Académique Documents
Professionnel Documents
Culture Documents
REPORT
4 X 700 MW PHWR HARAYANA ATOMIC
POWER PROJECT (HAPP)
AT
GORAKHPUR HARAYANA
MECON LIMITED
RANCHI 834 002
(JHARKHAND)
11.S2.Q6SY
NUCLEAR POWER
CORPORATION OF
INDIA LIMITED (NPCIL)
Nabhikiya Urja Bhavan,
Anushaktinagar, Mumbai 400094
May 2012
UNDERTAKING
I hereby undertake that prescribed TOR with respect to EIA/EMP Studies for
Haryana Atomic Power Project (Nuclear power projects and processing of
nuclear fuel) located near Gorakhpur Village, Bhuna Block, Tehsil, Subdivision and District Fatehabad, Haryana has been complied while
conducting the EIA studies. The contents (information and data) as given by
our consultant in the EIA report are factually correct, with full knowledge of
the undersigned.
Date:
Place:
[* Owner or his authorized signatory]
Contact Information:
Functional
Areas
Name of Expert
AP
C.D. Goswami
WP
SHW
Sanjay Sen
RH
SE
EB
HG
Dr. S Veezhinathan
GS
A.K. Mishra
AQ
Dr. V.V.S.N.
Pinakapani
10
NV
Dr. S. Bhattacharya
Involvement
(Period & Task)
Signature &
Date
SN.
11
Functional
Areas
Name of Expert
Involvement
(Period & Task)
LU
Dr. M.K.
Mukhopadhyay
Palash Banerjee
Vishal Skaria
Signature &
Date
Signature:
CONTENTS OF VOLUME I
Item No.
Particulars
List of Tables
List of Figures
List of Drawing
Contents to Volume II
Index to MoEF TOR Coverage in EIA Report
Abbreviations
Summary EIA
1.
Introduction
1.1
General
1.2
Purpose of the EIA Report
1.3
Identification of the Project and Project Proponent
1.3.1
The Project
1.3.2
Project Proponent
1.4
Statutory Requirements
1.4.1
Role of AERB on Establishment of Nuclear Power Project
1.4.2
Consent for Siting for the Proposed Project
1.5
Project Brief
1.5.1
Importance of the Project
1.5.2
Background
1.5.3
Location of the Project
1.5.4
Nature and Size of the Project
1.6
Scope of the EIA Study
1.7
Basic Data Generation, Field Studies and Data Collection
1.8
Structure of the EIA Report
2.
Project Description
Section-I: Project Description
2.1
Introduction
2.2
Type of Project
2.3
Need of the Project
2.4
Site Selection Considerations
2.5
Project Location
2.6
Land Requirement
2.6.1
Land Area
Resettlement and Rehabilitation of PAPs for the Land under
2.6.2
Acquisition Process
2.6.3
Land Acquisition
2.7
Size or Magnitude of Operation
2.8
Proposed Schedule for Approval and Implementation
2.9
Manpower Planning
2.10
Technology / Process Description
2.10.1
Salient Features
2.10.2
Engineering
2.11
Project Details
2.11.1
Safety Objectives and Principles
2.11.2
Barriers to Radioactivity Release
2.11.3
Special Safety Requirements
2.11.4
Safety Classification
2.11.5
General Design Criterion
2012 MECON Limited. All rights reserved
Page No.
viii
xii
xiv
xiv
xv
xx
Es 1 Es 13
1
1
1
1
1
2
2
2
3
7
7
8
8
8
8
13
13
15
15
15
15
15
15
18
20
20
20
21
21
21
22
22
22
22
22
22
25
26
27
29
Page (i)
Item No.
2.12
2.13
2.14
2.15
2.16
2.17
2.18
2.19
2.20
2.21
Particulars
Reactor Process Systems
2.12.1
Reactor Physics
2.12.2
Reactor Fuel
2.12.3
Reactor Core Systems
2.12.4
Reactivity Devices
2.12.5
Moderator Liquid Poison Addition System
2.12.6
Primary Heat Transport System
2.12.7
Moderator System
2.12.8
End Shield and Calandria Vault Cooling Systems
2.12.9
CO2 Annulus Gas System
2,12,10 Secondary Systems
2.12.11 Fuel Handling and Control System
2.12.12 Instrumentation and Control (I&C)
2.12.13 Electrical System
2.12.14 Plant Auxiliaries
2.12.15 Design Life
Reactor Safety Systems
2.13.1
Shutdown Systems
2.13.2
Containment
2.13.3
Containment Spray System
2.13.4
Secondary Containment Recirculation and Purge
2.13.5
Primary Containment Controlled Discharge System (PCCD)
2.13.6
Fire Protection System
2.13.7
Emergency Core Cooling System (ECCS)
2.13.8
Ultimate Heat Sink
2.13.9
Overall Risk to the Public
Radiological Protection
2.14.1
Radiation Levels and Access Control
2.14.2
Contamination Control
2.14.3
Radiation Monitoring
2.14.4
Environmental Monitoring
2.14.5
Effluent Release Criteria
Radio Active Waste Management
2.15.1
Radioactive Waste Management Plant
2.15.2
Treatment and Discharge of Gaseous Effluent Stream
2.15.3
Permissible Gaseous Discharges
2.15.4
Radioactive Liquid Waste Management System
2.15.5
Discharge Limits
2.15.6
Solid Waste Management
Safety Analysis
Plant Layout and Main Plant Buildings
2.17.1
Plant Layout
Power Requirements
Water Requirements
2.19.1
Provision of Water
2.19.2
Water Balance
2.19.3
Cycle of Concentration
Construction Facilities
Power Evacuation
Page No.
34
34
36
37
42
45
45
47
49
49
50
50
51
55
57
64
64
64
65
66
66
67
67
68
69
69
69
69
70
71
71
72
72
72
72
73
73
78
81
85
87
87
87
89
89
89
90
90
90
Page (ii)
Item No.
3.
4.
Particulars
Assessment of New & Untested Technology for the Risk of
2.22
Technological Failure
2.23
Project Cost
2.24
Resodential Complex of HAPP
2.24.1
Basic Features and site plan
2.24.2
Power Requirement
2.24.3
Water Requirement
2.25
Baseline Environmental Scenario
2.26
Impacts and Mitigation Measures due to Project Siting (Location)
2.26.1
Application of R & R Policy
2.26.2
Maintenance of Area Drainage Pattern
2.27
Impact and Mitigation Measures During Construction Stage
2.27.1
Soil Erosion, Topography and Rainfall
2.27.2
Impact on Flora and Fauna
2.27.3
Use of Local Building Material
2.28
Impact and Mitigation Measures During Operation Phase
2.28.1
Sewage Treatment Facilities and Guard Pond
2.28.2
Domestic Solid Waste Management at Township
2.28.3
Traffic Management
2.28.4
Education and Health Facilities, Police and Other Services
2.28.5
Rain Water Harvesting
2.28.6
Energy Conservation Measures
2.28.7
Use of Renewable and Alternate Source of Energy
2.28.8
Aesthetics
2.28.9
Landscape Plan, Green Belts and Open Spaces
Landscape Development and Roadside Plantation in
2.28.10
Residential Complex
Disaster Management Plan for Residential Complex of
2.28.11
HAPP
2.28.12 Security
2.29
Environment Monitoring Programme
Analysis of Alternatives : Technology and Site
Description of Environment
4.1
Introduction
4.1.1
General
4.1.2
Industries within 25km Radius
4.1.3
Project Site and Study Area
Baseline data Generation for Environmental Components
4.1.4
and Methodology
4.1.5
Study Period
Baseline Data Generation / Establishment of Baseline For
4.2
Environmental Components Conventional Pollutants
4.2.1
Meteorology
4.2.2
Ambient Air
4.2.3
Noise
4.2.4
Water Environment
4.2.5
Soil
4.2.6
Ecological Features
4.2.7
Location of National Park / Sanctuary within 10 km Radius
Page No.
90
90
92
92
97
97
98
98
98
100
100
100
100
101
101
101
103
104
104
106
107
107
108
108
108
108
109
109
110
112
112
112
112
112
113
113
114
114
117
123
126
129
132
140
Page (iii)
Item No.
5.0
Particulars
Baseline Data Generation/Establishment of Baseline for Environmental
4.3
Components Radiological Environment
4.3.1
Parameters of Radiological Status
4.3.2
Regulatory Limits for Radiation Exposure
4.3.3
Radiological Survey Around the Proposed Site
4.3.3.1
Ambient Radiation Levels
Estimation of Pre-operational Base Line Levels of
4.4.4.2
Natural and Fallout Radionuclides in
Environmental Samples
4.4
Traffic Density
4.5
Geology and Hydrogeology
4.5.1
Introduction
4.5.2
Physiography
4.5.3
Drainage
4.5.4
Geological Features
4.5.5
Hydrogeology
4.5.6
Seismo-tectonics
4.6
Landuse Pattern
4.7
Socio-Economics Featuires
Anticipated Environmental Impacts & Mitigation Measures
5.1
Introduction
5.2
Impacts and Mitigation Measures Due to Project Siting (Location)
5.3
Impacts and Mitigation Measures Due to Project Design
5.4
Impact and Mitigation Measures During Construction Phase
5.4.1
Land Use
5.4.2
Topography, Site Elevation and Filling Material
5.4.3
Air Quality
5.4.4
Water Quality
5.4.4.1
Surface Water
5.4.4.2
Ground water
5.4.5
Noise
5.4.6
Site Security
5.4.7
Industrial Safety
5.5
Impacts and Mitigation Measures During Operation Phase
5.5.1
General
5.5.2
Radio-active Releases During Operation Phase
5.5.2.1
Radio-active Releases: Air Emissions
Radio-active Releases: Liquid Effluent
5.5.2.2
Discharges
5.5.2.3
Radio-active Releases: Solid Waste Disposal
5.5.2.4
Land Environment
5.5.3
Conventional Pollutants During Plant Operation
5.5.3.1
Air Environment
5.5.3.2
Water Environment
5.5.3.3
Area Drainage and Surroundings
5.5.3.4
Solid Waste Generation and Disposal
5.5.3.5
Hazardous Waste Generation and Disposal
5.5.3.6
Noise Levels
5.5.3.7
Ecological Features
5.5.3.8
Transportation : Impacts and Mitigation Measures
Page No.
140
140
141
142
148
149
153
157
157
158
158
158
159
163
164
165
166
166
166
170
171
173
173
174
174
175
175
176
176
177
177
180
182
185
189
189
189
189
189
198
200
201
201
201
205
207
Page (iv)
Item No.
6.0
Particulars
Impacts and Mitigation Measures for Oversized
5.5.3.9
Dimensional (ODC)
5.5.4
Water and Energy Conservation Measures
5.5.5
Other Measures
5.5.6
Facilities for Casual Workers / Truck Drivers
5.6
Occupational Health and Safety
5.7
Impacts and Mitigation Measures because of Accidents
5.8
Impacts During Decommissioning Phase
5.8.1
General
5.8.2
Methods
5.8.3
Procedure
5.8.4
Surveillance
5.8.5
Documentation
5.8.6
Decommissioning Cost
5.9
Measures for Minimizing and / or Offsetting Adverse Impact
Irreversible and Irretrievable Commitments of Environmental
5.9.1
Components
5.10
Assessment of Significance of Environmental Impacts
5.10.1
General
5.10.2
Criteria for Determining Significance
5.10.3
Environmental Significance Against Predictability Criterion
5.10.4
Manageability Criterion
5.10.5
Issues Under Manageability Criterion
5.10.6
Environmental Significance Against Manageability Criterion
5.10.7
Environmental Significance
Technological Details of Environmental Protection Measures
6.1
Introduction
6.2
Construction Phase
6.3
Operational Phase
Mitigation by Facility Design Containment and
6.3.1
Contamination Control
6.3.2
Mitigation by Facility Design Ventilation System
6.3.2.1
Primary Containment Ventilation System
6.3.2.2
Secondary Containment Ventilation System
Reactor Building Heavy Water Vapour Recovery
6.3.2.3
System
6.3.2.4
RAB Air Conditioning and Ventilation System
6.3.2.5
Emergency Fresh Air Ventilation for MCR
Treatment and Discharge of Gaseous Effluent
6.3.2.6
Stream
6.3.2.7
Ventilation system availability
Mitigation by Facility Design : Radioactive Waste Storage /
6.3.3
Disposal
6.3.3.1
General
6.3.3.2
Radioactive Liquid Waste Management System
6.3.3.3
Radioactive Solid Waste Management System
6.3.3.4
Spent Fuel Storage and Management
6.3.4
Conventional Waste Management
6.3.4.1
Sewage Treatment Plant at HAPP
6.3.4.2
Sewage Treatment Plant at Township
Page No.
213
213
213
213
214
215
216
216
217
217
217
217
218
218
219
219
219
221
224
225
225
227
229
232
232
232
233
233
234
235
236
236
237
238
238
239
240
240
241
245
251
252
252
252
Page (v)
Item No.
7.0
8.0
Particulars
6.3.4.3
Solid Waste Disposal at HAPP
6.3.4.4
Solid Waste Disposal at Township
6.4
Green Belt Development: Mitigation Measures
6.4.1
General
6.4.2
Selection of Species
6.4.3
Plantation Scheme
6.4.4
Post Plantation Care
6.4.5
Phase Wise Green Belt / Cover Development Plan
6.5
Conclusion
Environmental Monitoring Programme (EMP)
Introduction
7.1
7.2
Implementation Arrangement
7.2.1
During Construction Stage
7.2.2
During Operation Stage
7.3
Environmental Aspects to be Monitored
7.4
Environmental Monitoring Programme: Construction Phase
7.5
Environmental Monitoring Programme: Operation Phase
7.5.1
Radiological Monitoring
7.5.1.1
General
7.5.1.2
Monitoring Program at the Work Place
7.5.1.3
Radiological Monitoring on Site
7.5.1.4
Radiological Monitoring in the Public Domain
Other Monitoring Requirements : Occupational Health and
7.5.2
Safety
7.5.3
Monitoring for Conventional Pollutants
7.5.3.1
Work Zone Noise Levels
7.5.3.2
Stack Monitoring for Diesel Generator
7.5.3.3
Flue Gas Monitoring
7.5.3.4
Effluent Monitoring for STP
7.5.4
Meteorology
7.5.5
Ambient Air Quality
7.5.6
Maintenance of Drainage System
7.5.7
Waste Water Discharge from Project Site
7.5.8
Ambient Noise
7.5.9
Ground Water Monitoring
7.5.10
Soil Quality Monitoring
7.5.11
Solid / Hazardous Waste Disposal
7.5.12
Municipal Solid Waste Disposal at Township
7.5.13
Green Belt Development
7.5.14
House Keeping
7.5.15
Socio-Economic Development
7.6
Monitoring Plan
7.6.1
Environmental Monitoring Programme
7.6.2
Progress Monitoring and Reporting Arrangements
7.6.3
Budgetary Provisions for Environmental Monitoring Plan
Budgetary Provisions for Environmental Protection
7.6.4
Measures
7.6.5
Procurement Schedule
7.7
Updating of EMP
Additional Studies: Public Consultation & Social Impact Assessment
Page No.
252
252
252
252
253
253
258
258
259
260
260
260
260
260
262
263
265
265
265
265
267
267
268
269
269
269
269
270
270
270
271
271
272
272
272
272
272
272
273
273
273
273
280
281
283
284
284
285
Page (vi)
Item No.
8.1
8.2
9.0
Particulars
Public Consultation
Social Impact Assessment
8.2.1
Introduction
8.2.2
Objectives
8.2.3
Methodology Adopted for the Study
8.2.4
Existing Socio-Economic Scenario
8.2.5
Prediction of Socio-Economic Impact
8.2.6
Peoples Perception
8.2.7
Conclusions
8.2.8
Corporate Social Responsibility
Additional Studies: Risk Assessment On/Off Site Emergency Plan and
occupational health & safety
9.1
Introduction
9.2
Natural Events
9.2.1
Earthquake Hazard
9.2.2
Flood Hazard
9.2.3
Cyclone Hazard
9.2.4
Landslide Hazard
9.2.5
Evaluation of HAPP Design Post Fukushima Event
9.3
Man Made Events
Aircraft Crash Including Consequences of Impact, Fire and
9.3.1
Explosion
9.3.2
Effect of Accidents Taking Place Outside the Project Site
9.3.3
Enemy Attack / Security Breach / Terrorist Activity
9.4
Events Within Plant
9.4.1
Hazardous Chemicals
Radiological Risk Assessment and Emergency Response
9.4.2
System
9.4.2.1
Introduction & Design Philosophy
9.4.2.2
Safety Objectives
9.4.2.3
Radiological Objectives
9.4.2.4
Monitoring of Environment Around HAPP Site
9.5
On / Off Site Emergency Plan / Emergency Response System
9.5.1
Emergency Standby
9.5.2
Personnel Emergency
9.5.3
Plant Emergency
9.5.4
Site Emergency
9.5.5
Off Site Emergency
9.5.6
Exercises
9.5.7
Emergency Preparedness System for HAPP
9.5.8
Volume I : Plant / Site Emergency Procedure
9.5.9
Volume II : Procedure for Off-Site Emergency
9.5.10
Frequency /Periodicity of Emergency Exercises
9.5.11
Habitability of Control Rooms under Accident Conditions
9.6
Occupational Health and Safety Plan
9.6.1
Corporate Environment OHS Policy
9.6.2
Occupational Health
9.6.3
Occupational Health Surveillance (OHS)
9.6.4
Safety Plan
9.6.5
Safety Organization
Page No.
285
285
285
286
286
288
295
301
303
303
306
306
306
306
306
307
307
309
310
310
310
311
312
312
317
317
317
319
322
323
325
325
325
325
325
326
327
327
328
329
329
332
333
333
333
334
335
Page (vii)
Item No.
10.0
11.0
12.0
13.0
Particulars
9.6.6
Safety and Quality Circle
9.6.7
Safety Training
9.6.8
Occupation Health and Safety - Mitigation Measures
Project Benefits
10.1
Economical Benefits of Nuclear Power
10.2
Levelised Lifetime Cost of Generation
10.3
Effect of Distance from Pit-head on Cost of Generation
10.4
Energy Security: Advantage
10.5
Reduction in Green House Gases (GHGs) Emissions : Advantage
10.6
Socio-Economic Development of the Region
10.7
Socio Economic Benefits
10.8
Employment Potential
10.8.1
Skilled and Semi-skilled
10.8.2
Un-skilled
10.8.3
Direct Employment Opportunities with NPCIL
10.9
Other Indirect Business Opportunities
10.10
Improvements in Physical Infrastructure
10.11
Other Tangible Benefits
10.11.1 Education
10.11.2 Other Benefits
10.11.3 Industrialisation Around the Proposed Project
10.11.4 Pattern of Demand
10.11.5 Consumption Behaviour
Environmental Management Plan
11.1
General
11.2
Organization Policy
11.3
Organisational Set Up
11.3.1
Administrative Set Up
11.3.2
Environmental Laboratory Set Up and Space
11.3.3
Functioning
11.4
Implementation Arrangement
11.4.1
Institutional Implementation Arrangements
11.4.2
Co-ordination with Other Departments
11.4.3
Interaction with State Pollution Control Board
11.4.4
Training
Summary & Conclusion
Disclosure of Consultant
Page No.
336
336
336
337
337
337
337
339
339
340
341
342
342
342
342
343
343
344
344
344
344
344
345
346
346
347
347
347
348
351
351
351
353
353
353
354
355
LIST OF TABLES
Chapter
No.
1
1
1
1
1
1
2
Table No.
Table 1.1a
Table
Table
Table
Table
Table
Table
1.1b
1.1c
1.1d
1.2
1.3
2.1a
Content
Safety Codes/Guides for Regulation of Nuclear and Radiation
Facilities
Safety Codes/Guides for Nuclear Power Plant Siting
Safety Codes/Guides for Operation of Nuclear Power Plants
Safety Codes/Guides for Quality Assurance
List of Consents / Authorizations
Index to MoE&F TOR Coverage in the EIA Report
Break-up of land in different villages to be acquired
Page
No.
4
4
5
5
6
9
20
Page (viii)
Chapter
No.
2
2
2
2
2
2
4
4
Table No.
Table
Table
Table
Table
Table
Table
Table
Table
2.1b
2.2
2.3
2.4
2.5
2.6
4.1
4.2a
Table 4.2b
Table 4.2c1
Table 4.2c2
Table 4.2c3
4
4
4
4
4
4
4
4
4
4
4
4
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
4.2d
4.3a
4.3b
4.3c
4.3d
4.3e
4.4a
4.4b
4.4c
4.5a
4.5b
4.5c
4
4
4
4
4
4
4
4
4
4
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
4.5d
4.6a
4.6b
4.6c
4.6d
4.6e
4.7a
4.7b
4.7c
4.7d
4
4
4
4
4
4
4
Table
Table
Table
Table
Table
Table
Table
4.7e
4.7f
4.7g
4.7h
4.8a
4.8b
4.8c
Content
Actual Land Requirement, Classification of Land and R&R Issues
Time Schedule for the First Two Units of the Project
Classification of Liquid Wastes
Estimated volumes of liquid waste generation at HAPP 1 & 2
Details of Fatehabad Branch of Bhakra Canal near Project site
Breakup of Total Water Requirement for Township
List of Major Industries within 25 km Radius of the Proposed Plant
Environmental Components and the Methodologies Adopted For
the Study
Summarised Monitored Meteorological Data at Gorakhpur March
to May 2011
Wind Frequency Distribution (%) during Day & Night (Overall)
March to May 2011
Wind Frequency Distribution (%) during Day Time March to May
2011
Wind Frequency Distribution (%) during Night Time March to May
2011
Pattern of Annual and Summer Winds in Study Area
Location of AAQ Monitoring Stations
Methodology of Sampling and Analysis for AAQ Monitoring
National Ambient Air Quality Standards
Dates of AAQ Sampling During Summer
AAQ during Summer
Noise Monitoring Locations
Results of Noise Monitoring
Ambient noise level norms
Location of Water Monitoring Station
Surface Water Quality
Central Pollution Control Board (CPCB) Surface Water Quality
Criteria
Ground Water Quality
Selection of Soil Sampling Locations and Justification
Physico-Chemical Properties of Soils
Available Major Nutrients in Soil
Exchangeable Cations
Available Micronutrients
Status of Agriculture at the Project Site
List of plants growing in study area
Average productivity of crops in the region
List of common trees/shrubs growing in and around human
settlement
List of faunal species and their conservation status in the study area
List of common birds and their conservation status in the study area
Plankton Abundance in Bhakra Canal
Fishes found in the study area
AERB Dose Limits
Sector wise major villages in different zones
Terrestrial Sampling Locations
Page
No.
20
22
74
76
89
97
112
113
Page (ix)
114
115
116
117
118
119
119
120
120
124
124
125
127
127
127
128
128
129
130
130
131
131
133
133
136
136
137
137
139
140
141
142
143
Chapter
No.
4
4
4
Table No.
Content
Table 4.8d
Table 4.8e
Table 4.8f
Table 4.8g
4
4
4
4
4
4
Table
Table
Table
Table
Table
Table
Table
Table
4.8h
4.8i
4.8j
4.8k
4.8l
4.9a1
4.9a2
4.9b1
Table 4.9b2
4
Table 4.10a
4
4
4
5
5
Table
Table
Table
Table
Table
4.10b
4.11a
4.11b
5.1a
5.1b
5
5
5
5
5
Table
Table
Table
Table
Table
5.1c
5.2a
5.2b
5.2c
5.2d
5
5
5
Table 5.2a
Table 5.3a
Table 5.3b
5
5
5
5
Table
Table
Table
Table
5
5
Table 5.5
Table 5.6a
5
5
5
Table 5.6b
Table 5.7a
Table 5.7b
Table 5.7c
5.4a
5.4b
5.4c
5.4d
Page
No.
143
144
148
Page (x)
149
150
151
152
152
153
154
154
155
156
157
159
164
165
167
168
172
180
181
181
182
183
186
186
190
192
193
193
201
202
203
207
208
209
Chapter
No.
5
Table 5.7d
5
5
Table 5.7e
Table 5.7f
5
5
5
5
Table
Table
Table
Table
5.8
5.9
5.10
5.11
5
5
5
5
5
5
5
5
Table
Table
Table
Table
Table
Table
Table
Table
5.12
5.13
5.14
5.15
5.16
5.17
5.18
5.19
6
6
7
Table 6.1a
Table 6.1b
Table 7.1
7
7
7
7
7
7
Table 7.2a
Table 7.2b
Table 7.2c
Table 7.3:
Part A
Table 7.3:
Part B
Table 7.4
Table 7.5a
Table 7.5b
7
7
8
8
8
8
8
Table
Table
Table
Table
Table
Table
Table
Table 8.2f
8
8
8
Table 8.3a
Table 8.3b
Table 8.3c
Table No.
7.6
7.7
8.2a
8.2b
8.2c
8.2d
8.2e
Content
Number of Busses with Timing for Transporting Project Personnel
from Township to the Project Site
Total Staff Busses Plying Between Township and Project Site
Increase in Traffic Density on Road Leading to Project Site from
Township
Potential Impacts Verses Mitigation Measures Adopted
Events and their Environmental Consequences
Issues Considered under Predictability Criterion
Level of Certainty in the Prediction of Activity Events and their
Associated Consequences
Predictability Criterion Significance Score
Predictability Criterion Table
Issues Considered under Manageability Criterion
Questions for Addressing Issues under Manageability Criterion
Manageability Criterion Significance score
Manageability Criterion Table
Matrix for Determining Level of Environmental Significance
Activity Environmental Significance (Environmental Damage
Potential)
Classification of Liquid Wastes
Estimated volumes of liquid waste generation at HAPP 1 & 2
Environmental Monitoring Programme Construction Stage (5
Years)
Noise Level to be Monitored
Monitoring of Effluent Inlet & Outlet of ETP
Ambient Air to be Monitored
Environmental Monitoring Plan
Page
No.
210
Page (xi)
211
212
218
220
221
222
224
224
226
226
227
228
230
231
241
242
263
269
270
271
274
279
280
282
282
283
283
288
290
292
292
293
293
295
296
297
Chapter
No.
8
8
8
8
9
9
9
10
10
10
11
11
13
Table No.
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
8.3d
8.3e
8.3f
8.4
9.1a
9.1b
9.2
10.1
10.2
10.3
11.1
11.2
Table 13.1
Content
Demand Functions for Food and Non-food Items
Source-wise distribution of family consumption
Fitted Consumption Function
Peoples Perception on the Project
Threshold Quantity and the Chemicals to be Stored and Handled
List of Toxic Chemicals Stored in Very Small Quantity in Laboratory
Radiological Emergency and Risk to Public
Nuclear and Coal-Fired Power: Per Unit Cost in Paisa Year of
Comparative CO2 (GHG) Emissions from Various Energy Sources
Qualitative Impacts on Socio-economic Environnent
Monitoring / Analytical Equipments Required
List of Coordinating Agencies, which may be involved for specific
Environmental Activities
List of Sectors for which NABET has given Accreditation
Page
No.
298
299
300
302
313
316
332
338
339
341
349
352
355
LIST OF FIGURES
Fig. No.
2.1
2.2a
2.2b
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12a
2.12b
2.13
2.14a
2.14b
2.14c
2.14d
2.15
2.16
4.2a
4.2b
4.2c
4.3a
4.3b
4.3c
4.3d
4.3e
Description
Proposed Project Site at Village Gorakhpur, District Fatehabad, Harayana
Reactor Building Elevation View 1
Reactor Building Elevation View 2
Secondary Shut Down System
37 Element Fuel Bundle
Simplified Schematic Flow Diagram for 700 MWe PHWR
End Fitting Assembly
Sectional View of Calandria
Diagrammatic Representation of PHT System
Pictorial view of main control room panels for 700 MWe Plant
Scematic Diagram of Liquid Waste Management Scheme
Solid Waste Management Scheme
Longitude and Latitude of the Proposed Project Site
Longitude and Latitude of the Township at Badopal Village
Water Balance Diagram for Haryana Atomic Power Plant 1 & 2.
Views of Township Site (February 2012)
View of Township Site - Prosopis juliflora Growth in Waste Land
(February 2012)
Views of Township Site (February 2012)
Road Leading by the Side of Township Site (February 2012)
Conceptual Pant of the Township
Flow Sheet of Sewage Treatment Plant
Wind-Rose During Summer Season: Day Time
Wind-Rose During Summer Season: Night Time
Wind-Rose During Summer Season: Day & Night (Overall)
SO2 Concentration in the study area
NOx Concentration in the study area
PM10 Concentration in the study area
PM2.5 Concentration in the study area
Ozone concentration in the study area
Page No.
19
32
33
36
37
38
39
41
46
54
80
82
87
88
91
93
94
95
96
99
105
115
116
117
121
122
122
123
124
Page (xii)
Fig. No.
4.4a
4.4b
4.5a
4.5b
4.5c
4.6a
4.6b
5.1a
5.1b
5.2a
5.2b
5.2c
5.3
5.4
6.1
6.2
6.3
6.4
6.5
8.1
8.2
9.1a
9.1b
9.1c
9.1d
9.2
9.3
9.4
10.1
11.1
Description
Noise levels during day time in the study area
Noise levels during night time in the study area
Basemap showing project site and radiological survey study area divided in to
different zones and sectors
Radiological survey study area showing terrestrial sampling locations
Radiological survey study area showing aquatic sampling locations
Depth of water level pre-monsoon in the study area (CGWB, 2008)
Depth of water level post-monsoon in the study area (CGWB, 2008)
Pathways of Exposure to Man Air Route
Pathways of Exposure to Man Water Route
Isopleths for SO2 Concentration Due to Proposed Project
Isopleths for NOx Concentration Due to Proposed Project
Isopleths for SPM Concentration Due to Proposed Project
Predicted Noise Levels due to Noise Sources in the Proposed Atomic Power
Plant
Steps for Assessment of Significance of Environmental Impact
Sources and Treatment of Liquid Wastes
Schematic section diagram of RCC trench
Schematic section diagram of the tile hole
Process flow diagram for package rotary klin incinerator
Schematic Diagram of Greenbelt Development
Distribution of Population by Land Holding Size
Occupational Structure of the Study Area
Earthquake Hazard Map Showing Project Site
Flood Hazard Map Showing Project Site
Cyclone Hazard Map Showing Project Site
Landslide Hazard Zone Map of India Showing Project Site
Occupiers Guide
Public Dose at 1.6 Km distance from NPPs (2006-2010) (AERB Prescribed
Annual Limit is 1000 micro-Sievert)
Action Flow Diagram for Site / Off Site Emergencies
Comparison of Waste Production from Nuclear and Thermal Power Stations
Organisation Chart Proposed for Environmental Survey Laboreatory
Page No.
125
126
145
Page (xiii)
146
147
161
162
179
179
195
196
197
204
223
245
249
250
251
255
296
298
307
308
309
310
314
322
331
340
348
LIST OF DRAWINGS
SN
1
2
3
4
Description
Drawing No.
At end of
Chapter No.
2
4
4
4
CONTENTS OF VOLUME II
SN
1
2
3
4
3
4
5
6
6
7
8
9
10
Annexure
ANNEXURE IA
ANNEXURE IB
ANNEXURE IC
ANNEXURE ID
ANNEXURE II
ANNEXURE III
ANNEXURE IVA
ANNEXURE IVB
ANNEXURE IVC
ANNEXURE IVD
ANNEXURE V
ANNEXURE VI
ANNEXURE VII
Page (xiv)
1.
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
Land requirement for the project, along with usage for different
purposes should be given. It should give information relating to
right of way (ROW), if required for pipeline etc, as well as
details of township.
Location of intake as well as outfall points (with coordinates)
should be given.
Topography of the area should be given clearly indicating
whether the site requires filling. If so, details of filling, quantity
of fill material required, its source, transportation etc. should be
given.
Impact on drainage of the area and surroundings should be
given.
Information regarding surface hydrology and water regime and
impact of the same, if any due to the project should be given.
xii)
xiii)
COVERAGE IN EIA
REPORT
REMARKS
Provided
Section 2.17.1,
Chapter 2.
Section 4.1.3, Chapter
4.
Section 4.6, Chapter 4
Section 4.2.7, Chapter
4
No National
Park,
Sanctuary,
Elephant /
Tiger Reserve
(existing as
well as
proposed),
migratory
routes, present
within 10km
radius of the
site.
No ROW
required
SN.
xiv)
xv)
xvi)
xvii)
xviii)
xix)
xx)
xxi)
COVERAGE IN EIA
REPORT
background natural
radio activity, Section
4.3, Chapter 4.
REMARKS
Section 2.28.5,
Chapter 2
Ground Water
will not be
used for the
project.
In the plant
area rain water
harvesting will
not be done to
avoid ground
water
contamination
Section 2.19.3,
Chapter 2
Section 2.19.2,
Chapter 2
Section 6.4, Chapter 6
No ROW
required
SN.
xxii)
xxiii)
xxiv)
xxv)
xxvi)
xxvii)
xxviii)
xxix)
xxx)
xxxi)
xxxii)
xxxiii)
xxxiv)
xxxv)
2.
i)
should be provided.
Details regarding waste management, liquid and solid waste
(conventional and radioactive) should be given in the EIA
report.
Details regarding storage and management of spent fuel should
be given.
Details regarding storage of hazardous chemical including
maximum inventory to be stored at any point of time should be
given.
Detailed risk assessment and disaster management plan
should be given. The risk contours may be plotted on location
map.
Issues relating to de-commissioning of the plant and the related
environmental issues should be discussed.
Demographic data of the study area as well as pre-project
health survey of the population in study area around the project
site should be collected.
Detailed environmental management plan to mitigate the
adverse environmental impacts due to the project should be
given. It should also include possibility of use of solar energy
for the project including measures for energy conservation.
Details of post project monitoring should also include in the EIA
report.
Details regarding infrastructure facilities such as sanitation,
fuel, restroom, medical facilities, safety during construction
phase etc. to be provided to the labour force during
construction as well as to the casual workers including truck
drivers during operation phase.
Public hearing points raised and commitment of the project
proponent on the same. An action plan to address the issues
raised during public hearing and the necessary allocation of
funds for the same should be provided.
Measures of socio economic influence to the local community
proposed to be provided by project proponent. As far as
possible, quantitative dimension to be given.
Impact of the project on local infrastructure of the area such as
road network and whether any additional infrastructure would
need to be constructed and the agency responsible for the
same with time frame particularly keeping in view the
transportation of over sized consignments should be given.
EMP to mitigate the adverse impacts due to the project along
with item wise cost of its implementation.
Any litigation pending against the project and /or any direction
/order passed by any Court of Law against the project, if so,
details thereof.
In respect of the township, the following TORs are prescribed
for addressing the same in the EIA report.
A site plan showing the project site and its surroundings with
COVERAGE IN EIA
REPORT
REMARKS
Refer Chapter 7
Nil
Section 2.24.1,
Page (xvii)
SN.
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
COVERAGE IN EIA
REPORT
Chapter 2.
REMARKS
Section 2.27.3,
Chapter 2.
Section 2.28.5,
Chapter 2
Section 2.28.1,
Chapter 2.
Section 2.28.4,
Chapter2.
For details of Flora &
Fauna refer Section
4.2.6, Chapter 4 &
Section 2.27.2,
Chapter 2.
Section 2.28.9 &
2.28.10, Chapter 2.
Section 2.27.1
Section 2.28.6 and
2.28.7, Chapter 2.
Section 2.28.2,
Chapter 2 and Section
5.5.3.8, Chapter 5.
Section 2.27.3,
Chapter 2 and Section
5.4.1, Chapter 5.
Section 5.2, Chapter
5, and Section 2.26.1,
Page (xviii)
SN.
xv)
xvi)
3.
a)
b)
c)
COVERAGE IN EIA
REPORT
Chapter 2.
Refer Chapter 6, 7 &
11
REMARKS
Page (xix)
ABBREVIATIONS
AAQM
AERB
AFR
AOO
AP
AVS
BA
BARC
BDBAs
BDL
BHAVINI
BOD
COD
CCWS
CDF
CEC
CFU
CHC
CPCB
CVCS
D
D.O.
DAE
DBAs
DBF
DNB
DS
EBS
EDG
EFWS
EIA
EMP
ESL
ESP
F
FA
FBRs
FP
FPCS
FPNGs
GSI
GWPS
HEPA
HP
HPD
I&C
IAEA
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
Page (xx)
ICRP
IIG
IMR
IRWST
IUCN
IVI
KAPP
KKNPP
LBLOCA
LCO
LHSI
LOCA
LP
LRF
MDR
MF
MFW
MHSI
MoEF
MOU
MSS
NAPP
NOx
NPCIL
ODC
OSHA
PAPs
PFBR
PGA
PHC
PPED
PHWRs
PSAR
PWD
PWRs
PZR
R&R
RCC
RAPS
RBA
RCP
RD
RHR
RPM
RPV
RSPM
RSS
SAHRS
SDI
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
Page (xxi)
SG
SO2
SPM
SRW
SSE
SSS
TAPS
TDS
TSS
US
:
:
:
:
:
:
:
:
:
:
Steam Generator
Sulphur dioxide
Suspended Particulate Matter
Solid Radioactive Waste
Safe Shutdown Earth Quake
Start-up and Shutdown System
Tarapur Atomic Power Station
Total Dissolved Solids
Total Suspended Solids
Up Stream
Page (xxii)
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
EXECUTIVE SUMMARY
1.0
INTRODUCTION
Nuclear Power Corporation of India Limited (NPCIL) is a Public Sector Enterprise under
Department of Atomic Energy (DAE), Government of India. NPCILs objective is to develop
nuclear power technology and to undertake generation of electricity under the provisions of
Atomic Energy Act, 1962. NPCILs emphasis is to produce Nuclear Power as a safe,
environmentally benign and economically viable source of electrical energy to meet the
increasing needs of the country.
In pursuance of Environmental (Protection) Act, 1986 and EIA notification 2006, new projects
necessitate statutory prior environmental clearance by conducting an Environmental Impact
Assessment (EIA) study. NPCIL entrusted MECON Limited to conduct an EIA study for the
proposed project.
2.0
PROJECT DESCRIPTION
2.01
2.02
Location
The project site is located in Gorakhpur Village, Bhuna Block, Tehsil, Sub-division & District
Fatehabad, Haryana, at geographical co-ordinates of longitude 750 37 56 E and latitude 290
26 30 N. and situated about 215 to 218m above mean sea level (MSL). The site is about 28
km in SE direction of Fatehabad town (district head-quarter) and is about 6.0 km from NH10
(connecting Hisar to Fatehabad).
The nearest railway station is Uklana Mandi (23 km) on Northern railway. Hisar is situated
about 33 km on the SSE of the project site. The nearest Airports to the plant site is at Hisar
(used for Helicopter training) at a distance of about 40 km from the plant site and Indira
Gandhi International Airport, Delhi is about 208 km from project site. The Bhakhara Canal
(Fatehabad Branch) flows from east to west towards north close to the site. There is no
major industry and no place of historical importance within 10 km off the site. There are no
facilities for handling, storing or transporting inflammable/toxic material and no major railway
siding or road transport depot within 10 km of the site. The site connects NH10 by
Kharakheri-Gorakhpur road. The Index map showing the location of the plant site is shown in
Fig. 1.
The total 1503.5 acres (608.48 ha) land required is private land, of which that required for
the project is about 1318 acres (533.5 hectares) and that for township is about 185.42
acres (75.04 hectares). The project site land (534 ha) comprises 1273.2 acres or 515.24 ha
of land under agricultural category and 32 ha of land is not cultivable. The land at the
township comprises mostly barren land. The locations of proposed site at Gorakgpur is
shown in Fig. 1.
2.03
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Shield, Calandria, Coolant Channels, End Fittings, Primary Coolant pumps, Heat
Exchangers, Fuelling Machine components, etc.
Proposed Site
NH
NH
Other Roads
Canals
Reactor Building (RB) and Reactor Auxiliary Building (RAB) house the main reactor and
associated process systems,
Safety related Buildings other than Nuclear Building consisting of Control Building (CB),
Station Auxiliary Building (SABs), Ventilation Stack with Monitoring Room and Station
Auxiliary Buildings (SABs), D2O Upgrading Plant Building, Waste Management Facility
and Exhaust Ventilation, Induced Draught Cooling Towers, Safety Related Pump House
(SRPH), Fire Water Pump House, Underground Tunnels and Trenches, Diesel Oil
Storage Area (DOSA), Emergency Makeup Water Pond, Covered Passage, etc as per
the design features of the plant.
Power Evacuation in principal is feasible for 2800 MWe power from site. The Power
generated at HAPP will be evacuated through 400 kv transmission system. The number of
2012 MECON Limited. All rights reserved
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
transmission outlets and their destination will be finalized taking into account share of
beneficial state in due course after a detailed power system studies are carried out by Power
Grid Corporation of India Limited (PGCIL) and approved by the concerned authorities
The project will use Natural uranium oxide as fuel and heavy water (D2O) as coolant and
moderator for the reactor with on-power refueling of reactor.
Steam generators supply nearly dry saturated steam to the turbine and turbine is directly
coupled to an electrical generator, which produces electricity. Generator voltage is stepped
up by the generator transformer. Generated power is transmitted to the grid from the nuclear
power station at 400 kV.
The concept of defense-in-depth is adopted in design of safety systems. Provision of multiple
barriers, double containment structures with liner on inner containment wall of Reactor
Building, containment spray cooling system, emergency core cooling system, reactor shut
down systems etc. as engineered safety systems ensure safe operation of reactor. Reactor
protection system ensures shutdown requirements through two independent fast acting shut
down systems. Reactor regulating system enables automatic control of reactor power and
maintains neutron flux profile.
Construction of the project will be taken up in two stages of 2X700 MWe each. Subsequent
two units are expected to be four years later. The 1st stage project will be commissioned in
60 months from the Zero-Date as August 2013 i.e. the start of construction activities at
site.
During construction stage maximum of 8000 persons (when construction of stage-I will be
nearing completion and construction of stage-II will be started) will be temporarily deployed
and up to the final stage of the project about 1700 manpower will be required (covering
technical and general administration).
During construction & commissioning maximum 10 MW power will be required which will be
sourced from State Grid. The water requirement for the project will be met from Fatehabad
Branch of Bhakra Canal. Assurance has been given to supply 783 Million Liters per Day
(MLD) or 32625 m3/hr and that for the township about 0.65 MLD or 27 m3/hr of water from
Haryana Government. About 18000m3/hr of water will be required for unit 1 to 4 for cooling
tower makeup and other plant requirements. Out of which 12680 m3/hr will be towards
consumptive use and the rest of the 5320 m3/hr will be returned to canal.
Township
A residential colony for about 1700 employees has been envisaged, with main features as
follows:
a. Land area is : 75 Ha
b. Ground Coverage area : 28.4 Ha (37.8%)
c. Built up area = 26.00 Ha [Floor Space Index (FSI1) : 0.34].
d. The township will have a maximum height of Ground + two stories limited to maximum
height of 11.45 m.
e. Water Consumption = 1.250 Million Litres Per Day (MLD) or 1250 m3/d
f. Power requirement = 2000 KVA for stage one and 2000 KVA for stage two. A 500 KVA
Standby DG set will be provided.
g. Connectivity: Via local roads near Badopal village on National High way number (NH-10)
connecting Hisar and Fatehabad.
1 Floor Space Index (FSI) = Total floor area including walls of all floors / Plot Area / Building Unit
2012 MECON Limited. All rights reserved
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
h. Parking requirements: Adequate parking space of about 1500 cars, light commercial
vehicles, buses etc. - available in the township.
i. Community facilities:
Hospital, Community centre, School and shopping centre
recreation club, sports complex, play ground, bank, post office, petrol pump etc. will be
provided in the proposed township.
j. All the civic amenities.
k. Measures to minimize energy consumption
Use of CFL2
Use of Low-pressure sodium lamps for outdoor lighting along the road and security
lighting with Solar Street Lights mix.
Use of solar water heater for hospital, guest house.
Automatic timing control mechanism will be incorporated in the street lighting to save
energy. Mechanism will involve staggering of on-off sequence of street lights.
l. Sewage treatment plant of 1MLD envisaged for treatment of sewage water. The treated
sewage shall be disinfected / filtered and used for gardening purpose.
m. Green belt will be developed in and around the township.
n. A fire extinguishing system as per the requirements of national Building Code will be
provided.
The estimated cost of 4 X 700MWe PHWR Atomic Power Project is about Rs 23502 Crores
(base cost 2011-12).
3.0
3.01
General
Study area has been taken as 10km radius around the project site for conventional pollutant
and other baseline study for which the baseline environmental data monitoring was
conducted during March 2011 to May 2011 (summer season). Whereas for baseline
radiological monitoring the study area taken was 30km radius around the project site and the
study was conducted during January to March 2011.
3.02
Meteorology
In summer season overall, the predominant wind directions for March 2011 May 2011 were
NW, W, NE, SE, SW, and N (prevailing for 16.03%, 10.06, 6.33, 4.75 and 4.34 of the time).
Calm conditions prevailed for 29.39% of the time. The wind velocity was mostly between 1.6
to 18.0 km/hr (70.59% of the time).
3.03
Parameters
SO2
Max
3
(g/m ) Min.
Avg
C 98
Khaujri
A8
11
5
7
11
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Parameters
NOx
Max
3
(g/m ) Min.
Avg
C 98
PM10 Max
(g/m 3) Min.
Avg
C 98
PM2.5 Max
(g/m 3) Min.
Avg
C 98
O3
Max
3
(g/m ) Min.
Avg
C 98
Gorakhpur
A1
31
9
17
29
85
53
78
85
49
22
37
48
35
22
28
35
Nehla
A2
23
7
13
20
84
52
72
84
49
29
41
49
33
21
26
33
Siwani
A3
36
8
21
36
84
49
72
84
46
28
39
46
34
20
26
33
Khaujri
A8
17
8
13
17
65
45
59
65
44
30
38
44
34
21
26
33
3.04
Ambient Noise
Noise mmonitoring was conducted at ten locations in and around the project site. The values
at all stations were below the respective statutory norms as applicable.
3.05
Water Environment
Four surface and four ground water samples were analysed for the study. All the parameters
in surface waters were within the CPCB norms for Classes B, C, D, and E for surface water.
Ground water analysis reveals that in village Sabarwas (GW2), total hardness, Chloride,
TDS, Ca, Mg and Alkalinity is exceeding the respective desirable / permissible norms of
IS:10500. Whereas in village Samani (GW3) TDS is higher than desirable limits. Other
parameters of all the samples are within the limits with the drinking water quality standards
(IS :10500).
3.06
Soil
Soil samples were analysed for ten locations in and around the project site and were found
good for plant growth.
3.07
Ecological Features
There is no wildlife or bird sanctuary within the study area. The study area falls under agroclimatic zone Trans-Gangetic Plains Region and under climatic region arid to semi arid characterised by dryness and extremes of temperature and scanty rainfall. The vegetation is
characterized by tropical desert thorn and comprises predominantly of xerophytes.
3.08
Traffic Density
The traffic density on NH 10 is highest for LMV (5167/d), followed by HMV (1841/d) and two
wheelers (1940/d), whereas that on road leading to project site from NH 10 is highest for two
wheelers (452/d), followed by LMV (341/d) and HMV (11/d).
3.09
Hydrogeology
Normal annual rainfall of Fatehabad district is 373 mm falling in 22 rainy days. The
groundwater is in water table condition at a depth of 3 to 20m below ground level and in semi
confined.
3.10
Socio-economic Status
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
The 10 km study area consists of 83044 persons. Basic socio-economic conditions are:
The population density up to 5 km is minimum followed by that in 10 km radius.
The study area consists of mostly rural population.
Predominance of individual land holdings in small to marginal category. Wheat is mostly
grown followed by cotton, paddy, gwar, etc.
The employment rate is moderate: 43% are engaged as main workers, 17% as marginal
workers and 40% as non-workers. Agriculture and small commercial activities plays an
important role in rural economy.
3.11
3 UNSCEAR 2000, Sources and effects of ionizing radiation, Report to General Assembly, with Scientific
Annexes, United Nation, 2000.
2012 MECON Limited. All rights reserved
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Radioactivity levels in food and related matrices are monitored in terms of 137Cs and 90Sr in
ten (10) biota (biological) samples, covering grass, cereals, leaves, fruits, etc. The activity
levels of 137Cs and 90Sr are comparable to the levels reported elsewhere(4).
4.0
4.01
4.02
4 UNSCEAR 2000, Sources and effects of ionizing radiation, Report to General Assembly, with Scientific
Annexes, United Nation, 2000.
2012 MECON Limited. All rights reserved
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
4.03
4.3.1
Radio-active Releases
The uranium dioxide (UO2) is used as fuel. At normal operating conditions all solid fission
products are permanently retained in UO2 matrix and only a fraction of noble gases and
volatile products diffuse into the inter space between fuel and cladding. Waste management
operations (liquid and solid), involves handling of radioactive wastes from all the facilities for
their ultimate storage/disposal.
All the processes / operations are carried out in leak tight enclosures, under negative
pressure so that the probability of the radioactive materials reaching the working
environment is reduced to a minimum. However, a small fraction of these radio-nuclides are
released into the environment in the form of gaseous emissions and liquid effluents are
released into the environment within statutory limit.
The radiation dose limit specified by AERB for the general pubic at the fence post (exclusion
zone) due to operation of all facilities within the site through all pathways is 1 mSv/yr (100
mrem/y). Compliance to this regulatory requirement is ensured by dose apportionment
estimation for different types of radio-nuclides of all the facilities. The dose apportionment
estimation implicitly specifies discharge limits for each kind of anticipated radionuclide. A
conservative estimate of dose apportionment of radioactivity released from HAPP has been
done as 0.40 mSv for the twin-unit 700-MWe HAPP.
Radioactive Air Emissions
Impacts:
The radioactivity through air route will be discharged within AERB limit which will not cause
any adverse impact to surrounding life systems.
Mitigation Measures
Design of the plant is based on minimizing the leakages from the plant system in to plant
buildings so that generation of radioactive effluents is minimized.
Gaseous radioactive effluents from reactor and service building ventilation exhaust
systems are passed through pre filters and absolute filters (to confine any radioactive
materials in the exhaust streams) before discharge through the 100m ventilation stack.
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Gaseous effluents are continuously monitored for radioactivity content before discharging
through ventilation stack.
Conventional Pollutants
Air Environment : Impacts
No direct use of fossil fuel in the plant process. However, for each unit of 700MWe there are
4 DG sets (1w + 3 stand by), for use during power failure. Each DG set is of capacity 4.2 MW
(sufficient for supplying power to one 700MWe reactor unit) with fuel (HSD) consumption of
979kg/hr. Thus 4 DG set will run for 24 hours during emergency power failure situation.
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
The resultant ambient air concentrations if the DG sets are run for 24 hrs continuously has
been presented in Table 3 for PM, SO2 & NOx. The values of different parameters are well
within the National Ambient Air Quality norms. Thus there will not be any adverse changes in
AAQ in the study area due to the project.
Table 3: Expected Ambient Air Quality after Proposed Plant
Monitored
Anticipated Maximum contribution of
AAQ after
(Max. C98)
pollutants in g/m3 due to proposed plant
proposed plant
(g/m3)
(g/m3)
(maximum GLC occurrence co-ordinate)
Four DG sets of 4.2 MW capacity each during emergency running continuously for 24 hrs
RPM
87.0
1.5 (18, 2.5km)
88.5
SO2
19.0
1.29 (17, 2.5km)
20.3
NOx
40.0
1.3 (17, 2.5km)
41.3
*Concentrations are in g/m3 and of 24 hours averaging time. Values in the parenthesis indicate
the coordinates of the grid points in Km (10, 10 km) is the centre of the plant.
Pollutants
Mitigation Measures
During the design phase all efforts have been made to adopt latest state of art technology
and to install adequate pollution control measures for point and fugitive emission sources so
as to meet the MOE&F / CPCB air emission norms. The following mitigation measures will
be employed to reduce the pollution level to acceptable limits:
Stack monitoring to ensure proper functioning of pollution control systems.
Air monitoring in the Work-zone.
Adequate plantation in and around different units and around the plant.
Monitoring of ambient air quality (AAQ).
4.3.3
4.3.4
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
4.3.5
All the equipment in different units designed/operated that the noise level will not exceed
85 dB (A) at a distance of 1m.
The noise generating equipments are housed in acoustic enclosures / buildings. The
presence of exclusion zone (1 km) with greenbelt will serve to insulate generated noise.
4.3.6
Workers exposed to noise level will be provided with protection devices like earmuffs and
will be deployed with rotational duties.
All workers will be regularly checked medically for any noise related health problem and
if detected, they will be provided with alternative duty.
Impact of Transportation
During construction stage there will be only marginal increase in traffic load on the road
leading to the project site, thus no impact is anticipated due to the same. However, the over
sized consignment maximum one vehicle per day will be plying on the road. For catering to
oversized consignment, the road leading to project site will be adequately widened and
strengthened.
During operation phase, the increase in vehicular movement for manpower transportation
from township to the plant (4 km), there will be some increase in traffic load only for short
duration during the opening and closing time of main shift office hours. Thus no congestion
of traffic on the road leading to project site is envisaged.
4.3.7
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Direct Disturbance: Ten feet high fencing erected all around the project site and the
green belt erected along the fencing will reduce the impact of direct disturbance.
Noise disturbance to faunal species: All technological measures to reduce noise
generation envisaged in plant design, moreover the green belt along the project boundary
will reduce the noise level.
Strong Light during Night: All the light posts erected along the boundary will face
inwards and down wards to reduce light spread out side the plant boundary.
4.3.8
4.3.9
Proper control of fugitive dust from sources inside plant including open stockyards. The
dust in work zone will be regularly monitored and reported for necessary control action.
Based on the environmental monitoring for dust, gases, radioactivity levels, noise &
vibration, the workers exposed to these will be regularly checked in medical unit and
results will be intimated to management.
Spot cooling facilities for workers exposed to high heat generating shops and will be
checked periodically.
Socio-economic Impacts
Advantages
i.
Project may generate more employment, directly and indirectly, and major portion of
it may be provided to the local people.
ii. Development of business opportunity in the area.
iii. Development of infrastructure facilities including roads may help in improving the
whole area.
iv. Improvement in living standard.
Disadvantages
ii. The releases from the plant during normal as well as off normal situations will be
maintained within the AERB approved limits and hence will not cause any advense
impact in the public domain.
iii. People perceive that the increase in pollution may cause damage to agriculture and
damage to health of people due to pollution.
iv. Loss of agricultural land.
Mitigation Measures
The community development efforts of the project for its stakeholders will fulfill their
aspirations.
The project will have structured interactions with the community to disseminate the
measures taken by the plant and also to elicit suggestions for overall improvement for
the development of the area.
Proper compensation to the Project Affected Persons (PAP).
More Higher secondary schools
Dispensaries / Health Centers and availability of doctors and other para-medical staff
Drinking water supply schemes
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
Loan facility for self employment to open petty shops, purchase of cycle rickshaws,
agricultural tools and implements, bullock carts, fertilizers, improved seeds and digging
of well for irrigation.
5.0
6.0
RISK ASSESSMENT
The major chemicals which will be stored by the project is only High Speed Diesel Oil (HSD).
However, the handled quantity is well below the lower threshold limit. Accordingly only rule
17 (of Manufacture, Storage and Import of Hazardous Chemical (Amendment) Rules, 1989
and its Amendment Rules 2000) applies, i.e. preparation and maintenance of material safety
data sheets are required and has been taken care off.
7.0
SN
1.
2.
3.
4.
5.
8.0
Executive Summary
4 X 700 MW PHWR HARYANA ATOMIC POWER PROJECT
AT GORAKHPUR HARYANA
The plant is designed with latest state of art technology so as to achieve minimum
radioactive releases (within AERB norm) from air and water route and minimal release of
conventional pollutants emitted from plant operation in form of air emissions, waste water
and noise levels. Further, maximum re-use wastewater has been envisaged.
The EIA report has thoroughly assessed all the potential environmental impacts associated
with the project. The environmental impacts identified by the study are manageable. Site
specific and practically suitable mitigation measures are recommended to mitigate the
impacts and to comply with AERB stipulation with considerable margin. Further, a suitably
designed monitoring plan has been provided to monitor and control the effectiveness of
envisaged mitigation measures during the operation phase.
CHAPTER 1 : INTRODUCTION
1.1
GENERAL
The report is an Environmental Impact Assessment (EIA) report for the proposed 4X700
MWe PHWR Haryana Atomic Power Project (HAPP) of Nuclear Power Corporation of
India Limited (NPCIL). The report is prepared as per the procedure specified in the EIA
2006 Notification of Ministry of Forest and Environment (MoE&F).
1.2
1.3
1.3.1
Page 1
Chapter 1
1.3.2
Project Proponent
Nuclear Power Corporation of India Limited (NPCIL) is a Public Sector Enterprise under
the administrative control of the Department of Atomic Energy (DAE), Government of
India. NPCILs objective is to develop nuclear power technology and to undertake the
activities of design, construction, operation and maintenance of atomic power stations
for generation of electricity in pursuance of the schemes and programme of the
Government of India under the provisions of Atomic Energy Act, 1962. NPCILs
emphasis is to produce Nuclear Power as a safe, environmentally benign and
economically viable source of electrical energy to meet the increasing needs of the
country.
1.4
STATUTORY REQUIREMENTS
Page 2
Chapter 1
(c)
(d)
(e)
Commissioning
Operation
De-commissioning
Page 3
Chapter 1
For evaluating the suitability of the site for locating the Nuclear Power Plant,
following are the major aspects that are considered.
i) Effect of external events (natural and man-induced) on the plant
ii) Effect of plant on environment and public
iii) Implementation of emergency procedures particularly protective counter measures
in the public domain.
The Site Evaluation Committee conducts its review based on the AERB Safety Code
No. AERB/SC/S.
Other Consents and Authorizations
The lists of consents / authorizations that have to be obtained and maintained for HAPP
are given in Table 1.2. These authorizations / consents shall be obtained prior to start of
construction or before the actual occurrence of the activity whichever is early.
Table 1.1a:
AERB Safety
Code/Guide Number
AERB/SG/G-1
AERB/SG/G-2
AERB/SG/G-3
AERB/SG/G-4
AERB/SG/G-5
AERB/SG/G-6
AERB/SG/G-7
AERB/SG/G-8
Title
Consenting Process for Nuclear Power Plants and Research Reactors:
Documents Submission, Regulatory Review and Assessment of Consent
Applications.
Consenting Process for Nuclear Fuel Cycle and Related Industrial Facilities:
Documents Submission, Regulatory Review and Assessment of Consent
Applications.
Consenting Process for Radiation Facilities: Documents Submission,
Regulatory Review and Assessment Of Consent Applications.
Regulatory Inspection and Enforcement in Nuclear and Radiation Facilities.
Role of Regulatory Body with respect to Emergency Response and
Preparedness at Nuclear and Radiation Facilities.
Codes, Standards and Guides to be Prepared by the Regulatory Body for
Nuclear and Radiation Facilities.
Regulatory Consents for Nuclear and Radiation Facilities: Contents & Format
Criteria for Regulation of Health and Safety of Nuclear Power Plant
Personnel, the Public and the Environment
Title
Code of Safety in Siting of NPPs
Meteorological Dispersion Modeling
Hydrological dispersion of Radioactive Materials in relation to Nuclear Power
Plant Siting
Extreme value Analysis for Meteorological Parameters
Hydro-geological Aspects related to NPP Siting
Calculation Models for Dose from Concentrations
Design Basis Flood for Inland Sites
Design Basis Flood for Coastal Sites
Man induced events and establishment of DBs
Influence of Site Parameters on Emergency Preparedness
Page 4
Chapter 1
AERB Safety
Code/Guide Number
AERB/SG/S-9
AERB/SG/S-10
AERB/SG/S-11
Title
Population Distribution and its Analysis
Quality Assurance in Siting
Design Basis Ground Motion for Nuclear Power Plant Sites
Title
Code of Practice on Safety in NPP Operation
Training & Qualification of Operating Personnel of NPPs
ISI of NPPs
Operational Limits and Conditions for NPPs
Commissioning of NPPs
Radiation Protection during Operation of NPP
Preparedness of the Operating Organization for Emergencies at NPPs
Maintenance and Modifications of NPPs
Surveillance of Items Important to Safety in NPPs
Management of NPPs for Safe Operation
Core Management and Fuel Handling for Heavy Water Reactor Based NPPs
Core Management and Fuel Handling for Boiling Water Reactor Based NPPs
Operational Management of Radioactive
Effluents and Wastes Arising in NPPs
Renewal Of Authorisation for Operation of NPPs
Operational Experience Feedback for NPPs
Life Cycle Management of NPPs
Probabilistic Safety Assessment Guidelines
Title
Code of Practice on QA for Safety in NPPs
Quality assurance in the design of nuclear power plants.
Quality assurance in procurement of items and services for nuclear power
plants.
Quality assurance in the manufacture of items for nuclear power plants.
Quality assurance during site construction of nuclear power plants.
Quality assurance during Commissioning and Operation of nuclear power
plants.
Assessment of Implementation of QA Program
Establishing and Implementing QA Program
Non-conformance control and Corrective Actions
Documents and Records
Page 5
Chapter 1
3.
4.
5.
Aspect
Regulatory Consent for Siting
Regulatory Consents for
Construction.
Excavation
First pour of concrete
Erection of Major Equipment
Regulatory Consents for
Commissioning
Regulatory Consents for Operation
Regulatory Consents for
Authorization for Power Generation.
6.
7.
8.
9
10.
11.
12.
13.
14
18
19
Lifts / Elevators
20.
21.
15
16.
17.
Legislation reference
Atomic Energy Act 1962
Atomic Energy Act 1962
Issuing authority
AERB
AERB
AERB
AERB
AERB
AERB
MoE&F
State Pollution Control
Board
State Pollution Control
Board
AERB
AERB
Page 6
Chapter 1
1.5
1.5.1
PROJECT BREIF
Importance of the Project
National
The development of power generation projects plays a key role in the economic growth
of a country. Power is the most important and crucial factor for growth and development.
Per capita electricity consumption is a major indicator of economic status of a country
and an index of industrial prosperity.
The development of the power sector in the country since independence has been
predominantly through the thermal and hydro power plants. Electric power generation
through nuclear power plant is essential and the need of the hour as coal reserves are
limited and only hydro power generation will not be able to meet the growing countries
demand of power in future. Hence setting up of new nuclear power plants is inevitable.
Although several new power projects of diversified energy sources have been identified
by Government of India with a view to bridge the gap between the demand and
availability, only a few could be taken up for implementation due to financial and other
constraints. This has resulted in large shortfall in the availability of both peak power and
energy as per 17th Electric Power Survey carried out by Central Electricity Authority
(CEA). The present demand for electrical power continues to grow and will continue to
outstrip the available and planned generation capacity leading to chronic shortage of
available power and energy in the future years.
Nuclear power is the fourth-largest source of electricity in the country after thermal,
hydroelectric and renewable sources of electricity. In the country, as on April 2012, 20
nuclear reactors with a total capacity of 4780 MWe are in operation - generating 4,680
(excluding Rajasthan Atomic Power Station (RAPS) 1 MWe while seven numbers of
reactors are under construction with this the total installed capacity will be 10080 MWe.
The nuclear power industry in the country is undergoing rapid expansion with plans to
increase nuclear power output to 63,000 MWe by 2032.
Considering the increasing demand of electricity, NPCIL intends to install a 4X700MWe
PHWR atomic power project at Gorakhpur, District Fatehabad, Haryana. NPCIL is well
positioned to fulfill its role in the nations quest for higher growth and development in the
new millennium.
Regional
The growth of industry significantly contributes to economic growth of the Nation as well
as to the region as it generates employment both directly and also due to development
of infrastructure and market. The infrastructural and other social amenities grow in the
region leading to overall development of the region. Establishment of the proposed
atomic power plant at Fatehabad District will promote the overall development of the
region and will reduce coal transportation from large distances for land locked Northern
Grid.
Page 7
Chapter 1
1.5.2
The planned project will use state of art technology which will result in manufacture of
products at a lower cost and more importantly in an environment friendly way.
Background
The site has been approved by Govt. of India based on the recommendation of the site
selection committee constituted by Government of India for identifying suitable sites for
Nuclear power projects and assigned to NPCIL through an authorization by Department
of Atomic Energy (DAE) to establish NPP units (Annexure IA). During site selection /
approval process, as a procedural requirement Haryana Government granted
permission for Harayana Atomic Power Plant (HAPP) which implicitly grants
administrative approval for acquisition of land and power connectivity for construction
and operation of HAPP.
MoE&F accorded Terms of Reference (TOR for conducting EIA study for the project at
Gorakhpur site in the 9th meeting of the Expert Appraisal Committee (EAC) on
Environmental Appraisal of Nuclear Power Projects of Ministry of Environment & Forest
(MoE&F) held on 21st September 2010
1.5.3
1.5.4
1.6
Page 8
Chapter 1
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
Chapter 1
SN
xiv)
xv)
xvi)
xvii)
xviii)
xix)
xx)
xxi)
xxii)
xxiii)
xxiv)
Chapter 1
SN
Refer Chapter 9
Chapter 6, 7 & 11
For Solar energy refer
Sections 2.28.6 & 2.28.7,
Chapter 2.
Refer Chapter 7 & 11.
Section 5.4.1,
Chapter 5.
Section 5.5.6, Chapter 5.
To be addressed after public
hearing
Refer Chapter 7
Nil
Chapter 1
SN
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
3.
a)
Chapter 1
SN
b)
c)
1.7
1.8
Page 13
Chapter 1
studies, whereas the Volume II contains the special study reports (as Annexures) as
carried out by various independent institutes / agencies and other supporting documents.
EIA Volume I consists of the following chapters:
Executive Summary
Chapter 1
Introduction
Chapter 2
Project Description
Chapter 3
Description of the Environment
Chapter 4
Anticipated Environmental Impacts and Mitigation Measures
Chapter 5
Technologial details of environmental protection measures
Chapter 6
Environmental Monitoring Programme
Chapter 7
Additional Studies: Public consultation and Socio-economic Studies
Chapter 8
Additional Studies: Risk Assessment Studies
Chapter 9
Project Benefits
Chapter 10
Environmental Management Plan (EMP)
Chapter 11
Summary and Conclusion
Chapter 12
Disclosure of Consultant Engaged
EIA Volume II
The Volume II contains special study reports from the Institutes / Agencies including
supporting documents / Annexures of the Volume I (the main EIA study report) as
presented below :
Annexure IA
Annexure IB
Annexure IC
Annexure ID
Annexure II
Annexure III
:
:
Annexure IVA
Annexure IVB
Annexure IVC
Annexure IVD
:
:
:
:
Annexure V
:
:
Annexure VI :
Annexure VII :
Page 14
Chapter 1
INTRODUCTION
Nuclear Power Corporation of India Limited has developed comprehensive capability in
the Design, Construction, and Operation & Maintenance of Pressurized Heavy Water
Reactors (PHWRs) type of nuclear power reactors. Considering the scenario of power
demand in the country, NPCIL have planned to set up a 4X700 MWe Atomic Power
Project at Gorakhpur Village, in the district of Fatehabad, Haryana.
2.2
TYPE OF PROJECT
The proposed project falls under the project or activity type - "Nuclear Power Project and
Processing of Nuclear Fuel" falling under Category A (as per Ministry of Environment
and Forests (MoE&F) EIA Notification 2006), which requires prior environmental
clearance from the Central Government in the MoE&F. The proposed plant of NPCIL
will produce 4X700 MWe electricity.
2.3
2.4
Page 15
Chapter 2
analyses the site with respect to the requirements of NPPs. As the State Government
Haryana has given umbrella consent for establishment of HAPP at Gorakhpur, the
Government subsequently facilitates the administrative approval for acquisition of private
and government land and power connectivity for construction and operation of HAPP.
The parameters analysed by site selection committee while selecting a candidate site:
a. Location and General Area
b. Land availability
c. Available source of cooling water
d. Electrical System
e. Meteorology
f. Population Distribution
g. Land Use
h. Foundation Conditions & Seismicity
i. Flood Analysis & Safe grade elevation at site etc.
j. Solid Waste Management & Radiological Burden
k. Proper access for transportation of heavy / over dimensional equipment.
l. Environment aspects
The site selection committee, during process of site evaluation and while submitting their
recommendations in June 2003, had recommended Gorakhpur site suitable for setting
up of four units of 700 MWe PHWRs in two stages of 2X700MWe PHWRs.
The following are some of the salient features of the proposed site for Atomic Power
Project:
Site Location :
(i) The adequate land required to set up multi unit APPs at Gorakhpur for plant site and
residential complex is being acquired in one go. The land to be acquired for the
plant site and the township involves no displacement of homestead population. Most
of the land being acquired for residential complex is barren.
(ii) Water availability and drawl of cooling water from Fatehabad branch of Bhakra canal
is assured at the site by State Government of Haryana.
(iii) The site is located in the Indo-gangetic alluvial plains with soil made up of both older
and newer alluvium with a thickness estimated to be of the order of about 300m.
The above geological formations are favorable for foundation conditions as required
for APP.
Site Seismicity :
(iv) The site area lies in Seismic Zone-III in the Seismic Zoning Map of India. The
seismo-tectonic study has concluded that there is no capable fault within five
kilometers of the project site. The site is engineer-able from seismo-tectonic
considerations.
Site Elevation :
Page 16
Chapter 2
(v) The ground elevation at plant site varies from RL + 215 m to RL + 218 m. The
detailed analysis / studies have been carried out by National Institute of Hydrology,
Roorkee to arrive at the safe grade elevation for proposed HAPP due to flood. The
maximum flood elevation level due to severe most anywhere within the plant site as
derived through model simulation is 218.1m and has been considered as base flood
elevation and flood submersion line. A free board of 1.0 m has been assumed and
the safe grade elevation has been worked out to be 219.1 m. The safe grade
elevation of 219.1 m is recommended for proposed HAPP site. The detailed report
on Estimation of Design Basis Flood and Safe Grade Elevation for Nuclear Power
Project at Gorakhpur, Haryana as studied by National Institute of Hydrology,
Roorkee, is enclosed as Annexure II.
Power Evacuation :
(vi) Power evacuation in principle is feasible for 2800 MWe power from site. The
Power generated at HAPP will be evacuated through 400 kv transmission system.
The number of transmission outlets and their destination will be finalized taking into
account share of beneficial state in due course after a detailed power system
studies are carried out by PGCIL and approved by the concern authorities.
Population Distribution :
(vii) As per the estimates based on census data 2001, the average population density
within 10 km around the site as estimated for 2011 is about 264 persons / sq .km as
compared to the population density of Haryana State of 478 per km2.
Site Approachability :
(viii) The nearest National Highway is NH-10 at 6 km distance from the site. The nearest
railway station Uklana Mandi (23 km) north-east of the project site on Northern railway
Jalandhar Doab extension.
(ix) The Over Dimensional Consignment (ODC) of APP equipments of HAPP will be
transported by road. Separate studies will be required to be carried out for
improvements of roads for transport of normal consignment of APP units at HAPP.
Site Land-use :
(x) The proposed site for the project is agricultural land whereas the township is almost
barren with no ecologically sensitive areas like National Parks or wild life sanctuary
exists up to 10km from the site.
No industries handling toxic chemicals or
explosives are reported to exist within 10 km. There are no railways sidings or road
transport depots within 10 km. There are no civil or military airports within 50 km
around the site (the nearest Airports to the plant site is at Hisar about 33 km from
the site, small air port - not used for commercial flights). In general, the industrial
activities in the area are practically nil and as such, impact on environment arising
out of human utilization is negligible .
Page 17
Chapter 2
2.5
PROJECT LOCATION
The project site is located in Gorakhpur Village in Bhuna Block of Tehsil, Sub-division
and District Fatehabad of Haryana State. The proposed site is located at geographical
co-ordinates of longitude 750 37 56 E and latitude 290 26 30 N. and situated about
215m -218 m above mean sea level. The site is about 28 km in SE direction of
Fatehabad town which is the district head-quarter of Fatehabad district. The site is
located about 6.0 km from NH10, which connects Hisar to Fatehabad. The site is
connected to NH10 by the Kharakheri-Gorakhpur road.
The nearest railway station is Uklana Mandi (23 km) north-east of the project site on
Northern railway Jalandhar Doab extension. Rail head Adampur at a distance of 32 km
south-western of the site on Northern railway Rewari-Bhatinda section (Hisar-Sirsa
Broad-Gauge section). The road from Adampur station to the site is 22m wide good
road. The North Railway track, New Delhi Firojpur and Jaipur to Amritsar passes
through Rail Station at Hisar, situated about 33 km on the SSE of the project site. The
Narwana or Jakhal Rail Junction is located on the Delhi-Bhatinda sections of the
Northern Railway, towards NE of the project site at about 33km from the project site. The
above Railway Stations caters to the commuter needs and transportation of goods in the
region.
The nearest Airports to the plant site are at Hisar (a small air port, presently used for
Helicopter training purpose) located at a distance of about 40 km from the plant site and
Indira Gandhi International Airport, Delhi is about 208 km from project site. The
Bhakhara Canal (Fatehabad Branch) flows from east to west towards north close to the
site. There is no major industry within the study area. The nearest coal fields are at
Patha Khera in MP, at a distance of about 1185 km from the site via Adampur-HisarNew Delhi-Itarsi-Amla. The nearest distance of site from the international border is about
180km. The Index map showing the location of the plant site is shown in Figure 2.1.
There are no installation for handling, storing or transporting inflammable/toxic material
within a distance of 10km. There is no major railway siding or road transport depot within
10 km of the site. There is no place of historical importance within 10 km from the
proposed site.
Page 18
Chapter 2
Proposed Site
NH
NH
Other Roads
Canals
Figure 2.1: Proposed Project Site at Village Gorakhpur, District Fatehabad, Haryana
Page 19
Chapter 2
2.6
LAND REQUIREMENT
2.6.1
Land Area
The land requirement for the proposed project is set to about 1318 acres (533.5
hectares) and that required for housing colonies of plant personnel and CISF personnel
is about 185.42 acres (75.04 hectares). The land for the power plant (534 ha) site
comprises 1273.2 acres or 515.24 ha of land under double crop agricultural category.
The remaining 32 ha of land is not cultivable (which includes 6.0 ha of low lying area,
which will be suitably used). The land at the township comprises mostly barren land.
The total land required 1503.5 acres (608.48 ha) for the project is private land (Table
2.1a).
Table 2.1a: Break-up of Land in different Villages to be Acquired
SN.
1
2
3
Village
Gorakhpur
Kajhalheri
Bodapal
Total
Private
0
0
185.42
185.42
Township (Acres)
Government
0
0
0
0
Total
0
0
185.42
185.42
The village wise actual land requirement for the project, classification of land and
Rehabilitation and Resettlement (R&R) issues are given in Table 2.1b.
Table 2.1b: Actual Land Requirement, Classification of Land and R&R Issues
Nonagricultural
land
Acres
Ha.
Acres Ha.
1 Gorakhpur 1270.49 514.16 43.19 17.48
2 Kajhalheri 2.68
1.08
1.79 0.72
3 Bodapal
70.23
28.42 115.19 46.61
Total
1343.4 543.66 160.17 64.81
SN Name of
Village
2.6.2
Agricultural
Land
Total Land
Affected
People
(Khatedar)
Acres
Ha.
Numbers
1313.68 531.64
844
4.46
1.81
10
185.42 75.04
125
1503.56 608.48
979
R&R Issues
Land
to
be
acquired through
Haryana
Government taking
in to account the
R&R issues of
Haryana
R&R
policy 2010.
Resettlement and Rehabilitation of PAPs for the Land under Acquisition Process
For the proposed project the Project Affected Persons (PAPs) includes only land
Oustees and no displaced population is involved. The total PAPs involved in the project
is 979. The village-wise breakup of land and Project Affected People (PAPs) of the land
under process of acquisition for the proposed plant is given in Table 2.1b.
Page 20
Chapter 2
2.6.3
Land Acquisition
2.7
Reactor Building (RB) and Reactor Auxiliary Building (RAB) house the main reactor
and associated process systems,
Safety related Buildings other than Nuclear Building consisting of Control Building
(CB), Station Auxiliary Building (SABs), Ventilation Stack with Monitoring Room and
Station Auxiliary Buildings (SABs), D2O Upgrading Plant Building, Waste
Management Facility and Exhaust Ventilation, Induced Draught Cooling Towers,
Safety Related Pump House (SRPH), Fire Water Pump House, Underground
Tunnels and Trenches, Diesel Oil Storage Area (DOSA), Emergency Makeup Water
Pond, Covered Passage, etc as per the design features of the plant.
Power evacuation in principle is feasible for 2800 MWe power from site. The Power
generated at HAPP will be evacuated through 400 kv transmission system. The number
of transmission outlets and their destination will be finalized taking into account share of
beneficial state in due course after a detailed power system studies are carried out by
PGCIL and approved by the concern authorities.
A residential colony has been envisaged for the proposed project for accommodating
1700 employees. The total land area required for the same is 186 acres. A sewage
treatment plant of capacity 1.0 MLD will be installed to treat the sewage water
emanating from the township. The proposed township and the proposed power plant is
depicted in 10 km locator map of the study area in No. MEC/11/S2/Q6SY/01.
2.8
Page 21
Chapter 2
Table 2.2: Time Schedule for the First Two Units of the Project
SN
1
2
3
2.9
Name of Milestone
Units 2X700
Land Acquisition and Statuary Clearances
Start of Construction Activities
Completion of Construction & start of operation
Unit 1
Unit 2
MANPOWER PLANNING
During construction stage maximum of 8000 persons (when construction of stage-I will be
nearing completion and construction of stage-II will be started) will be temporarily deployed.
Whereas during operation and maintenance stage the manpower deployed will be as
follows:
: 760
: 1620
: 1700
The manpower includes technical and general administration needs. The estimate
covers the top management, middle and junior level executives and other supporting
staff. The estimate, however, does not cover the personnel for township, medical
facilities, etc.
2.10
Page 22
Chapter 2
PROJECT DETAILS
Page 23
Chapter 2
calculated releases shall be within specified release limits. This requirement is met
by ensuring that plant conditions associated with high radiological consequences
have low likelihood of occurrence, and plant condition with a high likelihood of
occurrence have only small or no radiological consequences.
3. Incorporate emergency preparedness measures to deal with situations arising out of
highly unlikely Beyond Design Basis Accidents.
4. To meet nuclear security requirements as specified in AERB manual on security
Principles and Guidelines
The safety goal of protection of public from accidental release of radioactivity is achieved
by adherence to the following well-established principles and guidelines:
1. Application of defense-in-depth approach, incorporating several echelons of defense
viz.
Sound design, construction and operation to prevent failures and deviation from
normal operation.
To detect and intercept incipient failures and deviation from normal operation
conditions, in order to prevent these from escalating into accidents.
To limit the consequences of accident conditions.
In addition to the above, for more severe events, protection of the public by
making use of ultimate safety capability of the plant, and appropriate emergency
preparedness plan.
2. Application of defense-in-depth concept to containment of radioactive material, by a
series of physical barriers, each backing the others.
3. Provision of more than one means / systems for performance of each of the three
safety functions viz. shutdown of reactor, core cooling, and containment of
radioactivity.
4. Provision of redundancy in systems important to safety having mitigation function,
including safety systems, such that at least minimum safety function can be
performed even in the event of failure of a single active component in the system.
5. Specifying unavailability targets for safety systems.
6. Provision of physical and functional separation, and independence to the extent
practicable, among/between following systems including their services (including
cabling etc.) to prevent common cause failures:
i) Between process systems and related safety systems.
ii) Among systems performing same safety function.
iii) Among redundant components within a system.
7. Consideration given at all stages of design for logics and instrumentation to fail in the
safe direction.
8. Provision of periodic testability of active components in systems important to safety
having mitigation function, preferably on-power.
9. Provision of periodic in-service inspection of components important to safety.
Safety Analysis
To demonstrate that the safety objective of protection of the public from accidental
2012 MECON Limited. All rights reserved
Page 24
Chapter 2
Page 25
Chapter 2
Fuel Sheath:
Fuel Sheath also called fuel cladding, made of Zircaloy-2, encapsulates the fuel pellets.
This forms the second barrier and is designed to withstand stresses resulting from UO2
expansion, fission gas pressure, external hydraulic pressure and mechanical loads
imposed by fuel handling.
Primary Heat Transport System:
The fuel bundles and coolant are contained in Primary Heat Transport (PHT) system.
This is a closed system and forms the third barrier for fission product release.
Containment:
The fourth barrier is the containment building which houses the reactor and associated
nuclear systems. The containment is a leak tight pre-stressed concrete structure with
quick isolation feature. The containment structures are designed to withstand maximum
pressure and temperature generated by postulated accidents and maintains acceptably
low leak rates consistent with specified dose limits following the postulated accident
conditions. Containment system performs its functions in association with related
engineered safety features (ESFs).
Exclusion zone:
The exclusion zone of 1.0 km is provided around the reactor building where no
habitation is allower. This measure gives as added safety. Public domain starts from
exclusion zone and dose limit to public is defined at exclusion zone boundary
2.11.3 Special Safety Requirements
Radiation zoning:
The entire operating island is divided into 3 distinct zones based on the contamination
potential. These zones have been designated as Zone-1, Zone-2 and Zone-3 in the
ascending order of contamination potential
The Zone system ensure radiological safety to occupational worker.
2.11.4 Safety Classification
To ensure adequate safety to the public and plant site personnel, the plant design meets
following general safety requirements.
1. The capability for safe shutdown of the reactor and maintaining it in the safe shut
down condition during and after all operational states and postulated accident
conditions.
2. The capability to remove residual heat from the core after reactor shut down, and
during and after all operational states and postulated accident conditions and
maintain a cool-able geometry.
Page 26
Chapter 2
3. The capability to reduce the potential for the release of radioactive materials and
ensure that releases are within the prescribed limits during and after all operational
states and, postulated accident conditions.
4. To meet these requirements, systems, components and structures have to perform
certain safety functions. These safety functions include those necessary to prevent
accident conditions as well as those necessary to mitigate the consequence of
accident.
5. The relative importance of the safety function determines the safety class of the
systems, components and structures performing the safety function.
Based on the above methodology, the following four different safety classes (Class 1,2,3
& 4) are generally considered appropriate in view of the design codes and standards in
vogue.
Safety Class 1 The systems, Structures and Components (SSCs) required to perform
the safety functions necessary to prevent the release of a substantial fraction of core
fission product inventory to the containment / environment are classified as safety class
1.
Safety Class 2 The SSCs that perform the safety function necessary to mitigate the
consequences of an accident which would otherwise lead to release of substantial
fraction of the core fission product inventory or activation product inventory into the
environment are classified as safety class 2. The consequences of failure of these safety
class 2 safety functions need only be considered after an initial failure of another safety
function. Safety class 2 also includes those safety functions necessary to prevent
anticipated operational occurrences from leading to accident conditions; and those
safety functions whose failure under certain plant conditions may result in severe
consequences, e.g., failure of decay heat removal system.
Safety Class 3 SSCs required to perform a support role to safety functions in safety
classes 1, 2 and 3 are classified as safety class 3. They include :
a) Those safety functions necessary to prevent radiation exposure to the public or site
personnel from exceeding the relevant acceptable limits from sources outside the
reactor coolant system.
b) Those safety functions associated with reactivity control on a slower time-scale than
the reactivity control functions in safety classes 1 and 2.
c) Those safety functions associated with decay heat removal from spent fuel stored
outside the reactor coolant system and with maintaining sub-criticality of fuel stored
outside the reactor coolant system.
Safety Class 4 The SSC which incorporate safety functions that do not fall within safety
classes 1, 2 or 3. Not Important to Nuclear Safety (NINS) Class. This class includes all
2012 MECON Limited. All rights reserved
Page 27
Chapter 2
other systems which are not associated with any of the safety functions listed above and
designed as per industrial standards.
Seismic Classification to meet the requirement given in the previous section, a three tier
(or level) system has been adopted for the seismic classification of systems,
components, instruments and structures, i.e. (i) Seismic category-1 (Safe Shut down
Earthquake (SSE)), (ii) Seismic category-2 (Operating Basis Earthquake (OBE))
and (iii) Seismic category-3 (General (Codal))
Seismic Category 1 Structures : All systems, components, instruments and structures
required for safe shut down of the reactor shall be designed for the maximum seismic
ground motion potential site (i.e. SSE) obtained through appropriate seismic evaluations
based on regional and local geology, seismology and soil characteristics. The equipment
and systems that are required to be qualified for SSE are classified as seismic category
1. Seismic Category 1 structure shall be qualified as SSE and OBE.
Seismic Category 2 Structures : All systems, components, instruments and structures
which are to remain functional for continued operation of the plant without undue risk fall
under OBE category and the design basis shall be a lower level seismic ground motion
than SSE which may reasonably be expected during the plant life. A seismic event,
exceeding OBE level, would require a shutdown of the plant and carrying out a detailed
inspection of the entire plant. The equipment and systems that are required to be
qualified for OBE are classified as seismic category 2.
Seismic Category 3 Structures : This category incorporates those systems, structures,
instruments and components, the failure of which would not cause undue radiological
risk and includes all systems, components, instruments and structures which are not
included in SSE or OBE category. The seismic design basis shall be that prescribed by
the relevant Indian standards (IS-1893, Year 2002). The equipment and systems those
are required to be qualified for CODAL requirements are classified as seismic category
3.
2.11.5 General Design Criterion
Nuclear building
Nuclear buildings consisting of RB (Figure 2.2a & 2.2b) and
and associated process systems. RB is provided with
containments. Primary containment is made of pre-stressed
containment is reinforced concrete. RAB is a framed RCC
category 1 structure.
Page 28
Chapter 2
for both units. In addition, the Control Building acts as a main entrance to the station
complex and is located appropriately. This is a safety related structure and has been
classified as Category 1 (SSE) structure from seismic considerations.
(b) Station Auxiliary Building (SAB)
Separate buildings called station auxiliary buildings are provided to house emergency
power systems. Each unit has two station auxiliary buildings. Station Auxiliary Building
1A and 2A are located on either side of control building, while 1B and 2B are located
abutting the nuclear buildings 1 & 2 respectively.
These are safety related structures and are classified as Category-1 (SSE) structures
from seismic considerations. The buildings are three stories structure. Two D.G. sets are
located in each SAB, making the number of DG sets available for each unit four. The
internal layout of all the four buildings is identical except for some minor variations.
The day oil tanks with proper fencing are located outside the SABs in a fenced area.
CO2 fire fighting cylinder room is located in between the two day oil tanks.
(c) Ventilation Stack With Monitoring Room
The ventilation stack is common for both the units. It is located next to Waste
management plant building. The Stack is 100.0 m high above ground level and has an
internal diameter of 3.0 m at the top. The ventilation stack is of RCC construction. The
structure will be suitably founded and is unlined. External outside diameter at top is
3.440 m, with a shell thickness of 220 mm. The outside diameter of concrete shell
increases uniformly from 3.440 m at top to 9.00 m at top of foundation level (shell
thickness 500 mm).
(d) D2O Upgrading Plant Building
The building accommodates various equipments required for purifying the downgraded
Heavy Water collected from various sources during the operating of power stations. The
building is located to the west of Nuclear Building-4 abutting the covered passage. The
upgrading plant may be generally divided into four major areas D2O distillation towers,
D2O upgrading plant, D2O clean-up and evaporation area and downgraded D2O storage
area.
(e) Waste Management Facility and Exhaust Ventilation Building
This building is a two storied RCC framed structure with a basement and is designed as
seismic category 1. The building is located to the west of nuclear buildings abutting the
covered passage.
Proper passages are provided within the building, wherever zone change occurs. LESS
facility is located at the basement of the building and the decontamination facility is
provided just above LESS at EL 100000, for ease of drainage. The decontamination and
resin fixation areas, being in zone-3, are provided with shielding walls of sufficient
thickness. Evaporator system is provided for the disposal of Tritiated waste through air
route, instead of liquid route. The ventilation discharge from plant buildings is routed to
Page 29
Chapter 2
the exhaust ventilation system, at first floor of the building. The final gaseous exhaust is
then taken through the ventilation duct and led to stack.
(f) Induced Draught Cooling Towers
Two Induced Draught Cooling Towers (IDCT) per unit are provided. The main function of
IDCT is to remove heat from the active process water system. Active process water is
cooled in plate type heat exchanger. The cooling of hot water (from outlet of plate of
plate type heat exchangers) is achieved by mechanical induced draught created by fans
mounted on top of the Towers. This structure is classified as safety class 3 & seismic
category 1.
(g) Safety Related Pump House (SRPH)
The Safety Related Pump House (SRPH) is a R.C. framed building catering for both
units of plant. The Building is designed for seismic category 1.
(h) Fire Water Pump House
Firewater pump house is a RCC framed structures for pumps for firewater. FWPH is
located close to SRPH. The building is designed for seismic category 1.
(i) Underground Tunnels And Trenches
There are many reinforced concrete tunnels and trenches carrying a number of safety
related service pipelines and cables. The seismic category is 1 and safety class is 3. The
tunnels are buried under soil, with overburden, while the trenches have no earth cover
on top. The main safety related tunnel in the plant area, is the tunnel carrying APW and
SW lines from reactor auxiliary system to safety related pump house and IDCTs. Local
tunnels are also provided, wherever the trenches are crossing the roads.
Page 30
Chapter 2
Page 31
Chapter 2
Page 32
Chapter 2
Page 33
Chapter 2
2.12
Page 34
Chapter 2
CRs can be moved together depending on the error signal). They are capable of rapid
power reduction by action of controlled gravity fall and to compensate the reactivity
increase following power reduction.
Shutdown Systems
When certain plant parameters exceed operating limits and conditions, the shutdown
systems trip the reactor by fast insertion of a large amount of negative reactivity into the
core. Two independent and fast acting systems, SDS #1 and SDS # \2 capable of
independently shutting down the reactor are provided. The Reactor Protective System
(RPS) refers to equipment provided to generate actuation signals and devices to trip the
reactor. There are two reactor protection systems, RPS # 1 and RPS # 2. Each system
is designed to sense demand for reactor trip and give actuation command to respective
shutdown systems. The shutdown system instrumentation of SDS #1 and #2 provide
means to actuate the system. Instrumentation is provided for health and performance
monitoring. Each system is designed to perform the intended function assuming single
failure criteria. The design objectives of the shutdown systems are
1. Upon trip, to provide an initial negative reactivity insertion rate high enough to
countered all credible reactivity excursions.
2. Upon full insertion, to provide enough negative reactivity depth to ensure that the
reactor remains sub critical following shutdown.
SDS #1
SDS #1 consists of 28 vertical Shut-off Rods (SRs) consisting of cadmium absorber
sandwiched between stainless steel tubes, which fall into the reactor under gravity
upon its actuation.
SDS #2
SDS #2 consists of 6 horizontal tubes through which liquid poison in the form of
gadolinium nitrate is injected directly into the moderator. The schematic of SDS #2 is
given in Fig. 2.3.
Page 35
Chapter 2
Page 36
Chapter 2
Page 37
Chapter 2
Figure 2.5: Simplified Schematic Flow Diagram for 700 MWe PHWR
Page 38
Chapter 2
Page 39
Chapter 2
extensions of End shields on either side. The stepped down shells, called `Small Shells,
are joined to the Main Shell by means of flexible Annual Plates, thereby forming vertical
annular sections, which deflect to allow for the differential thermal expansion of stainless
steel shell with respect to the Calandria tubes and the concrete vault walls. The location
of the annular plates is selected to give an optimum reduction in inventory of expensive
heavy water in the low flux regions of the vessel and to provide adequate space for
welding of Calandria to the End shields at site. Sectional view of Calandria is given in
Fig. 2.7.
There are 392 coolant tubes and 392 Calandria tubes arranged in a square lattice of 286
mm pitch. The Zircaloy-4 Calandria tubes are rolled into the end shields. Four annular
spacers (garter springs) have been provided in each coolant channel to maintain
appropriate gap between the Calandria tube and coolant tube, carrying fuel and coolant.
The Calandria shell has 85 nozzles on top and another 13 on west side for housing
mechanisms for reactor control and monitoring. Corresponding to each reactivity
mechanism nozzle, housing is provided at bottom of the vessel to locate and support
different devices.
Four numbers of 500 mm NB over pressure relief lines are also provided on the top of
Calandria. These lines terminate in the pump room and are provided with rupture-discs
at the ends. The rupture discs are of reverse buckling type having a set pressure of 1.4
kg/cm2.
12 numbers of 150 mm NB moderator inlet connections (6 nos. on either side) are
welded to the main shell near its horizontal centerline plane. At each moderator inlet
location, an inlet diffuser of gradually increasing rectangular cross-section is provided.
These diffusers are oriented in such a manner that they discharge the incoming heavy
water all along the curved surface towards the top of the shell with low velocity and
without impinging directly on any Calandria tube. The lower end of the diffuser is welded
to the stainless steel nozzles already welded to the Calandria main shell. Four
moderator outlet nozzles of 250 mm NB are provided at the bottom of the main shell at
locations slightly away from the vertical axial plane.
Page 40
Chapter 2
Page 41
Chapter 2
Page 42
Chapter 2
assembly. While not in motion, the rod is held in position by the self-locking feature of
drive mechanism provided by proper design of worm gear unit. Adjuster rods remain
within the reactor core during normal operation. For regulating purposes, the adjuster
rods are driven out and driven into the core by Reactor Regulating System (RRS), as
required.
Control Rod Mechanism
The system consists of four control rods utilising cadmium absorber elements. At each of
the four locations, the system consists of control rod assembly, guide tube assembly,
guide tube locator assembly, stand-pipe-thimble assembly, shield plug cum push tube
assembly, drive mechanism and the supporting, sealing and shielding arrangements.
The control rod consists of a vertical tubular cadmium absorber sandwiched between
stainless steel tubes, a rope attachment at its top and an orifice at bottom. The upper
end of SS wire rope holding the CR is attached to and wound on a sheave inside the
drive mechanism. The rod is held in parked position with help of self locking feature
provided by design in worm gear unit of drive mechanism. An electric motor, through
gear drive and electromagnetic clutch, drives the rod up or down inside a guide tube
assembly. On de-energizing the electromagnetic clutch, the rod falls under gravity into
the guide tube assembly inside reactor core.
For the purposes of regulating functions, the control rods are driven into and out of the
core by Reactor Regulating System (RRS), as required. During a reactor set back, one
or both banks of control rods are driven partially or fully into the reactor core by RRS.
During reactor trip both banks of control rods are also dropped into the core along with
shut-off rods of shutdown system no. 1 (SDS #1).
In Core Flux Units
Self-Powered Neutron Detectors (SPNDs) are used for in-core flux measurement. There
are SPNDs belonging to Reactor Regulating System (RRS), known as Zone Control
Detectors (ZCDs), SPNDs belonging to Reactor Protection System 1 & 2 (RPS), know
as Regional Over Power Protection System ROPPS) Detectors and SPNDs belonging to
Flux Mapping System (FMS), known as Flux Mapping Detectors. In addition to these
SPNDs, there are Traveling In-Core Probes (TIPs) and in-core Start Up Counters
(SUCs). All these are housed in tubular in-core Carrier Tuber Assemblies (CTAs). These
Carrier Tube Assemblies along with related components are known as Vertical and
Horizontal Flux Units (VFU, HFU) depending on whether they are oriented vertically or
horizontally in the core.
Vertical Flux Units
There are 26 Vertical flux units located vertically inside the Calandria. The VFUs houses:
ZCDs of RRS
ROPPS Detectors of RPS # 1,
Flux Mapping Detectors,
Vertical Travelling In-core Probes (TIPs) and
In-core Start up counters (SUCs).
Page 43
Chapter 2
Page 44
Chapter 2
Page 45
Chapter 2
Page 46
Chapter 2
8. Leakage collection system to collect, contain and transfer the collected heavy water
and to provide venting and draining facility to the equipment.
9. Service system to facilitate filling and draining of steam generator primary coolant
pump loop and header level control.
10. Sampling system for monitoring the system chemistry.
11. Passive Decay Heat removal system (PDHRS) for decay heat removal during station
blackout condition.
Passive Decay Heat Removal System (PDHRS)
Primary function of the Passive Decay Heat Removal System (PDHRS) is to ensure
continued availability and recirculation of the inventory on the secondary side of the
Steam Generators in the event of class IV failure simultaneous with non-availability of
Auxiliary Boiler Feed Pumps (ABFPs) or Station blackout and in the process ensure
continued removal of decay heat from the core.
2.12.7 Moderator System
The purpose of heavy water moderator is to maintain criticality in the reactor core by
slowing down the high-energy neutrons to a lower energy level where their probability for
fission capture is higher.
Heavy water used as moderator inside the Calandria gets heated up due to neutron
moderation and capture, attenuation of gamma radiation as well as due to transfer of
heat from other reactor components in contact. The primary function of moderator
circulation system is to maintain equilibrium moderator temperature in the core, by
providing sufficient cooling to remove about 123 MW to heat generated in moderator at
full power. 6 x 20% canned motor pumps are provided for moderator circulation.
The system supplies heavy water to adjuster rod mechanisms for cooling of the adjuster
rods. Reactivity control by chemical shimming is done using boron / gadolinium nitrate
as liquid poison in moderator. The system supplies heavy water, as power water, to
Moderator Liquid Poison Addition System (MLPAS).
Presence of ionic impurities in moderator increases transport and buildup of radioactivity
in the circuit as well as increases rate of radio-lytic decomposition of heavy water within
Calandria. In view of this, a portion of the moderator flow is continuously circulated
through ion exchange columns. Separate ion exchange column are provided for removal
of boron or gadolinium nitrate poison from moderator, which are added through MLPAS
or Shut Down System #2.
Heavy water in the Calandria also functions as a heat sink in the unlikely event of Loss
of Coolant Accident (LOCA) coincident with the failure of Emergency Core Cooling
System (ECCS).
Moderator level in Calandria is maintained at 100% full tank (FT) level at full power.
Moderator level in Calandria varies from cold shutdown state to full power, due to
variation in temperature. The extent of variation could be 95.7% FT level under cold
2012 MECON Limited. All rights reserved
Page 47
Chapter 2
Page 48
Chapter 2
The main cover gas circulation system consists of Calandria, four over-pressure relief
pipes, standpipes of Reactivity Devices, helium blowers, Recombination Units and
necessary valves and piping.
2.12.8 End Shield and Calandria Vault Cooling Systems
The End Shield cooling system serves to remove nuclear heat generated in the End
Shield and heat transferred from the primary coolant across insulating gaps between
end fittings and lattice tubes and across support bearings of coolant channels.
The criteria for design are :
1. To limit Calandria side tube sheet temperature to levels acceptable from the point of
view of radial expansion.
2. To obtain a fairly uniform temperature distribution in the end shields structure and
minimise thermal stresses.
3. To maintain compatible water chemistry with the end shield components.
Water in the end shields also provides neutron shielding.
The minimum heat to be removed from each end shield is about 2450 kW and the heat
transferred from primary system is about 1130 kW. Water chemistry compatible with the
end shield structure is maintained and a purification loop is incorporated for removal of
impurities from the circuit.
The Calandria vault cooling system serves to remove the heat generated in the
Calandria vault water. Calandria vessel is submerged inside a pool of water in the
Calandria vault. The function of water is two-fold, firstly to serve as thermal shield
around the Calandria and secondly to cool the vault walls which serve as biological
shield. The radiation heat generated in the light water and the vault walls as well as the
heat from the Calandria shell is transferred to the Calandria vault water. The vault water
is recirculated through the Calandria vault cooling system by pumps and is cooled by
heat exchangers. The average temperature of vault water is about 52C and the vault
concrete temperature is about 60C. The acceptable maximum concrete temperature for
continuous operation is 65C. The heat to be removed from the vault water is about
4505 kW and system is designed for 5000 kW.
The End Shield and Calandria vault cooling systems reject the heat to the Active
Process Water System. The system is classified as safety class 3.
2.12.9 CO2 Annulus Gas System
CO2 is circulated through the annuli between coolant tubes and Calandria tubes.
Monitoring of moisture content of CO2 is done to assess the coolant tube integrity. High
purity CO2 is circulated through all the annuli continuously at a rate of 30 Nm3/hr. The
maximum permissible dew point of makeup CO2 is (-) 20C. Provision is made for on-line
dew point monitoring. Besides pressure rise monitoring in the circuit is also annunciated.
Annunciation is given if the dew point of circulating CO2 rises to (-) 5C, which indicates
2012 MECON Limited. All rights reserved
Page 49
Chapter 2
leak from one or more of the coolant tubes. Manual shutdown of the reactor is initiated.
The annulus gas tubes from individual channels are grouped into several strings and
these are grouped in sub groups and a process of elimination identifies the sub group
containing the leaky tube, isolating one group at a time. Design pressure of annulus gas
system is 1.75 kg / cm2.
2.12.10 Secondary Systems
The main steam supply system has been designed with the following objectives.
1. To act as a heat sink for the reactor coolant.
2. To transport steam from the steam generator outlet nozzles to the HP turbine reliably
and economically for power generation.
3. To supply steam to auxiliaries forming part of the turbine cycle and to other
miscellaneous needs.
4. To maintain the integrity of the pressure boundary of fluid system under normal
operation and anticipated operational occurrences.
5. To minimise poison outages of the reactor due to turbine faults, certain grid faults
and certain primary side conditions.
2.12.11 Fuel Handling and Control System
Two Fuelling Machines (FM) operating in conjunction, one at each end of Reactor, carry
out on-power refueling. Fresh fuel bundles are inserted at one end while the other
machine at the other end receives the spent fuel bundles. Bi-directional refueling in
adjacent channels is adopted (in the direction of flow) to smoothen axial flux pattern.
Spent Fuel Bundles received in the Fuelling Machine are transferred to the Fuel Transfer
Equipment i.e. mobile Transfer Machine and subsequently transferred from mobile
Transfer Machine to the Tray loading Bay (TLB) located in the Spent Fuel Building. The
spent fuel bundles are stored under water in trays in storage Bay for sufficient period
before they are transported to a reprocessing plant.
Normally eight bundles refueling is adopted to optimize utilizations of Fuel and operation
of Fuelling Machines. In an equilibrium core it would add reactivity of about 0.3 mK on an
average, for each channel in a refueling operation which normally takes about 4 hours.
Total number of channels to be refueled in a day is determined from the point of view of
addition of reactivity required for sustained operation.
Spent Fuel Bundles, while in FM Head, are cooled by re-circulating heavy water
whereas in mobile Transfer Machine cooling is done by re-circulating light water. From
the Fuelling Machine, only one pair of bundles at a time is transferred to light water
environment in the mobile Transfer Machine. This dry transfer operation normally lasts
about 4 minutes. During abnormal condition, if the dry transfer operation is not
completed within 5.72 minutes, cooling by water spray / filling is provided. After transfer
to light water environment, submerging the bundles in light water ensures cooling.
Thereafter the bundles are transferred to Tray loading bay and then to Storage Bay by
underwater operations only. Storage Bay water is cooled by re-circulation through heat
exchangers.
2012 MECON Limited. All rights reserved
Page 50
Chapter 2
The Spent Fuel Storage Bay and Tray Loading Bay are lined with stainless steel to
provide a primary leak tight barrier. The liner has provision to collect any leakage of bay
water. Spent fuel bundles are loaded in the trays at tray loading bay.
The tray loading bay also incorporates inspection facility for detection of ruptured spent
fuel bundles. The storage bay has capacity to store spent fuel discharged for about 10
reactor years in addition to provision for unloading of one core in case of emergency.
Provision also exists to ship spent fuel to either reprocessing plant or any other
consolidated interim storage facility.
A large number and variety of devices such as Pumps, Valves, Hydraulic Cylinders,
motors etc. are used in the Fuel Handling and Control System. The design of these
devices is based on following considerations :
1. Redundancy is provided to ensure cooling of Spent Fuel bundles after it is taken out
of the core.
2. Fail-safe devices and auto initiated back up actions are employed to the extent
feasible.
3. The maximum risk is limited to damage of only four pairs of bundles, which are also
always contained in a vessel.
The Fuel Handing Control System enables the control of Fuelling systems comprising
Fuelling machines, Fuel transfer, Vault and Service area doors and Roll-on shield. The
control system is computerized, which gives sequential commands to the two fuelling
machines to enable automatic refueling of reactor at any selected coolant channel. The
system also gives sequential commands to Fuel Transfer Tray Loading Bay. Both
Software and hardware interlocks are provided to ensure that the commands issued to
the system result in safe operation. The system provides for safe manual mode
operations during conditions when the control computer is not available. The
subsystems, which are not computer controlled, are designed to be operable only in
manual mode.
2.12.12 Instrumentation and Control (I&C)
The Instrumentation & Control (I&C) systems in 700 MWe include a variety of equipment
intended to perform display, monitoring, control, protection & safety functions. The
concepts presented form the basis for the system design and development. General
guidelines followed are :
1. Electrical transmission of signals is preferred to pneumatic, because of better
amenability to further processing in addition to inherent fast response etc.
2. Equipment free from ageing, wear and not needing routine and preventive
maintenance are preferred. Microprocessor-based systems, solid-state semiconductor devices are preferred over mechanical systems having moving parts. The
computerization of control algorithms and operator interface are provided wherever
required.
Page 51
Chapter 2
Page 52
Chapter 2
11. Instrument air, wherever required meets the availability requirements of I&C
systems, Independence and functional isolation is incorporated. Local instrument air
accumulators are provided wherever operation of valve is required even after
instrument air supply failure.
12. A high degree of automation is aimed at to eliminate human error affecting
availability / reliability. However, some systems, e.g. D2O leak detection, failed-fuel
detection etc. will need operator surveillance and action for remedial measures.
13. Simplicity in design, operator acceptance, obsolescence, current trend in technology
are given due consideration.
Main Control Centre
The control of power plant is based on the philosophy of a centralized control room
sufficiently instrumented to provide adequate information to the operator regarding the
status of the plant and to enable safe and efficient control of the plant. Main Control
Room (MCR) is located in the Control Building at 111 m floor. A common control room is
provided for two units. Fig. 2.9 indicates pictorial view of main control room panels for
700 MWe Plant.
VDU based soft controls are provided for all IB, IC & NINS systems. Conventional
controls, indication and displays are provided for safety critical applications and for some
safety related systems hard-wired backup is also provided. These controls, indications
and displays are provided on main control panels and operator consoles. Number of
large video screens is provided for displaying the plant information. The main control
room panels and operator consoles of each unit are arranged in Horse-shoe
arrangement. Arrangement of the systems on the main control room panels is done on
the basis of the functional requirements.
Window annunciations are provided on top portion of the panels. Window annunciations
call for immediate operator attention and are very important under all plant conditions.
With a view to present the desired information to the operator in an overall compact
fashion, a computer based operator information system is provided. Operator
Information Concoles (OIC) with VDU & Keyboard of various computerized systems are
provided in the MCR. OICs are designed for sitting operation. On these VDUs operator
can get information on various systems of the plant.
One computer room is provided for each unit. In this room, computers and peripherals of
computerized systems are located.
Only very essential controls and indications are provided on MCR panels. However, to
supplement these devices many other type of components / requirements are required.
These are mounted on auxiliary panels, which are located in Control Equipment Room
(CER). CER is located at the same floor are MCR. Physical separation of channel
equipment with total fire barriers is achieved by providing 3 separate rooms for each unit
for triplicated channels Power supply for illumination of control room of unit-3 is
independent of unit-4. Similarly, independent air-conditioning systems are provided for
2012 MECON Limited. All rights reserved
Page 53
Chapter 2
control rooms of both the units. In MCR, emergency fresh air ventilation system is
provided. During radioactivity release, air is made to pass through charcoal and HEPA
filters before being supplied to Control room.
Control and Instrumentation cables of redundant systems are segregated as per IEEE
384. Non-safety related cables are also segregated from the safety related cables as per
IEEE 384.
Fig. 2.9 : Pictorial view of main control room panels for 700 MWe Plant
Page 54
Chapter 2
Page 55
Chapter 2
Class I system
Class II system
Class III system
Class IV system
:
:
:
:
Class I power supply system (based on batteries) is used for the supply of control power
for circuit breakers and controls such as control of DG sets, turbo-generator, etc. The
DC supply system is normally supplied from Class III AC power system of the
emergency electric power supply system through AC-DC converter (ACVR). In case of
failure of AC power to ACVR, the batteries continue to supply to the loads without
interruption.
Class II power supply is derived from uninterruptible power supply system comprising of
rectifier, inverter and a dedicated battery bank. The battery bank is capable of feeding
inverter loads for a period of at least 30 minutes after the failure of AC supply to the
rectifier. Important loads on Class-II include FM supply pumps, emergency lights, ECCS
Valves.
Class III power supply is connected to emergency diesel generators which automatically
provide power supply in the event of class IV power supply failure. The system consists
of 4 numbers of diesel generator (DG) sets for each unit, each of 100% capacity. Loads
connected to the class III supply can tolerate short time interruptions (up to two minutes)
in power supply.
Major loads connected to class III power supply are primary feed pumps, power and
control UPS, moderator circulating pumps, ECCS pumps, air compressors, auxiliary
boiler feed pumps, shut down cooling pumps and process water pumps.
Class IV power supply is derived from 400 kV and 220 kV systems through GT & UT
combination and start-up transformers respectively. Further, Class IV power supply is
also derived from the turbo-generator through unit transformers. There are two numbers
of UTs and two numbers of SUTs per unit. Either two SUTs or two UTs are capable of
supplying the entire station load. Loads connected to this system can tolerate prolonged
power supply interruption.
Safety Related Electrical power supply system is divided into two independent,
redundant Divisions. One of the Divisions is normally supplied from the startup
transformers and the other Division is normally supplied from the unit transformers. The
capacity of each Division, their location and routing of the cables are such that common
mode failures are minimized. The electrical power supply systems catering to all safety
related loads are designed to meet the requirement of single failure criterion.
Redundant electrical power supply equipment are housed in separate rooms with walls
of appropriate fire rating. Cables to redundant loads are routed through independent
routes.
Page 56
Chapter 2
Adequate sealing has been provided at the reactor building penetrations to minimize
leakages. All cables are of fire retardant and low smoke type. Cables used in areas of
high radioactivity (like F/M vault) is designed to safety withstand the applicable radiation
levels.
The design and selection of equipment has taken into consideration steady state voltage
& frequency variations and transient voltage drops during switching operation.
The ambient conditions applicable for the station, fault conditions at the place of
installation are considered for selecting the equipment.
All safety related electrical equipment are qualified for the safe shut down earth quake
as well as OBE requirements.
Provision is made for testing of safety related electrical equipment during the operation
of the station. Unavailability of one DG set for a specified period due to maintenance has
been considered in providing redundancy.
2.12.14 Plant Auxiliaries
Cooling water systems
The various cooling water systems employed are as follows :
1.
2.
3.
4.
5.
6.
Page 57
Chapter 2
Page 58
Chapter 2
Under extreme emergencies (station black out etc.), firewater is available through diesel
driven pumps. Normally isolated `Hook up type arrangements for injecting water from
fire water system, Fire tender or some other suitable water source are provided for
injecting water into Passive Decay Heat Removal System (PDHRS), Auxiliary SG feed
water system, End Shield and Calandria vault cooling system, Emergency Core Cooling
System (ECCS) and Moderator circulation system. Fire Protection System is detailed
under Section 2.13.6.
Chilled Water System
A centralized chilled water plant caters to the following requirements :
1) Process load (D2O Recovery and upgrading plant) and local cooling load in Reactor
Building & Nuclear Building.
2) Air conditioning load in Nuclear Building, Turbine Building, Control Building, and
Station Auxiliary Building etc.
The system is designed with a bypass arrangement in order to match system
requirement under various operating conditions.
An expansion tank is provided to maintain system pressure and also to serve as a make
up for the system.
Ventilation System
Primary Containment Ventilation System
The Reactor Building (RB) is of double containment where the inner one is known as
Primary Containment (PC steel lined) and the outer one are Secondary Containment
(SC). The PC is further classified into two volumes namely high enthalpy areas and low
enthalpy areas. High enthalpy areas comprise of areas which contain high enthalpy
fluids and are potential source of heavy water (D2O) leakage. These areas are normally
not accessible. The SG room, Pump Room (PR) and Fuelling Machine (FM) vaults areas
fall under this category. Rest of the areas fall under the category of low enthalpy areas
and are normally accessible except moderator room, Fuel Transfer (FT) rooms, Delayed
Neutron Monitoring (DNM) and FM service areas (FMSA) during communication with FM
vault.
For the purpose of contamination control and ventilation requirements, separate high
enthalpy and low enthalpy areas are maintained as described above.
The PC ventilation system is designed fro the following requirements.
To supply cooled, filtered and dehumidified fresh air and exhaust stale air to meet
the fresh air requirement of O&M personnel during normal and Shutdown period.
Ensure flow of air from low active zones to high active zones thus preventing the
spread of activity inside RB.
Maintaining the PC under negative pressure with respect to SC and ambient to
prevent leakage of air from PC during normal operation.
Page 59
Chapter 2
The desired area temperatures inside PC are maintained by the APW fed air-cooling
units (ACUs) in high enthalpy areas and chilled water-cooled air handling units
(AHUs) in low enthalpy areas.
Ventilation flow has been decided in such a way as to meet the ventilation requirements,
while limiting heavy water vapor loss & tritium release (through exhaust) at a minimum.
Provision is made to monitor the activity release through stack. In order to ensure
negative pressure in PC with respect to SC and outside atmosphere, only exhaust fans
are provided in the ventilation system.
Provision is made to isolate moderator room and FM service areas from PC ventilation
system and connect them to Heavy Water Vapour Recovery (HWVR) system by
providing air operated dampers in supply and exhaust ventilation lines and also in
branch lines connecting these areas to dryer. The exhaust from FT room is passed
through a Combined HEPA and Charcoal filter to take care lodine release, if any. To
reduce the dust ingress into the PC, filers with minimum 90% efficiency down to 10
microns are provided at the intake. The exhaust to the stack is through pre filters
(designed for 99% efficiency down to 5 microns) and HEPA (designed for minimum
99.97% efficiency down to 0.3 microns) filters.
Secondary Containment Ventilation System
SC surrounds PC from raft to dome with a gap of about two meters. The objective of the
SC ventilation is to prevent the SC atmosphere from becoming stale and to provide fresh
air for occasional occupancy. SC ventilation system is designed on the following basis :
SC does not have any continuous occupancy as it does not house any equipment and
also there is no major heat load other than that from lighting. Consequently continuous
ventilation for SC is not required. However to prevent the atmosphere from becoming
stale, ventilation system with exhaust air flow is provided. Under normal operating
condition of the reactor, PC is negative with respect to SC and hence leakage flow can
take place from SC to PC and not vice versa. Hence activity will not spread from PC to
SC. Provision is made to isolate SC under RB isolation logic, with provision of two
isolation dampers on both supply and exhaust line.
Primary Containment Cooling System
The function of this system, provided in primary containment (PC) of Reactor Building
(RB), is to remove heat from equipment and piping under normal reactor condition and
to maintain desired area temperature in high enthalpy area such as pump room and
fuelling Machine vaults (FMVs) and low enthalpy areas like accessible areas, moderator
room, FM service areas (FMSAs) and Delayed Neutron Monitoring (DNM) rooms. Since
water spray system is provided for energy management during post accident condition,
PC cooling system is not performing any safety function during post accident condition.
PC air cooling system consists of air cooling units (ACU) for pump room & FM Vaults
and air handling units (AHU), located at various locations.
Page 60
Chapter 2
a. Low Enthalpy Areas (Moderator Room DNM and Other Accessible Areas) Cooling
System
Air handling units, are provided for this purpose. The system is designed to maintain the
area temperature 35C. Humidity in these areas is about 50 60%.
Air Handling Units (AHUs) are standard package units, each consisting of a cabinet,
which houses one or two cooling coils, fan, filters, inlet and outlet, grills. Room air is
drawn in, filtered, cooled and returned to the area. Chilled water at 8C at inlet is used as
the cooling water in the AHUs. Chilled water continues to flow to all AHUs. AHUs are
designed for air inlet temperature of 33C. Fan motors are on class IV electric power
supply. The units are provided with drain pan(s), directed to nearby floor drains.
b. High Enthalpy Areas (FM Vaults and Pump Room) Cooling System
FM vaults and Pump room are provided with air-cooling units (ACU) to maintain area
temperature around 48C and 45C respectively. Active process water (APW), supplied
at a design temperature of 35C at inlet is the cooling medium and it is continuously
flowing to all ACU during normal & hot shut down conditions. In the scheme of pressure
balance between various volumes, high enthalpy area atmosphere is maintained at
negative pressure with respect to rest of the area (About 15 mm wc) and hence a
continuous purge is maintained. Leak thightness and integrity of the boundaries is
maintained in order to minimize the purge. The purge copes with the in leakage of
compressed air and steam. A closed loop heavy water vapor recovery system is
provided to recover the heavy water vapor from the containment atmosphere.
Reactor Building Heavy Water Vapour Recovery System
The system is provided to recover heavy water vapor arising out of chronic leakages /
spills from primary heat transport, moderator and fuelling machine circuit in the Reactor
Building (RB) Primary Containment (PC) atmosphere. Recovery is made by adsorption
of the vapor on molecular sieves and then regeneration of the bed and condensing the
water. Condensate from the dryer equipment is collected by condensate collection
system.
Heavy water vapor recovery system maintains the fuelling machine vaults and pump
room (high enthalpy) areas under negative pressure with respect to low enthalpy
accessible areas thus preventing activity spread from these areas to accessible areas.
Heavy water vapor recovery system also helps in reducing the tritium activity levels in
pump room, fuelling machine vaults, fuelling machine service areas, moderator room,
delayed neutron monitoring room, fuel transfer room, fuelling machine valve station, etc.
High enthalpy area contains all high enthalpy heavy systems and includes pump room
(PR), fuelling machine vaults (FMVs) and fuelling machine service areas (FMSAs) when
connected with FMV. These areas are generally accessible only during shutdown period
of the reactor.
Page 61
Chapter 2
Low enthalpy areas like PHT equipment room, feed pump equipment room, moderator
room, delayed neutron monitoring room, fuel transfer rooms, north and south galleries,
staircase, FMSAs (when the area is not connected with FMV) are normally accessible
during reactor operation with a few exceptions. Some areas like moderator room,
delayed neutron (DN) monitoring rooms, fuel transfer (FT) rooms are not accessible
during normal operation.
Different areas in PC are connected to heavy water vapor recovery system, in which
heavy water vapors are recovered as downgraded heavy water condensate. Typically
each dryer consists of adsorption & regeneration circuits, ducting and condensate
collection system piping. Purge dryer is provided to maintain slight negative pressure in
FMV & Pump room with respect to accessible areas.
RAB Air Conditioning and Ventilation System
Air Conditioning (A/C) & Ventilation are provided for Reactor Auxiliary Building (RAB) of
HAPP-1 & 2. The system is designed with an objective of ensuring adequate supply of
fresh & filtered air for the operating personnel, remove heat load generated in the
operating areas due to equipment and / or human occupancy and maintaining air flow
from lower contaminated areas to higher contaminated areas to minimize spread of
contamination. RAB consists of the portion of Nuclear Building (NB).excluding Reactor
Building (RB). This building houses Spent Fuel Storage Bay (SFSB), equipment of
moderator and PHT purification systems, workshops & maintenance areas, change
rooms, Backup Control Room (BCR), Heavy water vapor recovery systems, supply unit
of RAB ventilation system including air washer, cable passage area, etc. Nuclear
building is divided into zone 3 or 2 or 1 based on contamination levels and potential for
activity release. Ventilation design for these buildings is based on activity considerations,
zoning and desired area temperature requirements. For the purpose of design, the
various areas may be categorized as follows :
1. Areas where occasional fission product activity release, particularly of I-131 is likely
spent fuel storage bay (SFSB) and Tray Loading Bay (TLB) areas, spent fuel flask
decontamination area.
2. Areas where high tritium release is likely PHT purification area, evaporation clean
up, dedeuteration facility etc.
3. Areas where occasional beta-gamma and tritium release are likely chemical
laboratories, mechanical maintenance shops, and decontamination areas.
4. Other areas where radiation levels are low.
(Exhaust from areas under category (1) requires to be filtered for iodine removal. The
number of air changes in all these areas is based both on activity considerations, heat
load and the local air coolers provided for the area).
Fresh air supply system caters to the fresh air requirements of the above areas and
Secondary Containment (SC) of Reactor Building (RB. Exhaust system is common for
RAB-1 and RAB-2, Waste Management Plant (WMP), Mechanical and FM workshops.
Page 62
Chapter 2
Page 63
Chapter 2
Page 64
Chapter 2
of the clutch, the rod falls into a guide tube inside the reactor core. The initial gravity fall
of the rod is assisted by a spring.
Shut Down System No. 2 (Liquid Poison Injection System)
Liquid Poison Injection System, as Shut Down System #2, employs direct injection of
liquid poison viz. Gadolinium nitrate solution in heavy water into moderator to shut down
the reactor. Gadolinium nitrate solution is stored in six poison tanks, each tank being
connected to a perforated injection tube. The injection tubes are horizontally oriented in
the Calandria. High-pressure helium is stored in a tank known as helium storage tank.
This is connected to the poison tanks through an array of six quick opening valves.
These valves are opened during an SDS # 2 trip and consequently the high-pressure
helium forces the gadolinium nitrate solution into the Calandria through the holes in the
injection tubes. The system is designed to introduce about 70 mK in about 2.5
seconds. However, the total negative reactivity introduced when the gadolinium nitrate
solution is completely dispersed in the moderator is about 300 mK.
2.13.2
Containment
Double containment philosophy has been followed. The containment system consists of
an inner (primary) containment enveloped by an outer (secondary) containment. The
Primary Containment is provided with Carbon Steel (CS) liner to reduce leak rate. The
annulus between the inner and outer containments is kept at a slightly negative pressure
with respect to the atmosphere so as to minimize ground level activity releases to the
environment during an accident condition.
The containment associated engineered safety features (ESFs) are specified to be
operable under post Loss of Coolant Accident (LOCA) condition. These ESFs are
qualified for Safe Shut down Earthquake (SSE) as well as LOCA environment.
i. Design Basis
ii. For Normal Operation
The purpose of containment building during normal operation is to:
Provide an envelope around the structure housing / supporting Calandria, end
shields, reactivity mechanisms, PHT and moderator systems, fuelling systems and
various associated systems.
Provide shielding, as also to permit access to equipment within the containment
building under reactor operating / shutdown conditions.
Provide shielding, as also to permit access to equipment within the containment
building under reactor operating / shutdown conditions.
To keep the release of radioactivity during normal operation within prescribed limits.
For Accident Conditions
Under accident conditions, the system must limit the activity release to environment such
that the exposure to an individual would remain within acceptable limits even at the
exclusion boundary. The stipulated dose limit is 0.5 Sv (50 rem) to thyroid of a child, and
0.1 Sv (10 rem) to whole body.
Page 65
Chapter 2
Containment Isolation :
Automatic isolation of containment is initiated in the event of Pressure rise in
volume V1 OR,
Activity in containment ventilation exhaust duct exceeding a pre-set limit.
Provision for remote manual isolation by hand switch is also kept.
Two isolation devices have been provided in each line communicating to the main PHT
system or containment atmosphere. These devices would either remain normally closed
or actuate automatically to provide leak tight barriers under an accident condition.
Design ensures that these barriers remain close or close during any failure of control
power or air supply to actuator. Preferably one of the isolation devices of these lines is
kept within the Primary Containment. For lines not communicating to the containment
atmosphere or to the main PHT system at least one isolation device is provided. The
system generally meets the requirements of the IAEA safety guide 50-SG-D12.
2.13.3
2.13.4
Page 66
Chapter 2
2.13.5
2.13.6
Oil system
Electrical fires
Charcoal filter fires
Diesel oil fires
Fire Prevention
Following methods have been adopted for fire prevention :
2012 MECON Limited. All rights reserved
Page 67
Chapter 2
1.
2.
3.
4.
5.
Physical barriers
Separation redundant systems with fire barriers.
Use of Fire Resistant Low Smoke (FRLS) and Fire Survival (FS) cables.
Early detection
Fire break
Fire Protection
A general network of water hydrants has been provided covering the plant area.
Following three categories of fire hazard are identified, based on fire load as per
handbook of Industrial Loss Prevention, prepared by Factory Mutual Engineering
Corporation :
Low fire hazard
Medium fire hazard
High fire hazard
For low fire hazard areas of Reactor Building, smoke detectors have been provided as
fire detection measure and firewater as fire fighting system.
For low fire hazard areas of Nuclear building, turbine building, station auxiliary building
etc., generally, smoke detectors and portable fire extinguishers are provided.
For high fire hazard areas such as turbine oil tanks, day oil tanks, and transformers,
High Velocity Water Spray Systems on automatic mode are provided for fire protection.
For DG room, smoke detectors and CO2 fire protection are provided.
For high and moderate fire hazard areas such as cable vaults, cable trays and PHT
motors etc. Medium Velocity Water Spray System with electrically operated deluge valve
is provided.
2.13.7
Page 68
Chapter 2
starts when the system pressure drop below 40 kg/m (g) with conditioning signal for
LOCA. The long term ECCS recirculation phase, takes over core cooling on, low level in
light water accumulator and low pressure in air accumulator. ECCS pumps, which take
suction from ECCS sumps, are poised for action at PHT pressure 40 kg/m (g).
However, recirculation starts only when the PHT system pressure falls below the pump
delivery head. During initial phase of recirculation, inventory of PDHRS system is
utilized. The Motorized Valve in the lines leading from PDHRS tank to ECCS sump /
suction would actuate on LOCA by suitably engineering logics.
All motorized valves in the system are duplicated to satisfy the single failure criterion.
For low-pressure injection and recirculation, 4 x 50% pumps are provided for
redundancy. They are powered from Class III electric power supply. Operability checks
for all ECCS valves and pumps, together with logic checks, are possible even when the
reactor is in operation. No operator action is envisaged in the operation of the ECCS
following a LOCA.
2.13.8
2.13.9
2.14
2.14.1
RADIOLOGICAL PROTECTION
Radiation Levels and Access Control
Design Objective
1. During normal operation, to minimize the radiation dose to plant personnel and
members of the public in accordance with the principle of `As low as Reasonably
Achievable (ALARA) and in any case not exceeding the prescribed limits specified
by the Regulatory Body. (Refer Radiation Protection Manual, AERB 2005 Rev 4).
2. To minimize the risk to the public from the release of radioactivity, if any, under
abnormal / postulated accident conditions. For scenarios within the design basis, the
calculated releases shall be within the specified release limits given in Technical
Specifications.
This objective is met by ensuring that plant conditions associated with high radiological
consequences have low likelihood of occurrence and plant conditions with a high
likelihood of occurrence have only small or no radiological consequences.
Page 69
Chapter 2
Design Criteria
The shielding has been designed to achieve the radiation levels below 1 Gy/h (0.1
mR/h) in all areas of the plant, intended for full-time personnel occupancy. For areas
with lower occupancy, shielding has been designed as under.
SN.
i)
ii)
Areas
Normal full-time occupancy areas (Supervised Areas)
Reactor Building (Controlled Areas)
a) Areas accessible during reactor power operation (Accessible Areas)
Occupancy 8 hours / day
Occupancy 4 hours / day
Occupancy 2 hours / day
Occupancy 1 hours / day
b) Areas inaccessible during reactor operation (Shutdown areas)
General field during reactor shut down
Areas with limited occupancy (70 h/y)
Max Radiation
Level (Gy/h)
1
5
10
20
40
40
150
Contamination Control
To control the spread of radioactive contamination, the plant is divided into three distinct
radiation zones, (Section 2.11.3) classified according to their potential for radioactive
contamination and / or radiation exposure.
The Zoning Philosophy is Implemented as Follows :
A single point entry is provided. This is in the Zone-1 area of the Nuclear building.
Personnel and material movement from higher to lower zone and vice-versa
permitted in sequence only.
Barriers and radiation monitors are provided at inter-zonal boundaries for effective
control of spread of contamination.
Page 70
Chapter 2
Decontamination Facilities :
For personnel decontamination, showers have been provided in Zone 2.
A special decontamination room near the main airlock of each unit is provided for
highly contaminated personnel.
Equipment decontamination facility is provided at 100m elevation in Waste
Management Plant (Zone-3).
2.14.3
Radiation Monitoring
In order to monitoring continuously the radiological status, fixed radiation monitors are
installed in certain areas of the reactor building, spent fuel building and reactor auxiliary
building. Each monitor has both local and control room indication / annunciation which
provides visual indication / audio annunciation when the radiation level exceeds a preset value. High-alarm (at pre-set values) are indicated / annunciated by the warning
buzzer as well as flashing lights. Monitors of appropriate ranges are installed in various
areas to monitor the radiation fields during various operational states and accident
conditions. In addition, portable radiation monitors are also available for monitoring, as
required. On-line sampling provisions are made for the assessment of air-borne activity
in different areas of Reactor Building.
The radiation dose rates at different areas in and around the plant areas are monitored
by installed monitors with indications / alarms in a number of locations around the plant.
In addition, thermo-luminescent dosimeters (TLDs) are also installed at a number of
locations. These TLDs will be collected periodically and the dose accumulated during the
period will be measured.
For personnel monitoring, thermo-luminescent dosimeters and direct reading dosimeters
are provided. Bioassay analysis and whole-body counting are done for monitoring
internal dose received by personnel. In addition, hand and foot monitors are installed at
inter zonal boundaries of various radiation zones.
Appropriate radiation monitoring instruments are installed for the sampling and
monitoring of radioactive effluents from the plant. The continuous monitors are provided
with alarms in control room to indicate if the releases exceed the preset values, in order
to enable the operating personnel to initiate corrective actions. All the materials, articles
or solid wastes released from the plant are monitored for radioactivity content and
contamination. All radioactive materials are handled, transported and stored as per
approved Radiation Protection Procedures (RPPs). Records of all the active materials
released from the plant will be maintained.
2.14.4
Environmental Monitoring
A programme of environmental monitoring is being carried out by Environmental Survey
Laboratory (ESL) with the following scope and objectives :
a. Establish the background radiation levels in the pre-operational period.
b. Collect meteorological data, especially on diffusion climatology, during the preoperational period.
Page 71
Chapter 2
c. Determine the safe recipient capacity of the air and water environment after studying
the dispersion pathways.
d. Establish allowable release limits to air and water from the plant.
e. Identify critical groups and critical radio nuclides based on trace element studies.
f. Identify indicator organisms and vegetation for regular monitoring.
g. Measurement of radiation levels in the environment during operational phase by
TLD.
h. Carry out demographic studies and monitor station release by measurements of
radioactivity in soil, vegetation, food, etc., on routine basis.
i. Evaluate impact of the NPP on the environment and population.
j. Be organized to cope with different aspects of monitoring and assessment for
radiological protection in the public domain in the case of an emergency.
2.14.5
2.15
2.15.1
2.15.2
Page 72
Chapter 2
All these stack-activity monitoring instruments are housed in a room known as the Stack
Monitoring Room, which is located, near the stack. This location provides low radiation
background. Iso-kinetic probe draws the air sample, which successively passes through
the filter detector assemblies of the air particulate and iodine activity monitors.
Subsequently, it is led to the inert gas monitor chamber and then routed back to the
stack. Individual signal processing unit provides release rate and integral releases over a
set period for the above mentioned activities. These are also compared with set levels
and alarms are generated if the activity exceeds the set levels.
2.15.3
Stack Release
4X700 MWe unit
GBq/d
2.02E+04
1.08E+01
1.10E+04
7.66E+03
2.02E-01
2.02E-01
Dose at Exclusion
Boundary (mSv/y)
Adult
Infant
1.61E-02
1.61E-02
9.28E-03
9.28E-03
3.04E-02
4.56E-02
3.72E-02
5.58E-02
4.70E-03
5.74E-02
4.12E-02
8.00E-02
1.39E-01
2.64E-01
Radioactive gaseous effluents when averaged over one day shall not exceed ten times
the annual average release rates specified above.
2.15.4
Page 73
Chapter 2
ALARA (As low As Reasonably Achievable). The principles used for the management of
radioactive wastes are:
Dilute and disperse applicable to low level wastes,
Delay, delay and disperse applicable to wastes containing short lived radio
nuclides
Concentrate and contain applicable to relatively high active wastes containing long
lived radio nuclides
Though complete prevention of radioactive waste generation is a difficult task, keeping
the waste generation to the minimum practicable is an essential objective of radioactive
waste management. In doing so, it is essential to minimize waste generation in all the
stages of a nuclear power plant. Waste minimization refers to waste generation by
operational and maintenance activities of plant and secondary waste resulting from
predisposal management of radioactive waste. Nuclear effluents are being given the
prime attention right from generation, handling, treatment, conditioning, transportation,
storage and final disposal, in a manner that it meets the requirements of the Safety
Guide AERB/SG/D 13 Liquid and Solid Radioactive Waste Management in PHWRs
and the discharge limits specified by them.
Following systems are provided at waste management plant :
a. Liquid effluent segregation system (LESS)
b. Storage, treatment and disposal system for low level activity and high volume liquid
waste.
c. Evaporation system (after ion-exchange process) for evaporating the relatively high
active and low volume tritium bearing liquid waste followed by dispersal through air
route / stack.
d. Spent Ion Exchange (IX) resin management system
e. Volume reduction facility
f. Decontamination system
g. Laundry system.
Liquid Effluent Segregation System (LESS)
LESS design philosophy is to ensure segregation and collection at source of all the liquid
wastes generated in the station based on level of activity and chemical nature, so as to
i. Minimize cross contamination and
ii. Facilitate judicious decision for management of each category of waste.
The classifications and the category they belong to and the origin of the wastes are
given in Table 2.3.
Table 2.3: Classification of Liquid Wastes
Sl.
No.
1.
2.
Classification
Category
Sources
I, II
I, II
Page 74
Chapter 2
Sl.
No.
Classification
Category
Waste (ANCW)
3.
4.
5.
I, II, III
I, II
Sources
drains from decontamination centre and other areas
of WMP and vent exhaust room. Laboratory rinses
and washes.
Laboratory solutions from nuclear building and
decontamination centre drains.
D2O upgrading reject, moderator room sump in RB,
drains from heavy water handling areas in Nuclear
building.
Liquid scintillation counters, contaminated oil, grease,
etc.
Waste Categorization
Categorization of liquid waste streams based on radioactivity concentration (as approved
by AERB) is as follows :
Category I :
Category II:
Category III:
Category IV:
Category V:
Gross beta activity more than 1 x 104 Ci/ml (3.7 x 108 (MBq/m).
This category waste is heat generating waste. Shielding,
treatment and cooling is required for such wastes. However waste
of this category is not encountered in PHWRs.
The quantity of liquid waste in each classification and the treatment methods are given in
Table 2.4.
Page 75
Chapter 2
Quantity
m/day
Activity levels
(Bq/ml)
Gross Tritium
-
1.0 Potentially Active Waste (PAW)
Showers
30
3.7E-3
250
Washings
20
3.7E-2
250
Laundry
25
3.7E-1
100
2.0 Active NonChemical
Waste
(ANCW)
12
Total
Activity inventory
Gross
- (KBq)
Tritium
(MBq)
111
740
10360
7500
5000
2500
Treatment
1.85
1850
22200
2220
1.85
11E4
3700
222000
0.371
7.4E4
2220
444000
- Do -
1850
18500
Occasional
Occasional
0.037
1850
Occasional
Occasional
39331
683220
96.01
Page 76
Chapter 2
Two nos. of receipt tanks for each stream have been provided at RCC dyke area in
which one will be receiving the liquid waste and the liquid from other tanks will be under
processing. Two nos. of micron filters (1 working and 1 standby) are provided for each
stream. The segregated liquid effluents, to decide the mode of discharge, are divided
into two categories viz. i) low level high volume waste (PAW and LW) and ii) tritium
bearing waste (ANCW, TTW and neutralized ACW). After filtration, the low level high
volume liquid wastes (waste water from shower, washroom and laundry area) are stored
in the post treatment tank.
Low level treated liquid waste from post treatment tank is sampled, analyzed in the
laboratory and monitored after preparing a batch of treated waste. This treated waste is
then injected into the plant water discharge (Blow down) piping. Inline mixers are
provided in the pipe line to ensure thorough mixing of treated waste with plant water
discharge system, before it gets discharged.
Liquid waste discharges are made in batches normally on single shift basis. Availability
of blow down flow is ensured through control logics and administrative control before
commencing of discharge of treated waste. The activity concentration of liquid waste
being discharged is monitored by an online activity monitor located on treated waste line
in WMP (before injecting it in plant water discharge system) in addition to sampling and
analysis carried out in laboratory. On attaining set level of activity the activity monitor
fitted in the discharge line will trip the discharge pump.
Liquid wastes having relatively high tritium and Beta gamma activity like Tritiated Waste
(TTW) generated from Upgrading plant rejects, Moderator room sump & Clean-up
system and Active Non Chemical Waste (ANCW) generated from Equipment
decontamination system of WMP, chemical laboratory & SFSB cask wash down area, of
less volume will be evaporated, diluted with exhaust air and discharged through stack to
air route. This quantum of liquid waste activity constitutes a major portion of the total
activity in the liquid waste. Therefore only less than 10% of total activity contained in
major volume of liquid effluent activity from HAPP 1&2 will be added to the liquid route
discharge point.
Treatment and Disposal Liquid Waste through Air Route (Evaporation System)
Liquid effluent having relativity higher activity are treated by filtration and ion exchange
process and disposed through air route using Evaporation system. Streams like ANCW,
ACW and TTW, after filtration, will be diverted to a synthetic ion exchange column to
remove the dissolved Beta-gamma activity and then stored in evaporation system feed
tank. These polished tritium bearing liquid waste streams (free of gross beta activity) are
sent to a steam heated evaporator with a controlled flow rate of 1.4 m/hr. This vaporized
stream is then injected into the ventilation exhaust ducting leading to 100 m high stack.
Evaporation of effluents having relatively higher level of activity ensures the discharges
through water route are kept at minimum. The air route mode of disposal offers unique
advantage of higher release limits per unit of dose allocation as compared to liquid route.
This mode of disposal suits inland site where water body is scarce and extensively used
by the surrounding population. The liquid waste disposal scheme is shown in Fig. 2.10.
Page 77
Chapter 2
2.15.5
Discharge Limits
For the plant, at the common discharge point the following discharge limits are
considered.
Radionuclide
Tritium
C-14
Cs-137
Sr-90
Total
Page 78
Chapter 2
Page 80
Chapter 2
2.15.6
Page 81
Chapter 2
COMPACTABLE
CAT. I
UPTO 200 mR/Hr
(upto 2mSv/Hr)
ASSORTED WASTE
<2mR/Hr
(0.02 mSv/Hr)
BALER
NON-COMPACTABLE
EARTH
TRENCH
>2mR/Hr <200mR/Hr
(>0.02 mSv/Hr <2mSv/Hr)
COMBUSTIBLE
CHIMNEY
INCINERATION
ABH
CAT. II
>200mR/Hr UPTO 2R/Hr
(>2mSv/Hr upto 20mSv/Hr)
TRANSFERRED TO CS
HOPPERS AND
DEWATERED
CAT. IIIA
UPTO 50R/Hr
(500mSv/Hr)
IMMOBILISED IN
POLYMER MATRIX
CAT. IIIB
ABOVE 50R/Hr
(ABOVE 500mSv/Hr)
SPENT IX RESIN
Page 82
Chapter 2
TILE HOLES
CAT. III
2R/Hr & ABOVE
(20mSv/Hr & ABOVE)
SOLIDIFICATION /
EMBEDDMENT IN
CEMENT
SLUDGES LIQUID
FILTERS COMPONENTS
RCC TRENCHES
SCRUBBING WATER
Page 83
Chapter 2
Page 84
Chapter 2
assess and record the radioactive content in each conditioned waste packages before
disposing them. Name of the vault and their identification also recorded.
The dose rate on the top of the sealed earth trenches and RCC trenches / vaults would
not exceed 0.01 mGy/h.
Spent Fuel
Spent fuel is removed from the reactor core and transferred to spent fuel inspection bay
(SFIB) where it is inspected for leaks / pin holes / damage. It is then stored in spent fuel
storage bay (SFSB) which is under continuous radiological surveillance. The spent fuel
is stored in SFSB till it cools down to dry storage level (about 5 years). Subsequent
action on the spent fuel is dictated by the policy of the Department of Atomic Energy /
Government of India.
Size of Spent Fuel Storage Bay
The size of one SFSB can accommodate 10 years of spent fuel discharge and one core
load.
2.16
SAFETY ANALYSIS
The objective of Safety Analysis is to demonstrate that the public is adequately protected
from the effects of power plant operation and abnormal events that might occur during
the plant life. It is to be ensured that the plant does not significantly add to the health
risks to which individuals and society are already exposed.
The basic approach adopted in the safety analysis centers on:
1. Identifying all abnormal events during the plant life that can lead to radiation
exposures, and their classification according to their probability of occurrence.
2. Identifying consequences of such events.
The events are further classified in two categories.
1. Single failure events
2. Multiple failure events
Single Failure Events
A single failure is defined as a failure of a process system.
Multiple Failure Events
Multiple failure events are defined as failure of a process system along with its
associated safety system. Safety analysis will be carried out for typical single / multiple
failure events in line with AERB safety guide.
Some example of postulated single failure / multiple failure are given below.
Safety analysis will be carried out for typical single / dual failure events :
Page 85
Chapter 2
Secondary side events (eg, turbine trip, BFP trip steam leaks)
Plant power change events (eg, power drops)
Electrical disturbances (eg. Net load rejection, frequency swing)
PHT system malfunctions (eg. Pressurizing pump trip, pressure controller
malfunction)
Page 86
Chapter 2
It is demonstrated that under the design basis accident, the dose to the members of the
public would not exceed 0.5 Sv (50 rem) to child thyroid and 0.1 Sv (10 rem) for the
whole body.
2.17
POWER REQUIREMENTS
During construction & commissioning Max 10 MW will be required which will be sourced
from State Grid as follows:
Construction power supply will be drawn from the existing 33 KV/ 11 KV sub-station
nearby.
Start up / commissioning power from 220 KV sub-station. This sub-station will
connect to nearby 220 KV sub-station.
Page 87
Chapter 2
Page 88
Chapter 2
2.19
WATER REQUIREMENTS
Page 89
Chapter 2
requirement stipulated by AERB and State Pollution control Board and there will not be
any restrictions on any use on downstream side.
2.19.3 Cycle of Concentration of Water
The estimated rate of water consumption for 4X700 MWe will be to the tune of 4.5 m3/hr
per MWe, taking cycle of concentration (COC) as 3. The major portion of this water is
lost through evaporation in evaporation tower and thus further reduction in water
consumption is not possible. The COC for HAPP, Haryana power project the COC value
of three is worked out based on studies carried out at Kakarapar site considering the
optimization of techno commercial considerations, water chemistry, nuclear safety and
water conservation.
2.20
CONSTRUCTION FACILITIES
2.21
POWER EVACUATION
2.22
All construction facilities like stone, metal, aggregate etc from Tosham village which
is about 40 km from Hisar and from other places like Chandigarh and Delhi.
Sand would be sourced from Karnal and / or Ghaghar river.
Construction power supply of about 10 MW is available from nearby 33 KV /11 KV
Water for construction purpose will be drawn from nearby canal system.
Power evacuation lines from project to major load centers at Hisar, Bhivani,
Fatehabad, Bahadurgarh and other load centers in northern grid through Centralised
Transmission Utility (CTU).
Power Evacuation in principal is feasible for 2800 MWe power from site. The Power
generated at HAPP will be evacuated through 400 kv transmission system. The number
of transmission outlets and their destination will be finalized taking into account share of
beneficial state in due course after a detailed power system studies are carried out by
PGCIL and approved by the concerned authorities
2.23
PROJECT COST
The estimated cost of 2X700MWe PHWR (Pressurised Heavy Water Reactor) Atomic
Power Project along with the residential complex at Gorakhpur, District Fatehabad,
Haryana is about Rs. 11751 Crores (estimates based on base cost of 2011-12) and that
for 4x700MWe is about Rs 23502 Crores (base cost 2011-12).
Page 90
Chapter 2
Fig. 2.13 : Water Balance Diagram for Haryana Atomic Power Plant 1 & 2.
2012 MECON Limited. All rights reserved
Page 91
Chapter 2
2.24
Water supply,
Storm water drainage, sewerage, power, etc.,
Disposal of treated wastes from the complex on land / water body and into
sewerage system.
2 Floor Space Index (FSI) = Total floor area including walls of all floors / Plot Area / Building Unit
2012 MECON Limited. All rights reserved
Page 92
Chapter 2
Page 93
Chapter 2
Fig. 2.14b : View of Township Site - Prosopis juliflora Growth in Waste Land
(February 2012)
Page 94
Chapter 2
Page 95
Chapter 2
Fig. 2.14d : Road Leading by the Side of Township Site (February 2012)
Page 96
Chapter 2
i.
1
2
3
3
F-Type
E-Type
D-Type
C-Type
No of
Quarters
4
110
512
1004
Estimated No
of Persons
20
550
2560
5020
Consumption
in Liters /Day
2700
74250
345600
677700
Page 97
Chapter 2
SN.
4
4A
5
6
7
8
9
10
Hospital
No of Beds
50
50
School
2000
Guest House with 50 rooms (occupancy 50%)
25
Service Personnel Hostel
30
100
Junior Hostel
30
60
Senior Hostel
6060
Shopping Centre & Convenience Shopping
30
Centre
Community Centre
30
Barrack
234
234
Single Officer Hostel
48
48
Administration Building
50
Environmental Survey Lab
15
Club House
25
Grand Total
Say in m3/d
Total Water requirement in liters per second (LPS)
Total Water requirement in Cubic Foot Per Second (Cusec)
11
12
13
14
15
16
2.25
No of
Quarters
Estimated No
of Persons
Consumption
in Liters /Day
17500
70000
3375
3500
8100
8100
1050
1050
31590
6480
1750
2025
875
1255645
1250.0
14.5
0.52
2.26
Page 98
Chapter 2
Page 99
Chapter 2
Page 100
Chapter 2
disturbance to the existing flora and fauna at the project site. Moreover, while designing
the township proper landscaping will be done and adequate green area, green belt and
avenue plantation will be undertaken to make a positive contribution to the status of flora
and fauna in the area.
2.27.3 Use of Local Building Material
The site is not in low lying area. It is a almost flat terrain no filling is required at the
township site. Sourcing of raw material during construction stage may cause
environmental concern to the site from where the material is being sourced. During
construction all efforts will be made to use local building material and due care will be
undertaken to avoid all environmental concerns arising due to sourcing of local building
material (for details refer Section 5.4.1, Chapter 5).
2.28
Page 101
Chapter 2
A guard pond will be provided in parallel to sewage treatment plant to store the domestic
wastewater in case breakdown or failure of wastewater treatment facility. The guard
pond will have capacity of 2000 m3 storage area for retaining wastewater during repair of
treatment plant. An adequate out fall for discharge of treated sewage from township will
be planned.
The residential complex of JNPP will be provided with a guard pond and a sewage
treatment plant (STP) for hold of slightly polluted water generated during various
activities in the residential complex and treatment of sewage from the houses and other
facilities. The design parameters of the STP shall be based on the conditions given in
Table 2.7a. The design criteria for different units in sewage treatment plant are given in
Table 2.7b. The flow sheet of sewage treatment plant is shown in Fig. 2.16. The STP
system will comprise the following sections:
Primary Treatment
- Screen Chamber
- Grit Chamber
- Sewage Collection Sump
Biological Treatment
- Fluidized Bed Bio Reactor (FBR)
- Clarisettler
Tertiary Treatment
- Chlorine Contact Tank
- Dual Media Filter
- Activated Carbon Filter
Sludge Handling / Guard Pond
- The sludge drying beds / pond of suitable capacity will be designed to dry the
sludge generated from the sewage treatment plant during its normal operation as
well as its break down. In case of failure of the STP, the sewage will be pumped
to the guard pond directly to allow the gravity settling of the solid waste / sludge.
This sludge will be removed from the guard pond regularly and will be used as
manure for development of green belt at the project site and residential complex.
Table 2.7a : Sewage Treatment Plant : Design Parameters (Total Flow : 1000m3/day)
SN.
Parameters
1
2
3
4
pH
BOD (mg/I)
COD (mg/I)
TSS (mg/I)
Before
Treatment
7.65
250
350
250
Screen Chamber
Velocity through screen
Value to be Considered
for Design
Range of Value
Specified by the Codes
0.75 m/sec
Page 102
Chapter 2
2
3
5
6
7
Clear openings
Grit Chamber
Detention time
Sewage Collection Sump at STP
Detention time
Air requirement for mixing
FBR (Two Stages)
Organic loading rate
Oxygen required
Oxygen transfer efficiency
Clarisettler
Detention time
Sludge Drying Beds
Drying cycle
Chlorine Contact Tank
Detention time
Dosage
20 mm
20 to 50 mm
60 sec
30 to 60 sec
6 hrs
750 to 800 m 3/d
6 to 8 hrs
0.9 m 3/m 3 of tank volume
12 - 2.0 hrs
15 - 2.0 hrs
10 - 12 days
6 - 12 days
45 - 60 min
To be maintained so that
residual chlorine is 2ppm
30 - 60 min
Page 103
Chapter 2
be worked out so that to run the pits in rotation taking into consideration the time taken
by a closed pit to decompose completely and time required evacuating the pit of manure
and the rate of compostible waste generation in the township. The compost by verminculture will be sold to the township houses for use in their kitchen garden. The excess
will be distributed free to the local farmers.
2.28.3 Traffic Management
Mass scale movement of residents of the township may cause traffic congestion the
area. Considering the traffic load in the area, an adequate traffic management plan has
been envisaged.
As per the master plan of the complex, no public road or highways (state or national) will
be allowed to pass through the residential complex. The official and private vehicles of
the employees will be parked in the residential complex at designated places and in the
stilt area provided in the residential buildings. The roads will be provided with footpaths
on both the sides of the roads and other essential road safety features. It is envisaged
that there would not be any loading / unloading heavy machinery and component in the
residential complex. All the official vehicles will be regularly checked and maintained for
their road worthiness.
During baseline data generation traffic survey was carried out during week days and
week ends at NH10 and road connecting NH10 to project site (Chapter 4, Tables 4.9a1
& 4.9a2 and 4.9b1 & 4.9b2), the traffic on the week ends is slightly more on the NH10
and road connecting NH10 with project site as compared to the weekdays. Detailed
traffic management plan for the project and the township has been planned taking in to
consideration the existing traffic load in the region (Section 5.5.3.7, Chapter 5).
2.28.4 Education and Health Facilities, Police and Other Services
The education, health, police and other facilities, post and telegraph, transport, etc in the
area is described in detail in Chapter 8, under Section 8.2.4. The above facilities in the
area considering a rural setup are adequate. The same may get overloaded due to the
residential project. Provisions have been made that all such basic facilities will be made
available to the residents of the township - matching to the facilities as available in cities.
The same will be accordingly planned and setup in the township.
Page 104
Chapter 2
Page 105
Chapter 2
Page 106
Chapter 2
Page 107
Chapter 2
Page 108
Chapter 2
Residential Complex also. Hence during any emergency situations arising due to natural
disasters and man made such as earthquake, cyclone/ flooding and radiological
emergencies will be dealt in line with the plan as presented in Chapter 9.
2.28.12 Security
The residential complex will be secured by fencing and no unauthorized entry will be
permitted in the construction area.
2.29
Page 109
Chapter 2
As such today our country has option for generating nuclear power by PHWR
technology with capacity of 220 MWe to 700 MWe, FBR technology with capacity of
500 MWe and Advanced Heavy Water Reactor of 300 MWe capacity which is under
launching stage by DAE. In addition, LWR technology of 1000 to 1650 MWe from
various countries are available for establishing at various sites in India.
The sites for location of a Nuclear Power Plant is surveyed, selected and
recommended by a Site Selection Committee constituted by Department of Atomic
Energy, Government of India. The above Committee has members from various
departments including one member from Ministry of Environment and Forest. The
above committee has a standard procedure as prescribed by AERB for selection of the
site covering all the studies, data, parameters which are necessary to meet the
requirements to establish a nuclear power plant at a particular site. The participation
of representative from AERB and MoEF in the higher level Site Selection committee
2012 MECON Limited. All rights reserved
Page 110
Chapter 3
ensures first order inputs from AERB & MoEF during site selection process. The
recommendation of the site selection committee are considered by Atomic Energy
comission which has member from the higher level of decision making bodies of
government of India The in Principal approval for the site is by theUnion Cabinat
which has in built provisions for under ministerial consultation, with the above
procedure in place for in principle approval of site..
The nuclear power plants are located either on inland site like Rawatbhatta, Narora,
Kakarpara and Kaiga and the coastal sites like, Tarapur and Madras. The inland sites
are assigned for reactor capacities varying from 220 MWe to 700 MWe. The above
limit of the capacity of reactor is mainly due to requirement of cooling water as well
as availability of infrastructure for transportation of heavy equipment of nuclear power
plant. The coastal sites are assigned for reactor capacity of 1000 MWe and more
because these units require huge amount of cooling water, which is available in
abundance from the sea and availability of sea route for transportation of heavy
equipment of nuclear power plant.
In line with the above program, Fatehabad site has been identified as the site, which
is having potential of setting up 4x700MWe PHWRs. The site has several favorable
factors for locating 4x700 MWe PHWRs. Some of the major ones are summarized
below:
(a)
(b)
(c)
(d)
(e)
Page 111
Chapter 3
DESCRIPTION OF ENVIRONMENT
4.1
INTRODUCTION
4.1.1
General
EIA is the most important aspect of overall environment management strategy. EIA
needs a datum on which the prediction can be done. Information on the existing
baseline environmental status is essential for assessing the likely environmental
impacts of the proposed project. For studying the existing baseline environmental
status the following basic steps are required:
Delineation of project site and study area.
Delineation of the environmental components and methodology
Delineation of study period.
After delineation of the above the following studies were conducted:
Environmental settings within the study area based on secondary data.
Baseline data generation / establishment of baseline for environmental
components.
Traffic density at the inter-phase of project site and study area.
4.1.2
SN
1
4.1.3
Table 4.1: List of Major Industries within 25 km Radius of the Proposed Plant
Name of Industry
From Project Centre
Capacity
Distance (Km)
Direction
2X300MW
Thermal Power Plant at village Khedar
20
E
(HPGCL)
Project Site and Study Area
The project site for the proposed project is at Gorakhpur Village, Fatehabad,
Haryana. The land requirement for the proposed project is about 1319 acres (534
ha), which is private land for which land acquisition process is in progress with the
approval of Government of Haryana. The proposed township for the project covers
about 186 acres (75 hectares), which is mostly barren land. The project will house
four 700 MWe PHWR units. Two of such units i.e. 2X700 MWe will form one twin unit
and there will be two twin units in the project. The two twin units will be separated by
a distance of 640m. The two units within a twin unit will be separated by 108m. The
exclusion zone of 1km is maintained around each 700 MWe PHWR unit. The outer
boundary of exclusion zone circle combining the four units will form the project site
(Fig. 2.12a).
Page 112
Chapter 4
The study area for all the environmental studies, except for radiological studies, is
taken as 10 km radius around the proposed project site (with Reactor Building (RB)
as center). About 3/4th of the 10 km study area falls in Fatehabad district and about
1/4th falls in Hisar district. However, for radiological studies the study area is taken as
30 km radius around the Reactor Building (RB). No forest land is involved in this
area.
4.1.4
4.1.5
Study Period
The baseline environmental data generation for conventional pollutant was carried
out during March 2011 to May 2011 and that for radiological survey was carried out
during January to March 2011.
Table 4.2a: Environmental Components and the Methodologies Adopted For the Study
S
Area
Environmental
Parameters
N
Components
Monitoring of Conventional Pollutants and other Environmental Components
1
Air
Water
Soil
4
5
6
7
8
Radiological Survey
1
30 km Radius
Methodology*
Meteorology
Ambient Air Quality (prescribed parameters
by MoEF).
Noise Levels
Water Quality
Surface (parameters as per surface water
quality criteria)
Ground (parameters as per IS: 10500)
Soil Quality (Physico-chemical characteristics)
Field monitoring
Ecological
features
-
Field
study
secondary data
Field monitoring
Geology
and
hydrogeology
Land-use
pattern
Socioeconomic
Study
Air
Traffic Density
Field monitoring
Field monitoring
/
Field
study
/
secondary data
Satellite imagery /
secondary data
Field
study
/
secondary data
Field Monitoring
Page 113
Chapter 4
S
N
2
Area
30 km Radius
Environmental
Components
Water
30 km Radius
Soil
30 km Radius
Biota
(biological
samples)
Parameters
Methodology*
of
in
Field Monitoring
of
in
Field Monitoring
of
of
in
Field Monitoring
4.2
4.2.1
Meteorology
A meteorological station was set up at Gorakhpur Village, which lies within the
proposed study area at a distance of 3.5km E of the project site. The location of the
meteorological data monitoring station is marked in Drg. No. MEC/11/S2/Q6SY/01.
At the meteorological station, Wind Speed & Direction, Temperature, Relative
Humidity, Cloud Cover and Rain Fall were recorded at hourly intervals throughout the
monitoring period. The detailed metrological data collected at the project site is
presented as Annexure IVA and summarised meteorological data is given in Table
4.2b.
March 35.2
- May
0.0
5.11
Temperature ( C)
Max. Min.
Avg.
45.0
70
5.0
25.6
27
38.5
Total
(mm)
53.75
Rainfall
Rainy Days
(Nos)
5
Cloud
Cover
(Oktas)
Clear
Wind frequency distribution during the monitoring period at the site is given as Table
4.2c (1 to 3) for the period March 2011 to May 2011 (summer season). The Wind
Rose diagrams are given as Figs. 4.2a, 4.2b and 4.2c respectively.
From Table 4.2c1 it was observed that overall, the predominant wind directions for
March 2011 May 2011 were NW, W, NE, SE, SW, and N (prevailing for 16.03%,
10.06, 6.33, 4.75 and 4.34 of the time). Calm conditions prevailed for 29.39% of the
time. The wind velocity was mostly between 1.6 to 18.0 km/hr (70.59% of the time).
Page 114
Chapter 4
Table 4.2c1: Wind Frequency Distribution (%) During Day & Night (Overall) March to
May 2011
Wind
Wind Speed Ranges (m/s)
Direction
0.44 2.0
2.0 3.0
3.0 5.0
4.0 - 5.0
N
3.39
0.59
0.27
0.09
NNE
1.27
0.09
0.09
0.04
NE
4.44
0.59
0.68
0.40
ENE
0.86
0.27
0.09
0.18
E
2.67
0.86
0.36
0.04
ESE
0.77
0.18
0.14
0.04
SE
2.85
1.22
0.32
0.36
SSE
0.36
0.41
0.27
0.18
S
2.40
0.86
0.27
0.14
SSW
1.13
0.45
0.27
0.18
SW
2.85
1.27
0.32
0.18
WSW
2.26
0.82
0.50
0.00
W
5.80
2.08
1.27
0.68
WNW
1.12
0.77
0.32
0.09
NW
9.69
3.76
1.54
0.59
NNW
0.72
0.23
0.09
0.04
Sum (%)
42.58
14.45
6.8
3.23
Calm ( Wind Speed <0.44 m/s or <1.6 km/hr) = 29.41%
Sum
5.0 6.0
0.00
0.04
0.18
0.18
0.04
0.00
0.23
0.23
0.14
0.09
0.09
0.14
0.09
0.09
0.36
0.00
1.9
>=6.0
0.00
0.04
0.04
0.00
0.09
0.00
0.00
0.32
0.09
0.04
0.04
0.04
0.14
0.04
0.09
0.00
0.97
4.34
1.57
6.33
1.58
4.06
1.13
4.98
1.77
3.9
2.16
4.75
3.76
10.06
2.43
16.03
1.08
70.59
Fig. 4.2a: Wind-Rose During Summer Season: Day & Night (Overall)
While during the Day (Table 4.2.c2), the predominant wind directions were NW
(prevailing for 20.95% of the time), W (14.34%), SW (7.22%), NE (6.43%), SE
(6.52%), and NE (6.43%). Calm conditions prevailed for 10.47% of the time. The
wind velocity was mostly between 1.6 to 18.0 km/hr (89.53% of the time).
Page 115
Chapter 4
Table 4.2c2 : Wind Frequency Distribution (%) During Day Time March to May 2011
Wind
Wind Speed Ranges (m/s)
Direction
0.44 2.0
2.0 3.0
3.0 5.0 4.0 - 5.0 5.0 6.0
N
3.36
0.69
0.20
0.10
0.00
NNE
1.78
0.10
0.09
0.00
0.00
NE
4.45
0.69
0.49
0.40
0.30
ENE
0.49
0.20
0.00
0.30
0.30
E
2.67
1.09
0.69
0.00
0.00
ESE
0.79
0.20
0.00
0.10
0.00
SE
2.96
2.08
0.59
0.79
0.10
SSE
0.59
0.59
0.30
0.10
0.10
S
3.66
1.58
0.47
0.10
0.00
SSW
1.19
0.79
0.09
0.10
0.00
SW
4.05
1.98
0.59
0.30
0.20
WSW
1.98
1.38
0.79
0.00
0.30
W
6.72
3.66
2.57
1.19
0.20
WNW
1.88
1.38
0.69
0.20
0.10
NW
10.97
5.93
2.77
0.69
0.59
NNW
0.79
0.40
0.20
0.10
0.00
Sum (%)
48.33
22.74
10.53
4.47
2.19
Calm ( Wind Speed <0.44 m/s or <1.6 km/hr) = 10.47%
Sum
>=6.0
0.00
0.00
0.10
0.00
0.10
0.00
0.00
0.69
0.10
0.10
0.10
0.00
0.00
0.10
0.00
0.00
1.29
4.35
1.97
6.43
1.29
4.55
1.09
6.52
2.37
5.91
2.27
7.22
4.45
14.34
4.35
20.95
1.49
89.53
Page 116
Chapter 4
Table 4.2c3 : Wind Frequency Distribution (%) During Night Time March to May 2011
Wind
Wind Speed Ranges (m/s)
Direction
0.44 2.0
2.0 3.0
3.0 5.0
4.0 - 5.0
N
3.43
0.50
0.33
0.08
NNE
0.84
0.08
0.08
0.08
NE
4.43
0.50
0.83
0.42
ENE
1.17
0.33
0.17
0.08
E
2.68
0.67
0.08
0.08
ESE
0.75
0.17
0.25
0.00
SE
2.76
0.50
0.08
0.00
SSE
0.17
0.25
0.25
0.25
S
1.34
0.25
0.08
0.17
SSW
1.09
0.17
0.42
0.25
SW
1.84
0.67
0.08
0.08
WSW
2.50
0.33
0.25
0.00
W
5.02
0.75
0.17
0.25
WNW
1.59
0.25
0.00
0.00
NW
8.61
1.92
0.50
0.50
NNW
0.67
0.08
0.00
0.00
Sum (%)
38.89
7.42
3.57
2.24
Calm ( Wind Speed <0.44 m/s or <1.6 km/hr) = 45.41%
Sum
5.0 6.0
0.00
0.08
0.08
0.08
0.08
0.00
0.33
0.33
0.25
0.17
0.00
0.00
0.00
0.08
0.17
0.00
1.65
>=6.0
0.00
0.08
0.00
0.00
0.08
0.00
0.00
0.00
0.08
0.00
0.00
0.08
0.25
0.00
0.17
0.00
0.74
4.34
1.24
6.26
1.83
3.67
1.17
3.67
1.25
2.17
2.1
2.67
3.16
6.44
1.92
11.87
0.75
54.59
Ambient Air
General
Ambient Air Quality (AAQ) was monitored in terms of Particulate Matter (PM10 &
PM2.5), Sulphurdioxide (SO2), Oxides of Nitrogen (NOx) and ground level ozone.
These parameters were monitored at selected Ambient Air Quality (AAQ) monitoring
stations.
Page 117
Chapter 4
N
10.5
4th
NE
6.5
6th
E
8.5
5th
SE
8.5
5th
S
5.0
7th
SW
12.5
3rd
W
17
1st
NW
13
2nd
Calm
17.5
Summer % Frequency
Predominance Sequence
14.7
3rd
5.8
8th
6.0
7th
6.7
6th
7.2
5th
13.8
4th
17.8
1st
17.5
2nd
11.6
The main objective of AAQ data generation / establishment of baseline for AAQ is to
assess the future scenario of the surrounding environment by superimposing the
predicted pollution levels on the existing pollution levels. Thus it will be possible to
identify the location where maximum concentrations of pollutants are likely to occur
due to emissions from the proposed plant. The predominant wind direction of nearest
IMD observatory at Hisar was identified with the help of wind frequencies. The
predominant annual wind frequencies are W (17%), NW (13%), SW (12.5%), N
(10%) and E & SE (8.5%), while the calm value is 17.5%. The predominant wind
frequencies during summer season are W (17.8%), NW (17.5%), SW (13.8), N (13.7)
and S (9.2%), while the calm values are 11.6% (Table 4.2d).
The locations of AAQ stations are given in Table 4.3a. The AAQ stations were
located in the upwind and downwind direction of annual and summer winds with
respect the proposed plant by considering the points mentioned below:
1. Location of AAQ stations within 10 km radius around the proposed plant.
2. Approachability to and habitation near the monitoring stations.
3. Location of other industries within 10 km radius around the proposed plant.
Page 118
Chapter 4
Location
A1
Gorakhpur
A2
Nehla
9.5
A3
Siwani
5.5, SE
A4
Kirmara
9.0, SE
A5
Chaubara
5.5, NE
A6
Sabarwas
5.0, S
A7
Kajalheri
A8
Khaujri
3,
WSW
4.25,
NNW
Project
Site
3.5, E
E
Remarks
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Continuous
Methodology
As per the CPCB guidelines on methods of monitoring & analysis, 8 (eight) AAQ
monitoring stations were selected. These stations are marked in Drg. No.
MEC/11/S2/Q6SY/01.
During the monitoring periods, 24 hourly samples were collected twice a week for
PM10, SO2 and NOx, on each monitoring day. However as the site is a green field
site, for PM 2.5 24 hourly samples were collected on selected monitoring days. Eight
hourly samples were collected on selected monitoring days for ozone. The
methods of sample collection, equipment used and analysis procedure as
followed are given in Table 4.3b. The AAQ results have been compared with MoEF
Revised National ambient Air Quality Standards 2009 as given in Table 4.3c. The
days on which monitoring was conducted at different AAQ stations is given in Table
4.3d.
Table 4.3b: Methodology of Sampling and Analysis for AAQ Monitoring
Parameter
3
SO2 (g/m )
3
NOx (g/m )
PM10 (g/m3)
PM2.5 (g/m3)
Ozone (O3) (g/m3)
Instrument/Apparatus
Used
HVAS with Impinger Tube,
Spectrophotometer
HVAS with Impinger Tube,
Spectrophotometer
Respirable Dust Sampler
PM 2.5 Sampler
HVAS with Impinger Tube,
Spectrophotometer
Methodology
Reference
-do-do-do-
Page 119
Chapter 4
1
2
3
4
5
*
**
Parameter
Time
Weighted
Average
Location
Gorakhpur A1
Nehla A2
Siwani A3
Kirmara A4
Chaubara A5
Sabarwas A6
Kajalheri A7
Khaujri A8
1
1
1
1
1
1
1
1
5
5
5
5
5
5
5
5
March11
9 13 17 21
9 13 17 21
9 13 17 21
9 13 17 21
9 13 17 21
9 13 17 21
9 13 17 21
9 13 17 21
25
25
25
25
25
25
25
25
29
29
29
29
29
29
29
29
Date of Sampling
April11
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1 5 9 13 17 21 25 29
1
1
1
1
1
1
1
1
5
5
5
5
5
5
5
5
9
9
9
9
9
9
9
9
May11
13 17 21
13 17 21
13 17 21
13 17 21
13 17 21
13 17 21
13 17 21
13 17 21
25
25
25
25
25
25
25
25
29
29
29
29
29
29
29
29
Gorakhpur
A1
15
5
9
15
31
9
17
29
85
53
78
Nehla
A2
14
4
7
12
23
7
13
20
84
52
72
Siwani
A3
20
4
10
19
36
8
21
36
84
49
72
Khaujri
A8
11
5
7
11
17
8
13
17
65
45
59
Page 120
Chapter 4
Parameters
C 98
PM2.5 Max
(g/m3) Min.
Avg
C 98
O3
Max
(g/m3) Min.
Avg
C 98
Gorakhpur
A1
85
49
22
37
48
35
22
28
35
Nehla
A2
84
49
29
41
49
33
21
26
33
Siwani
A3
84
46
28
39
46
34
20
26
33
Max
Min.
Khaujri
A8
65
44
30
38
44
34
21
26
33
Avg
90
80
SO2 Norm
60
SO2 (g/m )
70
50
40
30
20
10
A8
Khaujri
Kajalheri A7
A4
Kirmara
Sabarwas A6
A3
Siwani
Chaubara A5
A2
Nehla
Gorakhpur A1
AAQ Stations
Page 121
Chapter 4
Max
90
Min.
Avg
NOx Norm
80
NOx (g/m )
70
60
50
40
30
20
10
Khaujri
A8
Kajalheri
A7
Sabarwas
A6
Chaubara
A5
Kirmara
A4
Siwani
A3
Nehla
A2
Gorakhpur
A1
AAQ Stations
Max
Min.
Avg
120
PM10 Norm
PM 10 (g/m )
100
80
60
40
20
A8
Khaujri
Kajalheri A7
Sabarwas A6
Chaubara A5
A4
A3
Siwani
Kirmara
A2
Nehla
Gorakhpur A1
AAQ Stations
Page 122
Chapter 4
Max
Min.
Avg
80
PM 2.5 (g/m )
PM2.5 Norm
60
40
20
Khaujri
A8
Kajalheri
A7
Sabarwas
A6
Chaubara
A5
Kirmara
A4
Siwani
A3
Nehla
A2
Gorakhpur
A1
AAQ Stations
Max
3
Ozone (g/m )
120
Min.
Avg
Ozone Norm
100
80
60
40
20
Khaujri
A8
Kajalheri
A7
Sabarwas
A6
Chaubara
A5
Kirmara
A4
Siwani
A3
Nehla
A2
Gorakhpur
A1
AAQ Stations
Noise
Selection of Monitoring Locations
A total of ten noise monitoring stations were selected to cover all type of areas as
given in Table 4.4a.
Page 123
Chapter 4
Location
Distance w.r.t.
Site Centre (km)
Gorakhpur
3.5
Nahla
9.5
Siwani
5.5
Kirmara
9.0
Chaubara
5.5
Sabarwas
5.0
Kajalheri
3.0
Khaujari
4.25
Badopal Near NH 8.0
Direction w.r.t
Site Centre
E
E
SE
SE
NE
S
WSW
NNW
WSW
Type of Area*
Date of
Sampling
14.04.11
15.04.11
16.04.11
17.04.11
18.04.11
19.04.11
20.04.11
21.04.11
22.04.11
Commercial
Residential Area
Residential Area
Residential Area
Residential Area
Residential Area
Residential Area
Residential Area
National Highway
(Industrial Area)
N10
Project Site
0
E
Project Site
23.04.11
(Proposed Industry)
* Note: Type of area for representing Commercial, Residential & Industrial selected at site. NH 10
is taken as Industrial area.
Methodology
To have an idea of the present background noise level of the project site, a detailed
measurement of noise level was carried out at 10 locations during the monitoring
period. Precision integrated sound level meter (type 2221 of Bruel & Kjaer of
Denmark) was used for measurement of noise level for the study. The
measurements were carried out for 24 hours. Hourly readings were recorded by the
operating the instrument for 1520 minutes in each hour at one-hour intervals in
which leq(A) have been measured. The noise monitoring stations are marked in Drg.
No. MEC/11/S2/Q6SY/01.
Results
The results of ambient noise monitoring are given in Table 4.4b and shown in Fig.
4.4a and 4.4b. The results have been compared with MoEF norms [Noise
(Regulation & Control) Rules, 2000] given in Table 4.4c. The result shows that at
Gorakhpur (N1) both day and night time noise is below the norm for commercial
area. At Nahla (N2), Siwani (N3), Gorakhpur (Project Site) (N10) and Kirmara (N4)
both day and night time noise values are within the norm for residential area. At NH
near Badopal (Hisar to Sirsa) (N5), the noise levels are below the norm for industrial
area both during day and night time.
Table 4.4b: Results of Noise Monitoring
Stn. No.
Location
Page 124
Chapter 4
Max dB (A)
Min. dB (A)
Avg. dB (A)
Project
Site N10
Badopal
N9
Khaujri N8
Kajalheri
N7
Sabarwas
N6
Chaubara
N5
Kirmara
N4
Siwani N3
Nehla N2
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Gorakhpur
N1
Norm dB (A)
Fig. 4.4a: Noise Levels During Day Time in the Study Area
Page 125
Chapter 4
Badopal
N9
Project
Site N10
Avg. dB (A)
Khaujri N8
Kajalheri
N7
Min. dB (A)
Sabarwas
N6
Chaubara
N5
Kirmara
N4
Max dB (A)
Siwani N3
Nehla N2
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Gorakhpur
N1
Norm dB (A)
Fig. 4.4b: Noise Levels During Night Time in the Study Area
4.2.4
Water Environment
Water quality monitoring was carried out with the following objectives:
To collect baseline data on existing water quality.
To assess the impact of the proposed outfalls on water quality of receiving
water bodies.
To assess the raw water quality to be used by the proposed project.
Selection of Sampling Locations
A total of eight water-sampling locations were selected for the present study covering
four surface water and four ground water sampling locations. The Surface water
sampling locations were selected at different locations all along the Canal up-stream
and down-stream of project site keeping in view the confluence point of surface water
channels receiving proposed plant outfalls. The canal water is being used by the
villagers for bathing, washing and cattle washing. The ground water sampling
locations were selected up gradient and down gradient of the different units of the
proposed plant. These stations are marked in Drg. No. MEC/11/S2/Q6SY/01.
Methodology
In order to study the existing water quality within the study area, grab samples of
water were collected from locations, as given in Table 4.5a. Surface water samples
were analysed for different parameters as required by CPCB surface water criteria
and ground water samples were analysed for different parameters as per IS: 10500.
The water samples analysed for different parameters as per American Public Health
Association (APHA), 1995 - "Standard Methods for the Examination of Water and
Waste Water" and IS: 3205 (Part 39) 1990 (reaffirmed 1996).
Page 126
Chapter 4
Station /
Sample
No.
Surface Water
SW1
SW3
SW4
Sub-branch
SW2
Kishangarh
Canal
Ground Water
GW1
Gorakhpur
GW2
Sabarwas
GW3
Samani
GW4
Kajalheri
2.5
NE
1..0
NNE
3.0
WNW
2.5
3.5
5.0
5.5
3.0
E
S
SE
WSW
Surface
Water (Canal)
Surface
Water (Canal)
Surface
Water (Canal)
Surface
Water (Canal)
Ground Water
Ground Water
Ground Water
Ground Water
Date of
Sampling
28.04.11
28.04.11
28.04.11
28.04.11
28.04.11
28.04.11
28.04.11
28.04.11
Parameters
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
Chapter 4
SN
Parameters
26.
27.
28.
29
Table 4.5c: Central Pollution Control Board (CPCB) Surface Water Quality Criteria
SN
1.
2.
3.
4.
5.
6.
7.
8.
Parameters
pH
Dissolved oxygen (as O2), mg/l, min
BOD, 5 days at 20 C, max
Total coliform organism, MPN/100 ml, max
Free ammonia (as N), mg/l, max
Electrical conductivity, mhos/cm, max
Sodium absorption ratio, max.
Boron (as B), mg/l, max.
Class A
Class B
Class C
Class D
Class E
Below E
Class A
6.58.5
6
2
50
-
Class B
6.58.5
5
3
500
-
Class C
6.0-9.0
4
3
5000
-
Class D
6.58.5
4
1.2
-
Class E
6.58.5
2250
26
2
1.
2.
3.
4.
5.
6
7
8
9
10.
11
12
13
14
Parameters
Essential Characteristics:
Colour, Hazen units, Max.
Odour
Taste
Turbidity, NTU, Max.
pH Value
Total Hardness (as CaCO3), mg/l,
Max
Iron (as Fe), mg/l, Max.
Chloride (as Cl), mg/l, Max.
Fluoride (as F) mg/L, Max.
Desirable Characteristics
Total Dissolved Solids mg/l, Max.
Calcium (as Ca), mg/l, Max.
Magnesium (as Mg), mg/L, Max.
Copper (Cu), mg/l, Max.
Manganese (as Mn), mg/l, Max.
* Norms
1
* Norms
2
5
Unobjectionable
Agreeable
5
6.5 to 8.5
300
GW2
GW3
GW4
4
Unobj.
5
Unobj.
3
Unobj.
3
Unobj.
10
NR
600
Agre.
4
8.07
172
Agre.
5
8.47
1404
Agre.
6
8.76
120
Agre.
6
8.4
148
0.3
250
1.0
1.0
1000
1.5
0.11
14
0.6
0.91
1082
0.6
0.101
122
0.3
0.080
49
0.3
500
75
30
75
0.1
2000
200
100
200
0.3
534
37
19
<0.01
0.08
3410
345
132
<0.01
0.06
603
14
20
<0.01
0.061
338
29
18
<0.01
0.050
Page 128
Chapter 4
SN.
* Norms
1
200
45
0.001
Parameters
15
16
17
18.
19
20.
21.
22.
23.
24.
25.
* Norms
2
400
100
0.005
GW2
GW3
4.2.5
GW4
63
13
<0.001
<0.0005
<0.005
<0.005
<0.03
<0.01
<0.05
0.107
<0.1
<0.01
<2
116
<0.01
Soil
Selection of Sampling Location
The soil sampling locations were selected with the following objectives:
To assess the background / baseline soil quality of the region.
To assess the impact (if any) of proposed Plant air emissions, effluent outfall
and solid waste on soil of the study area.
A total of ten sampling locations as marked in Drg. No. MEC/11/S2/Q6SY/01, were
selected for the study. The selected locations and the justification for their selection
are given in Table 4.6a.
Table 4.6a: Selection of Soil Sampling Locations and Justification
Distance w.r.t. Direction
Type of
Date of
Site Centre
w.r.t Site
Land
Sampling
Station /
Location
Sample No.
(km)
S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
Gorakhpur
Nahla
Samani
Kirmara
Chaubara
Sabarwas
Kajalheri
Khaujari
Badopal
Project Site
3.5
9.5
5.5
9.0
5.5
5.0
3.0
4.25
8.0
0
Centre
E
E
SE
SE
NE
S
WSW
NNW
WSW
-
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
Agriculture
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
26.11.10
Page 129
Chapter 4
<0.2
Methodology
In order to have an idea about the baseline soil quality in the study area, samples of
topsoil were collected from the five locations once during the study period. The soil
samples were marked, brought to laboratory, air-dried and analysed for different
physico-chemical characteristics by following the methodology given in Jackson, M.L.
(1967): "Soil Chemical Analysis" (Prentice Hall of India Pvt. Limited, New Delhi) and
"Soil Test Methodology" (1992), Edited B.S. Mathur. SSAC (BAU) Tech. Bull. 3/92.
Pp. 312. Department of Soil Sciences and Agriculture Chemistry, Birsa Agriculture
University, Ranchi.
Results of Soil Analysis
The results of analysis are given in Tables 4.6b, 4.6c, 4.6d and 4.6e. Soil pH plays a
very important role in the availability of nutrients. The composition of the soil
microbial community is also dependent on the soil pH. In the study area the soil
samples had more or less neutral pH.
.
Electrical conductivity is a measure of the concentration of soluble salts and ionic
activity. Salt concentration is directly proportional to the osmotic pressure, which
governs the process of osmosis in the soil plant system. The electrical conductivity
in all the soil samples ranged from 0.075 mS/cm (S9) to 0.488 mS/cm (S4).
Table 4.6b: Physico-Chemical Properties of Soils
Characteristics
Type of Land
Colour
Texture (Soil
type)
Bulk Density
(gm/cc)
Water Holding
Capacity (%)
pH (1:5 ratio)
Electrical
Conductivity
(mS/cm)
Results
S1
Agr.
Bl.
White
S. Lm
S3
Agr.
Lgt
Brw
S. Lm
S4
Agr.
Ylw
White
S. Lm
S5
Agr.
Ylw
White
Sdy
S6
Agr.
Brw
Ylw
Sdy
S7
Agr.
Brw
Ylw
Sdy
S8
Agr.
Ylw
White
Sdy
134
S2
Agr.
Lgt
Brw
Lm.
Sand
140
S10
Agr.
Bl.
White
S. Lm
128
S9
Agr.
Ylw
White
Lm.
Sand
134
143
138
138
139
127
32.4
32.5
29.7
29.8
31.1
32.1
30.1
32.3
30.5
30.1
7.0
0.271
6.9
0.235
7.1
0.114
6.8
0.488
7.0
0.110
7.2
0.178
6.9
0.081
7.3
0.241
6.8
0.075
6.8
0.078
135
Phosphorus and Nitrogen are limiting nutrients. In the tested soil samples, availability
of Nitrogen is Medium (in S1, S5, S6, S7, S8, S9 & S10) to high (S2, S3, & S4) and
available Phosphorus is low in all the collected soil samples. However, Potassium is
high in all the soil samples. Organic carbon content is medium (S1, S2, S6 and S8) to
low (S3, S4, S5, S7, S9 & S10) in the soil samples.
Table 4.6c: Available Major Nutrients in Soil
Nutrients & Ratings
Organic Carbon (%)
Organic Matter (%)
Available Nitrogen
(kg/ha)
S1
0.71
M
1.6
364
M
S2
0.57
M
1.4
1254
H
S3
0.49
L
1.2
583
H
S4
0.47
L
1.2
715
H
Results
S5
S6
0.47
0.57
L
M
1.2
1.4
383
301
M
M
S7
0.38
L
1.0
326
M
S8
0.59
M
1.4
320
M
S9
0.44
L
1.1
354
M
Page 130
Chapter 4
S10
0.45
L
1.2
351
M
S1
2.0
L
709
H
:
:
:
:
S2
1.0
L
672
H
S3
2.0
L
560
H
S4
0.2
L
597
H
Results
S5
S6
2.0
1.0
L
L
299
1289
H
H
S7
1.0
L
373
H
S8
1.0
L
336
H
S9
1.0
L
336
H
S10
1.0
L
373
H
The results show that the Calcium and Magnesium constitutes the bulk of
exchangeable cations in the tested soil samples. This indicates that the collected soil
samples are showing the signs of increase in alkalinity (Sodium / Potassium).
Table 4.6d: Exchangeable Cations
Cations
Results
S1
S2
S3
S4
S5
S6
Calcium
12
8
4
8
4
24
(meq/100gm)
(47.21) (33.59) (27.03) (38.55) (26.44) (52.79)
Magnesium
12
14
10
8
10
20
(meq/100gm)
(47.21) (58.77) (67.57) (38.55) (66.09) (43.99)
Sodium
0.87
1.3
0.35
4.29
0.89
0.53
(meq/100gm)
(3.42)
(5.46) (2.36) (20.67) (5.88) (1.17)
Potassium
0.55
0.52
0.45
0.46
0.24
0.93
(meq/100gm)
(2.16)
(2.18) (3.04) (2.22) (1.59) (2.05)
Total base
25.42
23.82
14.8
20.75 15.13 45.46
(100)
(100) (100)
(100) (100) (100)
Values in ( ) give the % of respective cation of the total cations.
S7
32
(68.82)
14
(30.11)
0.2
(0.43)
0.3
(0.65)
46.5
(100)
S8
26
(63.55)
14
(34.22)
0.49
(1.20)
0.42
(1.03)
40.91
(100)
S9
4
(23.77)
12
(71.30)
0.51
(3.03)
0.32
(1.90)
16.83
(100)
S10
4
(23.95)
12
(71.86)
0.38
(2.28)
0.32
(1.92)
16.7
(100)
Soil micronutrients also play an important role in plant growth and can act as limiting
nutrients. Soil micronutrient analysis can be employed as a diagnostic tool for
predicting the possibility of deficiency of a nutrient and the profitability of its
application. For this it is necessary to fix the critical limits. The critical limit of a micro
nutrient is that content of extractable nutrient at or below which plantation practised
on it will produce a positive response to its application. Copper and Zinc is high in all
the tested soil samples. Iron is above the critical limits in all the soils samples. Since
in the study area, the level of some micronutrients are above the critical limits and
thus are in available amount and may prove helpful to plant growth. However it must
be noted that very high concentrations of one or more micronutrients may be
detrimental to plant growth and soil fertility may be adversely affected.
Table 4.6e: Available Micronutrients
Micro Nutrient
Iron (as Fe)
Copper (as Cu)
Zinc (Zn)
Manganese (Mn)
Iron
Results
S3
S4
S5
S6
0.3
0.41
0.4
0.32
0.57 0.61
0.64
0.51
5.5
5.7
5.9
4.8
2.5
2.7
3.4
3.8
Critical Limits (mg/kg)
4.5 6.0
Copper
0.20 0.66
S1
0.48
0.61
4.9
2.4
S2
0.31
0.52
5.6
2.7
S7
0.37
0.42
4.3
3.5
S8
0.31
0.52
4.6
2.9
Zn
S9
0.41
0.49
5.1
3.6
0.50 0.65
Page 131
Chapter 4
S10
0.47
0.58
4.8
2.5
4.2.6
Ecological Features
Objectives of the study
The present study was undertaken with the following objectives:
To assess the nature and distribution of vegetation in and around the project
site within the study area;
To assess the type of faunal species within the study area;
To assess the biodiversity of natural system present in the study area;
To ascertain migratory routes of fauna and possibility of breeding grounds
within the study area;
To assess the trophic status of the water bodies present in the study area.
Methodology of the Ecology Study
The study area taken for the study is 10 km radius with the project site as center. The
different methods adopted were as follows:
Inventorisation of flora / fauna: The list of Flora and Fauna found in the Forest
Division (Fatehabad) was collected from the Working Plan of the division for
reference. The list of flora and fauna found in the region was prepared by
conducting field survey and by discussions with concerned Forest Department
personnel using the list available in the Working Plan as a base.
Generation of primary data through systematic ecological studies: The phytosociology of the vegetation (covering frequency, density, abundance and
species diversity) in the forest areas falling in the study area was to be
determined by conducting field studies in selected areas (by laying suitable
sizes of quadrat). Since there are no forests in the study area, only
inventorisation of flora and fauna was done.
Discussion with local people so as to elicit information about local plant,
animals and their uses and Gathering data for ethnobiology.
The present study is based on field studies conducted during winter season
September to November 2011. The study area falls under the category of tropical
desert thorn and comprise predominantly of xerophytes. The area is sparsely
populated and is almost plain. The study area contains plantations around villages.
There is no wildlife and bird sanctuary within the study area. The biotic environment
can be described under following heads:
1.
2.
Project Site
Study Area: The study area can further be described as per the type of land use.
i) Agricultural land
ii) Plantations around Human Settlements
iii) Waste land
iv) Faunal and avi-fauna
v) Water Bodies
Project Site
The project site as of now is barren or agricultural land. The waste land is without any
vegetation and only sparsely scattered plants of Leonotis sp., Lantana sp., Calotropis
spp, Croton sp., Zyziphus sp., Xanthium Straumarium, etc are growing. There is no
forest land involved within the project site. The project area is predominantly double
crop agriculture land. The details of Rabi and Kharif crops, cultivation area along with
yield per ha is given in Table 4.7a.
Page 132
Chapter 4
Crop
Rabi
Wheat
Gram
Mustard
Kharif
Bajra
Cotton
Paddy
Area (ha)
Yield Kg/ha)
463.4
4.76
32.80
4920
980
1680
307.8
154
39.2
3040
973
3020
In between the agricultural fields, at the bund of the plots trees have been planted in
scattered manner. There are about 1027 Eucalyptus spp trees growing in the project
site, out of which the plant area located in the central part of the project area contains
575 trees.
Study Area
The study area is almost plain in topography. The plain areas are best utilized for
cultivation during kharif and rabi seasons. Tree species found in cultivated fields,
waste lands and habitations are Jand, Rohera, Khairi, Beri, Reru, Jal Or Van, Barh,
Peepal, Mesquite or Pahari Kikar, Kachnar, Amaltas, Lasura, Imli, Banna, etc.
Shisham, Kikar, Siris, Neem, Bakain Gultmohar. Parkinsonia Eucalyptus, etc. have
been planted along rail, road and canal strips and in other private areas. Eucalyptus
is also planted in agricultural and under farm forestry scheme. The Jand, Farash,
Khairi, Castor, kana and Ruhera have been planted to check soil erosion by high
velocity winds.
Common shrubs found are Hins, Bansa, Panwar, Babool, Karir, Phoa, Khip and Ak.
Medicinal herbs found in the district are Bansa, Indirain, Asgandha, Glo, Kharuthi,
Bhakhra, Dhatura, etc. Their collection becomes uneconomical because these are
available in scattered form.
The important grasses found in the district are Anjan, Dhamang, Dub, Kana and
Dabh. Anjan, Dhaman and Dub which are palatable fodder grasses are dwindling on
account of uncontrolled grazing. The grasses in waste, lands are poor in quality and
quantity. The plant species commonly found in the study area is given in Table 4.7b.
The authenticated list of flora and fauna found in the study area is given in Annexure
IVC.
Table 4.7b: List of Plants Growing in Study Area
SN.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Common
Names
Babool
Reru
Kikar
Khairi
Bansa
Unchti
Pahari Neem
Siris
Kala Siris
Safed Siris
Botanical Names
Family
Habbit
Remarks
Acacia jacquemontii
Acacia leucophloea
Acacia nilotica
Acacia senegal
Adhatoda Vasica
Ageratum conyzoides
Ailanthus excelsa
Albizia lebbeck
Albiziz odoratissima
Albizzia procera
Fabaceae
Mimosaceae
Mimosaceae
Mimosaceae
Acanthaceae
Asteraceae
Simaroubaceae
Mimosaceae
Mimosaceae
Mimosaceae
Shrubs
Trees
Trees
Trees
Herbs
Herbs
Trees
Trees
Trees
Trees
Medicinal
Medicinal
Page 133
Chapter 4
SN.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Common
Names
Dhinkwar
Gwarpatha
Chattin
Kalmegh
Sita Phal
Kadamb
Brhamadandi
Shatawar
Neem
Safed Kachnar
Semal
Dhak
Phoa
Botanical Names
Family
Habbit
Remarks
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
Ak
Bhang
Karir
Karaunda
Hins
Amaltas
Panwar
Panwar
Sadabahar
Anjan
Dhamanq
Indirain
Neebu
Lasura
Chota Lasora
Banna
Amarbel
Aloe barbeadensis
Aloe vera
Alstonia scholaris
Andrographis paniculata
Annona squamosa
Anthocephalus cadamba
Argemone maxicana
Asparagus racemosus
Azadirachta indica
Bauhinia verigata
Bombax ceiba
Butea monosperma
Calligonum
polygonoides
Calotropis procera
Cannabis sativa
Capparis decidua
Carissa carandus
Carissa spinarum
Cassia fistula
Cassia occidentalis
Cassia tora
Catharanthus roseus
Cenchrus ciliaris
Cenchrus setigerus
Citrullus colocynthis
Citrus medica
Cordia dichotoma
Cordia myxa
Crataeva adansonii
Cuscuta reflexa
Xanthorrhoeaceae
Xanthorrhoeaceae
Apocynaceae
Acanthaceae
Annonaceae
Rubiaceae
Papaveraceae
Asparagaceae
Meliaceae
Caesalpiniaceae
Malvaceae
Fabaceae
Polygonaceae
Shrubs
Shrubs
Trees
Herbs
Shrubs
Trees
Shrubs
Shrubs
Trees
Trees
Trees
Trees
Shrubs
Medicinal
Medicinal
Asclepiadaceae
Cannabaceae
Capparaceae
Apocynaceae
Apocynaceae
Caesalpiniaceae
Fabaceae
Caesalpiniaceae
Apocynacae
Poaceae
Poaceae
Cucurbitaceae
Rutaceae
Boraginaceae
Boraginaceae
Capparaceae
Convolvulaceae
Medicinal
Medicinal
Poaceae
Cyperaceae
Papilionaceae
Solanaceae
Caesalpiniaceae
Poaceae
Solanaceae
Verbenaceae
Myrtaceae
Moraceae
Moraceae
Moraceae
Malvaceae
Asclepiadoideae
Fabaceae
Meliaceae
Fabaceae
Moringaceae
Moraceae
Musaceae
Shrubs
Herbs
Shrubs
Shrubs
Shrubs
Trees
Shrubs
Shrubs
Herbs
Grasses
Grasses
Herbs
Shrubs
Trees
Trees
Trees
Parasitic
Plant
Grasses
Grasses
Trees
Herbs
Trees
Grasses
Shrubs
Shrubs
Trees
Trees
Trees
Trees
Shrubs
Shrubs
Trees
Trees
Herbs
Trees
Trees
Shrubs
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
Dub
Motha
Shisham
Dhatura
Gulmohar
Dabh
Kala Dhatura
Duranta
Eucalyptus
Barh
Gular
Peepal
Gudhal
Khip
Subabool
Bakain
Lajvanti
Saijan
Shahtut
Kela
Cynodon dactylon
Cyperus scariosus
Dalbergia sissoo
Datura stramonium
Delonix regia
Desmostachya bipinnata
Dhatura metal
Duranta repens
Eucalyptus hybrid
Ficus benghalensis
Ficus glomerata
Ficus religiosa
Hibiscus rosa-sinensis
Leptadenia pyrotechnica
Leucaena leucocephala
Melia azedarach
Mimosa pudica
Moringa oleifera
Morus indica
Musa sapientum
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Medicinal
Page 134
Chapter 4
SN.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
92.
Common
Names
Kaneer
Harsingar
Kali Tulsi
Papeeta
Parkinsonia
Druping Ashok
Popular
Jand
Prosopis
Mesquite or
pahari kikar
Amrud
Anar
Castor
Arand
Kana
Jal or van
Sita ashok
Kharuthi
Makao
Jamun
Imli
Farash
Rohera
Teak
Arjun
Pili Kaneer
Glo
Bhakhra
Asgandha
Beri
Mallah
Botanical Names
Family
Habbit
Nerium odorum
Nyctanthes arbor-tristis
Oscimum basilicum
Papaya coorge
Parkinsonia aculeata
Polyalthia longifolia
Populus sp.
Prosopis cineraria
Prosopis juliflora
Prosopis juliflora
Apocynaceae
Oleaceae
Lamiaceae
Caricaceae
Caesalpiniaceae
Annonaceae
Saliceae
Mimosaceae
Mimosaceae
Mimosaceae
Trees
Trees
Herbs
Shrubs
Trees
Shrubs
Trees
Trees
Shrubs
Trees
Psidium guajava
Punica granatum
Ricinus communis
Ricinus communis
Saccharum bengalense
Salvadora oleoides
Saraca indica
Sida acuta
Solanum nigrum
Syzygium cumini
Tamarindus indica
Tamarix articulata
Tecomella undulata
Tectona grandis
Terminalia arjuna
Thevetia peruviana
Tinospora cordifolia
Tribulus terrestris
Withania somnifera
Ziziphus mauritiana
Ziziphus nummularia
Myrtaceae
Punicaceae
Euphorbiaceae
Euphorbiaceae
Poaceae
Salvadoraceae
Leguminosae
Malvaceae
Solanaceae
Myrtaceae
Caesalpiniaceae
Tamariscineae
Bignoniaceae
Verbenaceae
Combretaceae
Apocynaceae
Menispermaceae
Zygophyllaceae
Solanaceae
Rhamnaceae
Rhamnaceae
Shrubs
Shrubs
Shrubs
Shrubs
Grasses
Trees
Trees
Herbs
Herbs
Trees
Trees
Trees
Trees
Trees
Trees
Shrubs
Herbs
Herbs
Herbs
Trees
Shrubs
Remarks
Medicinal
Medicinal
Medicinal
Medicinal
Saline soil
Medicinal
Medicinal
Medicinal
The ecological features of the study area can be described under following heads:
i)
Agricultural land
The study area falls under agro-climatic zone Trans-Gangetic Plains Region
(Planning Comission). The climate of the region is arid to semi arid (Koppen
Classification) - characterised by dryness and extremes of temperature and scanty
rainfall. It is very hot in summer and very cold during winters. Temperature ranges
from -1 to 48 degree Celsius. Annual rain fall is 373 mm. Topography of the district is
plain and sand dunes. Soils are sandy, sandy loam and clay with pH ranging from 7.5
to 9.00.
Paddy-wheat and cotton-wheat is the main crop rotation followed in the region. The
major crops grown are Wheat, Cotton, Paddy, Guar, Sugarcane, Bajra and Gram.
The other crops grown are oilseeds and pulses. Buffalo is the main milk animal
followed by cow, sheep and goat. Horticultural and vegetable crops are cultivated in
scattered form meant for home consumption. The region is gaining momentum to
produce Kinnow for domestic and international markets. Agro-forestry trees like Jandi
2012 MECON Limited. All rights reserved
Page 135
Chapter 4
is a part and parcel of farming system since time memorial. District Fatehabad is
having nearly 92 percent of its area under irrigation by both the canal as well as the
tube wells. The crop productivity in the area is given in Table 4.7c.
Table 4.7c : Average Productivity of Crops in the Region
SN.
1
2
1
2
3
4
5
6
Productivity (q/ha.)
43.54
76.04
46.46
37.15
23.57.
12.65
14.73
7.63
Scientific Name
Albezzia lebbeck
Annona squamosa
Azadirchta indica
Bougainvellea spectabilis
Carica papaya
Citrus lemon
Delonix regia
Eucalyptus hybrid
Ficus bengalensis
Ficus religiosa
Mangifera indica
Moringa oleifera
Musa sapientum
Pongamia pinnata
Tamarindus indica
Zyziphus sp.
Embelica officinalis
Psidium guajava
Polyalthia longifolia
Ricinus communis
Common Name
Siris
Sita Phal
Neem
Bougainvellea
Papita
Nimbu
Gulmohar
Eucalyptus
Bargad
Peepal
Mango
Saijan
Kela
Karanj
Imli
Ber
Aonla / Amloki
Amrud
Ashok
Rendi
Page 136
Chapter 4
Scientific Name
Antilope cervicapra
Boselaphus tragocamelus
Canis aureus
Felis chaus
Funambulus pennanti
Gazella gazella
Herpestres edwardsii
Hystrix indica
Lepus nigricollis ruficaudatus
Macaca mulatta
Mus booduga
Mus musculus
Presbytis entellus
Rattus rattus
Rhesus macaque
Scotophilus heathi
I
III
II
II
IV
I
II
IV
IV
II
V
V
II
V
II
V
Calotes versicolor
Mabuya macularia
Naja naja
Plyas mucosus
Rana tigrana
Typhlops parrectus
Uromastrix hardwickii
Vipera russelii
II
II
IV
IV
II
II
Bufo bufo
Bufo melanostictus
Geoclemys hamitloni
Kachuga dhongoka
Rana breviceps
Rana limnocharis
Rana tigrina
I
I
IV
IV
IV
Table 4.7f: List of Common Birds and their Conservation Status in the Study Area
SN
1
2
3
5
6
Common Name
Scientific Name
Jungle Myna
Common Mynah
Small blue kingfisher
Cattle Egret
Common crow pheasant
Chapter 4
SN
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Common Name
Scientific Name
Ceryle rudis
Columba livia
Copsychus saularis
Coracias benghalensis
Corvus macrorhynchos
Corvus splendens
Coturnix coturnix
Dicrurus adsimilis
Dinopium benghalense
Estrilda amandava
Eudynamis scolopacea
Francolinus francolinus
Gallus gallus
Grus antigone
Halcyon smyrnensis
Himantopus himantopus
Lonchura punctulata
Megalaima haemacephala
Megalaima zeylanica
Melophus lathami
Merops orientalis
Milvus migrans
Motacilla maderaspatensis
Mycteria leucocephala
Nectarinia asiatica
Oriolus oriolus
Orthotomus sutorius
Passer domesticus
Pavo cristatus
Ploceus philiphinus
Psittacula eupatria
Psittacula krameri
Pycnonotus cafer
Pycnonotus leucotis
Streptopelia senganis
Treron phoenicoptera
Turdoides caudatus
Upupa epops
Vanellus spp
Due to biotic pressure in the region and near the project site, the only animals found
are few rodents, reptiles and birds.
vi)
Water Bodies
Phytoplanktons
So as to have the baseline status of the planktons (phyto and zoo) present in the lotic
(Bhakra Main Canal) water bodies in the study area, plankton density was
determined at the two locations. As there are no industries in the study area and the
human habitation is sparse, the water bodies on physical appearance seem to be
Page 138
Chapter 4
oligo to meso trophic in nutrient status. The planktons present in the water bodies
are given in Table 4.7g.
Phytoplankton groups as observed at are members of basillariophyceae (diatoms),
chlorophyceae, Dinophyceae, myxophyceae and euglenophyceae. About 15 species
of phytoplankton from Bhakra Canal were observed. The average density of
phytoplankton group was 28 organisms / ml. Dominance of members of
Bacillariophyceae members and least representation of euglenophyceae members
indicated the oligotrophic status of the water body. The highest percentage was
Ceratium sp, Ankistrodesmus falcatus and Anabeana sp. and the lowest percentage
was Euglena sp. was observed during study period.
Percentage composition of zooplankton species varied among different species.
Among the zooplankton group, Cyclops (Copepods) and Brachionous sp (Rotifer)
showed highest percentage composition.
Table 4.7g: Plankton Abundance in Bhakra Canal
Plankton
Phytoplankton
Achnanthes sp.
Ankistrodesmus sp
Ceratium sp
Euglena sp.
Melosira sp.
Microcystis sp.
Navicula sp.
Nitzschia sp.
Oscilaltoria sp.
Pediastrum sp.
Pinnularia sp.
Pleurosigma sp.
Scenedesmus sp
Spirulina sp.
Volvox sp.
Phyto-plankton density (nos./ml)
Zooplankton
Arcella sp.
Keratella sp.
Asplancha sp.
Brachonus sp.
Daphnia sp.
Cyclops sp.
Cypris sp.
Zoo-plankton density (nos./ml)
Nos. / ml
% Composition
1
4
5
1
1
1
1
1
2
2
1
1
3
1
3
28
3.6
14.3
17.9
3.6
3.6
3.6
3.6
3.6
7.1
7.1
3.6
3.6
10.7
3.6
10.7
100
1
1
1
2
1
3
1
10
10
10
10
20
10
30
10
100
Hydrophytes
The hydrphytes growing along the water bodies are Hydrilla verticellata Aponogeton
sp., Potamogeton sp., Vallisneria spirals, and Nymphaea sp., etc.
Page 139
Chapter 4
Fishes
The common fishes found in the area are Labeo rohita, Catla catla, Cirrhina spp,
Wallago attu, etc. The fishes found in the study area are given in Table 4.7h. There
is no organized fishing activity within study area.
.
Table 4.7h: Fishes found in the Study Area
SN
1
2
3
4
5
6
7
8
9
10
11
12
13
4.2.7
Common Name
Parri
Katla
Mrigal
Chunni
Bata
Siriha
Rohu
Magur
Singhara
Ghally
Mallee
Dolla
Curd
Scientific Name
Notopterus notopterus
Catla catla
Cirrhina mrigala
Cirrhina reba
Labeo bata
Labeo gonius
Labeo rohita
Clarias batrachus
Mystys seenghala
Ompok bimaculatus
Wallago attu
Channa punctatus
Channa striatus
4.3
4.3.1
FOR
Cosmic sources and from natural radioactivity namely U, Th, 40K and their
daughter products.
Those originated from fall out radio-nuclides (137Cs, 90Sr) atmospheric nuclear
tests conducted in western countries during 1960s.
Page 140
Chapter 4
The regulatory limits for radioactive substances are specified not directly in terms of
the measured quantities such as the concentration of radio-nuclides in the
environment or the radiation levels but in terms of the consequent exposure to
radiation. Exposure / dose provide a measure of energy imparted by the radiation
and the resulting biological effects on living things. Given the basic measurements
mentioned above, established procedures can be used to deduce the radiation dose
received by persons. The procedures call for supplementary data such as (a) the
dietary patterns of the population groups living in the surroundings (b) transfer factors
of radioactivity among various elements of the exposure pathways and (c) dose
conversion factors. While data on dietary pattern is site-specific, recommended
standard values are made use of for transfer factors and dose conversion factors.
4.3.2
Occupational
20 mSv/year average over
defined periods of five years
Members of Public
1 mSv/year
Equivalent dose in
(a) Eye Lens
150 mSv/year
15 mSv/year
(b) Skin
500 mSv/year
50 mSv/year
(c) Hands and feet
500 mSv/year
--The limits specified are referring to radiation exposures over and above those received from
natural and medical sources.
When several nuclear facilities are located in a single site, the combined releases of
radio-nuclides by all the facilities should be such that the public exposure shall not
exceed the dose limit of 1 mSv in a year. Compliance with the regulatory requirement
is ensured by an apportionment of the dose limit among the different plants. The
apportionment is done by AERB based on technical considerations.
This practice of specifying the regulatory limits for radiation in terms of a single entity
(i.e. dose) is in contrast to the regulation of conventional pollutants where limits are
specified individually for each pollutant and environmental matrix. While the ultimate
regulatory criterion is the radiation dose, its practical implementation calls for
specification of discharge limits for each kind of anticipated radionuclide. This is done
by subdividing the apportioned dose limit among different nuclides and then
converting into corresponding dose (radioactivity) values by appropriate means.
Unlike the dose limits (Table 4.8a), these derived limits are specific to the plant and
the site.
Page 141
Chapter 4
4.3.3
SN Directions Sector
1
2
3
4
5
6
7
8
9
N
NNE
NE
ENE
E
ESE
SE
SSE
S
A
B
C
D
E
F
G
H
I
Page 142
Chapter 4
10
SSW
J
11
SW
K
12
WSW
L
13
W
M
14
WNW
N
15
NW
O
16
NNW
P
Total No of villages
The terrestrial and aquatic sampling locations for radiological survey are given in
Table 4.8c and Table 4.8d respectively. Different types of samples were collected
from the terrestrial and aquatic environs of the 30km study area covering, canal
water, soil, cereals, pulses and vegetation samples. Table 4.8e gives the number
and types of samples collected from various locations. The levels of various radionuclides of natural (238U, 232Th, 40K) and fallout (137Cs and 90Sr) origin were
determined.
Table 4.8c: Terrestrial Sampling Locations
SN.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Locations
Kumharia
Sabarwas
Kajalheri
Kirmara
Badopal
Agroha
Kuleri
Nangthala
Landheri
Kanoh
Dhani Majara
Bhuna
Nahla
Sarangpur
Bhana
Fatehabad
Mandi Adampur
Barwal
Hisar
Siswal
Badon/ Bahbalpur
Zones ( km)
1.6
1.6
1.6 -5.0
5.0 10.0
5.0 10.0
5.0 10.0
5.0 10.0
10-15
10-15
10-15
10-15
10-15
10-15
10-15
10-15
15-30
15-30
15-30
15-30
15-30
15-30
Latitude/Longitude
N 29.40484,E 075.61498
N 29.40187,E 075.62905
N 29.44599,E 075.60875
N 29.38327,E 075.69610
N 291640.6",E0753810.6"
N292151.5E0753022.4
N 29.37080,E 075.66758
N 29.21413,E 075.53508
N 29.18228,E 075.39455
-N 2929105,E 07532434
--N 292038.7",E0753220.5"
N 292155.1",E0753021.0"
N293023.8",E0752730.5"
N 291653.2",E0752830.9"
N 29.21444,E 075.53527
N291018.77 E0754407.7
N 292109.5",E0755313.7"
N 29.17244,E 075.48570
Sector
K L
I
N
F
M
I
H
G
H
F
O
B
D
K
L
N
K
F
H
J
G
Locations
Kajalheri
Kumharia
Between 1 & 2
Bhoda Hushnak
Kohli & Kalirawan
Khasa Mahajanan
Faransi
Ladvi
Baijalpur
Zones ( km)
2
2
5-10
10-15
10-15
10-15
10-15
>15
10-15
Latitude/Longitude
N 29.44599,E 075.60875
N 29.40484,E 075.61498
N 29.41760,E 075.59850
N 29.35190 ,E 075.60155
------
Sector
N
L
N-L
T
K-J
J
J
J
C
Page 143
Chapter 4
SN.
10
11
12
13
Locations
Diversion Point of Canal
Converging point of canal
Within 5 km
Within 5 km
Zones ( km)
5
5
<5
<5
Latitude/Longitude
-----
Sector
B
O
O
M
Locations
5
28
No. of Samples
5
265
3
1
3
1
14
6
52
14
6
289
Page 144
Chapter 4
W
NN
NN
E
SE
SW
ESE
W
WS
WN
E
EN
N
W
NE
E
SS
SS
W
Fig. 4.5a : Base-map Showing Project Site and Radiological Survey Study Area
Divided in to Different Zones and Sectors.
Page 145
Chapter 4
Terrestrial
Sampling
Points
Fig. 4.5b : Radiological Survey Study Area Showing Terrestrial Sampling Locations
2012 MECON Limited. All rights reserved
Page 146
Chapter 4
Aquatic
Sampling
Points
N
Fig. 4.5c : Radiological Survey Study Area Showing Aquatic Sampling Locations
Page 147
Chapter 4
Village
Kumharia (10)
Kajalheri (10)
Gorakhpur(10)
Siwani (10)
Kirmara (10)
Kuleri (10)
Agroha (10)
Badopal (10)
Talwandi (10)
Juglan (10)
Bahbalpur (10)
Badopal (8)
Bugana (8)
Sulakhani (8)
Dhansu (10)
Hisar (10)
Sector/ Zone
K/L (1.6-5 km)
N (1.6-5.0 km)
C (1.6-5.0 km)
E (1.6-5.0 km)
F( 5-10 km)
H ( 5 -10 km)
I ( 5 10 km)
M (5-10 km)
H (15 30 km)
G (15-30 km)
G (15-30 km)
G (15-30 km)
G (15-30 km)
G (15-30 km)
G (15-30 km)
H (15-30 km)
Latitude/Longitude
Range Gy/h Mean Gy/h
N 29.40484,E 075.61498
0.087-0.17
0.12
N 29.44599,E 075.60875
0.087-0.148
0.12
N 29.45767,E 075.65127
0.078-0.12
0.11
Not measured
0.096-0.13
0.11
N 29.38327,E 075.69610
0.11-0.17
0.14
N 29.37080,E 075.66758
0.10-0.18
0.14
N292151.5E0753022.4
0.11-0.18
0.14
N 291640.6",E0753810.6"
0.087-0.17
0.13
Not measured
0.07-0.16
0.12
Not measured
0.05-0.13
0.09
N 29.16534,E 075.48155
0.061-0.15
0.11
N 291640.6",E0753810.6"
0.061-0.15
0.12
Not measured
0.087-0.11
0.10
Not measured
0.078-0.14
0.10
Not measured
0.07-0.12
0.10
N291018.77 E0754407.7
0.12-0.22
0.16
Page 148
Chapter 4
Table 4.8i: Radiation Dose Rate Measurements using TLD January to March 2011
Location
Control
Hisar
Chikanwas
Asrawan
Fransi
Badopal
Kajalheri
Kumharia
Bhoda Hosank
Kuleri
Sabarwas
Gorakhpur
Nehla
Kirmara
Nangthala
Landheri
Fatehabad
Ratla
Bhutan Kalan
Chandrawal
Jandli Kalan
Mochiwali
Barawal
Adampur
Bhattu Kalan
Dhand
Bahana
Khajuri
Agroha
Thaska
Kanoh
Latitude/Longitude
---N291018.77 E0754407.7
---N 291640.6",E0753810.6"
N 29.44599,E 075.60875
N 29.40484,E 075.61498
N 29.35190 ,E 075.60155
N 29.37080,E 075.66758
N 29.40187,E 075.62905
N 29.45767,E 075.65127
-N 29.38327,E 075.69610
N 29.21413,E 075.53508
N 29.18228,E 075.39455
N293113.8",E0752616.8"
-----N 29.21444,E 075.53527
N 291653.2",E0752830.9"
--N 292155.1",E0753021.0"
-N292151.5E0753022.4
---
Days
Dose Dose Rate Dose Dose Rate
Exposed Received (Gy/90 Received (Gy/90
(Gy) days)
(Gy) days)
Indoor
Outdoor
97
424
---45714
93
670
307
69246
31413
93
463
428
47850
44226
93
475
275
49146
28518
93
305
216
3152.0
22422
93
461
353
47728
36416
93
438
383
45357
39532
93
500
51626
3298.0 318
93
414
287
42725
29715
92
545
512
55722
52324
92
353
4092.0 400
36140
92
446
45535
3016.0 295
92
513
429
52435
43928
92
446
45634
3171.0 310
92
436
268
4466.0
27425
92
319
4077.0 398
32620
91
560
422
56614
42712
91
421
454
42620
45964
91
532
299
53824
30216
91
432
284
43741
28729
91
448
45321
2497.0 247
91
4182.0 414
2674.0 264
92
520
6094.0 596
53251
90
510
51018
2746.0 271
90
535
513
43560
51929
90
340
387
43055
39275
90
517
299
51741
30226
90
397
330
39747
33413
90
431
362
43152
36645
89
438
359
43324
35521
89
496
349
49145
34572
4.3.3.2 Estimation of Pre-operational Base Line Levels of Natural and Fallout Radio-nuclides
in Environmental Samples
For base line survey, to estimate the levels of various radio-nuclides of natural (238U, 232Th,
40
K) and fallout (137Cs and 90Sr) origin, different types of environmental samples were
collected from the terrestrial and aquatic environs of the site up to a radial distance of
30km. The details of terrestrial and aquatic sampling locations are given in Table 4.8d and
4.8e, respectively. Figure 4.5b and 4.5c show the terrestrial and aquatic sampling
locations respectively. Canal water, soil, cereals, pulses and vegetation samples were
Page 149
Chapter 4
collected around the site. Table 4.8f gives the number and types of samples collected from
various locations.
Methodology
The collected soil and biological samples were processed at site and were sent to Health
Physics Division, BARC for gamma spectrometry and radiochemical analysis. Gross alpha
and gross beta measurements were carried out at site.
Soil samples were dried and sieved and the fraction containing less than 180 m size were
packed in a standard geometry for gamma spectrometry and stored for one month to attain
secular equilibrium1, before analysis.
Biological samples were oven dried, powdered and packed in standard geometry(1).
Biological samples were ashed as per the standard procedure1 for the estimation 90Sr.
The gamma spectrometric analysis1 of processed soil and biological samples and the
analysis of levels of 238U, 232Th, 40K and 228Ra, were carried out at Health Physics Division,
BARC, Mumbai. The samples were counted by gamma spectrometry with HPGe detector
for the estimation of 238U, 232Th, 226Ra and 40K. 137Cs was estimated gamma spectrometrically using HPGe detector (50% RE) system.
90
Location
1
2
Badopal
Bhana
Latitude/longitude
N292458.3 E0753300.4
N292211.8 E0752959.0
Gross Beta
Activity(Bq/m3)
BDL
BDL
Gross Alpha
Activity, (Bq/m3)
0.0003 0.00009
0.0030 0.0004
1 Analytical Procedure Manual, Health Physics Division, BARC/HPD/1992/002, Bhabha Atomic Research
Centre, Mumbai, India, 1992.
2012 MECON Limited. All rights reserved
Page 150
Chapter 4
SN.
Location
Latitude/longitude
Gross Beta
Activity(Bq/m3)
3
Sarangpur N292054.1 E0753146.6
0.0170.005
4
Hisar
N291018.77 E0754407.7
BDL
5
Agroha
N292151.5 E0753022.4
0.0110.005
3
Minimum Detection Limit (MDL) for Gross Beta = = 0.01 Bq/m
3
MDL for Gross Alpha =0.0002 Bq/m
Gross Alpha
Activity, (Bq/m3)
0.0002 0.00009
0.0006 0.0001
0.0005 0.0001
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Location
Distance Sector
(km)
Latitude / Longitude
Kajalheri (8)
1.0-5.0
N
N 29.44599,E 075.60875
Kumharia(25)
1.0
K-L
N 29.40484,E 075.61498
Sabarwas(5)
1.0
I
N 29.40187,E 075.62905
Gorakhpur(13)
1.0-5.0
C
N 29.45767,E 075.65127
Between 1 & 2(6)
5-10
N-L
N 29.41760,E 075.59850
Siswal (4)
15-30
J
Bhoda Hushnak (8) 10-15
T
N 29.35190 ,E 075.60155
Adampur(5)
15-30
K
-Bhuna(2)
10-15
B
-Sarangpur(5)
10-15
K
N292054.1 E0753146.6
Jagan(3)
-Badopal(6)
5-10
M
-Muhamadpur(4)
N 2927284,E 07533454
Dhani Majra(5)
10-15
O
N 2929105,E 07532434
Fatehabad(10)
15-30
N
-Prescribed Limit for packaged drinking water by BIS (Ref)
Detection Limit for Gross Alpha in water
Detection Limit for Gross Beta in water
Page 151
Chapter 4
Table 4.8m shows the 137Cs and 90Sr concentrations in soil samples from the study area of
the proposed project. The levels of 137Cs and 90Sr are comparable to the levels reported
elsewhere(2).
Table 4.8l : Natural Radioactivity Content in Soil Samples
Location
Agroha
Gorakhpur
Kirmara
Kumharia
Kuleri
Kirmara
Kuleri
Agroha
Siswal -1
Siswal -2
Badon
Kirmara
Kuleri
Bhana
Distance
(km)
5-10
1.6-5
5-10
1.6
5-10
5-10
5-10
5 -10
15-30
15-30
15-30
5-10
5 -10
5-10
Sector
226
Ra
238
232
Th
(Bq.kg dry)
26.61.5
41.7 1.5
18.41.1
32.61.1
11.50.9
20.20.9
15.81.0
30.71.0
45.12.0
83.82.1
14.90.9
26.10.9
49.33.6
97.53.6
61.55.0
103.75.1
50.03.8
89.33.4
49.53.3
83.03.2
70.816.2 118.713.8
53.73.5
91.73.6
49.33.6
97.53.6
27.12.4
90.72.4
40
-1
I
C
F
L
H
F
H
I
J
J
G
F
H
L
21.41.1
17.70.8
9.60.6
13.80.7
42.41.5
12.50.7
56.32.8
59.94.1
50.52.7
53.92.6
70.92.4
51.82.7
56.32.9
28.71.6
486.4 3.7
339.82.6
249.62.3
273.62.2
543.94.1
304.82.3
955.98.3
109112
771.87.5
798.27.4
1353 35
832.58.0
955.98.3
586.812.4
Distance (km)
1.6
1.6-5
5-10
5-10
5-10
5 -10
5-10
5-10
5-10
5-10
5 -10
15-30
15-30
15-30
Activity levels at
Kaiga(3)
(4)
Punjab
2 UNSCEAR 2000, Sources and effects of ionizing radiation, Report to General Assembly, with Scientific
Annexes, United Nation, 2000.
137
3 Karunakara N, Somashekarappa HM, Narayana Y, Avadhani DN, Mahesh HM, Siddappa K Cs
concentration in the environment of Kaiga of south west coast of India, Health Physics 2001 Aug; 81(2):14855.
2012 MECON Limited. All rights reserved
Page 152
Chapter 4
Location
1
2
3
4
5
6
7
8
9
10
Kumharia
Kajalheri
Kuleri
Agroha
Kirmara
Bhana
Siswal
Siswal
Badon
Badon
4.4
Distance
km
1.6
1.6-5.0
5-10
5-10
5-10
5-10
15-30
15-30
15-30
15-30
Sector
L
N
H
I
F
L
J
J
G
G
Biota
Samples
Grass
Bajra grain
Grass
Grass
Grass
Radish leaves
Amla fruit
Guava fruit
Guava leaves
Guava fruit
Cs-137
-1
(Bq.kg dry)
<0.17
<0.17
<0.17
<0.17
<0.17
<0.17
<0.17
<0.17
<0.17
<0.17
Sr-90
-1
(Bq.kg dry)
<1.0
<1.0
<1.0
<1.0
<1.0
NA
NA
NA
NA
NA
K-40
-1
(Bq.kg dry)
3.380.027
0.160.003
2.620.02
1.380.01
2.270.02
1.9 0.01
0.460.008
0.470.007
0.420.007
0.760.01
TRAFFIC DENSITY
In order to assess the impact of future traffic load (due to the proposed plant) on the
existing traffic infrastructure of proposed project site, the existing / baseline traffic density
on NH 10 and at road inlet locations of proposed site was studied. The existing traffic
density for different types of vehicles was counted at two locations during the study on a
particular day for 24 hours. The monitoring locations are as follows:
Tables 4.9a1 and 4.9a2 indicate the traffic density on NH 10 during weekends and
weekdays, respectively. There is not much difference in the traffic density between
weekends and week days. On weekends the traffic in all three categories is slightly more
than that on the weekdays. There to be conservative, all further analysis has been done on
the basis of traffic density on weekends. On weekends, the traffic density is highest for light
motor vehicles (5147/d), followed by heavy motor vehicles (1841/d), two wheelers (1930/d)
and there were no three wheelers. Total traffic density at this location is 14208.5 PCU per
day.
4 Ajaykumar et al. Distribution, enrichment and principal component analysis for possible sources of
naturally occurring and anthropogenic radionuclides in the agricultural soil of Punjab state, India. Radiation
Protection Dosimetry, 2011, pp. 1-11.
5 UNSCEAR 2000, Sources and effects of ionizing radiation, Report to General Assembly, with Scientific
Annexes, United Nation, 2000.
2012 MECON Limited. All rights reserved
Page 153
Chapter 4
Heavy Motor
Vehicles (HMV)
65
85
52
102
80
52
41
85
68
84
76
68
73
98
Page 154
Chapter 4
Time (Hrs.)
Traffic Volume (Vehicles Per Hour) w.r.t Hisar
15.06. 2011
Heavy Motor
Light Motor
Three
Two
Total Vehicles
(Wednesday)
Vehicles (HMV)
Vehicles (LMV)
Wheelers Wheelers (PCU)
798.5
14.00 - 14.59
105
292
91
488
740.5
15.00 - 15.59
88
284
101
473
814.5
16.00 - 16.59
86
332
117
535
797.5
17.00 - 17.59
70
342
149
561
872
18.00 - 18.59
80
369
157
606
845
19.00 - 19.59
105
296
172
573
480
20.00 - 20.59
53
194
60
307
360.5
21.00 - 21.59
55
122
25
202
336.5
22.00 - 22.59
60
97
22
179
290
23.00 - 23.59
52
88
4
144
Total Per Day
1783
4888
1909
8580
13635.5
Passenger Car Unit (PCU) : 3 for HMV, 1.5 for LMV; 0.5 for Two Wheelers
Tables 4.9b1 and 4.9b2 indicate the traffic density on road leading to project site from NH
10 on weekend and weekdays, respectively. There is not much difference in the traffic
density between weekends and week days. On weekends the traffic in all three categories
is slightly more than that on the weekdays. There to be conservative, all further analysis
has been done on the basis of traffic density on weekends. On weekends, the traffic
density is highest for two wheelers (452/d), followed by light motor vehicles (341/d) and
heavy vehicles (11/d). Total traffic density at this location is 766 per day. This road is
mostly used for the village transport from NH10.
Table 4.9b1: Traffic Density on Road leading to project site from NH 10 on Weekends
Time (Hrs.)
11.06. 2011
(Saturday)
24.00 - 00.59
01.00 - 01.59
02.00 - 02.59
03.00 - 03.59
04.00 - 04.59
05.00 - 05.59
06.00 - 06.59
07.00 - 07.59
08.00 - 08.59
09.00 - 09.59
10.00 - 10.59
11.00 - 11.59
12.00 - 12.59
13.00 - 13.59
14.00 - 14.59
15.00 - 15.59
16.00 - 16.59
17.00 - 17.59
18.00 - 18.59
4
3
1
0
1
5
3
5
21
26
41
26
22
15
8
18
18
14
11
0
0
1
0
3
4
18
14
37
37
35
21
36
28
21
22
21
20
36
4
3
2
0
4
9
21
19
58
63
76
47
58
43
29
40
39
34
47
6
4.5
2
0
3
15.5
13.5
17.5
53
63.5
82
49.5
51
36.5
22.5
44
37.5
34
34.5
Page 155
Chapter 4
Time (Hrs.)
11.06. 2011
(Saturday)
19.00 - 19.59
0
45
76
121
20.00 - 20.59
0
16
13
29
21.00 - 21.59
0
7
3
10
22.00 - 22.59
1
1
5
6
23.00 - 23.59
0
3
1
4
Total Per Day
11
314
452
766
Passenger Car Unit (PCU) : 3 for HMV, 1.5 for LMV; 0.5 for Two Wheelers
105.5
30.5
12
7
5
730
Table 4.9b2: Traffic Density on Road leading to project site from NH 10 on Weekdays
Time (Hrs.)
15.06. 2011
(Wednesday)
Page 156
Chapter 4
4.5
4.5.1
Introduction
The study area is located at the intersection of Northern Latitude 290 26 30 N and east
Longitude 750 37 56 E and can be located in the Survey of India Topo-sheet No. H43P10
and H43P11. The area falls under the seismic Zone-III in the Seismic Zoning Map of India
(IS:1893, 2002) The maximum Modified Mercalli (MM) intensity of seismic shaking
expected in the zone is VII, termed here as Moderate Damage Risk Zone.
The climate of the region can be classified into semi-arid and hot which is mainly dry
with very hot summer and cold winter except during monsoon season when moist air of
oceanic origin penetrates into the region. The hot weather season starts from mid
March to last week of the June followed by the south- west monsoon which lasts till
September. The transition period from September to November forms the postmonsoon season. The winter season starts in December and remains up to February.
Rainfall during as observed by IMD (Source: IMD website) during last five years from
2006 to 2011 in the districts falling in the study area is given in Table 4.10a.
The normal annual rainfall of Fatehabad district is 373 mm which falls over the area in
22 rainy days. The south west monsoon sets in from last week of June and withdraws
in end of September, contributes about 80% of annual rainfall. July and August are the
wettest months. Rest 20% rainfall is received during non-monsoon period in the wake
of western disturbances and thunder storms. Generally rainfall in the district increases
from southwest to northeast.
Normal Annual Rainfall
: 373 mm
Normal monsoon Rainfall
: 297 mm
Mean Maximum Temperature
: 41.6C(May June)
Mean Minimum Temperature
: 5.5 C(January)
Normal Rainy days
: 22
Annual Mean Wind Speed
: 1.25m/s
Maximum Wind Speed
: 1.95m/s
Table 4.10a: Rainfall (IMD data) During 2006-2011 in Districts Falling in the Study Area
Year
Jan
Feb
Mar
April
2006
0
2007
2008
0
2009
4.3
2010
0
Average 1.07
0
1.5
5
14
5.12
48.3
0.1
2.3
0
12.7
0
15.5
0
0
3.88
0
89.5
20.1
52.7
1.2
5.4
2006
2007
0.4
0
Rainfall in mm
May June July Aug
District : Fatehabad
45.8 54.5 75.3 21.7
76.6 50.3
26
25
168.8 32.7 169.7
0
3.9
60.2 11.3
0
0
133 68.7
17.7 60.76 70.3 59.48
District : Hisar
45.7 32.6 74.8 11.4
52.1
124
45.6 82.1
0
0
0
0.7
8
3
322.9
185.4
474.8
142.3
330.4
291.16
7.3
4.3
246.9
495.8
0
4
0
Page 157
Chapter 4
Year
Jan
2008
3.5
2009
7.8
2010
8
Average 3.94
4.5.2
Feb
2.4
8
3
20.6
Mar
0
3.8
2.4
15.8
April
11.9
12.8
0.4
6.34
Rainfall in mm
May June July
50.4 103.7 83.7
20.1 20.4 51.3
0.6
35.9 147.4
33.8 63.32 80.56
Aug
115.6
11.5
86.6
61.44
Physiography
The study area is located in the Indo-gangetic alluvial Plains. The area is an alluvial plain of
indo-gangetic basin. No perennial river flows through the district, however a seasonal river
i.e Ghaggar is flowing through Ratia and Jakhal. Bhakra and western Yamuna are two
main canals that irrigate most of the part of area.
The area is by and large flat and plain flat terrain is interrupted by the randomly located
sand dunes along the Ghaggar River, which are outside the study area. The regional
gradient of the area is from north to south west with an average gradient of 0.27m/km.
The area surrounding the proposed site is flat terrain with average elevation of about 211m.
The physio-graphy of the study area is shown in Drg. No. MEC/11/S2/Q6SY/02. The soil
of the region is sandy loam to loamy sands
.
4.5.3 Drainage
About 80% of the study area falls in Fatehabad district and the rest in Hisar district. The
two districts are alluvial plain of Indo-Gangetic basin with almost flat terrain interrupted by
randomly located sand dunes along the Ghaggar River. There is only a seasonal river
(Ghaggar), and no perennial river, flowing through the two districts. Bhakra and Western
Yamuna are two main canals which irrigate most part of these districts.
The study area being a flat terrain is conspicuous by absence of any well defined natural
drainage system. As per Haryana Space Application Centre (HARSAC, Hisar), there are no
natural drainage channels passing through project and township areas. At the project site,
general slope is away from canal to south direction. The drainage is of inland type and
the excess rainwater, accumulates in natural /artificial depressions. However, out of
study area in the northern part of the district, the Ghaggar River drains the area. The
river course falling in the area is very narrow and often causes floods when heavy
rainfall occurs in the catchment area.
4.5.4
Geological Features
The site area lies on the western part of Indo-gangetic alluvial plain on the Punjab side,
adjoining the Rajasthan shelf, separated underneath the alluvium, by the NW-SE trending
Lahore-Saharsa Ridge. The geological formations met within the region are Indo-Gangetic
alluvium consisting of Newer and older alluvium with a thin blanket of aeolian deposits. The
age of these formations range from upper-Pleistocene to Recent. Though the formations
were laid down from upper-Pleistocene to Recent age, they are conformable with each
other. Exploratory drilling in the area indicates that these Quaternary unconsolidated
Page 158
Chapter 4
sediments are underlain by hard rock formations of Achaean age comprising of Granites,
schists and gneisses. Bed rock is shallow in south western part of the district and thickness
of alluvium increases gradually towards northeast. The maximum thickness of alluvium so
far recorded in the boreholes drilled in Fatehabad district is 365.7m at Jhalnia (2903100
and 7503430), about 10km north of the project site.
The project site is located on alluvial soil made up of both older and newer alluvium with a
thickness estimated to be of the order of about 300m, below which hard rock formation of
the Lahore-Sahara Ridge is reported to occur.
Data from bore holes (up to 60 m depth) at the project site indicates that the substrata
consist of alternate layers of sandy silt/silty sand and silty clay/sandy clay (each layer being
of approx. 4m thickness) up to the entire depth of the bore holes. The strata at the depth of
the RB foundation level (17m) is silty clay in nature. N value at 17m depth is 40 and the N
value increases progressively to 609 at 58 m depth. While the sub-surface conditions at
this site are different from that at Narora, it may be possible to adopt at this site, foundation
of the type adopted at NAPP, with modifications as required by detailed studies, in view of
the reduced seismicity at the site.
4.5.5
Hydrogeology
As per bore hole data at site, the water table is 3 m below ground level in the month of July
(Source: site selection committee report). It is likely that the water table may rise to a higher
level during rainy seasons. Ground water movement is reported to be both West and WSW, nearly parallel to the canal flow. Hydraulic gradient is reported to be around 50-70
cms/km which is quite low, indicating poor transitivity of the sub-surface. This would be due
to the predominance of clay layers in the substrata. The ground water table as monitored in
the study area during summer season is given in Table 4.10b.
Table 4.10b: Ground Water Table of Well Investigated in the Study Area
Stn.
No.
H1
H2
H3
H4
H5
H6
H7
H8
H9
H 10
H 11
H 12
H 13
H14
H15
H16
Name
of
Village
Samani
Kirmara
Kirmara
Kanoh
Nehla
Nehla
Dahman
Baijalpur
Jandli kalan
Jandli Khurd
Jandli kalan
Badopal
Kumahria
Gorakhpur
Chaubara
Mochiwali
Reduced
level (m)
211
211
211
211
211
211
211
211
211
211
211
211
211
211
211
211
Water
Table
w.r.t M.S.L (m)
206.7
198.3
201.4
200.2
203.4
204.5
207.2
203.4
203.7
203.6
205.5
206.4
207.8
208.0
207.6
207.3
Page 159
Chapter 4
Stn.
No.
H17
H18
H19
Name
of
Village
Chandrawal
Bhuthan kalan
Dhangar
Reduced
level (m)
211
211
211
Water
Table
w.r.t M.S.L (m)
202.9
189.7
197.9
The depth of ground water level in the study area in Fatehabad District as observed by
Central Ground Water Board (CGWB) during pre-monsoon and post monsoon season is
given in Figures 4.6a and 4.6b. The observed water level (Table 4.10b) during summer
season in the study area during the present study matches with the ground water table
values of CGWB. In general it can be observed that the ground water table with the study
area is between 3 to 20m.
Page 160
Chapter 4
SI
Figure 4.6a: Depth of Ground Water Table Pre-Monsoon in the Study Area (CGWB, 2008)
Page 161
Chapter 4
Figure 4.6b: Depth of Ground Water Table Post-Monsoon in the Study Area (CGWB, 2008)
4.5.6
Seismo-tectonics
Page 162
Chapter 4
The site area lies in Seismic Zone III in the Seismic Zoning Map of India (IS:1893, 2002).
The site is situated on the ridge between the Bouguer gravity anomaly contours of -30 and
-40 m Gal, on a contour interval of -10m Gal. The highest value in the site area is greater
than - 20 m Gal. The important tectonic features around this site within a radius of 300 km
are as follows:
The important tectonic features to the north of alluvial plains in the Himalayan region are,
(a) Frontal Himalayan Thrust (FHT), (b) Main Boundary Thrust (MBT), and (c) Main Central
Thrust (MCT) at distances of about 190, 215 and 295 km respectively to the north-east of
the site. MBF and MCT run all along the 2400 km length of the Himalayas and are related
to Himalayan orogeny.
A NW-SE striking Sargoda-Lahore-Delhi ridge underlies the alluvium. In the Seismotectonic Atlas (GSI, 2000) the boundary of this ridge is demarcated for the portion northwest of Ferozpur but not to its south-east falling in Punjab-Haryana-Delhi Area. Some of
the features in the region are detailed below:
i.
Some transverse faults or tear faults have been identified along the northern fringe of
Indo-gangetic plain. Important among them are the Ropar Fault about 180 km to the
NNE and Ghaggar Fault about 170 km to the NE. Yamuna tear fault/Paonta fault is
about 210 km, ENE of the site. These tear faults generally displaces the HFT, MBT and
the Recent Alluvium and hence are reported to be younger and active during postPleistocene time.
ii. In the Seismo-tectonic Atlas (GSI, 2000) a lineament is shown to extend from Ropar
fault into the alluvial plain in NE-SW direction for about 260 km and it lies 80 km NW of
the site. The lineament passes over the buried Sargoda-Lahore-Delhi Ridge.
iii. The most significant subsurface tectonic feature to the SE of the site is the NE-SW
treading Delhi-Hardwar Ridge bound by parallel faults on either side. The western fault
and the eastern fault are at distances of about 95 km and 140 km from the site
respectively. These are not shown on Seismotectonic Atlas (GSI, 2000). However, one
subsurface fault trending NE-SW named as Mahendragarh-Dehradun fault running over
295 km is shown in the Atlas. It lies at a distance of 120 km from the site and is
obliquely disposed between the above said parallel faults.
iv. To the east of the subsurface Hardwar Ridge, the Sohna-Delhi Fault is associated with
a hot spring at a distance of 190 km from the site. Further east at a distance of about
255 km lies the ENE-WSW to EW treading Moradabad Fault beneath the alluvium in
the plains of Uttar Pradesh.
v. A minor lineament with MNE-SSW trend and 220 km length passes close to the site at
a distance of 25 km.
vi. As per the Seismo-tectonic Atlas (GSI, 2000) no significant tectonic feature is seen to
the west of the site within 300 km radius except those in the southwestern side of which
2012 MECON Limited. All rights reserved
Page 163
Chapter 4
Sardar Shahar fault that strikes NNE-WSW with a length of 270 km at a distance of 120
km is note worthy. Raisingh Nagar lineament, Tonk lineament, etc. are farther away
from site.
vii. No capable fault exists within 5 km .The site is engineer-able from this consideration.
4.6
LANDUSE PATTERN
Land-use pattern in the study area as shown in the satellite imagery (LISS III, March 2011)
is shown in Drg. No. MEC/11/S2/Q6SY/03 and given in Table 4.11a. The study area as
per the satellite imagery covers 17.76% built-up area, 75.11% agricultural land (including
horticultural plantations), 6.28 scrubs (non-forest area) covered area and 0.84% water
bodies.
Table 4.11a: Land Use Pattern of the Study Area
SN.
1
2
3
4
Type of Land-use
Built-up Land (settlements)
Agricultural Land
Crop Land
Plantations
Total
Scrubs
Water Bodies
Canal
Tanks
Total
Grand Total
Area in ha.
5591.51
Percent Landuse
17.76
9198.33
14453.48
29.21
45.90
75.11
6.28
1977.95
265
0.97
31487.24
0.84
0.00
0.00
100.00
In Haryana the classification of land have been done for assessment of land holding taxes,
by relying on classification of soil as an indirect indicator of measure of land productivity.
The land has been divided, under five classes I to V (based on broad soil classification(6)),
in to Abi, Chahi, Nehri, Barani, Banjar, Kallar, Thur, Sem, etc. Nehri is irrigated land is
placed under class I, while Banjar, Kallar, Thur and Sem come under Class V category.
Neri is the land where the irrigation source is canal, while Chahi, Tal, Barani are land where
canal is not the irrigation source. Tibba is undulated land with sand dunes and Gairmumkin is non-cultivable land belonging to Government allotted to the panchayat for
community activities. Based on the above land classification the village wise breakup of
land under acquisition for project and township are given in Table 4.11b.
The land use pattern of the project site is given in Table 4.11b. The power plant site is
predominantly double crop agriculture land. About 89% of the land being used for the
project and township is agricultural land and about 11% is waste land.
Table 4.11b: Land Use Pattern of the Project Site
Type of Land
Township (Ha)
Land-use
%
6 Dynamics of Agriculture Development, Vol. 3. : Policy Planning & Liberalisation. By K.S. Dhindsa & Anju
Sharma. Concept Publication Company. 2001.
2012 MECON Limited. All rights reserved
Total
Page 164
Chapter 4
4.7
Badopal
10.47
0
17.95
28.42
45.86
0.75
46.61
0
75.04
518.40
7.31
17.95
543.66
45.86
18.95
64.81
0
608.48
SOCIO-ECONOMIC FEATURES
The socio-economic feature of the study area is detailed in Chapter 8.
Page 165
Chapter 4
85
1
3
89
8
3
11
0
100
5.1
INTRODUCTION
In this chapter, the anticipated environmental impacts and the proposed mitigation
measures for the proposed Haryana Atomic Power Project (HAPP) have been
described.
Impact prediction is a way of mapping the environmental consequences of the
significant aspects of the proposed plant. The impact assessment will broadly cover the
following information and components:
-
The anticipated environmental impacts of the proposed plant are discussed below under
the following categories:
Impacts and mitigation measures due to project siting (location).
Impacts and mitigation measures due to project design.
Impacts and mitigation measures during construction.
Impacts and mitigation measures during operation.
Impacts and mitigation measures because of possible accidents.
5.2
Page 166
Chapter 5
abandoned canal is present. In the plant site of the project area, which falls in the centre
of the project site about 575 eucalyptus trees are standing.
In Haryana the classification of land have been done for assessment of land holding
taxes, by relying on classification of soil as an indirect indicator of measure of land
productivity. The land has been divided, under five classes I to V (based on broad soil
classification(1)), in to Abi, Chahi, Nehri, Barani, Banjar, Kallar, Thur, Sem, etc. Nehri is
irrigated land is placed under class I, while Banjar, Kallar, Thur and Sem come under
Class V category. Nehri is the land where the irrigation source is canal, while Chahi, Tal,
Barani are land where canal is not the irrigation source. Tibba is undulated land with
sand dunes and Gair-mumkin is non-cultivable land belonging to Government allotted to
the panchayat for community activities. Based on the above land classification the
village wise breakup of land under acquisition for project and township are given in
Table 5.1a.
Table 5.1a: Total Land Requirement and Land-use at the Project Site
Type of Land
Gorakhpur
Acres
Ha
Nehri
(Agricultural
land)
Chahi
(Agricultural
land)
Tal
(Agricultural
land)
Total
Agricultural
Land
Tibba (Waste
land)
Gair Mumkin
(Waste land)
Total Waste
land
Grand Total
Project Site
Kajalheri
Total
Acres Ha Acres
Ha
Township
Badopal
Acres Ha
Total
Acres
Landuse %
Ha
1252.43 506.85 2.68 1.08 1255.1 507.93 25.87 10.47 1280.98 518.40
18.06
7.31
18.06
7.31
18.06
7.31
17.95
1270.49 514.16 2.68 1.08 1273.2 515.24 70.23 28.42 1343.4 543.66
89
43.19
17.48
18.2
43.19
17.48
18.2
85
45.86
46.84
18.95
64.81
11
1.86
0.75
1313.68 531.64 4.46 1.81 1318.2 533.45 185.42 75.04 1503.56 608.48 100
The existing approach road from NH10 to the project site is from Badopal village (on
NH10). This road will be re-strengthened for movement of Heavy and Over Dimensional
Consignment (ODC) vehicles. The existing village roads passing through the project
area will be suitably diverted externally along the plant boundary.
The impacts and mitigation measures of locating the plant at the land acquisition for the
proposed site is given in Table 5.1b.
1 Dynamics of Agriculture Development, Vol. 3. : Policy Planning & Liberalisation. By K.S. Dhindsa &
Anju Sharma. Concept Publication Company. 2001.
2012 MECON Limited. All rights reserved
Page 167
Chapter 5
Table 5.1b: Impacts and Mitigation Measures of Locating HAPP at the Proposed Site
S
N.
1
a.
Issues in Locating
the Site
Main Plant Area
Agricultural Land
Mitigation Measures
515.24
b.
Barren-land /
wasteland
18.2
c.
99
d.
Eucalyptus Trees in
the
Power
Plant
Project Area
Abandoned Canal (2
ha) present in the
Power Plant Project
Area.
Village roads passing
through
residential
complex area.
575
g.
h.
e.
f.
Canal
covering 2
ha
Will be blocked
While
making
the
existing road as project
site approach road may
cause inconvenience to
local inhabitants.
Drainage Pattern of
the Area
There is no drainage
channel within the plant
and township area and
thus impact of changes
in local drainage pattern
Chapter 5
S
N.
Issues in Locating
the Site
2
a.
Township
Barren-land /
Wasteland / non
agricultural / non
cultivable land
b.
Agricultural Land
Total Land
28.42
608.48
Mitigation Measures
boundary.
Page 169
Chapter 5
Page 170
Chapter 5
5.4
and Zone-3 in the ascending order of contamination potential. These zones are
equipped with required safety features to limit the potential radiation within limits.
Reactor regulating system enables automatic control of reactor power and maintains
neutron flux profile.
Reactor protection system ensures shutdown requirements through two independent
fast acting shut down systems.
Reactor shut down systems etc
Emergency core cooling system,
Containment spray cooling system,
Double containment structures with steel liner on inner containment wall of Reactor
Building,
Exclusion zones
5.4.1
Land Use
Impacts and Mitigation Measures
The construction of nuclear power project of proposed magnitude would require large
input from civil, mechanical aspects including transport, labour etc. During construction
excavation, soil erosion, loss of topsoil is expected at construction site, which is
unavoidable. Further such huge construction activity requires large scale migration /
influx of labours camping in the area leading to direct and indirect impacts associated
due to such large scale migration.
The project site is rural area and fairly rich in manpower resources. The manpower
resources available in the region will fulfill the demand of construction labour. Further,
for labours / skilled labour coming from far off places labour colony will be established as
per statutory conditions.
Such temporary labour colonies, if not properly planned, may create environmental
pollution, unsanitary conditions and health problems in the area. However, it has been
planned that temporary labour colonies with all basic facilities like, sanitation, garbage
disposal, safe drinking water supply, etc will be established within the project site and
township site to minimize pollution of soil, water and public health problems.
It is therefore most unexpected that influx of construction labour is going to change
present land use pattern by forming residential colonies in the region.
During construction of the project, substantial quantity of soil and rock will be removed
during excavation thus requiring large scale dumping of soil, overburden material. The
soil overburden generated will be used for back filling, leveling, as sub-grade material in
Page 171
Chapter 5
making internal plant road, foundation works, filling green belt development areas and
filling low-lying areas. However, the following aspects will be taken care of.
Proper stock piling and back filling of the excavated soil.
All the disturbed land will be stabilized.
During dry weather condition, it will be necessary to control the higher dust levels
created by the excavation, leveling and transportation activities.
The top soil containing rich humus, soil will be preserved in separate top soil dumps
(height not more than 1m and re-vegetating the same with grasses and utilizing the
same for development of greenbelt in and around the project area.
Solid wastes generated during construction phase will be collected and segregated
and will not be disposed off on land. Combustible waste will be burnt in controlled
manner, whereas bio-degradable waste will be sent for composting and non bio
degradable will be sent to secured land fill area as designated by the State
Government in the region.
About 10MW of power will be required for construction and commissioning of the
project, which will be sourced from State Grid, permission regarding the same has
already been accorded from State Government while according permission for the site.
All care will be taken to get the construction material from local sources, if available in
required quantity. However, if the same is not available from local sources the same will
be sourced from distance sources. Construction material will be sourced from local
sources like, Stones and Aggregates from Tosham Village and Sand / Soil from Karnal
or Ghaggar River.
The supply of construction materials (like sand, soil, stones etc) to the project may
cause large scale excavation which will require mitigation measures to bring back the
excavated site as required by statutory authorities. The source of construction material
like, stones, aggregates, etc and the proposed mitigation measures (if any) is given in
Table 5.1c.
Table 5.1c: Quantity and Source of Construction Material for the Project
SN.
Material(s)
1.
Cement
2.
Coarse Aggregate
(Stones)
9,50,000
3.
Sand
5,50,000
4.
Admixture (Super-
Approx.
Quantity
(M.T.)
2,20,000
5,500
Sources
Mitigation Measures
Reputed
manufacturers /
suppliers in the region
Tosham Village (if
sufficiently available) /
Local suppliers
Karnal or Ghaggar
River sand (if
sufficiently available)
and Manufactured
sand from near by
area.
Reputed
Chapter 5
SN.
Material(s)
Approx.
Quantity
(M.T.)
plasticiser)
5.
6.
Reinforcement
steel
Fly-ash
2,00,000
1,50,000
Sources
Mitigation Measures
manufacturers /
suppliers in the region
TISCO / SAIL
Once the construction phase is over there will be positive impact on existing landscape
due to proper planning for landscaping, development of roads with avenue trees and
green belt development around the project building making the landscape beautiful with
lush green cover.
5.4.2
5.4.3
Air Quality
Impacts
The construction and other associated activities will lead to emission of different
pollutants. During the construction phase, dust and particulate matter will be the main
pollutant. As plant will be constructed in stages, construction activity covering a large
area is not expected. Therefore the particulate matter emission will not be much and will
be localized only. Gaseous pollutants like SO 2, NOx, CO will also be added to the
ambient air due to vehicular traffic movement associated with this construction phase.
Gaseous emissions from construction machineries and vehicles will be minimized by
enforcing strict emission monitoring system for the suggested mitigation measures. The
impact will be confined within the specific plant area where the construction is taking
place. Further, the impact of such activities will be temporary and will be restricted to the
construction phase only.
During the construction period the impacts that are associated with the air quality are:
Page 173
Chapter 5
Deterioration of air quality due to fugitive dust emissions from construction activities
(especially during dry season) like excavation, back filling and concreting, hauling
and dumping of earth materials and from construction spoils.
Generation of pollutants due to operation of heavy vehicles and movement of
machineries and equipment for material handling, earth moving, laying of sands,
metal, stones, asphalt, etc.
Mitigation Measures
The following mitigation measures will be employed during construction period to reduce
the pollution level to acceptable limits.
Proper and prior planning, appropriate sequencing and scheduling of all major
construction activities will be done, and timely availability of infrastructure supports
needed for construction will be ensured to shorten the construction period vis--vis
to reduce pollution.
Construction materials will be stored in covered go-down or enclosed spaces to
prevent the wind blown fugitive emissions.
Stringent construction material handling / overhauling procedures will be followed.
Truck carrying soil, sand, stone dust, and stone will be duly covered to avoid spilling
and fugitive emissions.
Adequate dust suppression measures such as regular water sprinkling at vulnerable
areas of construction sites will be undertaken to control fugitive dust during material
handling and hauling activities in dry seasons.
The construction material delivering vehicles will be covered in order to reduce
spills.
Low emission construction equipment, vehicles and generator sets will be used.
It will be ensured that all construction equipment and vehicles are in good working
condition, properly tuned and maintained to keep emission within the permissible
limits and engines turned off when not in use to reduce pollution.
Vehicles and machineries would be regularly maintained so that emissions confirm
to standards of Central Pollution Control Board (CPCB) / State Pollution Control
Board (SPCB).
Monitoring of air quality at regular intervals will be conducted during construction
phase.
Construction workers will be provided with masks to protect them from inhaling dust.
5.4.4
Water Quality
Page 174
Chapter 5
Mitigation Measures
Quality of construction wastewater emanating from the construction site will be
controlled through the drainage system with sediment traps (silting basin as water
intercepting ditch) for arresting the silt / sediment load before its disposal.
All the washable construction material will be stored under sheds or enclosed space
by fencing it with brick or earth in order to prevent spillage into the drainage network,
so that the same does not find its way into the surface water runoff.
The sediment traps and storm water drainage network will be periodically cleaned
and especially before monsoon season.
Majority of the water generated will be utilized for dust suppression and plantation
within the plant premises.
The vehicle maintenance / washing area will be maintained with proper drainage
system having oil trap mechanism to avoid contamination of surface and ground
water by oil / lubricants.
5.4.4.2 Ground water
Impacts
The water requirement during the construction phase will be low. No ground water will
be used for construction work. The construction water will be drawn from Fatehabad
Branch of Bhakra Canal to the tune of 1000m3/day (Commitment letter from
Government of Harayan enclosed as Annexure III) Therefore, it is most unlikely that
construction phase will bring any significant modification in the ground water regime of
the area. Therefore, the construction phase of the proposed plant will have insignificant
impact on the ground water.
Mitigation Measures
No impact envisaged.
5.4.5
Noise
Impacts
Major sources of noise during the construction phase are vehicular traffic, construction
equipment etc. The operation of the equipments will generate noise level ranging
between 75 to 90 dB (A). However this noise level will be near the source only and is not
expected to create any noise pollution problem at places away / outside the plant
premises. The noise generated during the construction phase from different equipments
may have some adverse impact on the operators.
Mitigation Measures
Protective gears such as earplugs, earmuffs etc. will be provided to construction
personnel exposed to high noise levels as preventive measures by contractors and
will be strictly adhered to minimize / eliminate any adverse impact.
It will be ensured that all the construction equipment and vehicles used are in good
working condition, properly lubricated and maintained to keep noise within the
permissible limits and engines turned off when not in use to reduce noise.
Page 175
Chapter 5
5.4.6
Site Security
The site will be secured by fencing and no unauthorized entry will be permitted in the
construction area.
5.4.7
Industrial Safety
During construction and operation phase of the project, all the project activities will be
carried out as per the regulations covered under Atomic Energy (Factories) Rules 1996,
Electricity Act and Rules, Explosives Act and Rules, Petroleum Act and Rules etc.
During Construction, the occupational Health aspects will be minimal as the work
location is open and is of dynamic nature. The main hazard potential will be fall of
person through a height, exposure to chemicals and noise, fall of material and electrical
shocks etc. which will be addressed by built in engineered safety provisions.
Accordingly, the construction workers will be provided compulsorily Personal Protective
Equipments (PPE) depending upon the risks and use of Safety Helmet and Shoes will
be must at the project construction sites. Separate safety clauses will be integrated in
the contract document for the project executing agencies to properly plan and to
appropriately provide the cost factor such that safety of the personnel at project
construction sites do not suffer for any reason. Safety coverage by professionals will be
mandatory for the construction works and posting of safety officers for particular works
will be must to enforce Industrial safety at the work sites. Such Safety officers and Safety
supervisors will be arranged to technically report to the departmental Industrial Safety
Head such that a direct guidance and monitoring of the contract works are made
possible effectively.
Other worker friendly measures adopted in the construction of Atomic Power Plant works
will be the compulsory induction and refresher training based on a syllabus monitored by
the corporate office for each worker. The worker will be issued a gate pass only after
undergoing the industrial safety training in which environmental management aspect will
also be touched upon properly. Facility of drinking water, urinals, toilets and construction
roads will be arranged in the beginning of the work itself. Similarly, provision of First aid
measures both departmental and that of contractors will be ensured in the beginning of
the work itself. Establishment of Fire fighting facility will be another area where priority
will be assured during the construction work.
During commissioning, operation and maintenance of the operating units, in addition to
the industrial hazards, the occupational hazard is the exposure to ionizing radiation
within prescribed limits which is governed by the Atomic energy Act and Radiation
Protection Act and Rules. In order to minimize possibility of radiation exposure to the
occupational workers, adequate safety measures are incorporated in the design,
construction, operation and work practices of the plant including the systems associated
with fuel handling and waste management. All the occupational workers undergo
periodical medical check ups, bioassay sampling and whole body counting as
applicable.
Only qualified engineers and technicians are recruited to carry out the design,
construction, operation and maintenance (O & M) of the plant. All O & M personnel
Page 176
Chapter 5
undergo mandatory training (at various levels) in the plant and related subsystems of the
plant through nuclear induction training. A committee consisting of a panel of experts
and a representative from the regulatory agency evaluates designated operating staff for
licensing. The qualification thus obtained will be renewed, periodically.
5.5
5.5.1
General
During the operation phase, depending upon operating conditions, environmental
releases may occur from raw material and product handling, processing, emergency DG
which are tested periodically etc. Environmental releases / emissions may be in the form
of:
a) Conventional Pollutants
i. Air emissions
ii. Waste water discharges
iii. Solid waste disposal
iv. Noise etc.
b) Radio-active emissions from source, liquid effluents and solid wastes
These emissions, discharges and disposal may release different pollutants, which may
affect air, water, land and ecological environment directly. However, all these are mainly
primary impact. In addition to these primary impacts, any industrial project has some
overall impact on its surrounding socio-economic environment through the existence of
social and economic linkages between the project and society, which are actually
secondary impact. Under this clause, all the primary impacts due to this proposed plant
are being discussed and wherever required, impacts have also been quantified.
Accordingly under subsequent clauses impacts on air environment, water environment,
soil and noise due to the operation of the proposed project are being elaborated. The
socio-economic impact due to the proposed project is separately discussed in Chapter
8.
There are two types of anticipated environmental impacts considered for nuclear power
plants, especially with respect to radio-activity releases. The first ones are those which
occur under normal operation of the plant and the second ones are those which can
occur under accident conditions.
The environmental factors that may be affected by the first type of environmental
impacts during operation phase due to radio-activity releases are discussed in
subsequent clauses. However, the second type of impacts and mitigation measures are
discussed in Chapter 9, under Section 9.4.2.
5.5.2
Page 177
Chapter 5
be carried out "on-power". The uranium dioxide (UO2) used for fuel is a ceramic with
high melting point and chemically inert to water at operating conditions. So long as the
ceramic fuel does not melt, the fission products remain entrapped in its matrix. During
normal operation virtually all solid fission products are permanently retained in UO2
matrix and only a fraction of noble gases and volatile products diffuse into the inter
space between fuel and cladding.
Waste management operations (liquid and solid), involves handling of radioactive
wastes from all the facilities for their ultimate storage/disposal. All these operations are
carried out in leak tight enclosures, under negative pressure so that the probability of the
radioactive materials reaching the working environment is reduced to a minimum.
Further, there are also clean up mechanisms like filters and traps to confine any
radioactive materials in the exhaust streams of the ventilation systems.
From the above operations, a small fraction of these radio-nuclides are released into the
environment in the form of gaseous emissions and liquid effluents. Natural processes in
the atmosphere and hydrosphere help carry and disperse them in the surroundings.
These residual radio-nuclides in turn find their way into soil and sediments, pastures and
foliage, and eventually enter the food chain such as rice, vegetables, fish and milk. Fig.
5.1a and Fig. 5.1b shows the various pathways through which the general public
receives radiation exposure as a result the operation of nuclear facilities.
The radioactivity discharged through air or water route may result in a small but
measurable addition to the already existing background of radioactivity and radiation
shine. However, under normal operation the radioactivity discharges are such that the
nuclear radiation dose at exclusion zone boundary (also called fence post, 1.0 km radius
around the plant) is only a small fraction of the radiation dose permitted for general
population and thus under normal operation of the plant impacts due to radio-activity
releases does not have any adverse impact on the surrounding environment vis--vis to
public residing beyond exclusion zone.
Operation and planned maintenance of the Atomic Power Plant facility do not result in
direct radiation exposures to the general public residing beyond the exclusion zone. But
radiation exposures are likely to be received through indirect means as shown in Fig.
5.1a and 5.1b.
Page 178
Chapter 5
SOURCE
CONTAMINATION
PROCESS
CONTAMINATED
MEDIUM
Dispersion
MODE OF
EXPOSURE
Water
Bioaccumulation
HABIT
DATA
DOSE
Ingestion
Irrigation
Liquid
Consumption
releases
Foodstuffs
Occupancy
External beta,
gamma
irradiation
Sediment
Concentration
Sedimentation
CONTAMINATION CONTAMINATED
PROCESS
MEDIUM
Air
Dispersion
MODE OF
EXPOSURE
DOSE
Inhalation
External beta,
gamma
irradiation
Soil
Atmospheric
releases
HABIT
DATA
Occupancy
Deposition
Vegetation
Animal
Ingestion
Consumption
Page 179
Chapter 5
Tritium
C-14
FPNG
Ar-41
I-131
Release
4X700 MWe
unit, GBq/d
2.02E+04
1.08E+01
1.10E+04
7.66E+03
2.02E-01
Dose
(mSv/y)
1.61E-02
9.28E-03
3.04E-02
3.72E-02
4.70E-03
Adult
Percentage
contribution
11.58
6.68
21.9
26.81
3.38
Dose
(mSv/y)
1.61E-02
9.28E-03
4.56E-02
5.58E-02
5.74E-02
Infant
Percentage
contribution
6.08
3.51
17.26
21.13
21.73
Page 180
Chapter 5
Radionuclide
Particulates
Total
Release
4X700 MWe
unit, GBq/d
2.02E-01
Dose
(mSv/y)
4.12E-02
1.39E-01
Adult
Percentage
contribution
29.65
100
Dose
(mSv/y)
8.00E-02
2.64E-01
Infant
Percentage
contribution
30.29
100
Table 5.2b: Apportioned Dose Limits for Liquid Effluents for 4X700 MWe
Radionuclide
Tritium
C-14
Cs-137
Sr-90
Total
Release
4X700 MWe
unit, GBq/d
2.02E+03
1.08E-01
1.00E-01
1.00E-01
Dose
(mSv/y)
4.04E-02
6.96E-05
1.44E-03
3.10E-03
4.50E-02
Adult
Percentage
contribution
89.76
0.15
3.2
6.89
100
Dose
(mSv/y)
4.80E-02
5.60E-05
7.76E-04
8.50E-03
5.72E-02
Infant
Percentage
contribution
83.71
0.1
1.35
14.84
100
Table 5.2a and 5.2b shows the dose apportionment scheme for adults and infants for
HAPP for gaseous and liquid effluent, respectively.
A total adult dose of 0.184 mSv/y is computed, 0.139 mSv/y coming from the
atmospheric route and 0.045 mSv/y from the liquid route. The corresponding total dose
for an infant is calculated as 0.321 mSv/y, with 0.264 mSv/y being derived from the air
route and 0.057 mSv/y from the liquid route (Table 5.2c). Noble gases and particulates
are the major contributors for the air route, and tritium for the water route.
Since an infant turns out to be a critical member of the population, a dose of 0.40 mSv is
apportioned for the 4X700-MWe power station at Fatehabad.
Table 5.2c: Dose Apportionment for HAPP 4X700 MWe
Nuclear facility
Reference
HAPP 1 to 4
Adult
Infant
Dose limit
Atmospheric Dispersion
The well-known Gaussian plume model is used for calculating the atmospheric
dispersion. The site-specific meteorological data in the form of joint frequency
distribution of wind speed, wind direction and the stability category is an essential input
to the model. The micrometeorological measurement data have been presented in
Annexure IVA. The plume rise due to the efflux velocity will be very small and that due
to the thermal will be negligible. As the heights of buildings are not large, the wake
effects due to buildings (normally felt within five times the height of the tallest building)
are also not considered in this calculation. The radioactive decay of the plume during
travel is also not considered, as the time taken for the plume to reach the 1.0 km is too
short compared to the half-lives of the radio-nuclides released. Therefore, the
calculations are conservative. The detailed dose apportionment report for HAPP is given
as Annexure V.
Page 181
Chapter 5
Once the spatial distribution of radio-nuclides is obtained, the radiation fluxes at receptor
locations of interest are obtained by integrating over the volume source with appropriate
geometric attenuation factors. The flux to dose conversion is done using standard
conversion factors taken from BSS 115. Dose computations for the all the pathways of
exposure were made in accordance with procedures described in Manual on Dose
Evaluation from Atmospheric Releases, BARC-1412.
For estimation of dose limit at 1.0 km plant boundary, the above considerations and the
annual average rate of discharge of gaseous radioactive effluents from all the units of
700 MWe are considered and estimation has been done and the results are shown in
Table 5.2d.
The dose limit for the general public due to operation of all facilities within HAPP site is 1
mSv/y. These are further apportioned among the various radio-nuclides (Table 5.2d).
Radiological gaseous effluents when averaged over one day shall not exceed ten times
the annual average releases rates specified above.
Table 5.2d: Gaseous Radioactive Releases and Corresponding Dose to Members
of Public at 1.0 km Exclusion Boundary
Stack Release
Dose at Exclusion
Gaseous Radio-active Effluents
Tritium
C-14
Total
Boundary (mSv/y)
Adult
Infant
1.61E-02
1.61E-02
9.28E-03
9.28E-03
3.04E-02
4.56E-02
3.72E-02
5.58E-02
4.70E-03
5.74E-02
4.12E-02
8.00E-02
1.39E-01
2.64E-01
Mitigation Measures
Design of the plant is based on minimizing the leakages from the plant system in to
plant buildings so that generation of radioactive effluents is minimized.
The gaseous radioactive effluents from reactor and service building ventilation
exhaust systems are passed through pre filters and absolute filters before discharge
through the ventilation stack.
The gaseous effluents are continuously monitored for radioactivity content before
discharging through ventilation stack. Otherwise the ventilation stack is meant only
for handling the ventilation exhaust of different units. There are three gross (Beta),
(Gamma) activity monitors on each of the reactor building (RB) ventilation exhaust
ducts (located in Service Building)
5.5.2.2 Radio-active Releases: Liquid Effluent Discharges
General
In atomic power plant water is required for:
Making up the losses in the waste heat disposal systems
Input for domestic water requirements
Radioactive waste dilution
2012 MECON Limited. All rights reserved
Page 182
Chapter 5
Waste heat from the non-safety related loads like condenser and auxiliaries is dissipated
using Natural Draught Cooling Towers (NDCTs) and heat from the safety related loads is
dissipated using Induced Draught Cooling Towers (IDCTs).
Radioactivity in liquid effluents from PHWRs is mainly due to tritium and other activation
products in moderator and coolants - at very low concentrations. Dilution is the only
treatment for tritium discharge to environment. Regulatory stipulation demands that the
radioactivity levels in the liquid effluents should be within limits such that the apportioned
dose for the general public utilizing the water at the discharge point is not exceeded. A
common liquid effluent discharge scheme has been envisaged for HAPP 1 to 4 (Fig.
2.10).
After using the water for the required purpose, both the treated active and inactive water
will be discharged into Fatehabad branch of Bhakra Canal. Total estimated plant drain
water quantity is about 5320 m3/hr. This includes the blow-own from NDCTs, IDCTs and
other miscellaneous plant drains.
The total water requirement of HAPP 1 to 4 units is 18000 m3/hr, out of which about
12680 m3/hr is for consumptive usage. About 5320 m3/hr is waste water discharge from
plant which is used as dilution water for HAPP 1 to 4. The same is available from
NDCT/IDCT blow-down and Plant Water Treatment Water (PTP) drains (Fig. 2.13).
Impacts
In an Atomic Power Plant waste water is generated from different waste streams as
given Table 5.2a.
The wastes from different streams may contain radioactivity levels as shown in Table
5.2a, which if discharged in to receiving water bodies may cause radiation exposure
to downstream users of the canal water and to the biotic environment of the canal
water.
Substantial heat is generated during the process and water is used as one of the
coolants. For HAPP closed loop cooling tower are used hence there will not be any
discharge of heated effluent to the receiving water body.
Sewage effluents from plant and township may contaminate the receiving water
bodies.
Table 5.2a: Waste Water Discharges
Waste stream
1.0
Quantity
m/day
Activity Levels
(Bq/ml)
Gross Tritium
-
3.7E-3
3.7E-2
3.7E-1
250
250
100
Activity Inventory
Gross
- (KBq)
Tritium
(MBq)
111
740
10360
7500
5000
2500
Treatment
Page 183
Chapter 5
Waste stream
2.0
Active Non-Chemical
Waste (ANCW)
3.0
4.0
5.0
Total
Quantity
m/day
12
Activity Levels
(Bq/ml)
Gross Tritium
-
1.85
1850
Activity Inventory
Gross
- (KBq)
22200
Tritium
(MBq)
2220
3700
222000
1.85
11E4
6
1
0.371
1850
7.4E4
2220
18500 Occasional
13.7 litre
/ day
0.037
1850
96.01
Occasional
39331
Treatment
Filtration,
polishing
through
IX
column,
evaporation, dilution with
exhausts
air
and
discharged
through
stack.
- Do 444000
Occasional Neutralized & treated like
ANCW.
Occasional Filtration, dilution with
plant water drainage
system and discharged
to Bhakra canal. Total
discharge 5320 m3/hr.
683220
Mitigation Measures
Design of the plant is based on minimizing the leakages from the plant system in to
plant buildings so that generation of radioactive effluents is minimized. In addition
waste management facilities will be set up to treat the different levels of radioactive
effluents to meet the authorized release limits stipulated by AERB. Further, the
effluents will be mixed with the blow-down water from cooling tower (NDCTs, IDCTs
and other miscellaneous plant drains) to provide the required dilution at the point of
discharge to meet the AERB limits.
As given in Table 5.2a only the Potentially Active Waste (PAW) to the tune of 75
m3/day, of low level radioactive waste will be diluted to well below prescribed AERB
norms will be the main effluent to be discharged into the Fatehabad Branch of
Bhakra Canal.
The total waste water to be discharged from HAPP in to Fatehabad Branch of
Bhakra Canal will be 5320 m3/hr.
The diluted low radioactive waste before discharged to Fatehabad Branch of Bhakra
Canal will be continuously monitored for radioactivity.
A Main Outfall (MOF) sampling system at the downstream of treated waste injecting
point in plant water discharge system will be provided - to further ensure that the
liquid waste discharges made from waste management plant (WMP) have been
adequately diluted with plant water discharge system and are within the permissible
discharge limits. This sampling will be done continuously over a period of 24 hours.
These samples will be analyzed in the laboratory for tritium and gross beta activity.
Rest of the liquid effluent (Table 5.2a) having relatively high tritium and Beta gamma
activity like Tritiated Waste (TTW) generated from Upgrading plant rejects,
Moderator room sump & Clean-up system and Active Non Chemical Waste (ANCW)
generated from Equipment decontamination system of WMP, chemical laboratory &
2012 MECON Limited. All rights reserved
Page 184
Chapter 5
SFSB cask wash down area, of less volume (21.01 m3/day) will be treated and
evaporated [in Induced Draught Cooling Towers (IDCTs)] after dilution with exhaust
air and will be discharged through stack to air route. Liquid effluent to the tune of
21.01 m3/day having relativity higher activity are treated by filtration and ion
exchange process and disposed through air route using Evaporation system.
Streams like ANCW, ACW and TTW, after filtration, will be diverted to a synthetic ion
exchange column to remove the dissolved Beta-gamma activity and then stored in
evaporation system feed tank. These polished tritium bearing liquid waste streams
(free of gross beta activity) are sent to a steam heated evaporator with a controlled
flow rate of 1.4 m/hr. This vaporized stream is then injected into the ventilation
exhaust ducting leading to 100 m high stack. Evaporation of effluents having
relatively higher level of activity ensures the discharges through water route are kept
at minimum. The air route mode of disposal offers unique advantage of higher
release limits per unit of dose allocation as compared to liquid route. This mode of
disposal suits inland site where water body is scarce and extensively used by the
surrounding population.
Periodical monitoring of receiving water body water quality at up-gradient and down
gradient of the effluent discharge point.
Page 185
Chapter 5
Impacts
Solid waste generated from different units may cause radio-active radiation in the
surroundings. The source of radioactive waste generation and the type of treatment and
disposal method is given in Table 5.3a. The type, quantity and surface dose rate of
radio-active waste generated from 4 x 700 MWe PHWR station is shown in Table 5.3b.
Table 5.3a: Type of Solid Waste Generated and Disposal Mode
SN.
Source of Waste
Treatment
Surface Dose
Rate
Surface dose rate
up to 0.01 Sv/hr
Laundry System
NA
Table 5.3b: Type, Quantity and Surface Dose Rate of Radio-active Waste Generated from
4x700 MWe PHWR Station
SN. Type of Waste
1.
Avg. Qty.
(m3/year)
Compactable waste
(before compaction)
i)
ii)
iii)
iv)
Assorted Waste
Pre-filters
HEPA filters
Charcoal filters
Remarks
Category-I
162
15
32.75
0.15
Page 186
Chapter 5
2.
3.
4.
Total i. to iv
Non-Compactable Waste
Spent liquid filters
Avg. Qty.
(m3/year)
210
20
2.0
Remarks
Category-I
Category-I,II, IIIA
Occasionally Cat-II
Radiation field (max.) in
PHT Gland filter 20R/hr
Generally Cat-IIIA
Occasionally Cat-II
Generally Cat-IIIA
Occasionally Cat-IIIB
Generally Cat-IIIA
Occasionally Cat-II
Generally Cat-II
Moderator - 48 nos.
9.6
ii)
PHT - 18 nos
3.6
2.4
Page 187
Chapter 5
activity ingress into ground water. This is one of the most widely used method for volume
reduction of low level combustible waste by which reduction in disposal space and cost
reduction in engineered barriers can be achieved. This system will cater to very low level
active combustible solid waste like paper-waste, cotton waste, mops, discarded clothing,
packing materials etc.
Capacity of incinerator:
Fuel requirement is about 50 litre/hr. of fuel oil (furnace oil) and the solid waste which can
be incinerated at a time is 20 kg/hr.
Plastic waste will be fused (melt densification method) in a drum to achieve significant
volume reduction.
This system will operate only after collecting required volume of waste to optimize the fuel
requirement to start the incinerator. Generally 2 to 3 days of operation per month is
sufficient. Height of chimney will be 30 metre as per state pollution control board norms.
Temperature of flue gas emitted from chimney will be very low as it is passed through two
stage water scrubber. The ash and scrubbing water after solidification / embedment in
cement will be disposed in RCC trenches. Continuous monitoring system is provided to
monitor the gas emitted from the chimney.
Considering sulphur content in furnace oil as 4% the SO2 emission from burning of furnace
oil in the incinerator will be 1.1 g/sec and this emission will be passed through two stage
water scrubbing system and moreover, the incinerator will be run occasionally for 2 to 3
days a month thus the impact on surrounding AAQ will be negligible and thus no further
assessment on this aspect has been done.
Mitigation Measures
Treatment and disposal of radioactive solid waste at the plant is carried out as per
AERB / SG / D-13.
Solid wastes after conditioning will be disposed off in the Near Surface Disposal
Facility (NSDF) area in earth trenches / RCC trenches / vaults / tile holes / HIC
depending upon their surface dose rate.
A waste assaying will be carried out to assess and record the radioactive content in
each conditioned waste packages before disposing them. Name of the vault and
their identification will also be recorded.
Packages having higher activity will be disposed off at the bottom of trenches / vaults
and will be suitably sealed permanently as per established practices. These data will
be utilised to assess the safety aspects of the waste repository.
Necessary geo-hydrological & soil analysis studies for the NSDF site will be carried
out to assess the safety of NSDF containing solid waste generated from 50 years of
plant operation.
Proper surveillance of Solid Waste Management Facility will be carried out - through
bore holes provided all around the NSDF to check the integrity of the engineered
Page 188
Chapter 5
Page 189
Chapter 5
A separate Control Building, common for the 700 MWe units 1 and 2 is provided. Each
700 MWe unit has two Station Auxillary Buildings (SAB). SAB are provided to house
emergency power. SABs 1A and 2A are located on either side of the Control Building of
unit 1 & 2, while SABs 1B and 2B are located abutting the Nuclear Buildings for unit 1 &
2, respectively. The same set of arrangement of SAB is there for the 700MWe unit 3 and
4. Two D.G. sets are located in each Station Auxiliary Building (SAB), making the total
number of DG sets available for each 700 MWe unit four, i.e total eight DG sets will be
there for one twin unit 1 and 2 and total 16 for the HAPP 1 to 4.
For each unit of 700MWe there are 4 DG sets. Each DG is of capacity 4.2 MW with fuel
consumption of 233g/KWhr (233g/KW/hr) or 979kg/hr. One DG set is sufficient for
supplying power to one 700MWe reactor. However, provision of 3 standby DG sets has
been kept for emergency situation. The fuel provision for fuel storage is 200KL for one
DG operating for 7 days (other 3 DG sets as standby). The DGs are required during
power failure emergency situation only. One DG set is tested for to 1.0 hour in a
week. The other DG sets kept under standby are tested in subsequent weeks. Thus 4
DG set will run for maximum one hour during testing period for the four units of HAPP
and during emergency situation 4 DG sets will run for 24 hours during emergency power
failure situation.
A common stack of 30 m will be provided to vent out the flue gases from the DGs of
each SAB. The stack height is estimated as per MoEF Notification GSR 489 (E) July,
2002 for estimation of stack height of DG set depending upon the 4.2MW capacity. The
diesel consumption will be about 979kg/hr. The test run of DG will be carried out for one
hour for once a week.
In order to predict impacts on ambient air quality due to DG sets operation on regular
and emergency basis proposed at HAPP site, data on emission scenario and
micrometeorology data collected at site and along with stability class data collected from
India Meteorology Department (IMD) were used to predict Ground Level Concentrations
(GLCs) of SO2, NOx and PM.
Table 5.4a: Stack Details and Emissions from DG Sets
SN
1
2
3
4
Stack ID
SAB 1A - DG1
SAB 2A DG1
SAB 3A DG1
SAB 4A DG1
Capacity
Stack
(MW) Height Internal STP Flow Exit Vel.
(m)
Dia.
Rate
(m/s)
3
(m)
(Nm /hr)
4.2
30
1.2
39000.0
20
4.2
30
1.2
39000.0
20
4.2
30
1.2
39000.0
20
4.2
30
1.2
39000.0
20
Exit Gas
Temp. (k)
623
623
623
623
Emission Rate
SO2 NOx PM
(g/s) (g/s) (g/s)
0.685
0.685
0.685
0.685
0.695
0.695
0.695
0.695
0.8
0.8
0.8
0.8
Page 190
Chapter 5
sources is a major concern as it will have an impact on the ambient air quality in the
surrounding area.
For prediction of impacts for any proposed project vis-a-vis to assess the impacts due to
increase in pollution load, in general, contributions from the proposed units is added to
the existing back ground AAQ concentrations and predictions is done accordingly.
Once the pollutants are emitted into the atmosphere, the dilution and dispersion of the
pollutants are controlled by various meteorological parameters like wind speed and
direction, ambient temperature, mixing height, etc. In most dispersion models the
relevant atmospheric layer is that nearest to the ground, varying in thickness from
several hundred to a few thousand meters. Variations in both thermal and mechanical
turbulence and in wind velocity are greatest in the layer in contact with the surface. The
atmospheric dispersion modeling and the prediction of ground level pollutant
concentrations has great relevance in the following activities:
-
The prediction of Ground level concentrations (GLC) of pollutants emitted from the
stacks have been carried out using ISCST-3 Air Quality Simulation model released by
USEPA which is also accepted by Indian statutory bodies. This model is basically a
Gaussian dispersion model which considers multiple sources. The model accepts hourly
meteorological data records to define the conditions of plume rise for each source and
receptor combination for each hour of input meteorological data sequentially and
calculates short term averages up to 24 hours. The impact has been predicted over a 10
km X 10 km area with the proposed location of the stack as the centre. GLC have been
calculated at every 500 m grid point.
Accordingly, the emissions are estimated and the details of the proposed stacks and
emissions from them are given in Table 5.4a.
Stack details like height, top diameter, exit velocity etc of all the stacks are taken from
similar facilities. However, these stack details may be changed at the detailed
engineering stage and as per design of know-how supplier, prevailing emission factors
as available in literature for DG sets and different statutory regulations prevailing in the
country.
Meteorological data plays an important role in computation of Ground Level
Concentration using ISCST-3 model. Meteorological data of the project site is another
input required for computation of the contribution by the proposed plant. The parameters
required are:
Wind velocity and direction
Stability
Mixing height
Page 191
Chapter 5
Data related to wind velocity and direction were generated during the monitoring period.
Part of this site specific monitored data have been used as input data of the model
during computation.
The hourly occurrence of various stability classes at the project site is also an important
input parameter to the model. Further site specific mixing depth (mixing height or
convective stable boundary layer and inversion height or nocturnal stable boundary
layer) is also an important input parameter for computation and assessment of realistic
dispersion of pollutants. There are different methods for generating these parameters,
but in the present case data published by CPCB in Spatial distribution of hourly mixing
depth over Indian region have been used. The input meteorological data used in the
computation are presented in Table 5.4b and uniform Cartesian grid system was used to
locate/fix sources and receptors in the study area. The predicted GLC values are given
in Table 5.4c.
The above computation is considering the stack emissions only and does not take into
account any changes in the fugitive emission. However, since the fugitive emissions are
being released mainly from near ground sources, are not expected to travel / disperse to
a longer distance to reach beyond the plant boundary and thus are not expected to have
any impact on the ambient air.
As stated earlier that out of the total sixteen DG sets only four will be in use and rest 12
will on standby. Thus at a time of test run or during emergency situation only four DG
sets will run. As a conservative approach the worst scenario prediction were done for
the two scenarios, as follows:
Scenario 1: When 4 DG sets are running for 1 hour per week for test run.
Scenario 2: When in emergency situation in case there is a power failure 4 DG set
runs for 24hrs.
For the above two scenarios, ISCST3 model is used to predict the GLCs for operation of
four DG sets as per the above two scenarios.
Table 5.4b: Meteorological Data used as Input for Air Quality Modeling
Hour
01
02
03
04
05
06
07
08
09
10
11
12
Wind Speed
(m/s)
1
1
1
1
1
1
1
1
1
1
2
3
Ambient Air
Temp. (K)
294.5
294.5
293.4
292.9
291.7
290.5
290.4
290.4
291
295.4
300.9
304.4
Predominant Wind
Direction (N as 1800)
360
315
315
315
360
360
315
315
315
315
315
315
Hourly Stability
Class
6
6
6
6
5
4
3
3
2
2
1
1
Mixing
Depth (m)
50
50
40
40
30
80
100
275
510
800
1300
1500
Page 192
Chapter 5
Wind Speed
Ambient Air
Predominant Wind
Hourly Stability
0
(m/s)
Direction
(N
as
180
)
Class
Temp. (K)
13
3
305.4
315
2
14
2
306.5
315
3
15
3
307.5
315
3
16
2
308.6
315
3
17
1
308.6
293
4
18
1
308.9
293
4
19
1
306.8
270
5
20
1
304
315
5
21
1
303.3
315
5
22
1
301.8
270
5
23
1
301
270
6
24
1
299.7
315
6
1= Extremely Unstable, 2= Moderately Unstable, 3= Slightly Unstable,
4 = Neutral, 5= Slightly Stable, 6= Moderately Stable
Hour
Mixing
Depth (m)
1600
1750
1850
1700
1500
1300
900
725
300
200
100
50
Monitored
C98 (g/m3)
Table 5.4d: Expected Ambient Air Quality for One Hour when DG Sets Running for
One Hour / Week
Pollutants
SO2
NOx
SPM
Page 193
Chapter 5
Mitigation Measures
Nuclear power contributes very little to atmospheric CO2 or sulphur or nitrogen oxide or
particulate matter from process. During the design phase all efforts have been made to
adopt latest state of art technology and to install adequate pollution control measures
and for possible fugitive emission sources. The following mitigation measures will be
employed during operation period to reduce the pollution level to acceptable limits:
To ensure that all the pollution control facilities envisaged at the design stage are
have been implemented and are functioning properly.
Stack monitoring to ensure proper functioning of different pollution control facilities
attached to major stacks.
Air monitoring in the Work-zone to ensure proper functioning of fugitive emission
control facilities.
Adequate plantation in and around different units.
Vehicles and machineries would be regularly maintained so that emissions confirm
to the applicable standards.
Monitoring of ambient air quality through online AAQ monitoring system at three
locations and through manual means at three locations (once in a year).
Workers will be provided with adequate protective measures to protect them from
inhaling dust.
The test running of all the four DG sets for one hour in a week will not be taken up
collectively at a time. Only one DG set will be tested at a time for one hour and
remaining three will be taken up in subsequent hour / day of the week.
Page 194
Chapter 5
Page 195
Chapter 5
Page 196
Chapter 5
Page 197
Chapter 5
Page 198
Chapter 5
Flood Analysis:
The project site is within 10 km radius of Bhakra Canal. The Fatehabad Branch of
Bhakra Canal is fully lined and hence there is very low probability of canal breach. The
flood analysis report is attached as Annexure II. The flood analysis report is briefed
under Section 5.4.2.
Water Usage
Background
In an Atomic Power Plant wastewater may be generated from different units / shops. The
liquid waste streams generated from the plant are segregated at source and are
collected in collection storage tanks located in Liquid Effluent Segregation System
(LESS) area. The waste management design philosophy is based on the principle of
ALARA (As low As Reasonably Achievable). The impact and mitigation measures for
radioactive liquid waste are given under Section 5.5.2.2.
Impacts
Substantial heat is generated during the process and water is used as one of the
coolants. For HAPP closed loop cooling tower are used hence there will not be any
discharge of heated effluent to the receiving water body.
Sewage effluents from pant and township may contaminate the receiving water
bodies.
Mitigation Measures
Thermal pollution: The closed loop cooling towers will be used, which will reduce the
possibility of discharge of thermal pollution to the aquatic environment of receiving
water body. No thermal effluents are discharged into water bodies at any stage of the
project.
A sewage treatment plant with zero discharge is envisaged for both township as well
as project area.
Effluent from DM plant is led to the STP after adequate neutralisation and settling.
Treated sewage effluents are recycled to the extent possible for green belt, lawn and
horticulture and road dust suppression.
The excess remaining treated sewage is dispersed over land during non-rainy
season.
However, during rainy season the treated sewage will be discharged to nearby
surface drains in the area, which will be meeting the surface water discharge criteria
of CPCB.
In the light of the above no significant change in the physico-chemical properties and
ecological features of the receiving water bodies is expected.
Periodical monitoring of receiving water body water quality at up-gradient and down
gradient of the effluent discharge point.
Page 199
Chapter 5
Ground Water
Impacts
For construction and other miscellaneous uses 1000m3/day of water will be drawn
during the initial phase of the proposed project from Fatehabad Branch of Bhakra canal.
Hence no impact on ground water availability around the plant is anticipated.
The waste disposal area around any industry is one of the major factors deteriorating
ground water quality, if the water leached from the waste dumps contains toxic
substances. At the proposed plant, all wastes are dumped in secured land fill sites and
only inert wastes, like sludge from sewage treatment plant of township is used for
gardening purposes. All other solid wastes containing radio-activity elements are
handled and dumped as per the guidelines of AERB.
Mitigation Measures
Periodical monitoring of ground water quality at up-gradient and down gradient of the
plant area.
Disposal of waste generated from the proposed project will be done in a systematic /
scientific manner as per guidelines of AERB to prevent any ground water pollution.
5.5.3.3 Area Drainage and Surroundings
Impact
The project may disrupt the natural drainage of the area and surroundings.
The area is semiarid with low rainfall and flat terrain without any well defined natural
drainage system. There are no natural drainage channels passing through project
and township areas. The general slope of the project site is away from canal to south
direction. The drainage is of inland type and the excess rainwater, accumulates in
natural /artificial depressions.
Mitigation Measures
Impact on drainage of the area is not anticipated.
A detailed site topographic survey of the project site and surroundings will be
undertaken and the site features will be so designed that the area and surrounding
drainages are not obstructed.
The power project and the township will have their separate storm water drainage
systems, designed for the rainfall and drainage of the area. The storm water
drainage from the project and township will be led to the Bhakra canal to avoid
flooding of the surrounding.
No construction / dumping activities will be done for establishment and operation of
the proposed project so as to disrupt the drainage pattern of the area.
Any adverse impact on the drainage pattern of the area is not anticipated.
Page 200
Chapter 5
Total
535
Cells will be
used
in
different
part of the
plant.
Mode of Disposal
Active Organic Liquid waste like Oil,
lubricants, scintillation liquid etc are burnt
along with low level solid waste using the
incinerator. No active organic liquid waste
will be disposed.
Collected from garage / shops and kept in
the central stores area from where it will be
sold / auctioned to the registered re-cyclers
as per. - The Batteries (Management and
Handling) Rules, 2001 and its amendments.
.
Mitigation Measures
All hazardous wastes to be disposed in secured landfill as per statutory norms.
5.5.3.6 Noise Levels
Impacts
The main sources of noise in the nuclear power plant are 1) Turbines, 2) Air
Compressors, 3) Ventilation inlets, 4) Diesel Generators, 5) Pump House Equipments, 6)
Chillers, 7) Vents, 8) Exhaust Fans and 9) Heavy and medium automobiles moving
around the plant. The noise levels likely to be generated by these sources are presented
in Table 5.6a. It is likely that improved technology may further reduce the noise levels.
Most of the machines will be working continuously round the clock during operation of
the nuclear power plant. However, these machines would be housed in acoustic
enclosures / buildings such that they would not be contributing any additional noise
levels in the surrounding environment.
Page 201
Chapter 5
Table 5.6a: Main Sources of Noise from Different Equipments & their Noise Levels
SN.
Location of Source
Noise level in dB
Distance from
(A)
Noise Source (m)
1
Chillier and compressor Room
98 - 105
2
2
Boiler Feed Pump area unit I
95
2
3
Turbo Generator 1st Floor
95 105
2
4
Boiler Feed pump are unit -2
95
2
5
Turbo Generator 2nd floor
95- 105
2
6
Up grading Plant
90 -95
2
7
CWPH
90-95
2
8
PWPH
90-93
2
Source : NPCIL
Note:
1. All the above-mentioned equipments will be housed in properly designed and engineered
buildings, which will work as protective enclosures.
2. The occupancy of human beings like occupational workers on continuous basis is not
envisaged in the areas around these equipments
Lptotal = 10 Log (10lpa/10 + 10lpb/10 + 10lpc/10 ..), where Lpa, Lpb and
Lpc are noise pressure levels at a point due to different sources.
Based on the above principle a Noise Model has been developed in house, which has
been used to predict the noise. The noise level contours due to the noise sources in
units of the proposed Atomic Power Plant without considering noise barriers are shown
in Fig. 5.3. Without any barriers viz. buildings and green belt, it is predicted that the
noise levels in the surrounding environment due to above said equipments of the
proposed units at a distance of 500 m will be 52 dB(A) and at 1000 m will be 50 dB(A). It
is also predicted that the noise levels from these sources at 2000 m distance will be <50
dB(A). Therefore, background noise levels in the nearest village i.e. Gorakhpur located
at a distance of 2 km will remain below 50 dB(A).
The maximum noise levels will occur at receptors located near all the proposed units
which are predicted to be less than 60 dB(A) without any barriers viz. buildings. These
noise levels would be significantly reduced when the barrier of building is considered at
the time of operation of plant.
Page 202
Chapter 5
Considering the attenuation due to specially designed building within which noise
generating machineries will be housed, the increase in noise levels will be around 1-2
dB(A) just outside the building of power plant. Thus, there will not be any change in the
ambient noise levels due to operation of nuclear power plant in the nearest village
Gorakhpur at 2 km distance.
2000
1700
1600
1500
1000
900
800
700
600
500
400
300
200
100
60
50
40
30
20
10
0
Fig 5.3: Predicted Noise Levels due to Noise Sources without Considering Attenuation
due to Barriers Like Building and Greenbelt.
As indicated above there will not be any increase in noise levels due to operation of the
proposed project in the nearest village Gorakhpur at 2 km distance. Therefore the
community will not be affected by the operation of the APP at Fatehabad.
Moreover, the predicted noises within the plant premises beyond work zone without
building will be as given in Table 5.6b.
Table 5.6b : Noise level with in existing plant premises beyond work zone
SN.
A
1
2
3
4
B
1
2
3
4
Location
Outside Building
Near Overhead Tank ( North)
Between TB-I & TB-2 (East)
Near Pipe Ramp (south)
Near CAS (West)
Boundary of Operating Island
North of operating island
East of Operating Island
South of Operating Island
West of Operating Island
Noise in the work place generated from operation of equipment is the only concern from
the point of view of occupational health.
Page 203
Chapter 5
Page 204
Chapter 5
All the equipment in different units will be designed/operated in such a way that
the noise level shall not exceed 85 dB (A).
Periodical monitoring of work zone noise and outside plant premises.
Management Measures
In Atomic Power Plant, with a variety of noise producing equipment, it may not be
practicable to take technological control measures at all the places. In such cases the
following administrative measures shall also be taken:
Un-manned high noise zone will be marked as High Noise Zone".
In shops where measures are not feasible, attempts shall be made to provide
operators with sound-proof enclosure to operate the system.
Workers exposed to noise level will be provided with protection devices like ear
muffs/ ear plugs and will be advised to use them regularly, while at work.
Workers exposed to noisy work place shall be provided with rotational duties.
The duration of exposure of the personnel will be limited as per the norms.
All workers will be regularly checked medically for any noise related health
problem and if detected, they will be provided with alternative duty.
Over and above all these adopted measures, trees and shrubs belts of substantial
depths within and surrounding plant premises will further attenuate the sound levels
within limits reaching the receptors out side the plant premises.
5.5.3.7 Ecological Features
Impacts
Erection and commissioning of the project may change the land-use pattern of the
area and may cause significant loss of habitat / agricultural land, which is
unavoidable.
During construction some existing vegetation / crops on the project site may be cut /
damaged.
The construction and operation of the project may cause direct impact to the fauna
present in the area.
Emissions from plant operation may affect the natural vegetation and agricultural
crops around the proposed plant.
The thresh-hold limit for continuous exposure of SO2 on plants is about 50 ug/m3
and that for NOx is 100 ug/m3 (Env. Engg., Chapter 7 by H. S. Pavy, D. R. Rowe,
G.T. Chobanoglous. Mc.Graw-Hill Book Co.1986). The level of air pollutants due to
DG set operation (only occasionally) will be much below the above said level. Thus it
is expected that the natural vegetation in the area will not be affected. So far as
agriculture crops are concerned, as they will remain in the field for three to six
months only, the impact on the same is also not anticipated.
Page 205
Chapter 5
There is no forest area within 10km radius of the project site. Thus it is expected that
the flora and fauna in the study area will not get affected due to the proposed
project.
Noise generated due to the proposed project may cause disturbance to the faunal
species.
Strong light in the project premises during night may cause some disturbance to the
fauna in the near by areas.
The waste water from plant operation and domestic use may cause surface water
pollution in the area.
Mitigation Measures
All care will be taken to avoid cutting of trees growing in the project site.
All technological measures to limit air emissions, waste water discharge and noise
generation are envisaged in the proposed plant design and hence no further
mitigation measures envisaged.
An elaborate green belt / cover already exists which will be further enhanced within
and around the plant as detailed in Chapter 6 to ameliorate the fugitive emissions
and noise from the project operation.
The domestic waste water will be treated and after treatment the same will be reused and recycled within the plant itself and only excess water will be discharged
which will meeting the statutory norm. Thus there will be no impact on the ecological
components of surface water bodies in the area.
Direct Disturbance: Ten feet high RCC concrete wall fencing is erected all around
the project so that no animals come to the project site. Further a green belt erected
within the fencing (facing the proposed plant expansion) all around the proposed
plant area will further reduce the impact of direct disturbance.
Noise: The maximum noise level reaching out side the proposed plant project
boundary will be below the statutory norms for residential and other areas will be
below the statutory norm. Further the green belt all along the project boundary will
further reduce the noise level so as to cause any disturbance to the faunal species.
Thus the animals in the study area will not get impacted due to the noise from the
proposed project activity.
Strong Light during Night: The strong light in the project premises during night
may cause some disturbance to the fauna in the near by areas. It is proposed that
all the light posts erected along the boundary wall will face inwards and down wards
(with reflectors facing the plant and downwards), so that the light do not spreads out
side the plant boundary.
Page 206
Chapter 5
Type of Vehicle
1
2
3
4
6
7
8
9
10
11
Trucks
Cars / Jeeps
Over Sized Consignment
Excavator
Wagon Drills
Dozer 80D
Grader
Air Compressors
Drifter
Dumper
(a) 6m3 Capacity
(b) 10m3 Capacity
Poclain
(a) 1.5 cum bucket
(b) 2.0 cum bucket
Front end loader JCB
Tractor mounted water tanker &
sprinkler for dust control
Magzine Van (10T)
Portable Magzine
DG set for batching plant area
Vibratory Road Roller 10 MT
Crushing plant for normal & heavy
aggregate 100 TPH
Remix / transit cars
6 cum capacity
3 cum capacity
125
30
1
2
8
2
1
500 CFM
3
12
13
14
15
16
17
18
19
20
30
3
Construction site only
6
2
2
5000 liters capacity
2 numbers
2
3
As required
1
1
10
3
A total of maximum 125 trucks (HMV) per day will be running in the region for the
construction material requirement of the plant. For traffic volume estimation, considering
receipt of construction materials in two shifts (16hrs.) about 8 trucks per hour (incoming / returning trucks) will be additionally running on the road leading to the project
site. Similarly for Cars / Jeeps (LMV) about 2 vehicles will be running in the region for
the construction requirement of the plant. It is anticipated that oversized consignment
vehicle will be plying at the most one vehicle per day in the region. While other vehicles
2012 MECON Limited. All rights reserved
Page 207
Chapter 5
as mentioned under serial number 4 to 9 (Table 5.7a), once moved to the project site
will be running at the site only and hence has not been considered further for estimation
of enhanced traffic load.
The increase in traffic load on NH10 due to the project is shown in Table 5.7b. It can be
seen that there will be only 3% increase in the traffic load over the existing traffic
volume. However, this increase will be temporary and will be there only during
construction stage. Thus it is anticipated that there will be not much impact of the project
on existing traffic load.
Moreover from air pollution point of view, increase in a maximum of 3% PCU per day will
be insignificant. Thus it can be said that impact of vehicular movement due to material
and manpower transport on the air environment will not be there.
Table 5.7b: Increase in Traffic Load on NH10 During Construction Phase
Time Hour
Existing#
PCU
Total
Final
PCU after
Project
Page 208
Chapter 5
Top Officials
Security Personnel
Managerial &
Executives
Skilled & Nonmanagerial
Total
Vehicle
Type
Used
Staff Car
Staff Bus
Staff Bus
Numbers
10
500
890
General Shift
Shift A / B / C (Numbers)
(Numbers)
Project
Car/
Project
Car / Vehicles
Personnel
Bus Personnel Bus per shift
%
Total
%
Total
Total
100
10
10
0
0
0
0
20
100
3
80
400
10
3
60
534
13
40
356
9
3
Staff Bus
300
45
1700
135
779
55
165
921
1
8
The project personnel transportation arrangement between township and the project site
during operation phase will be as follows:
Security Personnel: There will be four fleet of busses, designated as Fleet 1 to 4.
There will be three busses in each fleet - for carrying security personnel between
township and project site. The fleets are designated as Fleet 1 to 4. The duty / plying
roster along with timing is given in Table 5.7d.
Managerial / Executives: There will be four fleet of busses, designated as Fleet 1 to
4. The Fleet 1, 3, and 4 will be having 3 busses and fleet 2 will be having 13 busses
(Table 5.7d), for carrying managerial / excusive staff between township and the
project site.
2012 MECON Limited. All rights reserved
Page 209
Chapter 5
Fleet No.
Security Staff
1
Fleet 1
Buses)
2
Fleet 2
Buses)
3
Fleet 1
Buses)
4
Fleet 3
Buses)
5
Fleet 2
Buses)
5
Fleet 4
Buses)
6
Fleet 3
Buses)
7
Fleet 4
Buses)
From
Transportation
Time
To
Time
Number of
Busses
Running
(3
Township
06.30
06.45
(3
Township
08.30
(3
Project
site
Township
15.15
Project
Site
Township
17.15
Project
site
Project
site
23.15
(3
(3
(3
(3
(3
Managerial / Executive
1
Fleet 1 (3 Township
Buses)
2
Fleet 2 (13 Township
Buses)
3
Fleet 1 (3 Project
Buses)
site
4
Fleet 3 (3 Township
Buses)
5
Fleet 2 (13 Project
Buses)
Site
5
Fleet 4 (3 Township
Buses)
6
Fleet 3 (3 Project
Buses)
site
7
Fleet 4 (3 Project
Buses)
site
14.30
22.30
07.15
Project site
Purpose
06.30
Project site
06.45
08.30
Project site
08.45
15.15
Township
15.30
14.30
Project site
14.45
17.15
Township
17.30
22.30
Project site
22.45
23.15
Township
23.30
07.15
Township
07.30
Page 210
Chapter 5
3
3
3
3
3
3
3
12
3
13
3
3
13
3
3
3
SN.
Fleet No.
From
Transportation
Time
To
Purpose
Time
06.30
08.30
15.15
14.30
17.15
22.30
23.15
07.15
Project site
Number of
Busses
Running
22
06.45
1
3
1
1
3
1
1
1
6
Table 5.7e: Total Staff Busses Plying Between Township and Project Site
Time
From
To Security Personnel
06.30 06.45 3
07.15 07.30 3
08.30 08.45 3
14.30 14.45 3
15.15 15.30 3
17.15 17.30 3
22.30 22.45 3
23.15 23.30 3
Total
7
7
19
7
7
19
7
7
The increase in vehicular movement for manpower transportation of the Atomic Power
Plant operation is shown in Table 5.7f, wherein it can be seen that between 06.00 to
09.00 hrs about 33 busses will be plying additional and between 17.00 to 18.00 hrs
about 19 busses and between 22.00 to 24.00 hrs about 14 busses will be plying
additional on the road. However, as the township is about 4km from the project site, the
volume of traffic indicated will be only for short duration. The existing traffic on this road
is very low and that additional due to plant operation is also low (Table 5.7f). Thus it can
be said that there will be no congestion of traffic on the road leading to project site is
envisaged.
Page 211
Chapter 5
Table 5.7f: Increase in Traffic Density on Road Leading to Project Site from
Township
Time Hour
Existing#
PCU
Total
Final PCU
after
Project
90
26
74
77
3
16
14
18
137
85
82
198
51
37
23
44
121
55
35
106
31
12
7
5
1341
46%
Moreover from air pollution point of view, increase in a maximum of 80 HMV and 20
Cars per day will be insignificant. Thus it can be said that impact of vehicular movement
due to material and manpower transport on the air environment will be insignificant.
Mitigation Measures
No impact envisaged.
It will be ensured that material transport vehicles during construction phase will be
are in good working condition, properly tuned and maintained to keep emission
within the permissible limits and engines turned off when not in use to reduce
pollution.
It will be ensured that all staff busses during operation phase are in good working
condition, properly tuned and maintained to keep emission within the permissible
limits and engines turned off when not in use to reduce pollution.
2012 MECON Limited. All rights reserved
Page 212
Chapter 5
5.5.3.9 Impacts and Mitigation Measures for Oversized Dimensional Consignment (ODC)
During Construction Stage
It can be seen from Table 5.7a, that there will be transportation of only one oversized
consignment per day in the region, which may disrupt the traffic at congestion area. The
oversized consignment vehicle will be directed to ply only during night between 10.00
PM to 05.00 AM, to avoid traffic congestion. Further, the existing road from NH-10 to the
project site will be widened to 9 m and strengthened for transporting the ODC to the
project site. The existing bridge at the canal crossing will be strengthened and any
culvulets or other water body will be provided with suitable bridge system. In this regard
the road from Kajalheri head works is also being evaluated for its suitability to bear the
load of ODC.
5.5.4
5.5.5
Other Measures
The following activities will be carried out in a structured way for the benefit of the
surrounding people through close co-ordination with Personnel Department:
Improvement of social infrastructure through CSR activities like school buildings,
drinking water facilities, street lights, roads, sanitary facilities etc.
Community education & training.
Medical welfare.
Sports activities.
5.5.6
Page 213
Chapter 5
drinking water supply, etc will be established to minimize pollution of soil, water and
public health problems.
5.6
Page 214
Chapter 5
Workers exposed to noise prone areas will be medically checked and proper noise
protective equipment will be supplied to them and will be encouraged to use the
same.
Spot cooling facilities will be provided for workers exposed to high heat generating
areas and will be checked periodically. If necessary, rotation of duties is advised.
Proper attention is given to township water quality so that water borne disease may
not affect residents.
More doctors in hospital plant medical unit will be additionally trained in the field of
occupational health as policy matter.
5.7
Page 215
Chapter 5
Mitigation Measures
A detailed risk assessment, on-site / off-site emergency plans & Disaster Management
Plan is given in Chapter 9. In addition, various fixed installations for Fire Detection,
Alarm and Fire fighting will be available to effectively tackle the situation before the fire
escalates into a conflagration. Regular mock drills will be conducted to check the
effectiveness of the system
5.8
5.8.1
General
At the end of life of a nuclear power plant, a programme of decommissioning of the retire
plant is undertaken. This program which has been evolved well in advance will have
provision for the following:
1. Protect public, plant personals and the environment from possible adverse effect
arising during decommissioning
2. Provide measures for protective storage and/or safe disposal of all radioactive waste
arising out of decommissioning operation.
3. Decontaminate equipment and area to acceptable levels of residual activity.
4. Ensure continued protection to public from residual radioactivity and other potential
hazards in the retired Power plant
5. Methods and procedure, including radiological protection aspect for :
- Dismantling of equipment and structure.
- Collection, handling, processing, packaging, transporting and disposing
radioactive wastes.
6. Access control to radioactive areas to prevent spread of radioactive contamination
and to limit radiation doses to personnel.
7. Physical security of all contaminated and radioactive materials.
8. Surveillance and security of the retired nuclear power plant
9. Equipment, material, services and facilities including remote viewing , cutting and
handling tools and equipment required to implement the programme
10. Documentation and records.
Page 216
Chapter 5
5.8.2
Methods
The methods chosen for decommissioning may include any one or a combination of the
following:
1. Mothballing Putting the nuclear power plant in a state of protective storage after
removal of all fuel assemblies, radioactive fluids and wastes from site.
2. Entombment Removal of all fuel assemblies, radioactive fluids and waste from
site and sealing all the remaining radioactive and contaminated components within
a structure integral with the biological shield.
3. Dismantling of all radioactive and contaminated materials and removal from site
and decontamination of the plant area to acceptable levels for unrestricted use of
the site
5.8.3
Procedure
During decommissioning, work methods and procedures will be established to
demarcate areas which contain radioactive or contaminated material and regulate
access to such areas.
5.8.4
Surveillance
Till such time the retired nuclear power plant area is declared fit by AERB for
unrestricted use, the arrangement for surveillance and security of the plant area will
include:
1. Periodic radiation survey of the plant area to verify that no radioactive material is
getting dispersed around the area.
2. Periodic environmental survey to verify that no significant relapse of radioactive
material to the environment has taken place.
3. Round the clock security to enforce access control and prevent unauthorized entry
to the plant area.
4. Inspection of physical barrier for security.
5.8.5
Documentation
A decommissioning report which includes the below mentioned aspects, is issued after
all relevant operation are complete.
1. Details of decommissioning activities carried out.
2. Problems encountered and solution adopted to overcome them.
3. Final state of individual equipment and systems.
4. Type, Location, movement, quantity, and activity level of radioactive wastes.
5. Type, Quantity and activity of radioactive discharges to the environment.
6. Summary of the results of environmental survey and overall assessment of the
impact on the environment due to radioactive relapses.
7. Statistic of personnel exposures and man-ram consumption.
8. Background radiation level in the plant area after decommissioning.
9. Surveillance security arrangements for the plant area after decommissioning.
Page 217
Chapter 5
5.8.6
Decommissioning Cost
In arriving at the capital cost of nuclear power stations, it is normally not the practice to
include decommissioning cost. In recent year all over the world, operating nuclear power
station has started creating decommissioning fund. A Nominal charge is included in the
unit energy cost which will accumulate with interest over the operating life of the power
station for meeting the estimated cost of decommissioning of the station at the end of its
useful life time. In India, the provision of decommissioning charge was introduced since
1984.
Decommissioning experience so far is limited worldwide and no large scale commercial
nuclear power plant has yet been decommissioned. Based on the various studies
conducted abroad and the information available in India, a cost of 1.25 Paisa / Kwh has
been included as the decommissioning levy in Unit Energy Cost (UEC) for all types of
power station in India. This will be updated from time to time based on evolving
decommissioning experience. With effect from October 1991, the decommissioning levy
is revised to 2 paisa/kwh.
5.9
SN
.
1
Impact
Topics
Physical
Resources
Impact On
Impact Due To
of
Adopted Measures
Air
environment
Release
pollutants
air
Water
environment
Soil
Release of polluted
waste
water,
Deposition of SPM
released, & Dumping
of solid waste
Biological
Resources
Vegetation
Release of polluted
wastewater,
Deposition
of
pollutants released.
Land
acquisition
Land
environment,
Conversion of existing
land use pattern
Chapter 5
SN
.
Impact
Topics
Impact On
Impact Due To
Aesthetics
4
Noise
Habitats
Hazardous
Substance
Habitat,
Surrounding
environment
Transportat
ion
Social
&
Economic
Habitat,
Surrounding
environment
Human,
livelihood,
Education etc
Cultural
resources
Human
Use of equipment
having
operating
sound level more than
the statutory level.
Release of hazardous
chemicals
Release of pollutant,
Improper
traffic
management.
Influx
of
people,
Settlement, Stress on
existing infrastructure
etc.
Influx
of
people,
Settlement
Adopted Measures
green belt will be erected in and around
the plant premises to maintain aesthetics.
Noise Control measures as required have
been envisaged. All noise levels will be
maintained within the permissible statutory
limits.
Incorporation of different process control
systems,
Safety
features,
Alarm
arrangements, and follow up of Disaster
management / Emergency response plan
Use of vehicles meeting the statutory
norms related to emission, proper traffic
management.
No negative impact envisaged. Moreover
additional social improvement activities
have also been planned by the project
management in the region.
No negative impact envisaged.
5.10
5.10.1 General
The assessment of effects of a particular action judgment must be made as to whether
these effects are Significant. Significance is a relative concept, which reflects the
degree of importance placed on the impact in question. Having identified the events
associated with the proposed activity and their potential consequences, the next issue
required to be addressed is the extent to which these make the proposed activity
environmentally significant. In developing the criteria for determining this, the criteria
outlined in the different guidelines for determining the level of environmental impact were
considered.
These criteria entail an assessment of the level of certainty in the prediction of an
2012 MECON Limited. All rights reserved
Page 219
Chapter 5
Category of
Impact
Soil Impact
Air Impacts
Surface &
Ground
Water
Impacts
Natural
Environment
Social
Environment
Fauna
Impacts
Flora
Impacts
Sensitive
Area Impacts
Community
Resource
Type of Event
Likely Consequences
Soil earthworks
Emissions to air (eg. dust,
SO2, NOx gases etc)
Water extraction
Page 220
Chapter 5
Aspect of
Environment
Category of
Impact
Impacts
Cultural
Impacts
Heritage
Impacts
Community
Health
Impacts
Community
Welfare
Impacts
Economic
Environment
Natural
Resource
Impacts
Type of Event
Disturbance to natural or
man made features of an
area
Disturbance to aboriginal
sites
Air emissions
Noise and vibration
Water contamination
Potentially
hazardous
operations
(eg.
high
pressure
pipelines,
hazardous
substance
storage)
Altering economy of a
region
Altering employment rate
within a community
Disturbance of natural
resources
of
other
industries in the region
Altering existing land use.
Likely Consequences
Disadvantage
groups
within
the
community; Loss of recreational amenity
of a region
Reduction in aesthetic and recreational
value of area
Changes to community make up;
Changes in community cultural identity
and values
Changes to aesthetic value of area;
Changes to historical value of area
Loss of aboriginal affiliation with an area
Health problems in the community
Discomfort to local community;
Health risk to local community
Health and safety risk to local community
b)
c)
d)
Page 221
Chapter 5
e)
The likelihood at which the events that can potentially result in the consequences are estimated
to occur.
Stakeholder Concerns of event(s) & consequence(s)
The extent to which the stakeholder perceptions, views and concerns of the events and their
consequences associated with the activity is known.
As a first step, the level of certainty in the prediction of these issues has been
determined and categorised as Low, Medium or High as defined in Table 5.11.
Table 5.11: Level of Certainty in the Prediction of Activity Events and their
Associated Consequences
Low
Medium
High
The level of certainty for the above issues for each event is then determined. For ease of
assessment, the results has been tabulated as shown below in Table 5.12
Page 222
Chapter 5
Identify events associated with the proposed activity and any potentially
environmentally adverse consequences associated with these events
Predictability Criterion
Assess the level of certainty in the prediction of the activity events and their
associated adverse environmental consequences in relation to their:
Size
Scope,
Duration,
Likelihood and
Stakeholder Concerns
Manageability Criterion
Assess the level to which any adverse consequences for each event can be
managed in relation to :
Being avoided;
Likelihood of occurring;
Duration;
Size and scope;
Cumulative effects;
Stakeholder concerns
Determine the environmental significance scores for each event against the
predictability and manageability criterion (Table 5.11 and 5.15 respectively).
Ascertain the level of environmental significance (Low, Medium or High) for each
event (environmental significance matrix : Table 5.16).
Classify level of Environmental Impact of the overall proposed activity on the basis
of the level of environmental significance of each event.
Figure No. 5.4: Steps for Assessment of Significance of Environmental Impacts
Page 223
Chapter 5
2
3
4
5
Predictability Criterion
All of the issues outlined in Table 5.9 have been fully addressed; all events and their
consequences associated with the activity have been accurately predicted to a high
level of confidence.
There is a mixture of high and medium certainty of the issues. No issue is of low
certainty.
All issues are of medium certainty.
There is low certainty in at least 1 of the issues for either the events or their potential
environmental consequence(s).
There is low certainty in all of the issues for either the events or consequences.
Scope
Duration
Frequency
Significance
score
Size
Stakeholder
Concerns
High
High
Medium
Medium
High
High
High
High
Med.
Med.
High
High
High
High
Med.
Med.
High
High
High
High
Med.
Med.
High
High
High
High
High
High
High
High
1
1
2
2
1
1
High
High
High
High
High
High
High
High
High
High
1
1
High
High
High
High
High
High
High
High
High
High
1
1
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
1
1
1
Page 224
Chapter 5
Scope
Duration
Frequency
Significance
score
Size
Stakeholder
Concerns
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
1
1
1
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
1
1
1
Medium
High
High
Medium
Med.
High
High
Med.
Med.
High
High
Med.
Med.
High
High
Med.
High
High
High
High
2
1
1
2
High
High
High
High
High
High
High
High
High
High
High
High
High
High
High
1
1
Page 225
Chapter 5
b)
c)
d)
e)
f)
Avoidance of Consequences
The extent to which the associated consequences of the various activity events can be totally
avoided.
Likelihood of Event Occurring
The likelihood or probability of an event occurring must also be addressed. If the likelihood of
such an event or sequence of events occurring has been managed so as to be very low and
acceptable to other stakeholders, then it could be said that this is being managed appropriately
and therefore of low significance
If the likelihood of such an event or sequence of events occurring has been managed so as to be
very low and acceptable to other stakeholders, then it could be said that this is being managed
appropriately and therefore of low significance
Duration of Consequences
Whether the consequences can be managed to be short-term needs to be addressed shortterm needs to be defined in the context of the environment within which the potential
consequences are likely to occur. That is, concepts such as the resilience of the environment
would come into consideration.
Size and Scope
Consideration should be given to the extent to which the size and scope of the consequences
can be managed, for example area of land, amount of flora and fauna or number of people
affected by an activity. Consideration should be given to the size and intensity of the impacted
environment relative to the undisturbed surroundings. Also whether the consequences are
potentially catastrophic in terms of human and environmental well being, for example wide
scoping and irreversible consequences.
Cumulative Effects
This includes any cumulative effects of the consequences, for example, the number of individual
activities, which individually may not pose a significant environmental risk but collectively their
potential consequences may be very significant in a particular region.
Stakeholder Concerns
The level of severity of the environmental consequences perceived by stakeholders (e.g. the
outrage effect).
Table 5.15 outlines some basic questions, which can be used to address the above
issues.
Table 5.15: Questions for Addressing Issues under Manageability Criterion
Issues
Avoidance
of
consequences
Likelihood
of
event
Duration
of
consequences
Size and scope
Cumulative
effects
Questions
Can the potential adverse environmental consequences be avoided; or are there is
no such consequence? (Yes or No)
What is the probability of an event occurring, which may result in the adverse
environmental consequence(s)? (Low, Medium or High on the basis of the results of
the risk assessment carried out in accord with relevant standards)
Are the consequences likely to be Short, Medium or Long term?
Can the consequences be managed so as to be small or confined to a designated
area? (Small or Confined?) If they are not small or confinable are the consequences
potentially catastrophic? (Wide Scoping and Irreversible).
Is it likely that the potential consequences of the proposal in conjunction with those
of other existing activities are likely to pose a higher and unacceptable risk to the
environment than if the individual activities where carried out on their own?
Page 226
Chapter 5
Issues
Stakeholder
concerns
Questions
Is there any major concern of other stakeholders on any of the consequences of the
proposed activity?
3
4
Manageability Criterion
Adverse consequences of the various events associated with the proposed activity
can be totally avoided, or it is highly unlikely that the events will ever occur.
Adverse consequences can be managed to be short-term. Short-term needs to be
defined in the context of the environment within which the potential consequences are
likely to occur.
Adverse consequences are not or cannot be managed to be short-term, but they can
be confined so as to be insignificant in terms of size and scope relative to the
surroundings.
Adverse consequences in conjunction with those of existing activities pose significant
cumulative effects. Or Consequences are significant in terms of duration and/or size
and scope relative to surroundings.
Consequences are potentially catastrophic. Or There is high stakeholder concern on
the severity of the consequences. Catastrophic in this context means wide scope and
long term or irreversible consequences such as death or serious injury to many
individuals or permanent adverse change to the environment.
A step-by-step outline of the use of Tables 5.15 & 5.16 to assess the level of
environmental significance for each of the events associated with the proposed activity
against the manageability criterion is suggested as follows.
Step1: Where potential adverse consequences can be totally avoided; or where there
are no adverse consequences associated with the events of the activity; or where there
is a low likelihood of an event occurring which lead to adverse consequences being
realised, then the event would be considered as being of low significance. In this case a
significance score of 1 should be assigned.
Step 2: Where potentially adverse consequences cannot be totally avoided or where
their likelihood of being realised is not low, consideration needs to be given to the
duration of the consequences. If the consequences can be managed to occur only for
short term in the context of the environment within which they will occur. In such cases a
significance score of 2 should be assigned.
Step 3: If the consequences are not short term, then the question of whether or not they
2012 MECON Limited. All rights reserved
Page 227
Chapter 5
can be confined within a designated area, which is relatively small, compared to the
surrounding environment needs to be addressed. If they can be confined to being small,
then a significance score of 3 is assigned. If they cannot be confined to being small and
are significant in terms of size and scope relative to surroundings and/or duration, then a
significance score of 4 is assigned.
Step 4: Before assigning a 2 or 3 significance score, the question as to whether the
consequences may pose a significant risk to the environment as a result of the
cumulative effects with the consequences of other existing activities needs to be
considered. If it is considered that the cumulative effects are a significant risk, a
significance score of 4 should be assigned.
Step 5: In the case where the consequences are potentially catastrophic in terms of
being wide scoping and irreversible, or where there are major concerns by other
stakeholders of the consequences, then a significance score of 5 should be assigned.
The significance score can then be entered into the significance score column of the
manageability criterion Table 5.17.
Avoidance
Likelihood
Duration
Cumulative Effects
Stakeholder Concerns
Significance Score
No
Yes
Med
Low
Short
Short
Small
Small
No
No
No
Yes
2
2
Yes
Med
Short
Small
No
Yes
No
Yes
No
Low
-
Short
-
Small
-
No
-
Yes
-
1
2
1
No
No
1
1
No
No
1
1
No
Page 228
Chapter 5
Duration
Cumulative Effects
Stakeholder Concerns
Significance Score
No
No
1
1
No
No
No
Med
-
Med
-
Small
-
No
-
Yes
-
2
1
1
No
No
No
No
1
1
1
No
No
Yes
No
Low
Low
Low
Med
Short
Med
Small
Small
Small
No
No
No
Yes
Yes
Yes
2
1
2
2
No
No
No
Low
Med
Small
No
No
1
1
Avoidance
Likelihood
Page 229
Chapter 5
Predictability Criterion
1
L
L
L
L
L
Manageability Criterion
2
3
4
L
L
M
L
L
M
M
M
H
M
M
H
M
M
H
5
H
H
H
H
H
NATURAL ENVIRONMENTAL
IMPACTS
Soil Impacts
Earthworks
Contamination (eg spills)
Air Impacts
Air emissions
Surface/Ground Water Impacts
Water extraction
Water contamination
Altering drainage patterns
Fauna Impacts
Disturbance to species
Disturbance to habitats
Flora Impacts
Disturbing native flora species
Clearing extensive areas of native
vegetation
Sensitive Area Impacts
Disturbance to National Parks
Disturbance to World Heritage Areas
National and/or worldwide register or
Predictability
Criterion
Score 1-5
(Table 5.12)
Manageability
Criterion
Score 1-5
(Table 5.16)
Level of
Environmental
Significance H:
High M: Medium L:
Low (Table 5.18)
1
1
2
2
L
L
2
1
1
1
2
1
L
L
L
1
1
1
1
L
L
1
1
1
1
L
L
1
1
1
1
1
1
L
L
L
Page 230
Chapter 5
convention areas
SOCIAL IMPACTS
Community Resource Impacts
Public infrastructure
Land use
Changes to visual attributes of area
Cultural Impacts
Changes to demographic structure of
area
Heritage Impacts
Disturbance to natural features
Disturbance to man made features
Disturbance to aboriginal sites
Community Health Impacts
Air quality changes
Noise and vibration
Changes to water quality
Hazardous operations introduced
ECONOMIC IMPACTS
Community Welfare Impacts
Wealth and employment
Natural Resource Impacts
Disturbance of natural resources of
other industries
Altering existing land use
Predictability
Criterion
Score 1-5
(Table 5.12)
Manageability
Criterion
Score 1-5
(Table 5.16)
Level of
Environmental
Significance H:
High M: Medium L:
Low (Table 5.18)
1
1
1
2
1
1
L
L
L
1
1
1
1
1
1
L
L
L
2
1
1
2
2
1
2
2
L
L
L
L
Conclusion
The level of environmental significance as mentioned in Table 5.19 is the potential to damage
environment. As such all the impacts of the project on various elements of environment can be
predicted with significant certainty and are manageable therefore the chances of damage to
environment due to the plant activities are low as shown in Table 5.19.
Page 231
Chapter 5
6.1
INTRODUCTION
All new or expansion projects may be accompanied by certain undesirable
consequences requiring mitigative measures. Since the objective of environmental
impact assessment is to ensure that development proceeds hand in hand with
environmental conservation so as to achieve sustained growth, it becomes imperative
that a proper mitigative vis--vis environmental control measures are adopted at the
planning and implementation stage itself. Environmental control measures are
necessary for any major projects to maintain environmental balance and to check
possible harmful effects. These control measures are of multidisciplinary dimensions and
varies with type of projects. Therefore, the measures described in this report are to be
regarded as good beginning and depending upon the situations, continuing advice is to
be updated. In this part of the report environmental management plan has been worked
out based on present baseline status, and environmental impact assessment as
presented in the environmental impact assessment part of the report. It has already
been indicated earlier in the EIA part that a number of environmental factors needs to be
considered covering ambient air quality, water pollution, solid waste management, social
factors, etc. The technological environmental control measures envisaged for the
proposed project are described in following text.
Anticipated releases of hazardous substances like radioactive materials and fissile
materials to the environment and its impact have been discussed in previous chapters.
Reducing/ regulating releases to the stipulated levels and/or mitigation of consequences
of releases that occur call for incorporation of several engineered features and for the
adoption of appropriate work practices, too. This chapter deals with these aspects.
Conventional waste management is also dealt with in this chapter.
As in the previous chapter, the measures are discussed separately for each phase of
project activity.
6.2
CONSTRUCTION PHASE
The site is at Gorakhpur Village, Fatehabad, Haryana, which is a green-field site. During
construction phase, the environmental pollution is not expected to be significant and
would be of short duration. The project site is agricultural land and due compensation
will be paid to the land owners for the same. The site is at Gorakhpur Village,
Fatehabad, Haryana, which is a green-field site.
During site clearing, site-stripping activity will be carried out during non-monsoon season
to avoid any discharge of soil or silt to nearby surface water bodies. Topsoil excavated
will be stored separately for later use.
Page 232
Chapter 6
OPERATIONAL PHASE
The basic design of the Atomic Power Plant allows for planned / controlled release of
radioactive or chemical pollutants to the environment within statutory limits. There could
be accidents and off normal situations that may have a potential for large uncontrolled
releases. APP employs a twofold approach in design to deal with such situations.
The first approach aims to avert such situations to the best extent possible. This is done
by monitoring and rigorously controlling the plant operating conditions. Moreover, design
features such as process and equipment selection also play a role in this context.
The second approach aims at designing the facility in such a way that even if the event
were to occur, the resulting unplanned releases are contained as far as practical.
Provisions are made for directing the releases along planned flow paths, thereby
permitting their collection and treatment before discharge to the environment. This is
facilitated by handling / processing radioactive material in confined space, the
confinement being assured by providing multiple barriers between the environment and
the radiation sources. The multiple barrier approach is applied not only in processing,
but also in storage of hazardous materials / wastes. The sections that follow discuss the
use of multiple barriers as mitigative measures under normal plant operation.
Apart from the steps taken to avert / contain unplanned releases, the design provides for
the reduction of pollution burden by minimizing the quantum of wastes generated in
normal operation. These are also illustrated in the sequel.
6.3.1
Page 233
Chapter 6
not accessible. The SG room, Pump Room (PR) and Fuelling Machine (FM) vaults areas
fall under this category. Rest of the areas fall under the category of low enthalpy areas
and are normally accessible except moderator room, Fuel Transfer (FT) rooms, Delayed
Neutron Monitoring (DNM) and FM service areas (FMSA) during communication with FM
vault.
Double containment philosophy has been followed in RB. The containment system
consists of an inner (primary) containment enveloped by an outer (secondary)
containment. The Primary Containment is provided with Carbon Steel (CS) liner to
reduce leak rate. The annulus between the inner and outer containments is kept at a
slightly negative pressure with respect to the atmosphere so as to minimize ground level
activity releases to the environment during an accident condition.
The purpose of containment building during normal operation is to:
Provide an envelope around the structure housing / supporting Calandria, end
shields, reactivity mechanisms, PHT and moderator systems, fuelling systems and
various associated systems.
Provide shielding, as also to permit access to equipment within the containment
building under reactor operating / shutdown conditions.
Provide shielding, as also to permit access to equipment within the containment
building under reactor operating / shutdown conditions.
To keep the release of radioactivity during normal operation within prescribed limits.
To control the spread of radioactive contamination, the plant is divided into three distinct
radiation zones, classified according to their potential for radioactive contamination and /
or radiation exposure.
The Zoning Philosophy is Implemented as Follows :
A single point entry is provided. This is in the Zone-1 area of the nuclear building.
Personnel and material movement from higher to lower zone and vice-versa
permitted in sequence only.
Barriers and radiation monitors are provided at inter-zonal boundaries for effective
control of spread of contamination.
Decontamination Facilities :
For personnel decontamination, showers have been provided in Zone 2.
A special decontamination room near the main airlock of each unit is provided for
highly contaminated personnel.
Equipment decontamination facility is provided at 100m elevation in Waste
Management Plant (Zone-3).
6.3.2
Page 234
Chapter 6
The areas in the plant are divided into three zones1 based on the based on increasing
contamination potential. Ventilation system is designed to maintain pressure differential
between various confinement zones and also between the confinement zone and the
outside atmosphere so that the direction of the flow of air or gases is from the areas with
lower contamination potential to the areas with higher contamination potential.
For ventilation to be an effective barrier, the confinement of air borne radioactive
particulates, noxious fumes and vapors need to take place as close to the point of origin
as practicable. This is achieved by isolating the ventilation of operating areas, access
galleries etc from that of off gas streams from RB, auxiliary airlock, spent fuel
storage/inspection bay and decontamination centre & resin fixation area in waste
management building, etc.
Other salient features of the ventilation system that go to make it effective are outlined
below.
6.3.2.1 Primary Containment Ventilation System
The Reactor Building (RB) is of double containment [(Primary Containment (PC steel
lined)] and the outer one are Secondary Containment (SC)] as given under Section
6.3.2.2. The PC is further classified into two volumes namely high enthalpy areas (high
radioactivity contamination) and low enthalpy areas (low radioactivity contamination). For
the purpose of contamination control and ventilation requirements, separate high
enthalpy and low enthalpy areas are maintained.
The Primary Containment ventilation system is designed for the following requirements.
To supply cooled, filtered and dehumidified fresh air and exhaust stale air to meet
the fresh air requirement of O&M personnel during normal and Shutdown period.
Ensure flow of air from low active zones to high active zones thus preventing the
spread of activity inside RB.
Zone 1: No radioactive equipments are there in this zone and is kept free of contamination at all
times. All floors of Control Building, Station Auxiliary Buildings, Safety Related and Fire Water
Pump Houses, Turbine Building, EMWP, DOSA, IDCTs and buildings under safety class
NINS are in Zone-1.
Zone 2: This zone includes the service area for active equipment and material that have
potential for contamination and is likely to be contaminated at times. Instrument and control
maintenance shop, chemical control lab., FM testing area, FM maintenance area, shipping flask
loading area, shipping flask wash down area, bay equipment, electrical workshop, Reactor
Auxiliary System, bio-assay, counting room, source room, shift health physics room, emergency
showers & toilets in Nuclear Building, heavy water up-grading plant, exhaust ventilation area,
new fuel storage and waste management plant facilities excluding decontamination and resin
fixation areas and FM and mechanical workshop are in Zone 2.
Zone 3: This zone contains source of contamination. Contamination in this area is kept
localised and under control by routine cleanup operation, however, some parts are likely to
remain contaminated. The area/room which are grouped in this zone are RB, auxiliary airlock,
spent fuel storage/inspection bay and decontamination centre & resin fixation area in waste
management building.
Page 235
Chapter 6
Ventilation flow has been decided in such a way as to meet the ventilation requirements,
while limiting heavy water vapor loss & tritium release (through exhaust) at a minimum.
Provision is made to monitor the activity release through stack. In order to ensure
negative pressure in PC with respect to SC and outside atmosphere, only exhaust fans
are provided in the ventilation system.
Provision is made to isolate moderator room and FM service areas from PC ventilation
system and connect them to Heavy Water Vapour Recovery (HWVR) system by
providing air operated dampers in supply and exhaust ventilation lines and also in
branch lines connecting these areas to dryer. The exhaust from FT room is passed
through a Combined HEPA and Charcoal filter to take care of lodine release, if any. To
reduce the dust ingress into the PC, filers with minimum 90% efficiency down to 10
microns are provided at the intake. The exhaust to the stack is through pre filters
(designed for 99% efficiency down to 5 microns) and HEPA (designed for minimum
99.97% efficiency down to 0.3 microns) filters.
6.3.2.2
6.3.2.3
Page 236
Chapter 6
Heavy water vapor recovery system also helps in reducing the tritium activity levels in
pump room, fuelling machine vaults, fuelling machine service areas, moderator room,
delayed neutron monitoring room, fuel transfer room, fuelling machine valve station, etc.
High enthalpy area contains all high enthalpy heavy systems and includes pump room
(PR), fuelling machine vaults (FMVs) and fuelling machine service areas (FMSAs) when
connected with FMV. These areas are generally accessible only during shutdown period
of the reactor.
Low enthalpy areas like PHT equipment room, feed pump equipment room, moderator
room, delayed neutron monitoring room, fuel transfer rooms, north and south galleries,
staircase, FMSAs (when the area is not connected with FMV) are normally accessible
during reactor operation with a few exceptions. Some areas like moderator room,
delayed neutron (DN) monitoring rooms, fuel transfer (FT) rooms are not accessible
during normal operation.
Different areas in PC are connected to heavy water vapor recovery system, in which
heavy water vapors are recovered as downgraded heavy water condensate. Typically
each dryer consists of adsorption & regeneration circuits, ducting and condensate
collection system piping. Purge dryer is provided to maintain slight negative pressure in
FMV & Pump room with respect to accessible areas.
6.3.2.4
Page 237
Chapter 6
6.3.2.6
Page 238
Chapter 6
All these stack-monitoring instruments are located in a room known as the Stack
Monitoring Room, which is located, near the stack. This location provides low radiation
background. Iso-kinetic probe draws the air sample, which successively passes through
the filter detector assemblies of the air particulate and iodine activity monitors.
Subsequently, it is led to the inert gas monitor chamber and then routed back to the
stack. The data from the above monitors are analyzed by a signal-processing unit, which
gives release rate and integral releases over a set period. These are also compared with
set levels and alarms are generated if the activity exceeds the set levels.
Permissible Gaseous Discharge Limits
The radiation dose limit for the general pubic at the fence post due to operation of all
facilities within the site through all pathways is 1 mSv/y (100 mrem/y).
The annual average rate of discharge of gaseous radioactive effluents from all the units
of 700 MW(e) shall not exceed the following limits. Corresponding dose to the public at
1.0 Km boundary is also given.
Gaseous Radio-active Effluents
Tritium
C-14
Stack Release
4X700 MWe unit
GBq/d
2.02E+04
1.08E+01
1.10E+04
7.66E+03
2.02E-01
2.02E-01
Total
Dose at Exclusion
Boundary (mSv/y)
Adult
Infant
1.61E-02
1.61E-02
9.28E-03
9.28E-03
3.04E-02
4.56E-02
3.72E-02
5.58E-02
4.70E-03
5.74E-02
4.12E-02
8.00E-02
1.39E-01
2.64E-01
Radioactive gaseous effluents when averaged over one day, shall not exceed ten times
the annual average release rates specified above.
6.3.2.7
Page 239
Chapter 6
differential pressure in Cells and Glove boxes, face velocity in front of fume hoods,
pressure drop across filter banks, (ii) checking the working of the normal operating
sequence that would bring ventilation systems into action and (iii) checking the transfer
to alternative power sources when regular power is interrupted.
The materials of construction for the ventilation systems are carefully selected to
withstand corrosion particularly when associated with chemical processes, offer fire
resistance, ensure long operating life to avoid frequent replacement of contaminated
equipment and enable smooth surface finish to aid in decontamination.
6.3.3
6.3.3.1 General
The waste management design philosophy is based on the principle of ALARA (As low
As Reasonably Achievable). The underlying philosophy for radioactive waste
management is based on three major approaches, namely,
a. Dilute and Disperse: This approach is employed for the discharge of potentially
active liquid wastes (dilution is by water addition) and treated gaseous wastes
(dilution is by ventilation air). In this case, harm that can be caused by radio-nuclides
is brought down to an acceptable or insignificant level.
b. Delay, Decay and Disperse: All short-lived radio-nuclides are rendered harmless by
storing them for some time and allowing them to decay. The cooling of spent fuel
inside the reactor for 8 months may be cited as examples of this.
c. Concentrate and Contain: Nearly 99.9% of radio-nuclides with medium and long
half-lives are concentrated to reduce the waste volume, immobilized, sealed in
containers and then stored away inside engineered structures. The storage period is
sufficiently long for the radio-nuclides to decay.
Since bulk of the waste is going to be concentrated and contained, the third approach
needs to be looked at a little more closely. So long as the integrity of the isolation of
radio-nuclides is preserved, no harm to the environment or living organisms is expected.
Therefore, engineered measures aim to make the chance of failure of isolation very, very
low. This is done by making use of multiple barriers each of which has low failure
probability. Even if a failure of multiple barriers were to occur, the geological setting
selected for eventual disposal ensures that migration of radio-nuclides are retarded so
much that sufficient delay and decay would occur.
Though complete prevention of radioactive waste generation is a difficult task, keeping
the waste generation to the minimum practicable is an essential objective of radioactive
waste management. In doing so, it is essential to minimize waste generation in all the
stages of a nuclear power plant. Waste minimization refers to waste generation by
operational and maintenance activities of plant and secondary waste resulting from
predisposal management of radioactive waste. Nuclear effluents are being given the
Page 240
Chapter 6
Classification
Potentially
Active
Waste (PAW)
Active
Non-chemical
Waste (ANCW)
Category
I, II
I, II, III
4.
5.
2.
3.
I, II
I, II
I
Sources
Showers from Nuclear building and upgrading plant, wash
room and laundry waste
Equipment and floor drains from Nuclear building, drains
from decontamination centre and other areas of WMP and
vent exhaust room. Laboratory rinses and washes.
Laboratory solutions from nuclear building and
decontamination centre drains.
D 2O upgrading reject, moderator room sump in RB, drains
from heavy water handling areas in Nuclear building.
Liquid scintillation counters, contaminated oil, grease, etc.
Page 241
Chapter 6
Waste Categorization
Categorization of liquid waste streams based on radioactivity concentration (as approved
by AERB) is as follows :
Category I :
Category II:
Category III:
Category IV:
Category V:
Gross beta activity more than 1 x 104 Ci/ml (3.7 x 108 (MBq/m).
This category waste is heat generating waste. Shielding,
treatment and cooling is required for such wastes. However waste
of this category is not encountered in PHWRs.
The quantity of liquid waste in each classification and the treatment methods are given in
Table 6.1b.
Table 6.1b: Estimated Volumes of Liquid Waste Generation at HAPP 1 & 2
Waste stream
Quantity
m/day
Activity levels
(Bq/ml)
Gross Tritium
-
1.0 Potentially Active Waste (PAW)
Showers
30
3.7E-3
250
Washings
20
3.7E-2
250
Laundry
25
3.7E-1
100
2.0 Active NonChemical
Waste
(ANCW)
12
1.85
1850
Activity inventory
Gross
- (KBq)
Tritium
(MBq)
111
740
10360
7500
5000
2500
22200
2220
Treatment
Chapter 6
Waste stream
Quantity
m/day
Activity levels
(Bq/ml)
Gross Tritium
-
Activity inventory
Gross
- (KBq)
Treatment
Tritium
(MBq)
discharged
stack.
through
1.85
11E4
3700
222000
0.371
7.4E4
2220
444000
- Do -
1850
18500
Occasional
Occasional
0.037
1850
Occasional
Occasional
39331
683220
Page 243
Chapter 6
provided in the pipe line to ensure thorough mixing of treated waste with plant water
discharge system, before it gets discharged.
Liquid waste discharges are made in batches normally on single shift basis. Availability
of blow down flow is ensured through control logics and administrative control before
commencing of discharge of treated waste. The activity concentration of liquid waste
being discharged is monitored by an online activity monitor located on treated waste line
in WMP (before injecting it in plant water discharge system) in addition to sampling and
analysis carried out in laboratory. On attaining set level of activity the activity monitor
fitted in the discharge line will trip the discharge pump.
Liquid wastes having relatively high tritium and Beta gamma activity like Tritiated Waste
(TTW) generated from Upgrading plant rejects, Moderator room sump & Clean-up
system and Active Non Chemical Waste (ANCW) generated from Equipment
decontamination system of WMP, chemical laboratory & SFSB cask wash down area, of
less volume will be evaporated, diluted with exhaust air and discharged through stack to
air route. This quantum of liquid waste activity constitutes a major portion of the total
activity in the liquid waste. Therefore only less than 10% of total activity contained in
major volume of liquid effluent activity from HAPP 1&2 will be added to the liquid route
discharge point.
Treatment and Disposal Liquid Waste through Air Route (Evaporation System)
Liquid effluent having relativity higher activity are treated by filtration and ion exchange
process and disposed through air route using Evaporation system. Streams like ANCW,
ACW and TTW, after filtration, will be diverted to a synthetic ion exchange column to
remove the dissolved Beta-gamma activity and then stored in evaporation system feed
tank. These polished tritium bearing liquid waste streams (free of gross beta activity) are
sent to a steam heated evaporator with a controlled flow rate of 1.4 m/hr. This vaporized
stream is then injected into the ventilation exhaust ducting leading to 100 m high stack.
Evaporation of effluents having relatively higher level of activity ensures the discharges
through water route are kept at minimum. The air route mode of disposal offers unique
advantage of higher release limits per unit of dose allocation as compared to liquid route.
This mode of disposal suits inland site where water body is scarce and extensively used
by the surrounding population. The liquid waste disposal scheme is shown in Fig. 6.1.
Liquid Discharge Limits
For the plant, at the common discharge point the following discharge limits are
considered.
Radionuclide
Tritium
C-14
Cs-137
Sr-90
Total
Page 244
Chapter 6
Page 245
Chapter 6
for solid waste provided in WMP include processes like spent resin management for
resins from Primary Heat Transport (PHT) System, Moderator system, end shield
cooling system, calandria vault cooling system, SFSB cooling and purification system,
cementation of liquid filters / sludge and compaction of compressible wastes.
The waste after treatment / conditioning is disposed off in engineered barriers. There are
different types of structures depending on the radiation level encountered, like stone
lined earth trenches, RCC vaults / trenches and tile holes / high integrity containers
(HIC) located at the Near Surface Disposal Facility (NSDF), depending upon their
surface dose rate. The structures serve as engineered barriers preventing migration of
radioactivity into ground water, and together with the surrounding soil provide the
required radiation shielding. Some of the wastes may have to be stored temporarily in
specially designed facilities.
Solid Waste Categorisation
Solid waste is categorised on the basis of its surface radiation dose-rate and its physical
characteristics which call for specific treatment and handling processes. These are :
Cat. I : Waste with surface dose rate up to 2 mSv/h. For the purpose of segregation of
source, Cat. I waste is further divided into two groups viz.
a. Dose rate less than 0.02 mSv/hr Disposed off in stone lined earthen trenches.
b. Dose rate more than 0.02 mSv/hr and less than 2 mSv/h Disposed off in RCC
trenches / Vaults.
Depending upon the physical nature, these wastes are also classified as :
a. Compactable waste and
b. Non compactable waste.
c. Combustible waste
Cat. II : Waste with surface dose rate more than 2 mSv/h but less than 0.02 Sv/h.
Cat. III : Waste with surface dose rate more than 0.02 Sv/h. The category of waste is
further sub-divided into two groups viz.
a. Cat. III A : Waste packages with surface dose rate up to 0.5 Sv/h, and
b. Cat. III B : Waste packages having surface dose-rate more than 0.5 Sv/h.
Resin Transfer and Fixation System
Radioactive Spent Ion-Exchange resin is generated from Primary Heat Transport,
Moderator, End shield / calandria vault cooling and Spent Fuel Storage and Inspection
Bay (SFSB) clean-up systems in PWHR type reactors. These resins vary widely in dose
rate, radio nuclide content and their concentrations.
Disposal of Resins with Short Lived Radioactivity
Spent resins are transferred from the Ion Exchange vessel (Stainless Steel Hopper) of
moderator, End Shield / Calandria vault cooling system, into a Carbon Steel Hopper,
dewatered by compressed air and these CS Hoppers are disposed (after closure of all
Page 246
Chapter 6
Page 247
Chapter 6
by two stage water scrubbers before discharging it through 30m tall chimney.
Continuous monitoring system is provided to monitor the gas emitted from the chimney.
Solid Waste Disposal
Solid wastes after conditioning will be disposed off in the Near Surface Disposal Facility
(NSDF) area in earth trenches / RCC trenches / vaults / tile holes / HIC depending upon
their surface dose rate. As a matter of practice packages having higher activity are
disposed off at the bottom of trenches / vaults will be suitably sealed permanently as per
established practices. These data will be utilised to assess the safety aspects of the
waste repository. Necessary geo-hydrological & soil analysis studies for the NSDF site
will be carried out to assess the safety of NSDF containing solid waste generated from
50 years of plant operation. Proper surveillance of Solid Waste Management Facility is
carried out through bore holes provided all around the NSDF to check the integrity of the
engineered barriers through periodic water sampling. Additional array of boreholes will
be provided, whenever the facility is augmented. The NSDF area is fenced and
necessary access control procedures are established. A waste assaying is carried out to
assess and record the radioactive content in each conditioned waste packages before
disposing them. Name of the vault and their identification also recorded.
The dose rate on the top of the sealed earth trenches and RCC trenches / vaults would
not exceed 0.01 mGy/h.
Near Surface Disposal Facility (NSDF)
The engineered measures for solid waste disposal are graded in accordance with the
level of radioactivity activity encountered. An overview of these is presented below.
Stone Lined Earthen Trenches: The Suspected or low level solid wastes (surface dose
less than 0.02 mSv/h, Cat-I) after being immobilized in cement matrix are buried in stone
lined earthen trenches. These are shallow excavation in soil of size 5 m x 2.5 m x 2 m
deep. Filled trenches are covered by brick and overlain by soil.
Reinforced cement concrete (RCC) trenches: are used for disposal of part of Cat-I
and Cat-II waste (up to 0.5 Sv/h). These trenches have water-proof tiles at the bottom
and on lateral surfaces, and the top is closed with RCC covers. Typically, these are
constructed in a battery with four rows of sizes 1.2 m (depth) x 1.8 m (width) x 20 m
(length). The trenches are usually built zone by zone, each of which would be sufficient
for 3 5 years of operation. Fig. 6.3 shows a schematic of the RCC trench.
The site selected for NSDF is such that the ground water table is below the planned
storage depth, the soil has high enough cation exchange capability (CEC) to retain or
slow down the migration of radio-nuclides in the event of their leakage, and surface
water sources are at least 100 m away. Moreover, back fill materials with large CEC
could also be used all around the RCC trench / tile hole zones to enhance retention.
Bore holes are provided around NSDF to monitor activity leaking into ground water.
The net volume of solid waste generated (after due processing) per year that would be
disposed off in NSDF is around 514m3/yr.
2012 MECON Limited. All rights reserved
Page 248
Chapter 6
Page 249
Chapter 6
Page 250
Chapter 6
Feed to
incinerator
Main
combustion
chamber
(primary
rotating
chamber)
Post
combustion
chamber
(secondary
stationery
chamber)
Heat
recovery
system
(heat
exchanger
/spray dryer)
Gas cleaning
system
(bag filter,
Scrubber)
Stack
Fig. 6.4: Process Flow Diagram for Package Rotary Kiln Incinerator
6.3.3.4 Spent Fuel Storage and Management
Spent Fuel
Spent fuel is removed from the reactor core and transferred to spent fuel inspection bay
(SFIB) where it is inspected for leaks / pin holes / damage. It is then stored in spent fuel
storage bay (SFSB) which is under continuous radiological surveillance. The spent fuel
is stored in SFSB till it cools down to dry storage level (about 5 years). Subsequent
action on the spent fuel is dictated by the policy of the Department of Atomic Energy /
Government of India.
2012 MECON Limited. All rights reserved
Page 251
Chapter 6
6.4.1
General
Green belt, is an important sink for air pollutants, it also absorbs noise. Enhancing green
cover not only mitigates pollutants but also improves the ecological conditions /
aesthetics and reduces the adversities of extreme weather conditions. Trees also have
Page 252
Chapter 6
major long-term impacts on soil quality and the ground water table. By using suitable
plant species, green belts can be developed in strategic zones to provide protection from
emitted pollutants and noise.
Plant species suitable for green belts should not only be able to flourish in the area but
must also have rapid growth rate, evergreen habit, large crown volume and small /
pendulous leaves with smooth surfaces. All these traits are difficult to get in a single
species. Therefore a combination of these is sought while selecting trees for green belt.
The green belt should be planted close to the source or to the area to be protected to
optimize the attenuation within physical limitations.
The green belt / cover will serve the following purposes:
Compensate the damage to vegetation due to setting up and operation of the
proposed plant.
Prevent the spread of fugitive dust generated due to project and allied activities.
Attenuate noise generated by the project.
Reduce soil erosion
Help stabilise the slope of project site.
Increases green cover and improve aesthetics.
Attract animals to re-colonise the area.
6.4.2
Selection of Species
The species for plantation have been selected on the basis of soil quality, place of
plantation, chances of survival, commercial value (timber value, ornamental value, etc.),
etc. It is to be noted that only indigenous species will be planted. Exotic species like
Eucalyptus and Australian acacia will not be planted. The species for green belt /
vegetation cover development will be selected in consultation with State Forest
Department and State Soil Conservation Department. Mixed plantations will be done
keeping optimum spacing between the saplings. However, the species suitable for
planting in the area as recommended by Central Pollution Control Board in their
publication Guidelines for Developing Greenbelts (PROBES/75/1999-2000) are
given under various heads here under.
6.4.3
Plantation Scheme
Plant saplings will be planted in pits at about 2.0 m to 3.0 intervals so that the tree
density is about 1500 trees per ha. The pits will be filled with a mixture of good quality
soil and organic manure (cow dung, agricultural waste, kitchen waste) and insecticide.
The saplings / trees will be watered using the effluent from the sewage treatment plant
and treated discharges from project. They will be manured using sludge from the
sewage treatment plant. In addition kitchen waste from plant canteen can be used as
manure either after composting or by directly burying the manure at the base of the
plants. Since, tests have shown that availability of phosphorus, a limiting nutrient, is low,
phosphoric fertilisers will also be added. The saplings will be planted just after the
Page 253
Chapter 6
commencement of the monsoons to ensure maximum survival. The species selected for
plantation will be locally growing varieties with fast growth rate and ability to flourish
even in poor quality soils.
A total of more than 33% of total project area will be developed as green belt or green
areas in project area and other areas including the residential complex. The widths of
the belt will be >20m along the project boundary, depending on the availability of space.
The proposed Green belt / cover development is shown in Drg. No. HAPP-1 to
4/70000/2002/GA (DR.LWS).Rev.01
A very elaborate green belt development plan has been drawn for the proposed plant.
The areas, which need special attention regarding green belt development in the project
area, are:
1.
2.
3.
4.
5.
6.
Annual winds in the study area are mainly from W, NW, SW and N. Inside the HAPP
works area, the region with high fugitive pollution load are areas around road, parking
areas and go-downs where loading and unloading of different materials takes place.
To arrest the fugitive emissions emitted from above areas tree plantation will be
undertaken in general all around the HAPP but the more in strategic places especially on
E, SE, NE and S of the above areas along with that in other directions. To arrest the
fugitive emissions emitted from such areas, the approach adopted shall be - as
described below and as shown in Fig. 6.5:
Plantation all around close to the units / areas (fugitive emission source) in available
spaces to arrest fugitive emissions at the source.
Considering the HAPP as centre and planting trees in a V in SW-SE; SE-NE; NENW direction [i.e down wind (D/W) of predominant winds, E, SE, NE and S] at
staggered distances in available spaces to arrest fugitive emissions which have not
been arrested by the green belt at the source.
Plantation along the plant boundary - >20m depending on space availability.
Page 254
Chapter 6
Common Name
Babool
Kikar
Khairi
Bougainvellea
Hins
Duranta
Kamayani
Pink Kaner
Jand
Yellow Kaneer
Page 255
Chapter 6
(i) Curtain belt on the outermost boundary comprising tall trees with conical canopy.
(ii) Middle belt of large size trees with globose and spreading canopy and
(iii) Inner belt with medium size trees with spreading or trailing canopy. The desired
minimum thickness of these belts should be as follows:
Location
Outer belt (pollution attenuation)
Middle belt (pollution attenuation)
Inner belt (pollution attenuation and training of winds to middle & outer belt)
Width (m)
30
50
20
Common Name
Acacia nilotica
Acacia senegal
Albizia lebbeck
Azadirachta indica
Dalbergia sissoo
Melia azedarach
Polyalthia longifolia
Kikar
Khairi
Siris
Neem
Shisham
Bakain
Ashok
In the middle belt the following species of trees to be planted 3 m apart, from tree to tree
as well as from row to row:
Scientific Name
Common Name
Albizia lebbeck
Azadirachta indica
Bauhinia racemosa
Cassia fistula
Cordia dichotoma
Dalbergia sissoo
Delonix regia
Ficus benghalensis
Ficus religiosa
Melia azedarach
Siris
Neem
Kachnar
Amaltas
Lasura
Shisham
Gulmohar
Barh
Peepal
Bakain
In the inner belt the following species of trees and shrubs to be planted 2.0 m apart from
tree to tree as well as from row to row:
Scientific Name
Common Name
Acacia jacquemontii
Acacia leucophloea
Babool
Reru
Page 256
Chapter 6
Scientific Name
Common Name
Acacia nilotica
Acacia senegal
Capparis decidua
Carissa spinarum
Prosopis cineraria
Kikar
Khairi
Karir
Hins
Jand
Common Name
Albizia lebbeck
Azadirachta indica
Bauhinia racemosa
Cassia fistula
Cordia dichotoma
Dalbergia sissoo
Delonix regia
Ficus benghalensis
Ficus religiosa
Melia azedarach
Siris
Neem
Kachnar
Amaltas
Lasura
Shisham
Gulmohar
Barh
Peepal
Bakain
4. Plantation around Office Buildings, Stores, Garage etc of the Atomic Power
Complex and the Residential Complex
The species recommended for plantation around various buildings will include:
Scientific Name
Common Name
Albizia lebbeck
Azadirachta indica
Bauhinia racemosa
Cassia fistula
Cordia dichotoma
Dalbergia sissoo
Delonix regia
Ficus benghalensis
Melia azedarach
Polyalthia longifolia
Siris
Neem
Kachnar
Amaltas
Lasura
Shisham
Gulmohar
Barh
Bakain
Ashok
5. Avenue Plantation of the Atomic Power Complex and the Residential Complex
Double rows of avenue trees on the outer side of the footpaths are recommended; an
outer row of shade trees and an inner row of ornamental flowering trees will be planted.
(a) Foliage Trees for Outer Avenue:
Scientific Name
Common Name
Acacia leucophloea
Albizia lebbeck
Reru
Siris
Page 257
Chapter 6
Scientific Name
Common Name
Azadirachta indica
Cordia dichotoma
Dalbergia sissoo
Ficus benghalensis
Ficus religiosa
Melia azedarach
Neem
Lasura
Shisham
Barh
Peepal
Bakain
Common Name
Kachnar
Bougainvellea
Amaltas
Java-ki-rani
Gulmohar
Lagerstroemia
Pink Kaner
Ashok
Yellow Kaneer
6. Plantation in Township
In the 75 ha township there will be about 1700 dwelling units. The areas along the roads
and in vacant spaces will be available for plantation. The species for avenue plantation
will be same as given under Clause 5 above. The design of green belt and the species
all along the township boundary will be from among that given under Clause 2 above.
The species for vacant spaces and office buildings like, clubs, guest house, etc in the
township will be from among the species as mentioned respectively under Clauses 3 &
4 under Section 6.4.3.
6.4.4
6.4.5
Immediately after planting the seedlings, watering will be done. The wastewater
discharges from different sewage treatment plant / out falls will be used for watering the
plants during non-monsoon period. Further watering will depend on the rainfall. In the
dry seasons watering will be regularly done especially during February to June. Watering
of younger saplings will be more frequent. Manuring will be done using organic manure
(animal dung, agricultural waste, kitchen waste etc.). Younger saplings will be
surrounded with tree guards. Diseased and dead plants will be uprooted and destroyed
and replaced by fresh saplings. Growth / health and survival rate of saplings will be
regularly monitored and remedial actions will be undertaken as required.
.
Phase Wise Green Belt / Cover Development Plan
Green belt will be developed in a phase wise manner right from the construction phase
of the proposed project. In the first phase along with the start of the construction activity
the plant boundary, around the proposed waste dumps, and the major roads will be
Page 258
Chapter 6
planted. In the second phase the office building area will be planted. In the third phase
when all the construction activity is complete plantation will be taken up in the plant area,
around different units, in stretch of open land and along other roads.
6.5
CONCLUSION
From the foregoing description it is evident that mitigative measures form integral part of
the design of the Atomic Power Plant. The present plans to mitigate the environmental
impact from radiation and conventional pollutants seem to be adequate and no
additional measurers are likely to contribute effectively.
References
[1] "Manual on Security of Nuclear Power Plants". AERB
[2] "The Physical Protection of Nuclear Material", INFCIRC /225/Rev.1, IAEA Circular
Page 259
Chapter 6
7.1
INTRODUCTION
The monitoring and evaluation of the mitigation measures envisaged are critical activities
in implementation of the Project. Monitoring involves periodic checking to ascertain
whether activities are going according to the plans. It provides the necessary feedback
for project management to keep the program on schedule. The purpose of the
environmental monitoring plan is to ensure that the envisaged purpose of the project is
achieved and results in desired benefits.
To ensure the effective implementation of the proposed mitigation measures, the broad
objectives of monitoring plan are:
To evaluate the performance of mitigation measures proposed in the EMP.
To evaluate the adequacy of Environmental Impact Assessment
To suggest improvements in management plan, if required
To enhance environmental quality.
To implement and manage the mitigative measures defined in EMP.
To undertake compliance monitoring of the proposed project operation and
evaluation of mitigative measure.
7.2
IMPLEMENTATION ARRANGEMENT
The various components of the environment needs to be monitored on regular basis
during construction and operation phase of the project, as per the requirements of
regulating agencies as well as for trend monitoring of the pollutants levels in various
environmental matrices.
7.2.1
7.2.2
Page 260
Chapter 7
At plant level Technical Services Unit (TSU) will look after the environmental matters
and environmental monitoring programme. TSU will work out a schedule for monitoring
and will meet regularly to review the effectiveness of the EMP implementation. The data
collected on various EMP measures would be reviewed by this committee and if needed
corrective action will be formulated for implementation.
TSU will form short term & long term plans for environmental issues, which require
monitoring and effective implementation. The environmental quality-monitoring program
will be carried out in the impact zone with suitable sampling stations and frequency for
non radiological parameters as identified under Section 7.3.
Radiological parameters outside exclusion zone will be monitored by Environmental
Survey Laboratory (ESL) of Health Physics Division (HPD), Bhabha Atomic Research
Centre (BARC). The ESL will be set up at the site, at least 18 months before operation
of the plant units. Environmental Survey Laboratory (ESL) will report to Health Physics
Division (HPD), BARC. The two will periodically report the progress of the environmental
monitoring programme to the Station Director / NPCIL management and AERB for
review and necessary action (if required).
Radiological parameters within exclusion zone will be monitored by Health Physics Unit
(HPU), Chemical Laboratory and Waste Management Unit (WMU) formed at project
level by NPCIL. The radiological monitoring will be reported to Technical Services Unit
(TSU), which in turn reports to Chief Superintend (CS) and CS reports to Station
Director (SD) of the project.
Non-radiological pollutants will be monitored by HPU, Chemical Laboratory and Waste
Management Unit and these will report the results to TSU, which in turn reports to Chief
Superintend (CS) and CS reports to Station Director (SD) of the project.
Monitoring of radiation exposures to occupational workers and the releases to the
environment are controlled by the station and monitored by Health Physics Unit and ESL
within exclusion zone and beyond any exclusion zone, respectively.
During operation stage different issues / components involved in environmental
monitoring programme will be looked upon by Environmental Survey Laboratory (ESL),
Health Physics Unit, Chemical laboratory, Waste management Unit (WMU), Medical
Unit, Civil Maintenance, Maintenance Unit, Horticulture Unit / Service Maintenance,
Central Material & Management, Industrial Safety and Corporate Social Responsibility
(CSR) Unit / Human Resources Group. All the above mentioned units responsible for
different aspects of monitoring will periodically report the progress of the environmental
monitoring programme to TSU for review and necessary action (if required). The
reporting arrangement of different units responsible for environmental monitoring
programme during construction and operation phase is given under Section 7.6.2.
The TSU will monitor and make periodical review of the environmental monitoring
program and in case higher level interface is required will report the matter to EMARC
for higher management intervention.
2012 MECON Limited. All rights reserved
Page 261
Chapter 7
7.3
Page 262
Chapter 7
Air
Parameters
Location
Monitoring
Frequency
of
No. of Samples /
year (Locations X
Monitoring
Frequency)
4x3
Monitoring
Cost / Year
(Rs.)
12x20000
= 240000/-
Page 263
Chapter 7
Compon
ent
Parameters
Location
Monitoring
Frequency
of
Water
Surface Water:
CPCB surface
water criteria;
Ground Water:
IS:10500
No. of Samples /
year (Locations X
Monitoring
Frequency)
4x3
12x20000
= 240000/-
4x3
12x8000
= 96000/-
4x3
12x8000
= 96000/-
Note :
Monitoring
Cost / Year
(Rs.)
12x2000
= 24000/-
12x2000
= 24000/-
4x6000
= 24000/-
4x6000
= 24000/-
7,68,000/Say
8.0
Lakhs
Page 264
Chapter 7
7.5
7.5.1
Radiological Monitoring
7.5.1.1 General
The radiation exposures to occupational workers and the releases to the environment
will be controlled by the facility / HAPP and monitored by NPCIL (Health Physics Unit).
The radioactivity levels in the public domain will be monitored by the Environmental
Survey Laboratory (ESL), Health Physics Division (HPD), BARC to ensure compliance
with the regulatory requirements. The ESL at atomic power project site should be set up
18 months before the start of the actual operation of the unit to generate pre-operational
base line data for comparison as per AERB Safety Guide No. AERB/SG/O-9.
The radiological monitoring program to be followed at HAPP is described under three
separate categories.
Monitoring at the work place
Monitoring on site
Monitoring program in public domain
7.5.1.2
Page 265
Chapter 7
Page 266
Chapter 7
7.5.1.3
7.5.1.4
Watchdog monitors at all entry / exit points to the complex will be installed to detect
movement of radioactive substances. The movement may be a planned one or may
be unintentional as in the case of contaminated persons or goods leaving the area
unknowingly. The signals from the systems would be brought to a health physics
control panel for initiating early action, if needed.
Page 267
Chapter 7
Different types of samples will be collected from the terrestrial and aquatic environs of
the 30km study area covering, canal water, soil, cereals, pulses and vegetation samples.
Typically around 1000 samples will be collected and analysed every year. List of
sampling locations, frequency of sampling and different types of samples to be
monitored during post project period in different zones will be worked out as per the
requirements of AERB. The same for baseline levels in the area as worked out is given
under Section 3.3 of chapter 3.
ii) External Radiation Levels
The external gamma radiation levels will be monitored using integrating type dosimeters,
namely the thermo-luminescence dosimeter (TLD). The list of locations in the
surrounding areas where TLDs will be placed will be as per AERB. The measurement of
accumulated exposure will be done for quarterly periods. The same for baseline levels in
the area as worked out is given under Section 3.3 of chapter 3.
Measurement Techniques and Practices
Radioactivity levels in the environment are very low. Measurement of such low levels of
activity calls for special techniques. These have been developed and standardised over
the years in DAE. Relevant details about the methods of sample collection, quantity to
be collected, sample storage conditions, analytical procedures to be followed etc. are
well documented and are available in the form of a manual.
The environmental survey laboratory (ESL) will have a full-fledged laboratory for
analysing radiological parameters. The conventional pollutants will be monitored by
Chemical laboratory. The list of equipments required for sampling / analysis / monitoring
of conventional pollutants is given under Section 7.6.3. In addition, the list of
equipment/instruments specialty for radiation/radioactivity measurements is given under
Section 7.6.3. Regular inter-comparison exercises between the ESL / Chemical
Laboratory of different APPs in the country will be carried out as a measure of reliability
testing and quality assurance.
iii) Reporting of Results
Dose Assessment: The external, internal and total doses to the members of the public
will be monitored and estimated at various distances from the project as per AERBs
requirements.
Results of the survey carried out by the ESL will be brought out in the form of annual
reports and will be submitted to AERB for inspection and verification of compliance with
regulatory limits on radiation exposure.
7.5.2
Page 268
Chapter 7
(i)
(ii)
(iii)
7.5.3
7.5.3.1
7.5.3.2
7.5.3.3
Page 269
Chapter 7
7.5.3.4
Meteorology
The meteorological parameters will be regularly monitored for assessment and
interpretation of air quality data. The continuous monitoring will also help in emergency
planning and disaster management. The project will have a designated automatic
weather monitoring station. The following data will be recorded and archived:
-
7.5.5
Page 270
Chapter 7
7.5.7
Page 271
Chapter 7
7.5.8
Ambient Noise
Ambient noise shall be monitored at six locations in villages surrounding the proposed
project, once in each month. The villages selected for monitoring will cover the atomic
power plant site and the residential complex.
7.5.9
Page 272
Chapter 7
MONITORING PLAN
7.6.1
Page 273
Chapter 7
2. Solid
disposal
Waste
3. Air
Quality
at
construction site &
surrounding
4. Surface
water
quality
5. Ground
Quality
Water
6. Noise levels at
construction site &
surrounding
7. Soil Quality
8. Environmental
Protection
Measures
Mitigation Measure
Reference to
Contract
Documents
Approximate
Location
Project
Requirement
Construction
site within the
plant
-Do-
Construction
site within the
plant
and
dumping area.
At construction
site
and
surrounding
Bhakra
canal
up & down
stream
of
project site
Up & down
gradient
of
project site
At construction
site
and
surrounding
At construction
site
and
surrounding
All plant units
-Do-
Monitoring
quality
surface
water
-Do-
Monitoring
quality
ground
water
-Do-
-Do-
-Do-
Implementation/Installation of
all Environmental Protection
Measures as envisaged in
Chapter
5
&
7
for
controlling/abating pollution.
-Do-
Time
Frame
Mitigation Cost
Institutional Responsibility
Implementat
Superion
vision
During
construction
stage
Project
Cost
(Environmental
Component)
Contractor
Planning
Section
-Do-
-Do-
Contactor
Civil
Maintenance /
CCE PD
-Do-
-Do-
-Do-
-Do-
-Do-
-Do-
Planning
Section / CCE
PD
-Do-
-Do-
-Do-
-Do-
-Do-
-Do-
-Do-
-Do-
-Do-
Contractor
Industrial
Safety
Contactor
-Do-
-Do-
Contractor
Opration Stage
Page 274
Chapter 7
Planning
Section / CCE
PD
CCE / PD
Civil
Maintenance /
CCE
Planning
Section / CCE
Environmental
Issue/ Impacts
Mitigation Measure
1. Environmental
Protection
Measures
(Radiation levels /
exposure
within
exclusion zone)
2. Ambient radiation /
contamination
monitoring
within
plant area.
3. Effluent Monitoring:
Gaseous
4. Effluent Monitoring:
Liquid Waste
5. Monitoring Waste
Storage Integrity
6. Personnel
Monitoring
Institutional Responsibility
Implementat
Superion
vision
Health
TSU / EMARC
Physics Unit /
Station
/ Chemical Director (SD)
lab / Waste
management
Unit (WMU)
-Do-Do-
Reference to
Contract
Documents
Project
/
Statutory
requirement
Approximate
Location
Time
Frame
Mitigation Cost
Different units
of the operating
plant
Continuously
Project
Cost
(Environmental
Component)
-Do-
-Do-
-Do-
-Do-
Ventilation
stacks
Continuously
-Do-
-Do-
Waste
management
plant
&
discharge
location
of
receiving water
body.
Continuously
-Do-
-Do-
Bore-wells
around waste
storage facility
Quarterly
-Do-
-Do-
-Do-
-Do-
All workers in
side the plant
Continuously
-Do-
Health
Physics
Unit/Medical
TSU / EMARC
/ SD
Page 275
Chapter 7
Health
Physics Unit
/
Online
System
Control
Room
Waste
Management
Unit (WMU)
TSU
/
Operation
Superintende
nt / EMARC /
SD
TSU / EMARC
/ SD
Environmental
Issue/ Impacts
7. Radiation
Monitoring on Site
8. Radiological
Monitoring in the
Public
Domain:
Internal Radiation
Levels & External
Radiation Levels
9. Other
Monitoring
Requirements
:
Occupational
Health and Safety
10. Work Zone Noise
levels
11. Stack
Monitoring
for
Diesel
Generator Sets.
12. Stack
Monitoring
for
Waste
Incineration
Facility.
13. Performance
of
Mitigation Measure
Monitoring
of
gamma
radiation
levels,
continuously through field
mounted
environmental
gamma dose logger
Watchdog monitoring at all
entry / exit points to the
complex
to
detect
movement of radioactive
substances.
Monitoring
of
external,
internal and total radiation
doses to the members of the
public at various distances
from the project.
Reference to
Contract
Documents
-Do-
Approximate
Location
Time
Frame
Mitigation Cost
Specified 10
selected
locations.
Continuously
-Do-
Institutional Responsibility
Implementat
Superion
vision
Unit
Health
-DoPhysics Unit
-Do-
In
different
identified zones
within 30 km
radius of the
project.
Continuously
-Do-
ESL
HPD, BARC /
AERB / SD
-Do-
Periodic
-Do-
Industrial
Safety / HPU
TSU / EMARC
/ SD
-Do-
-Do-
-Do-
-Do-
DG Sets
-Do-
Waste
Incinerator
location.
Through out
operation
stage
Through out
operation
stage
Industrial
Safety group
Pollution
Monitoring
Agency.
Waste
Management
Unit
SD
Environmental
Cost
-Do-
-Do-
Project
Civil
Maintenance
site
-Do-
Page 276
Chapter 7
-Do-
-Do-
Maintenance
Group / SD
TSU / EMARC
/ SD
Environmental
Issue/ Impacts
Mitigation Measure
Reference to
Contract
Documents
Sewage Treatment
Facilities
14. Meteorology
-Do-
17. Maintenance
of
Storm
Water
Drainage System
-Do-
-Do-
-Do-
20. Ground
Water
Quality
conventional
pollutants
-Do-
-Do-
Approximate
Location
Time
Frame
Mitigation Cost
STP/Township
STP
Suitable
location within
plant premises
Institutional Responsibility
Implementat
Superion
vision
Maintenance Group / SD
Continuously
Project
Cost
(Environmental
Component)
/
Environmental
Cost
-Do-
ESL
Continuously
Environmental
Cost
-Do-
-Do-
Beginning
and end of
each
monsoon.
Continuously
Project
Cost
(Environmental
Component)
Contractor /
Service
Maintenance
Maintenance
Unit / SD
Environmental
Cost
Pollution
Monitoring
Agency
/
Chemical lab
TSU / EMARC
/ SD
-Do-
-Do-
-Do-
-Do-
-Do-
Pollution
Monitoring
Agency
/
Industrial
Safety
Pollution
Monitoring
Agency
/
TSU
At E, SE & NE
on
plant
boundary.
At E, SE & NE
of the plant in
three villages in
vicinity.
Entire
plant
drainage
network.
As per specified
waste
water
discharge
monitoring
programme
As per noise
level monitoring
programm
As per ground
water
monitoring
programme
Continuously
Page 277
Chapter 7
Contractor
TSU
HPD, BARC /
AREB
/
EMARC / SD
TSU / EMARC
/ SD
-Do-
Environmental
Issue/ Impacts
21. Soil
quality
conventional
pollutants
Mitigation Measure
Reference to
Contract
Documents
22. Solid
waste/Hazardous
Waste generation
and utililisation
Incineration
of
nonradioactive solid waste and
disposal of Hazardous waste
as per EMP.
-Do-
23. Municipal
Solid
Waste Disposal at
Township
24. Green Belt
Corporate
responsibility
Proper implementation of
green belt development and
maintenance.
Cleanliness of work place
Project
/
Statutory
requirement
-Do-
Approximate
Location
As
per
soil
quality
monitoring
programme
All the units of
the
proposed
plant
generating solid
wastes/HW
Entire
Township
green
belt
development
area
All units of the
plant.
Time
Frame
Mitigation Cost
Institutional Responsibility
Implementat
Superion
vision
-Do-Do-
-Do-
-Do-
-Do-
Project
Cost
(Environmental
Component)
Central
Material
&
Management
/ TSU
Chief
Superintende
nt / SD
-Do-
-Do-
-Do-
-Do-
Maintenance
Department /
SD
-Do-
-Do-
-Do-
Contractor /
Civil
Maintenance
Horticulture
Unit / Service
Maintenance
All
responsible
units/
Service
Maintenance
CSR Unit /
Human
Resource
26. Socio-economic
Development
-Do-
Page 278
Chapter 7
Table 7.3: Part B: Yearly Environmental Monitoring Plan for Performance Indicators at Final Stage
Environmental
component
Work zone Noise
levels
Project
Stage
Operation
stage
Parameters
Location
Frequency
Standards
Manual Stack
Monitoring for DG
Sets Stacks
Manual Stack
Monitoring for Waste
Incinerator
Effluent Quality
Operation
stage
Applicable
statutory
standards
-Do-
Operation
stage
-Do-
(1x12)X2000
=Rs. 24000
Operation
stage
Operation
stage
-Do-Do-
Operation
stage
2X2X12x8000
=Rs. 384000
3X9X20000
=Rs. 900000
-Do-
2X12x8000 =Rs.
288000
-Do-
6X12X2,000
=Rs. 144000
-Do-
5X12X8,000 =
Rs. 480000
3X6,000 = Rs.
18000
22,24,000
Manual AAQ
Monitoring
Waste Water
Discharge Quality at
Plant Outfalls
Ambient Noise levels
Operation
stage
Operation
stage
Operation
stage
Total
Approximate
cost (Rs)
12x3shiftx4quart
ersX2000 =Rs.
288000
(8X4)X2000
=Rs. 64000
Total Estimated Monitoring Costs = Rs 22,24,000 (say 22.5 Lakhs) per year during the operation years of the HAPP. The cost, automatic weather
monitoring station and continuous AAQ monitoring is not included in the cost estimated above. The same will be under Project Operation
Cost (Environmental Component).
Note: Cd -Cadmium; CO - Carbon Monoxide; Cr - Chromium; O3-Ozone; NOx - Nitrogen Oxide; Pb - Plumbum, (lead); PM10-Particulate Matter up to 10u
size; PM2.5-Particulate Matter up to 2.5u size; SO2 - Sulfur Dioxide; PM - Particulate Matter; ESL = Environmental Survey Laboratory, EMARC =
Environmental Management Apex Review Committee; IS - India Standard; OSHA = . Occupational Safety and Health Administration, USA; CPCB =
Central Pollution Control Board.
Page 279
Chapter 7
7.6.2
SN
Details
A.
1.
2.
3.
B.
1.
2.
C.
1.
Indicators
Effluent
Monitoring:
Liquid
Waste
Monitoring
Waste
Storage
Integrity
Personnel Monitoring
2012 MECON Limited. All rights reserved
Stage
Responsibility
Supervision
Reporting
Contractor /
Planning Section /
PD
Contractor / Civil
Maintenance / HR
(Human Resource)
Contractor / Civil
Maintenance
/
Planning Section
Contractor through
approved
monitoring agency /
Planning Unit / PD
-do-do-do-doContractor / Civil
Maintenance /
Planning Unit / PD
Operation
Operation
Operation
Page 280
Chapter 7
/
/
SN
Details
Indicators
Stage
Operation
Operation
Operation
2.
Operation
3.
Operation
4.
5.
6.
Pant
Medical
Unit/Competent
Authority
/
Industrial Safety
Industrial
Safety
group / TSU
Approved Agency /
TSU
Civil Maintenance /
Maintenance Group
Operation
ESL
Operation
Contractor / Civil
Maintenance
CMM
/
Civil
Maintenance
8.
9.
Operation
Operation
7.6.3
Operation
Operation
Preconstruction
Construction
Operation
/
/
Service
Maintenance
/
Maintenance Group
Horticulture Unit /
Civil Maintenance
All
responsible
units
/
Service
Maintenance
Plant CSR Unit /
Human Resources
Page 281
Chapter 7
/
/
Operation
7.
Responsibility
Supervision
Reporting
/ Medical Unit
HPU / TSU
ESL
Page 282
Chapter 7
SN.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Monitoring Equipments
Numbers Required
1
1
1
1
1
1
1
1
In Lot
7.6.4
22.5 Lakhs
92.0 Lakhs
5.5 Lakhs
120.0 Lakhs
2.
3.
2350
40.0
15.0
30
0.3
1.2
Page 283
Chapter 7
4.
5.
3.0
0.3
1.5
2399.5
0.3
42.1
Procurement Schedule
Construction of the project will be taken up in two stages of 2X700 MWe each. Planned
schedule for the proposed two units of 1st stage will take about 60 months. Subsequent
two units are expected to be four years later. The 1st stage project will be
commissioned in 60 months from the Zero-Date which is reckoned as start of
construction activities at site.
Thus the procurement of different equipments for laboratory (Table 7.5a and 7.5b)
shall be planned to be procured in yearly phase wise manner by the end of 48 months
i.e. before the 1st stage of the plant gets under operation, so that the environmental
enhancement measures are implemented with the start of the project.
7.7
UPDATING OF EMP
The directives from MOEF and the regulations in force at any time shall govern the
periodicity of monitoring. However it is suggested that the implementation of various
measures recommended in the EMP be taken as EMPs in the ISO 14001 system to
effectively implement the measures for continual improvement in environmental
performance. OHSAS 18000 shall also be implemented for the total plant.
Page 284
Chapter 7
ADDITIONAL STUDIES:
ASSESSMENT
8.1
PUBLIC CONSULTATION
PUBLIC
CONSULTATION
&
SOCIAL
IMPACT
8.2.1
Introduction
All industrial projects have social and economic linkages. Therefore, putting up a new
project and/or modernization/ expansion of existing projects has impact on the socio
economic environment of the locality around it. This impact may be marginal or non
2012 MECON Limited. All rights reserved
Page 285
Chapter 8
marginal. The intensity of impact may depend upon the various social and environmental
factors associated with it and the extent of change caused by the project to alter the
existing equilibrium of the socio-economic system. Influx of people from outside during
various stages of the project may also alter the existing cultural identity of the local
people. Further, there is a cash flow associated with the project which may affects the
existing socioeconomic activities and introduces many more new activities associated
with the project to which the local people have strong adherence. M/s NPCIL has
proposed an atomic power plant near Gorakhpur village of Fatehabad district, Haryana..
The various activities of the proposed projects are likely to stimulate the existing socio
economic environment in the surrounding area. The influx of money and various
construction activities may not only change the economic status of the area but also
influence the existing cultural scenario. This impact is expected to be more in the area
closer to the site, which decreases with increase of distance from the site.
8.2.2
Objectives
The proposed project will have a widespread impact on the social and economic
conditions of the people of the region in terms of direct and indirect employment, skill
diversification, infrastructure development, business development etc. On this backdrop,
the present study is directed towards the following objectives:
i)
ii)
To assess the present appraisal of the demographic profile of the study area
To assess the agricultural situation and to assess the impact of the project on
agricultural situation;
iii) To assess the impact of the project on pattern of demand;
iv) To examine the impact of the project on consumption pattern;
v)
To examine the employment and income effects of the project;
vi) Assessment of the educational status of the people and to explore the impact of
the project on education;
vii) To ascertain the impact of the project on industrialization in the study area;
viii) To examine the impact of the project on community development activities;
ix) To analyze peoples' perception regarding impact of the project
8.2.3
Page 286
Chapter 8
Socio-economic survey was carried out covering all the villages / towns of the study area
to record awareness, opinion, apprehensions, quality of life and expectations of the local
people about the proposed plant. The opinion of local people about the proposed
expansion plan was obtained through socio-economy survey of the villages / towns in
the study area.
A brief about the sampling design adopted for the field survey is described below. The
survey has been conducted through specially designed questionnaire covering every
aspect of the present study. In addition to the field data, secondary data / information
collected, compiled and published by different Governmental agencies / departments
were also collected and utilized appropriately.
Sampling
For selection of respondents from the study area, Two Stage Random Sampling has
been adopted. In the first stage, villages are selected and in the second stage,
households/ respondents are selected. From each selected village, the respondents are
selected randomly to account intra-village variability among the respondents for the
character under study. As the variability of the characters under in each strata study
does not vary widely among the households, a smaller sample size is expected to
represent the population. Samples of 24 respondents were drawn from the study area.
The sample covers an estimated 65 persons (Socio-economic survey on questionnaire
to be conducted).
Composition of the Questionnaire
Households/respondents were interviewed with the structured questionnaire specifically
designed for this study keeping in view the objectives of the study. The questionnaire
consists of following major sections:
a)
a)
b)
c)
d)
e)
f)
g)
Page 287
Chapter 8
The model is fitted to data applying Least Square (LS) technique to obtain estimated
demand and consumption functions.
2. Fitted regression models are used to work out
i) Elasticity of demand with respect to disposable income (e) in case of demand
functions:
e = (dy / dx) . (x/y)
ii) Marginal propensity to consume (MPC) from consumption function:
MPC = dC / dY
3. Frequency distribution of demographic parameters, peoples' perception, educational
status, agricultural status etc.
8.2.4
SN.
1
2
3
Population Data
Page 288
Chapter 8
SN.
Population Data
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Total Females
Female per 1000 Males
Rural Population
Urban Population
Percent Rural Population (%)
Population Density (Nos/sq. km)
Schedule Cast Total Population
Schedule Cast Male Population
Schedule Cast female Population
Schedule Tribe Total
Total Literates
Literates Males
Literate Females
Total Literacy Percent (%)
Total Illiterates
Male Illiterates
Female Illiterates
Derived from Population Census 2001 and decadal growth rate from 1991 to 2001
Occupational Structure
The occupational structure of residents in the study area is studies with reference to
main workers, marginal workers and non-workers. The main workers include 10
categories of workers defined by the Census Department consisting of cultivators,
agricultural laborers, those engaged in live-stock, forestry, fishing, mining and quarrying;
manufacturing, processing and repairs in household industry; and other than household
industry, construction, trade and commerce, transport and communication and other
services.
The marginal workers are those workers engaged in some work for a period of less than
six months during the reference year prior to the census survey. The non-workers
include those engaged in unpaid household duties, students, retired persons,
dependents, beggars, vagrants etc.; institutional inmates or all other non-workers who
do not fall under the above categories.
As per estimates based on 2001 census, in 2011 altogether the main workers work out
to be 37% and 33% of the total population, within 10km and 25km radius respectively.
The marginal workers constitute to 16% and 13% of the total population, within 10km
and 25km radius respectively. The non-workers constitute to 47% and 54% of the total
population, within 10km and 25km radius respectively. The distribution of workers by
occupation indicates that the non-workers are the predominant population. The
occupational structure of the study area is shown in Table 8.2b.
Page 289
Chapter 8
The marginal workers constitute 17%, 16% and 13% of population within 5 km, 10 km
and 25 km radius of the project site. The marginal workers can possibly be the pool
for unskilled labour in the area during the construction stage of the plant.
Table 8.2b: Occupational Structure in the Area
SN.
Population Data
1.
2.
3.
4.
5.
Total Population
Total Worker Population
Total Worker male
Total Worker Female
Total Working Population % to
Total Population
Total Working Male % to Male
Population
Total Working Female % to
Female Population
Main Workers Total
Main Workers Male
Main Workers female
Total Main Workers (%)
Total Main Workers Male (%)
Total Main Workers Female (%)
Total Cultivators
Total Cultivators Male
Total Cultivators female
Main Agricultural Labour
Main Agriculture Labour Male
Main Agriculture Labour Female
Main Household Industry Labour
Total
Main Household Industry laboure
Male
Main House Hold Industry Labour
Female
Main Other Workers Total
Main Other Workers Male
Main Other Workers Female
Marginal Worker Total
Marginal Worker Male
Marginal Worker Female
Total Marginal Workers % to
Total Population
Male Marginal Workers % to
Male Population
Female Marginal Workers % to
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
56
57
53
53
54
58
48
49
39
35
37
5114
3154
1960
43
49
36
4079
2443
1636
406
248
159
75
25429
17309
8120
36
46
24
16978
10853
6125
3328
2454
874
554
30543
20463
10080
37
46
26
21056
13295
7761
3734
2701
1033
629
36463
28413
8050
31
45
15
19878
14640
5238
4144
3005
1139
823
157261
117006
40255
33
46
18
75851
52019
23833
21281
14136
7145
3788
224266
165881
58385
33
46
18
116785
79954
36831
29159
19843
9316
5239
70
381
451
638
2874
3963
173
178
185
914
1276
554
394
160
2015
806
1209
17
4570
3621
949
11653
3755
7898
16
5124
4015
1109
13668
4561
9106
16
11619
10130
1489
18780
5333
13448
16
56341
47978
8364
54698
17914
36784
11
73084
62123
10961
87145
27808
59338
13
13
10
10
22
24
23
24
17
19
Page 290
Chapter 8
SN.
Population Data
Female Population
Non Working Population Total
4751
34083 38834
63115
264044
Non Working Population Male
2428
16829 19256
29346
119401
Non Working Population Female
2324
17254 19578
33769
144643
Total Non-workers % to Total
40
48
47
53
55
Population
36. Male Non-workers % to Male
38
44
43
47
47
Population
37. Female Non-workers % to
42
52
51
61
65
Female Population
Source: District Census Hand Book 20011, National Informatic Center, New Delhi
32.
33.
34.
35.
365993
168004
197989
54
46
63
Infrastructure Facilities
About 4/5th of the 10 km study area falls in Fatehabad district and about 1/5th falls in
Hisar district. The infrastructure and amenities available in the district denotes the
economic well being of the region. The area as a whole possesses moderate level of
infrastructural facilities.
A review of infrastructure facilities available in the area has been done based on the
information given in Fatehabad District Statistical Abstract 2008 09 and the data of
District Socio-economic Re-evaluation, Fatehabad 2008 09.
Similar type of
information is not available for Hisar District. It is presumed that the infrastructure
facilities available in 4/5th part of the study area will also be present in remaining area of
the study area. Moreover, Fatehabad district has been carved out of Hisar district in
1997. Therefore the Infrastructure facilities available in the Fatehabad district are
described in the subsequent sections as those available in the study area. The
geographical area of Fatehabad district is about 2538 km2.
Educational Facilities
The available educational facilities in the blocks falling in study area are given in Table
8.2c. As per the District Education Officers of Fatehabad and Hisar districts the
education facilities in the two district in general and in particular in the blocks falling in
study area is adequate and as per Government of India norms, i.e. availability of primary
school within one kilometer of habitation, middle school within 3 kilometer of habitation
and high school and secondary education within 5 kilometer of habitation. The above
requirements are almost met in the area considering the fact that a middle school, high
school and secondary school also have the lower level classes, i.e. from standard one to
onwards standards.
Page 291
Chapter 8
SN.
1.
2.
3.
4.
Health Facilities
Different types of health facilities including hospital and dispensaries are available in the
district. The level of health facilities is found to be moderate. The available health
facilities as per Fatehabad District Statistical Abstract are given in Table 8.2d. As per
Civil Surgeon Fatehabad and Hisar District there is one sub-centre on 5000 population,
one Primary Health Centre (PHC) on 30,000 population, one Community Health Centre
(CHC) on 1,20,000 population and a General Hospital at District level. In general the
sub-centres are at Panchyat level, CHC is at Block level and Sub-divisional Hospital
(SDH) is at sub-division level and General Hospital (GH) is at district level. At subcentres Multipurpose Health workers are there (one male and one female), at PHCs two
medical officers are posted, at CHCs four medical officers and one incharge is posted
and at GH specialists of major discipline like, general surgery, orthopedics, general
physician, pediatrics, gynecology, anesthesia, etc are posted. As per the civil surgeon
the medical facilities are adequate in the area and as per government of India norms.
Table 8.2d: Health Facilities in Fatehabad District
District
Fatehabad
Hisar
1.
Sub-centers
103
198
2.
Primary Health Center
16
35
3.
Community Health Centre
4
8
4.
Sub Divisional Hospital
1
2
5.
General Hospital
1
1
Source : Civil Surgeon Fatehabad & Hisar District 2012
SN.
The number of patients treated vis--vis falling ill in the Fatehabad and Hisar district is
given in Table 8.2e. Out of the total population overall about 10% in Fatehabad and 5%
of the population per year falls sick to the extent to be admitted in hospital. The percent
population getting treatment in out-door is 110% for Fatehabad and 63% for Hisar. The
figures are low in Hisar may be due to more private medical fascilities in the district the
population seek their medical requirement from private sources. The figure may overall
indicate the availability of Government Hospitals and access of masses to the same in
the two districts.
Page 292
Chapter 8
Table 8.2e: Number of Patients Treated in Health Institution in Fatehabad and Hisar
District (2011 data)
SN. Particulars
District
Fatehabad Hisar
1 Population 2001
423438
1537117
2 Projected Population 2011
529298
1921396
3 New Indoor Patient
33396
47771
4 New Out Door Patient
488131
900396
5 New & Old Indoor Patient
54462
88456
6 New & Old Outdoor Patient
584411
1211704
7 Total Patients Treated
638873
1300160
8 Percent Population Getting Treatment in Indoor
10
5
9 Percent Population Getting Treatment in Outdoor
110
63
10 Percent Population Getting Treatment in Indoor & Out Door 121
68
Health Status in the Study Area
The health status in the district was assessed by the information provided by the Civil
Surgeon Fatehabad and Hisar. The common diseases are viral fever, cough and colds,
diarrhea and enteric fever are the prominent diseases in the region. During monsoon
viral fever, diarrhea and cough are very common diseases and could be attributed to the
rains, which generally contaminate water in the region and also the moist climate.
Tuberculosis is also disease observed in the region, however in a very less proportion.
The major communicable diseases prevalent in the study area are presented in Table
8.2f.
Table 8.2f: Principal Communicable Disease Occurrence Pattern in Fatehabad and Hisar
District (Data 2011)
Total
Disease
Type of Diseases
Fatehabad Hisar
Occurrence (%)
0
0.00
Cholera (Lab Confirmed)
0
0
15199
9.18
Acute Dairrhoeal Diseases
6478
8721
0
0.00
Diptheria
0
0
0
0.00
Tetanus other than Neonatal
0
0
0
0.00
Neonatal Tetanus
0
0
0
0.00
Whooping Cough
0
0
2
0.00
Measles
1
1
143669
86.81
Acute Respiratory Infection (Including
86397
57272
Influenza and Excluding Pneumonia)
366
0.22
Pneumonia
235
131
1752
1.06
Enteric fever
1255
497
408
0.25
Hepatitis A
286
122
39
0.02
Hepatitis B
34
5
0
0.00
Hepatitis C, D, E
0
0
0
0.00
Meningococcal Meningitis
0
0
108
0.07
Rabies
108
0
496
0.30
AIDS (As Reported to NACO)
496
132*
2012 MECON Limited. All rights reserved
Page 293
Chapter 8
Type of Diseases
Fatehabad
Hisar
Total
Disease
Occurrence (%)
Syphilis
Gonococcal Infection
Other STD Diseases
Swine Flue (H1N1)
Pulmonary Tuberculosis
Malaria
JSW
Total
NA : Information not available
* Figures are from Hisar General Hospital
1
1
1298
0
714
1044
NA
98348
83
157
NA
NA
NA
NA
23
67144
84
158
1298
0
714
1044
23
165492
0.05
0.10
0.78
0.00
0.43
0.63
0.01
100
Transport Facilities
The area is served by rail and road transport facilities. There are four railway stations of
Northern Railways in the area. The nearest railway station to the project site is Uklana
Mandi 23 km NE of the project site on Jalandhar Doab rail extension. Adampur railway
station is 32 km SW of the site on Rewari-Bhatinda rail section. New Delhi Firojpur and
Jaipur to Amritsar rail track passes through railway station at Hisar situated about 33 km
SSE of the project site. The Narwana or Jakhal Rail Junction is located on the DelhiBhatinda rail sections, 33 km NE of the project site. The above Railway Stations caters
to the commuter needs and transportation of goods in the region.
The area has a good level of road network almost all the villages are connected by
public works department (PWD) road. Above all the area is connected to NH10 by the
Kharakheri-Gorakhpur road. In Fatehabad district the total length of the PWD road in
district is about 1589 km. In 2008 09 there was one main bus depot and a sub depot of
Haryana State Bus Transport Corporation and about 146 buses were plying within and
outside the district, carrying about 35197 passengers per day.
Post and Telegraphs
Fatehabad district has moderate level of Post and Telegraphic services. Altogether there
are 146 post offices, 44 telegraph offices and 653 public telephone booths in the district
as shown below.
Facilities
Post office
Telegraph Offices
Public Telephone Booth
Number
146
44
653
Number / 10 km2
0.6
0.17
2.6
Electrification
All villages in the district are electrified and the electricity is supplied for domestic,
agricultural and public lighting purposes.
Page 294
Chapter 8
Fatehabad
9
12
Hisar
11
20
8.2.5
Bhuna
Number Area
1 Marginal (< Absolute 4743
2466
1 Ha.)
%
35
7
2 Small (1 2 Absolute 2981
4228
Ha.)
%
22
12
3
Semi
Absolute 3117
8809
Medium (2
%
23
25
4 ha.)
SN
Blocks
Bhatu-kalan
Number Area
4515
2344
35
7
2838
4018
22
12
2967
8370
23
25
Fatehabad
Total
Number Area Number Area
8400
4355
17658
9165
35
7
35
7
5280
7467
11099 15713
22
12
22
12
5520
15556 11604 32735
23
25
23
25
Page 295
Chapter 8
SN
Blocks
Bhuna
Bhatu-kalan
Fatehabad
Total
Number Area Number Area Number Area Number Area
4 Medium (4- Absolute 2304
13390
2193
12722
4080
23645
8577
49757
10 ha.)
%
17
38
17
38
17
38
17
38
5 Large (>10 Absolute
407
6343
387
5926
720
11202
1514
23471
ha.)
%
3
18
3
18
3
18
3
18
Total
Absolute 13552 35236 12901 33480 24000 62225 50453 130941
%
100
100
100
100
100
100
100
100
Source : Comprehensive District Agriculture Plan (C-DAP) District Fatehabad Haryana, XIth
Five Year Plan
Semi Medium (2
4 ha.)
23%
Small (1 2 Ha.)
22%
Fig. 8.1: Land Holding Pattern in the Study Area
Table 8.3b depicts the cropping pattern and production in the Fatehabad District.
Matching data for Hisar are not available and since Agroha block of Hisar District covers
only 1/5th of the study area thus it is presumed that the agricultural pattern as present for
Fatehabd district will also be there for the entire study area (including the 1/5th of Agroha
block of Hisar). The crops are grown during Rabi, Kharif and summer seasons. The
cropping pattern in the general study area reveals that wheat, cotton and paddy are the
most predominant crop followed by Guar, Bajra and Sarson, etc.
Table 8.3b: Cropping Pattern of the Study Area
SN.
1.
2.
3.
Cropping Pattern
Paddy
Wheat
Sarson
Yield kg/ha
% Area
17
43
3
3952
5081
2126
Page 296
Chapter 8
SN.
4.
5.
6.
7.
8.
9.
10.
11.
Cropping Pattern
Bajra
Cotton
Guar
Other Crops & Horticulture
Gross Cropped Area
Net Cultivated Area
Irrigation by Canal
Irrigation by Tube well
Yield kg/ha
% Area
3
22
7
4
100
46.23%
45.49%
2407
625
-
Value
207
27239
12005
Agricultural situation of the study area indicates that agriculture in this area is good using
latest development in the country. The project is not going to cause any damage to
agricultural situation of the study area. Instead, it is likely to help agriculture by way of
providing income from non-farm sources
Pattern of Demand
The survey reveals that the respondents spend major portion of their disposable income
on food items. However, there has been a growing tendency among the respondents of
allocating higher expenditure on non-food items although their basket of consumption
have only few items other than food. To go to the details of their pattern of demand,
income elasticity of demand is calculated by fitting demand functions. Table 8.3d
presents the results of the regression analysis conducted for fitting the demand
functions. It is observed that all the demand functions give uniformly good fits to the data
because R2 in all the cases are found to be quite high. Moreover, as indicated by t-test,
the relevant parameter of the demand functions is found to be statistically highly
significant at 1% level. The income elasticity of demand as measured from the fitted
functions is 0.998 and 0.996 for food and non-food items respectively.
The inelastic nature of demand for food items indicates their necessity for these items to
the households. The non-food items are found to be elastic to the income of households.
This implies that for any additional income, households will spend for non-food items
including luxurious goods.
Page 297
Chapter 8
0%
Service
24%
Cultivation
68%
Page 298
Chapter 8
Direct Employment
Agriculture, business, and service are major sources of income in the study area.
However, unemployment is quite common in the study area. The project has
employment generation potential by way of recruiting local people directly for different
activities of the project, specifically at the construction phase. It is expected that
substantial portion of the investment in this project will trickle down to the local people in
the form of employment and income.
Indirect Employment
Indirect employment and income effects of Atomic Power Plant (APP) are non-marginal
and usually remain widespread across a long region. The proposed project will cause
generation of income and employment opportunities in the ancillaries and service units
which came in the vicinity of the APP, specifically, in ancillary, transport and
manufacturing sectors. The growth of employment in services activities is likely to be
much stronger due to its multiplier effect.
As the proposed project is implemented indirect employment is likely to grow very fast.
The project is expected to generate substantial indirect employment in other sectors
such as ancilliary, transport and related manufacturing sectors, service units etc.
Further, increase of population in the study area as a result of the project will lead to
higher demand for food. As consequence, price of food is expected to increase. It is
expected that the project may bring infrastructure development in the study area which
may multiply in employment generation many fold. Hence, the project is expected to
generate substantial indirect employment in other sectors.
Overall assessment of the employment and income effects indicates that the project has
strong positive direct as well as indirect impact on employment and income generation.
Consumption Behaviour
Table 8.3e presents the source-wise distribution of average family consumption. It is
observed that the major portion of total consumption expenditure goes to meet the need
for food (56%). The consumption expenditure on clothing is second highest (22.4%).
Average expenditure on medical purposes is 10.9%. About 3.9% of total consumption
expenditure goes to meet the other social requirements. Expenditure on education in the
study area is observed to be low.
Table 8.3e: Source-wise distribution of family consumption
Item
Consumption (Rs/yr)
Distribution of average
family consumption (%)
Food
Education
Clothing
Medical
Others
TOTAL
163030
20015
65283
31660
11313
291301
56.0
6.9
22.4
10.9
3.9
100.0
Page 299
Chapter 8
(2)
I = Investment
(3)
Page 300
Chapter 8
Peoples Perception
The results of the opinion poll are analysed and furnished in Table 8.4. The major
advantages and disadvantages shown by the people is given in Table 8.4. It is observed
that 83% of them have identified creation of employment opportunity as the main
advantage. People are hopeful of getting employment in the small-scale units likely to
come up in the vicinity of the plant. About 33% of the respondents are expecting
improvement in business. Around 58% of the respondents feel improvement in peripheral
development activities. The major disadvantages shown by the people are radioactivity
related threat to life in case of accidents as in other part of the world seems to be the
cause of worry of the people. About 100% of the respondents are fearful about this aspect.
Among other disadvantages, loss of land and house, about 83% are fearful about this
Page 301
Chapter 8
aspect. About 75% of the respondents are showing concern to health due to
environmental pollution.
Table 8.4: Peoples Perception on the Project
Perception
ADVANTAGES
Employment opportunity
Development of the area
Business development
DIS-ADVANTAGES
Radioactive Damage in Case of Accidents
Pollution
Loss of land and house
Damage to health
Total Respondents
No. of Respondents
Distribution (%)
20
14
8
83
58
33
24
18
20
10
24
100
75
83
42
Major Advantage:
i.
Present project may generate more employment, directly and indirectly, and
major portion of it may be provided to the local people.
ii. Development of business opportunity in the area.
iii. Development of infrastructure facilities including roads may take place due to the
project which may help in improving the whole area.
iv. Improvement in living standard.
Major Disadvantage:
i.
Accidents in the plant may cause radioactive releases which may be detrimental
to life in the area as in some part of the world.
ii. Pollution in the study area is expected to rise due to the project. People perceive
that the increase in pollution may cause damage to agriculture and damage to
health of people due to pollution.
iii. Loss of agricultural land.
Needs of the Villagers and their Expectations
It appears that the expectations and needs of the villagers are quite moderate. The
people in the study require basic minimum amenities wherever they are not available
and improving these facilities wherever these are inadequate. They appealed to the
government through this survey, for provision and improving of the following facilities:
Proper compensation to the Project Affected Persons (PAP) of the Project
Affected Villages
More Higher secondary schools
Adult education centers
Dispensaries / Health Centres and availability of doctors and other para-medical
staff
Protected drinking water supply schemes
Page 302
Chapter 8
8.2.7
Loan facility for self employment to open petty shops, purchase of cycle
rickshaws, agricultural tools and implements, bullock carts, fertilizers, improved
seeds and digging of well for irrigation.
Conclusions
On the basis of the overall results of the present impact assessment the following
conclusions are drawn:
The project is not going to cause any damage to the existing agricultural situation.
Instead, it is likely to provide the farmers with supplementary income.
The project has positive impact on pattern of demand
The project has very strong positive employment and income effects.
There is a possibility increase in industrialisation in the vicinity of the plant. This is
likely to bring more skill diversification among local people.
The project has strong positive impact on raising average consumption and also
income through multiplier effect.
The CSR activities of the project will have very strong positive impact on the social
and economic condition of the people of the study area
The project has positive impact on health situation of the local people through
development of the area.
The project has significant positive impact on community development activities of
the project which are likely to bring handful of benefits to the people of the study
area.
Overall peoples perception on the project is not very encouraging However, they
want implementation of a comprehensive Resettlement and Rehabilitation Action
Plan (RAP)
8.2.8
Page 303
Chapter 8
Community development activities (including that for its employees) are very important
aspects for any organization / project, because people of the villages surrounding the
plant and its employees are the stakeholders. The project proponents have always
treated its periphery as a key stakeholder. The main objective of the Community
Development Programme has been to create synergy and synthesis with the
environment. Guided and inspired by the objective of enhancing the living standards of
the people.
The policy of NPCIL towards social welfare & community development aims at
strengthening the bond between the project / station authorities and the local population
in the vicinity of nuclear power plants. In line with this policy, NPCIL at the existing
nuclear power stations and projects has been carrying out number of community welfare
activities in the following areas:
Accordingly NPCIL plans to implement above social and community welfare measures in
area around the Gorakhpur Project with the following action plan.
Page 304
Chapter 8
Introduction of the talent nurture schemes for students from nearby villages by
providing admission to AECS schools of NPCIL for free education or by providing
suitable scholarships.
Page 305
Chapter 8
9.1
INTRODUCTION
Risk to the Atomic Power Plan (APP) and its surrounding may arise due the following
factors:
i. External natural events that are likely to affect plant safety and operation like
earthquakes, floods, extreme winds, land slides, soil liquefaction etc.
ii. External man made events that are likely to affect plant safety and operation
iii. Events within the plant due to hazardous chemicals used in the plant operation that
may affect the public and the environment.
iv. Events within the plant due to radiological emissions that may affect the public and
the environment.
9.2
NATURAL EVENTS
As discussed earlier in Chapter 2 under Section 2.4, a site evaluation study is a
prerequisite before a site is approved for the construction of an atomic power facility like
HAPP. The purpose of the study is by AERB to assess the engineer-ability of the plant at
the selected site, in view of the effects of external natural events - like earthquakes,
floods, extreme winds, land slides, soil liquefaction etc.
9.2.1
Earthquake Hazard
The earthquake hazard map of part of northern India showing the project location is
given in Fig. 9.1a. It can be seen that the project site falls under moderate damage risk
zone. All precautionary measures have been considered while designing the engineering
of the facility to meet any such events. The seismo-tectonic study conducted for the site
as given under Section 4.5.6 (Chapter 4), revealed that the site is engineer-able from
this consideration.
9.2.2
Flood Hazard
The flood hazard map of part of northern India showing the project location is given in
Fig. 9.1b. It can be seen that the project site is not falling under area liable to floods.
However, the project site is within 10 km radius of Fatehabad Branch of Bhakra Canal.
The canal is fully lined and hence there is very low probability of canal breach. Further
all engineering precautionary measures have been considered while designing the
facility to meet any such incidents.
Page 306
Chapter 9
9.2.3
Cyclone Hazard
The cyclone hazard map of part of northern India showing the project location is given in
Fig. 9.1c. It can be seen that the project site falls under high damage risk zone, with
wind velocity reaching up to 47m/s. All engineering precautionary measures have been
considered while designing the facility to meet any such events.
9.2.4
Landslide Hazard
The landslide hazard map of part of northern India showing the project location is given
in Fig. 9.1d. It can be seen that the project site falls under zone which is unlikely to get
any landslide events. However, all precautionary measures have been considered while
designing the engineering of the facility to meet any such events.
1 Seismic Zones of India Map IS:1893; 2002, Beuro of Indian Standards, Government of India.
2012 MECON Limited. All rights reserved
Page 307
Chapter 9
2 Flood Atlas Task Force Report, Central Water Commission, Government of India
2012 MECON Limited. All rights reserved
Page 308
Chapter 9
3 Basic Wind Map IS 875(3) 1987, Cyclone Data, 1877-2005, IMD, Government of India
2012 MECON Limited. All rights reserved
Page 309
Chapter 9
Fig. 9.1d : Landslide Hazard Zone Map4 of India Showing Project Site
9.3
9.3.1
9.3.2
Page 310
Chapter 9
chemicals like LPG, chlorine or ammonia, plying on the road. Traffic or other accidents
may lead to large release of toxic chemicals or to chemical explosion. Three postulated
events are considered below.
Leakage of Chlorine: Consequence Analysis
Chlorine is usually transported in horizontal tanks (usually referred to as tonner)
constructed of mild steel with a capacity to store about 1000 kg. The typical dimensions
of the tank are 0.785 m diameter and 2.1 m length. The storage is done at a pressure of
about 10 kg/cm2 and at ambient temperature. The failure of the 9.5 mm spindle of the
valve in the liquid phase and release of liquid chlorine into the atmosphere is taken as
the maximum credible accident. A portion of the continuously releasing liquid chlorine
would flash. The flashed chlorine would initially expand as a dense gas resulting in fatal
concentrations. Subsequently it would disperse in the environment, greatly influenced by
the prevailing atmospheric stability condition.
Two types of parameters are estimated to provide a measure of the impact. One is the
Effect Distance, which corresponds to the distance up to which lethal concentration
(LC50) of vapor would be felt. Analysis indicated that the effect distance is approximately
480 m from the source under stable weather condition. For distances beyond 500 m,
concentration profile was obtained using GPM, considering stability class F and wind
speed as 2 m/s. The concentration of chlorine at a distance of about 2 km from the
source is found to be about 20 ppm (60 mg/m3). Hence, event of this kind has no effect
on safe operation of HAPP, which is about 6.0 km from the NH10.
Leakage of Ammonia: Consequence Analysis
A failure of the cylinder valve in the ammonia storage tank is postulated, leading to
release of ammonia, initial flash and subsequent dispersion in the atmosphere. A
continuous release and worst-case weather stability class (F, 2 m/s) have been
considered for the dispersion. It has been observed that LC50 value of ammonia (6164
mg/m3) would be felt up to a distance of about 160 metres. This does not affect the safe
operation of HAPP.
LPG Tanker Explosion
The postulated incident considered is a catastrophic failure of an LPG tanker, taking
place on the NH10. The effect of vapour build-up due to LPG tanker explosion is limited
to a maximum of ~ 153 m, heat radiation effect on equipment is limited to ~ 114 m,
overpressure effects are limited to ~ 175 m, and the structural damage is limited to ~ 146
m. The maximum damage distances are far less compared to the distance between
HAPP and the highway.
9.3.3
Page 311
Chapter 9
9.4
9.4.1
Hazardous Chemicals
Industrial activities, which produce, treat, store and handle hazardous substances, have
a high hazard potential endangering the safety of man and environment at work place
and outside. Recognizing the need to control and minimize the risks posed by such
activities, the Ministry of Environment & Forests have notified the Manufacture Storage
& Import of Hazardous Chemicals Rules in the year 1989 and subsequently modified,
inserted and added different clauses in the said rule to make it more stringent. For
effective implementation of the rule, Ministry of Environment & Forests has provided a
set of guidelines. The guidelines, in addition to other aspects, set out the duties required
to be performed by the occupier along with the procedure. The rule also lists out the
industrial activities and chemicals, which are required to be considered as hazardous.
In the proposed project the power generation from atomic power (pressurized heavy
water reactor (PHWRs)), is being planned.
The major chemicals which will be stored by the project includes High Speed Diesel Oil
(HSD). In view of the proposed activities are being scrutinized in line of the above
referred Manufacture, Storage and Import of Hazardous Chemical (Amendment)
Rules, 1989 and its Amendment Rules 2000 and observations / findings are
presented in this section. This plan covers mainly the HSD, which is going to be stored
and subsequently handled during the plant operation.
As per the Schedule I Schedule 1, paragraph (b) (iv) of Manufacture, Storage and
Import of Hazardous Chemical Rules, 1989, MOE&F High Speed Diesel (HSD) falls
under category flammable liquids: chemicals which have a flash point lower than or
equal to 600C but higher than 230C.
The assessment has been made in a systematic manner covering the requirements of
the above-mentioned rules.
Process Description
The operation of the proposed project involves use of natural uranium oxide as fuel and
heavy water (D2O) as coolant and moderator for the reactor. Refueling of the reactor will
be carried out "on-power". The uranium dioxide (UO2) used for fuel is a ceramic with
high melting point and chemically inert to water at operating conditions. So long as the
ceramic fuel does not melt, the fission products remain entrapped in its matrix. During
normal operation virtually all solid fission products are permanently retained in UO2
matrix and only a fraction of noble gases and volatile products diffuse into the inter
space between fuel and cladding (for details see Chapter 2).
Page 312
Chapter 9
For each unit of 700MWe there are 4 DG sets. Each DG is of capacity 4.2 MW with fuel
consumption of 233g/KWhr (233g/KW/hr) or 979kg/hr. Each DG set will be provided with
114KL of capacity diesel Tank and with day tank of 8 hr duration of capacity 12 m3. Thus
at a time maximum (114 m3 X 8 + 12 m3 X 16 = 2016 m3 or say) = 2100 m3 of HSD will
be stored. One DG set is sufficient for supplying power to one 700MWe reactor.
However, provision of 3 standby DG sets has been kept for emergency situation. One
DG set is tested for to 1.0 hour in a week. The other DG sets kept under standby are
tested in subsequent weeks. Thus 4 DG set will run for maximum one hour during
testing period for the four units of HAPP and during emergency situation 4 DG sets will
run for 24 hours during emergency power failure situation.
Applicability of the Rule
From the above description of the process, it is observed that the chemicals stores /
handled and involved are:
(i) Bulk Storage of High Speed Diesel (HSD):
To decide whether the above mentioned industrial activities are likely to come within the
scope of the above mentioned Manufacture Storage and Import of Hazardous
Chemicals Rules, flow chart i.e. Fig. 9.2, pertaining to occupiers guide to the hazardous
chemical regulation -1989 and the threshold quantities mentioned in the rules are used
as given in Table 9.1a.
Table 9.1a: Threshold Quantity and the Chemicals to be Stored and Handled
SN
Chemical Stored /
Handled
Qty.
Stored
/
Handled
(In
Tonne)
And
Storage / Handling
Conditions
2100 m3 or 1890 t
Whether
Included
in
The List of
Hazardous &
Toxic
Chemicals
Yes
10,000
After comparison of the stored / handled and threshold quantities, it can be noticed that
none of the stored / handled hazardous chemicals are more than the lower threshold
quantity. However, for the other chemicals, the threshold quantities are not listed.
Accordingly only rule 17 i.e. preparation and maintenance of material safety data
sheets for these chemicals are required.
The proposed project is going to utilise the HSD oil storage facility. The storage
installation will conform to the requirement for such storages. All equipment will conform
to the provision of statutory and other regulations of Government of India, including
Indian Boiler Regulation and Tariff Advisory Committee and also provisions of National
Fire Protection Association (NFPA) of USA.
Page 313
Chapter 9
YES
IS IT AN ACTIVITY WITHIN
THE MEANING OF REG 2
YES
NO
NO ACTION
YES
DOES THE QTY EXCEED
THE THRESHOLD QTY IN
SCH - 3 COL 4
YES
NO
YES
YES
ACTION PREP ON SITE
EMERGENCY PLAN (REG - 13);
PROVIDE INFORMATION TO
LOCAL AUTHORITY FOR
DRAWING OFF SITE
EMERGENCY PLAN (REG-14)
INFORM PUBLIC ABOUT MAZOR
ACCIDENT HAZARD (REG-15)
IS THE HAZARDOUS
CHEMICAL LISTED IN
SCHEDULE - 2
NO
NO
DOES THE QTY EXCEED
THE THRESHOLD QTY IN
COL - 3 OF SCH - 3
NO
NO
NO ACTION
NO
DEMONSTRATE SAFE
OPERATION AT ANY
TIME REG -4
YES
YES
INFORMATION REGARDING
IMPORTS OF CONCERNED
AUTHORITY PREPARE &
MAINTAIN MSDS & LABEL
(REG - 17 & 19)
YES
NO
YES
YES
NO
Page 314
Chapter 9
.
Combustible Liquid : Yes
Flammable material : Yes
Pyrophoric Material : N. A.
Corrosive material : No
4. Reactivity Data
Chemical stability: Stable
Incompatibility with other material: oxidizers such Peroxides ,Nitric acid and Perchorates
Hazardous reaction products: on fire it will liberate some amount of carbon monoxide, sulphur
dioxide Nitrogen oxide and other aromatic hydrocarbons.
5. Health Hazard Data
Routes of entry: : Inhalation, Skin absorption ,ingestion
Effects of Exposure / symptoms: excessive inhalation Vapors cause rapid breathing, excitability,
staggering, headache, fatigue, nausea and vomiting, dizziness, drowsiness, narcosis
convulsions, coma.
Skin Contact: Skin-dryness, cracking, irritation eyes watering, stinging and inflammation.
Emergency treatment: In case of eye or Skin contact, flush with plenty of water. Remove
soaked clothing. in case of excessive inhalation move the victim to fresh air, obtain medical
assistance.
L.D50 (Oral-Rat) :
> 5g/kg
L.C 50: (rat 4hrs) 5g/m3
Permissible Exposure limit: N.A.
Odour threshold: N.A.
TLV (ACGIH) :
800 ppm
STEL: N.A.
NFPA Hazard signals
Health Flammability Reactivity/Stability
Special
1
2
0
-
Page 315
Chapter 9
6. Preventive Measures
Personal Protective equipment: Canister type gas mask. PVC or Rubber. Goggles giving
complete protection to eyes. Eye wash fountain with safety shower.
Handling and storage precautions: Do not expose to heat and naked lights, keep containers and
valves closed when not in use.
7. Emergency and First Aid Measures
Fire:
Fire Extinguishing Media: Foam, Carbon Di-oxide, Dry Chemical Powder. Water may be used to
cool fire-exposed containers.
Special Procedures: Shut off leak, if safe to do so, Keep non-involved people away from spill
site. Eliminate all sources of ignition.
Unusual Hazards: It will spread along ground and collect in sewers
Exposure:
Skin Contact: In case of contact with skin flush with fresh water, remove containment clothing.
Inhalation: In case of excessive inhalation move the victim to fresh air, if problem in breathing
give artificial respiration; give oxygen. Obtain medical assistance.
Ingestion: Give water to conscious victim to drink. Do not induce vomiting
Antidotes / Dosage : N.A.
Spills:
Steps to be taken to shutoff leak, if safe to do so, keep non-involved people away from spill site.
Eliminate all sources of ignition. Prevent spill entering in to sewers, for Major spillage contact
emergency services.
Waste Disposal Method : N. A.
(i) Small Storage of Toxic Chemicals in Analysis Laboratory
Apart from HSD no other hazardous chemical are stored in bulk quantity. However, there
may be some toxic chemicals used in different laboratories of the plant, which will be
used in analysis in the laboratory. But the quantity of the same will be very small.
Preparation and maintenance of material safety data sheets for all such chemicals will
be maintained at each laboratory as per the OSHAS 18000 requirements. The list of
such chemicals is given in Table 9.1b.
Table 9.1b: List of Toxic Chemicals Stored in Very Small Quantity in Laboratory
SN.
1
2
3
4
5
6
7
8
9
Item Description
Acetic Acid Glacial
Acetone
Acetonitrile
Conc. Sulphuric Acid
Ammonia Solution
Ammonium Nitrate
Benzoyl Peroxide
Chromium Chloride Hexahydrate
Copper Chloride Crystal
Page 316
Chapter 9
SN.
10
11
12
13
14
15
16
17
18
19
20
21
22
9.4.2
Item Description
Copper Nitrate Trihydrate
Copper Sulphate Pentahydrate
Cyclo Hexamine
Dioxan
Hydrochloric Acid
Hydrogen Peroxide
Iodine Resublimed
Magnesium Metal Power
Morpholine
Nitric Acid
O- Tolodine reagent
Perchloric Acid
Pyridine 2,6-Dicarbocyclic Acid
Page 317
Chapter 9
public as a result of discharge of radioactive substances from the plant remain within the
limits specified by AERB.
Safety Aspects
All the radioactive sources in the plant which may lead to radioactive releases are
identified and assessed for their hazard magnitude. However, the worst case scenario
for any nuclear power plant is considered to be the damage of core where the fuel is
loaded and a sustained chain reaction takes place in normal course of plant operation.
Accordingly, safety aspects are identified and evaluated by deterministic as well as by
probabilistic assessment. Probabilistic safety assessment is seen as an extension of or
complement to deterministic analyses. It systematically considers conceivable accident
causes (Postulated Initiating Events (PIEs)) and for each initiating events, which can
lead to core damage of different categories Core Damage Frequency (CDF) is
calculated based on individual initiating events (IE) frequency. Through individual event
sequence analysis for different IEs, it is estimated that the plant is provided adequate
safety features and measures to mitigate or minimize any unsafe consequences.
As per AERB Safety Guide (SG-D-5), DBE (Design Basis Events) are categorized into
four categories on the basis of their expected frequency of occurrence. Each of the DBE
considered should be assigned to one of the following groups.
(1)
(2)
(3)
(4)
Events not falling in any of the above categories are called BDBE (Beyond Design Basis
Events).
The concept of defense-in-depth is conveyed at all phases or activities related to
ensuring the APP safety. Here, the strategy for preventing unfavorable plant damage
state initiating events, especially for the 1st and 2nd level is of primary importance
(details are provided in Section 2.11.1 to 2.11.4, Chapter 2).
In normal operating conditions, all of the physical barriers must be capable of
functioning, whereas the measures on protecting them must be available. On detecting
any problems in any of the barriers envisaged by the design or unavailability of
measures for protecting it, the reactor plant must be shut down and measures for
bringing the atomic power unit in a safe state must be taken.
The engineering measures and managerial, decisions meant for ensuring safety of APP
must be proven by the previous experience or tests, studies or operating experience with
prototypes. Such an approach should be applied not only when developing the
equipment and designing the APP, but when manufacturing the equipment, constructing
and operating the APP and upgrading its systems (components) as well.
Page 318
Chapter 9
The values of overall Core Damage Frequency (CDF) will be within the design target of
1.0 E-6 /reactor-year for the reactor proposed to be set up at Fatehabad, which is below
acceptable limit of 1.0 E-5 /reactor-year, as per International Atomic Energy Agency
(IAEA) Safety Series No. 75 INSAG-3, 1988.
Multi Barriers of Safety
The safety of the NPP is ensured by incorporating many barriers between the source
and the receptor. Protection implies a system of physical barriers on the way by which
the ionizing radiation and radioactive substances can release into the environment. This
system is used together with a complex of engineering and managerial measures for
protecting these barriers and maintaining their effectiveness and measures for protecting
the personnel, population and the environment.
The system of physical barriers of the NPP power unit incorporates: a fuel element, fuel
element cladding, the pressure boundary of the reactor coolant and the containment. An
exclusion zone also provides a dilution of radioactivity before it is reaches to the public
domain.
9.4.2.3 Radiological Objectives
The general principle applied is that, for the transients, incidents and accidents
considered in the design (Table 9.2), the more frequent the event, the lower the
radiological consequences.
The normal operating and transient conditions must not result in normal operating limits
being exceeded. These operating conditions and transients are covered by the overall
dose limit of 1.0 mSv /yr to the members of public at 1.0 km from the reactor i.e. the
fence post of the exclusion zone.
The radiological objectives associated with other conditions viz. accidents (Table 9.2) to
meet the appropriate reference dose limits under these conditions. For the above
referred conditions, the maximum thyroid and whole body doses from APP at a distance
of 1.0 km would be kept well within the reference doses of 500 mSv to child thyroid and
100 mSv to an adult whole body as stipulated by AERB.
Radiological Aspects
The radiological consequences to the public can be broadly divided into two categories
i.e. during normal operation and during accident condition. During normal operations, the
controlled release of radioactive materials is governed by the Effective Dose Limits
(EDL), applicable to the members of public. EDL as stipulated by AERB is 1 mSv/year.
There are mainly two routes of exposures i.e. air route and aquatic route. In accident
conditions, the consequence depends on the accident scenario.
While siting atomic power plants, three areas are defined as exclusion zone, sterilized
zone and monitoring zone. Exclusion zone extends up to 1.0 kms, which will be under
the exclusive control of the power station where no public habitation is allowed. The
sterilized zone is the annulus between 1.0 kms and 5 kms radius from the reactors
where natural growth is permitted but new expansion of activities which lead to enhance
2012 MECON Limited. All rights reserved
Page 319
Chapter 9
population growth are regulated. The area from project to site 30 kms zone is the
monitoring zone. The areas under plant zone, exclusion zone and sterilized zone for the
HAPP Project are shown in Fig. 9.4.
For, Fatehabad Site, the methodology for calculation of doses during off normal
situations will be as per AERB safety guide (AERB/SG/S-5D-21). The doses will be
worked out by using the two types of dose conversion factors. For initial two hrs into the
accident, the site-specific worst meteorological parameters are assumed to maximize
the dose. For subsequent releases, time averaged dispersion parameters are used. The
worst affected sector will be taken with no change in wind direction.
The maximum thyroid and whole body doses from APP under abnormal situations at a
distance of 1.0 km will be kept well within the reference doses of 500 mSv and 100 mSv
as stipulated by AERB for child thyroid and whole body respectively.
Radiation Protection Considerations
ALARA Policy
The radiation protection policy taken into account for design is to ensure that the
individual dose of site personnel and members of the public does not exceed the dose
limits set by the regulatory agency and is kept at a level As Low As Reasonably
Achievable (ALARA) and as per the requirements of AERB. The details are presented as
in Section 2.15.4, Chapter 2.
This policy is embodied in the design, construction, operation, maintenance, in-service
inspection, refueling, and non-routine activities.
General Design Considerations
General design considerations and methods employed to maintain in Plant occupational
radiation exposures, in line with ALARA have two objectives:
to minimize the amount of personnel time spent in radiation areas,
to minimize radiation levels in routinely occupied Plant areas and in the vicinity of
Plant equipment expected to require personnel attention.
Equipment and facility design are considered in maintaining occupational radiation
exposures ALARA during plant operations including: normal operation, maintenance and
repairs, refueling operations and fuel storage, in-service inspection and calibrations,
radioactive waste handling and disposal, and other anticipated operational occurrences.
General equipment design considerations to minimize the amount of personnel time
spent in a radiation area include:
Reliability, durability, construction, and design features of equipment, components,
and materials to reduce or eliminate the need for repair or preventive maintenance.
Service convenience for anticipated maintenance or potential repair, including ease
of disassembly and modularization of components for replacement or removal to a
lower radiation area for repair.
Page 320
Chapter 9
General facility layout design considerations to minimize the amount of personnel time
spent in a radiation area include:
locating equipment, instruments, and sampling stations which will require routine
maintenance, calibration, operation, or inspection, for ease of access and minimum
required occupancy time in radiation areas,
laying out Plant areas to allow remote or mechanical operation, service, monitoring,
or inspection of highly radioactive equipment,
providing, where practicable, for transportation of equipment or components
requiring service to a lower radiation area.
General facility layout design considerations directed towards minimizing radiation levels
in Plant access areas and in the vicinity of equipment requiring personnel attention,
include:
separating radiation sources and occupied areas, where practicable (e.g., pipes or
ducts containing potentially highly radioactive fluids, do not pass through occupied
areas),
providing adequate shielding between radiation sources, and access and service
areas,
where appropriate, separating equipment or components in service areas with
permanent shielding,
locating equipment, instruments and sampling sites in the lowest practicable
radiation zone,
providing means and adequate space for utilizing movable shielding for sources
within the service area, when required,
providing means for decontamination of service areas,
providing means to control radioactive contamination and to facilitate
decontamination of potentially contaminated areas.
Average Environmental Radiation Dose to the Members of Public Out Side of
Exclusion Zone for Operating APPs in India
As per the reports from Environmental Survey Laboratory (ESL), BARC, the average
environmental radiation dose (micro Sievert per year) at 1.6 Km radius due to operation
of Nuclear Power Plants in India 2006-2010 is given in the Fig. 9.3. The present AERB
public domain dose limit is 1000 micro Sievert/year. It may be seen that the public
domain dose values in case of TAPS, RAPS and MAPS have been reported to be
mostly below 50 micro Sievert / year (20 times lesser than stipulated standard). In the
case of NAPS, KAPS and Kaiga, these value are in the range of 1.7 to 2.8 micro Sievert
/ year. This is also to mention that these values are excluding background natural
radiation average dose of 2400 micro Sievert / year and medical exposures. This
indicates that the exposure of public to the radiation is far below the stipulated limit in all
the nuclear power plants in India.
2012 MECON Limited. All rights reserved
Page 321
Chapter 9
Fig. 9.3: Public Dose at 1.6 Km distance from NPPs (2006-2010) (AERB Prescribed
Annual Limit is 1000 micro-Sievert)
Page 322
Chapter 9
9.5
Type of samples
Surface water
Drinking water
Well water
Air Samples for tritium
Air samples for particulates
Goat Thyroid
Vegetables, milk, pulses, cereals, meat, eggs, fish, etc.
Weed, silt, soil, sediments, grass, leaves, etc.
Number
of
Typical
Analysed per Year
500
200
400
500
50
50
70
40
Samples
Page 323
Chapter 9
from significant radiation exposures in the unlikely event of a severe accident. The
probability of a major accident resulting in the releases of large quantities of radioactivity
is extremely small. The probability, however, can never be reduced to absolute zero and
therefore this residual risk is sought to be mitigated by appropriate siting criteria and
implementing suitable arrangements for emergency planning and preparedness.
As stipulated in AERB Safety Guide No. SG/HS-1, to limit the radiological consequences
in public domain, the whole area around NPPs is divided into three domains based on
severity of prevailing radiation fields subsequent to the accidental release of
radioactivity. Appropriate intervention levels and derived intervention levels are assigned
in advance for each domain so that off-site emergency countermeasures could be
implemented in a pre-planned manner. Following countermeasures have been found
suitable to deal with radiological emergency in the public domain.
The selection of one or more of the above protective measures is based on the nature of
the accident and its associated risk and in particular, time factor associated with these
two factors.
The intervention levels as stipulated in AERB Safety Guide No. SG/HS-1 for protective
measures are implemented at very low radiation levels, compared to radiation levels
which cause serious injurious to persons receiving acute whole-body radiation exposure.
The requirements of emergency counter-measures in case of various DBE are
assessed. Emergency counter-measures like distribution of iodine prophylaxis and
sheltering would be needed based on intervention level.
The agencies responsible for carrying out remedial measures during the different
categories of emergencies mentioned above are as follows:
Type of Emergency
Emergency Standby
Personnel Emergency
Plant Emergency
Site Emergency
Off-site Emergency
Responsible Agency
Page 324
Chapter 9
9.5.1
Emergency Standby
Emergency standby is defined as abnormal plant conditions with potential to develop
into accident situations, if timely preventive actions are not taken. During this situation
pre-identified plant personnel are placed in a state of alert for implementing the
emergency response procedure.
9.5.2
Personnel Emergency
When the radiological consequences of an abnormal situation are confined to some
personnel working in a plant, without affecting the plant, it is described as a personnel
emergency. For example, some of the plant personnel may be working at a location
within the reactor building where the radiation field is significantly above prescribed limits
for extended period resulting in their excessive radiation exposure. Some other
examples of personnel emergency are given below:
o splashing of radioactive material on personnel while carrying out
o operation/maintenance in such a manner that excessive contamination,
o internal and/or external, has occurred or is suspected;
o high uptake of radioactive material has inadvertently occurred or is suspected;
o personnel contamination at levels exceeding prescribed limits;
o high external exposures has occurred or is indicated;
o the person is physically ill or incapacitated;
o exposed to a heavy chlorine dose in a chlorine plant.
9.5.3
Plant Emergency
When the radiological consequences of an abnormal situation are expected to remain
confined to the plant, it is described as a plant emergency. This situation may arise
during operation or shutdown maintenance of the reactor.
9.5.4
Site Emergency
An accidental release of radioactivity extending beyond the plant but confined to the site
boundary (exclusion zone) constitutes a site emergency. An assessment of such a
situation would imply that protective measures are limited to the exclusion zone. Site
Emergency is declared and terminated by Site Emergency Director (SED). The
protective measures in a Site emergency include evacuation from the affected parts of
the site and also radiological monitoring of the environment in the Emergency Planning
Zone (EPZ). The emergency reference level for on-site emergency is given below.
9.5.5
Page 325
Chapter 9
The protective measures in public domain shall be implemented by the District Officials
under the supervision of the district collector or the divisional Commissioner, who shall
be designated as the Off-site Emergency Director (OED).
The manual on Off-site Emergency Response Plans would be issued by the State Level
Emergency Response Committee. The manual shall specify the need of radiation impact
assessment based on immediate, intermediate and long-term consequences according
to space-time domain concept and the necessary intervention measures such as
evaluation, sheltering and food control. Off-site emergency shall be declared and
terminated by OED on the basis of technical assessment made by SED.
The Station Director HAPP is identified as the Plant Emergency Director (PED) and all
the Superintendent and Health Physicist are the members of the plant Emergency
Committees.
Consequent to the declaration of the site emergency the Station Director of HAPP
handover the charge of Plant emergency director (PED) to Chief Superintendent and
assumes the charge of Site Emergency Director (SED). The PED provides all plant
related information to the SED and works as per the advice of the SED to mitigate the
situation in the plant.
The SED is the Chairman of the Site Emergency Committee (SEC) and is responsible
for convening the SEC, when the 1st report of the initiation of an emergency is received
by SED. SED shall obtain technical inputs, such as particulars of the accident, from the
members of the SEC. The decisions for declaration/termination of an emergency shall
be based on inputs so obtained. The Site Emergency Organisation structure & the
recommended plant emergency response action flow diagram are chalked out.
Consequent to the declaration of the Off-site emergency For HAPP, the District
Collector, Fatehabad will be the Off-site Emergency Director (OED). Its membership
includes the chiefs of all public services relevant to the emergency management in the
district and the Station Director of HAPP. The OED shall be the Chairman of the Off-site
Emergency Committee (OEC) and is responsible for convening OEC when the report of
the initiation of an emergency is received by OED. The Action Flow Diagram for the
site/off-site emergencies and Information Flow Diagram for site/off-site emergencies
have been chalked out.
The Shift Charge Engineer (SCE) on duty is among the first to learn about the
occurrence of an off-normal situation. He shall evaluate the condition and the data on
the basis of which an emergency may be declared / terminated. He shall notify SED
about any condition which may warrant the declaration of an emergency.
9.5.6
Exercises
Emergency scenarios shall be developed to test emergency plans and operational
response at all levels. Exercises and drills shall be conducted once in a quarter for Plant
Emergency to see that the staffs are adequately trained and all the emergency
Page 326
Chapter 9
equipment are kept in good conditions. At the end of each exercise/drill an evaluation of
the response call shall be carried out to take care of any deficiency noticed. Site
emergency exercise is carried out once in a year. Off-site Emergency exercise is carried
out once in two years.
Emergency plan shall be reviewed at least once in five years, the improvements and
updating procedures shall be implemented based on feed back and critiques from
exercises.
Periodic exercises are conducted as per stipulation of AERB with the active participation
of relevant state and public authorities. These exercises are witnessed by observers
from Crisis Management Group (CMG), DAE, AERB, BARC and NPCIL-HQ.
Feed back is a very valuable aspect of the exercise of offsite emergency and authorities
will resolve the deficiencies surfaced out and action plan will be chalked out depending
upon the requirements.
The approved plan for HAPP will be ready before criticality of HAPP.
The nature and magnitude of response measures would depend on the specific category
or extent of emergency. Though safety evaluation of an APP relates to design basis, the
HAPP emergency response plan shall be based not only on design basis events but also
on accident conditions due to more severe events, even if they have a very low
probability of occurrence. An analysis of such events and the projected radiological
consequences specific to the APP shall form the basis of response plan, so that the
nature and magnitude of response actions could be established.
9.5.7
9.5.8
Page 327
Chapter 9
Communication
The responsibility of communication during emergency lies with Communication Group.
This group ensures that all communication equipment is kept functional at all time. It
consists of Engineer-in -charge of the Plant, communication system, Telephone
operators and wireless operator.
Resources and Facilities
Main Control Room conference room will be made into Plant Emergency Control Centre
(PECC) and Station Directors Office will be converted in to Site Emergency Control
Centre. These centers will be provided with communication facility within the HAPP site
and outside agency.
The plant emergency equipment centre will be located at Administrative building or any
suitable location and it will be augmented with ready to use equipment for the plant /site
emergency. Normally Zone-II and Zone III area shower and wash room are to be used
for emergency personnel decontamination purpose. However there will be a separate
facility for casualty at Residential complex hospital when it is commissioned. A special
emergency service vehicle fitted with two way radio equipment and necessary
monitoring & survey equipment will be available at all time under control of on duty Shift
Charge-Engineer (SCE). Different assembly areas for different working groups will be
identified inside the operating area or plant fencing and maintained for assembly in the
event of an emergency. Emergency shelter locations will be identified for sheltering
/evacuation due to emergency condition and the plant personnel shall proceed to the
shelter areas in the event of an emergency.
Action plan for responding to Emergency
After hearing the emergency siren and announcement about emergency situation and or
getting information of the same through telephone, all responsible members of the JEC
shall proceed to Main control room/ PECC. Details of handling plant /on-site emergency
situations will be documented and made available at PECC. The action flow diagram for
on site and off site emergencies is given in Fig. 9.4.
9.5.9
Page 328
Chapter 9
As per AERB requirements, the exclusion zone covers a distance of about 1.0 km
around the plant site within which no habitation is permitted and is protected by security
personal from state /central government agency/Central Industrial Security Force (CISF).
The sterilized zone covers a distance from exclusion boundary at 1.0 km to 5 km radius
around the plant site within which natural growth of population is permitted and
unrestricted growth of population and development are controlled by state administration
through administrative measures. The zone of 0 -16 km is termed as emergency
planning zone (EPZ) and is divided in to 16 sectors marked as A to P in clockwise
direction .
9.5.10 Frequency /Periodicity of Emergency Exercises
Page 329
Chapter 9
Outdoor air, now passes via filters, is cleaned, and supplied to suction of the air
conditioning system. The air conditioning system continues functioning as in mode I.
Mode III Mode of Total Isolation of the MCR Rooms
This mode is introduced during emergencies for a period permitting the external services
of radiometric and chemical control to determine the content and concentration of toxic
substances in the atmospheric air in the MCR conditioners air intake area.
Besides, mode III shall be introduced in case of the outdoor air contamination by toxic
substances, carbon monoxide (in case of fire) and other harmful substances not retained
by the absorbing filters. In mode III air-tight valves in the outdoor line close, the operator
opens manually a valve on compressed air pipeline. On loss of power supply to the
system the operator manually opens a valve on compressed air pipeline. The
conditioning system continues operating for full recirculation.
To maintain the required pressure in the MCR rooms, compressed air from cylinders is
used. The mode duration is assumed to be 4h, without replenishment. With
replenishment, the occupancy for indefinite period is possible. Storage location on the
cylinders is decided considering this aspect.
By signals of external surveillance services the operator takes decision about the
necessary mode of ventilation (I, II, III).
Page 330
Chapter 9
Fig. 9.4 : Action Flow Diagram for Site / Off Site Emergencies
2012 MECON Limited. All rights reserved
Page 331
Chapter 9
Risk Categories
Affected Zone
1
2
Normal operation
Operational
deviations
Natural or any man
made incidents/
accidents without
release of
radioactivity
Nil
Nil
9.6
Hypothetical Incidents
or accidents that
causes impact within
operating area or plant
boundary
Hypothetical Incidents
or accidents that
causes impact with in
Plant boundary and
within 1.6 km radius
(Exclusion Zone)
Hypothetical Incidents
or accidents that
causes impact beyond
1.6 km radius
(Exclusion Zone)
Classification of
Emergency/ agency
for handling it
Nil
Nil
Risk to Public
Nil
Nil
Plant Emergency/
Plant management as
per existing
preparedness
procedure
Plant Emergency/
Plant management as
per existing
preparedness
procedure
Nil
On-Site Emergency/
Site/Plant
management as per
existing emergency
preparedness
procedure for on-site
Off-Site Emergency/
off-Site emergency
preparedness
procedure/manual
Nil
Nil
Countermeasures
are implemented to
mitigate the
consequences.
Page 332
Chapter 9
9.6.1
9.6.2
Occupational Health
Occupational health needs attention both during construction and erection and operation
and maintenance phases. However, the problem varies both in magnitude and variety in
the above phases.
Full fledge hospital facilities will be made available round the clock for attending
emergency arising out of accidents, if any.
Construction and Erection Phase
The occupational health problems envisaged at this stage can mainly be due to
constructional accident and noise. To overcome these hazards, in addition to
arrangements to reduce it within the threshold limit value (TLVs), personal protective
equipments will be supplied to workers.
Operation and Maintenance Phase
The problem of occupational health, in the operation and maintenance phase is due to
noise hearing losses. Suitable personnel protective equipment will be given to
employees.
9.6.3
Page 333
Chapter 9
Safety Plan
Safety of both men and material during construction and operation phases is of concern.
The preparedness of an industry for the occurrence of possible disasters is known an
emergency plan. The disaster in the project is possible due to leakage of hazardous
chemicals / radiation, collapse of structure and fire / explosion etc.
Keeping in view the safety requirement during construction, operation and maintenance
phases of the proposed plant, a safety policy will be formulated with the following
regulations:
Page 334
Chapter 9
9.6.5
To take steps to ensure that all known safety factors are taken into account in the
design, construction, operation and maintenance of plants, machinery and
equipment;
To ensure that adequate safety instructions are given to all employees;
To provide wherever necessary protective equipment, safety appliances and clothing,
and to ensure their proper use;
To inform employees about materials, equipment or processes used in their work
which are known to be potentially hazardous to health or safety;
To keep all operations and methods of work under regular review for making
necessary changes from the point of view of safety in the light of experience and up
to date knowledge;
To provide appropriate instruction, training, retraining and supervision to employees
in health and safety, first aid and to ensure that adequate publicity is given to these
matters;
To ensure proper implementation of fire prevention methods and an appropriate fire
fighting service together with training facilities for personnel involved in this service;
To organize collection, analysis and presentation of data on accident, sickness and
incident involving personal injury or injury to health with a view to taking corrective,
remedial and preventive action;
To promote through the established machinery, joint consultation in health and safety
matters to ensure effective participation by all employees;
To publish / notify regulations, instructions and notices in the common language of
employees;
To prepare separate safety rules for each types of occupation / processes involved in
a project; and
To ensure regular safety inspection by a competent person at suitable intervals of all
buildings, equipments, work places and operations.
Safety Organization
Construction and Erection Phase
A qualified and experienced safety officer will be appointed. The responsibilities of the
safety officer will include identification of the hazardous conditions and unsafe acts of
workers, giving advice on corrective actions, conduct safety audit, organize training
programs and provide professional expert advice on various issues related to
occupational safety and health. He will also be responsible to ensure compliance of
Safety Rules / Statutory Provisions. In addition to employment of safety officer by the
project, every contractor, who employs more than 200 workers, will also employ one
safety officer to ensure safety of the worker, in accordance with the conditions of
contract.
Operation and Maintenance Phase
When the construction is completed the posting of safety officers would be in accordance
with the requirement of Factories Act and their duties and responsibilities would be as
defined there of.
Page 335
Chapter 9
9.6.6
9.6.7
Safety Training
A full fledged training center will be set up at the plant. Safety training would be provided
by the Safety Officers with the assistance of faculty members called from Corporate
office, Professional Safety Institutions and Universities. In addition to regular employees,
limited contractor labors would also be provided safety training. To create safety
awareness safety films would be shown to workers and leaflets would be distributed.
In general some of the precautions and remedial measures which would be stressed to
the workers to prevent fires would be:
Compartmentalization of cable galleries: use of proper sealing techniques of cable
passages and crevices in all directions would help in localizing and identifying the
area of occurrence of fire as well as ensure effective automatic and manual fire
fighting operations;
Spread of fire in horizontal direction: Checked by providing fire steps for cable shafts;
Reliable and dependable type of fire detection system with proper zoning and
interlocks and alarms - for conveyor galleries as an effective protection method.
High standard house keeping to eliminate the causes of fire and regular fire watching
system to strengthen fire prevention and fire fighting; and
Proper fire watching by all concerned.
9.6.8
Page 336
Chapter 9
10.3
Page 337
Chapter 10
annual fuel requirement for each unit of 4x700 MWe (PHWR) power station is:
Atomic 4x700MWe
Super Critical
The break-even discount rate for nuclear vs coal-fired power generation has been
worked out at various distances from coal pit-head. The result shows that the nuclear
power is favorable for regions located away from pit-head. About 90% coal reserves in
India are located in Bihar, Jharkhand, Orissa, Madhya Pradesh and West Bengal. Thus
the parts of the country, much away from coal mines, are economically better location for
nuclear.
Further, for illustrative purpose, the costs of electricity generation from nuclear and coalfired power at various locations from coal pit-head for the first eight years of operation
are indicated in Table 10.1.
Table 10.1: Nuclear and Coal-Fired Power - Per Unit Cost in Paisa
Year of
Nuclear*
Coal Fired Thermal Power Plant (km distance from pithead)
Operation
500
600
700
800
900
1000
Cost per unit (Paisa/kwh)
1
260
234
243
251
260
268
276
2
266
241
250
259
268
277
286
3
273
249
258
268
277
286
295
4
281
257
267
276
286
296
305
5
288
265
275
286
296
306
316
6
270
254
264
275
286
297
307
7
279
263
274
285
297
308
319
8
288
272
284
296
308
320
332
* Not affected by distance
It is observed that cost of coal-fired power generation is very sensitive to its location
form pit-head. At very near to pit-head e.g. at about 500 km. Cost of nuclear generation
is only marginally higher than the cost of coal-fired generation (about 1-25 paisa/kwh for
about half the lifetime period). At a distance of about 700-800 km from pithead, nuclear
is cheaper. Therefore, Fatehabad site, which is far away from the coal pit head (1185km)
and on the NW part of the country is ideal site on economical considerations for locating
Atomic Power Plant.
Page 338
Chapter 10
The contribution of fuel cost is least in case of nuclear and this gives long term economic
advantages to Atomic over others. It is to mention that the distance of the coal pit form
Fatehabad site is around 1185 km, which makes the Fatehabad site cost competitive for
establishing Atomic Power Plant.
10.4
10.5
Page 339
Chapter 10
Energy Sources
Gram CO2/KWh Ratio (over Atomic Power)
Gas
181
22.63
Oil
205
25.5
Coal
295
36.88
Source: Working Material for RCA Workshop on Economic and Financial Aspect of
NPPs-MANILA (August 1997)
Fig. 10.1: Comparison of Waste Production from Nuclear and Thermal Power
Stations
10.6
Page 340
Chapter 10
The policy of NPCIL towards social welfare & community development aims at
strengthening the bond between the project / station authorities and the local population
in the vicinity of nuclear power plants. In line with this policy, NPCIL at the existing
stations and projects will carryout a number of community welfare activities in the
following areas:
Education Gyan Gangothri Yojana
Health Arogya Sudha Yojana
Community Welfare
The following action plan will be followed for implementing social and community welfare
measures in area around the HAPP:
NPCIL would contribute in implementing social welfare activities in collaboration with
local Gram Panchayat, Block Development Office etc. for better development of
area.
To minimize strain on existing infrastructure, adequate provision of basic amenities,
viz. education, health, transport etc. would be made considering the needs of
workforce and migrating population.
Sanitation facilities in residential complex and labour colonies would be provided to
ensure better hygiene and health
Regular environmental awareness programs would be organised by NPCIL to
impress upon the surrounding population about the beneficial impacts of the project
and also about the measures being undertaken for environmental safety.
10.7
SN
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
+
Income
+
+
+
Transport
+
Education
+
Medical facilities
+
Communication
+
Availability of power supply +
+
Sanitation
+
+
Housing
+
Health
+
+
Agriculture
+
+
Cost of living
Page 341
Chapter 10
SN
Parameter
13. Business
14. Per Capita Income
+ Positive Impact
10.8
10.8.1
Direct
Indirect
+
+
+
-Negative Impact
Reversible Irreversible
+
Insignificant
EMPLOYMENT POTENTIAL
Skilled and Semi-skilled
Skilled and Semi-skilled employment potential in terms of indirect employment of the
proposed project will be non-marginal and will usually remain widespread across a long
region. The proposed project will cause generation of income and employment
opportunities the ancillaries and service units which will came in the vicinity of the plant,
specifically, in transport and manufacturing sectors. The project is expected to generate
substantial indirect employment in other sectors. Overall assessment of the employment
and income effects indicates that the project has strong positive direct as well as indirect
impact on employment and income generation of the area.
10.8.2
Un-skilled
Unemployment for un-skilled workers is quite common in the study area. The present
project has employment generation potential by way of recruiting local people directly for
different activities of the project, specifically at the construction phase. It is expected that
substantial portion of the investment in this project will trickle down to the local people in
the form of employment and income.
10.8.3
Page 342
Chapter 10
construction, operation and maintenance phase of the Plant. This also meets the
provisions of National and State R&R Policy. The brief details are given below:
Award of Small Value Contracts to Registered Local Societies
NPCIL promotes formulation of Registered Societies consisting of members from local
including Project affected families. These Societies are proposed to be given small value
contracts for auxiliary services such as Housekeeping, Gardening, Transport service etc.
with the provisions to deploy as much Project affected persons in the project as possible.
These societies will be awarded various contracts like (i) contract for Housekeeping to
maintain the Liaison Office-cum-transit Guest House of HAPP at Fatehabad, (ii) contract
to meet transport service requirement of the Liaison Office at Hisar and (iii) contract for
providing fabricated wooden boxes for storage of borehole logs at the site.
Allotment of Shops in Residential Complex
NPCIL also propose to provide allotment of shops in Shopping Centre of Residential
Complex at HAPP like Milk Vending, Barbershop, Washer man shop, Vegetable
shops, Communication centre, Chemist shop etc. through Registered Societies.
10.9
Page 343
Chapter 10
The local peoples interest towards education will increase due to the expectation of
getting jobs, especially from non-agricultural sources such as the industries (which
are expected to grow in the vicinity of the proposed project.
The project is expected to increase such aspirations by bringing opportunities of
some direct & indirect employment for the local people.
The general awareness towards the importance of education is expected to increase
as a result of the new project.
The project will have positive impact on the level of education of the people of the
study area.
Page 344
Chapter 10
With the implementation of the project and development of the locality, existing demand
pattern is likely to continue which indicates more importance on consumer goods and
quality products. This will affect the local consumer goods market will grow, thus creating
more income opportunities to the local people
10.11.5 Consumption Behaviour
Presently in the area the major portion of total consumption expenditure goes to meet
the need for food followed by expenditure on clothing, expenditure of social
requirements and expenditure on medical services. The expenditure on education in the
study area is observed to be medium. The proposed project is going to have positive
income effect and consequently, the multiplier effect is expected to lead to an overall
increase in average consumption of the people of the study area.
After the implementation of the proposed project, average family income of the study
area is likely to grow. As income increases, Marginal Propensity to Consume (MPC) will
rise in first three years and then will taper down.
Page 345
Chapter 10
11.1
GENERAL
Environmental Management Plan is the formulation, implementation and monitoring of
environmental protection measures during and after commissioning of the project.
Objectives of EMP
Ensure the mitigation measures are implemented
Establish systems and procedures for this purpose
Monitor the effectiveness of mitigation measures and
Take any necessary action when unforeseen impact occur
Components of EMP
1. Careful consideration of the site for its suitability to the proposed activity - described
in Chapter 2, Section 2.4.
2. Potential impact (based on baseline environmental study) & proposed mitigation
measures for different stages of the project - Chapter 5, Impacts and Mitigation
Measures.
3. Installation of state of art pollution / radiation level control equipment and devices as
described in Chapter 6 Technological Mitigation Measures.
4. Various measures proposed to be taken including cost components (Section 7.6.4,
Chapter 7).
5. Adopting a very strong monitoring / analysis programme - Chapter 7,
Environmental Monitoring Programme.
6. Administrative and technical setup for management of environment for:
- Monitoring facilities setup
- For regular and periodic monitoring of indicator parameters.
- Regular analysis of the results of the Environmental Monitoring to ensure that
the indicator parameters are within the stipulated norms vis--vis the adopted
mitigation measures are working efficiently.
- Periodic review by the higher management to see that the monitored indicator
parameters are within the expected range and if not to draw the intervention
of higher management.
- Institutional arrangements proposed with other organizations / Govt. authorities
for effective implementation of environmental measures proposed in the EIA, .
Point number 1 to 5 of the EMP have been covered as referred above, the
organizational setup for environmental monitoring is being presented hereunder under
Section 11.3.
Page 346
Chapter 11
11.2
ORGANIZATION POLICY
The importance of environmental control has been recognised by project proponent at
the organizational level. Environment Management has been declared as one of its
thrust areas of operation in the proposed project and other units. Accordingly NPCIL has
a Corporate Environmental Policy approved by CMD, NPCIL.
The above objective has been intended to be achieved through the following:
i)
ii)
iii)
iv)
v)
Using automation & Computer control to have state of the art technology.
Pollution Monitoring and Control,
Occupational health set up including regular medical monitoring of employees,
A well developed safety management organisation,
Preparation of Emergency / Disaster Control plan and a properly trained group to
meet the emergency situations,
vi) Green belt development inside the plant and surroundings.
vii) Development of awareness in employees and public including student population
towards environmental preservation,
viii) R & D activities in regard to specific pollution problems.
The proposed project has given maximum importance for adopting latest technologies
for keeping the pollution to minimum levels. A separate Environment Survey Laboratory
will be set up with an Environmental Laboratory with latest monitoring instruments.
11.3
ORGANISATIONAL SET UP
Page 347
Chapter 11
The person responsible for taking care of all environmental issues at Technical services
Unit (TSU) will be of the rank of General Manager (GM). In his day-to-day work, DGM
(Environment) will be assisted by three Managers namely, Manager (Environment) of
Wate Management Unit (WMU) and Station Chemist from Chemical laboratory and
Station Health Physist from Health Physics Unit (HPU). These three Laboratories on
requirement may further include Technicians / Laboratory Assistants. The organizational
chart at the project and the proposed manpower required to undertake the
environmental aspects of the proposed APP is given in Fig. 11.1.
During operation stage, for monitoring of radiation outside exclusion zone is done by
Environmental Survey Laboratory under Health Physics Division, BARC, which reports
to BARC with intimation to Station Director (SD)..
The organizational composition for other departments like Infrastructure Unit
(Department), Health Physics Unit, Medical Unit, Horticulture Unit, Industrial Safety
group and Corporate Social Responsibility (CSR) Unit, responsible for different aspects
of environmental monitoring programme, will be framed before the start of construction /
operation phase of the project. Here only orgainsational set-up looking after
environmental monitoring is being presented, which is responsible for major portion of
environmental monitoring programme (Table 7.3 Part A and Table 7.4).
INCHARGE WASTE
MANAGEMENT UNIT
Group of Scientific
Officers / Scientific
Assistants &
Technician(s)
STATION
CHEMIST
CHEMICAL LAB
Group of Scientific
Officers / Scientific
Assistants &
Technician(s)
STATION
HEALTH
PHYSISTS HPU
Group of Scientific
Officers / Scientific
Assistants &
Technician(s)
Page 348
Chapter 11
The personnel deployed in the laboratory will be given training to carry out necessary
environmental monitoring including radiation monitoring as well as analysis. The
recruited officers shall be adequately trained to undertake the environmental
requirements of the proposed plant. The requirement of equipments for carrying out
environmental monitoring and frequency of the use of different equipments for the
proposed plant is given in Table 11.1.
Table 11.1: Monitoring / Analytical Equipments Required
Monitoring Equipments
Equipments
Numbers
Required
Air / Stack / Noise Monitoring
1.
PM2.5 & PM10 sampler
3
along with gaseous
sampling assembly
2.
Stack Monitoring Kit
2
(manual)
3.
Portable Flue Gas
2
Analyser for stack
monitoring
SN.
4.
5.
Continuous AAQ
Monitoring Station SO2,
NOx, CO & PM2.5 & PM10
Sound Level Meter
Parameter / Function
Frequency
24 hr continuous;
Once per month
CO%
3
SO2 mg/m
NOX mg/m 3
NO mg/m 3
CXHY PM
Temperature
PM10, PM2.5, SO2, NOx & CO
Noise Level
As
and
required
Meteorological parameters
Continuous
NH3, CN, F
Regularly
Regularly
Meteorological Monitoring
6.
Automatic
Weather
1
Monitoring Station
Water Monitoring & Chemical Analysis
7.
Ion Analyser with Auto1
titrator
8.
Hot Air Oven
1
9.
Hot Plate
10.
Muffle Furnace
11.
12.
1
1
13.
BOD Incubator
BOD Apparatus, Oxitop
(1 set of 6)
DO Meter
BOD
14.
Spectrophotometer
15.
COD
COD,
NO3 N
PO4 - P
COD
Digestion
Continuous
Regularly
As
and
when
required
Twice in a week
Twice in a week
As
and
required
Regularly
Regularly
Page 349
Chapter 11
when
when
SN.
Parameter / Function
Frequency
pH
TDS
Heavy metals in water & As & Ni
analysis
Regularly
Regularly
As
and
required
Weighing
Weighing
Regularly
Regularly
Regularly
Regularly
Regularly
21.
22.
23.
Monitoring Equipments
Equipments
Numbers
Required
Assembly
pH meter
2
Conductivity Meter
1
AAS along with Graphite
1
furnace,
Hydride
Generator and Cold
Vapour Technique
Digital Micro-Balance
2
Digital
Top
Load
1
Balance (Range 1 to
500g)
Filtration Apparatus
2
Heating mental
3
Refrigerator
2
24.
Fuming Chamber
SS / MLSS
Distillation
Preservation of chemicals and
samples
For exhaust
25.
26.
Water Bath
Vacuum pump
2
2
Evaporation of sample
Hardness alkalinity etc.
27.
Turbidity Meter
Turbidity
16.
17.
18.
19.
20.
28.
Filter
Papers,
Glassware,
Plastic
wares, Chemicals
Radiation Monitoring
29. High
Volume
Air
samplers
30. Ashing equipment
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
As
and
when
required
As when required
As
and
when
required
As
and
when
required
In Lot
4
2
Regularly
Regularly
2
1
1
1
-do-do-do-do-
Regularly
Regularly
Regularly
Regularly
-do-
Regularly
-do-
Regularly
-do-
Regularly
-do-
Regularly
-do-
Regularly
Regularly
Regularly
Page 350
Chapter 11
when
SN.
42.
43.
44.
Monitoring Equipments
Equipments
Numbers
Required
Instrumented
1
Meteorological tower
Portable
Diesel
1
Generator set
Parameter / Function
Frequency
-do-
Regularly
-do-
Regularly
Filter
Papers,
Glassware,
Plastic
wares, Chemicals
-do-
Regularly
In Lot
11.3.3 Functioning
Environmental monitoring programme and its reporting has been designed to provide a
close watch on the surrounding environment and provide early warnings of any adverse
changes that may be related to some dimension of the plants operations.
The Environmental Survey Laboratory (ESL) of BARC and Waste Management Unit
(WMU), Chemical Laboratory and Health Physics Unit (HPU) will look after the major
portion of the environmental aspects, carry out day to day environmental monitoring /
inspection requirements and maintain records. These laboratories will look after the
radiation monitoring, complete air monitoring, noise level monitoring, special monitoring
on water and air, effluent, special surveys and impact assessment and solid waste
management. The over all responsibility matrix of monitoring different aspects of
environmental monitoring plan are given in Table 7.3A and 7.4, Chapter 7.0. Part or
total of the environmental monitoring programme will be carried out through external
agencies on a contract basis. However, casual labourers etc. will be employed for
plantation, drain cleaning etc as and when required.
The TSU shall frequently analyse the data and periodically assess the progress of the
EMP.
11.4
IMPLEMENTATION ARRANGEMENT
Page 351
Chapter 11
The EMARC will consist of heads of different sections of the project. The Project Director
/ Station Director will be overall In-charge of the Project / Station. The role of the EMARC
would be to review the implementation of all environment related matters. TSU and other
units of the plant looking after different aspects of environmental monitoring programme,
will report all the environmental matters to PD / SD as per the reporting schedule on
prescribed formats. The EMARC will review the reported activity from time to time for
smooth implementation of Environmental Mitigation and Management measures and will
suggest necessary actions if required.
For successful implementation of the environmental management plan other agencies of
the State may also be involved, if required (for regulatory requirement or technical
support). The coordinating agencies, which may be involved for specific environmental
related activities, are given in Table 11.2.
Table 11.2: List of Coordinating Agencies, which may be involved for specific
Environmental Activities
State Level Agency
SFD
District Level
Project Area: Plantation Programme
Study Area: Air, noise, water quality, soil,
waste water discharge quality monitoring.
Radiation Monitoring
Study Area: CSR Activities
Project Area: Stack monitoring, work-zone
noise, effluents from outlet of STP.
Project Area: Solid / Hazardous Waste
Disposal
Project Area: Radiation Monitoring &
Human Health
Study Area / Project Area Interface: Road
safety measures
DFO
SPCB
Chairman
RO
DOH
Chief Engineer
Ex. Engineer
DDA
Chief Engineer
Ex. Engineer
Index:
SFD
SPCB
DOH
DDA
DFO
RO
Local NGOs will also be identified at the district and block level to provide help and
advice for implementation of EMP especially on matters related to community
development programmes.
11.4.2 Co-ordination with Other Departments
The Technical services Unit (TSU) will also co-ordinate with other departments of HAPP
like Occupational Health, Safety Management, Project Engineering, Horticulture and
2012 MECON Limited. All rights reserved
Page 352
Chapter 11
Corporate Social Responsibility (CSR) Unit, Water Supply Department etc. and also do
the liaison work with external agencies like State Pollution Control Board..
11.4.3 Interaction with State Pollution Control Board
TSU shall be in regular touch with SPCB and shall send them quarterly progress report
on EMP in the prescribed format, as per the prevailing practice of the Board. Any new
regulations considered by State Pollution Control Board / Central Pollution Control Board
for the Industry shall be taken care of by responsible units.
11.4.4 Training
The different laboratories and departments who would be responsible for the
implementation of the EMP, needs to be trained on the effective implementation of the
environmental issues. To ensure the success of the implementation set up proposed,
there is a high requirement of training and skill up-gradation. For the proposed project,
additional training facilities will be developed for environmental control. For proper
implementation of the EMP, the officials responsible for EMP implementation will be
trained accordingly.
To achieve the overall objective of pollution control it is essential not only to provide
latest pollution control and monitoring systems but also to provide trained man power
resources to operate and maintain the same. So far, the practice with many plants is to
utilize the plant operations and maintenance crew for operation of systems. This has
shown adverse results due to lack of specialized knowledge in addition to priority
selection. Therefore apart from the different laboratories involved, specific training will be
provided to personnel handling the operation and maintenance of different pollution /
radiation control equipments. In-plant training facilities will be developed for
environmental control. Specialised courses at various Research / Educational institutes
will be organised.
The training will be given to employees to cover the following fields:
Awareness of pollution control and environmental protection to all.
Operation and maintenance of specialised pollution / radiation control equipment.
Field monitoring, maintenance and calibration of pollution / radiation monitoring
instruments.
Laboratory testing of pollutants / radiation.
Repair of pollution monitoring instruments.
Occupational health/safety.
Disaster management.
Environmental management.
Afforestation / plantation and post care of plants.
Knowledge of norms, regulations and procedures.
Risk assessment and Disaster Management.
2012 MECON Limited. All rights reserved
Page 353
Chapter 11
Page 354
Chapter 12
DISCLOSURE OF CONSULTANT
The EIA report has been prepared by MECON Limited, a Public Sector undertaking
under the Ministry of Steel Government of India, is a premier multi disciplinary planning,
design, engineering and consultancy organisation in the country in the field of ferrous,
non-ferrous, thermal, petrochemical, defense and other related projects and in the field
of environment. MECON's Head Office is at Ranchi and site offices in Bangalore, New
Delhi, Bhubenashwar, Pune, Vyzak, Bhailai, Durgapur, Raurkela, Bokaro, and many
other places in the country. The Environmental Engineering Division of MECON has
provided services for more than 200 numbers of Environmental projects.
MECONs Environmental Engineering Division is a multi-disciplinary group of engineers,
specialists and scientists whose services are backed up by a sophisticated
Environmental Engineering Laboratory recognized by Ministry of Environment & Forest
and several State Pollution Control Boards. There are specialists in the field of
hydrogeology, geology, ecology, forestry, microbiology, biotechnology, audit & socio
economics and engineers from different disciplines. MECON has been preparing
regularly EIA / EMP reports for different projects. MECON also renders its services for
rehabilitation action plan for affected people, inspection and audit including
environmental audit, etc.
National Accreditation Board for Education and Training (NABET) - under the
Accreditation Scheme for EIA Consultant Organisations has accredited MECON Limited
as EIA consultant for 16 EIA Sectors, vide NABET notification dated 24.03.11. The list of
sectors for which the accreditation has been accorded by NABET is given in Table 13.1.
The same can be referred from the NABET website www.qcin.org/nabet/about.php ,
by following the link - EIA Accreditation Scheme Accreditation Register Accredited
Consultant - List of Accredited Consultants with Scope (Rev. 02) dated 18th
August 2011.. The present EIA study pertains to an Atomic Power Project (APP),
which falls under the category Nuclear power projects and processing of nuclear
fuel.
Table 13.1: List of Sectors for which NABET has given Accreditation
Accreditation for
SN. Sector Details
Category
of
Project
1. Mining of minerals including Opencast / Underground mining
A
2. Only Offshore oil and gas exploration, development & production
A
3. River Valley, Hydel, Drainage and Irrigation projects
A
4. Thermal Power Plants
A
5. Coal washeries
A
6. Mineral beneficiation including pelletisation
A
7. Metallurgical industries (ferrous & non ferrous) both primary and A
secondary
2012 MECON Limited. All rights reserved
Page 355
Chapter 13
8.
9.
10.
11.
12.
13.
14.
15.
16.
Accreditation for
Category
of
Project
Cement plants
A
Coke oven plants
A
Induction/arc
furnaces/cupola
furnaces/submerged
arc A
furnace/crucible furnace/re-heating furnace of capacity more than
5Tonne per heat.
Oil & gas transportation pipeline (crude and refinery/ petrochemical
A
products), passing through national parks/ sanctuaries/coral reefs /
ecologically sensitive areas including LNG terminal
All ship breaking yards including ship breaking units
A
Industrial estates/ parks/ complexes/areas, export processing Zones A
(EPZs), Special Economic Zones (SEZs), Biotech Parks, Leather
Complexes
Ports, harbours, jetties, marine terminals, break waters and dredging A
Highways, railways, transport terminus mass rapid transport
systems.
Common Municipal Solid Waste Management Facility (CMSWMF)
A
For Nuclear power projects and processing of nuclear fuel sector MECONs application
along with other consultants are still pending at NABET. However, till date NABET has
not cleared any application related to nuclear sector.
Page 356
Chapter 13