Académique Documents
Professionnel Documents
Culture Documents
SPECIFICATIONS
For
CIVIL WORKS
August 1999
Page 1 of 10
August 99
SECTION 2
SECTION 3
SECTION 4
SECTION 5
SECTION 6
SECTION 7
SECTION 8
SECTION 9
Page 3 of 10
August 99
Nature of Contract
1.2
General Conditions
1.3
Contractors Responsibility
1.4
Time of Commencement
1.5
1.6
Construction Program
1.7
Discrepancies
1.8
Wet Weather
1.9
1.10
Overtime Worked
1.11
Setting Out
1.12
1.13
1.14
Sanitary Accommodation
1.15
1.16
Explosives
1.17
Maintaining Access
1.18
Safety of Traffic
1.19
Make Good
1.20
Statutory Responsibilities
1.21
1.22
Hours of Work
1.23
1.24
Field Assistance
1.25
As Constructed Notes
1.26
Payment
1.27
Page 4 of 10
August 99
1.1
1.2
GENERAL CONDITIONS
The General Conditions of Contract applicable shall be the Australian Standard
2124-1992. A copy of the General Conditions is not included in the Tender
Documents, but may be inspected in the Market Testing Unit at the Shires
Lilydale Office. Alternatively, Tenderers if they are not familiar with the document,
should obtain a copy for themselves. Annexure Part A and B as they relate to
this Contract are attached.
1.3
CONTRACTORS RESPONSIBILITY
The Contractor shall be entirely responsible for ensuring that all operations and
methods of construction, set out, materials and workmanship are safe, sufficient
and in accord with the contract documents. No inspection by the Superintendent
and no instruction given or certificate issued by the Superintendent shall be
deemed to imply that the Superintendent has assumed or taken over any part of
the contractors responsibility or liability.
Page 5 of 10
August 99
1.4
TIME OF COMMENCEMENT
The contractor shall commence the works of this contract within four weeks of
the date of the Letter of Acceptance of the contract. Failure to commence within
the specified time may be treated as a breach of contract. The contractor shall
give 14 days clear notice in writing to the Superintendent's Representative before
commencing the work.
1.5
1.6
CONSTRUCTION PROGRAM
The contractor will be required to submit for the approval of the Superintendent a
construction program within 14 days of acceptance of tender in accordance with
Clause 33.2 of the General Conditions of Contract.
The program is to allow for installation and alterations of all services.
The period for practical completion of works, as shown in Annexure A, includes
the time required for the installation of services, including those to be installed by
other contractors or authorities, statutory public holidays, industry paid days and
rostered days off.
No claims for extensions of time resulting from the above will be considered.
The contractor shall be deemed to have made his own assessment of the period
required to complete the works and where this is at variance with Annexure A
shall state the period of completion at the time of tendering.
1.7
DISCREPANCIES
Where discrepancies exist between this section of the specification and the
requirements of the General Conditions of Contract, the provisions of this section
shall apply.
Where discrepancies exist between this section of the specification and
requirements of the Municipal or standard technical specifications, the provisions
of this section shall apply. The General Conditions of Contract shall have
precedence over the Municipal or technical specifications.
Page 6 of 10
August 99
1.8
WET WEATHER
The contractor shall allow in his construction program and in the period for
practical completion, an amount for wet weather. The contractor shall be entitled
to extensions of time for wet weather in excess of one day or longer for the
period of time during and after rainfall where work on site is unable to proceed.
1.9
1.10
OVERTIME WORKED
Where approval has been given by the Superintendent's Representative for work
to be carried out other than during normal working hours, any expense incurred
by the Superintendent's Representative for payment of overtime supervision
resulting from such approval shall be deducted from the contract payments.
In this regard, the contractor will be required to give Council 48 hours notice of
his intention to work so that the necessary arrangements of staff may be carried
out.
1.11
SETTING OUT
The Superintendent's Representative has furnished basic reference lines and
bench marks from which the contractor shall establish such other points as may
be necessary for the proper completion of the contract.
The contractor shall take every care to preserve all Engineering reference and
title survey pegs. Any pegs which are to be covered by the work must be kept
marked with stakes and the location of any pegs which must be removed in order
to complete the works must be accurately preserved to the satisfaction of the
Superintendent's Representative. In the event of failure by the contractor to
preserve the position of any survey pegs, which will necessitate a re-survey, the
cost of this survey will be deducted from the contract payments.
1.12
Where the works under this contract are constructed through private property the
contractor shall take whatever precautions are necessary to protect the property,
buildings, occupiers or livestock from any damage or risk. This may include
temporary fencing, shoring, drainage or other works as deemed necessary. The
contractor shall not enter any land or remove any fence until he has given at
least one weeks notice to the owner or occupier of his intention to do so.
On completion of the works, including all reinstatement, a clearance in writing
shall be obtained from the property owner stating that the owner is satisfied with
the reinstatement and does not have any claims for compensation or damages
against the contractor.
1.13
1.14
SANITARY ACCOMMODATION
The contractor shall provide, to the satisfaction of the Superintendent's
Representative, suitable sanitary accommodation for all persons employed on
the works in accordance with relevant industrial awards.
1.15
1.16
EXPLOSIVES
Page 8 of 10
August 99
MAINTAINING ACCESS
The contractor shall program all works in such a manner so as to offer the least
possible obstruction and inconvenience to the public, and he shall have under
construction no greater length or amount of work than he can properly manage
with due regard to the rights of the public.
Unless otherwise specified, all traffic shall be permitted to pass through the
works with as little inconvenience and delay as possible.
All sections of existing formations and side tracks which are being used by traffic
or pedestrians shall be maintained in a safe and trafficable condition throughout
the period of the contract. Material falling on any carriageway as a result of
carting operations shall be removed immediately by the contractor at his
expense.
In the event of the failure of the contractor to provide adequate access, the
Superintendent's Representative may provide such access as he may deem
necessary and deduct the cost thereof from contract payments.
1.18
SAFETY OF TRAFFIC
The contractor shall be held responsible for the safety of traffic and the public
and shall erect and maintain all warning signs, lights and barriers, necessary for
the adequate control and safety of traffic and pedestrians. Adequate illumination
of these signs and barriers shall be provided and maintained by the contractor
and kept alight from sunset to sunrise. All signing and lighting must be in
accordance with the Vic Roads Roadworks Signing Code of Practice AS1742.3.
If the arrangements as provided by the contractor are not considered satisfactory
by the Superintendent's Representative, the contractor shall remedy the defects
immediately, and in default thereof, the Superintendent's Representative may
provide such barriers, warning signs and lights as he may consider necessary
and deduct the cost thereof from contract payments. The contractor will be
required to supply, at his own expense, all necessary barriers, warning signs and
lights.
1.19
MAKE GOOD
Page 9 of 10
August 99
On completion of the work, the contractor shall make good all footpaths,
naturestrips, easements and other surfaces disturbed by the works, do all other
necessary repairs, properly clean up and leave the site in a condition satisfactory
to the Superintendent's Representative.
The contractor shall also re-erect and/or repair, to the satisfaction of the
Superintendent's Representative, all fences, signs, gates and buildings removed
or damaged during the progress of the works.
1.20
STATUTORY RESPONSIBILITIES
Before commencing any excavation in which the depth of face exceeds 1.5 m, or
any tunnelling operation, the contractor shall notify in writing the Department of
Labour, Building and Construction Industry Division, Construction/Excavation
Section and shall comply with the requirements of the Department and the
instructions of any authorised Inspector.
A copy of the Notice of Intention to Commence Operations shall be forwarded to
the Superintendent's Representative prior to commencing work.
The contractor shall comply with the provision of the Extractive Industries Act (if
the material is extracted from more than 2 m below the natural surface) or
Section 17A of the Soil Conservation and Land Utilisation Act (if extraction is
from less than 2 m below the natural surface and covers more than 0.2 ha in
extent). Non-compliance with this clause shall render this contract void, at the
Superintendent's Representative's discretion.
1.21
1.22
HOURS OF WORK
No works or deliveries shall be carried out outside the hours of 7.00am to
5.00pm Monday to Friday, inclusive, or any public or municipal holiday, unless
approval in writing is given by the Superintendent's Representative.
1.23
Page 10 of 10
August 99
The Contractor's construction plant operating during declared fire danger shall:(a)
(b)
(c)
1.24
FIELD ASSISTANCE
The contractor shall provide a person to assist with the checking and surveying
of as constructed works during the course of the contract, as may be required by
the Superintendent's Representative.
1.25
AS CONSTRUCTED NOTES
The contractor must provide on or before practical completion of the contract one
set of construction plans noting any changes made during the course of
construction ( as constructed notes), to the Superintendents Representatives.
The as constructed notes must be made on a clean set of plans in red pen, and
detail anything that has deviated from the design and/ or is outside the specified
tolerances.
1.26
PAYMENTS
The contractor must make all claims for payments in accordance with Councils
standard format as detailed in Appendix 1 of the Specification
1.27
Page 11 of 10
August 99
APPENDIX 1
COUNCILS STANDARD PAYMENT CLAIMS FORM ( Clause 1.21 of the Specification )
Item No:
Description
Quantity
Unit
Rate
Amount
Claimed
1
2
3
4
Amount Claimed
Sub-Total
$
$
Variations
Item No:
Description
Quantity
Unit
Rate
Amount
Claimed
Amount Claimed
1
2
3
4
Sub-Total
Less previous payments
1
2
Amount Claimed
$
$
Sub-Total ($
Total
Page 12 of 10
August 99
APPENDIX 2
................
......./........./......
Melway Ref:
.................
Project:
......................................................................................................
Contractor:
......................................................................................................
Location of Works
.....................................................................................................
Office Hours
Name
Phone
Mobile
Pager
Fax
Phone
Mobile
Pager
Fax
After Hours
Name
If any of the phone numbers are changed throughout the contract, the contractor must inform
Council in writing before the number has changed.
Signature :...................................................................................
...................................................................................
(Please print name )
Date
........../............../ 19..........
2.1
Public Utilities
2.2
Services
2.3
2.4
Service Conduits
ID 6002
Page 14 of 10
August 99
2.1
PUBLIC UTILITIES
Prior to commencing any of the works of this contract, the contractor shall obtain
all relevant information from the appropriate authorities concerning the location of
any water, sewerage or gas mains, underground pipes or cables which may be
affected by the works of this contract. Any alterations to authorities plant (other
than services to households) will be altered and costs borne by the Shire of Yarra
Ranges. The contractor shall have no claims against the Superintendents
Representative for any delay, loss or inconvenience which may occur through the
necessity of such alteration. The contractor shall notify the Superintendents
Representative as soon as possible of any required alterations.
The contractor shall be responsible for any damage which in the opinion of the
Superintendents Representative has been caused to any of the authorities
services by any works or operations under his control. Where any damage is
caused, the contractor shall notify the appropriate authority immediately of the
damage.
The contractor shall at all times keep all water main cocks and fire fighting
appliances free from obstruction.
Should it be necessary to temporarily dump spoil or other material over authorities
surface fittings, the position of these fittings shall be conspicuously marked by the
contractor.
2.2
EXISTING SERVICES
All gas and water services shall be lowered to a minimum of 150 mm below the
finished subgrade level of the road and to 450 mm below the finished levels in the
naturestrip. All such alterations to services shall be carried out by the contractor
at his own expense and he will be held responsible for making good any services
damaged during the execution of the contract work.
Page 15 of 10
August 99
2.3
2.4
SERVICE CONDUITS
Service conduits shall be provided under the road pavement where shown on the
plans or where directed by the Superintendents Representative. The pipes shall
be laid 375 mm below the edge of the low wing and have a rise of 75 mm to the
high side, and shall extend at least 600 mm behind the back of kerb. Where
conduits cross agricultural pipes, the bottom of the service pipe shall be not less
than 75 mm above the top of the agricultural pipe.
Service conduits shall be 50 mm diameter GI pipe, Class 12 UPVC or other type
of pipe approved by the Superintendents Representative and shall be laid on a
straight line and grade. All pipe ends shall be securely plugged.
Page 16 of 10
August 99
The kerb shall be marked over each conduit with a 50 mm high letter indicating
the type of conduit, W to indicate water, G to indicate gas, T to indicate
Telecommunications and E to indicate Electricity conduits
Conduits should be laid square to the road, however, if necessary to lay skewed,
letter marks on the kerbs should also be angled.
Trenches shall not be backfilled until the pipe line has been inspected and
approved by the Superintendents Representative. The pipe trenches shall be
backfilled with 20mm nominal size class 2 fine crushed rock unless otherwise
directed by the Superintendents Representative.
Page 17 of 10
August 99
Description
3.2
3.3
Area
3.4
Clearing
3.5
Grubbing
3.6
3.7
Survey Marks
3.8
Damage to Property
ID 6003
Page 18 of 10
August 99
3.1
DESCRIPTION
Clearing and grubbing shall consist of the removal and proper disposal of all
trees, brush, stumps, logs, grass weeds, blackberries, roots and all decayed
vegetable matter, pole stumps, refuse dumps, and all other objectionable matter
resting on or protruding through the surface of the original ground from the
specified area except as hereinafter set out. It shall also include the removal of
concrete paving and foundations from all areas, and the removal and proper
disposal of all obstructions including kerbs, kerbs and channel, drainage pits,
fences and any old or incidental structures within the specified area which will
conflict or interfere with construction.
The method of clearing, grubbing and disposal of the material cleared and
grubbed from the specified area shall be in accordance with the provisions and
requirements of this specification and in conformity with the requirements
indicated on the plans or as directed by the Superintendent's Representative.
The price for clearing and grubbing shall be included in the cost of the earthworks
unless allowed for in a separate item in the schedule.
3.2
Page 19 of 10
August 99
3.3
AREA
The area to be cleared and grubbed shall comprise the minimum area required for
completion of all works included in this contract.
3.4
CLEARING
The surface within the specified area shall be completely cleared of all perishable
or objectionable vegetable matter and all obstructions as hereinbefore specified.
No trees shall be removed or trimmed without prior approval of the
Superintendent's Representative. Trees shall be felled within the area to be
cleared in such a manner as to avoid damage to vegetation or any property
outside this area.
Separate planning permits for tree removal may be required.
Trees shall be felled one at a time, and except for those actually engaged in
felling no other persons shall work nearer to any other trees being felled at a
distance less than 6m plus the estimated height of the tree.
Where possible, trees shall be felled towards the centre of the area being cleared,
and where they cannot be felled without danger to traffic or damage to other trees,
shrubs, structures or property, they shall be cut in sections from the top down.
Tree branches extending over the roadway which hang within 5 m of the finished
road level shall be cut off close to the boles in a workmanlike manner.
All cuts on trees shall be made flush with the trunk so as to leave no stubs. All
branches or long stubs 50 mm or more in diameter shall be under cut so that the
branches or stubs will not tear down the trunk when falling. All timber, scrub and
debris shall become the property of the Contractor, and shall be disposed of as
specified in Clause 3.6. If so desired the Contractor may stack surplus timber in
such a manner as to be convenient for removal as firewood by others. Royalties
to be paid if wood sold.
On no account shall logs be placed near the toes of embankments to act as
retaining walls. No timber shall be allowed to fall on private property. The
Contractor shall remove at his cost any timber so fallen before final payment is
made.
Page 20 of 10
August 99
3.5
GRUBBING
The entire specified area shall be grubbed free from heavy grass, vegetation,
decayed stumps, roots other perishable matter, foundations, concrete works, pits,
tanks and other structures. All matter and material to be grubbed shall be
removed to a depth of not less than 600 mm below the existing surface. All holes
shall be backfilled with approved material in accordance with the requirements of
the earthworks specification.
3.6
3.7
SURVEY MARKS
During clearing and grubbing, care shall be taken not to disturb any benchmarks,
survey or level pegs. Any survey pegs lost as a result of the contractors
carelessness shall be replaced at the Contractor's costs.
3.8
DAMAGE TO PROPERTY
In all circumstances the Contractor will be held responsible and liable for any
damage to fences, buildings, grass cultivation or other property caused by or
arising from the execution of work under this section.
Any damage to fences shall be repaired immediately to the satisfaction of the
Superintendent's Representative at the Contractor's expense.
Any trees outside the specified area, which are damaged by the Contractors action, directly or
indirectly, shall be removed or rendered safe as determined by the Superintendent's
Representative.
Page 21 of 10
August 99
General
4.2
4.3
Topsoil
4.4
Excavation
4.5
Rock Excavation
4.6
Filling
4.7
4.8
4.9
Soft Spots
4.10
Compaction Plant
4.11
Compaction of Earthworks
4.12
Vehicle Access
4.13
Test Rolling
4.14
Dust Nuisance
4.15
ID 6004
Page 22 of 10
August 99
4.1
GENERAL
This specification covers the requirements for stripping topsoil, forming and
grading of earthworks including excavation, placement and compaction of filling,
disposal of surplus and unsuitable materials and the trimming and shaping to
alignments, grades, levels and cross sections shown on the drawings or as
directed by the Superintendent.
4.2
Minus
40mm
Topsoil areas
20mm
40mm
50mm
75mm
Page 23 of 10
August 99
4.3
TOPSOIL
In cut and fill areas, the Contractor shall remove a sufficient quantity of the best
topsoil available from the site before commencing excavation. The topsoil shall
be stockpiled on the job and used as topsoil for the naturestrips, batters,
easements and disturbed areas.
The Contractor shall be responsible for ensuring that there is sufficient topsoil to
reinstate and topsoil all areas as required. If sufficient topsoil is not available onsite, the Contractor shall allow to import topsoil from his own sources.
Topsoil shall be fertile, dark coloured loam, friable soil containing organic matter
and shall be free from subsoil, refuse, tree roots, noxious weeds, clay lumps and
stones.
On completion of the works, fill areas, easements and naturestrips shall be
surfaced with a 75 mm minimum depth of topsoil. Naturestrips shall be neatly
raked and trimmed on an even grade from footpath to back of kerb.
4.4
EXCAVATION
Excavation shall consist of excavation, removal and satisfactory disposal of all
materials from within the limits of the work. Where specified, pavement materials
shall be salvaged from existing pavements and spread or stockpiled as directed.
Excavation operations shall be so conducted that the material outside the limits of
the batters is not disturbed. Any slips or falls of material outside the specified
batters due to lack of precaution on the part of the Contractor shall be made good
at his expense to the satisfaction of the Superintendents Representative.
On no account shall any surplus spoil be deposited on private land, without the
written permission of the landowner. Should any such spoil be placed on property
not owned by the Contractor, then the Superintendent's Representative shall
require the Contractor to obtain a clearance in writing from the owner of the
property on which the spoil has been placed before making the final payment. No
spoil shall be dumped on reserves or roadsides without prior permission from the
Council.
Page 24 of 10
August 99
ROCK EXCAVATION
No claim will be considered on the account of any rock or other materials met
within the excavation as the contract amount for excavation shall be binding.
All rock or boulders encountered shall be excavated at least down to the finished
surface of the subgrade. Any resulting depressions shall be backfilled with
approved material properly compacted and drained to suitable outfalls to the
satisfaction of the Superintendent's Representative.
No additional payment will be made for this work.
4.6
FILLING
Material to be used for fill construction shall consist of approved materials free
from logs, stumps, weeds or other perishable matter. Areas upon which fills are to
be constructed shall first be grubbed, cleared and stripped as specified.
After completion of clearing, grubbing and stripping of areas upon which filling is
to be placed, the Superintendent may direct or authorise that any unsuitable
material immediately below these areas shall be treated in situ or excavated to
depths as directed or authorised and replaced with approved material which shall
be spread and compacted as specified.
Page 25 of 10
August 99
Prior to filling the surface of the prepared areas shall be test rolled. Any unstable
area detected by test rolling shall, unless otherwise specified or directed by the
Engineer, be rectified by the Contractor using methods agreed to by the
Superintendent and shall be re-presented for test rolling.
All filled areas shall be constructed in layers of uniform thickness not exceeding
200 mm loose depth. Each layer shall be compacted as specified in Clause 4.11
and 4.13. The maximum size of fill material shall be 150 mm.
Filling over and around pipes, culverts, bridges and other structures shall be
placed in such a manner that will avoid unbalanced loading and that will not cause
movement or place undue strain on any structure. Any rocky material present in
the filling for any layer shall be uniformly distributed within the layer and the whole
shall be compacted as specified.
During the filling operation, the surface of each layer shall be kept generally
parallel to the surface of the subgrade, except that where necessary the outer 1 m
of the fill shall be raised so as to prevent uncontrolled flow of water down the
batter. Prior to the cessation of work each day, the top of the fill shall be shaped
and compacted to minimise damage resulting from wet weather.
Densities shall be checked in situ and fill not meeting the required density shall be
re-excavated and recompacted at the Contractor's cost.
Fill material shall be derived from on-site excavation or from external sources. It
shall be the responsibility of the Contractor to provide all of the filling required for
all purposes necessary to achieve the lines and levels of finished work shown on
the drawings.
Unless otherwise specified, all embankments shall have side slopes not steeper
than 3 to 1.
Page 26 of 10
August 99
4.7
4.8
4.9
SOFT SPOTS
Where directed by the Superintendent's Representative, any soft, wet or unstable
areas of depths exceeding 150 mm below the designed levels of the subgrade
which exists or develop during construction shall be excavated and replaced with
approved material in layers not exceeding 150 mm loose thickness compacted, as
hereinafter specified. The depth to which soft spots shall be dug out shall be
determined on-site by the Superintendent's Representative.
As an alternative to excavation, the Superintendent's Representative may instruct
the Contractor to treat the soft areas in situ by stabilisation or other methods, as
determined by the Superintendent's Representative.
Payment for excavation of soft spots and backfilling materials will be made in
accordance with the relevant item in the schedule.
Page 27 of 10
August 99
Should excavations not remain free draining during the currency of the work or
where material has, in the opinion of the Engineer, become unsuitable to any
depth due to the Contractor's negligence or use of inappropriate methods, shall
be treated in situ or excavated and replaced and no additional payment will be
made for this work.
4.10
4.11
COMPACTION OF EARTHWORKS
Compaction of earthworks shall include the compaction of the subgrade in
cuttings, the compaction of areas upon which fill is to be placed and the
compaction of all fill material to the standard indicated hereunder.
All compaction shall be carried out using approved rollers.
(a)
The top 150 mm of the subgrade shall be compacted to a dry density not
less than 100% of the maximum value obtained in the standard compaction
test carried out in accordance with AS 1289.
(b)
(c)
All fill material shall be compacted to a dry density not less than 98% of the
minimum density required under (a) above, except for the top 150mm of
any subgrade which shall be compacted in accordance with (a) above.
Construction equipment and traffic shall not be allowed on the subgrade or fill
while it is in a wet condition. Material which has become excessively wet shall be
dried or removed from the site and replaced by material of suitable moisture
content for compaction at the Contractor's expense.
Page 28 of 10
August 99
4.12
VEHICLE ACCESS
Vehicle access is to be provided to all properties as directed by the
Superintendent's Representative.
All allotments must be accessible at the title boundary at a maximum grade of 1 in
5.
Where the grade of such access is unobtainable within the road reserve, the
construction work is required to be extended into the property concerned for a
maximum distance of 7.5m, in order to achieve an acceptable grade or as
described on the plans.
4.13
TEST ROLLING
All layers areas shall be test rolled prior to the placement of any subsequent
pavement materials. The finished surface of filled areas shall likewise be test
rolled. Any unstable area detected shall be rectified by the Contractor using
methods agreed to by the Superintendent's Representative.
All layers shall be compacted such that no visible deformation or springing is
visible under the action of test rolling. Test Rolling shall be carried out by the
contractor in the presence of and to the satisfaction of the Superintendents
Representative by using; six (6) cubic metre truck fully loaded with approved
material or a vehicle of equivalent weight as agreed by the Superintendents
Representative.
4.14
DUST NUISANCE
Under no circumstances shall a dust nuisance be allowed to develop during
construction works. Any dust problems determined by the Superintendents
Representative shall be contained by watering or any other methods approved by
the Superintendents Representative.
Page 29 of 10
August 99
4.15
When directed by the Superintendent, temporary control works shall be removed and the area
reinstated to the satisfaction of the Superintendent.
Page 30 of 10
August 99
General
5.2
Definitions
5.3
5.4
Materials
5.5
Construction Plant
5.6
Construction Method
5.7
5.8
Test Rolling
5.9
ID 6005
Page 31 of 10
August 99
5.1
GENERAL
This section covers the requirements for materials and construction for insitu
cement and lime stabilisation of the subgrade. The requirements relate to
preparation of soil, quality of lime and cement, mixing and compaction plant, and
spreading, mixing and compaction procedures.
5.2
DEFINITIONS
Quicklime
Quicklime is a granular form of lime consisting primarily of calcium oxide and can
be readily slaked.
Hydrated Lime
Hydrated lime is a powdered form of lime consisting primarily of calcium
hydroxide.
Equivalent Calcium Oxide Content
Equivalent calcium oxide content is the amount of calcium oxide, expressed as a
percentage by mass, which:-
5.3
(a)
(b)
Page 32 of 10
August 99
MATERIALS
5.4.1 Lime Properties
(i)
Quicklime
The equivalent calcium oxide content of quicklime shall be not less
than 60%.
When slaked in accordance with AS 1672 testing procedures the
residue of quicklime shall not exceed 30%.
At the time of spreading, quicklime shall comply with the grading
requirements specified in Table 1.
Table 1
Sieve Size
AS (mm)
9.5
4.75
2.36
Test Value
(% Passing)
100
95-100
85-100
Page 33 of 10
August 99
(ii)
Hydrated Lime
The equivalent calcium oxide of hydrated lime shall be not less than
60%.
Hydrated lime shall be dry and shall have been produced not more
than 14 days before delivery.
At the time of spreading, hydrated lime shall comply with the grading
requirements specified in Table 2.
Table 2
Sieve Size
AS (mm)
9.5
4.75
2.36
Test Value
(% Passing)
100
95-100
85-100
Page 34 of 10
August 99
Lime and cement may be delivered to the site either in bulk or in bags and
shall be stored in weatherproof structures. Lime or cement which is
damaged by moisture shall not be used and shall be removed from the site
by the Contractor.
5.5
CONSTRUCTION PLANT
5.5.1 General
The Contractor shall provide and operate sufficient spreading, mixing,
watering and compacting plant to carry out the work specified.
5.5.2 Spreading Plant
Plant for spreading both the lime and the cement shall be capable of
distributing the material evenly over the area at the required spreading
rate. The spreading rate shall be capable of being varied within the range
3 kg/sq.m to 22 kg/sq.m.
5.5.3 Mixing Plant
The mixing plant shall be capable of pulverising the soil as specified and
uniformly mixing the pulverised soil, lime, cement and added water to a
depth at least equal to the specified thickness of the stabilised layer.
The plant shall be fitted with an adjustable screed plate and cover flaps.
5.5.4 Watering Plant
Watering plant shall have spray bars capable of uniformly distributing water
in a mist and shall be fitted with rapid-acting positive shut-off valves
controlled from the operator's cabin.
Watering plant shall be fitted with constant head devices or pumps capable
of delivering a uniform rate of flow regardless of the quantity of water in the
tanks.
Page 35 of 10
August 99
5.6
CONSTRUCTION METHOD
5.6.1 General
Construction includes the preparation of soil, spreading of lime, spreading
of cement, slaking of quicklime, mixing of lime, cement and soil, and
compaction, trimming and curing of stabilised soil.
Unless otherwise approved by the Superintendent's Representative,
construction carried out each day shall be completed across the full
specified width.
The Contractor shall ensure that his employees are instructed concerning
the hazards of working with lime and that safe working practices are
observed. Personnel engaged in handling, spreading and mixing of lime
shall wear suitable protective clothing such as overalls, boots, gloves,
goggles and respirator and shall have access to skin protection cream,
hand cleanser, clean water and towels.
5.6.2 Preparation of Soil
The soil to be stabilised shall be scarified to a depth equal to the specified
thickness of the stabilised layer. Any stones larger than 75mm shall be
removed from the scarified soil and the scarified soil shall be compacted
sufficiently to provide a reasonably even surface.
5.6.3 Spreading of Lime and/or Cement
Spreading of lime and/or cement shall not commence without the consent
of the Superintendents Representative. Spreading shall not be carried out
during windy periods if, in the opinion of the Superintendent's
Representative, lime or cement could be dispersed or become a nuisance
or a hazard to persons, property or livestock.
(i)
(ii)
Page 36 of 10
August 99
Page 37 of 10
August 99
Material
Page 38 of 10
August 99
5.6.9 Trimming
After compaction, the surface shall be trimmed, to the required levels,
grades and cross sections. The finished surface shall be smooth riding
and free from loose material.
5.7
Page 39 of 10
August 99
5.8
TEST ROLLING
All layers shall be test rolled prior to the placement of any subsequent pavement
materials. The finished surface of filled areas shall likewise be test rolled. Any
unstable area detected shall be rectified by the Contractor using methods agreed
to by the Superintendents Representative.
All layers shall be compacted such that no visible deformation or springing is
visible under the action of test rolling. Test rolling shall be carried out by the
contractor in the presence of and to the satisfaction of the Superintendents
Representative by using; six (6) cubic metre truck fully loaded with approved
material or a vehicle of equivalent weight as agreed by the Superintendents
Representative.
5.9
Page 40 of 10
August 99
General
6.2
Standards
6.3
6.4
6.5
Watering Plant
6.6
Compaction Plant
6.7
Spreading of Material
6.8
Compaction of Material
6.9
Test Rolling
6.10
6.11
6.12
6.13
6.14
6.15
Testing
ID 6006
Page 41 of 10
August 99
6.1
GENERAL
This section covers the requirements for the delivery, spreading and compaction
of various quarry materials, construction plant, and methods and finished
properties for the construction of pavement courses. Other items and types of
plant may be used subject to the agreement of the Superintendents
Representative.
6.2
STANDARDS
The following Australian Standards shall apply to these works:
AS 1141
AS 1315
AS 1317
6.3
6.4
6.5
WATERING PLANT
Watering plant shall have spray bars capable of uniformly distributing water on the
road and shall be fitted with rapid acting positive shut-off valves controlled from
the operator's cabin. Watering plant used for construction of plant mixed wet-mix
and cement treated crushed rock courses shall be fitted with constant head
devices or pumps, capable of delivering a uniform rate of flow regardless of the
quantity of water remaining in the tank.
Page 42 of 10
August 99
6.6
COMPACTION PLANT
The Contractor shall provide and operate sufficient compaction plant and
equipment of suitable type and mass to carry out the works in accordance with the
specification.
6.7
SPREADING
Spreading of any layer of material shall not commence without the prior consent
of the Superintendent or his representative.
Each layer shall be spread and compacted as soon as practical after the previous
layer has been compacted and the consent of the Superintendent's
Representative has been given. The previous layer shall be kept in good
condition during spreading of the layer. Until compaction has been completed and
the consent of the Superintendents Representative has been given, no further
material shall be spread.
Plant mixed wet-mix crushed rock shall be spread with a self-propelled paver
unless otherwise approved by the Superintendents Representative. Care shall be
taken to minimise segregation of material. If segregation occurs in plant mixed
wet-mix crushed rock, the segregated material shall be replaced at the
Contractor's expense.
If segregation occurs in crushed rock, the segregated material shall be mixed and
respread using methods agreed to by the Superintendents Representative.
Unless otherwise specified or shown on the drawings, the compacted thickness of
any layer of any course shall not exceed 150mm or be less than 3 times the
nominal size of material.
The Superintendents Representative may consent to a greater thickness.
6.8
COMPACTION
Compaction shall commence promptly after spreading and all material spread
each day shall be compacted sufficiently to provide a dense surface to minimise
the entry of water in the event of rain.
Watering and compaction plant shall not be allowed to remain standing on
pavement being compacted or on newly compacted pavement.
Where the work of the contract includes preparation of the surface for sealing, the
top of the base course shall be rolled with a suitable roller to provide a hard dense
surface capable of being swept with a rotary broom to leave a tight surface free
from loose material.
Page 43 of 10
August 99
Fine crushed rock pavements shall be placed and compacted in layers to obtain a
final density of not less than 98% Australian Modified Maximum Density as
determined by the Australian Modified Compaction Test. All tests shall be carried
out in accordance with Australian Standard AS 1289.
The Contractor shall be required to provide compaction test results to the
Superintendent and shall allow, in the amount tendered for pavements, to engage
a Soils Consultant ( or independent N.A.T.A. laboratory ) approved by the
Superintendent to carry out compaction testing on all layers of pavement, based
on the following criteria :Pavements in siteworks or roadways shall be tested at 30m centres or a 30m grid
of testing over the site. Tests shall be taken on each layer of pavement. It will be
an expressed condition of this contract that the contractor allows for the cost of
compaction testing in accordance with this Clause in the tendered price for the
works.
The Superintendent's Representative may require additional testing over and
above the nominated testing interval set out above. The Contractor shall be
reimbursed from the prime cost sum for materials and compaction testing for
these tests. The costs for testing pavement which is found to be faulty together
with the cost of replacing and recompaction of the faulty pavement material shall
be borne by the contractor.
Material not meeting the required density
specification will be reworked and recompacted until the specified density is
achieved.
6.9
TEST ROLLING
All layers shall be test rolled prior to the placement of any subsequent pavement
materials. The finished surface of filled areas shall likewise be test rolled. Any
unstable area detected shall be rectified by the Contractor using methods agreed
to by the Superintendents Representative.
All layers shall be compacted such that no visible deformation or springing is
visible under the action of test rolling. Test rolling shall be carried out by the
contractor in the presence of and to the satisfaction of the Superintendents
Representative by using; six (6) cubic metre truck fully loaded with approved
material or a vehicle of equivalent weight as agreed by the Superintendents
Representative.
6.10
Page 44 of 10
August 99
Sieves
%
Passing
TOLERANCE OF SIZING
Percentage by Weight Passing Sieves Designated (mm)
150
106
53
26.5
13.20 2.36
1.18
425u
0
m
100
846450382217-22
8-14
88
72
58
45
28
300u
m
7-12
(ii)
which case no point on the surface shall lie more than 20mm below
the straightedge.
Thickness
The average thickness of the salamander course at any point shall
be not less than the thickness specified on the drawings. At no point
shall the thickness of the salamander layer be more than 20mm
below the required depth.
(iii)
Page 46 of 10
August 99
6.12
Sieve Size
AS (mm)
53.0
37.5
26.5
19.0
13.2
9.5
4.75
2.36
0.425
0.075
Page 47 of 10
August 99
The coarse crushed rock and fine crushed rock shall have maximum stone sizes
of 40mm and 20mm respectively and shall comply with the tolerance on physical
properties set out below.
Sieve Size (mm)
53.0
37.5
26.5
19.0
13.2
9.5
4.75
2.36
0.425
0.075
Page 48 of 10
August 99
(i)
(ii)
Thickness
The average thickness of each crushed rock layer at any point shall
be not less than the thickness specified on the drawings. At no point
shall the thickness of the crushed rock layer be more than 10mm
below the required depth.
(iii)
6.14
Page 49 of 10
August 99
Delivery
The methods of loading and unloading material shall be such that
segregation will be minimised.
Material shall be delivered to the site within 75 minutes from the time
of completion of mixing. Material delivered to the site more than 75
minutes from the time of completion of mixing or at a time of day
which in the opinion of the Superintendents Representative would
not allow the specified spreading and compaction procedure to be
completed may be rejected by the Superintendents Representative.
Material which does not comply with the Specification shall be
removed from the site at the Contractor's expense.
(b)
Delivery Vehicles
Delivery vehicles shall have bodies approved by the
Superintendents Representative and be fitted with covers of canvas
or other approved material to prevent loss of moisture during
transport. Vehicles used for delivery of material to the hoppers of
pavers shall have bodies or discharge equipment which will enable
the load to be discharged direct into the hopper without spillage and
in such a way that segregation will be minimised.
Page 50 of 10
August 99
(ii)
Thickness
The average thickness of each cement treated crushed rock layer at
any point shall be not less than the thickness specified on the
drawings. At no point shall the thickness of each layer be more than
10mm below the required depth.
(iii)
6.15
TESTING
The Contractor shall provide test results including Sieve Analysis, Plasticity Index,
Los Angeles Abrasion Loss, and Lower Liquid Limit prepared in accordance with
AS 1141 on a quarterly basis throughout the duration of the contract period
demonstrating compliance with each type of material defined in this specification.
The Contractor shall allow for the cost of this testing in his tender price.
Page 51 of 10
August 99
Quarterly test results produced by the Contractor shall not take away the right of
the Superintendent's Representative to reject material delivered to job sites that
does not comply with this specification.
The Superintendent's Representative may require additional testing to be
undertaken by an independent laboratory on a random sampling basis. The
Contractor shall provide access to material at the quarry site during normal
working hours to enable samples to be taken by Council's nominated testing
officer.
Page 52 of 10
August 99
Australian Standards
7.2
Description
7.3
Cement Content
7.4
Storage of Cement
7.5
Water
7.6
Steel Reinforcement
7.7
7.8
Coarse Aggregate
7.9
Mixture
7.10
Mixing
7.11
Transportation of Concrete
7.12
Cement Mortar
7.13
7.14
Measuring
7.15
Placing
7.16
Compacting
7.17
Curing
7.18
Construction Joints
7.19
Concreting
7.20
Forms
7.21
Arrangement of Formworks
7.22
Removal of Forms
7.23
Surface Finish
7.24
Defective Concrete
7.25
ID 6007
Page 53 of 10
August 99
7.1
STANDARDS
The following Australian Standards shall apply to these works:
AS 1302
AS 1303
AS 1304
AS 1315
AS 1317
AS 1379
AS 1465
AS 1478
AS 1479
AS 3600
7.2
DESCRIPTION
The concrete shall consist of a mixture of cement, fine aggregates, coarse
aggregate, and water proportioned so that there will be the quantity of cement in
each cubic metre of finished concrete as set out in clause Cement Content of
this specification. The proportion of fine aggregate to coarse aggregate will
depend on the grading of the materials, but the amount of fine aggregate shall
always be the minimum which, combined with cement, will produce only
sufficient mortar to fill the voids in the coarse aggregate and leave a slight
excess for finishing. The proportions will be determined by the Superintendents
Representative and shall be strictly adhered to by the Contractor.
7.3
CEMENT CONTENT
The proportions of cement to aggregate for the various parts of the work, will be
determined by the Superintendents Representative. The Contractor shall at all
times when ordering concrete ensure that the order is for a minimum 25 mPa
mix.
Page 54 of 10
August 99
7.4
STORAGE OF CEMENT
Cement shall be stored in a shed so that it is kept thoroughly dry. Any that
becomes wet or otherwise defective will be condemned, and shall be removed
from the works immediately.
7.5
WATER
All water used in concrete shall be subject to the approval of the Superintendents
Representative, and shall be reasonably clear, free from oil, alkali, or vegetable
substance and neither brackish or salty.
7.6
STEEL REINFORCEMENT
Reinforcement shall be thoroughly cleaned of all loose scale, rust, and other
detrimental coatings and shall be accurately placed, secured and maintained in
position until incorporated in the concrete to the satisfaction of the
Superintendent.
Where shown on plans, steel reinforcement shall be left protruding for the
purpose of bonding on future work. Care shall be taken to avoid damage to the
dowels after they have set and any dowels damaged in any way shall be cut out
and replaced by the Contractor at his own expense.
7.7
Description
Fine aggregate shall consist of clean, hard durable naturally occurring
uncoated grains of silica free from lumps, dust, soft or flaky particles, shale,
salt, alkali, organic matter, loam, or other deleterious substances.
(b)
Grading
Fine aggregate shall be uniformly graded from coarse to fine material and
shall, when tested with laboratory sieves comply to the following limits:
Sieve Sizes AS (mm)
4.75
2.35
1.18
600um
300um
Percentage of total
Sample Passing
Not less than 100
76
56
40
20
Page 55 of 10
August 99
150um
(c)
Strength
Mortar composed of one part by weight of Portland Cement, two and half
parts by weight of fine aggregate and one half by weight of water mixed
and tested by the laboratory of an authority approved by the
Superintendent, shall develop compressive strength at the age of seven
days of not less than 25 mPa.
(d)
Organic Impurities
Fine aggregate when tested in standard manner with 3% Sodium
Hydroxide solution, shall not after 24 hours show a colour darker than a
pale yellow. If aggregates which are defective in this respect are
satisfactorily washed, permission may be given to use them.
7.8
COARSE AGGREGATE
The coarse aggregate shall conform to the following requirements:(a)
Description
Coarse aggregate shall consist of crushed stone or gravel having clean,
hard, strong, durable, uncoated particle, free from soft friable, thin
elongated or laminated pieces, disintegrated stone, salt, alkali, organic
matter, or other deleterious substance.
(b)
Prevention of Segregation
To avoid segregation in supply delivery and stacking, coarse aggregate
shall be delivered on to the site in the following sizes:
(c)
(i)
(ii)
(iii)
Grading
Coarse aggregate shall be well graded from the largest to the smallest
pieces, and when tested by means of laboratory sieves shall comply with
the following limits:
Sieve Sizes
19.00mm
Percentage of Whole
Sample Passing
Not less than 100
Page 56 of 10
August 99
13.2mm
9.50mm
6.70mm
4.75mm
2.36mm
80
60
39
14
0
The actual grading shall be such that the sum of the maximum divergence
above the curve of the specified grading plotted and the sum of the
maximum divergence below the curve of the specified grading plotted shall
not exceed 10%. The divergence shall be considered as a percentage of
the amount passing each sieve.
(d)
Abrasion
When tested in the Los Angeles machine in the standard manner, the loss
shall not exceed 22%.
The various grades of stone and sand shall be stored in such a manner
and place that they will be kept clean and not become mixed. Materials
condemned by the Superintendents Representative shall be forthwith
removed from the works.
7.9
MIXTURE
Unless otherwise specified, all concrete used on the works shall consist of:One (1) part cement
Two (2) parts sand (half part fine sand, 1.5 parts coarse sand)
Three (3) parts bluestone screenings (20mm)
One (1) part bluestone toppings (10mm)
Limil shall be added to the mortar mixture in such proportion as the
Superintendents Representative shall determine.
The ratio of fine to coarse aggregate may be varied by the Superintendents
Representative, but the ratio of cement to the total aggregate shall remain
unaltered.
The quantity of water used shall be as directed by the
Superintendents Representative, and shall be the minimum required to give a
workable mixture. Concrete shall have a maximum slump of 50mm when the
standard slump test is applied. The measured concrete slump at the point of
placement shall be within 10mm of the approved design value when measured in
accordance with requirements of AS 1012 Part 3. Any concrete that does not
comply with this requirement shall not be used.
All concrete shall have 28 days compressive strength of not less than 25 mPa for
general concrete work and shall be a minimum of 30 mPa for road pavement.
Test cylinders will be prepared on the job by the Contractors representative when
directed by the Superintendents Representative.
Page 57 of 10
August 99
Page 58 of 10
August 99
7.10
MIXING
The concrete shall be mixed in such quantities as are required for immediate use.
The use of partly hardened concrete or remixing of such concrete, with or without
additional cement, aggregate or water, will not be permitted. Hand mixing will only
be carried out with the approval of the Superintendent.
Machine mixing may be completed at site or at a central mixing plant. The mixing
of concrete shall be done in a batch mixer of an approved type which will ensure
the uniform distribution of materials throughout the mass, so that the mixture is
uniform in colour and consistency and is homogenous. The entire contents of the
mixer are to be discharged before recharging. The mixer shall be cleaned at
frequent intervals while in use. The volume of material mixed in each batch shall
not exceed the manufacturers rated capacity of the mixer. The order of placing
materials in the mixer shall be coarse aggregate, water, sand, cement or such
order as may be approved by the Superintendent's Representative. The mixing
period shall not be less than 1.5 minutes after all ingredients have been placed in
the mixer.
7.11
TRANSPORTATION OF CONCRETE
Concrete mixed at a central mixing plant shall be transported either in an
approved water tight agitator in which segregation will not take place and from
which the concrete can be discharged freely, or in a truck mixer operating at
agitator speed. Agitation shall be maintained from the time the concrete is placed
in the agitator until delivered to the works. In the case of truck mixed concrete the
mixer on completion of mixing shall continue to operate at agitating speed until
the concrete is delivered to the work.
Concrete shall be discharged at the work from the truck mixer or agitator and
placed in its final position in the forms within 1.5 hours from the addition of cement
to the aggregates.
7.12
CEMENT MORTAR
All cement mortar shall consist of:
One (1) part cement
Two (2) parts sand, (to include 1/2 part of fine finished sand)
One (1) part screened bluestone dust
7.13
Page 59 of 10
August 99
7.14
MEASURING
All aggregate shall be proportioned on a gravumetric or by weight basis but where
suitable apparatus is not available, volumetric measurement will be permitted on
the following basis:
Cement shall be measured as packed by the manufacturers and a sack of cement
containing a known weight shall be considered the unit of measurement in
proportioning measures. Batches shall be proportioned on the basis of integral
sacks of cement.
The measures for the aggregate shall be approximately rectangular, and the
maximum dimensions shall not be greater than twice the minimum dimension.
They shall be of such dimensions as will give, when struck, the exact volumes
required.
7.15
PLACING
After mixing, concrete shall be conveyed to the place of final deposit without
delay, and shall be placed immediately. The methods of handling shall be such as
will prevent the segregation or loss of the ingredients and avoid rehandling.
Dropping the concrete a greater height than 1m, depositing large quantities at any
point and moving or working it along the forms will not be permitted. A plastic
surface shall be maintained until the completion of the unit.
Concrete shall be placed in a spreading platform as specified hereinafter after
transport from the mixer. It shall be turned over to ensure that consistency is
constant and shall then be shovelled into place. Under no circumstances shall
concrete be thrown from the shovels. No concrete is to be placed under water.
Page 60 of 10
August 99
7.16
COMPACTING
During and immediately after placing, the concrete shall be thoroughly compacted
by means of continuous tamping, spading, slicing and vibration as specified.
Care shall be taken to fill every part of the forms to force the concrete under and
around the reinforcement without displacing it, to work back coarse aggregate
from the face, and to remove all air bubbles and voids. The men employed on
compacting shall have had experience in concrete work, and shall be under the
control of the Superintendent's Representative during the period of compacting
concrete.
7.17
CURING
7.17.1 Cold Weather
During colder weather (as determined by the Superintendent's
Representative), no form work may be stripped until the concrete is at least
seven days old so that the insulating properties of the boards will be
available. Any top or exposed surfaces of newly placed concrete which are
not protected by timber formboards shall be covered within six hours and
for at least seven days by a layer of sand or other approved heat insulating
materials.
7.17.2 Hot Weather
The forms shall be removed as specified under the clauses Removal of
Forms.
In both cases, concrete shall be protected from premature drying.
Surfaces exposed to the sun shall be shaded by means of canvas, hessian
or sand, placed as soon as the concrete has taken hard set. All exposed
surfaces, formwork, hessian, canvas, or sand shall be kept continuously
wetted for a period of at least seven days.
New surfaces shall be effectively protected from rain until hard set has
occurred.
Page 61 of 10
August 99
CONSTRUCTION JOINTS
Whenever the work of placing concrete is delayed; until the concrete placed shall
have taken its initial set; the point of stopping shall be deemed a construction
joint. The location of construction joints shall be planned in advance, and shall be
made only when approved by the Superintendent's Representative. The placing
of concrete shall be carried continuously from joint to joint. These joints shall be
perpendicular to the principal lines of stress, and in general shall be located at
points of minimum shear.
Before placing new concrete on or against concrete which has set, the form shall
be re-tightened and the surface of the set shall be roughened as required by the
Superintendent's Representative, thoroughly cleaned of foreign matter, laitance
and loose or porous material, and saturated with water. The surface shall then be
covered with a thin coat of neat cement and water to ensure bond, and concreting
shall then proceed immediately.
No work shall be stopped or temporarily discontinued within 375mm of the top of
any finished surface, unless such work is finished with a coping having a
thickness less than 375mm in which case the joint shall be made at the under line
of the coping.
7.19
CONCRETING
The Contractor shall pour the whole of each monolithic section of the work in one
continuous operation excepting when permission to use construction joints is
given by the Superintendent's Representative.
No construction joints will be permitted on exposed faces excepting where moulds
or other features enable the joints to be effectively masked.
Concreting of the superstructure shall commence at one end of the monolithic
section to be poured and shall then be proceeded with simultaneously and
uniformly for the full structure width.
The concrete shall be wheeled on a substantial gangway. The gangway shall be
supported above the reinforcement by means of trestles resting on the formwork.
A further similar gangway shall be provided transversely to the aforementioned
gangway for distribution at the working face. For a width of 2m on both sides of
the centre lines of the gangway, the formwork and reinforcement shall be
Page 62 of 10
August 99
FIXED-FORM PAVING
17.4.1 Fixed-Form Paving
Sideforms shall consist of steel, timber, or steel-shod-timber forms.
Excepting for small or irregular-shaped pavement areas, the face of the
form against which concrete is to be placed shall not be made of built-up
elements.
Forms shall be of such cross section and strength and so secured as to
resist the pressures of the concrete when paced, and the impact and
vibration of any equipment they support, without springing or settlement.
The method of connection between adjacent form units shall be such that
the joints are braced against movement, and continuity of gradient across
the joint is maintained. For curves of radius 30 m or less flexible or curved
forms shall be used. Where required forming strips for keyways shall be
accurately dimensioned, located and securely fastened against the form
face.
Page 63 of 10
August 99
Forms shall be pinned or staked into place with not less than three pins in
each 3m length and with a pin placed at each side of every form joint. The
pins shall be of sufficient length to hold the forms securely in position
during construction. The top surface of an individual form unit or a
completed length of formwork shall not deviate by more than 3mm from a
3m straightedge supported at its ends. The inside face of the form shall be
vertical.
Forms shall be fully and continuously supported over the entire length of
paving runs by either one or both of the following methods:
(a)
(b)
Forms shall be adjusted to the correct level by the use of steel shims
or wedges. In this case the space between the sub-base and the
form shall be filled solid and trimmed flush with the inside face of the
form.
Forms shall be set sufficiently in advance of concrete placing to
permit inspection. Where any form or the sub-base has been
disturbed, the sub-base shall be corrected if necessary and the
forms reset and rechecked. Forms shall be cleaned and coated with
a suitable form-oil before each use.
Forms shall remain in place for at least one day unless joints are to
be sawn, in which case forms shall remain in place from the time of
concreting until the concrete is ready for sawcutting. Forms shall be
carefully removed to avoid damage to the pavement and any
projecting tie-bars or dowels.
7.21
ARRANGEMENT OF FORMWORKS
The whole of the formwork for each monolithic section of the work shall be wholly
constructed before concreting of that section is commenced.
If so directed by the Superintendent's Representative, the Contractor shall submit
details of the proposed arrangement of formworks, and no formwork shall be
erected until such details have been approved by the Superintendent's
Representative.
Placing of the concrete will not be permitted to proceed until the formwork has
been checked by the Superintendent's Representative.
7.22
REMOVAL OF FORMS
Unless adequate supports are provided, forms shall not be disturbed until the
concrete has adequately hardened. While the temperature of the air remains
Page 64 of 10
August 99
above 10oC forms supporting slabs shall remain in place at least seven days and
forms supporting beams and girders at least 21 days; and if the temperature of
the air drops below 10oC supporting forms shall remain in place for longer periods.
No forms or falsework whatever shall be removed at any time without the approval
of the Superintendent's Representative.
In order to obtain a satisfactory surface finish on ornamental work, parapets, and
on exposed faces of the structure, forms unless directly supporting the concrete
shall be removed as soon as the concrete has hardened, but in not less than 12
nor more than 48 hours after placing of the concrete, except in cold weather as
specified under Curing. The form-work of adjacent parts of the structure shall be
designed to facilitate this early removal.
7.23
SURFACE FINISH
All concrete surfaces shall be true and even, free from stone pockets, excessive
depression, or projections. Surfaces shall not be plastered or cement washed,
and shall be in accordance with the finish as specified or noted on the drawings.
7.24
DEFECTIVE CONCRETE
The Contractor shall be fully responsible for employing effective methods of
mixing, placing, protecting and curing concrete, and for the adequacy of falsework
and forms. Approval of any such work or methods by the Superintendent's
Representative will be tentative only, shall not relieve the Contractor of his
responsibility.
Concrete which is not placed and completed in accordance with this specification
or which is, in the opinion of the Superintendent's Representative, defective, shall
be removed within the limits assigned by the Superintendent's Representative,
and replaced to his satisfaction.
7.25
Page 66 of 10
August 99
Australian Standards
8.2
General
8.3
8.4
Bedding Preparation
8.5
8.6
Concrete
8.7
8.8
Compaction
8.9
Joints
8.10
Drainage Openings
8.11
Household Drains
8.12
Perambulator Crossings
8.13
ID 6008
Page 67 of 10
August 99
8.1
AUSTRALIAN STANDARDS
AS 1379
AS 2876
AS 3610
AS 3799
8.2
GENERAL
This work shall consist of the construction of cast in-situ concrete kerb and/or kerb
and channel, and vehicle and pram crossings, together with the necessary
excavation, in the locations shown on the drawings.
8.3
8.4
(a)
The level of the kerb and/or kerb and channel shall not differ from the
specified level by more than 20mm. Grades shall be constructed in
accordance with the drawings and the kerb and channel shall at no point
hold water.
(b)
Alignment of the kerb and channel shall not differ from the specified line by
more than plus or minus 50mm providing that the minimum pavement
width is achieved at all points throughout the construction.
BEDDING PREPARATION
A minimum 50mm layer of bedding material consisting of 20mm class 2 crushed
rock, toppings or other approved granular material shall be spread on the boxing
with the surface flat perpendicular to the alignment and true to levels and grades.
The bedding shall be firmly compacted to the satisfaction of the Superintendent's
Representative.
The cost of all works specified above, including the supply of bedding material
shall be deemed to be included in the scheduled price for the construction of kerb
and channel.
8.5
be
used
subject
to
approval
by
the
Page 68 of 10
August 99
Concrete used shall be of such consistency that after extrusion it will have the
moisture content to maintain the shape of the kerb section without support.
Where it is intended to form a vehicular or pram crossing opening in machine
placed kerb and channel, all concrete shall be thoroughly compacted by rodding
and ramming to produce a dense and water tight structure, free from
honeycombed or porous patches. Additional water may be required to achieve
this.
Joints shall be constructed at regular intervals not exceeding 2.5m by a method
approved by the Superintendent's Representative.
8.6
CONCRETE
Concrete, the material and methods of mixing, placing and curing shall comply
with the requirements set out in Section 7, Concrete.
8.7
Page 69 of 10
August 99
8.8
COMPACTION
All concrete placed in kerb and channels shall be compacted both manually and
by use of vibrators immersed in the concrete to the satisfaction of the
Superintendent's Representative.
The internal, or immersion, vibrating tool shall have a frequency of not less than
4000 per minute and shall have a rotating eccentric of at least 1 kg with an
eccentricity of 12mm.
At least one hand tamper shall be used for every 4 cubic metres of concrete
placed per hour. Two internal vibrators shall be used for the first 4 cubic metres of
concrete placed per hour and one additional internal vibrator shall be used for
every additional 4 cubic metres of concrete placed per hour.
8.9
JOINTS
Steel templates cut to the cross sectional dimensions shown on the standard
drawings shall be used on all joints. Joints shall be at regular intervals and the
spacing between joints shall not exceed 2.5m without the approval of the
Superintendent's Representative.
Joints shall be 3mm in width and clean for the full area of the plates with edges
neatly rounded by jointing tool.
8.10
DRAINAGE OPENINGS
In order to provide for drainage from vacant allotments, and for natural drainage
where necessary from built on allotments, a House Drain Connection shall be left
in the kerb opposite each allotment in the position as directed by the
Superintendent's Representative, generally 5m from low side boundary.
The contractor shall supply and lay house drains to each allotment where shown
on the drawings or where directed by the Superintendents Representative. Pipes
shall be 100 mm PVC laid from the building line to the channel in a straight line
with a uniform fall of not less than 1 in 60, generally 5m from the low side
boundary.
OR
Page 70 of 10
August 99
The contractor shall assess the integrity of each existing house drain within the
road reservation and replace conduits where necessary or where directed by the
Superintendents Representative and also allow for connection of existing house
drains that are within 2 metres away from the construction zone.
Where it is necessary to lower or relocate any sewerage connection from a house
or building to the sewer, the appropriate sewerage authority shall be notified and
the alterations carried out by the contractor at his expense under the supervision
of that authoritys representative.
Where house drains connect directly to a piped drain behind the kerb, the kerb
shall be marked with a 50 mm high H to indicate the location of the house drain.
The location of all house drains shall be marked with a 50 mm high H on the
back of the footpath.
8.11
HOUSEHOLD DRAINS
Existing house drains across naturestrips shall be relaid and/or extended if
necessary, and neatly connected to the concrete channel in accordance with
standard drawings and with approved adaptors. Actual length of pipes required to
connect existing drains to new channel shall be paid for at scheduled rate.
House drainage shall be kept unobstructed during the progress of the Contract.
8.12
PERAMBULATOR CROSSINGS
Where shown on the plans, perambulator crossings shall be constructed in
accordance with the detailed drawings for disabled perambulator crossing. For
the purposes of tendering and payments the cost or perambulator crossings shall
be treated as the same as the scheduled price for concrete kerb and channel.
Page 71 of 10
August 99
8.13
Page 72 of 10
August 99
Formation
9.2
9.3
Bedding
9.4
Plinths
9.5
Concrete
9.6
Placing
9.7
Compaction of Concrete
9.8
Finishing
9.9
Curing
9.10
Expansion Joints
ID 6009
Page 73 of 10
August 99
9.1
FORMATION
The Contractor shall excavate to the full depth of paving plus approved granular
material bed below the finished levels of the pavement. All formation shall be
neatly trimmed true to line, level and cross slope so as to give the full thickness of
concrete and bedding material at all places.
Soft spots in the formation shall be excavated , filled with approved material and
compacted to the satisfaction of the Superintendent's Representative.
9.2
9.3
(a)
Footpaths and surfacing shall be shaped to match existing fixtures, eg. pit
covers, edgings and driveways, within 5mm.
(b)
The level of the concrete paving shall not differ from the specified level by
more than 20mm. Grades shall be constructed in accordance with the
drawings and the concrete paving shall at no point hold water.
(c)
Alignment of the concrete paving shall not differ from the specified line by
more than plus or minus 50mm providing that the minimum pavement
width is achieved at all points throughout the construction.
BEDDING
Upon the trimmed formation a minimum 50mm consolidated thickness of 20mm
class 2 crushed rock, toppings, or other approved granular material shall be laid
as a bed for the concrete pavement. The bedding shall be compacted by an
approved method to the satisfaction of the Superintendent's Representative.
Page 74 of 10
August 99
9.4
PLINTHS
Unless otherwise ordered by the Superintendent's Representative, the Contractor
shall lay temporary 75mm x 40mm hardwood plinths on both sides of the path.
Plinths shall be in long lengths and shall be true to line and level and shall be
securely pinned in position. Plinths shall extend an adequate distance in advance
of concreting. Pavement at street corners shall be laid as directed by the
Superintendent's Representative, and all plinths at street intersection shall be set
out in full before any concrete is placed. Approved steel forms (76mm x 5mm
equal angle) may be used in lieu of hardwood plinths.
9.5
CONCRETE
Shall comply with the requirements set out in Section 7.
9.6
PLACING
After mixing, concrete shall be conveyed to the place of final deposit without delay
and shall be placed immediately. The methods of handling shall be such as will
prevent the segregation or loss of the ingredients and will avoid rehandling.
During and immediately after placing, the concrete shall be thoroughly compacted
by means of tamping, spading and vibrating to ensure that all concrete is
thoroughly consolidated and fills all space between forms.
The concrete shall be screeded off on the plinths or adjacent finished slabs until a
true surface is obtained. Slabs shall be cut through at intervals of 1.4m or as
specified and the joint ruled with a jointing tool.
No concrete shall be poured until the formation, bedding and placing of formwork
has been approved by the Superintendent's Representative.
9.7
COMPACTION OF CONCRETE
All concrete shall be compacted both manually and by the use of a mechanical
vibrating screed of approved type to the satisfaction of the Superintendent's
Representative.
Page 75 of 10
August 99
9.8
FINISHING
After screeding off all slabs shall be floated to a smooth even surface with wooden
floats and steel trowels and then flat trowelled with a steel float. To give a non
skid surface the Contractor shall, if necessary, after trowelling lightly broom the
surface with a hair broom. All joints shall be finished with an approved grooving
tool and the edge of the footways shall be finished with an approved edging tool.
The use of driers or rendering will not be permitted.
9.9
CURING
Refer Section 7.17.
9.10
EXPANSION JOINTS
Expansion joints shall be constructed at approximately 10m intervals as directed
by the Superintendent's Representative. See Section 7.18. An expansion joint
shall be constructed at each joint between 75mm thick and 150mm thick concrete
which occurs one thickened bay either side of driveways.
These expansion joints shall be constructed by placing strips of an approved
jointing material in accordance with the manufacturer's specifications. Unless
otherwise directed jointing strips shall be 13mm thick and the width of the strips
shall equal the thickness of concrete.
Expansion joints shall be constructed both sides of sewer manhole covers and
driveways or as directed by the Superintendent's Representative.
Page 76 of 10
August 99
Australian Standards
10.2
General
10.3
10.4
Age of Pipes
10.5
10.6
10.7
Diversion of Water
10.8
Excavation
10.9
Timbering
10.1
AUSTRALIAN STANDARDS
The following Australian Standards apply to these works:
AS 1741
AS 1693
AS 2032
AS 2033
AS 1597
AS 1646
AS 4058
CA 56
AS 4139
AS 2566
10.2
GENERAL
This specification covers the materials, procedures, workmanship and installation
of underground stormwater drainage pipes, pits, manholes and drainage
connections shown on the drawings as specified, or as directed by the
Superintendent.
10.3
All pipes up to and including 600mm in diameter shall be spigot and socket,
rubber ring jointed pipes.
In road reserves, pipes greater than 600mm diameter shall be spigot and socket
rubber ring jointed.
Pipes in other locations and greater than 600mm diameter where not under head
may have interlocking joints.
Page 78 of 10
August 99
Solvent welding of joints in uPVC pipe works may be permitted subject to the prior
approval of the Superintendents Representative.
Pipe Types/Class to be
used
For Roadways and heavy trafficed areas
Depths in millimetres
0-400
400 - 600
FRC pipe
RC pipe
High Density
Polyethylene Pipe
Polyethylene/stee
l composite pipe
(300dia to
600dia)
Polyethylene/stee
l composite pipe
(750dia to
900dia)
uPVC Pipe
600-1500
1500-2500
2500-3800
Class 2
Class 2
Class 3
Class 2
Class 2
Class 3
3000 N/m/m 3000 N/m/m 4000 N/m/m
*
*
*
Class 10
Class 10
Class 15
3800greater
TBA
TBA
TBA
TBA
TBA
Not to be
used
Not to be
used
Class 2
Class 2
Not to be
used
Not to be
used
Not to be
used
Not to be
used
Class 15
Class 15
Class 40
TBA
Not to be
used
SEH *
SH *
SH *
SH *
TBA
600-1500
1500-2500
2500-3800
3800greater
TBA
TBA
TBA
TBA
TBA
TBA
Not to be
used
Polyethylene/stee Not to be
l composite pipe
used
(300dia to
600dia)
Polyethylene/stee Not to be
l composite pipe
used
(750dia to
900dia)
uPVC Pipe
Not to be
used
SH = Sewer heavy
Class 2
Class 2
Not to be
used
Not to be
used
Class1
Class 2
Class 3
Class 2
Class 2
Class 3
1250N/m/m 1250N/m/m 3500N/m/m
*
*
*
Class 10
Class 10
Class 15
TBA
Not to be
used
Class15
Class 15
Class 40
TBA
SH *
SH *
SH *
SH *
TBA
10.4
AGE OF PIPES
Page 79 of 10
August 99
No concrete pipe shall be transported from the place of manufacture until the
minimum 28 days strength has been attained, or without the approval of the
Superintendents Representative.
10.5
10.6
10.7
DIVERSION OF WATER
During the progress of these works, the Contractor shall provide for the effective
diversion and disposal of surface water to the approval of the Superintendent's
Representative. The Contractor shall provide at his expense, equipment for
effective de-watering of excavations during the period of the works, and shall be
solely responsible for all damage to any portion of the works or surrounding
properties due to inadequate drainage diversion or de-watering equipment.
10.8
EXCAVATION
Excavation for installation of pipes shall include all excavation necessary to
prepare the pipe foundation, and to provide the full specified depth of pipe
bedding.
Trenches shall be excavated to a minimum width (external diameter of the pipes +
300mm) sufficient to allow for proper jointing of the pipe sections and thorough
compaction of the bedding and backfill material under and around the pipe.
Where practicable trench walls shall be vertical. Excavations shall be supported
by satisfactory means to ensure the safety of workmen and traffic.
The base of the completed trench shall be firm and uniform for its full length so as
to avoid any unequal settlement along the length of a pipe.
Excess excavation below the required level shall be backfilled at the Contractor's
expense with sand, gravel or other material as directed by the Superintendent's
Representative, and thoroughly compacted.
Page 80 of 10
August 99
No claim will be considered on the account of any rock or other materials met
within the trench excavation.
Where directed and authorised in writing by the Superintendent's Representative,
soft, wet or unstable areas below the level of the minimum required thickness of
pipe bedding shall be excavated and backfilled with gravel or other approved
stable material spread in layers not exceeding 150mm loose thickness and
thoroughly compacted to ensure an unyielding foundation.
Payment for authorised excavation and replacement of unsuitable material below
the level of the minimum required thickness of pipe bedding shall be made at the
schedule rate applicable for this work.
Wet or unstable areas of any depths which, in the opinion of the Superintendent's
Representative, have been caused by the Contractor's negligence or improper
methods shall be excavated and replaced with gravel or other approved stable
material spread and compacted as above by the Contractor at his own expense.
10.9
TIMBERING
The Contractor shall supply and fix at his own expense strong and sufficient
timber, when necessary, to support the sides and/or bottom of the excavations in
open cut or trench in accordance with the relevant codes of practice and to the
satisfaction of the Superintendents Representative.
The Superintendent's Representative may order the ground to be close timbered
wherever it may appear to him to be necessary, and no extra charge shall be
made for this by the Contractor.
Notwithstanding the above requirements, procedures and precautions as set out
in the Department of Minerals and Energy publication Safety Precautions in
Trenching Operations are to be adhered to.
The Contractor shall be responsible for any injury to workers, and any
consequential damage caused or arising out of the removal of timbering, and
advice, permission or approval given by the Superintendent's Representative
relative to the removal of timbering shall not relieve the Contractor from the
responsibility here defined.
Before commencing any excavation in which the depth of face exceeds 1.5
metres, or any tunnelling operation, the Contractor shall notify in writing the
Department of Labour, Building and Construction Industry Division,
Construction/Excavation Section and shall comply with the requirements of the
Department and the instructions of any authorised Inspector.
manufacturer in its correct position. Care must be taken to see that the invert of
each pipe length at the joints fit accurately with the next.
Pipes shall only be laid in a dry trench. All pipes shall be bedded so as to bear
evenly for the full length on a 50mm compacted bed of 20mm crushed rock class
3 or 5 to7mm aggregate.
Pipe laying shall commence at the outlet unless otherwise directed by the
Superintendents Representative.
Pipes shall not be laid before the trench and bed has been inspected and
approved by the Superintendents Representative.
10.11 JOINTING OF PIPES
Spigot and socket pipes and interlocking joint pipes shall be properly jointed with
cement mortar. Rubber ring jointed pipes shall be jointed with a neatly fitting
rubber ring. In the case of internally jointed pipes, the mortar shall be struck off
flush with the bore of the pipe.
Page 82 of 10
August 99
Page 83 of 10
August 99
(a)
Within paved areas - not less than 100% of A.S. Standard Maximum Dry
Density.
(b)
Within other areas - not less than 95% of A.S. Standard Maximum Dry
Density.
Page 84 of 10
August 99
Trench excavation
Laying and jointing or assembly
Backfilling
Page 85 of 10
August 99
Frames for pit covers shall be cast into the top of the pit or bedded on fresh
mortar, 5mm thick, consisting of two parts of sand, one part of cement and
sufficient water to produce a mix of suitable consistency.
10.19 STEP IRONS
Pits greater than 1.00m deep shall be fitted with step irons. The top step shall be
not more than 300mm below the bottom of the lid. Steps shall be located that
they do not obstruct openings other than subsoil drain pipe openings and that
water does not discharge onto them. Unless otherwise directed by the
Superintendents Representative, steps shall be set into a wall which has no
openings.
10.20 BLASTING
The Contractor, in excavation through hard materials shall not use any explosives
without the written permission of the Superintendents Representative.
The Contractor shall hold and obtain all necessary licenses and permits from the
Authorities concerned including the Department of Labour (Hazardous Materials
Division ) and the local Municipal Council. The Contractor shall conform to all
Regulations and By-laws relating to transport, storage, handling and use of
explosives. Blasting mats shall be used to prevent fly rock leaving the excavation
and care shall be taken to protect adjacent property, services and mains.
The Contractor shall be solely responsible for any accidents, damage or injury
and shall make good at his own expense any claims or demands arising from
blasting activity.
10.21 DISPOSAL OF SPOIL
Excavated materials not required for fill or backfilling shall be removed from the
site of the works by the Contractor.
The Superintendent's Representative may direct the dumping of excess spoil at
any point within 4km of the site of the work.
10.22 SUBSOIL DRAINS
10.22.1 Description
This work shall consist of the supply and installation of perforated subsoil
drainage pipes and filter material where shown on the drawings or
directed by the Superintendent's Representative.
10.22.2 Materials
Page 86 of 10
August 99
(i)
Pipes
Pipes supplied for this work shall be of minimum size of 90mm and
the type shown on the drawings and shall comply with all relevant
provisions of the standard shown hereunder:
Type of Pipe
Standard
Perforated Plastics
AS 2439
Other types of pipe not Approved sample
listed
Where required, the Contractor shall submit one sample length of
pipe for the approval of the Superintendent's Representative before
work is commenced. This sample when approved shall be retained
as a standard, and all pipes supplied shall be at least equal in all
respects to such standard.
Perforated plastics pipes supplied in coils shall have been cooled
before coiling and when uncoiled shall be free from any permanent
curved set.
(ii) Filter Material
Filter material for use in backfilling trenches, under, around and over
pipes shall be 20mm screenings free from clay balls and organic
matter.
10.22.3 Subsoil Pipe Installation
Trenches shall be excavated to the dimensions and grade required by
the drawings or directed by the Superintendent's Representative. Pipes
shall be a minimum of 750mm below the top of the kerb.
The minimum trench width shall be the pipe diameter plus 100mm with
the maximum width of trench of 300mm and the pipes shall be laid true
to line and grade to discharge into pits or in accordance with the
drawings.
The pipes of the type and size specified shall be laid firmly embedded in
the bedding material with adjacent lengths butted together or connected
where necessary. Open joints shall be suitably wrapped to permit entry
of water. Perforated or slotted pipes shall be laid preferably without the
openings facing down.
Subsoil drain shall not be layed more than 150mm below any stabilised
subgrades unless otherwise directed by the Superintendents
Representative.
Page 87 of 10
August 99
After the pipe installation has been inspected and approved, 20mm
screenings shall be placed to within 150mm of the top of the kerb, care
being taken not to displace the pipe or the covering at open joints
The final 150mm shall be filled with approved top soil material, except in
paved areas where the top of the screenings is level with the sub-base of
the pavement.
Page 88 of 10
August 99
Australian Standards
Description
Definitions
Aggregates
Filler
Bituminous Materials
Mix Design Procedures
Mix Design Requirements
Tolerances
Mixing Plant
Stockpiles
Preparation of Aggregates
Temperatures of Bitumen, Aggregates and Asphalt
Mixing
Inspection and Testing at the Mixing Plant
Commencement and Completion
Rate of Delivery
Possession of Paving Site
Provision for Traffic
Damage
Removal of Debris
Delivery
Construction Plant
Preliminary Work
Ambient Conditions for Placing
Tack Coat
Regulating Course
Spreading
Joints and Junctures
Compaction Procedures
Requirements for Testing and Acceptance of
Compaction
Equipment for Setting Out and Checking
Surface Finish, Shape and Thickness
Tests
Schedule of Details
ID 6011
Page 89 of 10
August 99
11.1
STANDARDS
The following Australian Standards shall apply to these works:
AS 1160
AS 2008
AS 2150
AS 2157
AS 2341
AS 2357
AS 2734
AS 2809
AS 2891
11.2
DESCRIPTION
This section covers the requirements for the manufacture and placing of asphalt
of Types V, H, N, L and R and of Sizes 7, 10, 14 and 20. The requirements relate
to quality of aggregates and bituminous materials, mix design criteria, mixing plant
and manufacturing procedure and properties, supplying and placing of the
asphalt. The types and sizes of asphalt to be supplied shall be as specified in
Clause 11.35(a) .
11.3
DEFINITIONS
Asphalt (Asphaltic Concrete)
Asphalt is a designed and controlled, dense graded mixture of coarse and fine
aggregates, filler and bitumen binder which is mixed, spread and compacted while
hot to a uniform dense mass. For the purpose of this section asphalt types will be
designated by the symbols V, H, N, L or R.
Asphalt Base Course
Asphalt base course is that part of an asphalt pavement supporting the
intermediate and wearing courses.
Asphalt Intermediate Course
Asphalt intermediate course is that part of the pavement which rests on the base
and is immediately under the wearing course.
Page 90 of 10
August 99
Page 91 of 10
August 99
AGGREGATES
11.4.1 General
The combined aggregate mixture shall consist of crushed rock or crushed
gravel, or a mixture of crushed rock with sand or crushed gravel with sand.
When aggregates are crushed rock, each aggregate shall consist of clean,
hard, durable, angular rock fragments of uniform quality, produced by
crushing sound unweathered rock quarried from a source acceptable to the
Superintendents Representative. Unless otherwise approved by the
Superintendents Representative, only metamorphic or igneous rocks shall
be used.
Aggregate produced from source rock which does not comply with the
specified requirements but which has been proven to have satisfactory
durability may be accepted for use subject to the written approval of the
Superintendents Representative. When aggregates are crushed gravel,
not less than 75% by mass of all particles shall have two or more faces
produced by crushing.
When aggregates are sands, they shall consist of clean, hard, durable
grains free from lumps, clay, mica and foreign matter.
11.4.2 Source Rock
Source rock shall comply with the relevant durability and hardness
requirements specified in Tables 1 and 2. If the contractor proposes to use
a source rock type other than those listed in the tables the
Superintendents Representative will determine if the rock type is
acceptable and the appropriate test values are achieved.
Page 92 of 10
August 99
Table 1
Test Value
Sound Rock
Degradation
Secondary
Factor for
Mineral
Source Rock
Content %
(min)
(max)
ACID IGNEOUS
Granite
50
Adamellite
50
Grandiorite
50
Granophyre
45
Rhyolite
45
Rhyodacite
45
INTERMEDIATE IGNEOUS
Diorite
45
Porphyry
45
Trachyte
50
BASIC IGNEOUS
Basaltic
50
25
Rocks
METAMORPHIC
Hornfels
40
Quartzite
45
Schist
45
Phyllite
45
Gneiss
45
Greenstone
45
Rock
Type
Marginal Rock
Degradation
Secondary
Factor for
Mineral
Source Rock
Content %
(min)
(max)
35-49
35-49
35-49
35-44
35-44
35-44
35-44
35-44
30-44
30-49
26-30
20-39
30-44
30-44
30-44
30-44
30-44
Table 2
ROCK TYPE
ACID IGNEOUS
Granite
Adamellite
Grandiorite
Granophyre
Rhyolite
Rhyodacite
INTERMEDIATE IGNEOUS
Diorite
Porphyry
Trachyte
BASIC IGNEOUS
Basaltic
Rocks
METAMORPHIC
Hornfels
Quartzite
Schist
Phyllite
Gneiss
Greenstone
25
20
25
25
25
25
25
Page 93 of 10
August 99
The Contractor shall nominate the source and the location within the
source from which the rock will be obtained. If at any time the Contractor
proposes to change the source or the location within the source, the
Superintendents Representative shall be notified in time to allow the
Superintendents Representative to perform such inspections, tests and
evaluations as may be required to establish whether rock from the
proposed new source or new location within the source complies with the
specified requirements.
11.4.3 Crushed Aggregate Products
(a)
(b)
Table 3
Type of
Asphalt
Flakiness
Index
% (max)
V&H
N&R
L
35
35
35
Total of Marginal
Unsound
& Unsound
Rock %
Rock %
(mass max)
(mass max)
8
3
10
5
15
5
(b)
(c)
Percentage Passing
(by mass)
100
70-100
20-55
Page 94 of 10
August 99
0.075
(d)
5-20
(b)
(c)
Page 95 of 10
August 99
11.5
FILLER
Filler shall comply with the requirements of Australian Standard 2357, Mineral
Fillers for Asphalt.
The filler required by Clause 11.8 to be included in wearing course mixes shall be
hydrated lime, Portland cement or cement works flue dust.
11.6
BITUMINOUS MATERIALS
11.6.1 The class of bitumen for each course shall be as specified in Clause
11.35(a).
Bitumen shall comply with the requirements of AS 2008, Residual Bitumen
for Pavements and with the additional requirement specified in Table 6.
Table 6
Class of
Bitumen
170
320
Durability*
Minimum time to reach the
specified apparent
viscosity
level (SAVL) (days)
9
7
Viscosity at
25oC (kPa)
100-350
300-1000
Page 96 of 10
August 99
11.6.3 Bitumen emulsion shall be a cationic rapid setting type manufactured from
Class 170 bitumen and complying with AS 1160, Bitumen Emulsions for
Construction and Maintenance of Pavements.
11.6.4 Where requested by the Superintendents Representative the Contractor
shall provide test certificates as to the quality of bitumen used. Such
certificates shall be issued by a laboratory registered by the National
Association of Testing Authorities for the performance of such tests.
11.7
Contractor;
(b)
quarry or source;
(c)
material;
(d)
size;
(e)
proposed use;
(f)
Contract number.
Page 97 of 10
August 99
(b)
(c)
(d)
(e)
stability (kN);
flow (mm);
air voids (%);
voids in mineral aggregates (%);
bulk density (t/m3);
bitumen film thickness (microns).
graphs showing the properties listed in (d), plotted against the respective
bitumen contents.
A period of at least four weeks will be required from the date of samples for the
design or checking of design of a mix.
Design or checking of design of asphalt mixes by the nominated laboratory shall
be at the expense of the Contractor unless otherwise specified.
Where the Contractor proposes to use a mix design previously approved for use
on other Council works to satisfy the requirements of this specification, details of
such mix and current gradings of the components shall be submitted to the
Superintendents Representative at least seven days before commencement of
work. Mixes for which testing was completed more than two years previously will
not be approved.
Where the Superintendents Representative determines that the job mix should be
redesigned due to changes of source, grading or nature of any of the constituent
materials, the mix will be redesigned at the Contractor's expense. Alternatively,
the Contractor may submit a mix design for checking by the nominated laboratory
at the expense of the Contractor.
Page 98 of 10
August 99
11.8
Mix Size
7
95.0-92.5
10
95.5-93.0
14
95.5-93.5
20
96.0-93.5
5.0-7.5
100
4.5-7.0
100
4.5-6.5
100
4.0-6.5
100
The Marshall cylinder test properties of the job mix for asphalt Types V, H, N and
L shall comply with the requirements of Tables 10 and 11.
Page 99 of 10
August 99
Stability
(kN/min)
Flow
(mm)
7
10
14
20
5.5
6.5
6.5
6.5
1.5-3.5
1.5-3.5
1.5-3.5
1.5-3.5
Air Voids
%
Type
V
6-6.5
6-6.5
H&N
5-5.5
5.5.5
5-5.5
5-5.5
Voids in
Mineral
Aggregate
s
(minimum)
Bitumen
Film
Thickness
(micro/min)
17
17
16
15
7.5
7.5
7.5
7.5
7
10
4.5
5.5
1.5-3.5
1.5-3.5
Air Voids
%
3.2-4.2
3.2-4.2
Voids in
Mineral
Aggregate
s
(minimum
)
16
16
Bitumen
Film
Thickness
(micro/mm)
7.5
7.5
Asphalt used for wearing course and asphalt containing aggregates of coarse or
medium grained acidic rocks (eg. granite, adamellite, granodiorite, quartz
porphyry) shall contain not less than 1% filler as specified in Clause 11.5 but the
actual type and amount will be determined by the Superintendents
Representative for the job mix having due regard to the nature of the aggregate to
be used.
Page 100 of 10
August 99
11.9
TOLERANCES
Unless otherwise approved by the Superintendents Representative, the
tolerances on the job mix grading aim before compaction shall be as specified in
Table 12.
Table 12
Sieve Size
AS (mm)
26.5
19.0
13.2
9.5
6.70-4.75
2.36-0.600
0.300-0.150
0.075
10
Nil
Nil
Nil
+/-6
+/-6
+/-5
+/-3
+/-1.0
14
Nil
Nil
+/-6
+/-6
+/-6
+/-5
+/-3
+/-1.0
20
Nil
+/-6
+/-6
+/-6
+/-6
+/-5
+/-3
+/-1.0
(b)
Page 101 of 10
August 99
(c)
(d)
(e)
(f)
The feeders on the cold storage bins for fine aggregates and added
filler shall be equipped with warning devices to indicate any
interruption to material flow.
Page 102 of 10
August 99
Page 103 of 10
August 99
mixing plant
Page 104 of 10
August 99
(b)
Page 105 of 10
August 99
Where stockpiles are formed by tipping from trucks, the material shall be
reclaimed by working the full depth of stockpile on a face.
Where surge piles are constructed material shall be reclaimed from the
surge pile by conveyor belt. If fixed bins are used for storage,
reciprocating, vibratory or variable speed belt feeders shall be used to
deliver the material directly onto a conveyor belt. All materials shall be
handled in such a manner as to minimise segregation.
11.11.2 Filler
Filler shall be stored and handled under a weather-proof cover.
11.12 PREPARATION OF AGGREGATES
11.12.1 Basic Requirements for all Plant
Each separate size or type of coarse aggregate, sand and crusher fines
shall be proportioned correctly before feeding to the dryer or mixer.
The coarse and fine aggregates shall be heated at the plant to a
temperature not greater than that specified in Clause 11.13. Heating
shall continue for a time sufficient to reduce the moisture content so that
the requirement of Clause 11.14 will be met.
Page 106 of 10
August 99
(b)
Page 107 of 10
August 99
Table 13
Material
Bitumen delivered into plant storage
Bitumen delivered into mixer
Aggregates on leaving dryer
Asphalt at discharge from mixing plant
Temperature
o
C (max)
185
165
200
175
The temperature of the asphalt at the spreading site shall be suitable for placing
the asphalt in accordance with the Specification.
Where acceptance of compaction is not based on density testing of the work in
accordance with Clause 11.31, asphalt shall not be placed if the temperature of
asphalt at the spreading site is less than that specified in Table 14.
Where suitable equipment for measurement of the temperature of the surface on
which asphalt is to be placed is not available, air temperature shall be used as an
approximation of road surface temperature.
Where placing of the asphalt is not part of the Contract, the Superintendents
Representative may fix a range of temperature of the asphalt at discharge from
the mixing plant or at the point of delivery. Such range will be not narrower than
10oC.
Page 108 of 10
August 99
Table 14
Compacted
Layer
Thickness
Less than
40
40-100
More than
100
Road
Surface
Temperatur
e (oC)
Less than
10
More than
10
5-10
10-15
15-25
More than
25
5-10
10-15
15-25
More than
25
50
Bitumen Class
170
Refer Clause 11.25
320
140
145
150
140
135
130
125
145
140
135
130
150
145
140
135
125
120
115
110
130
125
120
115
135
130
125
120
11.14 MIXING
The mixing period shall be such that at least 95% of the coarse aggregate
particles are fully coated.
The moisture content of the mix shall not exceed 0.5%.
11.15 INSPECTION AND TESTING AT THE MIXING PLANT
The Superintendents Representative reserves the right to station an Inspector at
the plant to inspect production and loading of asphalt, to endorse delivery dockets
and to carry out assurance testing. When an Inspector is present at the plant,
delivery dockets for each load will be endorsed.
Endorsement of dockets shall in no way constitute approval of the asphalt, but
loads arriving at the point of delivery without such endorsement may be rejected.
Unless otherwise directed by the Superintendents Representative, the Contractor
shall carry out the following checks utilising current test methods and procedures
in accordance with AS2891.
Table 15
Checks Required
Frequency
Scrutiny
for
segregation,
uncoated particles, separated Each loaded truck
Page 109 of 10
August 99
Page 110 of 10
August 99
Before the Final Certificate is issued any damage caused by the Contractor to
kerbs, channels, structures or private property shall be made good by the
Contractor to the satisfaction of the Superintendents Representative and at the
Contractor's expense.
11.21 REMOVAL OF DEBRIS
During the progress of the work under the Contract the Contractor shall keep all
channels and pits free of debris at all times. The Contractor shall remove all
sweepings, spoil and excess or rejected material from the site within two weeks of
the Date of Practical Completion of the Works or of the date for completion for any
particular section of the work specified in Clause 11.35(b) and shall leave the area
clean to the satisfaction of the Superintendents Representative.
11.22 DELIVERY
11.22.1 General
Delivery shall be made during the hours specified or approved by the
Superintendents Representative. Asphalt which is segregated, has
been overheated, is too cold, contains separated bitumen or uncoated
particles or which appears to the Superintendents Representative to not
comply with the Specification shall be removed from the site at the
Contractor's expense. In the latter case if subsequent testing proves
that such material complies with the Specification the Superintendents
Representative may agree that some costs be reimbursed to the
Contractor.
Page 112 of 10
August 99
(b)
(c)
(d)
(e)
(f)
class of bitumen;
(g)
Page 113 of 10
August 99
11.23.2 Pavers
Pavers shall be self-propelled. They shall be equipped with hoppers and
distributing screws of the counter-rotation type to place the asphalt
evenly in front of the screed. Means shall be provided to heat the screed
uniformly over its full width. The total paver width provided for the work
shall be not less than that specified in Clause 11.35(f), and may
comprise any paver combination approved by the Superintendents
Representative.
Pavers shall be capable of spreading the asphalt without segregation in
thicknesses between 12 mm and 150 mm and to widths between 1.8m
and 4.3m except in the case of wide or twin pavers which shall be
capable of spreading to widths up to 8.0m.
Where automatic level control is specified in Clause 11.35(g), it shall be
capable of controlling accurately the longitudinal or the longitudinal and
transverse slopes when working from a fixed reference line or a skid type
levelling beam of suitable length, or a joint-matching shoe.
11.23.3 Compaction Plant
Rollers shall comply with the following requirements:
(a)
All Rollers
Rollers shall be self propelled and capable of reversing without
backlash. Rollers shall be fitted with brushes or similar devices to
enable the contact surface of each roll or tyre to be kept uniformly
damp with a minimum amount of water and free from foreign
material. The taps controlling the rate of flow shall be readily
accessible to the driver. Water shall not be allowed to run directly
from taps on to the asphalt being compacted.
Page 114 of 10
August 99
(c)
Page 115 of 10
August 99
Page 116 of 10
August 99
Page 117 of 10
August 99
Page 118 of 10
August 99
Page 119 of 10
August 99
(b)
(c)
transverse joints shall be offset from layer to layer by not less than
2 m except that the Superintendents Representative may direct
that the minimum offset shall be up to 7 m;
(d)
longitudinal joints shall be offset from layer to layer by not less than
150 mm. Longitudinal joints shall be parallel to the centreline of the
carriageway.
Where directed by the Superintendents
Representative, longitudinal joints in the wearing course shall
coincide with lane line positions and the position of joints in lower
courses shall be planned accordingly. Longitudinal joints at ramp
connections and intersections shall be so positioned as to avoid
joint layouts and may misdirect traffic away from designed travel
paths.
The exposed edges of each paver run shall be formed while hot to a
straightline with a dense face which shall lie between vertical and 45 o to
the vertical for the full depth of the layer. When the Superintendents
Representative directs, the unsupported longitudinal edges of spread
asphalt shall be side tamped to slightly raise the level of the asphalt to
secure maximum edge compaction from subsequent rolling.
Rollers shall not be permitted to damage the unsupported longitudinal
edge except that, on intermediate and base course work, the
Page 120 of 10
August 99
Page 121 of 10
August 99
Page 122 of 10
August 99
Page 123 of 10
August 99
Page 124 of 10
August 99
Page 125 of 10
August 99
Table 16
Size of
Aspahlt
7
10
14
20
Individual
Core Thickness
(mm) (min)
11
15
21
30
Mean Valueof
Core Thickness
15
20
30
35
Acceptance
of
Remove and
replace or
alternatively the lot
may be accepted at
a rate fixed by the
Superintendent's
Representative not
greater than 70% of
the scheduled rate
(Rc) is the Characteristic Value of Relative Compaction for the lot and
(P) is the percentage of the relevant scheduled rate to be paid which
shall not be greater than 100%.
Where the Contract is a lump sum Contract the relevant scheduled rate
will be that shown in the schedule of prices accompanying the lump sum
tender or such other rate or price as the Superintendents
Representative may fix.
Page 126 of 10
August 99
(Rm) is the mean of the individual relative compaction tests for the lot
and (P) is the percentage of the relevant scheduled rate to be paid which
shall not be greater than 100%.
Where the Contract is a lump sum Contract the relevant scheduled rate
will be that shown in the schedule of prices accompanying the lump sum
tender or such other rate or price as the Superintendents
Representative may fix.
Page 127 of 10
August 99
Page 128 of 10
August 99
11.33.3 Thickness
Where payment has been scheduled at a rate per square metre, the
average compacted thickness of each layer of asphalt shall be not less
than the thickness specified in Clause 11.35(h) or shown on the
drawings.
Where the above tolerances are exceeded, the
Superintendents Representative will direct that the defective areas of
asphalt be:
(a)
(b)
(c)
(d)
the
the
Page 129 of 10
August 99
Page 130 of 10
August 99
Table 21
Layer
Main Carriageways
Tonne per
Tonne per
Hour
Day
Restricted Areas
Tonne per
Tonne per
Hour
Day
Wearing
Intermediate
1
Intermediate
2
Base 1
Base 2
Regulation
***(d) Possession of Paving Site (Clause 11.18)
Table 22
Section
Width
Hours
Echelon
Wearing
Intermediate 1
Intermediate 2
Base 1
Base 2
Regulation
Page 131 of 10
August 99
Table 24
Layer
Fixed Wire
Levelling
String Line
Beam
Joint
Matching
Shoe
Transverse
Slope Control
Wearing
Intermediate
1
Intermediate
2
Base 1
Base 2
Regulation
Compacted
Thickness
(mm)
Requirement for
Testing and
Acceptance of
Compaction*
Scale
Scale
Scale
Scale
Scale
Scale
Page 132 of 10
August 99
Standards
12.2
General
12.3
12.4
12.5
12.6
Delivery
12.7
Construction Plant
12.8
Compaction
12.9
Page 133 of 10
August 99
12.1
STANDARDS
The following Australian Standards shall apply to these works:
AS 2734 Asphalt (Hot-Mixed) Paving - Guide to Good Practice
AS 2809 Road Tank Vehicles for Dangerous Goods
AS 2891 Methods of Sampling and Testing Asphalt
12.2
GENERAL
Refer to Section 11 - Specification for Asphalt for manufacture, supply and placing
of asphalt. This section covers the requirements for laying and compacting
asphalt paving.
12.3
Level
The level of the top of each layer shall not differ from the specified level
by more than 10mm, except that where asphalt is placed against kerb
and channel the surface at the edge of the wearing course shall be flush
with or nor more than 5mm above the lip of the channel unless otherwise
specified or shown on the drawings.
12.3.2
Shape
No point on the finished surface of the wearing course shall lie more than
4mm below a 3m straight edge laid either parallel to the centreline of the
pavement or, except on crowned sections, at right angles to the
centreline. For immediate and base course layers, the distance below
the straight edge shall not exceed 6mm and 10mm respectively.
Page 134 of 10
August 99
12.3.3
Thickness
Where payment has been scheduled at a rate per square metre, the
average compacted thickness of each layer of asphalt shall be not less
than the thickness specified in Clause 11.35(h) or shown on the
drawings.
Where the above tolerances are exceeded, the
Superintendents Representative will direct that the defective areas of
asphalt be:
(a)
(b)
(c)
(d)
the
the
Page 135 of 10
August 99
12.5
12.6
DELIVERY
Delivery shall be made during the hours specified or approved by the
Superintendent. Asphalt which is segregated, has been overheated, is too cold,
contains separate bitumen or uncoated particles or which appears to the
Superintendent to not comply with the Specification shall be removed from the site
at the Contractor's expense.
All delivery vehicles shall be of a type approved by the Superintendent. Vehicles
bodies shall be such that the asphalt cannot leak or spill, and shall be fitted with
covers of such size, thickness, and material as will minimise the loss of heat from
the load.
The interior of each vehicle body shall be cleaned of all foreign materials and
lightly lubricated as necessary with a slightly detergent solution or other approved
material. All foreign material and excess lubricate shall be removed prior to
loading the vehicle.
12.7
CONSTRUCTION PLANT
Construction plant shall comply with the following requirements except that other
items and types of plant may be used subject to the approval of the
Superintendent :(a)
Sprayers
Sprayers shall be capable of uniformly spraying the tack coat through jets
in a spray bar at the desired rate of application. Spray bars shall be fitted
with end shields. Each sprayer shall be fitted with a hand lance.
(b)
Pavers
Page 136 of 10
August 99
Compaction Plant
Rollers shall comply with the following requirements :(i)
All rollers
Rollers shall be self-propelled and capable of reversing without
backlash. Rollers shall be fitted with brushes or similar devices to
enable the contact surface of each roll or type to be kept uniformly
damp with a minimum amount of water and free from foreign
material. The taps controlling the rate of flow shall be readily
accessible to the driver. Water shall not be allowed to run directly
from taps on to the asphalt being compacted.
(ii)
(iii)
Page 137 of 10
August 99
COMPACTION
Asphalt shall be uniformly compacted to the Standards specified as soon as the
asphalt will support the roller without undue displacement. Standard rolling
procedures shall be adopted for compaction unless otherwise approved by the
Superintendent. The speed of the rollers shall at all times be slow enough to
avoid undue displacement of the asphalt. Final rolling with a steel wheeled nonvibrating roller shall give a finish free from all roller marks.
12.9
Page 138 of 10
August 99
When spraying the tack coat, shields shall be used and all necessary precautions
taken to protect kerbs, channels, adjoining structures, traffic and parked vehicles.
Where asphalt is to be spread over clean, freshly laid asphalt, or over a clean, dry
and cured primed surface, or where the depth of the layer exceeds 50mm, the
Superintendent may require the Contractor to omit the tack coat.
12.11 EQUIPMENT FOR SETTING OUT AND CHECKING
The Contractor shall provide the following equipment at the paving site for setting
out, for checking levels and depths of asphalt layers and for measuring asphalt
temperature.
(a)
(b)
(c)
(d)
Page 139 of 10
August 99
Standards
13.2
General
13.3
Plant
13.4
Materials
13.5
Depot
13.6
13.7
Method of Work
13.8
Second Seal
13.9
Weather Limitations
Page 140 of 10
August 99
13.1
STANDARDS
The following Australian Standards shall apply to these works:
AS 1160
AS 1742.3
AS 1743
AS 2008
AS 2157
AS 2758.2
AS 2341
13.2
GENERAL
This specification covers the supply of plant, materials, the use of materials, the
cleaning of the surface to be treated, the application of primer and/or
primerbinder, and the supply and/or lifting, carting, spreading and rolling of
aggregate as described hereinafter.
13.3
PLANT
The Contractor shall supply all necessary plant and equipment to the approval of
the Superintendent's Representative, in order to carry out the works, the major
items of which shall comprise:
(a)
Road Broom(s)
Rotary road brooms to be used on the works shall be either drawn or selfpropelled with a minimum core width of 1.8m and shall be capable of
cleaning the road prior to the application of primer or primer-binder to the
satisfaction of the Superintendent's Representative.
(b)
Sprayer(s)
The sprayer(s) to be used on the work shall be of not less than 1800 litres
capacity and shall be equipped with suitable spray bars and appliances so
designed as to distribute evenly, material within the temperature range as
set by the Superintendent's Representative.
Page 141 of 10
August 99
Page 142 of 10
August 99
In the case of a sprayer fitted with a by-pass valve and pressure gauge the
operator shall control and maintain the desired pressure in accordance with
the spraying table.
(c)
Loading Equipment
Equipment for loading aggregate from quarry or roadside stacks into motor
trucks, shall be a Vic Roads type aggregate loader(s) or its equivalent
unless approval is granted by the Superintendent's Representative to the
use of a front end loader(s).
A Vic Roads type aggregate loader(s) or its equivalent shall be equipped at
all times with a full set of screens and mild steel sheets.
(d)
(e)
Aggregate Spreader(s)
Mechanical aggregate spreader(s) capable of uniformly spreading the
aggregate shall be used. Aggregate spreader(s) shall be the box type
and/or the rotating belt type and/or some other type approved by the
Superintendent's Representative.
Page 143 of 10
August 99
(f)
Drag Broom(s)
The drag broom(s) shall be constructed so that the pressure on the broom
bristles can be controlled. The drag broom(s) shall be capable of
distributing aggregate evenly without damaging the work.
(g)
Roller(s)
Roller(s) shall be self-propelled multi-wheeled pneumatic tyred roller(s)
weighing not less than 8 tonnes and with tyre pressure up to 700 kPa and
shall be used as and when directed by the Superintendent's
Representative.
(h)
Tractor(s)
Tractor(s) fitted with pneumatic tyres approved by the Superintendent's
Representative shall be used to tow drawn roller(s), drawn rotary road
broom(s) and drawn drag broom(s) and shall be operated in such a
manner as to avoid damage to the work.
The Contractor shall submit with his tender a statement indicating the plant
and equipment he proposes to use on the works of this Contract.
13.4
MATERIALS
Unless the Superintendent's Representative directs otherwise, the Contractor
shall supply all materials required for priming and primersealing in accordance
with this specification. The Contractor shall have access to sufficient storage of
such materials to enable the ordered work to be done at 24 hours notice.
Page 144 of 10
August 99
DEPOT
The Contractor shall nominate the location of the depot or depots from which he
proposes to operate during the currency of the Contract.
13.6
Grade
Spraying
Temperature oC
Coal Tar
C.V.R. Tar
C.H.R. Tar
40 - 50
45-55
Petroleum Tar
Very Light
20 - 35
Page 145 of 10
August 99
Light
Heavy
Primerbinder
35 - 45
55 - 70
100 - 120
Very Light
Light
Heavy
15 - 30
40 - 50
55 - 70
Cutback Bitumen
AMC.00
AMC.0
AMC.1
Ambient
35 - 55
60 - 80
Special Cutback
Bitumen
Very Light
Ambient
Grade
Spraying
Temperature oC
Light
Heavy
Primerbinder
30 - 45
55 - 70
110 - 130
Class R90
178 - 185
Table 1 (Contd)
Type of Material
Proprietary Grades
Bitumen
Page 146 of 10
August 99
13.7
METHOD OF WORK
13.7.1 Preparation of the Road Surface
Prior to the application of a primer or primerbinder, the surface to be
covered shall be swept clean and free from dust, dirt, caked clay and loose
foreign materials by means of a rotary road broom and/or any other
method approved by the Superintendent's Representative. Particular care
shall be taken to thoroughly clean the outer edges of the surface to be
treated.
Sweeping shall continue until all dust or loose dirt is removed and the top
surfaces of the larger sized aggregate on the surface is exposed. Where
required, handbrooming shall be used at intersections, bellmouths and
other areas as directed by the Superintendent's Representative.
13.7.2 Application of Primer
Primer shall be applied uniformly to the specified areas. Unless otherwise
directed by the Superintendent's Representative, primer shall be applied
only to one half of the width to be treated at a time. It shall be sprayed
100mm wider than the half width of pavement. The inner edge shall be
over the centreline by 25mm (to provide an overlap when the primer is
applied to the second half width) and 75mm outside the outer edge. The
second half width shall not be primed until the first half has dried and will
not be damaged by traffic. If permission to prime full width has been given
by the Superintendent's Representative, the primer shall be applied over a
width 200mm wider than the width of the proposed seal.
When the primer is applied in half width or in part of the full width as
directed by the Superintendent's Representative, the application on each
width shall be arranged so as to provide for a lap of 50mm over the
adjoining previously sprayed primer in order to provide a uniform film of
material over the full width. Primer shall be sprayed at the temperature as
directed by the Superintendent's Representative.
Page 147 of 10
August 99
Equivalent
Page 148 of 10
August 99
Page 149 of 10
August 99
Loading Aggregate
The loading of aggregate shall be done with an approved type
aggregate loader. A front end loader may be used only when
approval is granted by the Superintendent's Representative.
(ii)
Spreading Aggregate
The covering aggregate may be either sand, grit, size 5, size 7, size
10 or size 13 screenings. It shall be loaded into pneumatic tyred tip
trucks and shall be spread uniformly.
Page 150 of 10
August 99
Gritting
When directed by the Superintendent's Representative primed
surfaces shall be gritted to obviate undue delay to traffic. No primer
shall be gritted for at least three hours after spraying or until directed
by the Superintendent's Representative.
(iv)
Precoating of Aggregate
All aggregate for a Class R90 bitumen binder seal coat shall be
precoated with diesel fuel oil or distillate or with a solution of one
part by volume of adhesion agent for 100 parts of diesel fuel oil or
distillate, unless otherwise directed by the Superintendent's
Representative.
The precoating shall be such that a thin uniform film of precoating
material is applied over each individual piece of aggregate and shall
be done while the aggregate is being loaded into the tip trucks used
to spread the aggregate on the job.
All aggregate precoating shall be done to the satisfaction of the
Superintendent's Representative.
(v)
Rolling
Rolling shall be by self propelled pneumatic tyred multi-wheeled
rollers. Drawn multi-wheeled pneumatic tyred rollers shall not be
used, unless approval has been obtained from the Superintendent's
Representative.
Page 151 of 10
August 99
Drag Brooming
Drag brooming shall be carried out in conjunction with rolling to
ensure that a uniform distribution of aggregate is achieved. The
operation of the drag broom and the duration of drag brooming shall
be as directed by the Superintendent's Representative.
13.8
SECOND SEAL
The second seal or reseal shall be placed no less than six months after the
previous seal unless otherwise directed by the Superintendents Representative.
13.9
WEATHER LIMITATIONS
Unless specifically directed by the Superintendent's Representative no material
shall be sprayed onto a surface which is wet or when the air temperature in the
shade is less than 15oC.
Page 152 of 10
August 99
Page 153 of 10
August 99
General
14.2
Paving Units
14.3
Base Course
14.4
Edge Restraints
14.5
Bedding Sand
14.6
14.7
Laying of Pavers
14.8
Compaction
14.9
Jointing Sand
Page 154 of 10
August 99
14.1
GENERAL
Segmental paving shall be constructed in all areas as shown on the
drawings.
The Contractor shall supply and deliver sufficient paving units to satisfactorily
complete works under this Contract and stockpile them in a manner that does not
interfere with pedestrian or vehicle traffic.
14.2
PAVING UNITS
14.2.1 Clay Pavers
Clay pavers shall be manufactured from clay, shale or other argillacious
materials which may be mixed with additives.
They shall be pressed or extruded and cut or moulded to the required
shape then dried and fired.
The pavers will be of first quality and must comply with the requirements
specified herein.
Testing shall be initiated by taking a random sample of pavers from a
consignment in accordance with AS 1226.1 (1984) from which sub-samples
are taken at random for specific tests.
Manufacturers Standards
.
= 65 mm
Edge Treatment
(a)
Bevelled Edge
= 5 mm ( max.
plan width)
(b)
Rounded Edge
radius)
= 7 mm ( max
Page 155 of 10
August 99
sampled
in
Durability
Pavers shall have a durability class
of exposure to resist salt attack as
defined in AS 1225 - 1984.
Pitting
Pavers shall conform to a 'moderate'
standard as defined in AS 1225 - 1984.
Slip/Skid Resistance
The slip/skid resistance of a paver shall
be determined by using British Pendulum
Skid Resistance Tester as defined in Brick
Development Research Institute,
Design Note 13(c), ie. BPN
= 60 (Minimum).
Abrasion Resistance
Pavers shall have a high abrasion resistance
to satisfy current A.R.R.B. standards.
Page 156 of 10
August 99
Manufacturing Standards
.
= 80 mm
.
Dimensional Tolerance relative to = +/- 2 mm in
Manufacturers' specified
the horizontal
dimensions
plane
= +/- 3 mm in
thickness
.
Edge Treatment - Bevelled Edge = 8 mm (Max.
plan width)
.
Compressive Strength
the
= 45 mPa
(Appendix C )
.
14.3
Abrasion Index
=1.5 ( Appendix 0)
BASE COURSE
The crushed rock base course shall be 3% cement treated and constructed in
accordance with Section 6 of Council's specifications to a standard normally
required for bituminous surfacing treatment.
For paving subject to traffic base course shall be 150mm concrete normally
reinforced (25 mpa) in accordance with Section 7.
14.4
EDGE RESTRAINTS
Edge restraints shall be provided along the perimeter of all paving in the form of
integral kerb and gutter, concrete kerb, or edge strip or established structure. The
face of the edge restraint, where it abuts the paving units, shall be vertical down to
the sub-base.
Edge restraints shall be constructed to the dimensions and levels shown on the
drawings and shall be supported on a compacted sub-base not less than 75 mm
thick.
Page 157 of 10
August 99
14.5
BEDDING SAND
The bedding sand shall be a naturally occurring angular sand having a grading
within the range given below:
Sieve Size
9.52mm
4.75mm
2.36mm
1.18mm
600umm
300umm
150umm
14.6
% Passing
100
90-100
75-100
55-90
35-59
8-30
0-10
14.7
LAYING OF PAVERS
Paving units shall be placed onto the screeded uncompacted bedding sand in a
90 degree herringbone pattern unless otherwise approved. The paving units shall
bear evenly on the sand. The units shall be placed to achieve a gap 2-4mm wide
between units, such that all joints are correctly aligned.
Page 158 of 10
August 99
The first row of paving units shall abut an edge restraint with a gap of 2-4mm and
shall be laid at a suitable angle to the restraint to achieve the required visual
orientation of the completed pavement.
In each row, all complete paving units shall be laid first. Closure units shall be cut
and fitted subsequently. Closure units shall not be less than 25% of the complete
paving unit. Paving units shall be cut using an approved method, such as
guillotine, bolster or power saw.
Concrete with 10 mm aggregate shall be used to infill gaps between 25 and
50mm after the paving units have been laid. Smaller gaps shall be filled with
cement mortar. The colour shall match that of the paving units.
Paving units shall not be hammered into position, unless it is necessary to correct
minor variations to the laying bond.
Care shall be taken to prevent pre-compaction of the bedding sand.
Prior to compaction, no construction traffic is to be allowed onto the laid paving
units. Boards shall be provided for foot and barrow traffic.
14.8
COMPACTION
Paving units shall be compacted as soon as practicable after laying and prior to
traffic usage. Compaction shall achieve consolidation of the bedding sand and
bring the paving units to design levels and profiles with three passes of a suitable
plate compactor.
Compaction shall not be carried out within 1 m of the laying face. Compaction
shall continue until lipping has been eliminated between adjoining units.
Compaction shall be carried out using a high frequency, low amplitude
mechanical, flat-plate vibrator. The plate area shall be sufficient to cover a
minimum of 12 paving units.
All work to within 1 m of the laying face shall be compacted at the completion of a
days work.
Page 159 of 10
August 99
14.9
JOINTING SAND
Both bedding and jointing sand shall be free of deleterious soluble salts or other
contaminants likely to cause efflorescence or lead to the reduction of skid
resistance.
The sand shall be of a uniform moisture content when spread and shall be
protected against rain when stockpiled on site prior to spreading. The moisture
content shall be in the range 4-8% at the time of placement.
Sieve Size
2.36mm
1.18mm
600umm
300umm
150umm
70umm
% Passing
100
90-100
60-90
30-60
15-30
5-10
Page 160 of 10
August 99
10mm with a
Page 161 of 10
August 99
Standards
15.2
General
15.3
Roadmarking Materials
15.4
15.5
Site Preparation
15.6
Noise - EPA
15.7
Health Act
15.8
Layout of Markings
15.9
Application of Markings
Page 162 of 10
August 99
15.1
STANDARDS
The following Australian Standards shall apply to these works
AS 1742
AS 1743
AS 1744
AS 1580
AS 2009
AS 2709
AS 4049.1
15.2
GENERAL
This section covers the requirements for installation and/or removal of pavement
markings in roadmarking paint, thermoplastic roadmarking material, cold-applied
plastic material or pliant polymer roadmarking tape carried out under period
quotation. It also covers the installation and/or removal of raised pavement
markers under period quotations.
15.3
ROADMARKING MATERIALS
(a)
Roadmarking Paint
Paints shall comply with the requirements of Australian Standard AS4049.1
Paints and related materials-Road marking materials, part 1: Solventborne paint - For use with drop-on beads, or shall be a water-borne paint
approved for use by VicRoads. The following paints are approved for use
under this quotation:
(i) DULUX
Page 163 of 10
August 99
(ii) ANZOL
(iii) WATTYL
Page 164 of 10
August 99
The precise product to be used from the range available shall be approved
by the Superintendents Representative. Approval to use materials from
other manufacturers may be given by the Engineer subject to the
Contractor submitting satisfactory evidence that the material conforms to
AS 4049.2 or BS 3262 with softening point range as specified in AS 4049.2
and that the material has been proved in service elsewhere at the
thicknesses specified herein.
(c)
(d)
(e)
Glass Beads
Drop-on glass beads shall be used on all roadmarkings except tape. They
shall conform with Australian Standard 2009 Glass Beads for Traffic
Markings.
Materials (b), (c) and (d) above are collectively defined as longlife
materials.
(f)
Ray-O-Lite Australia
Hardman
Stimsonite Australia
15.5
SITE PREPARATION
(a)
Cleaning
The Contractor is to ensure that the area to be marked is dry and free from
dirt, gravel, oil or other loose or deleterious material. Sweepings shall be
collected and removed from the site to prevent contamination of the
completed marking. Legal disposal of such sweepings shall be the
responsibility of the Contractor. The cost of cleaning shall be included in
the relevant schedule item for the work.
Page 166 of 10
August 99
(b)
(c)
Priming
Where the new marking is to be in longlife a tack coat or primer shall be
used on the cleaned surface in accordance with the manufacturers
recommendation. Where the Contractor believes a tack coat or primer is
unnecessary, for example on new asphalt, he shall seek the approval of the
Superintendents Representative to the omission of such tack coat or
primer. The cost of tack coat or primer shall be included in the relevant
schedule item for the work.
15.6
NOISE - EPA
The Environment Protection Authority do not appear to have direct control over
noise emanating from road work sites.
It is Council policy to comply as far as practicable with the intent of the EPAs
regulations and policies and the following is provided for information.
The Special Gazette No 31 of 15 June 1989 being the State Environment
Protection Policy (Control of Noise from Commerce Industry and Trade) is the
means by which the Environment Protection Authority prescribes noise limits for
commercial, industrial or trade premises (Clause 9). The day is split into a
day period from 0700 hours to 1800hrs (6pm), an Evening period from 1800hrs
to 2200hrs (10pm) and a Night period from 2200hrs to 0700hrs.
Page 167 of 10
August 99
The EPA have issued guidelines for ROAD REPAIR AND TRACK MAINTENANCE
Clause D being:
If routine work is planned outside the hours specified by the schedule all affected
premises in the residential area should be notified of the intended work, its
duration and times of occurrence. The hours in the schedule are 7am to 6pm
Monday to Saturday and 9am to 6pm Sunday and Public Holidays.
15.7
HEALTH ACT
The Health Act 1958 Part 39A applies to nuisances which are, or liable to be,
dangerous to health or offensive and in particular to nuisances arising from or
constituted by - ...
...(e) any noise or emission: or ...
Part 41. A council must remedy as far as is reasonably possible all nuisances in
its municipal district.
Part 42. A person must not(a)
cause a nuisance; or
(b)
knowingly allow or suffer a nuisance to exist on or emanate from any land
owned or occupied by or in the charge of that person.
Part 435 (1) Any authorised officer of the Department or of any council or any
authorised member of the police force may prosecute for any breach of or offence
against this Act.
Clearly it is the Courts discretion as to what noise constitutes a nuisance.
A complainants medical condition may cause a noise to be dangerous to health in
which case a prosecution may be successful.
Therefore the Contractor shall be responsible for minimising the noise of these
stripping operations to comply with the spirit of the EPAs Noise Regulations.
Each job shall be assessed as to the likely impact of the proposed stripping and
the Contractor shall carry out such stripping at a time which balances the affect of
the noise on residents with the disruption caused to traffic.
Page 168 of 10
August 99
15.8
LAYOUT OF MARKINGS
(a)
Standards
The position and dimensions of the roadmarking shall conform with the
standard drawings attached, or with AS 1742, or with site drawings
supplied with the job requisition or as otherwise directed by the
Superintendents Representative on site.
Where these references are in conflict the Superintendents Representative
shall direct which to comply with. Standard drawings attached include:
References:
(b)
Tolerances
At locations where the existing markings are badly worn or where new
markings are required, these shall be first set out using a chalk string line
or similar method to achieve correct alignment of the markings.
Where it becomes evident that the position of an existing marking is not in
accordance with the standard drawings, the Contractor shall not proceed
with the work but shall contact the Superintendents Representative who
will direct what action to take.
The Contractor shall place markings so that:
(i)
the distance between the centreline of the marking and the
the spotting out mark is less than 30 mm; and/or
(ii)
(iii)
(iv)
centreline of
(v)
the gap between double lines is within + 10mm of the
specified gap.
The acceptance of markings outside the above tolerances will be at the sole discretion
of the Superintendents Representative who will determine the extent of reduced
payment or other remedial action for our of tolerance markings.
Page 169 of 10
August 99
15.9
APPLICATION OF MARKINGS
(a)
Page 170 of 10
August 99
(ii)
Page 171 of 10
August 99
(c)
Painted Markings
Completed markings shall be uniform in appearance, texture, width and
thickness and the surface shall be substantially free from streaks, overlaps,
unbeaded areas, tyre marks or other defects. Edges and cut-offs should
be neat and sharp, and care should be taken to ensure minimal spatter to
the surrounding area.
Glass beads shall be sprinkled or sprayed on to the painted surface while it
is still wet immediately after spraying. The beads shall be uniformly
distributed over the whole marking.
Thickness (unbeaded, measured by laboratory assessment of the mass
and density of the paint sprayed on a metal plate placed in front of the
applicator):
(i)
(ii)
Page 172 of 10
August 99
Page 173 of 10
August 99
Brand name or Product Name and the name of the supplier of the following:(i)
Paint
(ii)
Thermoplastic
(iii)
(iv)
Tape
(v)
Glass Beads
(c)
It should be also noted that the acceptance of a tender shall not be taken to imply that the
materials, plant or equipment are sufficient or satisfactory and shall not relieve the Contractor
from the necessity for compliance with the specified conditions.
Page 174 of 10
August 99
General
16.2
Cold Planing
16.3
16.4
16.5
Schedule of Details
ID 6016
Page 175 of 10
August 99
16.1
GENERAL
This section covers the requirements for the cold planing of existing pavements
including the cleaning up, removal and disposal of the excavated materials.
16.2
COLD PLANING
Cold planing shall be carried out in such a manner as to leave a uniform surface
on a plane parallel with the ultimate finished surface of the pavement as shown on
the drawing or fixed by the kerb and channel or as directed by the Engineer.
The nominal depth and width of pavement to be removed shall be as specified in
Section 16.5. After planing, no point on the planed surface shall lie more than
15mm below a 3m straight-edge placed on the planed surface in any direction.
For contracts requiring both removal and replacement of asphalt, the production
rate of the cold planing operation including clean up shall match the production
rate of the asphalt replacement operation.
The Contractor shall make his own arrangements for the supply water required for
the work.
16.3
Page 176 of 10
August 99
16.4
ASPHALT REPLACEMENT
Where work under the Contract includes replacement of planed material with
asphalt, unless otherwise specified or directed, the following requirements shall
apply:
(a)
(b)
(c)
SCHEDULE OF DETAILS
(strike out items which are not applicable)
(a)
Type of work:
(i)
(ii)
(iii)
(iv)
(b)
Sq.m.
mm.
(c)
(d)
(e)
m.
Page 177 of 10
August 99
17.2
Sub-base preparation
17.3
17.4
17.5
17.6
17.7
Initial finishing
17.8
Final finishing
17.9
Curing
ROAD
17.10 Joints
17.11 Tolerances
17.12 Protection of pavement and opening to traffic
ID 6017
Page 178 of 10
August 99
17.1
CONCRETE
Concrete road pavement works should also comply with Section 7 of this
Specification, unless otherwise specified in this section.
17.2
SUB-BASE PREPARATION
A crushed rock sub-base shall be placed to the thickness specified on the
drawings in accordance with the following requirements. The crushed rock subbase shall be Class 3 fine crushed rock. The sub-base shall extend to the rear
face of side forms. Longitudinal and transverse construction joints in cementbound sub-bases shall be offset at least 300mm from joint locations in the
concrete base.
The sub-base shall be compacted to 100% standard compaction as defined in AS
1289.
The sub-base shall be trimmed to within +0/-10mm of nominated design levels.
The surface of the prepared sub-base shall not deviate by more than 10mm from
a 2m straightedge supported at its ends and laid in any direction.
The sub-base shall be inspected and approved by the Superintendent's
Representative before subsequent operations proceed.
Prior to placing of the concrete the sub-base shall be thoroughly moistened, but
no puddles shall be allowed to form.
17.3
Page 179 of 10
August 99
Openings for manholes or gullies shall be formed by casting the main slab
against formwork boxes. The forms shall be removed and a preformed
10mm thick (nominal) joint-filler fixed to the exposed slab edges for their
full depth before the pit surround is constructed.
17.4
Page 180 of 10
August 99
(b)
Forms shall be adjusted to the correct level by the use of steel shims
or wedges. In this case the space between the sub-base and the
form shall be filled solid and trimmed flush with the inside face of the
form.
Forms shall be set sufficiently in advance of concrete placing to
permit inspection. Where any form or the sub-base has been
disturbed, the sub-base shall be corrected if necessary and the
forms reset and rechecked. Forms shall be cleaned and coated with
a suitable form-oil before each use.
Forms shall remain in place for at least one day unless joints are to
be sawn, in which case forms shall remain in place from the time of
concreting until the concrete is ready for sawcutting. Forms shall be
carefully removed to avoid damage to the pavement and any
projecting tie-bars or dowels.
Page 181 of 10
August 99
Page 182 of 10
August 99
Page 183 of 10
August 99
(b)
Page 184 of 10
August 99
17.7
INITIAL FINISHING
The concrete shall be screeded to the required cross section profile. This work
shall be completed in conjunction with the placing and compaction of the concrete
as specified above. While the concrete is still plastic, depressions shall be filled
with fresh plastic concrete, compacted and refinished. High areas shall be cut
down by scraping with straightedges or other approved devices, and refinished.
Where slipformed pavements exhibit edge slump in excess of specified
tolerances, the Superintendent's Representative may direct that the Contractor
use temporary side forms for surface correction. The forms shall be capable of
maintaining surface profile during surface correction work. The forms shall be
adequately braced and shall remain in place until their removal will not cause
damage to the new concrete.
17.8
FINAL FINISHING
17.8.1 General
Final finishing includes floating and texturing the pavement. Final finishing
shall commence only as soon as water sheen has left the pavement
surface. It shall not be attempted in any area where there is free surface
water.
17.8.2 Floating
The concrete surface shall be floated where necessary to remove any
surface irregularities, porous areas or depressions. Floating shall be
performed by means of mechanical helicopter type floats or long-handled
'bull floats' having a metal blade approximately 1 m long and 150 to 200
mm wide with a pivoting head attached to the handle. These floats shall be
operated in a series of continuous overlapping passes transversely across
the full width of the pavement.
17.8.3 Hand Finishing
Unless otherwise approved, finishing by small handheld floats shall not be
permitted except:
(a)
(b)
Page 185 of 10
August 99
(a)
General
The texturing operation shall not be commenced until the condition
of the concrete is such that the surface will not be torn or coarse
aggregate particles unduly loosened.
In the case of slipform construction the texturing shall be carried out
by means of a machine spanning the pavement and guided by the
paver guide wires, or by suitable manually operated equipment.
(b)
17.9
The broom shall be drawn across the full width of the pavement, in a
series of continuous, slightly-overlapping strokes, transversely to the
direction of traffic. The broom's angle of contact with the pavement
surface shall be constant. The broom shall be cleaned by washing
and/or tamping after each pass.
CURING
17.9.1 General
As soon as practicable after the texturing operations have been completed
the entire surface of the pavement, including exposed sides, shall be cured
by protecting it against loss of moisture for at least four days. Curing shall
be carried out by one or more of the following means. All of the equipment
and materials necessary for the curing operations shall be on hand at the
location of paving before concrete placement commences.
Page 186 of 10
August 99
Page 187 of 10
August 99
17.10 JOINTS
17.10.1
General
Contraction Joints
General
Sawcutting or forming vertical grooves in the top of the pavement
and shall be constructed by either of the following methods.
Transverse contraction joints shall extend continuously across the
full width of the pavement.
(b)
Sawn Grooves
For sawn grooves, joint locations shall be marked on the surface by
suitable means in advance of sawing to permit verification of joint
locations. Grooves shall be sawn vertically in the concrete to a
depth not less than one quarter the concrete thickness, at the
nominated joint locations, by experienced operators using power
saws and blades specifically suited to the early sawing of concrete.
A standby saw and blades shall be available at the location of
paving in progress to maintain continuity of work in the event of plant
breakdown.
Sawcutting shall commence as early as possible (to avoid
uncontrolled shrinkage cracking) but not so early as to cause
unacceptable ravelling of joint edges. The joints shall be sawn in
sequence. Sufficient saws shall be employed to maintain the
necessary rate of sawcutting.
Concurrently with the sawing operations the sawn groove shall be
washed or hosed free of fine grit resulting from the sawing. Material
hosed from the groove shall be cleaned from the pavement surface.
Sawn grooves forming a reservoir for a joint sealant shall be formed
either:
(i)
Page 188 of 10
August 99
(ii)
(c)
Formed Grooves
Formed grooves shall be made by depressing an approved tool or
device vertically into the plastic concrete to one quarter the
pavement thickness from a work bridge spanning but not touching
the pavement. Steel devices shall be coated with an approved
bondbreaking compound and vibrated into the concrete. Other
proprietary inserts which may include a parting strip shall be
installed and the parting strip later removed in accordance with the
supplier's specification. The tool or device should be continuous for
the full width of the paving run, and unless fitted with a parting strip,
shall remain in place until the concrete is in a condition such that its
removal will not disturb adjacent concrete. Parting-strip inserts shall
not be depressed below the pavement surface but shall remain flush
with the surface and visible after insertion. The concrete surface
shall be corrected by floating across the formed groove. The
pavement shall be checked longitudinally with a straight-edge to
confirm restoration of continuity of the surface across the groove.
Page 189 of 10
August 99
17.10.3
Construction Joints
(a)
(b)
17.10.4
Isolation Joints
Isolation joints shall be provided between the pavement and all abutting
and penetrating structures - eg poles, gully pits and public utility manholes and at pavement intersections where shown on the Drawings. The joint
shall be constructed as specified and shall extend for the full depth of the
pavement and for the full perimeter or line of the joint as required.
17.10.5
Joint Sealing
Page 190 of 10
August 99
17.11 TOLERANCES
17.11.1
The width of the completed pavement shall not be less than that specified
and the edge of the completed pavement, or individual paving runs, shall
not deviate by more than 25mm from the designated alignment.
17.11.2
Joint Position
Thickness
Page 191 of 10
August 99
Page 192 of 10
August 99
Imported Topsoil
18.2
Mulch
18.3
Weed Mat
18.4
Fertiliser
18.5
Stakes
18.6
18.7
18.8
Preparation of Subgrade
18.9
Topsoiling
Page 193 of 10
August 99
18.1
IMPORTED TOPSOIL
Where existing topsoil gained from the site is insufficient or unsuitable, imported
topsoil from an approved supplier may be used conforming to the following:
(i)
pH:
Slightly acid to neutral, ie. 5.5 - 7.0.
(ii)
Stone content:
No stone
(iii)
Colour:
Dark grey brown to red brown.
(iv)
Extraneous matter:
Free from rubbish, petrol, oil, free of lime or other deleterious matter.
(v)
Sample:
Provide 0.03 cubic metre sample of topsoil for approval prior to delivery.
Imported topsoil, where required, will be paid by cubic metre substantiated
by delivery dockets from supplier.
18.2
MULCH
Areas to be mulched are:
(i)
Page 194 of 10
August 99
(ii)
18.3
(i)
(ii)
Eucalypt mulch.
WEED MAT
Where required approved weed mat 600mm x 600mm to be pegged with four wire
ties at the corners at each tree planted.
18.4
FERTILISER
Osmocote slow after release fertiliser shall be applied to the base of plant to the
width of the pot, positioning the plant in the hole, at the manufacturers
recommended rate.
18.5
STAKES/GUARDS
(i)
Three hardwood stakes per plant to be placed around all plants with
450mm X 400mm clear sleeve to protect the plants. Hardwood stakes to
be 25mm X 25mm pointed stake, 750mm long. Stakes to be driven
200mm below surface level and placed so as not to disturb the root ball of
the plants.
OR - if directed
(ii)
Two stakes per tree to be placed at all trees in lawn areas, to identify and
protect the trees. Hardwood stakes 50mm x 50mm x 1800mm high to be
used. Stakes to be driven 450mm below surface level and placed not to
disturb the root ball of the plants.
Page 195 of 10
August 99
18.6
18.7
18.8
PREPARATION OF SUBGRADE
Excavate as required to establish subgrade level to allow for addition of topsoil
and mulch.
Equipment:
equipment.
All garden areas that are heavily compacted from construction work shall be
broken up by an initial cultivation prior to the placement of the topsoil. This shall
be carried out by ripping to a depth of 300 mm and shall be along the contours to
prevent erosion. The ripping shall leave the ground in a loose and friable
condition.
18.9
TOPSOILING
Spread topsoil to an even depth of 250 mm and do not deliver or spread in a
muddy condition. Where access is required over established or proposed garden
areas, keep the vehicular routes in the smallest possible area and after
completion of deliveries, rip to a depth of 300 mm to leave compacted soil in a
loose and friable condition.
Page 196 of 10
August 99
All plants shall be healthy, well grown, true to type, disease free and have a well
developed root system supplied in 150 mm minimum diameter size pots.
(Tubestock may only be supplied with Project Officers approval.)
All plants shall be handled at all times in such a manner as to prevent damage in
transit.
The Project Officer shall be contacted in the event of difficulties with quality, size
or availability of nominated species, and shall approve all plants before planting is
to commence. Note that any such substitution may involve a price reduction.
18.11 SETTING OUT
The plants shall be positioned as shown on the plan and to the general
satisfaction of the Project Officer who may at his direction request on-site
modifications, provided always that such variations are clearly justified and kept to
a reasonable minimum.
18.12 PLANTING HOLES
A planting hole for each plant shall be dug at least 300 mm in diameter or twice
the diameter of the plant container, whichever is the greater, to a depth of 75150mm greater than the depth of the container. The sides and base of the hole
shall be broken down to facilitate root penetration into the surrounding soil where
necessary. Care must be taken to avoid disturbance or damage to underground
services.
18.13 PLANTING
The plant shall be removed from its container and, where necessary, the roots
shall be loosened and frayed out, with twisted roots either straightened or pruned.
The plant shall then be positioned in the hole so that the soil level around the
plant is 25mm below that of the surrounding soil.
Page 197 of 10
August 99
The backfill soil shall be free of rubble, clods, etc, greater than 50 mm diameter.
Where necessary (where there is too much rubble or clay), an adequate amount
of acceptable topsoil shall be added to the backfill soil.
A shallow saucer depression of approximately 500 mm diameter cleared of weeds
shall be formed around the plants for watering purposes.
Mulch:
In garden areas the mulch is to be returned to the disturbed area. Keep mulch
away from the tree trunk to avoid rotting.
18.14 GRASSING
(a)
All areas specified on the detailed landscaping plan to be sown at the rate
of 4kg per 100sq m with a seed mix determined by the Project Officer.
(b)
(c)
(d)
(e)
At the time of the first grass cut, grass is not to be cut lower than 50mm in
height.
(f)
Sweep grass cuttings from paths, drives, etc, as directed and trim grass
edged at path and drive boundaries, etc, at end of maintenance period.
Page 198 of 10
August 99
(b)
Replace any dead, pest damaged or badly diseased plants during the
currency of the maintenance works. Replacing all such plants at the
completion of the maintenance period shall not be acceptable unless
approved by the Project Officer;
(c)
(d)
Maintain the 800mm diameter mulched area around the plants in a weed
free condition;
(e)
(f)
Page 199 of 10
August 99
Description
19.2
19.3
Materials
19.4
19.5
Beaching Placement
19.6
Grouting
19.7
Perimeter Walls
19.8
Cleaning
ID 6019
Page 200 of 10
August 99
19.1
DESCRIPTION
This section covers the requirements for the supply and placing of rock, stone or
manufactures block bleaching for the protection of batter slopes, drainage
channels and culvert endwalls as shown on the drawings. Four types of beaching
are covered by this section.
Type
Type
Type
Type
19.2
1:
2:
3:
4:
19.3
MATERIALS
Unless otherwise specified, the Contractor shall supply all materials necessary to
construct the beaching as specified, including rock or paving blocks, bedding
materials, geotextile, concrete, reinforcement and drainage pipes.
(a)
Beaching Material
(i)
Type 1 Beaching
Rock for type 1 beaching shall consist of sound, dense field or
quarry rock.
Field or quarry rock shall be resistant to weathering action of air and
water and shall be free from cracks and other structural defects
which may reduce its mechanical strength and resistance to
weathering.
All rock, shall have a mass of between 20 and 70 kg and at least
60% by number shall be over 40 kg mass. Rocks shall be of such
size that the layer of beaching is not less than 225 mm thick.
Page 201 of 10
August 99
(ii)
Type 2 Beaching
Rock for Type 2 beaching shall conform with the same general
requirements as for Type 1 beaching except that the rocks shall be
of such size that the layers of beaching shall be at least 150 mm
thick and of mass between 10 kg and 40 kg with at last 60% by
number having a mass over 25 kg. The rocks shall be reasonably
uniform in colour.
(iii)
Type 3 Beaching
Type 3 beaching shall consist of sound dense flat stone.
Beaching stone shall be free from cracks and other structural defects and
reasonably uniform in size, shape and colour. Each piece shall be not less than
65 mm thick and have a face area not less than 0.1 m2. At least 50% of the
pieces by number shall have an area of more than 0.2 m.
(iv)
Type 4 Beaching
Paving blocks shall be of a type, face size, thickness and colour as
specified.
Bedding
Type 1 beaching shall not require a granular bedding. However a needlepunched non-woven geotextile, with a mass not less than 250 g/m and
with a robustness (geotextile strength Rating G) of 600 to 900, shall be laid
over the trimmed surface where beaching is to be placed. The geotextile
shall be buried to a depth of 300 mm at the edges of beaching and
wrapped under the toe wall unless otherwise specified. the geotextile shall
be laid evenly with no kinks or folds, and joints shall be formed by
overlapping the geotextile by not less than 300mm and not more than
500mm.
Type 2 beaching shall not require bedding unless otherwise specified or
shown on the drawings.
Page 202 of 10
August 99
19.5
BEACHING PLACEMENT
(a)
(b)
Type 1 Beaching
Gaps between rocks shall be as narrow as practicable. Unless otherwise
specified, voids shall be fitted to at least mid-height of the rocks with
topsoil.
(c)
Type 2 Beaching
Width of joints may vary between 10 mm and 60 mm, with an average not
exceeding 40 mm. Level difference between edges of adjacent rocks shall
not exceed 40 mm. The joint pattern shall be random and the joints kept
free from debris before grouting.
Page 203 of 10
August 99
(d)
Type 3 Beaching
Beaching material shall be thoroughly cleaned and saturated with water
before being bedded on fresh mortar as specified in clause 19.3(b).
The joint pattern shall be random and the joints kept free from debris prior
to grouting. Width of joints may vary between 10mm and 60mm, with an
average not exceeding 40mm. Level difference between edges of adjacent
stones shall not exceed 25mm.
(e)
Type 4 Beaching
The blocks shall be placed on the specified bedding sand and laid in
accordance with the manufacturers recommendation. Edge blocks shall
be neatly cut to establish straight edges. Dry sand shall be broomed into
joints on completion and lightly watered. The sand use in mixture shall all
pass a 1.18mm AS sieve and 10-20% shall pass a 0.075mm AS sieve.
19.6
GROUTING
Joints shall not be grouted until the Superintendent has reviewed the beaching.
Grouting with mortar shall be carried out when the air temperature is above 5C
and work shall be kept moist for 3 days after grouting.
Joint mortar shall consist of one part Portland cement, six parts sand by volume,
thoroughly mixed with water to produce grout of suitable consistency.
The joints shall be neatly finished by filling with mortar. Care shall be taken to
keep the exposed rock face clean. Brooming of mortar across the face of the
rocks will not be permitted.
Page 204 of 10
August 99
19.7
PERIMETER WALLS
Perimeter and toe walls shall be constructed where shown on the drawings.
For Type 1 Beaching, toe walls 600mm wide by 600mm deep shall be
constructed. They shall be lined with geotextile fabric and filled with hand packed
rock, the larger voids between rocks being filled with smaller stones.
For Type 2, 3 and 4 Beaching, concrete perimeter walls shall be constructed
around exposed edges of the beaching.
Toe walls shall be 300mm wide by 400mm deep at the front face and reinforced
with 3-8TM trench mesh top and bottom. The upper surface of the toe wall shall
slope upwards at either the slope of the rock beaching or the adjacent verge as
shown on the drawings. Side walls and top walls shall be 150mm wide by 250mm
deep. The top of the walls shall be continuous with the beaching.
19.8
CLEANING
On completion of the work, the beaching shall be cleaned to remove all foreign
material and discolouration from the beaching surface. Any joint mortar adhering
to the surrounding rock surfaces shall be removed.
Page 205 of 10
August 99
General
20.2
Description
20.3
20.4
20.5
Rates of Application
20.6
20.7
ID 6020
Page 206 of 10
August 99
20.1
GENERAL
This section should be read in conjunction with the Specification for Priming and
Primersealing and covers special requirements for bitumen scrap rubber sealing
that override or are in addition to the requirements for Section 13.
20.2
DESCRIPTION
A bitumen scrap rubber seal incorporates granular scrap rubber which is added to
modify the characteristics of bitumen. A concentration of 5 parts of added scrap
by mass (Nominal 5% Scrap Rubber) can be used to improve aggregate retention
characteristics under severe traffic conditions. A concentration of 20 to 25 parts of
added scrap rubber by mass (Nominal 20 to 25% Scrap Rubber) will improve the
elastic recovery of the binder to aid the waterproofing of moderately cracked
surfaces.
20.3
2.36
100
1.18
80-100
0.600
15-40
0.150
0-3
100
100
70-100
0-5
Page 207 of 10
August 99
Page 208 of 10
August 99
20.5
RATES OF APPLICATION
The design rates of application are the rates of application of residual binder only
(Bitumen and any flux oil) and do not include the proportion of rubber, kerosene
and adhesion agent in the mixture. The Contractor shall spray such higher rates
of application of the mixture to compensate for the effect of rubber kerosene and
adhesion agent.
20.6
20.7
Page 209 of 10
August 99
Standards
21.2
Description
21.3
Proportioning
21.4
Mixing
21.5
Spreading Equipment
21.6
Laying
21.7
21.8
21.9
Mix Design
ID 6021
Page 210 of 10
August 99
21.1
STANDARDS
The following Australian Standards shall apply to these works:
AS 1160
AS 2758.2
AS 2357
AS 2341
21.2
DESCRIPTION
The Cold Overlay surface shall consist of a mixture of polymer modified bitumen
emulsion, aggregate, water, additives and fillers, properly proportioned, mixed and
spread evenly on the surface as specified herein and as directed by the
Superintendents Representative.
The cured Cold Overlay shall have a
homogenous appearance, fill all cracks, adhere firmly to the surface and have
skid resistant texture.
21.3
PROPORTIONING
A job mix design shall be submitted by the Contractor for approval by the
Superintendents Representative that conforms to the specification limits, and that
is suitable for the traffic, climatic conditions, curing conditions and final use.
The Cold Overlay mixture shall be proportioned by the operation of a single
start/stop switch or lever which automatically sequences the introduction of
aggregate, bitumen emulsion, additives and water to the pugmill. Calibrated sight
flowmeters shall be provided to measure both the addition of water and additives
to the pugmill.
Water and additive shall be added to ensure proper workability and;
(a)
(b)
Page 211 of 10
August 99
If more than one kind of aggregate is used, the correct amount of each kind of
aggregate to produce the required grading shall be proportioned separately in a
manner that will result in a uniform and homogenous blend.
21.4
MIXING
The Cold Overlay shall be mixed in a self-propelled mixing machine equipped with
a continuous flow pugmill capable of accurately delivering and automatically
proportioning the aggregate, bitumen emulsion, water and additives to a double
shafted, multiblade pugmill mixer capable of minimum speeds of 200 revolutions
per minute.
The mixing machine shall have sufficient storage capacity of aggregate, bitumen
emulsion and water to maintain an adequate supply to the proportioning controls.
The mixing machine shall be equipped with hydraulic controls for proportioning
the materials by volume to the mix. Each material control device shall be
calibrated, properly marked, preset and lockable at the direction of the
Superintendents Representative.
The mixing machine shall be equipped with a water pressure system and nozzle
type spray bars to provide a water spray immediately ahead of the spreader box.
The mixing machine shall be equipped with an approved filler feeder that provides
a uniform, positive, accurately metered, pre-determined amount of a mineral filler,
at the same time and location that the aggregate is fed.
21.5
SPREADING EQUIPMENT
The Cold Overlay mixture shall be uniformly spread by means of a controlled
spreader box conforming to the following requirements.
(a)
(b)
The spreader box shall have strips of flexible rubber belting or similar
material on each side and in contact with the pavement to prevent loss of
Cold Overlay from the box.
(c)
The spreader box shall have baffles or other suitable means, to ensure
uniform application on super-elevated sections and shoulder slopes.
(d)
The rear flexible stike-off blade shall make close contact with the pavement
and shall be capable of being adjusted to the various crown shapes so as
to apply a uniform seal coat.
LAYING
Page 212 of 10
August 99
The Cold Overlay shall not be placed if either the pavement or the air temperature
is below 13oC and falling. However, it may be laid when both the air and
pavement temperature is 10oC or above and rising.
Before laying the Cold Overlay, the pavement surface shall be cleaned by
sweeping, flushing or other means necessary to remove all loose particles of
paving, all dirt and all other extraneous material.
Before the Cold Overlay operations are commenced, the contractor shall give 24
hours notice to all residents, businesses and agencies by written notice detailing
streets and limits of work to be done and the hours of work.
The contractor shall also post in all streets to be worked upon 24 hours before
commencement of operations, notices with temporary no parking signs. These
signs shall also state the day of the week and the hours of no-parking.
Immediately before commencing the Cold Overlay operations, all surface metal
utility covers shall be protected by thoroughly covering the surface with an
appropriate adhesive and oiled or plastic paper. Covers are to be uncovered and
cleaned of Cold Overlay material by the end of the same work day. Hand tools
shall be available in order to remove spillage.
The mixture shall be uniform and homogenous after spreading on the surface and
shall not show separation of the emulsion and aggregate after setting.
Page 213 of 10
August 99
Adequate means shall be provided to protect the Cold Overlay from traffic until
such time that the mixture has cured sufficiently so that the Cold Overlay will not
adhere to and be picked up by the tyres of the vehicles.
21.7
21.8
21.9
MIX DESIGN
The contractor shall furnish to the Superintendents Representative the following
mix design tests of Cold Overlay before commencing operations.
(a)
(b)
0 - 5mm
(% Passing)
100
100
90-100
65-90
45-70
30-50
18-30
10-21
5-15
Consistency Test
Indicate water content required in the mix design to enable the Cold
Overlay mixture to flow 2.5-3.00cm using an approved test method.
(c)
(d)
Abrasion Test
Page 214 of 10
August 99
Adhesion Test
Furnish data indicating acceptable adhesion between the aggregate and
bitumen using an approved test method.
Page 215 of 10
August 99
Description
22.2
Supply of Materials
22.3
22.4
Foundations
22.4.2
Posts
22.4.3 Signs
22.5
Erection of Posts
22.5.1 Steel and Timber Posts
22.5.2 Foundations
22.5.3 Backfilling of Post Holes
22.6
Erection of Signs
22.7
Masking of Signs
ID 60022
Page 216 of 10
August 99
22.1
DESCRIPTION
This section covers the requirements for the handling, storage and erection of
signs and sign supports.
22.2
SUPPLY OF MATERIALS
All signs, posts, fittings and where applicable, masking materials as listed in the
Sign and Post Schedule will be supplied at the Council depot compound located
at XXX or at some other location agreed with the Superintendent.
Signs will be supplied to the Contractor on at least three weeks notice to the
Superintendent by the Contractor. All other materials, equipment and labour
necessary to erect the signs, including cement or concrete for post hole backfill
shall be supplied by the Contractor.
22.3
(b)
Vertically and clear of the ground with adequate care to protect the edges
of the signs.
(c)
(d)
Page 217 of 10
August 99
22.4
(ii)
Post tops are to be 50 10mm below the top edge of the signboard.
22.4.3 Signs
22.5
(i)
(ii)
(iii)
(iv)
The faces of the signs shall present an even surface free from
twists, cracks, indentations or any other faults after erection.
ERECTION OF POSTS
Details of post erection are shown on the Sign and Post Schedule.
Before the erection of posts proceeds, the Superintendents Representative
will review and confirm the required positions of all posts and signs.
Page 218 of 10
August 99
- 1625mm
- 2165mm
- 2800mm
- 3250mm
- 2700mm
- 4600mm
Page 219 of 10
August 99
22.5.2 Foundations
All posts shall be set in footings to the depths shown in the Sign and Post
Schedule. Foundation hole diameters shall be as follows:
For 32mm & 50mm Nominal Bore steel posts: 225mm diameter
For 80mm to 150mm Nominal Bore steel posts:
300mm diameter
For 180mm X 100mm Frangible Hardwood posts: 300mm diameter
Socket Size
50mm Nominal Bore
pipe
65mm Nominal Bore
pipe
The sockets shall be plugged at the bottom and shall protrude between
20mm and 30mm above the finished surface of the concrete foundation.
22.5.3 Backfilling of Post Holes
Backfilling of post holes shall not proceed until the Superintendents
Representative has reviewed and confirmed the adequacy of the post
holes.
Posts shall be installed to the depths shown in the Sign and Post Schedule.
(i)
(ii)
For 32 and 50mm Nominal Bore Steel Posts, the following shall
apply:
*
Posts carrying more than 0.6m 2 of sign area each are to have
two concrete collars each 150mm deep.
Page 220 of 10
August 99
(iii)
22.6
ERECTION OF SIGNS
Details of sign erection are shown on the Sign and Post Schedule.
22.6.1 Signs shall be attached to the post(s) or structures using the type and
number of fittings as specified in the schedule. When a sign is braced it
should be attached to the post at every intersection point between a post
and a sign bracing member.
Page 221 of 10
August 99
22.6.2 Where a sign assembly consists of two or more signs, the signs shall be
mounted in accordance with the sign assembly drawings.
22.6.3 Signs shall be mounted to:
(i)
(ii)
(ii)
the sign at the longer post is 2200mm minimum above the ground at
that point.
22.6.5 Where a sign is to be mounted on a utility pole with stainless steel straps,
the brackets shall be attached to the pole using stainless steel strapping
having a minimum width of 12mm and a minimum breaking strain of 6.5kN.
22.6.6 Where the drawings indicate that a sign is to be erected so as to face
oncoming traffic directly, it shall be mounted on posts which have been
rotated in accordance with the requirements of Clause 22.5.1, with the
exception of signs mounted on structures over traffic lanes.
22.6.7 Where signs are to be removed or relocated, as specified in the Schedule,
the Contractor shall dismantle the assembly and transport the signs, posts
and fittings to the specified new location or to the VIC ROADS Site
Compound as appropriate. Post holes shall be backfilled and compacted
to the finished surface. Relocated signs shall be erected in their new
position as specified.
22.6.8 After erection of each sign all stiffening bars are to be removed.
Page 222 of 10
August 99
22.7
MASKING OF SIGNS
Where indicated in the Schedule the Contractor shall arrange to mask the
nominated sign(s) with material supplied by Council.
Masking of signs shall consist of placing a black plastic sheet over the face of the
sign which shall be held in position by wire mesh over the sign.
Adhesive material shall only be applied to the plastic and not be applied to either
the front or rear face of the signboard.
Signs to be masked are marked m in the Sign and Post Schedule.
The size of the masking material and its method of attachment shall be such that
the sign is effectively and securely covered, either in whole or in part, as required,
at all times and under all conditions.
Page 223 of 10
August 99
General
23.2
Materials
23.3
Supply of Materials
23.4
Construction
23.5
Gates
23.6
Junctions
23.7
ID 60023
Page 224 of 10
August 99
23.1
GENERAL
This section covers the requirements for the construction of fencing at the
locations shown on the drawings or described in this specification.
Fences that are to remain in place but have been damaged by the Contractor
shall be repaired or replaced to the satisfaction of the Superintendents
Representative at the Contractors expense.
23.2
MATERIALS
Material for fencing shall conform with the following:
(a)
(b)
Page 225 of 10
August 99
Treated timber posts and stays shall be straight and of dimensions not less
than shown on the detailed drawings. Posts to be driven shall be square
ended, or shall be blunt pointed prior to treatment to a bevel angle not
exceeding 30 degrees.
(c)
(d)
(e)
Concrete Posts
Concrete posts shall be steel reinforced and of good commercial quality of
the lengths shown on the drawings.
(f)
Droppers
Timber droppers shall be sawn hardwood or pine free from cross grain and
large knots and of the length shown on the detailed drawings.
Bored hardwood droppers shall be of 50mm X 38mm nominal size timber.
Treated hardwood droppers attached without boring shall be not less than
35mm X 19mm section.
Page 226 of 10
August 99
Wire
Wire shall be galvanised and conform with the appropriate Australian
Standards and be of the gauge and type specified in the detailed drawings.
Fabricated wire fencing shall be of a commercial type. The width, mesh
and gauge shall be as specified or as shown on the detailed drawings.
(h)
Gates
Gates shall be good commercial quality of the type and dimensions
specified or shown on the detailed drawings.
(i)
Miscellaneous Materials
All ferrous bolts, nuts, ties, staples and fittings for fences and gates shall be
galvanised and of commercial quality and design.
Portland cement concrete shall be produced from commercially available
aggregates and cement and shall contain not less than 240kg of cement
per cubic metre. 1 part cement to 10 parts aggregate.
(j)
Page 227 of 10
August 99
23.3
SUPPLY OF MATERIALS
(Strikeout (a) or (b))
(a)
(b)
23.4
CONSTRUCTION
Fences shall be constructed true to the lines pegged on the ground. All logs,
stumps, saplings and undergrowth within 1 metre of the fence line, and all trees
which will interfere with proper construction of the fence shall be removed and
disposed of by the Contractor. Any high points which interfere with the placing of
wire or wire netting shall be cut down to provide the clearance shown on the
detailed drawings, any low spots shall be filled.
Fences shall be constructed in accordance with the drawings. All posts shall be
set in line so that the tops bone uniformly without sudden dips or irregularities.
Unless otherwise specified, surplus earth from holes and trimming shall be spread
within the road reserve and the area shall be left clean and tidy on completion of
the work.
Page 228 of 10
August 99
(a)
Page 229 of 10
August 99
(b)
(c)
(d)
(e)
Page 230 of 10
August 99
(f)
(g)
23.5
GATES
The Contractor shall install gates of the types and sizes specified, or shown on
the drawings. Gate posts shall be of the dimensions shown on the detailed
drawings and be firmly set into the ground to the depth specified. Each post shall
be fitted with a strut as shown on the detailed drawings. Tubular metal posts shall
be set in concrete as detailed. At gateways in wire netting fences, a timber sill
shall be set tightly between the posts and flush with the ground.
All gates shall be hung with hinges securely attached to the gate posts. Each
gate shall be fitted with a catch. For wire netting fences, gates shall be finished
so as to be rabbit proof when closed.
23.6
JUNCTIONS
Existing cross fences shall be connected to the new fences. Corner posts with
braces for every direction of strain shall be placed at the junction with existing
fences. The wire in existing fences shall be strained and securely fastened to the
posts.
Page 231 of 10
August 99
23.7
Page 232 of 10
August 99
General
24.2
Definitions
24.3
24.4
Materials
24.5
Construction Plant
24.6
Construction
24.7
Jointing
24.8
Test Rolling
24.9
Page 233 of 10
August 99
24.1
GENERAL
This section covers the requirements for insitu stabilisation of existing pavement
layers by the addition of cement, blended cement, lime or other specified
pozzolanic material. The requirements relate to preparation of existing pavement
materials, quality of additive, construction plant, and spreading, mixing and
compaction procedures.
24.2
DEFINITIONS:
Quicklime
Hydrated Lime
Equivalent Calcium
24.3
(a)
(b)
Page 234 of 10
August 99
24.3.2 Thickness
The thickness of the stabilised layer at any point shall be not less than the
thickness specified by more than fifteen (15) millimetres. The average
thickness of the layer over any one hundred (100) metre section for the full
carriageway width shall be not less than the specified thickness as
determined from measurements taken in accordance with the following:
The surface level of each completed pavement layer shall be checked
longitudinally and transversely for conformity with the specified
requirements at intervals not exceeding twenty (20) metres in the
longitudinal direction. At each location which is checked for longitudinal
level conformity, the surface level shall be checked in the transverse
direction at all of the following locations:
1.
2.
3.
Page 235 of 10
August 99
24.3.5 Shape
No point on the surface of the stabilised layer shall lie more than fifteen
(15) millimetres below a three (3) metre straightedge placed in any
direction on the surface.
24.4
MATERIALS
24.4.1 Cement
Cement shall be supplied by the Contractor and shall be General Purpose
Cement Type GB complying with AS 3972. The Contractor shall nominate
the type, brand and source of cement or blended cement.
The use of other pozzolanic additives shall be subject to prior
approval in writing by the Superintendents Representative
The Superintendents Representatives approval shall be obtained
prior to changing the source and quality of the nominated cement.
24.4.2 Quicklime
The equivalent calcium oxide content of quicklime shall be not less than
sixty per cent (60%).
The residue of quicklime after slaking shall not exceed thirty per cent
(30%).
At the time of spreading, quicklime shall comply with the grading
requirements specified in Table 1.
Table 1
Sieve Size
AS (mm)
9.5
4.75
2.36
Test Value
(% Passing)
100
95-100
85-100
Page 236 of 10
August 99
Bulk hydrated lime shall be dry and shall have been produced not more
than fourteen (14) days before delivery.
At the time of spreading, hydrated lime shall comply with the grading
requirements specified in Table 2.
Table 2
Sieve Size
AS (mm)
4.75
0.600
0.075
Test Value
(% Passing)
100
95-100
85-100
CONSTRUCTION PLANT
24.5.1 General
The Contractor shall provide and operate sufficient spreading, mixing,
watering and compacting plant to carry out the specified work.
Page 237 of 10
August 99
CONSTRUCTION
24.6.1 General
Construction includes the preparation of insitu materials, spreading and
mixing of additives and materials, and compaction, trimming and curing of
stabilised layer.
Unless otherwise specified, stabilisation work carried out each day shall be
completed across the full pavement width.
Stabilisation operations should only continue in the event of rain, if the
moisture content of the pavement is kept below modified optimum moisture
content.
Page 238 of 10
August 99
Page 239 of 10
August 99
24.6.4 Mixing
Mixing shall commence as soon as practicable after spreading of additive
and sufficient mixing shall be undertaken to ensure that all pavement
materials and additives are uniformly blended throughout the full depth of
the stabilised layer
The moisture content of the stabilised material at the time of mixing shall
be within the range eighty per cent (80%) to one hundred per cent (100%)
of the Modified optimum moisture content.
24.6.5 Compaction
Compaction of the mixed material shall commence immediately after
mixing and shall be carried out in a continuous operation from initial to final
rolling.
Compaction other than that required for surface preparation shall be
completed within two (2) hours of mixing cement additive. Unless
otherwise specified, compaction of pavement materials stabilised with
additives other than cement shall be completed on the same day that
mixing occurs.
Where necessary during compaction, the Contractor shall water the
material to maintain the moisture content within eighty per cent (80%) to
one hundred per cent (100%) Modified optimum moisture content.
24.6.6 Trimming
On completion of initial rolling, the stabilised material shall be trimmed to
the specified surface tolerances. Light applications of water may be
applied during this operation to replace evaporated moisture and to assist
in rapid achievement of a tightly knit surface.
Surface irregularities, deficiencies in level and high areas shall be rectified
by the Contractor within thirty (30) minutes of trimming. Within this period,
scarification, addition or removal of material, reshaping and recompaction
shall be permitted. Rectification after thirty (30) minutes shall be carried
out by replacing material with freshly stabilised materials as necessary.
The material trimmed off shall be cut to waste and shall be removed from
the site.
24.7
JOINTING
The work shall be organised such that longitudinal joints between compacted and
freshly mixed material are avoided. Transverse joints shall be formed where
Page 240 of 10
August 99
stabilisation operations have been halted for more than two (2) hours and at the
end of each days work. Longitudinal joints shall be constructed parallel to the
centreline of the carriageway and transverse joints at right angles to the
centreline.
Joints shall be formed by cutting back into the previously stabilised material to a
fully compacted section, over the full depth and width of the layer(s), and
continuing stabilisation from that point. The material disturbed during cutting back
shall be remixed and incorporated into the new work. Additional stabilising
additive shall be spread adjacent to the joint. Placement of additional additive
shall be deemed to be part of the joint preparation.
The level and shape of the surface at all joints shall be within the limits specified
in Clause 24.3.
24.8
TEST ROLLING
All layers areas shall be test rolled prior to the placement of any pavement
materials. The finished surface of filled areas shall likewise be test rolled. Any
unstable area detected shall be rectified by the Contractor using methods agreed
to by the Superintendent's Representative.
All layers shall be compacted such that no visible deformation or springing is
visible under the action of test rolling. Test Rolling shall be carried out by the
contractor in the presence of and to the satisfaction of the Superintendents
Representative by using; six (6) cubic metre truck fully loaded with approved
material or a vehicle of equivalent weight as agreed by the Superintendents
Representative.
Page 241 of 10
August 99
24.9
(b)
(c)
(d)
Page 242 of 10
August 99
General
The work shall be assessed for compliance with Scale A, Scale B, or Scale
C requirements for lot acceptance of compaction as specified in Clause
24.14. The calculation of density ratio shall be based on Modified
compactive effort. A lot shall consist of a single layer of work.
24.11.2
Scale A Requirements for Lot Acceptance of
Compaction
Acceptance of compaction will be based upon the characteristic value of
density ratio of lots. The number of tests per lot shall be six (6).
Acceptance and payment shall be in accordance with Table 3.
Table 3
Characteristi
c
Density
Ratio (Rc)
Assessment
Payment
More than
95.0%
Accept
100%
90.0 to 94.9%
Accept
(4Rc-280)%
Less than 90 %
Reject
Nil
24.11.3
Scale B Requirements for Lot Acceptance of
Compaction
Acceptance of compaction will be based upon the mean value of density
ratio of lots. The number of tests per lot shall be three (3). Acceptance
and payment shall be in accordance with Table 4.
Table 4
Page 243 of 10
August 99
Mean Value
of
Density
Ratio (Rm)
Assessment
Payment
More than
95.0%
Accept
100%
90.0 to 94.9%
Accept
(4Rm-280)%
Less than 90 %
Reject
Nil
24.11.4
Compaction
comply with the specified requirements but which is not less than that shown in
Table 5.
Page 245 of 10
August 99
Table 5
Test
Grading
Additive Content
Uniformity of spreading
Compaction
Lot size to be within the range
of:
Min: 500 m2
Max: one days production
Course/Layer
Chainage
From
Distribution
Rate
(kg/m2)
Compacte
d
Thickness
(mm)
Requirements
for Testing
and
Acceptance
of
Compaction
To
Scale ***
Page 246 of 10
August 99
Standard of Work
25.2
Grassing
25.3
25.4
Standards Required
ID 60025
Page 247 of 10
August 99
25.1
STANDARD OF WORK
Prior to sowing the area shall be prepared to provide an evenly consolidated
seedbed, free of depressions. After sowing the area shall be maintained in a
continuing state of growth and good appearance. Growth shall be strong,
vigorous and healthy but not necessarily lush. The turf shall have a dense cover
with multiple tillering, branching of stolons, and a deep root system. Thatch
accumulation is to be minimised. Any bare or damaged areas shall be rectified
promptly.
25.2
GRASSING
25.2.1 Amendments and Fertilisers
Agricultural lime is to be applied to the area at a sufficient rate to modify the
soil pH to a level of at least 6.5.
The following fertilisers are to be applied at sowing:
NPK (8:11:10) granular fertiliser
Trace element mix
500 kg/ha
250 kg/ha
20%
20%
20%
40%
Page 248 of 10
August 99
Only certified seed is to be used, and bag labels showing purity and
germination levels are to be produced on request.
25.2.4 Sowing Method
Two alternative methods of sowing will be permitted.
(a)
(b)
25.2.5 Watering
Following sowing of the seed, the surface is to be kept moist during the
germination and establishment phase.
25.3
Page 249 of 10
August 99
The mowing height of the mature turf surface will be 40mm with frequency
being at least once per week.
With any mowing, no more than one-third of the leaf length is to be
removed.
The grass shall be cut in even swathes. The formation of windrows is not
permitted. Grass cuttings shall be spread evenly over the mown area
without the formation of clumps.
Mowing equipment shall be reel-type mowers, kept in a good and properly
adjusted condition at all times.
25.3.4 Disease Control
During the establishment period, strict observation is to be kept to detect
the incidence of seedling disease. If evident two applications of Ridomil
MZ fungicide is to be applied at the rate of 15 kg/ha, 10 days apart.
Any other potential disease outbreaks are to be identified by an
experienced pathologist and correct control procedures carried out as
recommended.
25.3.5 General Maintenance
Any areas that are not providing a full grass cover will be either reseeded,
or returfed to ensure that a complete cover is developed.
Any depressions which develop will be topdressed out using a sand similar
to that used for topsoil rootzone. This is to be determined by soil testing
prior to use. A maximum depth of topdressing at any one time is to 10mm.
If additional topdressing is required, it shall only be applied when the grass
has fully grown through the previous dressing.
Page 250 of 10
August 99
STANDARDS REQUIRED
It is expected that after 12 months the oval will have a fully grassed surface,
uniform in texture, and botanical composition. Volunteered species are to
constitute less than 3% of the sward. All necessary steps will be taken to achieve
this.
Page 251 of 10
August 99
General
26.2
26.3
26.4
26.5
26.6
26.7
26.8
Vegetation Removal
26.9
Page 252 of 10
August 99
26.1
GENERAL
This specification contain the requirements for appropriate approach to the proposed
project or works to ensure the environment is protected.
No vegetation shall be removed from site unless shown on the drawings or as directed
by the Contract Supervisor.
The contractor shall ensure that all employees and subcontractor are aware of all
requirements under this specification.
26.2
Page 253 of 10
August 99
26.4
The contractor shall walk the route in conjunction with the Contract Supervisor prior to
commencement of work.
This is to ensure the contractor has a good understanding of the environment.
To minimise the impact of construction on vegetation, they should identify:
the limits of vegetation removal. (Tape is to be used to mark trees for removal);
significant or protected vegetation, habitat areas and sensitive areas which should be
protected from disturbance using marking tape;
identify the location of noxious and environmental weeds; (refer to Clause 26.3) and
indicate the exact location of stockpiles, plant compounds and access roads.
26.6
Stockpiles, construction compounds and machinery parking and turnaround sites should
be located as approved according to the Environment Management Plan or as directed
by the Contract Supervisor and be clear of any vegetation.
This may be permitted on nearby private land, with Council and landholders approval.
Do not store materials and machinery under trees as this compacts the soil and may
kill trees and small plants ( refer to Clause 26.2);
Delineate extent of stockpile areas using tape, fence or large logs to prevent the
stockpile area from spreading;
Do not push stockpiles into surrounding vegetation.
Page 254 of 10
August 99
26.7
The contractor shall remain within the construction zone and avoid disturbance to any
vegetation and embankments.
The Construction Zone is the area clearly marked where all construction activities take
place (such as the area stripped for road construction, stockpile areas, compounds,
access routes, etc.).
Vegetation shall be guarded by a temporary protective fence. The fence shall comprise
of paro web mesh fence and star pickets, with a top of support wire. The fence shall be
placed as shown on the plan or as directed by the Contract Supervisor. This will be done
at no cost to Council. The fence shall not be removed at practical completion unless
directed by the Contract Supervisor.
26.8
VEGETATION REMOVAL
The contractor shall clear only the minimum amount of vegetation required for
construction (marked vegetation within the construction zone) and that required for
safety.
Fell trees into the construction zone, not into undisturbed vegetation.
Removed vegetation shall be chipped for mulch and respread on exposed areas to
spread the local seed.
Removed vegetation shall not be burnt.
26.9
Page 255 of 10
August 99
Upon removal, the site must be replanted as directed by Contract Supervisor using a
minimum of five trees of either the same species or as agreed with Contract
Supervisor of works. Where the original site is unsuitable then a preferred site within
the vicinity of the original site will be nominated by Contract Supervisor. The
replanting and a 6 month maintenance period on the planted trees will be carried out
at the contractors own cost.
26.10
CLEAN MACHINERY
The contractor shall clean all dirt and weeds from all machinery prior to transporting to
site. Work shall start from weed free area and work towards areas with weeds and/or
soil disease to prevent their spread.
26.11
FIRE PREVENTION
Contractors should refer to and be familiar with the Country Fire Authority Act 1951.
26.12
Trees and other plants on Shire controlled land should be preserved wherever possible.
Careful pruning of overhanging branches can often reduce the need for tree removal.
The contractor shall consider the following points before any action is taken.
1. Safety of staff, property and road users;
2. All staff carrying out the works are adequately trained and competent in the use
of chainsaws and are approved by the Contract Supervisor;
3. The effect of the tree removal on the appearance of the roadside;
4. The historical and cultural significance of the tree.
5. Ensuring that the necessary permits have been obtained
Minimise the dumping of wood. Retain stumps and logs for animal shelter wherever
possible. Light material can be chipped for mulch.
Page 256 of 10
August 99
The contractor shall avoid bark injury below the cut, by using the three cut method on
all but the smallest branches.
1.
The under cut
2.
The upper cut (to remove the branch)
3. The final trim cut: Cut close to, but not flush with the main trunk or limb. Always
cut on the outside of the branch collar - this assists the tree in wound healing
(callusing) and provides a protective barrier against decay.
Where possible hollow bearing trees should only have weight reduction of the crown so
that minimal loss of tree hollows occurs.
Where a limb 200mm or greater is to be removed this work is to be undertaken by a
qualified arborits.
Trees outside the construction zone that require removal shall not be removed by using
machinery to push over the tree.
26.13 RECTIFICATION WORKS
In the event of unauthorised removal of vegetation being carried out by the contractor or
subcontractor, the appropriate reinstatement including planting, soil preparation and
mulching shall be carried out to a standard as directed by the Contract Supervisor.
The cost of rectification work will be borne by the contractor.
Page 257 of 10
August 99