Rx Imola Installation

Site Survey

1. Instructions
The Field Engineer or Sales Representative must schedule a preliminary Site Survey visit in
accordance with local branch operating procedures.
Conduct the survey in cooperation with the customers biomedical or maintenance engineer. You
must define acceptance or rejection of each requirement listed in the Site Survey form by
checking Accepted or Rejected in the Preliminary Visit section.
Describe the reason for the rejection of any parameter, and inform the customer of all
unacceptable parameters and the reasons for rejection.
If any parameters are marked Rejected during a preliminary site visit, a final visit must be made
to ensure that all unacceptable conditions have been satisfied. Time must be allowed for
corrective action to be taken before the final visit. If, after the final site survey visit, there are still
unacceptable conditions, notify the customer and Service Manager.
The Service Manager should notify the customer that specific system installation requirements
have not been met and that delivery of the system may be delayed if all the site problems are not
resolved before the scheduled installation date.
2. Distribution
Forward a completed copy of the site survey forms to:
a. Customer (Laboratory Supervisor)
b. Randox Office
3. Customer Details

Institution:
Address
City:

County:

Post Code:

Country:

Telephone:
Lab Director:
Primary Contact:

Rx Imola Site Survey


December 2005

Telephone:

4. Installation Route
Analyser dimensions are as follows:
Width

970 mm

Depth

582 mm

Height

690 mm

Weight

150 kg

Provide a brief description of the route the analyzer will take from the delivery area to the
proposed installation site. Particular attention should be made to doorways, staircases, etc.

5. Power Requirements
The Rx Imola requires a 3-pin (or 2-pin depending on site location) power outlet with a ground
(A-Type, S-Type or O-Type) within the reach of the analysers accessory power cable.

Power outlet installation must be referred to qualified personnel only

Specifications

Power

900 VA

Maximum Current Draw

Circuit Breaker Ratings

Input Voltages

Does the AC power outlet meet the required specifications ()?

Yes

No

The system should not be installed near sources of high frequency noise (i.e. centrifuges or
discharge units).
Is the proposed installation site free of such noise ()?

Accepted

Yes

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

6. UPS
The UPS should be capable of supplying 1230 watts for the RX Imola / PC system.
Furthermore, the required maximum power requirements should take into account the
laboratory water system. The UPS needs to maintain this supply for as long as the power out
situation lasts or as determined by the customer.
Maximum Power Consumption (Watts)
Rx Imola

900

Dell E153FP 15 Monitor

164

Dell Optiplex GX280 PC

26

Calculations based on 220-240 AC volt mains at 50 Hz and pf 1.0

Accepted

Rejected

If Rejected, state reasons.

7. Water Requirements
The analyzer needs a purified water generator. The water supply must be within acceptable
reach of the analyser.

Specifications

Pressure

0.15 0.34 MPa

Capacity

18 L

Connection Tubing

Inside diameter: 12

Outside diameter: 18

Does the purified water generator meet the required specifications ()?

Accepted

mm

Yes

mm

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

8. Drainage Requirements
The drainage system must capable of removing at least 18 L of waste per hour.
The drainage outlet should be positioned at least 500 mm lower than the proposed analyzer
position.

Analyser

500 mm

Waste Outlet

Does the drainage system meet the required specifications ()?

Accepted

Yes

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

9. Environmental Requirements
The analyser installation site must satisfy the following environmental conditions:

()

Task
No direct sunlight
Dust free environment
No vibration or excessive sound levels
A floor and supporting worktop capable of holding the analyser weight (~160 kg)
Placement on a horizontal surface
No variation in voltage supply (less than 10 %)
Avoid placement under fluorescent lighting

Are all environmental conditions satisfied ()?

Accepted

Yes

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

10. Temperature / Humidity Conditions


The analyser must meet the following criteria:

()

Task
Indoor temperature: 15 30C
Variation: > 2C per hour
Good air ventilation
Indoor humidity: 45 85% (without condensation)
No exposure to air conditioning or heat exchangers

Are all temperature and humidity conditions satisfied ()?

Accepted

Yes

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

11. Space
Refer to the diagram below for required installation space. This is essential for maintenance and for
exhaust ventilation. (Unit: mm)

<space for exhaust>

150+

PC
300+

Analyser

300+

1340

300+
690

600
970
500+

Front

2470

Are all space conditions satisfied ()?

Accepted

Yes

No

Rejected

If Rejected, state reasons.

Rx Imola Site Survey


December 2005

12. Host Connections


Conditions for communication with the host PC and analyser PC are defined below (bold
indicates default settings):

Baud Rate

Selection of baud rate: 19200 / 9600 / 4800 / 2400 / 300 bps

Data Bit

Data bit length: 7/8 bits

Stop Bit

Stop bit length: 1/2 bits

Parity Bit

Parity: None/Even/Odd

Protocol (E1381)

Normal/No Handshake

Check the proposed installation position of the analyser within the laboratory and the
connection point for the Host PC.
Is there sufficient RS232 cable length to allow connection?
Are all communication conditions satisfied ()?

Accepted

Yes

Yes

No
No

Rejected

If Rejected, state reasons.

13. Laboratory Plan


Rx Imola Site Survey
December 2005

Use the space below to sketch a proposed location of the system in the laboratory, with
particular reference to:
a.
b.
c.
d.

Approximate laboratory dimensions


Distances from the system water supply
Waste drain
Electrical supply

Rx Imola Site Survey


December 2005

Site Survey Report Reviewed by Laboratory Personnel:


Preliminary Visit:
Date:

Signature: _______________________________

Final Visit:
Date:

Signature: _______________________________

Field Engineer / Sales Representative Performing Survey:


Preliminary Visit:
Date:

Signature: _______________________________

Final Visit:
Date:

Signature: _______________________________

Is the site ready for installation ()?

Rx Imola Site Survey


December 2005

Yes

No