)]
hrs
hrs

hrs

cumecs
cumecs

. The plotted points were joined to draw synthetic unitgraph.


ummed up and compared with the volume of 1.00 cm direct

Qp

75% Qp
W75

W50

50% of
Qp

Column C

10

11

12

13

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

cumecs

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

hrs
hrs

=
=
=

24.00
0.49
11.76

=
=

0.950
11.17

cm

(From Plate-10)
(from Fig-10)

cm
(From Fig 12 (a) or 12 (b))
cm

n of Rainfall Excess

Design Loss
Rate (cm/hr)

Rainfall
Excess
(cms)

0.5
0.5
0.5

8.10
1.29
0.28

s per part 3.6 of flood estimation report lower

ed for this zone (from para 3.7 of flood estimation report

units were re-arranged against the ordinates such that the


. ordinates, the next lower value of effective rainfall against
ow:

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

cumecs
cumecs
cumecs

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

Input Data
Chaung Name
Design Chainage
Skew Angle
Catchment Area ,A
Existing/Proposed span details
Pier /internal wall width
Abutment /External wall width

A)

Empirical Formula
Description

Dicken's

Ryve's

Value of C adopted in the present case


Catchment area (M) (Sq Km)
Discharge, Q (Cumecs)

12.000
56.372
246.876

8.500
56.372
124.967

Longitudinal Section
272.500
272.000
f(x) = - 0.0032805958x + 271.909224505

271.500
271.000
270.500

Column I

270.000

Linear (Co

269.500
269.000
268.500
268.000
0

100

200

300

Average Bed Slope of River, S

400

500

600

700

800

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
Manning's Coefficient,n

Discharge by
SUH Method
Dicken's formula
Ryve's formula
Design Discharge
Maximum Discharge

=
=
=
=
=

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
D)

HFL Calculation
Design Discharge

276.000
275.000
274.000
273.000
272.000
271.000
270.000
269.000
268.000
0.000

10.000

20.000

30.000
Column D

Column E

Distance (m)

RL of Existing
GL (m)

RL of Modified
GL (m)

0.000
5.126
10.324
14.629
20.585
24.112
39.835
43.277
48.070
54.293
55.000

274.654
274.316
273.327
272.042
271.635
270.882
270.968
271.696
272.271
272.740
274.800

274.654
274.316
273.327
272.042
271.635
270.882
270.968
271.696
272.271
272.740
274.800

C/S area of stream ,An1 =


Average depth
(i.e davg considered with in the entire
cross section), d avg=
Wetted perimeter P =
Hydraulic Radius, (r=An1/P) =
Discharge (Q) =
Lowest Bed Level
E)

40.000

Afflux calculations
Design Discharge
Area of C/S at bridge location
Velocity of Water V=Q/A

118.918 m2
2.318 m
51.848 m
2.294 m
216.017 m3/sec
270.882 m

50.000

60.000

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
HFL
Bed Level
Effective Linear waterway provided (no of spans *length of each span
(i.e c/c of bearings))-(no. of piers * width of pier)-(Abutment width)

Regime width
HFL (Without Afflux)

4.8 x Q^0.5

Average depth of flow at bridge cross section (d avg)


( i.e davg considered b/w the Extream edges of the bridge cross section)
Area before construction, An1
Average velocity prior to construction, Vn1=Q/An1
Area after construction,An1* (An1* calculated from RLs which we have considered in
between the Extream edges of the bridge cross section taken from the topo survey)
Net C/S area of flow under bridge,
An2=(An1*-(no. of piers*width of piers * depth (d avg))-(2*width of abutment*depth
(davg))), An1* calculated as mentioned above so we have to deduct two times of
abutment thickness
Average Velocity after construction, Vn2= Q/An2
Afflux due to construction (by Molesworth Formula),
h= [(Vn1^2)/17.88+0.015] [ (An1/An2)^2-1]
Design HFL

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

H.

Check for free board


Free board is the difference between HFL and road formation level
Free board required (Cl.107.1 of IRC :5-1998)
Min FRL required for New bridge

I.

Recommendation
Design Discharge, Q
Design Affluxed HFL
Average Velocity, Vn2
Required vertical clearance
Minimu soffit level required

00

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

=
=
=

Twaose chaung
519+906 Km
0 degree

=
=
=
=

56.37 Km2
3
18.000 m
1.5 m
1.75 m

(From Article-4 of IRC:SP:13-2004)

Column I
Linear (Column I)

800

0.0033

Cum
RD (m)
0
136
253
326
433
605
717

Avg bed
level
@ C/S (m)
272.185
271.015
270.941
270.925
270.903
269.710
269.583

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
0.055

551.238
246.876
124.967
339.454
339.454

(Rugosity Co- efficient,n table 5.1 of IRC:SP:13-2004)

cumecs
cumecs
cumecs
cumecs
cumecs

From Annexure-1

000

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

339.454

50.000

HFL (m)
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
274.263
An1=

cumecs

60.000

Area, a
(sqm)

Wetted
Depth, d (m)
Perimeter,p (m)

2.296
6.796
14.441
10.597
52.486
10.089
10.926
10.938
0.349
118.918

5.291
4.493
5.970
3.606
15.723
3.518
4.827
6.241
2.178
51.848

0.936
2.221
2.628
3.381
3.295
2.567
1.992
1.523

=
=
=

216.017
118.918
1.817

2.318

Cumecs
Sq.m
m/sec

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV
=
=

274.263
270.882

m
m

L provided

49.250

=
=

70.548
274.263

m
m

2.318

=
=

118.918
1.817

sq m
m/s

we have considered in
from the topo survey)

118.918

sq m

of abutment*depth
duct two times of

103.851

sq m

2.080

m/s

0.062

274.325

section)

Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100


Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on DBFOT
pattern under NHDP phase IV

=
=

=
=
=
=
=

1.750 m
276.075 m

216.017
274.325
2.080
0.9
275.225

cumecs
m
m/sec
m
m

Vous aimerez peut-être aussi