Académique Documents
Professionnel Documents
Culture Documents
The State of Louisiana has given permission to use the planning documents (includingmaps)
developed in coordination with State, Parish, and Federal personnel. The State asked that
users remember they were developed in planning workshops and are not final. Due to the
time frame, support documents and training have not yet been developed. Informationon the
maps is current and correct. The scenario used to guide the planning included a "Hurricane
Pam" strikingall 13 parishes in Southeast Louisianawith an approximate storm surge of 16-20
feet and was based on a composite of most of the existing models from various government and
academic sources.
Ascension 77,000
Assumption 23,000
Jefferson 455,000
Lafourche 90,000
Orleans - 485,000
Plaquemines 27,000
St. Bernard 67,000
St. Charles 48,000
St. James 21,000
St. John 43,000
St. Tammany 191,000
Tangipahoa 101,000
Terrebonne 105,000
\
Memorandum ~ IEM.
Re: Development History of the Southeast Louisiana Catastrophic Hurricane
Plan Documentation
The current version of the Southeast Louisiana Catastrophic Hurricane Plan Documentation
is Revision 5, dated January 5, 2005. It was delivered to FEMA HQ, FEMA Region VI,
and the Louisiana Office of Homeland Security and Emergency Preparedness (LOHSEP)
for review and comment. Revision 5 contains information developed during Phase 1 (July
16-23,2004) and Phase lA (November 29-December 3,2004) of the Southeast Louisiana
Catastrophic Hurricane Planning Workshop.
These two sections were released as separate files to FEMA on August 27,2005.
Following Phase 1B, on August 23-24, 2005, the Southeast Louisiana Catastrophic
Hurricane Temporary Medical Care Supplementary Planning Workshop was held. As a
result, Temporary Medical Care (Section 14) was updated with notes taken at the
workshop. This section was submitted to FEMA on September 1,2005, as Update 1. It was
replaced on September 3,2005, as Update 2, incorporating additional appendices along
with updates to the Concept of Operations (CONOPS).
The period of performance for the contract that funded development of these documents was
originally September 30, 2005. In early August 2005, FEMA Region VI requested an extension to
November 30, 2005, to give more time to the contractor to integrate sections of the document
developed in July and August 2005 (the July workshop was originally scheduled for April 2005).
The extension was agreed to by the COTR in conversation with the contractor but has not been
formalized in a memorandum to the Contracting Officer at FEMA HQ.
- ueel1
'
If Il1for1l1a t
1011/tet ,
Matrix of Planning Topics and ESFs ~
In the summer and fall of 2004 emergency management and disaster responders from the local,
state and federal levels met to develop a comprehensive, integrated plan to guide response and
recovery efforts in the event a major hurricane hits southeast Louisiana causing catastrophic
damage, injury and loss of life.
More than 250 people worked together for more than a week in Jul/ to develop several
component or "functional" plans addressing specific dimensions of an integrated response effort.
In August, 2004, leaders from three of the planning groups2met to review their plans and design
a follow-up workshop to further develop and enhance their plans. These three leadership teams
drafted the objectives and agendas for a smaller, more focused workshop, which was held
November29 - December3, 2004.
The attached table lists the various topics or issues for which plans were developed during the
Louisiana Catastrophic Hurricane Planning Project in addition to projected topics for later
discussion. Ofthe "Topics Proposed for Future Planning" listed at the bottom of the following
matrix, only Transportation was discussed at the subsequent workshop in July, 2005.
Participants .at a workshop in August 2005 discussed aspects of Temporary Medical Care not
covered in earlier workshops.
1 State and federal personnel met July 16-18to develop pre-landfall plans. Local personnel joined them July 19-23
to develop post-landfall plans.
2 The three leadership teams meeting on August i 8, 2004 were those planning for Temporary Medical Services,
Sheltering, and Temporary Housing. .
;::
"' ~ ""§
._;:;
Q)
-
.f'
..
>-.:::
~ 0
E ~ u ~ ;:; '2'-
~~
",.Vj 1:: ::E ~
"en ~3
::: '" ~;:;~ E.-
r/J
::: :::~
0 §;:;~o~
0 u 0. -y;:;oZ
"" 0 0. ~E'-;::~
0:2: .-
0 ~ X! :2: :I:'s: g. -£ ..<::"E ~ ~ .c u IS
.~
~ i3
.- .. g?
0.-.5 01) >-.
u e-..'" r/J 0:; Q) ~
'" "'''
N en e;:; en ~'" E ~>-."""
'j
.. :::;S:" ~ ::: ",r/J 1$:I:en Q) ~-~1$ r/J""-
8. ;:; u ~ ~ ~ u::: .. u 8 en ""'.~"3" >-. u <¥ ~ "' E
en
::: ~ :.=.5 ~
..DOl) '"
.. en "'
'" E 15 :'='-
en en..D>..D § ~ ~"enQ).~ i5 i:?
'" :.=
..D 01)
:::u0 ~
~ 0 E
;:;:::.!:: "';:; '" ;:; \) .. :-;::'" 01)'" ::: ;:; 0 '" x
Plannin2 Topics E-< U ~ ~ "'" ~ :2::I: " ~ r/J :J 0:2: ~" ~ ~ 1" ~
Pre-Landfall
Annex A: Incident Action Plans
Annex B: Louisiana State Hurricane Checklist
Annex~: FEMA Region VI Hurricane X X X X X X X X X X X X X X X
Checklist
Annex D: Pre-Landfall Concept of Support
Post-Landfall
Main Planning Topics
Debris X X X X X .X
Schools X X X X X
Search and Rescue X X ? X X X X X ? X
Sheltering X X X X X X X? X
Temporary Housing X X X X X X X?? X
Temporary Medical Care X X X X X X X X ?? X
Discrete Planning Topics
(The "?','s represent ESFs that may be applicable to the topic indicated depending on how the ESF is defined in the new NRP.)
3 The Louisiana Catastrophic Hurricane Plan was developed under the Federal Response Plan. Under that plan some Emergency Support Functions
(ESFs) had different names or did not exist. The differences are listed below.
ESF #5 was Informatipn & Planning ESF #13 did not exist
ESF #6 was Mass Care ESF #14 did not exist
ESF #8 was Health & Medical Services ESF #15 did not exist
ESF#10 was HazardousMaterials
ESF #11 was Food
4 This includes movement of people ITom Search and Rescue to Temporary Medical Care to Sheltering to Temporary Housing.
August 28, 2005 Page 2 of2
Prepared By
IEM, Inc.
Four United Plaza
8555 United Plaza Blvd., Suite 100
Baton Rouge, LA 70809
Prepared For
DHS/FEMA
500 C Street S.W.
Washington, DC 20472
LOHSEP
7667 Independence Boulevard
Baton Rouge, LA 70806
Prepared Under
FEMA BPA HSFEHQ-04-A-0288, Task Order 001
IEM/TEC04-070 r5
January 5, 2005
This document is for reference only. Readers should not construe this document as
representing official policy or regulations. The functional plans contained in this document
were produced during the Southeast Louisiana Catastrophic Hurricane Planning
Workshops (July 16–23, 2004, and November 29–December 3, 2004). These functional
plans have been edited for clarity. The information contained herein is current as of
December 3, 2004, and is subject to change.
This page intentionally left blank.
Southeast Louisiana Catastrophic Hurricane Plan
TABLE OF CONTENTS
1.0 PRE-LANDFALL 1
2.0 UNWATERING 5
9.0 DEBRIS 45
10.0 SCHOOLS 55
12.0 SHELTERS 71
1.0 Pre-landfall
1. Situation
a. General
i. A catastrophic hurricane is threatening southeast Louisiana.
b. Assumptions
i. Resources and support may be needed to respond to another event occurring
in United States territory.
ii. Resources identified will be available for the State of Louisiana.
iii. The State of Louisiana has identified a shortage in resources required to
evacuate and support shelters, including the special needs population.
c. Organization
i. Louisiana Office of Homeland Security and Emergency Preparedness
ii. DHS/FEMA Region VI
iii. DHS/FEMA Headquarters
2. Mission
a. The joint mission is to conduct the necessary pre-landfall activities that will help
save lives, minimize injuries, and position assets in the numbers and locations that
will sustain immediate response activities for 72 hours.
b. The Louisiana Office of Homeland Security and Emergency Preparedness
mission is to take necessary actions to provide Parish leadership with the
necessary information so they can make timely evacuation and preparedness
decisions; give the media the necessary messages that will guide the citizens
during pre-landfall; and provide DHS/FEMA Region VI with an updated resource
request no later than 72 hours before the initial effects of the storm reach the
coastal Parishes.
c. The DHS/FEMA Region VI mission is to take the necessary actions to increase
the regional Federal preparedness; coordinate with DHS/FEMA Headquarters to
provide the teams and resources identified by Louisiana Office of Homeland
Security and Emergency Preparedness; and have resources in place 24 hours prior
to tropical storm force winds affecting staging areas.
d. The DHS/FEMA Headquarters mission is to facilitate the development and
dissemination of common operational information between agencies within DHS,
applicable DHS/FEMA regions, and coastal states; support the regional and local
pre-landfall media strategy; and develop and execute a resource/team distribution
plan that will equitably support the applicable coastal states and move assets
appropriately to increase levels at specific mobilization centers once the storm is
confirmed to enter the Gulf.
3. Execution
a. Concept of Operations
i. Joint Concept of Operations
1) When the National Weather Service and National Hurricane Center
forecasts indicate a hurricane may strike Louisiana, DHS/FEMA and the
Louisiana Office of Homeland Security and Emergency Preparedness will
2.0 Unwatering
1. Situation
a. General
i. Because of the topography, New Orleans proper exists as a bowl, higher on
the edges and tapering lower nearer the center. That bowl is surrounded by
several other similar areas that are also enclosed and protected by systems of
levees and floodgates. The entire Metropolitan New Orleans Area is
dramatically affected by a catastrophic hurricane depositing a great deal of
water, which is trapped within these bowls, flooding the city and surrounding
areas.
b. Assumptions
i. Greater New Orleans is inundated with at least 10 feet of water in the levee
systems.
ii. Due to the magnitude of the event and the loss of local and State resources in
a catastrophic hurricane, the U.S. Army Corps of Engineers will receive a
mission assignment from DHS/FEMA to unwater.
iii. Because much response and recovery activity depends on the successful
unwatering of bowls (at least to the +2 foot elevation), the Unified Command
will place a very high priority on transportation, equipment, and personnel
needed to support the unwatering mission.
iv. There will be surviving residual knowledge of the levee system and the pump
stations after hurricane passage.
v. Due to the magnitude of the contamination of water during an event of this
size, the U.S. Environmental Protection Agency will grant variances on water
quality standards. However, sampling will be required to determine the types
of material released for follow-up work, such as maintaining worker safety
and monitoring of long-term impacts.
vi. Local aerial reconnaissance assets will be assigned to other tasks and will not
be available for surveying levees.
vii. For the purpose of this plan it is assumed there are no levee breeches.
c. Organizations
i. Local
1) Levee Boards
2) Parish Directors
3) Public Works
ii. State of Louisiana
1) Department of Environmental Quality
2) Department of Transportation and Development
3) Louisiana Office of Homeland Security and Emergency Preparedness
4) National Guard (subject to National Defense Deployments)
5) Public Works
iii. Federal
1) Department of the Army (normally as a last resort)
2) Environmental Protection Agency
3) DHS/FEMA
2. Mission
a. The U.S. Army Corps of Engineers will work with DHS/FEMA, State, and local
governments to unwater the water entrapped by the levee system in the Greater
New Orleans area as a result of a catastrophic hurricane; repair 80% of pumping
stations within 60 days of start of work; and initiate repair of hurricane protection
systems.
3. Execution
a. Concept of Operations
i. General
1) Unwatering efforts of the Greater New Orleans area through opening gates
and breaching levees will result in the lowering of the water level to +2
feet within approximately one week of the start of work. This timeline is
highly speculative due to the number of preconditions needed to complete
work (e.g., transportation of equipment and personnel, access to the work
area, and access to necessary material).
2) Details of unwatering operations are found in the U. S. Army Corps of
Engineers Unwatering Plan, Greater Metropolitan Area, New Orleans,
Louisiana of August 18, 2000. At the +2 feet level, about one quarter of
the city of New Orleans, closest to the Lake Pontchartrain, will remain
under water. Additional efforts at unwatering will be delayed until pumps
are dried and repaired and associated generators for non-standard voltages
and 25-cycle equipment are available. Due to the capacity required, use of
pumps shipped in from other areas will have minimum impact on
unwatering except for localized areas. Similarly, access and drainage
realities prevent the use of stationary dredges as an unwatering resource.
As a result, the installed pumps will remain the primary method of
unwatering. Large areas of standing water will remain for at least 30 days.
ii. The U.S. Army Corps of Engineers will conduct assessments to:
1) Determine the status of the levee protection system. Aerial or satellite
surveillance will be the primary method of initial assessment. All local
capability to assess the levee status will be used.
2) Determine availability of workforce, including skilled and unskilled labor
and specialized skills needed for pump and levee system available
resources at local, State, and Federal levels.
3) Determine availability of necessary heavy equipment such as earthmovers
for breaching levees.
4) Determine availability of additional material needed for unwatering and
pump repair (e.g., drying fans and generators).
iii. As required, the U.S. Army Corps of Engineers will take expedient actions to
lower water levels by opening gates and breaching levees in a prioritized
manner (as outlined in the tasks below). As soon as water levels are reduced
viii. ESF-3 will coordinate with U.S. Coast Guard to issue a notification and take
other measures to prevent endangerment of personnel due to water flow from
breeches.
ix. ESF-3 will repair breeched levees to prevent flooding from a second event and
to facilitate remaining pump out.
x. ESF-3 will coordinate with U.S. Environmental Protection Agency for the
handling of debris removed from channels at pump intakes.
xi. ESF-3 will rehabilitate pumps.
c. Coordinating Instructions
i. Due to the probable evacuation of local U.S. Army Corps of Engineers
personnel and the need for such personnel to take care of their families, the
Memphis District U.S. Army Corps of Engineers will most likely be tasked to
carry out the U.S. Army Corps of Engineers functions in this plan.
ii. If appropriate, the Interagency Levee Task Force will be implemented.
iii. The U.S. Environmental Protection Agency will conduct sampling of water
throughout the process.
d) Marsh boats
4) Pumps
a) Temporary power
b) Temporary pumps
c) Drying equipment
d) Parts for both pumps and associated generators (see the U.S. Army
Corps of Engineers Unwatering Plan)
e) Fuel and transport
ii. Sources for the critical resources are not in place and are highly situation
dependent. Much will be obtained through U.S. Army Corps of Engineers
contracting.
c. Personnel
i. TBD
xv. Other Federal, State, and local hazardous materials-related resources will be
made available over time, as circumstances permit.
xvi. Non-traditional approaches to hazardous materials response may be required
to be successful (e.g., transportation by boat will be required to access many
areas).
c. Organizations
i. The Louisiana State Emergency Operations Plan, Annex H, Hazardous
Materials (direct quotes noted in this plan by italics) describes functional
responsibilities for responding to hazardous materials emergencies as listed
below:
“A. The owner of the substances that are creating the problem has the
primary responsibility for dealing with the consequences of a HazMat
release, whether by mobilizing internal response resources, hiring a
private contractor, or reimbursing Federal, State and local authorities
for their response activities.
B. The Louisiana State Police (LSP) have the primary responsibility at
the state level for HazMat incidents. The Superintendent of the
Louisiana State Police shall implement, administer, and coordinate the
services, programs, and resources required under this function.
C. The Emergency Coordinator designated by the Superintendent shall
be responsible for the liaison and coordination of all response efforts
and emergency services provided under this Annex.
D. State agencies supporting the LSP in this function are identified in
the Emergency Function and Responsibility Chart.”1
1
State of Louisiana, Office of Emergency Preparedness. Emergency Operations Plan. March 2001.
2
State of Louisiana, Office of Emergency Preparedness. Emergency Operations Plan. March 2001.
hurricane, the State of Louisiana and the United States Government will
exercise appropriate discretion in the application and assignment of liability
and responsibility toward public and private entities involved in hazardous
materials releases experienced as a result of the disaster.
2. Mission
a. The mission is to minimize the impact of hazardous materials released into the
environment as a result of a catastrophic hurricane on disaster response and
recovery personnel, members of the public, and public and private lands and
property.
3. Execution
a. Concept of the Operations
i. Phase I
1) No hazardous materials response activities will be possible during the
extremely unsafe conditions occurring during a catastrophic hurricane.
ii. Phase II
1) Immediately following the hurricane’s passage over the area, life safety
issues will likely take precedence over hazardous materials containment
and abatement response actions.
2) Hazardous materials operations-trained personnel will accompany search
and rescue personnel when seeking out survivors to provide subject matter
expertise and technical assistance should hazardous materials be
encountered.
3) Over time, more conventional hazardous materials response roles may be
anticipated.
b. Specific Tasks to Lead, Support, and Coordinate Agencies
i. State of Louisiana
1) Louisiana State Police (lead agency)
a) “When the State Police are notified of a HazMat emergency that
requires their assistance, they will respond as soon as possible with
the resources required by the situation, using the Incident Command
System. When a situation arises that cannot be solved by immediately
available resources, the Louisiana State Police may notify the LOEP
[Louisiana Office of Emergency Preparedness], which will alert the
appropriate State and Federal authorities, and put the State EOC
[Emergency Operations Center] into operational status.”
b) “All state agencies having a role in HazMat response and recovery
will provide support as required through their emergency coordinator
at the emergency operation center or directly to the on-site Louisiana
State Police incident commander, as circumstances may dictate.”3
2) Louisiana Department of Environmental Quality (support agency)
a) The Louisiana Department of Environmental Quality will be charged
with a variety of hazardous materials-related functions including
radiological (primary agency), and support functions including:
3
State of Louisiana, Office of Emergency Preparedness. Emergency Operations Plan. March 2001.
4
State of Louisiana, Office of Emergency Preparedness. Emergency Operations Plan. March 2001.
2. Mission
a. The mission is to provide billeting for all initial response and recovery personnel
who will be brought into Louisiana as a result of a catastrophic hurricane.
3. Execution
a. Concept of Operations
i. Phase I—Quarter-boats6 (see DHS/FEMA’s Use of Corps’ Quarter-Boats,
U.S. Army Corps of Engineers, Mississippi Valley Division, Emergency
Management)
1) Within five days of activation of the first phase, housing on quarter-boats
for up to 250 responders will be in place at the U.S. Army Corps of
Engineers Port Allen, Louisiana, facility.
2) Within 10 days, housing for an additional 250 (total limit of 500)
responders will be available.
ii. Phase II—Base Camp Phase
1) Base camps can be set up and will provide as much housing as is needed
for up to 1,500 people per camp.
5
Billeting is defined as food and lodging for response personnel.
6
Quarter-boats is a U.S. Army Corps of Engineers’ term for special-purpose barges built during the 1990s
to house work-crews that install, maintain, and replace revetments along the Mississippi River banks.
i. TBD
6. Contingency Plan
a. Possible alternate locations for quarter-boats include:
i. St. Francisville, Louisiana
ii. Old River Locks, Lettsworth, Louisiana
iii. Alexandria, Louisiana
5 . 0 P o w e r, Wa t e r, a n d I c e D i s t r i b u t i o n
1. Situation
a. General
i. Southeast Louisiana has been impacted by a catastrophic hurricane, causing a
need for emergency power, water, and ice for victims.
b. Assumptions
i. Thousands of victims lack power, water, and ice.
ii. In the core area affected by the disaster, it will require more effort to deliver
ice, water, and power than to evacuate the families to shelters. It will not be
possible to provide logistical support to such victims.
iii. In the core area, public health risks and the inability to provide logistical
support will be so great that the affected Parishes will issue a mandatory
evacuation order.
iv. Most personnel evacuated from the core area will have to be sheltered or
placed in temporary housing for a relatively long period.
v. Based on historical precedents, approximately 10% of the affected population
will be self-sustaining.
vi. Servicing shelters will be a major aspect of achieving the mission. Four-
hundred to 500 thousand victims (the estimate of the Sheltering Committee)
will need to be supplied in shelters. These shelters will not be in the core area.
Triage areas will be established for the core areas. These medical and triage
sites will need to be sustained.
vii. The per person absolute minimum amount will be 1 gallon of potable water
and 8 pounds of ice per day.
viii. General power restoration will be under the control of the Louisiana State
power companies, municipalities, and cooperatives.
ix. Since most emergency generators and associated switching and control
facilities throughout the area are installed at or below the ground level, these
generators will not be available for emergency power in the immediate
aftermath of flooding.
x. Disruption of transportation due to debris and road damage will be a major
limiting factor to initial distribution.
xi. Since power will be minimal in areas of distribution, availability of fuel will
be a limiting factor in determining distribution, including access of victims to
the distribution points.
xii. Competition for refrigerated space for mortuary use may be a limiting factor
for ice storage and distribution. Use of refrigerated space for things such as
mortuaries and the storage of drugs and food will reduce the capacity to
provide ice for disaster victims.
c. Organizations
i. Local
1) Parish Offices of Homeland Security and Emergency Preparedness
2) Parish Presidents
ii. State
1) Louisiana Department of Natural Resources
2. Mission
a. The mission is to provide water and ice to disaster victims and emergency power
generators at critical facilities.
3. Execution
a. Concept of Operations
i. General
1) There will be three areas of concern.
a) There will be a core area (area I) where victims cannot be supported
on a sustained basis. Victims will need to be evacuated from this area.
For the mission to succeed, the evacuation of these victims must be
outside of the sustainable area (area II) as described below. However,
the number of victims involved will be so great that ice and water (but
not power) distribution will remain a major issue. Since it will be a
considerable time before these victims may return to their homes,
sustainment will be required over a relatively long term.
b) In the surrounding area—the sustainable area (area II)—largely
affected by flooding, victims may be logistically sustained by Parish,
State, and Federal efforts. Due to transportation limitations, focus in
this area will be on the re-supply of shelters. Victims will be expected
to obtain water and ice at shelter distribution points.
c) Beyond the sustainable area, wind damage will prevail. Once debris is
cleared and power restored, there will be only a limited demand for
water and ice and the area may be considered self-sustaining (area III).
Power restoration in this area will be much quicker since outlets and
electrical boxes will not have to be cleaned and restored.
2) DHS/FEMA will stage water, ice, and generators. Planning and readiness
teams and installation teams will be staged based on commodity
requirements for the State.
3) Staging areas for water and ice will be determined by State officials. The
primary staging area will be Camp Beauregard, Pineville, Louisiana.
Distribution points will be selected by the Parishes.
4) Planning for distribution at the Parish level must be done based on the
situation using all available resources and priorities set by the Parish.
5) The U.S. Army Corps of Engineers water contractor estimates the ability
to deliver 500,000 to 625,000 gallons of water within 24 hours, from 2
million gallons per day within 48 hours and daily thereafter.
6) The U.S. Army Corps of Engineers ice contractor estimates the ability to
deliver between 500,000 and 2 million pounds of ice within 24 hours.
Within 72 hours, the capability will increase to 3 to 4 million pounds per
day and daily thereafter.
ii. Emergency Power Restoration
1) Priorities for providing generators and power to critical facilities have
already been set by the State and will be used to determine initial
distribution. These priorities will be set based on Parish input.
Assessments should be maintained by each Parish and provided to the
State. The general priorities for restoration are as follows:
a) Hospitals
b) Nursing Homes
c) Police Stations/911 Centers/Communications Centers
d) Fire Stations
e) Water Treatment Plans
2) DHS/FEMA will stage generators at Camp Beauregard, Pineville,
Louisiana, before landfall. Distribution will depend on preliminary
assessments at the Parish level. Logistics readiness reports are provided
daily to reflect on-hand response resources.
3) Although the U.S. Army Corps of Engineers has done power assessments,
the assessments will have to be verified for an actual event. A critical
aspect of the verification will be having a point of contact at the facility
level to allow assessors access. This point of contact, along with facility
location, and other critical information will be passed to the U.S. Army
Corps of Engineers via the State Emergency Operations Center.
4) Since generator installation and hookup by the U.S. Army Corps of
Engineers will be limited to 10 to 25 hookups each day under current
plans, DHS/FEMA Region VI will task the U.S. Army Corps of Engineers
to issue additional contracts as necessary to meet the extra needs.
5) Federal controlled generators will be installed by U.S. Army Corps of
Engineers contractors.
6) Installation of emergency power will be accelerated where Parishes have
pre-identified critical facilities and assessed potential power requirements.
iii. Water and Ice Distribution
1) Water is contracted in liter bottles but the U.S. Army Corps of Engineers
contracts allow the government to specify bulk deliveries. Bulk delivery is
preferred for supplying shelters. Contracts are written to deliver a specific
amount on the first day growing over several days to a sustainable level.
2) The U.S. Army Corps of Engineers will task ESF-1 to provide certified
containers for bulk storage of water; the U.S. Environmental Protection
Agency/ESF-10 will certify these containers and test the water.
iii. Daily reports for status of water and ice consumption will be made by the
Parishes to the State Emergency Operations Center for passing to DHS/FEMA
and the U.S. Army Corps of Engineers. This figure should be available no
later than 1800 each evening to allow adjustments to be made for the
following day.
iii. Communications between ESF-3 and the points of contact will be critical, so
the Emergency Operations Center will attempt to provide multiple points of
contact.
6 . 0 Tr a n s p o r t f r o m Wa t e r t o S h e l t e r
1. Situation
a. General
i. Southeast Louisiana has been impacted by a catastrophic hurricane, causing a
need for rescue and sheltering of thousands of victims.
b. Assumptions
i. Search and rescue will perform immediate rescue of victims and transport
them to high ground, wherever that may be found. The search and rescue
forces will take responsibility of moving such victims from high ground to a
Search and Rescue Operating Base. A volunteer flotilla organized by the U.S.
Coast Guard Auxiliary and under the operational control of the Search and
Rescue Command will transport victims from the Search and Rescue
Operating Base to land based transportation for further transportation to the
Temporary Medical Operations Staging Areas.
ii. Medical triage capability will be in place at the Search and Rescue Operating
Base to prioritize evacuation of victims.
iii. Search and rescue operations will continue for seven days, and then operations
will shift to search and recovery.
iv. Victims will be transported from the affected areas to the Temporary Medical
Operations Staging Areas with a target of 100,000 per day. The expected first
day search and rescue load will be approximately 22,000 victims. Three
hundred fifty thousand in the first four days (half by search and rescue and
half self-rescued) can be expected.
v. Four Search and Rescue Operating Bases will be established. This number
may vary depending on circumstances.
vi. Three Temporary Medical Operations Staging Areas will be established:
Louisiana State University (Baton Rouge, Louisiana), Nicholls State
University (Thibodaux, Louisiana), and Southeastern Louisiana University
(Hammond, Louisiana).
c. Organizations
i. Local
1) Parish Office of Homeland Security and Emergency Preparedness
ii. State of Louisiana
1) Louisiana Department of Corrections
2) Louisiana Department of Transportation and Development
3) Louisiana Department of Wildlife and Fisheries
4) Louisiana National Guard
5) Louisiana State Police
iii. Federal
1) ESF-3/U.S. Coast Guard
2) ESF-1/U.S. Department of Transportation
3) ESF-6/American Red Cross
4) National Disaster Medical System
5) U.S. Department of Defense
6) U.S. Fish and Wildlife Service
2. Mission
a. The mission is to manage the flow of victims from Search and Rescue Operating
Bases (at the water-land interface), through Temporary Medical Operations
Staging Areas, to shelters, thence to temporary housing, in the aftermath of a
catastrophic hurricane in Louisiana.
3. Execution
a. Concept of Operations
i. General
1) Given the number of expected victims rescued by search and rescue
operations and those self-rescued, a major limiting factor in executing this
plan will be the shortage of transportation facilities. The Louisiana
National Guard will be tasked to numerous missions and may not be able
to meet the need for transportation of victims. Sufficient transport to move
personnel to Temporary Medical Operations Staging Areas may not be
available for 48 to 72 hours.
2) It will take hundreds of buses per day to transport victims to Temporary
Medical Operations Staging Areas from Search and Rescue Operations
Bases or the land-water interface. The number of victims to be transported
is expected to wane after 72 hours. The following table illustrates an
example of the number of victims transported daily.
7 . 0 Vo l u n t e e r a n d D o n a t i o n s M a n a g e m e n t
1. Situation
a. General
i. A catastrophic hurricane has made landfall in southeast Louisiana resulting in
heavy structural damage due to high winds, a significant storm surge that
overtopped levees, and riverine flooding as a result of heavy rainfall. This
event will create a need to coordinate donated goods and volunteer services.
b. Assumptions
i. Unprecedented heavy casualties have been reported.
ii. This plan addresses unsolicited donations only.
iii. Donations
1) Catastrophic disasters will create a need to coordinate donated goods and
volunteer services. It is assumed that not every disaster incident will
generate donated goods and services. However, when circumstances
warrant, a united and cooperative effort by Federal, State, and local
governments, volunteer organizations, the private sector, and donor
community is necessary for successful management.
2) It is not the State’s intent to alter, divert, or otherwise impede the normal
operation or flow of goods or services through volunteer organizations,
but to help coordinate offers of donated goods and services. Many
volunteer organizations have operational networks set up to receive,
process, and deliver needed goods and services to disaster victims. The
Louisiana Office of Homeland Security and Emergency Preparedness,
through its Donations Coordination Team and its Volunteer Coordination
Team, will work closely with volunteer organizations that have agreed to
operate in accordance with this plan. The Louisiana Office of Homeland
Security and Emergency Preparedness will look to those organizations to
provide a means to implement the donations management system and
coordination of emergent volunteers.
3) The Louisiana Office of Homeland Security and Emergency Preparedness
has entered into a Statement of Understanding with Adventist Community
Services, wherein Adventist Community Services is designated by the
Louisiana Office of Homeland Security and Emergency Preparedness to
perform management and distribution of donated goods and services.
4) The Louisiana Office of Homeland Security and Emergency Preparedness
and the State of Louisiana assume immunity from liability as described in
Section S735, Paragraph A of the Louisiana Emergency Assistance and
Disaster Act of 1993.
5) The Director of the Louisiana Office of Homeland Security and
Emergency Preparedness is responsible for maintaining this plan. The plan
will be reviewed, exercised, and updated periodically according to the
basic plan. The volunteer agencies shall integrate their planning efforts in
the development, maintenance, implementation, and testing of this plan
and its procedures.
iv. Local Needs
1) Local needs for donated goods and volunteers will be coordinated through
the State Emergency Operations Center using established procedures.
v. Reception Points/Congestion
1) The Donations Coordination Team will coordinate with the Department of
Transportation and Development to allow authorized shipments of donated
goods for processing. Requested donations will proceed to pre-designated
areas.
2) The screening process for receiving donated goods utilized by the
Department of Transportation and Development will be implemented.
Donated materials without approved destinations will be routed to the
nearest donation warehouse locations to be processed.
3) Donation warehouse locations will be located near primary interstate entry
points in the State, in conjunction with weigh stations serving as
Department of Transportation checkpoints.
vi. Warehouses
1) The preliminary processing warehouses will be located near points of
entry—the Department of Transportation and Development weigh
stations.
2) Preliminary inventory sorting will be conducted at these locations. Usable
donations will be transported to centralized donation centers, or to
appropriate areas for distribution.
3) Warehouse locations will be coordinated with the Donations Coordination
Team and the Office of Economic Development.
4) Processing at weigh stations will be conducted by the Department of
Transportation and Development.
5) Security will be provided by local law enforcement.
vii. Volunteers
1) Volunteers will be a valuable resource in executing this plan.
2) Spontaneous volunteers who are not assigned or attached to any agency,
church, religious organization, medical organization, first responders, or
skilled and non-skilled labor will respond from outside the affected area.
3) The influx of unsolicited first responders and other highly skilled
volunteers will likely be ongoing and unpredictable.
4) Many times, disaster victims will be volunteers.
5) Volunteers fall under human resource compliance and will be given the
same benefits as employees of the organization.
6) Unsolicited volunteers will be responsible for their own feeding, lodging,
and maintenance. However, the Volunteer Coordination Team will work
actively with member agencies to assign unsolicited volunteers.
7) Requests for local resources and volunteers will be directed to the State
Emergency Operations Center and routed to the Donations Coordination
Team/Volunteer Coordination Team using established procedures.
8) The Volunteer Coordination Team will be working with its member
agencies to assign unsolicited volunteers.
c. Organization
2. Mission
a. The Louisiana Office of Homeland Security and Emergency Preparedness, in
coordination with voluntary agencies, will provide victims of disasters with as
much support as possible by effectively and efficiently channeling unsolicited
donations from individuals or from public and private sector organizations and
emergent volunteers.
3. Execution
a. Concept of Operations
i. In accordance with the Louisiana Emergency and Disaster Act of 1993, the
Governor is responsible for meeting the dangers to the State and people
presented by emergencies or disasters. The law designates the Adjutant
General as Director of the Louisiana Office of Homeland Security and
Emergency Preparedness. The Governor, through the Louisiana Office of
Homeland Security and Emergency Preparedness shall determine
requirements of the State and its political subdivisions for food, clothing,
shelter, and any other necessities, including procurement and pre-positioning
of supplies, medicines, materials, and equipment. This donations plan and its
implementing procedures will be activated when any significant event causes
spontaneous flow of or a major need for donated resources within the State of
Louisiana.
ii. The Louisiana Office of Homeland Security and Emergency Preparedness will
establish a Volunteer Coordination Team to coordinate volunteer
organizations, including Louisiana Voluntary Organizations Active in
Disaster, and other partner agencies—organizations in the management,
credentialing, and assignment of unsolicited volunteers.
b. Specific Tasks to Lead, Support, and Coordinate Agencies
i. The Director of the Louisiana Office of Homeland Security and Emergency
Preparedness, will assign a State Donations Coordinating Officer and other
staff as necessary to work with representatives from Louisiana Voluntary
Organizations Active in Disaster, thus comprising the principal Donations
Coordination Team. The State’s role will be to support local government.
ii. The Director of the Louisiana Office of Homeland Security and Emergency
Preparedness will activate the Donations Management plan and Volunteer
Coordination procedures when a significant event causes a spontaneous flow
of, or a major need for, donated resources.
iii. Voluntary agency representatives in the Donations Coordination Center will
retain supervision of their agency personnel. The Donations Coordination
Team will work together in a collaborative effort to manage donated goods.
iv. Volunteer agencies will provide a liaison to the Volunteer Coordination Team
and Volunteer Registration Center.
v. The Volunteer Coordination Team will coordinate registration and/or referral
of emergent volunteers with government and voluntary agencies.
vi. First responders include the emergency medical service, emergency medical
technicians, volunteer firefighters, urban search and rescue, law enforcement,
dog teams, and community emergency response teams.
1) Spontaneous first responder volunteers will be strongly encouraged to
register with the call center.
2) The Donations Coordination Team Public Information Officer will
coordinate with the Joint Information Center to inform unsolicited first
responders and other skilled volunteers of registration procedures through
the Joint Information System.
3) Spontaneous first responder volunteers, registered through the call center,
will be referred to the appropriate emergency support function group for
assignment.
vii. Volunteers will furnish contact information and other pertinent information to
the Volunteer Coordination Team in order to provide an effective
communication process.
viii. The Donations Coordination Team and the Volunteer Coordination Team
will recommend activation of a call center within 24 to 48 hours after impact
to document offers of volunteer services.
ix. The call center will be established at a location where electric power and
telephone service will be unlikely to be interrupted.
x. The call center team needs to identify and designate (in writing) workspaces
with telephones and computer capabilities.
xi. Daily reports will be required to provide volunteer resources to other agencies
and organizations to meet needs.
xii. Based on volume, the Donations Coordination Team and the Volunteer
Coordination Team will evaluate the need to either increase or decrease call
center capacities.
xiii. Call center setup, operational procedures, and scripts are identified in the
DHS/FEMA Donations Toolkit.
c. Coordinating Instructions
i. Donations Management staff will operate from a Donations Coordination
Center as part of the State Emergency Operations Center. The State Donations
Coordinating Officer will be seated in the State Emergency Operations
Center, and will stay in close contact with the Donations Coordination Team.
Liaison personnel from participating organizations will be in all other
donations operations facilities (e.g., staging areas and distribution centers).
ii. Because it is extremely important that only carefully stated, factual
information be disseminated, a joint media management and coordination
system will be established. All media information will be coordinated through
the Donations Center Coordinator, the Operations Chief, and Public
Information Officer utilizing the Joint Information System/Joint Information
Center. Local, State, and Federal government news releases will be
2. Mission
a. The mission is to provide phased entry procedures to manage the return of
residents to areas evacuated after the impact of a catastrophic hurricane.
3. Execution
a. Concept of Operations
i. Re-entry will be operated in phases, highlighting the need for first responders
and other recovery personnel to return before the general public.
1) Phase I (First Response Phase): This phase will provide for the immediate
entry of first responders, damage assessors, and other organizations or
personnel to assist with search and rescue, damage assessment, and
hazardous materials identification. During this phase, the identification
and establishment of safe zones will be completed.
a) Rapid needs assessment of damaged areas to establish safe zones will
be conducted by:
i) Responding Agencies (First Responders)
1. Louisiana Department of Transportation and Development
2. U.S. Environmental Protection Agency
3. U.S. Army Corps of Engineers
a. Unwatering
b. Debris assessment
c. Clearance
4. U.S. Army Reserve
ii) Internal Parish Assessment Teams
iii) Local search and rescue personnel
b) National critical and strategic assets should be assessed/restored
beginning in Phase I.
c) The following tasks must be completed before moving on to Phase II:
i) Usable roads, waterways, railways, and airfields (along with
capacity for runways) have been identified.
ii) Dry zones have been identified.
iii) Potentially dangerous wildlife has been contained.
iv) Safe zones have been established and hot zones (both land and
water) have been secured.
v) Search and rescue will continue into Phase II.
2) Phase II (Critical Infrastructure Response): During this phase, critical
infrastructure such as public utilities, public safety communications, and
hospitals will be established. By the end of this phase, enough of the
9.0 Debris
1. Situation
a. General
i. A catastrophic hurricane has impacted southeast Louisiana, resulting in
millions of cubic yards of debris, including household hazardous waste and
toxic waste.
b. Assumptions
i. For the purpose of example, it is assumed that 30 million total cubic yards of
debris has been generated. Of this total amount of debris, 237,000 total cubic
yards are hazardous household waste and an unknown amount is hazardous
toxic waste.
ii. It is assumed that over 600,000 residential structures were impacted, of which
77% were destroyed.
iii. It is assumed that over 6,000 commercial structures were impacted, of which
67% were destroyed.
iv. The New Orleans metropolitan area is currently under water.
v. Emergency debris clearance will begin in the outlying areas and structure
demolition will be needed on a large-scale basis.
vi. Presidential declaration for Category A and B has been made requesting full
funding authority.
vii. Human remains are not part of the debris mission; however, human remains
will alter the debris mission.
viii. Empty coffins will be treated as debris.
ix. In the affected area, the typical debris will be construction and demolition at
70%, with vegetative debris at 30%.
x. Direct Federal assistance will be requested to supplement long-term local
debris removal efforts.
xi. Demolition of damaged structures will be required.
xii. Local resources will be used for initial emergency road clearance.
xiii. The limited land space, landfill capacity, and wet, saturated soil conditions
will limit burial as a disposal option.
xiv. Natural Resources Conservation Services will perform debris removal from
non-navigable waterways as resources allow.
xv. The U.S. Army Corps of Engineers will survey and certify depths and
obstructions on navigable waterways.
xvi. The U.S. Army Corps of Engineers will handle debris removal from
navigable waterways, and, if mission assigned, clear non-navigable
waterways.
xvii. The U.S. Coast Guard, while conducting over-flights for search and rescue,
will aid in the identification of major obstructions on navigable waters. The
U.S. Coast Guard will verify and replace navigational aids to reopen
navigable waters.
xviii. All livestock carcasses will be handled by Louisiana Department of
Agriculture and Forestry with requested cooperation from the U.S.
2. Mission
a. The Louisiana Office of Homeland Security and Emergency Preparedness will
coordinate operations involved to clear, remove, and dispose of debris from areas
impacted by a catastrophic hurricane so that response and recovery operations can
be accomplished in a timely manner, while minimizing public health impacts and
delays in economic recovery.
3. Execution
a. Concept of Operations
i. All Federal, State, and local response agencies will operate under the National
Incident Management System. The Louisiana Office of Homeland Security
and Emergency Preparedness will activate a Debris Task Force that is
composed of appointed members from the Louisiana Office of Homeland
Security and Emergency Preparedness; the Louisiana Department of
Environmental Quality; the Louisiana Department of Culture, Recreation, and
Tourism; the Louisiana Department of Health and Hospitals; the Louisiana
Department of Transportation and Development; the Louisiana Department of
Agriculture and Forestry; and Federal agencies (DHS/FEMA, the U.S. Army
Corps of Engineers/ESF-3, and the U.S. Environmental Protection Agency
/ESF-10). The designee of the Adjutant General will co-chair the Debris Task
Force with the DHS/FEMA Deputy Public Assistance Officer for Debris. The
Debris Task Force may be composed of multiple working groups as
appropriate. For a catastrophic hurricane, there will be working groups for
inundated and non-inundated areas. The operation will be divided into phases:
1) Phase I: Clearance (Day 1–5)
a) Phase Ia: Inundated Area—As water recedes in each area
b) Phase Ib: Non-inundated Area—Estimates of 5.7 million cubic yards
of debris: 3 days
2) Phase II: Removal/Reduction/Disposal
a) Phase IIa: Inundated Area—When water recedes
b) Phase IIb: Non-inundated Area—As soon as sites are identified
ii. State and local resources will perform emergency debris clearance.
iii. Federal, State, and local resources will aid in removal, reduction, and disposal.
iv. Reduction will be accomplished by recycling, incineration, grinding, and other
approved methods.
v. Disposal options for debris include on-site treatment, disposal, and/or
landfills. Various types of landfills will be utilized including permitted
hazardous waste, construction and demolition, or solid waste. In addition,
emergency non-permitted disposal sites may be authorized by the Louisiana
Department of Environmental Quality. On-site treatment of hazardous waste
may include use of thermal desorption units. On-site disposal may include the
use of Resource Conservation and Recovery Act vaults. The collection and
disposal of hazardous household waste will be tasked to ESF-10.
c. Personnel
i. The following personnel template may be used as a guide. Numbers are
provided for example only.
1) Louisiana Office of Homeland Security and Emergency Preparedness,
Deputy Debris Officer, Debris Task Force Coordinator
a) Phase I
i) Inundated Area: Deputy Debris Ops Officer and 10 Project
Officers
ii) Un-inundated: Deputy Debris Ops Officer and Project Officers
b) Phase II
i) Inundated Area: Deputy Debris Ops Officer and 30 Project
Officers
ii) Un-inundated: Deputy Debris Ops Officer and 30 Project Officers
2) DHS/FEMA Public Assistance (to include Permanent Full Time, Stafford
Act Employees, and Technical Assistance Contractors)
a) Phase I
i) Inundated (Clearance: 8 staff members): Infrastructure Branch
Chief, Public Assistance Officer, Deputy Public Assistance Officer
for Debris, Deputy Public Assistance Officer for Operations,
Debris Advisor, and Debris Specialists.
ii) Un-inundated (Clearance: 15 staff members): Debris Advisors, and
Debris Specialists.
b) Phase II
i) Inundated (Removing/Reduction/Disposal: 50 staff members):
Debris Advisors and Debris Specialists, Debris Monitors, Public
Assistance Coordinators, Project Officers, and Technical
Specialists.
ii) Un-inundated (Removing/Reduction/Disposal: 350 staff members):
Debris Advisors and Debris Specialists, Debris Monitors, Public
Assistance Coordinators, Project Officers, and Technical
Specialists.
3) U.S. Environmental Protection Agency
a) Phase I
i) Inundated (Clearance: 15 staff members): Environmental
Protection Agency On-Scene Coordinators, Superfund Technical
Assessment Response Team, and Emergency Rapid Response
Services
ii) Un-inundated (Clearance: 3 staff members): Environmental
Protection Agency On-Scene Coordinators, Superfund Technical
Assessment Response Team, and Emergency Rapid Response
Services
b) Phase II
i) Inundated (Removing/Reduction/Disposal: 500 staff members,
includes hazardous materials activities): Environmental Protection
Agency On-scene Coordinator, Environmental Protection Agency
7
Estimate based on 2:1 ratio personnel to trucks.
8
Estimate based on Hurricane Andrew (Florida) with a 2:1 ratio personnel to trucks.
10.0 Schools
1. Situation
a. General
i. A catastrophic hurricane has made landfall in southeast Louisiana. Its arrival
resulted in heavy structural damage due to high winds, a significant storm
surge that overtopped levees, and riverine flooding as a result of heavy
rainfall. Damage to schools and thousands of relocated children create a need
for emergency educational services.
b. Assumptions
i. Extensive damage was done to schools in many of the Parishes affected by the
hurricane. In many cases the damage is severe enough that it will take an
extended period of time to repair or rebuild the schools.
ii. Families in many Parishes will be displaced from their homes for an extended
period of time due to home damage, even after floodwaters subside. These
families will be living in shelters, temporary housing, or alternate housing in
areas outside their home Parish for an extended period.
iii. In some cases, school records for children in affected Parishes will be
permanently lost because of a catastrophic hurricane. For others, a backup of
those records exists, but it will take an extended period to access them.
iv. The combination of riverine flooding due to heavy rainfall and storm surge
from the hurricane will result in flooding of many roads, limiting access to
schools for assessment and repair in many areas until floodwaters subside.
v. Much of Orleans, Jefferson, and Plaquemines Parishes and parts of St.
Bernard Parish will only be accessible by water until levees are breached
when floodwaters have receded to normal levels.
vi. Large quantities of hazardous waste, both industrial and household, will be
released as a result of hurricane wind and flooding, resulting in potential
contamination of land surrounding schools, as well as potential contamination
of structures and contents coming in contact with flood waters.
vii. Since students and faculty are dispersed, an evaluation must be conducted to
match student location and human and material resources in a safe location.
viii. Education services will be provided by local education agencies.
ix. Existing schools in host Parishes may not be able to handle the influx of
displaced students (both public and non-public), and will therefore need
additional resources.
x. Temporary sheltering and temporary housing patterns will impact the
schooling needs and should be looked at together.
xi. Laws and rules, such as the examples listed below, may impact educational
services and, therefore, be suspended temporarily or revised as a result of the
disaster.
1) Teacher certification
2) Attendance
3) Testing
4) School accountability
5) Federal and State funding
6) Purchasing processes
7) Court order desegregation consent decrees
8) Data collection/records
xii. Crisis counseling will be needed statewide to help children deal with the
disaster.
xiii. Some school systems may exist in name only.
xiv. Media, phone banks, and web sites may be used to disperse information to
the public regarding recovery of the educational system. This is to include
coordination between various agencies (e.g., local education agencies, local
Offices of Homeland Security and Emergency Preparedness, the Louisiana
Department of Education, the Louisiana Office of Homeland Security and
Emergency Preparedness, and DHS/FEMA).
xv. The money to execute this plan will be available.
xvi. The Louisiana Educational Emergency Operation Center will be formed in a
disaster.
c. Organization
i. Federal
1) Lead Agency
a) Department of Education
2) Support Agencies
a) Department of Agriculture
b) Department of Commerce
c) Department of Defense
d) Department of Health and Human Services
e) Department of Homeland Security
f) Department of Housing and Urban Development
g) Department of Labor
h) Department of the Interior
i) Department of Veterans Affairs
j) Environmental Protection Agency
k) General Services Administration
l) Tennessee Valley Authority
ii. State of Louisiana
1) Lead Agency
a) Department of Education
2) Support Agencies
a) American Red Cross
b) Board of Regents
c) Department of Health and Hospitals
d) Department of Social Services
e) Division of Administration
f) Louisiana Office of Homeland Security and Emergency Preparedness
g) Louisiana State Police
iii. Parish
1) Lead Agency
a) Public local education agencies
2) Support Agencies
a) Catholic Diocese
b) Nonpublic local education agencies
c) Parish Office of Homeland Security and Emergency Preparedness
iv. Volunteer
1) Louisiana Volunteer Organization Active in Disasters
2. Mission
a. The mission is to restore delivery of educational services to children whose
schooling was disrupted following landfall of a catastrophic hurricane in southeast
Louisiana.
3. Execution
a. Concept of the Operations
i. The restoration of educational services for the displaced population will occur
in four phases: Pre-Disaster, Initial Assessment, Response and Stabilization,
and Long-term Recovery.
1) Phase I: Pre-Disaster
a) All local education agencies must have a disaster recovery plan, which
includes a line of authority.
b) A critical educational records maintenance procedure must be
established by the local education agencies, in coordination with the
Louisiana Department of Education.
c) All local education agencies will be required to establish a procedure
for securing and retrieving appropriate educational records as a part of
a disaster recovery plan.
d) Local education agencies must initiate a communication plan that
includes contact information for key personnel.
e) The Louisiana Department of Education, the Board of Regents, and
local education agencies will assess as much as possible the areas that
could be used as educational facilities.
2) Phase II: Initial Assessment
a) The Louisiana Educational Emergency Operation Center will be
activated.
i) The Louisiana Department of Education and Board of Regents will
establish the Louisiana Educational Emergency Operation Center
to coordinate the re-establishment of educational services for the
displaced population. (Potential sites include Baton Rouge,
Shreveport, and Monroe.)
b) Initial damage information will be gathered through normal processes
from the Parish Emergency Operations Center to the Louisiana
Educational Emergency Operation Center. Additional information will
be requested as needed from local education agencies.
c) Procedures for contacting staff:
i) Local education agencies
ii) School district administrations
DHS/FEMA
Local Office of
Homeland Security Local Education
and Emergency Agency
Preparedness
ii. The local education agency will provide the Louisiana Educational
Emergency Operation Center with their shortfalls, which will assist in filling
those needs with State and Federal support (e.g., teachers, books, facilities,
support staff, food services, fuel, and transportation).
iii. The media will be used to disseminate information regarding the
establishment and delivery of educational services.
iv. ESF-2 will provide support in the priority and restoration of communication
services. For example, call centers can be developed or expanded.
b. Special Assistance
i. Medical
1) Immunization
2) Additional school nurses
3) School-based health clinics for routine medical care
4) Grief and trauma training for staff
ii. Students with Disabilities
1) Individual Disabilities Education Act and Americans with Disabilities Act
compliancy
2) Wheelchairs, medical beds, special transportation, trained
paraprofessionals, auditory and vision assistance, and assistive learning
devices
3) English Language Acquisition certified staff
iii. Equipment and Supplies
1) Specialty books (e.g., auditory transcript, Braille, and large print books)
c. Personnel
i. Educational personnel will be required based on a 20:1 student-to-teacher
ratio. This includes certified support staff.
ii. Teacher personnel will come from displaced teachers, former teachers, retired
teachers, emergency certified teachers, pre-service teachers, and other
displaced college graduates who can obtain temporary certification.
iii. Non-certified support staff will come from displaced paraprofessionals,
displaced support staff, and members of the general population.
iv. Many existing rules and regulations may be waived, but it is not the intention
of this plan to waive criminal background checks or drug tests for school staff.
v. The Louisiana Educational Emergency Operation Center will be staffed by the
Louisiana Department of Education and the Board of Regents, allowing
consideration for a 24-hour operation.
ii. Local education agencies directly impacted will perform the following tasks:
1) Execute a disaster and recovery plan.
2) Collect and secure records.
3) Reestablish school leadership and safe location.
4) Assess the initial damage.
5) Report damage assessment to the emergency management agency.
6) Continue to assess and maintain communications.
7) Upon request, provide student records to requesting local education
agency.
iii. Once notified by the Louisiana Educational Emergency Operation Center of
potential student impact, the local education agencies indirectly impacted will
perform the following tasks:
1) Assess available student capacity.
2) Assess available resources and instructional materials.
3) Assess transportation.
4) Assess staff and funding resources
5) Prepare for increase in student enrollment.
6) Notify shelters and temporary housing of enrollment procedures.
7) Enroll additional students.
8) Request student records through the Louisiana Educational Emergency
Operation Center.
9) Evaluate capability based on current situation and determine the course of
action for the delivery of educational services.
10) Identify shortfalls to local emergency operation center.
11) Maintain ongoing execution between local education agencies and the
Louisiana Educational Emergency Operation Center.
l2) Deliver educational services.
iv. The Louisiana Department of Education will serve as the lead agency in
providing coordinated support services to local education agencies.
Supporting agencies may include, but are not limited to, local emergency
management agencies, local education agencies, the Board of Regents, the
Louisiana Office of Homeland Security and Emergency Preparedness,
DHS/FEMA, and the U.S. Department of Education.
v. The Board of Regents will serve as the lead agency in providing the facilities
needed for the Louisiana Educational Emergency Operation Center.
Supporting agencies may include, but are not limited to, Parish Offices of
Homeland Security and Emergency Preparedness, local education agencies,
the Louisiana Department of Education, the Louisiana Office of Homeland
Security and Emergency Preparedness, DHS/FEMA, and the Louisiana
Division of Administration.
vi. Local emergency management agencies will serve as the lead agency in filling
local needs and coordinating requests for needs that could not be provided at
the local level. Supporting agencies may include, but are not limited to, local
education agencies, the Louisiana Department of Education, the Board of
Regents, the Louisiana Office of Homeland Security and Emergency
Preparedness, and DHS/FEMA.
vii. The Louisiana Office of Homeland Security and Emergency Preparedness will
serve as the lead agency in filling State and unmet local needs and for
coordinating requests for needs that could not be provided at the State level.
Supporting agencies may include, but are not limited to, Parish Offices of
Homeland Security and Emergency Preparedness, local education agencies,
the Louisiana Department of Education, the Board of Regents, and
DHS/FEMA.
viii. DHS/FEMA will serve as the lead agency in filling State requested unmet
needs. Supporting agencies may include, but are not limited to, all Federal
agencies through the emergency support function (ESF) structure.
b. Communications Requirements
i. The Louisiana Educational Emergency Operation Center will serve as the
focal point of communication. The following tools will be the main means of
communication in the areas indicated:
1) Computers via the World Wide Web will be the primary means of
communication for data and official requests.
2) Telephones (both landline and wireless) will be the primary means of
voice communication.
3) The Louisiana Educational Emergency Operation Center hotline will be
the primary means of receiving and collecting information from the
educational certified staff.
4) Backup means for data and official requests will be by fax.
5) Backup means for voice communication will be amateur radio operators.
6) The U.S. Postal Service may be used for identification of address changes.
7) The media will be used to disseminate information from the Louisiana
Educational Emergency Operation Center on the location and recruitment
of educational staff and to provide general information to the public.
8) Louisiana public information officers will be used to coordinate and
disseminate information in conjunction with the joint information center.
9) The Louisiana Public Broadcast System (open broadcast, closed circuit)
will be used to disseminate information.
10) Shelters and temporary housing will be used as points to disseminate
information, particularly when to register, and for identification of
educational staff.
2. Mission
a. After initial assessment, timely execution of search and rescue operations in order
to minimize loss of life to persons unable to reach safe shelter outside of the
affected area prior to landfall of a catastrophic hurricane.
3. Execution
a. Concept of the Operations
i. The commitment of State, Federal, and local resources under a unified
command structure utilizing the National Incident Management System in a
unified effort to rescue the highest number of human victims in the shortest
length of time. Search and rescue will include all air, ground, and waterborne
searches for lost or missing persons and the rescue of endangered, sick, or
injured persons. The lead State agency is the Department of Wildlife and
Fisheries. The lead Federal agency is the U.S. Coast Guard for water rescue
and ESF-9 for urban search and rescue. The Search and Rescue Command is
comprised of these agencies. The Parish Office of Homeland Security and
Emergency Preparedness Director will coordinate requests for assistance with
the Louisiana Office of Homeland Security and Emergency Preparedness
operations personnel for mission response.
ii. Search and rescue resources of all types (including urban search and rescue,
helicopter-aquatic, and swift-water) will be needed for response DHS/FEMA,
Emergency Management Assistance Compact, the Louisiana Office of
Homeland Security and Emergency Preparedness, and the Search and Rescue
Command will establish resources necessary to effectively and efficiently
deploy and support their mission.
iii. Search and rescue operations will utilize time-phasing concepts in deploying
teams and resources into all affected areas based on situational requirements.
iv. Levees will be established launching points for search and rescue operations
for a catastrophic hurricane.
v. Phase I: Pre-Landfall. Search and Rescue Command will perform the
following tasks:
1) Identify all available internal and external resources for search and rescue
operations (all levels).
2) Maintain situational awareness (all levels).
3) Stage initial search and rescue response resources where applicable (all
levels).
4) Develop an action plan that is specific to the event.
5) Evaluate resource capabilities.
6) Identify shortfalls and request additional resources.
vi. Phase II: Landfall. Search and Rescue Command will perform the following
tasks:
1) Continue to maintain situational awareness.
2) Continue to evaluate resource capabilities.
3) Identify shortfalls and request additional resources.
vii. Phase III: Post-Landfall. Search and Rescue Command will perform the
following tasks:
1) Assess and evaluate search area using:
a) High-resolution overflight
b) Initial water-based assessment
2) Plan to deploy resources.
a) Evaluate search area.
i) Identify bases of operations.
1. Appropriate number of bases of operations will be established.
2. Bases of operations will be mobile/dynamic.
ii) Sectors will be defined by search area.
b) Decide to deploy resources to specific areas.
3) Continuously evaluate safety of rescue area (for search and rescue
operations personnel).
4) Inbound rescue platforms will attempt to deliver supplies to non-emergent
victims.
5) Identify and deploy resources and volunteers.
6) Continue to evaluate resource capabilities.
7) Identify shortfalls and request additional resources.
8) Coordinate and evacuate rescued persons.
9) Follow chain of custody of rescuees as determined by Unified Command.
viii. Phase IV: Transition from Rescue to Recovery shall be approved by the
Louisiana Office of Homeland Security and Emergency Preparedness when
all rescue sectors have been cleared of apparent survivors.
b. Specific Tasks to Lead, Support, and Coordinate Agencies
i The appropriate representative for each Parish will be responsible for
coordinating local resources to accomplish search and rescue operations.
ii. Given the severity of the hurricane, a State of Emergency has been declared,
and all local resources for search and rescue may be exhausted.
iii. The lead agencies will prepare for and respond to people in need of rescue.
iv. The specific tasks they will follow are below:
1) Respond, identify shortfalls, and plan to fill those shortfalls.
2) Identify and establish geographical locations of control (Bases of
Operations) and populate those sectors with personnel and supplies to
rescue stranded persons.
3) At the end of each day, measure activities, plan, and reprioritize for the
following day.
v. Support agencies will supply resources for the rescue effort.
vi. Coordinating agencies will assist the lead agencies with command and control
of overall operation and assist the support agencies with the distribution of
scarce resources.
1) Coordinating State Agency: Louisiana Office of Homeland Security and
Emergency Preparedness
a) Louisiana Department of Health and Hospitals
2) Coordinating Federal Agency: DHS/FEMA
a) ESF-8 (Medical)
b) ESF-6 (Mass Care)
c. Coordinating Instructions
i Coordination of instructions and reports will be accomplished utilizing the
National Incident Management System as approved by the Unified Command.
Strategy for implementing the action plan and specific missions by supporting
agencies will be communicated and coordinated as specified in the Incident
Action Plan.
ii. In order to meet continued operational requirements, status reports shall be
submitted to the Unified Command at the end of each operational period as
specified in the Incident Action Plan.
iii. The map in Search and Rescue Appendix A from the Office of State Police
may serve as a baseline for the geographic divisions of the Bases of
Operations.
iv. Individual Parishes or segments of Parishes may be used to delineate actual
bases of operations according to need.
initial assessment indicates that the Parish is severely damaged and is not
capable of requesting assistance. The relief will be obtained through mutual
aid from unaffected Parishes, State, and Federal assistance. Resources, such as
personnel, assets, fuel, food, water, and spare operational equipment, will be
coordinated through the Unified Command. Support identified shall be for the
use of response personnel and initial care of victims. Bases of Operations will
be determined by situational environment and established in specific
geographic sectors. Identified needs for the Bases of Operations in each sector
are described in Search and Rescue Appendix B.
b. Special Assistance
i. Medical Support Required
1) Primary medical assistance will be required at each base of operations.
2) The first responders will provide limited first aid, which will require
resupply at the bases of operations.
3) Rotary wing assets with medical assistance will be required to support
search and rescue operations.
ii. Shelter/Transportation Coordination for Victims
1) ESF-6 will provide a shelter coordinator for rescued victims.
2) ESF-1 will provide transportation of rescued victims.
iii. Tactical Air Traffic Control
1) ESF-1 will provide Tactical Air Traffic Control
c. Personnel
i. See Search and Rescue Appendix B.
12.0 Shelters
1. Situation
a. General
i. A catastrophic hurricane made landfall in southeast Louisiana, resulting in
thousands of victims requiring public shelter.
b. Assumptions
i. For the purpose of this plan, a total of 57,896 people are assumed to require
public shelter prior to landfall. The assumed number of evacuees seeking
public shelter outside the affected area prior to landfall is summarized by
sector below:
ii. Additional people who do not initially evacuate but survive the storm will be
seeking public shelter because their homes have been destroyed or will require
extensive repair to be made livable. Some number of persons rescued from
water-bound areas will require shelter. Residents who evacuated to
Mississippi will seek to return to shelters in Louisiana at some point. Some
number of residents who evacuated prior to landfall, but whose homes have
been destroyed, or will require extensive repair, will seek public shelter at
some point for a period of time. For the purposes of this plan the total number
of people requiring shelter post-landfall is estimated at 500,000.
iii. Evacuation is complete.
iv. The Shelter Task Force Plan is activated and working.
v. The purpose of emergency shelter is to get people away from the impact of the
disaster.
vi. Special populations shelter operations will be conducted in accordance with
the Louisiana Hurricane Shelter Operations Plan, Annex X, Special Needs
Plan. The plan is adequate to address a catastrophic scenario.
vii. The Governor’s order will be required to ensure all Parish and State resources
are made available to meet the emergency needs of people for a minimum of
12 months.
viii. A total of 40,000 people will be needed to assist with the sheltering of
500,000 people, dispensing of 1 million meals, and the distributing of life-
sustaining supplies.
ix. The 500,000 post-landfall shelter population will include people that were
sheltered in hotels or with families pre-landfall. Some Parishes within sector
D will open shelters during the pre-landfall phase. Some of these, although
2. Mission
a. Provide shelter to members of the public forced from their homes by a
catastrophic hurricane until they are able to return to their homes, find alternate
housing, or can be provided with temporary housing arrangements.
3. Execution
a. Concept of the Operations
i. General
1) A method to identify, segregate, and decontaminate potentially
contaminated shelterees will be developed.
2) A method to conduct sampling at shelter sites will be developed.
3) Shelterees rescued from the affected area will pass first through one of the
Temporary Medical Operations Staging Areas. They will be grouped by
area of origin before being transported to shelters, in order to facilitate
return assistance once they can return home.
4) Emergency shelter will not be reconstituted in impact areas until
temporary housing is established.
5) Temporary housing will be reconstituted in or near the impact areas as
soon as possible.
6) Resources and support will be available from the Louisiana Office of
Homeland Security and Emergency Preparedness through the guidelines in
the Emergency Operations Plan.
7) All shelter-related public service messages will be communicated by the
Louisiana Office of Homeland Security and Emergency Preparedness
through the Emergency Alert System. Parish Offices of Homeland
Security and Emergency Preparedness can use the Emergency Alert
System in accordance with existing procedures.
8) Some shelters will be closed and others opened as the situation warrants.
Some facilities in inundated areas will be closed and the population
relocated in a safer area. Some will be closed as people are shifted closer
to their homes.
2) State of Louisiana
a) The Louisiana Hurricane Shelter Task Force will perform the
following task:
i) Coordinate with Parish operation of existing shelters and
identification of potential locations for new shelters.
b) The Department of Health and Hospitals will perform the following
tasks:
i) Provide medical personnel staffing for special needs shelters.
ii) Provide/coordinate medical support for general population shelters
based on medical needs at the time.
1. Forward additional health care requests to ESF-6 for
coordination.
iii) Provide medical screening of all rescued persons post-landfall
before assignment to shelters.
c) Louisiana Voluntary Organizations Active in Disasters will perform
the following task:
i) Coordinate volunteer personnel, activities, and donations.
d) Office of Indian Affairs will perform the following tasks:
i) Identify reservation needs and coordinate State support with tribal
governments.
ii) Coordinates donations and volunteer designated for non-
reservation Indian populations.
e) Department of Agriculture and Forestry will perform the following
task:
i) Provides available commodities for mass feeding.
f) Department of Corrections will perform the following task:
i) Supplements shelter feeding effort when requested.
g) National Guard will perform the following task:
i) Provides assistance in shelter operations as requested through the
Louisiana Office of Homeland Security and Emergency
Preparedness (reference the Louisiana State Emergency Plan).
h) Department of Environmental Quality will perform the following
tasks:
i) Assist with decontamination and air and water quality monitoring
in shelters.
ii) Ensure that no hazardous materials are near shelter facilities.
i) For the purposes of this plan, State and local level chapters of the
American Red Cross are included as providing support to shelters at
the Federal level.
3) Local support
a) Parish President will perform the following task:
i) Authorize and direct use of Parish government personnel and other
resources to direct and/or assist with the sheltering operations.
b) Parish Director of Homeland Security and Emergency Preparedness
will perform the following task:
9
The Personnel Data Tracking System would greatly facilitate the shelters’ efforts to track people, as well
as better achieve other objectives like family reunification and education.
10
The agency authority for individual shelters must coordinate with the local school administration (e.g.,
principal and superintendent) to determine the viability of utilizing the school as an on-going shelter while
continuing student education.
1 3 . 0 Te m p o r a r y H o u s i n g
1. Situation
a. General
i. A catastrophic hurricane has hit southeast Louisiana causing heavy structural
damage, including many homes, due to high winds and flooding. Thousands
of families will be displaced for an extended period of time and will require
temporary housing while their homes are being rebuilt or until they find new
permanent housing.
b. Assumptions
i. See Temporary Housing Appendix A
ii. For this purposes of this plan, it is assumed that 457,000 households will be
displaced, with an estimated 200,000 or less requiring long-term housing.
iii. It will take over one year to re-enter areas most heavily impacted.
iv. Temporary housing will last longer than normal, depending on utilities and
structure areas.
v. Those displaced will move the minimum possible distance and return at the
earliest possible time.
vi. Housing will require supporting infrastructure to include water, power,
sanitation, access-medical, security, schools, and community services.
vii. Multiple group sites will be in multiple Parishes.
viii. Available rental unity will be minimal.
ix. Housing solutions for New Orleans metro areas will differ from those for the
other Parishes.
x. Parishes will have little or nothing to offer by way of resources.
xi. Each identified group housing site will have to be evaluated and possibly
tested for hazardous materials advisories sent out.
xii. There will be an accelerated environmental assessment for group sites.
xiii. Decisions about where to locate temporary housing in the short term will
impact longer-term decisions regarding locations where permanent rebuilding
can take place.
xiv. Parish resources in the most severely impacted areas will not be available for
several weeks or even months, as they were not removed from the area prior
to the storm.
xv. Certain large tracts of land enclosed by levee systems will have been flooded
due to storm surge overtopping levee walls beyond the capacity of pumping
systems. Most, if not all, pumping systems will have been rendered inoperable
by the flooding. These areas will only be accessible by water until levees are
breached after floodwaters have receded to normal levels. This means much of
Orleans, Jefferson, and parts of St. Bernard Parish will not be suitable
locations for temporary housing.
c. Organizations
i. Federal
1) Lead Agency
a) DHS/FEMA
2) Supporting Agencies
a) Department of Agriculture
b) Department of Commerce
c) Department of Defense
d) Department of Energy
e) Department of Health and Human Services
f) Department of Housing and Urban Development
g) Department of Labor
h) Department of Transportation
i) Department of the Treasury
j) Department of Veterans Affairs
k) American Red Cross
l) Tennessee Valley Authority
m) U.S. Postal Service
n) Small Business Administration
o) U.S. Army Corps of Engineers
p) Forest Service
q) General Services Administration
ii. State of Louisiana
1) Lead Agency
a) Louisiana Office of Homeland Security and Emergency Preparedness
2) Supporting Agencies
a) Department of Insurance
b) Department of Health and Hospitals
c) Department of Revenue
d) Department of Public Safety
e) Department of Economic Development
f) Department of Transportation and Development
g) Department of Corrections
h) Planning and Development Commission
i) Public Service Commission
j) Louisiana National Guard
iii. Local
1) Lead Agency
a) Parish Office of Homeland Security and Emergency Preparedness
2) Supporting Agencies
a) Sheriff’s Office
b) Fire Departments
c) Department of Public Works
d) Levee Board
e) Local Planning and Zoning Commissions
2. Mission
a. The mission is to provide temporary housing to members of the public in
southeast Louisiana whose homes sustained major damage as a result of a
catastrophic hurricane and will not be able to return to their homes until
permanent alternate housing is obtained or their home is restored to habitability.
3. Execution
a. Concept of Operations
i. Pre-disaster group site identification and selection process:
1) The identification of sites by the State and local officials is essential to the
timely implementation of the temporary housing program. Site
identification should be accomplished before hurricane season and
reviewed/updated annually (see Temporary Housing Appendix E: Group
Site Data Collection Sheet Draft).
a) Partner with the State of Mississippi and Native American Tribes
within the State of Louisiana to identify sites using the Group Site
Data Collection Sheet (Temporary Housing Appendix E: Group Site
Data Collection Sheet Draft) for temporary housing.
b) Request neighboring states to identify any closed military installations
that can possibly be used for temporary housing.
2) Site selection will be completed by DHS/FEMA.
ii. Coordinate with the Individual Assistance Strike Team (Task Force) to assess
any unmet housing needs (wholesale), act as liaisons to locals, and coordinate
with local community relations teams, mobile home teams (retail), and
potential sites.
iii. Execute a multi-faceted phased temporary housing strategy to move people
from emergency shelter to temporary housing on to permanent housing as
quickly as possible. Priorities of effort will go to emergency shelter residence,
giving priority to those individuals from the most heavily impacted areas that
will require long-term temporary housing. Concurrent strategies are as follows
(see Temporary Housing Appendix B: Phases of Housing Requirements and
Programmatic Approaches):
1) Strategy 1: Enable use of existing resources.
2) Strategy 2: Conversion of existing resources and construction of
emergency group sites.
3) Strategy 3: Development of temporary housing sites.
b. Specific Tasks to Lead, Support, and Coordinate Agencies
i. Strategy 1: Enable use of existing resources
1) Intermediate housing will encompass all alternatives that provide a
minimum family living environment that can be executed quickly,
including local and regional relocation. Possible alternatives will include
college campuses, barracks, hotels and motels, personal travel trailers and
recreational vehicles, adopt-a-family, rental rooms in private homes,
vacation homes, camp facilities (e.g., church, Boy/Girl Scouts, and 4-H),
cruise ships, and all available rental units. This strategy will also include
assistance to survivors moving in with family or friends and/or relocating
to areas outside of the State, and negotiating with hotel chains in and out
of the State. Lump sum payments may be an option.
2) ESF-1 will perform the following tasks:
a) Provide transportation assets to support interim housing transition.
b) Establish a mass transit plan.
Months
1 2 3 4 5 6 7
Travel Trailers:
Individual Sites 400 600 1000 2500 - - -
(Assume 4500)
Mobile Homes/Travel
Trailers:
Existing Sub- - 200 500 1000 800 500 -
divisions/Commercial
Parks (Assume 3000)
Small Group Sites:
500 Units - 100 400 1000 5000 6000 -
(Assume 25)
Medium Group Sites:
1000 Units - - 5000 10,000 15,000 - -
(Assume 30)
Large Group Sites:
5000 Units - - - 25,000 50,000 50,000 25,000
(Assume 30)
Total 200,000 (Worst-
400 900 6900 39,500 70,800 56,500 25,000
Case Scenario)
c. Personnel
i. The following table is an example of the personnel requirements distributed
over time. These estimates do not include administrative support staff.
Time
ESF Day 1–5 Day 6–10 Day 10–30 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8
1 125 175 250 300 300 300 300 300 300 300
2 6 6 12 12 12 12 12 12 12 12
3 100 200 800 4880 9750 10050 7800 5930 1460
4 150 150 150 285 1785 1635 1635 1635 1635 1635
5–IA 1000 (*) 1500 3000 3000 3000 3000 3000 3000 3000 3000
5–LOG 275 450 500 500 500 550 650 650 650 650
6 **
7 16 27 30 50 50 50 50 50 50 50
8 ***
10 6 6 12 12 12 12 12 12 12 12
11 150 150 150
12 6 6 12 12 12 12 12 12 12 12
OFA/HUD 6 6 6 6 6 6 6 6 6 6
State**** 264 364 734 734 734 734 734 734 734 734
Total 1104 3040 5656 9791 16161 16361 14211 12341 7871 6411
b. Communications Requirements
i. Travel trailer/mobile home delivery
1) The Department of Transportation will be required to adjudicate road
access issues for movement of mobile homes from production facilities to
the disaster area.
ii. Sweep teams
1) See Temporary Housing Appendix D.
iii. Site selection
1) The site selection process will require coordination between DHS/FEMA,
the State and Parish governments, U.S. Army Corps of Engineers, and the
Environmental Protection Agency.
1 4 . 0 Te m p o r a r y M e d i c a l C a r e
1. Situation
a. General
i. A catastrophic hurricane has made landfall in southeast Louisiana. In many
affected Parishes, a high percentage of the population remained at landfall,
resulting in high numbers of fatalities and non-fatal injuries.
b. Assumptions
i. Transportation will be limited due to flooded roadways and a shortage of
resources such as fuel.
ii. There is no medical treatment available within the affected area; therefore,
there is a need for a medical staging area outside the affected area.
iii. Local resources are exhausted and the blood supply will be stressed. Medical
staffing will not be at full capacity.
iv. Communication networks are non-functioning and interoperability among
hospitals may be a problem.
v. Large numbers of people are expected to require treatment for a variety of
illnesses, both related and unrelated to the hurricane, before health care
facilities in the affected areas are returned to operation.
vi. For the purposes of this plan, the following summary of the expected
casualties during pre-landfall, impact, and post-impact is assumed.
vii. Search and rescue missions will need to be supported by medical personnel to
do screening/triage on rescuees prior to transport to shelters or release to
families.
viii. Large quantities of hazardous waste, both industrial and household, will have
been released because of hurricane wind and flooding, resulting in potential
airborne and waterborne contamination, and possible combustible/flammable
conditions.
ix. Many families seeking shelter will have not brought needed over-the-counter
and prescription medicines with them.
x. Certain large tracts of land enclosed by levee systems will have been flooded
due to storm surge overtopping levee walls beyond the capacity of pumping
systems. This will include the majority of Orleans Parish, much of Jefferson
Parish, and parts of St. Bernard Parish.
xi. All 40 medical treatment facilities in the impacted area are affected by the
high-water levels, loss of electricity, loss of communications, and storm-force
winds, rendering them isolated and useless. At best, they will shelter-in-place
whatever patients they were not able to discharge prior to landfall. In addition,
refugees (non-injured or ill individuals) will come to those treatment facilities
for sheltering. All patients, staff, family members, and refugees will require
evacuation from nonfunctional facilities. These treatment facilities may
require restoration of power, as well as medical, water, and food re-supply,
until evacuation is complete.
xii. Some nursing homes will have already been evacuated, per emergency plans,
as required by the State. However, some residents will not be able to evacuate
pre-incident and will require medical evacuation.
xiii. The standard acceptable level of care will not be possible in an extreme
emergency situation.
xiv. Concern about inpatient care will be much greater than concern for outpatient
care.
xv. The State will request Federal support and the President will declare a major
disaster. ESF-8 will be activated, including the National Disaster Medical
System (Disaster Mortuary Operational Response Team, Disaster Medical
Assistance Team, and Veterinary Medical Assistance Team).
xvi. Search and rescue will be activated to conduct aerial assessments to
determine Search and Rescue Bases of Operation.
xvii. The Strategic National Stockpile will be activated and the Technical
Assistance Response Unit will be deployed.
xviii. Based on estimates from search and rescue, approximately 75,000 persons
will be transported to medical facilities daily for four days. If a conservative
estimate of 10% requiring medical treatment is applied, receiving 7,500
patients per day in need of medical care will be anticipated.
xix. The State will establish nine triage lines and special needs shelters.
xx. The Strategic Medical Assistance and Response Team (SMART) and mobile
hospital system will be activated.
c. Organization
i. Federal
1) Lead Agency
a) Department of Health and Human Services
2) Support Agencies
a) DHS/National Disaster Medical System
b) Department of Agriculture (U.S. Forest Service)
c) Department of Defense
c) Department of Energy
d) Department of Justice
f) Department of Transportation
2. Mission
a. The mission is to plan for medical transportation, temporary public health and
medical care, emergency medical care, normal outpatient care (e.g., doctors,
dentists, laboratory, radiology, dialysis clinics, and home nursing), and definitive
hospital care to the population of southeast Louisiana. The mission is also to plan
for identification, storage, and assistance with final disposition of remains and to
plan for minimal support of animal care as needed. These services will be
provided until customary medical facilities and services are returned to
operational status in the areas impacted by the catastrophic hurricane.
3. Execution
a. Concept of Operations
i. Search and Rescue Base of Operations
1) The Louisiana Department of Health and Hospitals will coordinate with
search and rescue efforts to provide decontamination and/or medical care
at each Search and Rescue Base of Operations. Search and rescue will
transport victims requiring medical attention to the Bases of Operations or
to acute treatment facilities as dictated by the patient’s medical condition.
2) It is recommended that Search and Rescue Bases of Operations be located
next to or very near selected rail lines and viable ground transportation
routes.
3) The Search and Rescue Bases of Operations will be staffed by local
emergency service and public safety providers (e.g., emergency medical
service and fire departments), as well as Disaster Medical Assistance
Team members. Disaster Medical Assistance Teams, organized into
medical strike teams, will be located at each Search and Rescue Base of
Operations.
4) From the Search and Rescue Bases of Operations, refugees in need of
medical care will be transported to one of three Temporary Medical
Operations Staging Areas or more definitive care facilities as determined
by patient condition through a combination of the following assets:
emergency medical service, State resources (including public/private
ambulances and helicopters), Emergency Management Assistance
Compact resources, National Mutual Aid and Resource Management
Initiatives resources, Federal assets to be determined by DHS/FEMA, and
other pre-event open-ended-agreement procured modes of transportation.
5) Refugees not in need of medical care will be transported via various
means of transportation from the Search and Rescue Bases of Operations
to nearby shelters in Baton Rouge, Thibodaux, and Hammond.
6) Within five days of rescue operations, search and rescue assets will switch
from rescue efforts to evacuation of hospitals in the affected area. Hospital
evacuation must be a priority, due to the lack of electricity, number of
patients, and the influx of refugees into the stranded healthcare facilities
overwhelming available resources. Patients will be moved to Temporary
Medical Operations Staging Areas, directly to designated hospitals outside
of the affected area, or out of the State. Refugees will be transported to
temporary shelters.
7) Hospitals in the affected areas will be re-supplied with critical supplies
within one to seven days.
8) Patients and refugees will be decontaminated at the Search and Rescue
Bases of Operations as needed prior to forward movement to the
Temporary Medical Operations Staging Areas.
ii. Temporary Medical Operations Staging Areas
1) The State Department of Health and Hospitals has designated Temporary
Medical Operations Staging Areas in the following locations: Southeastern
Louisiana University (Hammond, Louisiana), Nicholls State University
iii. The General Services Administration will provide four T1 lines via mobile
satellite unit and any additional resources necessary to re-establish hospital
communications.
iv. Interoperability and communications between multiple users is an ongoing
issue. Communications need to be coordinated to ensure effective tracking
and response at the unified command centers.
v. Tracking of medical personnel responding to the area, medical supplies, and
patients will all be coordinated by the Louisiana Department of Health and
Hospitals.
Prepared For
DHS/FEMA
500 C Street S.W.
Washington, DC 20472
LOHSEP
7667 Independence Boulevard
Baton Rouge, LA 70806
Prepared Under
FEMA BPA HSFEHQ-04-A-0288, Task Order 001
IEM/TEC04-070 r5 Appendices
January 5, 2005
This document is for reference only. Readers should not construe this document as representing
official policy or regulations. The functional plans contained in this document were produced
during the Southeast Louisiana Catastrophic Hurricane Planning Workshops (July 16–23, 2004,
and November 29–December 3, 2004). These functional plans have been edited for clarity. The
information contained herein is current as of December 3, 2004, and is subject to change.
This page intentionally left blank.
Southeast Louisiana Catastrophic Hurricane Plan
TABLE OF CONTENTS
PRE-LANDFALL 1
Appendix A: Incident Action Plans 1
Appendix B: State of Louisiana Hurricane Checklist 26
Appendix C: FEMA Region VI Hurricane Checklist 36
DEBRIS 51
Appendix A: Organizational Chart 51
Appendix B: Debris Timeline 52
SHELTERS 63
Appendix A: Materials and Services 63
TEMPORARY HOUSING 65
Appendix A: Planning Assumptions 65
Appendix B: Phases of Housing Requirements and Programmatic Approaches 67
Appendix C: Representative Timeline 69
Appendix D: Sweep 70
Appendix E: Draft Group Site Data Collection Sheet 71
POINTS OF CONTACT 87
Pre-landfall
Appendix A: Incident Action Plans
Continuing FEMA HQ
Refine identification of second tier One-Time Lead for this Task:
6.
response and re-supply systems. Continuing FEMA HQ
Lead for this
e. Objective: Conduct Joint Media Campaign Objective:
LOHSEP – JIC
Refine media releases to focus on those Lead for this Task:
One-Time
1. who missed evacuation and may be
isolated.
Continuing ALL – JIC
Develop media messages for emergency One-Time Lead for this Task:
2.
protection measures. Continuing ALL – JIC
Tasks:
Develop media messages to assist with One-Time Lead for this Task:
3.
response and volunteer efforts. Continuing ALL – JIC
One-Time Lead for this Task:
4. Begin to manage expectations
Continuing ALL – JIC
Lead for this
f. Objective: Coordinate Louisiana Evacuations Objective:
LOHSEP
Coordinate with Mississippi, Department of Lead for this Task:
Transportation and Development, One-Time
1.
Louisiana State Police for cessation of Continuing LOHSEP
contraflow and other evacuation activities.
Tasks: One-Time Lead for this Task:
2. Support ongoing evacuation activities
Continuing LOHSEP
One-Time Lead for this Task:
3.
Continuing
COORDINATION
EST DIRECTOR Name and Signature:
APPROVAL
ROC DIRECTOR Name and Signature:
FEMA Form 90-131 (Variation) Note: EST Director coordination is required when EST is at Level 2 or 1
Increase readiness at the State, Region VI, and FEMA HQ level in anticipation of
Tropical Storm force winds
Refine Asset Protection Plan and Support Structure for Emergency Responders
6. Weather Forecast for Operational Period:
Organization List (ICS 203) Medical Plan (ICS 206) Incident Briefing (ICS 201)
Division Assignment Lists (ICS 204) Incident Map Action Plan (FEMA Form 90-131)
LOHSEP -- JIC
Continue media and public affairs Lead for this Task:
One-Time
1. information support, press releases, media
statements, etc.
Continuing ALL -- JIC
COORDINATION
COORDINATION
EST DIRECTOR Name and Signature:
APPROVAL
ROC DIRECTOR Name and Signature:
FEMA Form 90-131 (Variation) Note: EST Director coordination is required when EST is at Level 2 or 1
Increase readiness at the State, Region VI, and FEMA HQ level in anticipation of
Tropical Storm force winds
Refine Asset Protection Plan and Support Structure for Emergency Responders
6. Weather Forecast for Operational Period:
Organization List (ICS 203) Medical Plan (ICS 206) Incident Briefing (ICS 201)
Division Assignment Lists (ICS 204) Incident Map Action Plan (FEMA Form 90-131)
Continuing
COORDINATION
EST DIRECTOR Name and Signature:
APPROVAL
ROC DIRECTOR Name and Signature:
FEMA Form 90-131 (Variation) Note: EST Director coordination is required when EST is at Level 2 or 1
Increase readiness at the State, Region VI, and FEMA HQ level in anticipation of
Tropical Storm force winds
Refine Asset Protection Plan and Support Structure for Emergency Responders
6. Weather Forecast for Operational Period:
Organization List (ICS 203) Medical Plan (ICS 206) Incident Briefing (ICS 201)
Division Assignment Lists (ICS 204) Incident Map Action Plan (FEMA Form 90-131)
Increase Readiness at the State, Region VI, Lead for this Objective
b. Objective: and FEMA HQ levels in anticipation of
ALL
Tropical Storm Force Winds
1. Louisiana Activate Personnel and One-Time Lead for this Task:
Resources as appropriate Continuing LOHSEP
One-Time Lead for this Task:
2. Deploy State Liaison to Louisiana
Continuing FEMA Region VI
Task: EST Deploy teams and resources to One-Time Lead for this Task:
3.
Logistics Centers as appropriate Continuing FEMA HQ
FEMA Region VI make administrative and Lead for this Task:
logistics arrangements for staging One-Time
4.
equipment and teams and for berthing Continuing
FEMA Region VI
personnel
c. Objective:
Communicate, Coordinate, and Cooperate Lead for this Objective
at All Levels ALL
1. Deploy Regional Representative to X One-time Lead for this Task:
Hurricane Liaison Team Continuing Region VI
One-time Lead for this Task:
Task: 2.
X Continuing
Region VI
One-time Lead for this Task:
3.
Continuing
Approval
ROC Director Name and Signature
FEMA Form 90-131 ROC (Variation) (05/11/04) Note NRCC Director coordination is required when NRCC is at Level 2 or 1.
Increase readiness at the State, Region VI, and FEMA HQ level in anticipation of
Tropical Storm force winds
Organization List (ICS 203) Medical Plan (ICS 206) Incident Briefing (ICS 201)
Division Assignment Lists (ICS 204) Incident Map Action Plan (FEMA Form 90-131)
Increase Readiness at the State, Region VI, Lead for this Objective
b. Objective: and FEMA HQ level in anticipation Tropical
ALL
Storm Force winds.
1. Alert personnel, verify resources and Lead for this Task:
One-time
allocation of resources X Continuing ALL
Review Hurricane Check Lists, update One-time Lead for this Task:
Task: 2.
and execute as appropriate X Continuing
ALL
c. Objective:
Communicate, Coordinate, and Cooperate Lead for this Objective
at all levels. ALL
Begin Video and Tele- Conferences as Lead for this Task:
appropriate. NOTE: The need to
communicate, Coordinate and
Cooperate is basic. It includes all
involved parties including Parishes,
1. the State of Louisiana, contiguous One-time
States, FEMA Region VI and X Continuing All
contiguous Regions, FEMA HQ, the
HLT, private entities, etc. This task
Task:
continues throughout pre-landfall but
will NOT be repeated on each Incident
Action Plan
One-time Lead for this Task:
2.
Continuing
Approval
ROC Director Name and Signature
FEMA Form 90-131 ROC (Variation) (05/11/04) Note NRCC Director coordination is required when NRCC is at Level 2 or 1.
Increase readiness at the State, Region VI, and FEMA HQ level in anticipation of
Tropical Storm force winds
Organization List (ICS 203) Medical Plan (ICS 206) Incident Briefing (ICS 201)
Division Assignment Lists (ICS 204) Incident Map Action Plan (FEMA Form 90-131)
LEVEL IV ACTIVATION
Date/Time/Initials
__________ A. LOHSEP Crisis Action Team (CAT) is activated by the Director (D) or
Assistant Director (AD).
__________ B. CAT opens and partially staffs the State Emergency Operations center (EOC).
__________ C. CAT prepares SITUATION REPORT (SITREP) and Operations Logs (OPS
Log) for Governor, Governor’s Chief of Staff, Governor’s Press Secretary, The
Adjutant General, and FEMA Region VI, advising CAT is operational and
monitoring the event, with information copies to State agencies.
__________ D. CAT initiates event and operational log, using both automated and written
means.
__________ F. In concert with AD and the Operations Officer (OPSO), the CAT LOGs and
maintains communications with risk Parish EOCs and the following State,
Federal, and volunteer agencies as required by the AD:
1. FEMA Region VI (940) 898-5280
2. Mississippi State EOC (601) 352-9100
3. Arkansas State EOC (501) 730-9750
4. Texas State EOC (512) 424-2138
5. LSU Earth Scan Labs (225) 388-2952
The following represents a list of State, Federal, and Volunteer Agencies LNOs normally
contacted for EOC staffing, but by no means represents all who can report if required (refer to
contact list in SOP):
**IF ACTIVATION BEGINS AT LEVEL III ENSURE ALL ACTIONS AT LEVEL IV ARE
REVIEWED AND ACCOMPLISHED AS REQUIRED**
Date/Time/Initials
__________ C. OPS staff collects Parish Declarations of Emergency from which a State
Declaration is processed.
__________ E. LOHSEP Executive prepares proclamations for the State to intervene in local
situations if local governments fail to act, in accordance with RS 29:721-735.
__________ F. OPS staff notifies FEMA VI ROC (940) 898-5280 to be prepared to forward
deploy FEMA Liaison to the State EOC.
__________ G. OPS staff initiates and LOGs contact with risk Parishes and test all
communications means, (800MHZ, Satellite, RACES, CONFERENCE CALL
PROCEDURES).
__________ H. OPS staff requests that DOTD clear any evacuation route obstructions on an
emergency basis.
__________ I. OPS staff request that DOTD provide GIS data and traffic counts for
situational awareness on evacuation routes and number of vehicles leaving the
State. DOTD reports count every eight hours to EOC.
__________ J. OPS staff requests that DHH/DSS establish special needs shelters, order
contract generators, and place LANG on standby for security and cots.
__________ K. OPS staff through the Shelter Task Force, issues a standby alert to host
Parishes to review their shelter status and prepare to host evacuees.
__________ L. OPS staff requests National Guard place Parish LNO’s on standby alert.
__________ O. OPS staff provides potentially effected Parishes with the Needs
Assessment/Reports Team phone numbers and request 12 hour status/SITREP
updates be provided the Needs Assessment/Reports Team upon activation of
the Parish EOC. LOHSEP staff advises risk Parishes of reporting requirements
and request a status report as of activation of their EOC.
__________ T. OPS staff faxes damage assessment, re-entry forms and reports to all risk
Parishes as well as receive and distribute within the agency.
__________ U. OPS staff provides LANG Security Team with EOC access roster.
Based on status reports and predictive modeling, LOHSEP staff conducts an analysis of the
situation and recommends to the D/AD the need to place selected FEMA assets on alert. Special
considerations given to the following:
__________ Y. DSS coordinates with Mississippi, Arkansas, and Texas regarding shelter
status.
__________ BB. DSS/American Red Cross (ARC)/DHH coordinate health and sanitary needs of
shelters.
LEVEL II ACTIVATION
**IF ACTIVATION BEGINS AT LEVEL II ENSURE ALL ACTIONS AT LEVEL IV, AND
III
ARE REVIEWED AND ACCOMPLISHED AS REQUIRED**
Date/Time/Initials
_________ A. LOHSEP increases the State EOC staffing at the level directed by the
AD/OPSO, increased staffing will include as a minimum the Levels I and II
staffing as noted on the attached EOC Organization chart. Selected State
Agencies may augment the EOC staff as required by the AD.
__________ B. OPS staff collects Parish Declarations of Emergency from which a State
Declaration is processed (on-going from Level III).
__________ D. LOHSEP Executive prepares proclamations for the State to intervene in local
situations if local governments fail to act, in accordance with RS 29:721-735.
(If starting at Level II activation.)
__________ E. Public Information Officer (PIO) initiates news media contacts to disseminate
public information on potential evacuation and shelter operations.
__________ F. OPS through the IT division activates EAS system to disseminate hurricane
advisories and evacuation and shelter information.
__________ I. OPS staff request Evacuation Route Status Report from DOTD and LA State
Police.
__________ J. OPS staff request LANG Military Support Directorate activate Dining,
Security, COMMO Support, and LNO teams for duty.
__________ K. OPS staff request additional kitchen support as needed from Dept. of Public
Safety (DPS).
__________ M. OPS staff notifies the following agencies of EOC activation with date and
time, remaining State, Federal, and Volunteer agencies are notified of their
requirement to locate in the EOC:
Affected Parishes
State Agencies
FEMA Region VI (940) 898-5280
Mississippi State EOC (601) 352-9100
Texas State EOC (512) 465-2138
Arkansas State EOC (501) 730-9750
Alabama State EOC (205) 280-2200
Tennessee State EOC (615) 741-4330
__________ N. OPS staff requests Parish EOC activation status report from risk Parishes.
Reminds activated Parish EOC officials of daily report requirement.
__________ P. OPS staff /Reports Section secures local emergency declarations as required.
__________ R. OPS staff informs PIO of State Declaration of Emergency for preparation and
dissemination of EAS Message.
__________ S. PIO notifies the following agencies of EAS evacuation and shelter messages:
FEMA Region VI (940) 898-5280
Mississippi State EOC (601) 352-9100
Texas State EOC (512) 465-2138
Arkansas State EOC (501) 730-9750
Alabama State EOC (205) 280-2200
Tennessee State EOC (615) 741-4330
LEVEL I ACTIVATION
**IF ACTIVATION BEGINS AT LEVEL I ENSURE ALL ACTIONS AT LEVELS IV, III
AND II ARE REVIEWED AND ACCOMPLISHED AS REQUIRED.**
Date/Time/Initials
__________ A. At the direction of the D/AD, OPSO increase the level of EOC activity to
Level I, full activation of the EOC. All State, Federal, and Volunteer
organizations will report to the EOC as required.
__________ B. OPS staff notifies following agencies of EOC activation with date and time,
remaining State, Federal, and Volunteer agencies are notified of their
requirement to locate in the EOC:
Affected Parishes
State Agencies
FEMA Region VI (940) 898-5280
Mississippi State EOC (601) 352-9100
Texas State EOC (512) 465-2138
Arkansas State EOC (501) 930-9750
Alabama State EOC (205) 280-2200
Tennessee State EOC (615) 741-4330
__________ D. LOHSEP executive consults with risk area Parishes to finalize mandatory
evacuation orders.
__________ F. Louisiana Nursing Home Association EOC Liaison calls all nursing homes and
other custodial care organizations in the risk areas to ensure that they are
prepared to evacuate their residents.
__________ J. Begin discussions for Precautionary Evacuation (if starting at Level II).
__________ L. DSS, ARC, DHH, DOTD, and LSP staff keeps EAS evacuation and shelter
information updated on a two-hour basis, or more frequently if information is
available on a more timely basis.
__________ M. DSS, ARC, DHH, DOTD, LSP, and JIC keeps news media informed and
updated on evacuation and shelter information.
__________ N. DSS request risk and host Parishes send evacuation and shelter status reports to
State EOC twice daily.
__________ P. LSP and DOTD staffs keep neighboring States informed of status and traffic
control decisions.
__________ Q. Begin discussions for Recommended Evacuation (if starting at Level II).
__________ S. DHH/Nursing Home Association and LOHSEP monitors the evacuation and
shelter of persons having mobility limitations, including persons in nursing
homes, hospitals, group homes, and non-institutionalized persons.
__________ T. DSS, ARC, DHH, DOTD, LSP, JIC staff keeps EAS evacuation and shelter
information updated on a two-hour basis, or more frequently if information is
available on a more timely basis.
__________ U. JIC keeps news media informed and updated on evacuation and shelter
information.
__________ V. DOTD and LSP staffs keep neighboring States informed of status and traffic
control decisions.
__________ W. Begin discussions for Mandatory Evacuation (if starting at Level II).
__________ Y. DOTD and LSP implements mandatory evacuation traffic controls. Convert
specified limited access routes to one-way outbound operations. Control main
evacuation routes with State resources.
__________ Z. LSP and DOTD staffs keep neighboring States informed of status and traffic
control decisions.
__________ AA. DSS, ARC, DHH, DOTD, LSP, and JIC staff keeps EAS evacuation and
shelter information updated on a two-hour basis, or more frequently if
information is available on a timelier basis.
__________ BB. JIC keeps news media informed and updated on evacuation and shelter
information. (RECURRING)
__________ CC. DOTD/LSP mobilizes State evacuation traffic control active and passive
resources and people. Position barriers and people where they can take up their
duties within an hour of being ordered to do so.
__________ DD. JIC advises news media of preparations for orderly evacuation, traffic control,
and hosting operations.
AT LANDFALL02:00 HOURS
__________ EE. Executive/Ops staff consults with LSP to close evacuation routes.
__________ FF. DOTD/LSP alerts risk Parishes and State traffic control posts of the time that
evacuation routes will be closed.
__________ GG. OPS staff alerts EAS (refer to map) and news media so that people still in the
risk area can seek last resort refuge.
__________ HH. LOHSEP executive coordinates with Parishes the opening of last resort refuge
buildings to people still in the risk area.
__________ II. OPS staff /Recovery Division prepares for damage assessment and post
disaster recovery activities and requests DSS, DOTD, DHH, DNR, State
Police, and OTM be prepared to report on food, water, electric, telephone,
shelter, road and special needs status as early as possible after the storm makes
landfall.
__________ KK. Reentry into the disaster area will be coordinated by LOHSEP and will be
authorized only after local Parish elected officials certify to LOHSEP their
ability to provide essential services to Parish citizens:
Food
Water
Utilities
Medical Support
RST TASKS
Convene an initial Regional Coordination and Planning Meeting
with the senior regional management team as
appropriate, identify the situation, strategy, requirements,
mobilization, plan for an anticipated Federal response,
and any associated support for liaison with LOHSEP to
include ERT-A, RNA, and ERT requirements.
Notify emergency rostered personnel and senior management
team of threat and probability.
Activate the RST at Level 2
1) Establish NACs rights
2) Ensure surge funding is in place.
3) Activate Regional Emergency Support Function
(ESF) agencies as required.
4) Deploy Regional HLT Liaison
5) Deploy State Liaison(s)
6) Begin Action Planning Process
Establish JIC.
Declaration process
i. Process Governors request
ii. Initiate FEMA /State Agreement
iii. Close incident period as appropriate
Issue post-declaration mission assignments as appropriate
P o w e r, Wa t e r, a n d I c e D i s t r i b u t i o n
Appendix A: U.S. Army Corps of Engineers Commodity
Distribution/Staging Area Requirements
Tr a n s p o r t f r o m Wa t e r t o S h e l t e r
Appendix A: Search and Rescue to Shelter to Temporary Housing
Flow Chart
Land Access
via Louisiana
Water Access National Guard
via Volunteer Flotilla
Temporary
Land Access
Medical Special
Land Area via Louisiana Medical Facility
Operational Transport
National Guard
Staging Area
Mass
Transport
Personal
Temporary
Shelter Transport or
Housing
Mass Transport
Debris
Appendix A: Organizational Chart
D+18-24
Months • 100% Mission Completion (estimated)
Air Operations 20
Communications
Wildlife and Fisheries 8
U.S. Coast Guard 8
Air Operations 8
Volunteer 8
TOTAL Communications 32
1
To help with logistics and establish and maintain bases of operations.
Shelters
Appendix A: Materials and Services
1. Categories of Supply
a. Food
i. Federal: U.S. Department of Agriculture (food and nutritional)
ii. State: Department of Corrections
b. Ice and Water
i. DHS/FEMA
1) ESF-3
2) Contractors established
3) Takes 24 hours to put in place
ii. State: Louisiana Office of Homeland Security and Emergency Preparedness
c. Sheltering
i. Tents, tarps, material goods, plastic sheeting, cots, mattresses, bedding
1) National Guard will provide cots for nine regional special needs shelters
2) DHS/FEMA has bedding for up to 100,000
3) Any request for cots will go through LOHSEP (servicing beyond landfall)
4) Department of Social Services will provide for special needs shelters
d. Soft Goods
i. Clothing, tentage, tarps
1) Federal: Voluntary Organizations Active in Disaster, other volunteer agencies
2) Red Cross at Federal level will assist in clothing
3) DHS/FEMA will mission assign once there is a declaration
4) ESF-6, under bulk distribution/mission assignment
e. Petroleum and Fuels
i. Generators
ii. Gasoline
iii. Oil
f. Construction and Repair
i. Lumber, wire, etc. (including repairs to shelters)
ii. Local Agencies
iii. DHS/FEMA mission assignment
g. Hygiene Items
i. Red Cross comfort kit (ESF-7 can provide 260,000; American Red Cross can provide
240,000)
ii. Additional needs will be met by the State, Department of Social Services, and special
needs shelters.
h. Other Equipment
i. Generators, lighting, heaters
1) Federal: General Services Administration to DHS/FEMA mission assignment
process
2) State: Louisiana Office of Homeland Security and Emergency Preparedness
ii. Radios, bulk transistor radios, State Police radios
i. Medical Supplies
i. Red Cross
ii. State: Department of Health and Hospitals
iii. DHS/FEMA mission assignment process
j. Cleaning/Sanitation
i. Red Cross, Voluntary Organizations Active in Disaster
ii. Department of Social Services for special needs shelters
2. Services
a. Identification of transportation requirements/resources (agency running shelter will
probably not need to provide transportation)
i. Federal: General Services Administration and Department of Transportation
ii. State: Department of Transportation and Development, Louisiana Office of
Homeland Security and Emergency Preparedness
b. Maintenance
i. Local agency/owners (responsible for the shelter) performs, submits receipts to
DHS/FEMA
ii. Louisiana Office of Homeland Security and Emergency Preparedness
c. Medical
i. Hospitals
ii. Dental
iii. ESF-8—Contractors secured before going through State to DHS/FEMA may not be
reimbursed
iv. State: Department of Health and Hospitals, Louisiana Office of Homeland Security
and Emergency Preparedness
d. Security
i. Local: Sheriff’s Department
ii. State: National Guard at special needs shelters
iii. ESF-6
e. ESF-3 will provide 2.5 million gallons of water per day
i. Sanitation: ESF-3
1) 190 portable toilets and/or latrines for a minimum of 25 shelters in the affected
area, other shelters will be assumed to have sufficient plumbing
2) Disposal of approximately 2.5 millions pounds of solid waste per day (5 pounds
per person)
ii. 1,000 refrigerator trucks (48-foot minimum of one per shelter)
1) Including fuel, maintenance (ESF-7)
2) In locations without refrigerator trucks, 5 pounds of ice per person per day (ESF-
3/7)
iii. Shelters without power will need items such as generators, fans, and emergency
lighting (estimated minimum of 25 shelters in affected Parishes; ESF-3 provides and
coordinates).
f. ESF-7
i. 1,000 dry storage trailers (48-foot minimum of one per shelter)
g. ESF-11
i. 1.75 million pounds of food per day
Te m p o r a r y H o u s i n g
Appendix A: Planning Assumptions
Appendix D: Sweep
Prepared by:
Site Name:
Location:
Parish:
Identification:
Latitude/Longitude:
Te m p o r a r y M e d i c a l C a r e
Appendix A: Definitive Care Patient Estimates and Associated
Staffing Needs
Primary Care Needs/Estimates
Based on search and rescue estimates, a maximum of 7,750 patients per day will arrive at the
Temporary Medical Operations Staging Areas. If the National Disaster Medical System carries
the full responsibility for medical treatment at these sites, up to 31 Disaster Medical Assistance
Teams operating at full capacity (250 patients per day each) will be needed to adequately meet
the patient load estimates. In order to meet the requirement, 22 operational Disaster Medical
Assistance Teams and nine developmental Disaster Medical Assistance Teams will be deployed.
This will decrease the National Disaster Medical System’s ability to augment area hospital staff
and to provide for personnel rotation after a two-week period.
The amount of patients not counted in U.S. Health Resources and Services Administration bed
numbers (e.g., injured victims streaming into affected hospitals after landfall) needs to be
factored in. Using data from a small sample of local hospitals during Hurricane Ivan (2004), an
average ratio of 1 patient to 4.25 healthcare workers, visitors, and sheltered family members in
the affected hospitals was obtained. Again, one must factor in the effects of the storm, along with
post-landfall effects, that will cause an additional surge of patients from trauma, infections,
snakebites, psychological trauma, and other illnesses. It is unknown how many additional
persons will come to the affected hospitals after landfall, and what supplies (e.g., food, water,
and critical supplies) hospitals will have on hand prior to landfall. These unknown factors add
urgency to the need to define clearly a plan for communications with affected hospitals, and to
define the specific plans for re-supply prior to evacuation.
The consensus of the temporary medical care planning group, confirmed by U.S. Health
Resources and Services Administration participants’ experience in Hurricane Ivan (2004), was
that the estimate of 2,000 patients needing evacuation from affected hospitals was too low. A
total of 926 patients were housed in three of the metropolitan New Orleans area hospitals alone
during Hurricane Ivan.
It is the recommendation of the planning group that licensed beds in affected areas be used as
estimates of the number of patients requiring rescue from affected areas and further inpatient
care. In addition, it is estimated that there would be a minimum of 900 special needs patients,
along with approximately 100 nursing home staff in the affected areas. It should be noted,
however, that nursing home representatives reported a significant problem in obtaining bus and
other transportation for evacuation of ambulatory residents during Hurricane Ivan. It is
recommended that this issue be studied further as part of the planning process. Due to this factor,
the estimate of nursing home staff and residents left in the affected areas could possibly be much
higher.
The total number of inpatients needing evacuation from affected areas is 10,026 and the total
number of staff, family, visitors, victims arriving for refuge after landfall, and others needing
evacuation from affected hospitals and nursing homes is 38,885. This yields a total number of
48,911 for patients, staff, visitors, family, refugees requiring re-supply, and evacuees from
affected hospitals. The 2004 U.S. Health Resources and Services Administration surge capacity
estimate for areas outside of Regions 1, 3, and 9 is 3,116 beds.
The estimated total number of patients requiring inpatient care for the first four days post-
landfall is 11,325. This estimate is the sum of the number of patients from Temporary Medical
Operations Staging Areas (1,299), the number of patients from evacuated hospitals (9,126), and
the number of special needs patients from nursing homes (900).
Using the staffing ratios from Acute Care Center: A Mass Casualty Care Strategy for Biological
Terrorism Incidents2, the following staff would be required for a 24-hour shift to accommodate
the patient numbers referenced above (for a series of 50 bed nursing units): 434 physicians, 453
nurse practitioners/physician’s assistants, 2718 registered nurses/licensed practical nurses, 1812
nursing assistants/technicians, 906 medical clerks, 453 respiratory therapists, 453 case managers,
453 social workers, 906 housekeepers, and 906 patient transporters.
Recent experiences from the 2004 Florida hurricane season added the need to provide for
housing for staff’s family members, if needed, in order to get staff to report to work.
2
U.S. Army Soldier and Biological Chemical Command. Acute Care Center: A Mass Casualty Care Strategy for
Biological Terrorism Incidents. Department of Defense, December 2001.
All the medical treatment facilities in the area affected by the high-water levels will be virtually
useless. At best, they will shelter in place whatever patients they were not able to discharge prior
to landfall.
In addition, refugees (non-injured or ill individuals) will come to treatment facilities for
sheltering. The Louisiana Hospital Association has provided estimates for the numbers of
population at risk (patients by categories, staff, family members, and refugees) (see Appendix
A). The Nursing Homes Association needs to address their population at risk, specifically those
that have residents with special needs.
Several treatment facilities owned by the State and the Department of Veterans Affairs were
identified in the immediate area (and two Veterans Affairs Medical Centers in Alexandria and
Shreveport) that could provide surge alternate facilities. These facilities are the St. Gabriel
Women’s Correctional Facility, St. Gabriel, Louisiana; Jetson Youth Correctional Facility,
Scotlandville, Louisiana; Veterans Affairs Nursing Home, Clinton, Louisiana; and Carville
Hospital, Carville, Louisiana. The Louisiana Hospital Association will identify other facilities
around the State with surge capacity.
The following are Federal assets that may be requested by the State to fill the need for inpatient
and acute care temporarily.
Department of Defense
• Army Contingency Support Hospital (296 beds)
This is a large medical capability that has eight wards providing intensive nursing care
for up to 96 patients; seven wards providing intermediate care for up to 140 patients; two
wards providing minimal nursing care for up to 40 patients; and one ward providing
neuropsychiatry care for up to 20 patients. Surgical capability is based on eight operating
rooms or 144 operating room hours per day. The unit can be further augmented with
surgical/medical specialty teams to increase its capability. This facility requires several
days’ notification before deployment and two weeks to set up.
• Navy Expeditionary Medical Facility (115 beds)
Buildup begins with deployment of a 25–45 person Mobile Medical Augmentation
Response Team, which can arrive within 12–24 hours. This team provides emergency
care and some psychiatric counseling and can treat 200–250 patients per day on a 24-hour
basis for 72 hours. Re-supply will extend duration of operations.
The Mobile Medical Augmentation Response Team can be the advance element for the
Expeditionary Medical Facility. The Expeditionary Medical Facility can be onsite within
two to three weeks, self-sustaining with food service and lodging for staff. The setup time
is one to two weeks (if tent layout is utilized versus building of opportunity).
The Expeditionary Medical Facility has four operating rooms, 15 intensive care unit beds,
and 115 holding beds. It can perform 20–30 life-saving surgeries per day, and has an x-
ray, lab, and pharmacy capable of self-sustaining for seven days before requiring re-
supply. It also provides ambulance service, patient evacuation, and medical regulating.
• Air Force Expeditionary Medical Support System (builds from 10 beds and up by
increments of 25 beds)
The basic Expeditionary Medical Support System consists of a 10-person team that can
care for 500–2000 patients. It provides primary, preventive, and critical care, including a
field surgical capability (20 patients in 48 hours, including 10 life- or limb-saving
surgeries) with four holding beds. It can deploy within six hours of notification. A 60-
person team can care for 2000–3000 patients with 10 hospital beds, basic radiology,
dental, and laboratory support. An additional 20 personnel increases the number of beds
and care to 3000–5000 patients. Additional increments of 25 beds or medical specialties
can be added.
The following resources are available for patient movement from staging areas to Temporary
Medical Operations Staging Areas or definitive care.
Ground Ambulance
Model Litters Ambulatory Attendants
997 Military Ambulance 4 2 1
998 Military Ambulance 2 2 1
Civilian Ambulance 2 1 1
Helicopters
Model Litters Ambulatory Attendants
UH-60 Blackhawk 4 6 2
CH-43 15 25 2
CH-47 Chinook 20 30 2
State Police TBD TBD TBD
Once the State of Louisiana decides to evacuate patients using the National Disaster Medical
System, at the request of the Department of Health and Human Services, the Department of
Defense coordinates with ESF-1 to provide support for the evacuation of seriously ill or injured
patients to locations where hospital care or outpatient services are available.
The Department of Defense is responsible for regulating and tracking these patients to
appropriate treatment facilities (e.g., National Disaster Medical System non-Federal hospitals,
Veterans Affairs hospitals, and Department of Defense military treatment facilities). Using
available transportation resources, and those from other supporting agencies, if necessary, and in
coordination with the National Disaster Medical System Medical Interagency Coordination
Group, the Department of Defense evacuates and manages victims/patients from the patient
collection point (Baton Rouge Regional Airport) to National Disaster Medical System patient
reception areas, using the Department of Defense’s patient tracking and regulating system. The
Global Patient Movement Requirement Center (part of the U.S. Transportation Command) will
coordinate the required beds (using the Federal Coordinating Centers, Department of Defense,
Department of Veterans Affairs, or contract civilian treatment facilities) and airlift possibilities.
In addition to military aircraft, the Global Patient Movement Requirement Center may use
commercial air ambulance companies.
Under the National Response Plan, the National Disaster Medical System would be activated.
Disaster Medical Assistance Teams have been already incorporated into the plan. The
Department of Defense could be asked to provide temporary field medical treatment facilities to
support the relief and recovery. The National Disaster Medical System, Department of Health
and Human Services, Department of Defense, and Department of Veterans Affairs can quickly
provide temporary medical personnel to augment civilian medical personnel. If needed, field
treatment facilities could be set up at flat, well-drained ground.
The National Disaster Medical System provides primary care medical services in austere
environments. As discussed previously, 22 operational teams exist that can function in a self-
sufficient manner for 72 hours, and support triage and primary care operations at each of the
Temporary Medical Operations Staging Areas. Each team can triage and treat up to 250 patients
per 24-hour period. Patient holding, and even limited critical care patient support, can be
provided, but at the expense of primary care services. If asked to provide care for the estimated
7,750 injured victims at the staging areas, all 22 operational teams must be fielded and
augmented with an additional nine developmental teams. These developmental teams are not
self-sufficient and would require facility and/or material support.
catastrophic incident. Each National Medical Response Team can perform the following
specific functions:
a. Provide mass or standard decontamination.
b. Collect samples for laboratory analysis.
c. Provide medical care to contaminated victims.
d. Provide technical assistance to local Emergency Medical Services.
e. Assist in triage and medical care of chemical, biological, radiological, nuclear, or
explosive events before and after decontamination.
f. Provide technical assistance, decontamination, and medical care at a medical facility.
g. Provide medical care to Federal responders on site.
4. International Medical Surgical Response Team: There is currently one operational
International Medical Surgical Response Team, located in Boston, Massachusetts. The
mission of the International Medical Surgical Response Team is to assist in international
disasters at the request of the Department of State and to augment other U.S. disaster
assets outside the U.S. Each team is comprised of 25 medical and five logistical
personnel. The medical personnel include trauma and general surgeons, physician’s
assistants, registered nurses (some with trauma expertise), anesthesiologists, and
paramedics. The International Medical Surgical Response Team provides triage and
initial stabilization, definitive surgical care, critical care, and evacuation capacity. The
team can deploy in four hours and is self-sustaining for 72 hours.
5. Disaster Mortuary Operational Response Team: There are currently 11 Disaster
Mortuary Operational Response Teams. Each team is comprised of Funeral Directors,
Medical Examiners, Coroners, Pathologists, Forensic Anthropologists, Medical Records
Technicians and Transcribers, Finger Print Specialists, Forensic Odontologists, Dental
Assistants, X-ray Technicians, Computer Professionals, administrative support staff, and
Security and Investigative personnel. During an emergency response, Disaster Mortuary
Operational Response Teams work under the guidance of local authorities by providing
technical assistance and personnel to recover, identify, and process deceased victims.
Capabilities include temporary morgue facilities; victim identification; forensic dental
pathology; forensic anthropology; and processing, preparation, and disposition of
remains. The Disaster Mortuary Operational Response Team program maintains two
Disaster Portable Morgue Units at FEMA Logistics Centers (one is in Rockville,
Maryland, and the other is in Sacramento, California). The Disaster Portable Morgue
Unit is a cache of equipment and supplies for deployment to an incident site. It contains a
complete morgue, including workstations for each processing element and prepackaged
equipment and supplies.
would be activated and could begin arriving on site in an additional 24 hours. Assumptions
include the following:
• Ground and air transportation routes are available to move National Disaster Medical
System assets.
• 24 hours post-activation, teams will be in place, setup, and providing care within their
region (East, Central, and West).
• If an incident occurs in one region (East or West), only one third of the assets will be on-
site and providing care at 24 hours post-activation. All other activated teams will arrive
and initiate care within 48 to 76 hours.
• In the event of catastrophic incident, the standard of care will be minimal life support and
patient holding for two to three days.
Based on the specific treatment plan developed for southeast Louisiana, up to nine teams are
anticipated to be staged in preparation for this event. By the third day post-landfall, an additional
22 teams could be brought in if required to meet the projected casualty estimates. In a
catastrophic event, the entire National Disaster Medical System could be brought to bear by the
third day post-event. The timeline for deployment of the National Disaster Medical System
personnel post-event is anticipated to occur as shown in the table below.
Single Nine 31
Care Provided Team Teams Teams
(Patients per Day)
Treat and Release
250 2250 5000
(Outpatient Facility)
Treat and Limited Holding
160 1440 4500
(Alternate Care Facility)
Standard Medical Holding Facility
50 450 1400
(Hospital Ward)
Mass Casualty Incident
150 1350 4200
(Holding Collection Facility)
The National Disaster Medical System has approximately 1800 medical personnel that could be
deployed for a catastrophic event. It is estimated that between 300 and 1100 personnel can
support the triage and primary care operations at the Casualty Collection Points and Temporary
Medical Operations Staging Areas. The remaining 700 could be made available for definitive
care support. A summary of the National Disaster Medical System force strength is shown in the
table below.
The Commissioned Corps Readiness Force can provide the following approximate staffing:
• 50 total medical personnel in the first 24 hours
• 150 total medical personnel within 48 hours
• Possibly support two rotations of 150 for two-week increments for a total of one month
• Unable to provide long-term support after one month
Commissioned Corps officers can provide a wide variety of public health and medical services
(both domestically and internationally), to include:
1. Providing direct medical and dental care to disaster victims and/or responders:
a. In support of community clinics or hospitals.
b. To augment the National Disaster Medical System Teams.
c. To augment the American Red Cross in shelters and outreach programs.
d. To provide prophylaxis or vaccination teams to communities, to include utilization of
the Strategic National Stockpile.
2. Providing mental health and social work services to victims and/or responders:
a. In support of community clinics or hospitals.
b. To augment the Disaster Medical Assistance and Disaster Mortuary Operational
Response Teams.
c. To augment the American Red Cross in shelters and outreach programs.
d. To support prophylaxis or vaccination clinics.
3. Providing occupational health support to responders. Corps officers can provide
occupational health support to include personal protective equipment, environmental
hazards, hygiene, food, water and sanitation, mental health, and social work services to
victims and/or responders:
a. In support of American Red Cross operations.
Points of Contact
DHS/FEMA Point of Contact
DHS/FEMARegion VI
Attention:Joe Bearden
800 North Loop 288
Denton,TX 76209
(940) 898-5470
1
DRAFT
2
DRAFT
within the Parish boundaries and if the resources of one Parish are
required in a neighboring Parish.
xxvii. Parishes are responsible for independently establishing local
distribution points.
xxviii. A representative from each agency (Federal, State, and local) will
be available for decisions.
xxix. Local distribution points will be in place and operational within 72
hours (almost the full system).
c. Organizations
i. Federal
1) The Federal Department of Homeland Security (DHS)/Emergency
Preparedness and Response/Federal Emergency Management
Agency (FEMA), has the responsibility for the coordination of
Federal emergency/disaster operations and resources in support of
State and local government capabilities.
2) Supporting Agencies
a) U.S. Department of Transportation
b) U.S. Army Corps of Engineers
c) U.S. General Services Administration
d) U.S. Department of the Interior
e) U.S. Coast Guard
f) U.S. Department of Energy
g) U.S. Department of Defense
h) U.S. Department of Agriculture (Forest Service/Food and
Nutrition Service)
i) U.S. Department of Veterans Affairs
j) U.S. Department of Justice
k) U.S. Department of Housing and Urban Development
l) U.S. Postal Service
m) U.S. Bureau of Prisons
n) U.S. Department of Commerce
o) U.S. Department of Labor
p) Office of Personnel Management
q) Corporation for National and Community Service
ii. State
1) The Governor has the overall responsibility for emergency
management in the State and is assisted in these duties by the
Louisiana Office of Homeland Security and Emergency
Preparedness (LOHSEP) Director.
2) Supporting Agencies
a) Louisiana Department of Transportation and Development
b) Louisiana National Guard
c) Louisiana State Police
d) Louisiana Department of Public Safety
e) Louisiana Department of Wildlife and Fisheries
f) Louisiana Department of Social Services
3
DRAFT
4
DRAFT
2. Mission
The mission for transportation, staging, and distribution is to stage, transport, and
distribute critical resources prior to and following a catastrophic hurricane in southeast
Louisiana. These resources include, but are not limited to, generators, ice, water, food,
response assets, and temporary housing.
3. Execution
a. Concept of the Operations
i. Timeline for Transportation, Staging, and Distribution Operations
1) See Appendix 1: Transportation, Distribution, and Staging
Execution Timeline
ii. Site Identifications
1) Federal Operational Staging Areas (FOSA)
a) Lead Agency
i) DHS/FEMA
b) Primary Location
i) Camp Beauregard, Rapides Parish
c) Alternate Locations
i) Camp Minden, Webster Parish
ii) NASJRB, New Orleans
2) Federal Mobilization Centers
a) Lead Agency
i) DHS/FEMA
b) Primary Locations
i) Barksdale Air Force Base, Caddo/Bossier Parish
ii) Fort Polk, Vernon Parish
3) State Regional Staging Areas (SRSA)
a) Lead Agency
i) LOHSEP
5
DRAFT
6
DRAFT
7
DRAFT
8
DRAFT
b) Clothing
c) Decontamination kits
d) Pumps (water)
e) Disaster Mortuary Operational Response Team (DMORT)
supplies (e.g., body bags, refrigerated trucks)
f) Insect repellant
g) Family living kits (for travel trailer/motor home)
3) The timing and distribution of critical resources will be largely
dependent upon context (size of storm, local needs, local resources,
and the impact). Timelines are most effective for Federal and State
planning (upstream), but flexibility and general timelines are more
useful for local and Parish planning.
4) See Appendix 4: Concept of Operations for Distribution Planning
for the State of Louisiana.
5) See Appendix 5: Local Distribution Point Planning for
Commodities (United States Army Corps of Engineers, June
2005).
6) See Appendix 6: Commodities Planning (United States Army
Corps of Engineers).
iv. Transportation
1) Lead Agency
a) U. S. Department of Transportation
2) Types and Sources of Transportation
a) See Appendix 7: Transportation Lists.
b) Movements of Federal personnel, equipment, and supplies
are managed through prioritizing shipments. To facilitate
the prompt deployment of resources, priorities for various
incidents are developed and maintained through an
interagency process led by DHS prior to an incident to
facilitate the prompt deployment of resources. Each ESF is
responsible for compiling, submitting, and updating
information for inclusion in the ESF-1 prioritized
shipments.
c) Military transportation will be provided in accordance with
the Defense Support of Civil Authorities section of the
NRP and the Memorandum of Understanding between the
Department of Defense and Department of Transportation
concerning commercial aviation programs.
3) Assessment of Infrastructure/Routes
a) State Roads and Bridges
i) Louisiana Department of Transportation and
Development is the lead agency responsible for
damage assessment, repair, and debris removal of
State highways, State bridges, and the interstate
systems.
9
DRAFT
10
DRAFT
11
DRAFT
12
DRAFT
13
DRAFT
14
DRAFT
15
DRAFT
16
DRAFT
17
DRAFT
18
DRAFT
19
DRAFT
i. General
1) Agencies will be competing for resources, which will require
Parishes to call for more resources. Primary sources are routinely
utilized, but in the event of additional needs, the group has
identified a number of sources for labor and equipment at the local,
State, and Federal levels.
2) The State and Parish EOCs should coordinate regularly regarding
site needs and expectations. Once sites have been identified, they
should be prioritized in terms of location and event characteristics.
ii. Existing Resource Conflicts
1) BOOS
a) Water vessels
b) Air transportation
i) Rotary wing/chinook (both injured and uninjured)
c) Fuel
i) Aviation
ii) Water craft
iii) Ground
d) Ground transportation (both injured and uninjured)
i) Buses (refugees and responders)
ii) High water vehicles (refugees and responders)
e) Support commodities for responders and victims
i) Water
ii) MREs
iii) Tents/tarps
iv) Light towers
v) Portable toilets with service
f) Light maintenance
NOTE: Empty aircraft en route to the impact area to pick-up
survivors will carry food/water to lower priority victims, as
prioritized by air crew.
2) Initial Refugee Collection Points
a) Water vessels
b) Air transportation
i) Rotary wing/chinook (injured)
c) Fuel
i) Aviation
ii) Water craft
iii) Ground
d) Ground transportation (uninjured)
i) Buses
ii) High water vehicles
e) Support commodities for responders and victims
i) Water
ii) MREs
iii) Tents/tarps
20
DRAFT
21
DRAFT
b) Fuel
i) Aviation
ii) Water craft
iii) Ground
c) Ground transportation/support equipment
i) 53’ trailers
ii) Tractors
iii) MHE
iv) Golf carts/gators
v) Light towers
vi) IT/network communications
vii) Support staff
d) IRR Shortages
i) Water
ii) MREs and items for infants (e.g., baby food, baby
formula)
iii) Generators (for critical infrastructure only)
iv) Ice
v) Tarps
1. Roofing
2. Miscellaneous
vi) Cots
vii) Blankets
viii) Sleeping bags
ix) Personal toilet kits
x) Personal wash kits/Camp kits (personal hygiene)
xi) Flashlights with batteries
e) Maintenance
f) Security
6) Local Distribution Points
a) Forklifts
b) Pallet jacks
c) Light towers (generator type)
d) Portable toilets with service
e) Tents (any temporary shelter or canopy)
f) Tarps
g) Dumpsters with service
h) Two-way radios
i) Special equipment operators
j) Multi-lingual staff
k) Community relations people
l) Security/crowd control
m) Labor
n) Incident Management Teams (U. S. Forest Service—tied
into LA Department of Transportation and Development)
7) Billeting/Base Camps
22
DRAFT
a)Ground transportation
b)Food
c)Bedding
d)Shelter (e.g., warehouses, tents)
e)Water
f)Shower
g)Laundry trailers
h)Location/proximity to other sites
i)Incident Management Teams (U.S. Forest Service—tied
into LA Department of Transportation and Development)
j) Power generation equipment
k) Medical support
l) Security
8) DMORT
a) Refrigerated trucks
NOTE: Refrigerated trucks will be required across many
agencies. There may be a resource push for these trucks;
however, that may occur at the staging level and not at the
distribution level (although it would clearly impact the flow of
resources into distribution points).
b) Body bags
c) Earth-moving equipment
d) Security
c. Personnel
i. Staging Areas
1) See Appendix 1: Transportation, Distribution, and Staging
Execution Timeline.
ii. Local Distribution Points
1) Personnel requirements for the local distribution points will be
decided later (see Appendix 3: Letter sent to Parishes regarding
identification of Local Distribution Points).
2) Individual worker numbers to be determined through the United
States Army Corps of Engineers software with Parish information
sources (see Appendix 4: Concept of Operations for Distribution
Planning for the State of Louisiana).
23
DRAFT
b. Communications Requirements
i. In the event that normal means of communications become overburdened
or destroyed, State Communications and Information Processing
Personnel shall use private industry, amateur radio teams, and Federal
assistance while re-establishing primary communications systems.
1) Layers of communication backups exist, but the event may limit
communication methods.
2) Communication will largely be radio based, as one cannot rely on
cellular communications during this time.
3) Equipment will include 800mhz radios, satellite phones (minimal
use as a backup), and/or HAM radio operators to support
distribution communications.
ii. The State Communications Coordinator will canvass State, Federal, and
local communicators to ensure that all communications and information
processing media have been restored to normal operations.
1) Communication flow: Local Distribution Point Site Manager to
the local EOC (via E-team when available) to the State to FEMA
iii. Communications are established and maintained with ESF-5 (Emergency
Management) to report and receive assessments and status information,
with ESF-7 (Resource Support), the National Response Coordination
Center, Regional Response Coordination Center, or Joint Field Office.
iv. FEMA internal commodity tracking logs are required and used for
tracking commodities received and shipped from FOSA sites. With the
aid of the U. S. Forest Service, this information is gathered upon both
arrival and departure of trucks to the FOSA. The information included in
this tracking log includes the positive control number assigned to the
truck, the date, time, driver’s name, contact number (cell), tractor
number, trailer number, and commodity being hauling (see Appendix 8:
Commodities Tracking Logs).
24
DRAFT
25
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 1
Appendix 1: Transportation, Staging, and Distribution Execution
Timeline
Pre- operations)
Landfall Determine size of footprint.
(H-72) → 480,000 ft2 (10 to 12 acres)
Determine number of Material Handling Equipment (MHE).
→ Two full MHE kits (forklifts, pallet jacks, ramps)
Determine size of warehouse requirement.
→ 1 to 50 ft. truck of baby food (22/pallet truck) 64
ft2/pallet—total 1,408 ft2
→ 1 to 50 ft. truck of diapers (1,408 ft2)
→ 1 to 50 ft. truck of baby formula (1,408 ft2)
→ 1 to 50 ft. truck of bottles/nipples (1,408 ft2)
Determine shuttle driver process and additional transportation
requirements for specialty items.
→ 25 shuttle drivers/SRSA
→ 26 ft. panel trucks (~14 pallets)
Determine ownership transfer.
→ Upon receipt at the staging area
Pre-
Air (heavy lift rotary wing on request—4)
Landfall
● Identify/validate sources of buses and drivers.
(H-70) 600 buses—50 passengers each (Local/State/Federal)
1200 drivers—(Local/State/Federal/Volunteers)
● Pre-Stage Louisiana Department of Transportation and Development
equipment for ContraFlow.
● Identify personnel and equipment for ContraFlow.
● FOSAs
Team, equipment, commodities start arriving (150+ trucks)
● SRSA—Pre-Deployment Activities (per staging area)
Order Federal resources
Shuttle drivers—25+ (if additional are needed, make request)
Empty boxes—25+ (if additional are needed, make request)
MHE (e.g., forklifts, pallet jacks, ramps)—10 sets (predicted
upon breakdown requirement)
Personnel—requirements unknown at this time
Pre- Light Towers—8 to 12 sets
Landfall Security
(H-48) Fuel and life support requirements for entire staging area team to
include contractors, truck drivers, etc.
Fuel—1 to 5,000 gallon tank (diesel) MOgas (50/gallon
per truck) 24/7 refueling is desirable at the SRSA
Food—base camp supplies (contract kitchens)
Bathroom facilities—1 porta potty per ~25
Contractors (truck drivers, truck support personnel)—
power team—100 people
Shuttle drivers—25 drivers
Pre-
tropical storm winds. Includes areas south of the Mississippi River,
Landfall
which are levee protected but remain vulnerable to Category 2 or
(H-40) higher storms. During Phase II there are no route restrictions.
Pre-
Mississippi River in the New Orleans Metropolitan Area which are
Landfall
within the levee protection system but remain vulnerable to a slow-
(H-30) moving Category 3 or any Category 4 or 5 storm. During Phase III,
certain routes will be directed and the Contraflow Plan implemented.
● FOSAs/SRSAs
Pre-deployment activities continued
Pre-
Landfall Finalize transfer of ownership procedures (upon receipt at
(H-24) SRSAs).
Government to Government procedures (communication
between Parish, State, and Federal Government)
Operational period (24 hrs/day day/night shift)
Identify shortages.
Identify Communications shortage (e.g., walkie-talkies,
radios, cell phones, laptops).
Federal partners arrive (State/Federal Coordinators)
° 2 per shift per staging area
State SRSA teams arrive (H-24 to H+24)
190+ people per staging area (working #’s)
Receiving—15/shift—30 total
Shipping—25/shift—50 total
Transload—50/shift—100 total
Security—5/shift—10 total
Life Support (Medical, Safety, etc.)—TBD
Commodities/Equipment arrive
● Backfill/Sustainment
Tractor-trailers (commercial assets controlled by
Landfall
(H-Hour) DOT/FEMA/GSA)
Buses (commercial assets controlled by DOT/FEMA/GSA)
Rail (commercial assets controlled by DOT/FEMA/GSA)
Air (commercial assets controlled by DOT/FEMA/GSA)
● SRSAs
SRSA teams arrive at staging areas
Post-
MHE arrives
Landfall
Empty trailers/shuttle drivers arrive
(H+24)
Commodities start to arrive (H+12 to H+36)
Commodities distributed (H+24 continuing)
Landfall – and TMOSAs to Trans-Shipment Points (Shuttle
Recon/ Staging/Reception Areas).
Rescue Buses
(H+48) Air
Rail
Water
● Transport victims, refugees, and commodities from Trans-
Shipment Points to temporary and long-term shelters.
Buses
Air
Rail
Landfall – Staging/Shuttle Areas, and Trans-Shipment Points
LSA Road
Hubbing/ Rail
Sustainment Air
Water
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 2
Loo',',,, P"',h 0' '0" -Pol.."",
P"'sh ,'" REOMOAType Foelll'yName Phy,'oo'Add,... CKy Zip Fad"'y Ph 1 Coo"d 1 OOo'ad 1Wi<Ph. Cootact1HmPh. Coota,' C,II Con'act 1Pg' Contact' Coot,d 'Wi<Ph. Contact, HmPh. Con"ct, C,II Cootad , "",
A~d'a 59.168 4 X 05 Ray.. CM,C..,,, 112FmgF..',,, 0,. Ray.. 70576 337-334-9976 J,m"J. P.III~ao R,"'rtD.H."rt
A~d',
All.. 25,407 5
4 X OS
X OS
R'ooF"'''''60lld'""
609TIg"Lao.
Cmwl.y
0"'",0
70526
70655
337-766-4124 TimRo"'"'''''
-"..
377-639-4396 JohoRI,h",OEP
, ,,,b.lI. HO","y,
J'ho Oood"y
All," 5 OS "" Sob-Stal'oo 206E,M"o EI.''''1Ii 70636 3186343473 JohoRi,h",OEP Thorn" Moo"
All," 5 OS "" SI'lioo 115N.10th5'"" O,kda'. 71463 3183351155 JohoR''"".oEP Thorn"Moo"
All.. 5 OS "" St"'oo O"',lio 70655 3376394333 JolioR',h".OEP Thorn" Moo..
All.. 5 OS "" Sob-S',lioo 31"..d 51 R."" 70668 3376662405 JohoR',h",OEP Th'm"Moo"
A,oo,,'oo 87,164 2 X RPOD L'm" 0000 E,po C..", 903951.Laod"IRood Go""I" 70737 225"21-1700 FloMag", O".d..
A,oo,,'oo 2 X OS 5""0" Ciw'C..," 9608Ain'.. Hwy S..,.." 70778 225-675...59 K..oy Mala"" 8"h CI"k
A"",,"o 2 X OS '.maooC..,,, 1100C"y 0' Do"'d",,,'"' 70346 225-473-0657KoooyM",,,, Saod"C..,
A,,"mplioo 23.234 3 X OS A',"mpliooPao'"H""h Uoll 156Hwy1008 N'poloo,,"', 70390 965.369-6031 D",dLyoo R',".,,,C"II..
","mplioo 3 X OS 5' ""'ph Th. W..k" P,,',h H," 3306Hwy70Soo'h PI"" P,rt 70339 965-252-6868 50"0 Hoe Coo'giao" Co<
","mplioo 3 X OS PI".. P,rt M'dd" 3321Hwy705 P'.". P,rt 70339 965-369-2956 Cw.. 600d,,,,,,, RobyM.,..,,,o
A',"mplioo 3 X OS A,,,,mp'looH'gh5,"0°' 4660Hwy308 Napo'oo,,"', 70390 965-252-6359JoeyCom""" 000T'""
A,"y.II" 41,961 6 X as 600k" H""h UM 220Soolhw."M"o 51. 800k" 71322 318-346-25650..,,,, Thompooo Aog.'a
Gaol"'"
A'"y.II" 6 X OS A,"y.lI"p",,., H""hUoll 657Go"mm,"1 5' Ma~wlII. 71351 318-253-45260..,,,,Thom""o "ho Napoo',k
~, ".-
6"0"g,,d 34.094 5 X OS M""I'iI'. HlghS'hool 7061Hwy110W.. M,,<y"'" 70653 337..25-6046 C"o M,,~, OEP Thorn"Moo"
8"0"g,,d 5 X OS Slog" H'gh5,"0°' 153Hwy110E", Slogor 70660 337-463-5606 G'ooM..~, OEP
B"o"g"d 5 X OS E'. B."".g"d H'ghS'hool 5364Hwy113 0"1C"" 70637 337-326-7511GlooM..~. OEP
~-
B,..,m.
BO~'"
Bo~'" .
7
104,080 7
7
X as
X RSS
OS
R'o,oIdH'ghS,hool
80~'''C'~ C"" C..."
'oo'.,oeDowoo
4044B,..,m. Rd
620B..,oo Rd
8000Ea.T"" 5'
RIO,o~
8'~I "C'
8'~",c,~
. .
~
71068
71111
71111
316"'4-2271
316-741-8900 Rolh F",,'oIh
VI ::::: ()
,'--<
. .-+- -
(1)
.
1..-
"'''18,,,,
Bo~'" 7 OS C..lo",.' C..." 2000C,"o<yl.,Coo'"0, Bo~",Cily 71051 (/) '"I:j
Bo~'" 7 X OS Bo~'''H'ghS'hool 777 B."kat0, Bo~'"C'~ 71111 318.549-6680
D.C.M,'".. :--- g. ::r'
\ .J 0... 0
Bo~'"
80~'"
Bo~'"
7
7
X OS
X DS
7 X OS
BoolooH'gh 5,"00'
"',,"' H'ghS,",oI
HaaghlooH"h S,hool
6136 Hwy 3
2601A""" D'
210E,,' M,,"o'.y
BOO'oo.
800"" C"y
Hoo,h'oo
71006
71111
71037
318-649-5240 D.C. Moohoo
316-549-5060DC.Moo",o
318-549-5450 D.C.Mooh,"
.VI ~ (1)
~
Boo,'" 7 X OS P'''''''y H'gh5,"001 430IPoo'h" Boo""C'~ 71112 318-549"910 D.C.M,,"oo VI VJ
Bo~'" 7 X OS P"'o 0"'., HighS,"ooi N ~ ~
-300E.V,"oo--'" Pla'oD.."og
"" 71064 318-218-9369 DC. Mooh..
-_C, "-"-~
Coddo 251.506 7 OS CoddoP,,,,,,H,,"hUo" 1035C",w."", Sh""port 71101 0- a 0"
~::::
C,ddo
; g; ~~:.~:~~~~:,:~~:';:~M'"
7 X OS
~~~~.::~.~" ;:;:::::~ ;::~:
Northwood H'gh 5,"0°' 5939 Old Mo..'og,port Rd Sh.."port 71107 316-929-3513 R,y C. M.."y
X:::::
~ 0- (1) (1)
Coddo
C,ddo
7
7
X OS
X OS
Soolliwood H'gh S'hool
Hoo"ogloo H'gh5,"00'
9000 Walk" Rd
6601R,,""<Y'0
Sh'",port
Sh""port
71118
71129
318-686-9512 Roy C. MOH'y
318-667..655 RoyC.MOHay ~
0... ~ RooF..","
RooF.."..
C,dd, 7 X OS C'pl,'o Sh"" H'ghS,"ool 6115 Ea. K'og' Hwy Sh""port 71105 316.658-7137 Roy C. Mooey ~ 0- ~ Roo,.."..
C,ddo 7 X OS NorthC,ddoH'ghSchoo' 201A',port0, V"'.. 71082 316-375-3256RoyC.M",.y 0... '--<: ~ Roo"."'0
C,dd, 7 X OS ""p"k HighS,hool 3222G,,,owood
Rd Sh""port 71109 318-635..181 RoyC.MOH'y ,.-., .-+- 0... Roo"."'0
0\ ::r' (1) .
~(1)a
"Tj~
@ =:
(1) ~
0...0...
0 0...
a0 @ IZ>
Parish "04 Pop", REO MOAType 'ootll'yN.me Phy.I,,'A""'... City Zip FooilliY~h1 Cootad1 Coolad1Wi<~h.' >-+> ~ ~coo"~'1PO' Conloc'2 Con,ocl2WkPh. .~.o''''U!m~h_,Con'act2C.1I Coo'act2fo'
C""... 184,961 5 X RPOD L'k. Ch"',,C'," C..." 900Lak"ho" 0, ',k. Ch,,'" 70601 337-491-1256JooephToop, S" VJ
~:::~:: ; ~ ~~OD ::~~~,~~:;"m ;~: ~~~;;; ~::'C~;"'" ;:::~ ;;;~;~~;~ ~::,~~:::. '=" ::r' Poo'R,iowa",
C.I"'.. 5 X OS -D.,o'ooyH'gh5,"001 207North0"",0 D.Qo'ooy 70663 3377665251 B.. F"ok"o §~ Roo Hay"
~:::~:: ; ~ g; ~:W~H~:~':~~~5,"001 ~~OM;'~'N"oe ~:;: Ch,,'" ;:::~ ;;;:,~:~ ::~~::~:::: ~ (1) ::~ ~::::
c"",.. 5 X OS "G"og. H'gh5,"001 3420loo,"..,A". L'" Ch,,", 70605 3374774571B..F"ok"o ~ 0- RooH.y"
C"",.. 5 X OS L,k. Ch,,'" Bo.ooHigh5," 1509E""pM", BI'd. LakeCh"'" 70601 3374369594 B.oF"ok"o r=. (1) Roo Hay"
Cat",.. 5 X OS W'''''og''o M.Moo H'gh 5,"001 2602 P'o,,"w ',k. Ch"',, 70601 3374335692 Boo'"ok"o 0 (1) RooH.y"
Cat",.. 5 X OS S,m Hoooloo H'gh Schoo' 660 5'01 Hoo"oo Joo" "k. Char'" 70611 3376553526 Boo F"ok"o ~ ~ RooH.y"
C.,,,,..
C"",..
C.,,,,..
5
5
5
X OS
X OS
X OS
St"k, H'ghS,"oo'
So'ph.. H'gh 5,"001
'VIO'OOH.h S,hool
137 Hwy 1095
100Sy"mo.. 51.
1603 G"".
S'ark,
Solph..
VIOloo
70661
70633
70668
3377435341
337 527 6679
3375697223
800 F"ok"o
B.. F"ok'IO
B.. F"Ok'IO
>a Roo H.y"
RooH.y"
RooHay"
C.,"'.. 5 X OS -W..',k. H'gh 8ohool 1000 Gard.. 0'''. W..',k. 70669 3374336866 B.. '"oklIO .-+- Roo H,y"
CatdWa" 10,B37 ~ I.
C,m"oo 9,681 5 X OS C.m"oo EI.m.."<y 5,"001 510 M,,"',II 51 C.m"oo 70631 337-775-551B '"ddl. R''""d,OE Roo H,y"
C,m".. 5 05 C"od L.k. H'gh Schoo' 1039 Hwy 384 G"od ',k. 3375982231 F"ddl. R,,",,d.OE
C'm"oo 5 OS Hoc""',"1 H'gh 5",0°' 1390 Schoo' 5' H.",,,,,<y 70645 3377623305 F"dd" R<hard.OE
C.m."o 5 OS Joho",o 8,yoo H'9h 5,"001 6304 Goll Bmh Hwy Joho",o B,yoo 3375692'36 '"ddl. R<hard,OE
'" .
Cat.hoola
C"lbom.
10,627 6
16.471 7
X OS
X OS
Cat,hool, p,,,," H""h Urut
9960 Hwy 79
Joo",m.
Hay..",II.
71343
71036
-
316-339.6352
318-624-0905
AoO" App,.by
Ga<y Joo"
t
Joho Napo""k
D"dI.y G"oo
.
Clalb'ma 7 X DS H'm" High S'hool 1006 North M.'o Hom" 71040 318-927-2965 Ga<yJoo"
i,
COI""'d" 19.724 6 X OS Coooord" P,rt,h H""h Uoit F"'lday 71334 316-757-0032 Ma<ySpooo Joho Napoo_k ,
D.Soto 26,231 7 X OS Moo,..'d High S'hool 401 ,"og' Hwy M-:";'d 71052 316..72-0793 T,mm,era', ,
0.5010 7 X OS NorthD.So"H'ghS,hoo' 2571 Hwy171 Slo",w.1I 71036 316-925-6917 TommyC"ig Dodl.yGI..o
EB.looRoo,e \ 412,633 2 RSS Dept,°, Ag.W,"eho,,, B.looRooge
EB"oo Rooge 2 X DS Beth'"yWortdP"y" Cft.N P',"' Rd B.,,, 70714 225-774-1700 Dm,
EB"oo Rooge 2 X DS B,lh,"y WortdP"y" Cft.So",h 1101Ho,,,. L' B.,ooRooge 70709 225.293-2100 DooS.m. G.", Mi""
EB.to, Rooge 2 X DS B,,,emoolG,," HALL 7370Ai,,,,,Hwy B.,ooRoog, 7OB06 Vem. J."",
EB.to, Rooge 2 X DS B.looRoog,M.g"l High50001 2825G""'mootST B.looRoog' 7OB06 225.383-0520 N,""" G"", p", Pe"y Wogh',C,,,
EB.looRoog, 2 X DS BIO.dmo"H'ghS,hoo' 10100GoodwoodBWd B.looRoog. 7OB15 225.926-1420 D.'Y'G',,", P'i, R.H.milto"C,,'
EB.lo, Roog' 2 X DS Cen',,' HighS,hoo' 10200E,B,ook'ldeD, B.,ooRooge 70B18 225-261-3438 Roo,ieD"''',P,i, CI.m"BIOw"C,
EB.lo, Rooge 2 X DS C.pilolHighSohool 1000N231dSI B"oo Rooge 7OB06 225-383-0353 EttooB'oo',P,i, Eddi,D"I.,C,,'
EB"oo Rooge 2 X DS G., 0." HighSohool 6650C.d" GIO" B"oo Roog. 7OB12 225-356-4306 Mild"dHoo'Y,P,i, Ciri..G'p""AP
EB"oo Rooge 2 X DS RobertELooHighSohool 1105LooD' B"ooRooge 7OBOB 225-383.7744 Joe' Sto,.Id,P,i, H"dyWonen,C,,,
EB"oo Roog. 2 X DS T." HighSohool 9I)021M"I.h.II B.,ooRoog. 7OB06 225-927-6100 JohonyJoe'''',P,i, J.m" N.wm,",AP
EB.looRooge 2 X DS Woodl.w,H~hS,hool 15755OldJoff."", Hwy B.'oo Roog. 7OB17 225-763.1200 Joh, M,C.on,P,i, R.S,"gg',C,"
E.C.nott 8,954
EF."o,", 2O,9SO 2 X DS Joe'''' SohoolCompl" 3501Hwy.10 Joe"', 70748 225-634-5931 P"I Kenl.S'p' F Jo"phJoo", P,i,
E"'ge"ne 35,45' 4 X DS North"deCi", Cen", 704N5011",51. V,II.PIette 70586 337-363-7478 R"nelSm"" Roo,,, I.end",,,,
E"'g,"ne 4 X DS M.mooR..".,..., Compl" 94M.,"SI M.moo 70554 337-468-2595 J.m" Fonlooo' H.""," CeI""ne
F""", 20,812
G,,'" 19,139 6 X DS G"~; Peo'" H""h ""it 513E'gh'h51. CoI~, 71417 318-627':""" T,"y,C,,",~ j;h' N.po",,'
G",I 6 X DS G",I P,,',h Ci,i, Cool" 420Rioh."", D, Cott" 71417 RobertMoo'" Joh, N.po,i,'
~
I: , :E
VI (')
~_. (1)
-
.~
"~.Con'ac'-z ,.ph-]
P.rl.h
,be,,, 2,.. PoP,,' 74.4494
REGMOAType Fac""yN"",Sohoo'
DS W..g."H'gh Phy.',,'
Add.",
'''endRd clly.
230SJ,""", N,w'be'" Zip
70560 FacUttyph,Con"'" . .....-
'-<
'be,i. 4 X DS N.w'be'" Seni" High 100'E.Adm,Doy',D,. N,w'be,i. 70560 337-369-6412 J"'R,," (/) ~ "'0 C,rtL,"''Y
'be,i.
'beNit"
4
32,497 2
X DS
DS
J",,,.tt, Seni" HighSchoo'
'beNitteP,,',hCi'i, Cen'"
B217E.OldSp,"i'" T"iI
24700JGB""tt BI,d
J"ne"tt,
P"q"mln,
70544
70764
337-276-6038 R.ymoodM""",
L",i, OoilO',OEP
~ 0~ g 0.. :::I
Cy,'hi. A'lo'ne
!b'N,II, 2 DS E." 'beN,II,H'ghSohool 3285 Hwy 75 SlGebne' 70776 L,",i, DoilO',OEP ~~ (1)
Jeok",
Jeok",
15,278 8
8
DS
DS
Jon"bo"
Jon"boIO
Hodg, Middl, Schoo'
Hodg,HighS,hoo'
440 Old IM",.1d Hwy
225P'ffihl,g
Hwy.
Jon"b"o 71251 318-259-6611
Jon"boIO 71251 318-259-4138
D",dJoo"
Roo.""tt B~.nt N ~ :::I
, ,- ~ V,,,Boo'"Joe
Joe'''' 8 DS J P Commoni~Cen'" 1821,dool," P.rt<Rd. Jon"bom 71251 318.259-8675 D,.C"'"" G""II t, ~ 0" S R,"d,IIH""'gto,
JeIlD,,"
J.IID""
31,235 5 X D5
5 DS
J.IID"',M,lIi-P",po,,B"lding """.Arl'",A..'"",,26, J''''"9'
EllonH'ghSohoo' 9032nd Elloo
70548 337-824-7301Em''YB''."
3375842991 Thom..D"hol"
N:E cr'
'-"' (1) ~ Ci'dyA,hen,
JellD"" 5 DS Fen'onH'ghSohool 5091" Fento' 706'" 3377562326 Thom.. D"hol" 0..en
J,II D"i, 5 DS L." Arth",Hi9hS,hoo' 437411g"Len, CO'eArth", 70549 3377745152 Tbom.. D"hol,' § cr'
JellD"" 5 DS W".h HighSohool 304Boo'g"" W".h 70591 3377342361 Thom.. D,,",Io' 0.. "'<: §
Jeff"", 453,590 1 X RPOD Pon""'""", Cenlo' 4545W,IIi.m.BI,d Ken,,, 70054 504-465.9985 L" C"". , , 0.. Z,b M,y".
Jelf"", 1 DS J,IIP"i'" H""hU,it"M.",,, 1855Am"B',d M'''." 70072 0'\ ~ (1)
~:~:::: : ~~; ~,~,J~:'':.'~i~~~~~~~01
:~,"~~:::~;;P',,, ~:::::: 70001 ;=:;~;~ =~~di.,~~~~ ':-' (1) S ~~:;~~::':'
J,If"", . X DS Ri"'"'' Middl,Sohool 3900Jeff,,,,,, Highw'y J,ff,,,on 70021 504-828-2706 R,""y Bennell,A"II >-rj ~ LJ. T.y'"
J,""", 1 X DS Ri","" H~hSohoo' 2'" R'",d", °"" J,If'ffion 70121 504-833-7288 Con,i, TiIi.,.. I (is :::.: Re9i'''dw,"'.m'
J,If"", 1 X DS Co<,Ho'en,J,m" HighS,hoo' 2200I.'P"oo Boo'''',d H'N'y 70058 504-367-6388 P"'y M.p""", (1) F.ithJo"ph
~:~::::~ : ~~; ::~~:::~7.,:~'~~~';::"
;~~:~i~"'" ~:~,:; ~~: ;~:::::: ~,:;::.:::" 0.. ~ A'" Ho'm"
J,If"",
J.lfe"",
1 X DS
1 X DS
F"d,Hen'Y,Jon., HighS,hoo'
L,,,,d.i,Jon",H,ghSohoo'
435SoolhJ.mi,Boo'''',d A",d".
925L'''''.'A"'" T."'I'ow,
70094 504-436-2474A"enH,y"
70056 504-393.7544Sh,",onV.",II
g 0..
;::J (is
K..i'M'h'
M"gi.F,oem,"
Jeff"", 1 X DS Eh"Uob" High5'",0' 4300P""015',,,, M.""o 70072 504-340.7651 G,'YB"", en Thorn"°'Y
J.ff"", 1 E..,,,,,, P.M.H'ghSohool 8600B,"" "',,' M.,.i,,, 4431452Joeq,,''"' P."", 0 en
J.ff,,,on 1 F.'"hitd,J,B"Jon<"HighSohool 3900J.""", Highmy J.If."", B362636Hoo'YSh"" (1)
J.ff"", . W,."'" P.M.Hi9hS,hoo' 8800B,"i"D,'" M.I.,", 4431452J'q,"inePi"'", >-; en
J.ff"", 1 G"I.. Jooi" High7th 910G,,", Boo"",d G"'ne 3669292 F,,,o,"o Mendo," :::I ,...,..
J.""", 1 M.rty',Joh,H..HighS,hoo' 1108Sh"w"',~Rood Jell"", 8333711M,ti...C"dle '='"' .....
J.ff,,,,,, 1 X DS G,,'noJooi"HighSOhoo' 910G,,", Boo'""d G"I.. 504-388-0120G'enG,,, 0 ~ E,..belhD"i,
J,ff,,,,,, 1 X DS H'ggi""L.W,HighS,hoo' 7201L,p,'o Boo'.."d M'""o 70072 504-341.2273 C"o'Y' VenN"m,"
,..",.." -
,
b.,::!
::! ~ L
D"""M,~"i"
CO5"," 14,161 6 X DS L. S.IIePOI''''H"," U,iI 304BN,",. 5' Jo.. 71342 318-992-4842 D.no E"", ~ cr' R,""" bligg,
CO"". 6 X DS L. 5.", High 1460B'" SI 011, 71465 D.b Poo' ~. (1) Joh' N.po""
0 (1)
L.,.y..,
L.toyeti.
195,7074 X RPOD C.,oodom.Co",,"'~,Cen'"
4 X DS C"ondom.
444C.,ondom,B"d,
444C.joodom'B"d.
I..~y""
L"'y'ti.
70506 337.265-2100G"gD""
70506 337.265-2100 G"g D"i,
:::I :::I PhilA""ffi'
Ph"A""ffil
I.".yell, 4 X DS H'ym,",Cen'" 13735. CoII'9' Rd Lti"y'ti. 70503 337.291.55'" MikoM,G,irt< >- F""B"''''.w
L.,.y"" 4 X DS N.P.Mo" MiddleSohoo' 805Too''''g' DIi" L"'y,tt, 70501 337-289.1994 Ch,,'" R',h"d (") Ch"',, "'on"
I."'y"" 4 X DS Com,,,, H,ghSohoo' .00 B,,,bi'd Dne, L"'y,tt, 70508 337-984-8395 B""''' Co"" Ch,,'" ",,,i.
1."'y,lI, 4 X DS A"di... HighSchool 315R" d, B.'ti" L,"y"" 70506 337-964-2646 Joo,' H"tt ~ Ch"',, ",,,i'
1.."y.lI, 4 X DS C"'OCIOHighSohool 721W B'''h'' Swil,hRd, L."y.lI, 70507 337-896-6192 D,.DooAg'itto" Ch.rt" "'oni'
I..'oo"h, 92,157 3 X DS I."'" C',i, C,"'" 307E..151hSI"" L.".. 70373 985-693.7355 HonllBoo'" J"" Ay'
L.'oo"h, 3 X RPOD Thlbod'" Ci,i, C,"'" 310NorthC'"., B',d. Thlbod", 70301 985-446.7260 C,.ioJ. H", Di, C'"on.. Honl
I..'oo"h, 3 X DS So",hL,'o",oheHi9hSohoo' 16911E'" Mol,SI",' G.lii"o 70354 965-632.5721 M''YC'IO" G"g T",",o"",
L.'oo"he 3 X DS Thlbod,,, H~hSohool 135511g"D"" Thlbod." 70301 985-447-4071 Sh""" H."," Y",ne W.im"
I..'oo"h. 3 X DS C'''',,'','o",oh' H'ghSohoo' 4820Hwy1 R'..,.", 70394 985-532-3319 B,.inoD.g,"i.. Jimmy1.,'eI
I."""h, 3 X DS R,,,',"d Em"gon,y,R'''''I~' .. 241R..",,,on D,i" R'.."", 70394 985-537-1700 D,"'" M.y" Milto'A"".
COFoo,,", 3 X DS L"oo"h, P"i.h H..lih U,it 2535V",,,", B',d. Th,bod." 70301 985-447-0921 RonFoI" K.lhyBo",goo',
L.Foo,,", 3 X DS Cot011Y"lh C."" 205W", 7~h SI C" Off 70345 985-632.7616 D,"o' C",.i, Jeni" D,'"ne
"Foo,,", 3 X DS L,'oo"h. P,..h H..lih U,it-G.Ii"", 133W"11121hSI C" °" 70345 985-832.5567 RonFoI~ Sheo'. G,,,
~
P,,'..
U,on', POPE.', 42,382 REG MGAType ..ot"'y N.me Phys'''' Add,,,, Clly Zip ',,"ity Ph , Con",,, ~ Con'"'' , Ph,
0","'1" 148,355 8 X RPOD Mom" CWI,C,",,, 401l" Joyo" E,pwy Mooc" 71201 318-329-2225 Ch", WoI""
0",",1" 8 X RPOO 0","'1" P.'''' HI,h500001 681Hwy594 Mooc" 71203 318-343-2769 Dc,W,""'c D.mooG"doo
0","'1" 8 X DS 0",001" P.'''' Joo'" HI,h 55008"0" 51. Mom" 71202 318-348-5100 Dc,Wob"'c G,oo'dO'H""
0,,,,,. 8 X OS W,~ Rld9' Mldd"Sohool 6977Cyp"" 51. W,~ Mooc" 71291 318-397-1J444 Dc.Wob"'c
0,,,,,, 8 X DS S"clio,'ooH"h Sohool 233K,,~oo' Rood St'ill09100 71280 318-665-2725 Dc.Wobb"
0","'". 8 X DS R'",woodHI,hS,hoo' 5901Hwy165So",h Moo", 71202 318-361-0467 D' Wob"',
P'.,"m'o" 28,969
PICoop" 22.537 2 X OS soon CI,', COO," 1200M'j" P'wy N,. Rood' 70780 225-638-3870 5., Goo,,,, E'''' J,..II
R.p'd" 128,013 6 X RSS(5"1 R.p"" P.,,,, ColI..,m 5800Coli..,m 81,d A'",od" 71303 318-442-9581 Do"," G,"'"y
R'pld" 6 X DS loo'.,". 51." Uo'""II, 8100Hwy71SO~h A'",odc'. 71302 318-473-6474 DLC",o,",h JohoN.pool"
R'p'd" 6 X os R'pld" p"", H"lth Uolt 5604A CoII..'m8',d A',,,od', 71303 318-487-5282 5''''° H,b," Uol",OI, Poli",
R'pld" 6 X RSS R.p'd" P,,'''' E,","'oo H'II 5600Coli..,m 8',d A'",odcl, 71303 318-442-9581 Do",ldG"II°'Y Aog," ""~II,"
RodR,," 9,606 7 DS R'd R"" HIOhS"'OOI 915E"I C""II Co"h'''. 7101'
RI",',"d 20,485
S,bioo
S,bm,
7
7
DS
DS
Floh," H"h S'hool
Z.oll' HI,h5'"'01
500HighS,lIooID,
764Chompio",h,pD'
Fto,'oo
Z_oll,
71429
71486
V1 ~
r-< <:
, ,.
n
~
51. 8'm"d 65,554 1 X RPOD St. B,m"d Ci,,, COO," 8245 W M" p"" Ch,'m,n, 70043 504-278-1507 Ch"'" R,pp"
'---<~-
. ::r' - EI""
Noo"
51.8'm"d
~:::~:::
St.B'm"d
I X DS
1 X DS
M,"ml,C"(Aoobl
: ~ ~~ ~~:;~:;:~':~~~o~:dd"
E',ml
S,hoo':~:~:::~,~::dp""
Ch,'m,'" M'dd"SOhoo'
721F''''','''' A"o"
Dc.~~,~:;;:d;~:; ::~;:~ ~:;o~::~~~';,O
Aoobi
St.H,""' 10,309 9 X DS 51H",,,, C,",oo'HighS",ooJ 14340Hwy37 G,,,,,b"g 70441 225-222-4402 Thood"Colli" Y (l)
>Tj~
S D"'d Hood'''oo
""1 ,....
p",,,, 200'pop..' REGMOAT,.. "clUly'.m. PhY"oaIAdd,,,, C"y Zip F.dUlyPh'Coo"", (l) - Conl"l2~
SU,m"
SU,m"
21,146 3 X DS
3 X OS
St.Jom"P,,',11H""IIUOII
SI'thWocdE',moo"'Y
29170H,,"IIUoIiSt
3245V,'oo"A'm'51
V,,,,,,
V,",,,,,
70090 225-265-2161 R,yB""
70090 225-265-3942J,d, ""doe,
~ ~
0..
M"",Wo,mp""
T"'YM,Cc,,'Y
St.J'm" 3 X OS Goom"" EI,moo"'Y 601E..I 20dSt. Goom"" 70052 225-669-3001 Eltgoo'Hoo'" 0 0.. T,oyM,C",'Y
~: ~:~:: : ~~ :':::: P::~:~::'~::;~'d9 ;:;: ~'Z.:,~ ~~~~~;' 70071 3 Ci1
0 Cf) L-
SUolio
51.Joho
45.581 3
3
X
X
DS
DS
5' JohoP,,'''' H,,"II Uoil
E,. 51.JohoH"h 5",00'
473Cooloo'A"o",
" IM'd,,1D<.
R'''N'
R'''N'
70064
70064
9B5-538-212B R" B',,,
985-536-4226 M<h,,1K COb"m
H, ~
Cf)
Foooo"M'Do","
D,booS"'m
SUolio 3 X DS W,~ St.JohoH'gllSohool 480I.AHwy3127 Ed,"d 70049 985-497-3271 M<h", K Cob,m =::s J,,'Y G'''o."
SUolio 3 X DS G,'Y"'" R,,,,,,,oo, 100. 127GYORood G,'Y"'" 70051 985-535-2943 Wood,1IM","ooo '='"> ::r' tOmI.""
SUolio 3 X DS M.". E,oo'd!<nlgll"ofCoI,m,,",H'" 114W"l7th Slc,,1 R'''N' 70064 '85,538-6633 R',,", J.A,oolo 0 ~ G,oo'dMoc..
:::! -< h
51.lolldO' 89,635 4 X OS 0",,,,,,,, HI,hS",,,' 1014J,doooWo'''' D, 0",,,,,,,, 7OS71 337-942-5634 Rodoo,JoIIoooo d (l) IMIII,Sto,,,
St.I.,"d'Y
st. M.rt",
4
50,453 4
X OS
X DS
Eoo'", H"hS",oo'
St.M.",,,,,,,, 5, H',OS",,,'
30160b"l D'"
762N,M"o
Eoo,,,,
S,M"'","',
70535
7OS62
337-457-3011 M"g"'l l""
337-394-6261 MIoh'"Knom"
~,... . cr'(l) '- R,doo,DI"""
Glog" Fc,"",
St.M'",o 4 X OS C,bI", ScHI,II5'",01 2397Coo". 5, HI,h5,'1 Rd Bc"" B"dg' 7OS17 337-394-6261 M,'oomC.Oi, gg JohOOfD""Ii"
StT,mm,", 213,553 9 X RPOD C,~loo Coo""P,II"o P,~ 63350P"'"o Dc. M,"d",It, 70446 965-626-7997 ><Oth,Fo'"
StT,mm,", 9 X DS S"mooHigh5",00' 4040B'~'" SIId,1t 70458 985-643-7358 B,,,o IMItI,m"P,;o B'm'~ J,hoooo
StT,mm,", 9 X DS Fo""'obl,,, HI,h 100B'ltd', D"" M,"d"III, 70471 985-892-7112 DLWR,"d, Mo',,"
51.T,mmoo, 9 X DS g"" 1.'0010'"Mldd" 275275' Jo"pll l,oom'" 70445 985-882-5418 Dooobl,D'og'","d
51.T,mmooy 9 X DS Fo'oomE',moo"'Y 82144Hwy25 Fotoom 70437 985-796-3820 Am., WOO"""
; ~
T'",lp,hoo 105,158 9 X DS W,.Od, E',moo"'YS,hoo' 2500W'.p"kA" H,mmood 70403 985-542-2580 Th'''.. Doml,", Th"". ~og
T'",lp,hoo 9 X OS W,.Od' Mldd"S,hoo' 401Wo"O'kS"..1 Ami" 70422 985-748-5545 Jo '''cb,m B"od, J,hoooo
Too", 6,176
i
;
T'H,b,oo, IOS,523 3 RPOD H"m'-T'H''''''' CI", COO," 346C,,,, Cool" BNd Hoom' 70380
T""oooo. 3 X DS T'H,boo" p"" H"IIIIUm 600Polk51 Hoom, 70360 985-957-3501AIR"..1t tOmD"'''d
T""boo", 3 X DS M"'''g"' R."..II", Di.,i,"6 '07 R",..II", D,i" M"'''g", 70377 985-594-3174 F"",R,dd, M"".Tr"..i'
T""b",,,, 3 X DS ThoAm"i"'o L'g"o P,,'3I 602L'9i'" A"o", Heom. 70364 985-872-0885 "M", R.d"",od
T.".b,"", 3 X DS Seothd'w""',m",'."1 Sohoo' "2451 Ch"',, 5'"'' Heom. 70364 985-872-9429 ''''M'''. Boh,P.IIi"
T""b,"",
T""b",,,,
T.".b,"'"
U"i," 22.894
3
3
3
X
X
X
DS
DS
DS
Seo'hT",,"""'" Hi9hSchool
C'I"" C"""
HL 8'"'g.." HighSohoo'
3879 HWY.24
4694W M.i"5'"''
, R'''N.Ii," Ceo"
8'",g
Heom.
G",
70343
70360
70359
985-868-7850
985-223-1525
985-872-3277
""Moo"
'"oj", D"p'OOIi'
J"'M,,,. VI::En(t>
C. ~::r'-
"'"
l
Pori.h
V,m,"
'80' pop,,' REG MGAType
49.545 6 X DS
_!,,'II'y N.me.
Hi'" High""'00'
ph,"OO'.Add.....
1296Hi'" S,hoo' Rd
C'y
L.."ill'
Z,p
71446
."\I\ly PhJ. C'"'''''
337-239-9645 K",N,bI.
X::Ecr"
tV (t> (t>
~C''''oe'
,
J.ffF.""
V.m,"
V.m,"
6 X DS
6 X DS
V.m," Pori'hH..llh U"iI
R'''pi", Hi9hSoh,,,
406WF,"itl.8',d L.."iI',
R,,,,pi,,,
71483
70659
337-238-8410 V.',,,G",,,
337-463-6079 K",N,bte
'-' 0.. ~ '"kI.S,1f
J'h"N."o'"
V,m," 6 X DS ",,"' HighSohoo' ",,"' 337-286-5289 K",N,bI, § cr" ~ Joe".S,1f
V,m," 6 X DS H,mbed<HighSOho" H,mbed< 71439 318-565-4440 Ke"N,bI. 0.. '< ::s J"..S.1f
' - , ,,-..,~o.. l '
WF.II,ioo.
W."'iog''"
15,106 2
44,1619
X DS
X DS
WF""ioo. P.ri'" HighSohoo'
F""kI,"IooHigh5oh'"
8604 Hwy 61 N
1 D'm," D,.
51 F""."tIt.
F""'lioloo
70775
-
985-839-6781 B.".,Yeo"g
O\::r'(t>
':-' (t> S ~
W.,"'D,,,,oo
9 F""",V.m.',
W."'iog''"
W''''''' 41,254 7
X DS
X DS
B'g."" Hi9hSohoo'
F.B.C.F.mil, UfoC"""
100M""..I D'.
310p",""Woo" ",
B,g.",:,
Mio'",
70427
71055
985-735-8161 J.m" R.bom
R'ckCh".",
'Tj~
(t>-
'"1 ..... " ~
R,"F""""
W,b,'" 7 X DS Mio'''' R"".Ii," C.",,, 520B".dW., M'od", 71058 W.K."'M""" N.w" (t> ~ M'k. B.",',1d
W.",,,, 7 X DS Mio'", H'ghSchool 203R"""',,,oS' M'od", 71058 3IB-377-2766 W.,"' !M1ti.m, 0..0..
W.""" 7 X DS L.'"id. H'ghSchool 9090Hw,371 Sib'., 71073 318.377.2133 W.,"' !M1ti.m, 0 0..
Web"" 7 X DS C,,'" V,",y HighSohoo' 6245 Hwy 160 C"",V.II., 71016 3IB-832-4716 W.,"' !M1ti.m'
S~
W,"',,,
21,B80 2
X
X DS
DS SprioghillHighSohoo'
3553R,"" R'
Sp"oghtlt
P,riAlI",
71075
70767
318-539-2563 W.,"' !M1ti.m,
W..C""II 11,963 B X DS 0.. G'" HighSoh'" -501 w"M.,,, sr. O,'G,,,. 71263 '1'-428'2;0;; ::s ::r'
Je'''I9.''h''
, 8'~
!Moo POI'''' 6 X DS Wooo POI'''' H."h"", 318-62'.2148 ",,,,5.11
a~ ~cr"
16,151 301 W.M""5' Wooo'"'' 71483 '"'9'0" B.riI..
:::to(t>
0 (t>
::s ::s
»a
~......
J,hoN.",,,,o'
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 3
July 27, 2005
During the week of 25-29 July 2005, the Louisiana Catastrophic Planning Phase 1-B
workshop identified the need to further integrate Parish, State, and Federal plans for the
distribution of commodities (water, ice, food, etc.) following a catastrophic event. The
desired outcome was to design a distribution plan that will help the State more effectively
assist you, the Parishes, and to serve the needs of your population.
The State of Louisiana and FEMA need to know the extent of your capabilities, and lack
thereof, in performing these tasks. Given the present situation—an extremely active
hurricane season and a global rise in terrorist activity—the task of preparing for
catastrophic disasters is especially urgent. Based on your Parish’s current population, the
U.S. Army Corps of Engineers (USACE) estimates that as many as ____ distribution
points might be necessary in your Parish during a catastrophic event (details regarding
the calculation of this estimate are enclosed for use in your planning.) Collaborative
contingency plans need to be in place for the State to assist you in responding in a timely
manner and your provision of this information will help us to be better prepared in these
circumstances.
A team consisting of representatives from seven Parish OEPs, the Louisiana National
Guard, LOHSEP, FEMA, and other Federal agencies designed a process, which
addressed concerns regarding the identification, establishment, coordination, and
operation of local distribution points. In order to complete this goal, we need your help
with the following requests (See Enclosures 1-4), a completed example has been
provided.
Please complete the enclosed requests for information relevant to distribution point
identification and operation in your parish and return them to:
The Office of Emergency Preparedness will verify and compile the data received to
create a statewide distribution plan that is sensitive to the unique nature of each Parish.
This plan will also be integrated into the Louisiana Catastrophic Plan currently being
developed. Completed enclosed materials should be received by August 30, 2005.
For additional information and/or questions, please contact: Chris Walker, Project
Officer at #225-925-7500.
1
Enclosure 1
Site Identification
Provide an inventory of the sites that meet the minimum requirements for distribution
points within your parish. Please include a site identifier, relevant site details, digital
photographs, and latitude/longitude location, preferably in GIS-ready format.
Equipment Inventory
Provide an inventory of the required equipment the parish can provide at each identified
site.
1. Forklifts
2. Pallet jacks
3. Power light sets
4. Toilets
5. Tents
6. Dumpsters
7. Traffic cones
8. Two-way radios
Personnel Inventory
Provide an inventory of the required personnel the parish can provide at each identified
site. This list is based on the USACE organizational chart for distribution point staffing
(see example on next page.)
1. Team leader
2. Forklift operator
3. Labor
4. Loading point
5. Pallet jacks labor
6. Law enforcement
7. Administrative staff
8. Community relations staff
9. Multi-lingual staff
2
Site Manager
Law Enforcement
Community Relations
Security
Communications Capabilities
List the primary, secondary, and tertiary means of communication available in your
Parish during an emergency.
(CUT OFF HERE FOR PARISH PRESIDENT—INSERT NOTE SAYING THAT THE
PARISH OEP DIRECTOR HAS BEEN SENT ADDITIONAL INFORMATION TO
ASSIST IN DATA COLLECTION)
3
Enclosure 2
In the event of a catastrophic event/worse case scenario, your Parish will require the
following number of distribution points.
This will require, per Type III location, the following staffing requirements.
4
Enclosure 3
Type III Distribution Point Layout (typical)
5
Enclosure 4
Type III Distribution Point Configuration (typical)
There are 3 basic models established for the operation of a Distribution Point. All are
based on the expected affected population of an area. Type I is established for the
operation and sustaining of a population of roughly 20,000 persons per day and/or 560
vehicles per hour. Type II is established for the operation and sustaining of a population
of 10,000 people and/or 280 vehicles per hour. Below (figure 3) is an example of a Type
III (Figure 4) Distribution Center established for an affected population of 5,000 and/or
140 vehicles per hour.
6
General Commodity/Supply Information
7
Example
Plan
8
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 4
Concept of Operations for Distribution
Planning for the State of Louisiana
Overview
Once a Federal Emergency has been declared, operations from FEMA’s Staging
Area at Camp Beauregard will be activated. Based on the needs of affected
Parishes and with the coordination of LOHSEP, needed commodities and
supplies will begin to flow to each Parish’s designated RSA. From the RSA, a
coordinated effort to distribute these supplies to the various DPs (Figure 1) within
each of the Parishes for distribution of supplies to the general public will begin.
Figure 1
1
Assumptions
1) RSAs and DPs will be managed by Parish officials and upon request,
through the State EOC, can be supplemented with State and Federal
assistance.
5) DPs will be open to the public for 12 hours per day. Re-supplying of
centers will primarily be at night.
2
Primary and Alternate RSA and DP checklist
SITE CHECKLIST
Notes: _____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________
3
Regional Staging Area/ Distribution Point Operations
At the request of the State EOC, and under the direction of FEMA, needed
commodities and supplies (water, ice, MREs, and tarps) will be ordered and
delivered to FEMA’s regional staging facility at Camp Beauregard in Pineville,
Louisiana.
From Camp Beauregard, the FEMA controlled and owned supplies will be loaded
in FEMA contracted and/or federally owned tractor trailers and begin their routes,
escorted by local and/or State assets, to the State’s designated RSA (Figure 2).
Note: The State of Louisiana has designated, if needed, up to eight RSAs located
along the Louisiana I-10/I-12 corridor, to cover the southern Parishes of
Louisiana.
Louisiana Regional
Staging Areas
Camp Beauregard
FEMA
Staging Area
FE
M
A
Covington
RSA
A.
RSA RSA
RSA
H. G.
F. Metairie
Lake Charles Lafayette New Orleans
Thibodaux RSA Chalmette
RSA
E.
D. RSA
B.
RSA
C.
Belle Chase NAS
Figure 2
4
At the RSA, FEMA and the State of Louisiana will each provide two Staging Area
Managers per RSA to co-manage commodity accounting. The Federal Staging
Area Manager’s responsibilities are acceptance and validation of shipment
contents. The State’s Staging Area Manager primary responsibilities are to
assume all other operations, to include setup, and day-to-day operations of the
RSA and DP facilities. At this time, accountability will be transferred to the State
via the State’s appointed Staging Area Manager (JOC).
At the RSA, the commodities and supplies will be broken down, if needed, by
Louisiana National Guard personnel, packaged, and delivered to each of the
designated DPs located throughout the Parish (Figure 3).
Figure 3
FEMA will provide one 4,000 lb capacity forklift and portable lighting equipment
for operations at each RSA. The State will be responsible for providing
maintenance and certified operators for the forklift(s) at each RSA. Also,
transportation from the RSA to specific DPs will be accomplished with State
resources.
5
Once an order has been built for a DP, National Guard personnel and equipment
will deliver the needed supplies to its final destination for distribution to the public.
Folsom Elementary
St. Tammany Parish
82144 Hwy 25
70437
Distribution Points
Fair Grounds
RSA
A.
Sta
te
of
Fountainbleau HS La
100 Bulldog Dr.
70448
Castine Center
63350 Pelican Dr.
70448
Salmen HS
4040 Berkley
70458
Figure 5
Any variation to this concept of operations will be elevated from the field
management level to the Staging Area Manager, and then to State/Federal
management at the State Emergency Operations Center/Joint Field Operations.
6
Models of DP Operations
There are 3 basic models established for the operation of a Distribution Point. All
are based on the expected affected population of an area. Type I is established
for the operation and sustaining of a population of roughly 20,000 persons per
day and/or 560 vehicles per hour. Type II is established for the operation and
sustaining of a population of 10,000 people and/or 280 vehicles per hour. Below
(Figure 3) is an example of a Type III (Figure 4) Distribution Center established
for an affected population of 5,000 and/or 140 vehicles per hour.
Figure 4
7
General Commodity/Supply Information
Notes/Questions:
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
8
Layout Plans for Distribution Points
Figure 5
A loading point is where a stockpile of ice, water, MREs, and tarps are located.
Each loading point has a team of people (1 for water, 1 for ice, and 1 for
MREs/tarps) that load these items into the vehicle as it stops in front of their
position (Figure 2).
Based on past experience, a well planned and operated distribution point with
one lane of traffic and 3 loading points can service 140 cars per hour. Based on
a 12-hour workday, about 1,680 vehicles or 1,680 x 3 = 5000 people can be
served.
9
Required Resources for a Type III DP
10
This is an active Excel File, simply double click on the face of the sheet, enter the # of people
without power and push the enter key, the data will update with each entry.
USACE
PRE-EVENT Commodities Model
Figure 6
The pre-planning of DPs and their locations is critical to the public. Pre-planning
allows these DP location(s) to be known to the public prior to an event and
potentially before communications are impacted. This also allows for route
clearing priorities and route mapping to be performed during the pre-planning
process in lieu of the post/ response process.
11
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 5
June 7, 2005
1. Purpose: The purpose of this document is to provide state, local and tribal agencies guidance
when planning for distribution of emergency supplies and commodities to the public. This
guidance centers on local distribution points where the commodities are placed into the victims’
hands.
3. Overview: The type and quantity of supplies that the public will need in the aftermath of
disasters or other crises will vary due to many factors and no one event will be just like another.
Experience in emergency response over the years suggests some common necessities that the
public will require to meet health, safety, and lifesaving needs. They include potable water
(usually bottled), packaged ice, Meals Ready to Eat (MRE) and other supplies. In small scale
disasters and in the initial hours of larger disasters, these commodities are often supplied by state
and local governments, donations from industry, and volunteer agencies. When the need for
commodities exceeds the state’s capability, under a Presidential Declaration, the state can request
that FEMA provide the additional requirements. FEMA will provide commodities stored in bulk
quantities at regional logistics centers in various locations and, if needed, task ESF#3 (USACE)
to purchase additional quantities of ice and water. The FEMA/USACE provided commodities
are delivered from the federal staging areas to state logistical staging areas where the state in-
turn supplies the local distribution points. These commodities and supplies are most often
delivered in over-the-road tractor trailer loads. Since these types of trucks (eighteen wheelers)
are eighteen to thirty feet long, with a trailer that is forty-five to fifty-two feet long, large open
areas are required to accommodate the vehicles with their loads. Distribution points must be
areas that are paved, concrete, or gravel hard-stand that can withstand loads that are at load limits
of national roadways. In addition to the area needed for the trucks, planning must include area
for unloading, dumpsters, proper traffic flow, stockpiles, and ingress and egress for the
distribution to the public. Figure 1 below shows the general flow of commodities from Federal
to State to local distribution points.
4. Key Background Information: We live in a "just in time" world. The vendors that supply
bottled drinking water, packaged ice and other commodities are geared to supply their normal
business clients. They minimize storage costs and personnel costs by keeping production in line
with demand. In large response efforts, packaged ice and water are provided from all over the
US and Canada in order to meet the immediate demand. The same is true with the trucking
1
Federal Staging
y
p pl
Su
ly
pp
Su
Distribution
State Staging Distribution
Points
Distribution
ly
Points
pp
Distribution
Points
Distribution
Su
Points
Distribution
Points
Points
Distribution
State Staging Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Points
Distribution
State Staging Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Points
Figure 1
industry. Large, over-the-road trucks are seldom idle and are in business to serve clients. This is
especially true of refrigerated vans which are in high demand. When disaster strikes, the
commercial world has to change their normal business structure to provide support to the effort.
Vendors have to continue to support their normal customer base and gear up operations to
support disaster requirements. This process, by rule of thumb for large orders, takes 48 hours
during the weekday to deliver up to 50 loads and 72 hours to deliver up to 50 loads if initiated on
a Friday after 12:00 noon. Because of these factors, the pre-positioning of commodities for a
pending event is crucial.
4.1 In past responses, the industry has been impacted by large orders being cancelled and then
re-ordered the next day. You can imagine the whiplash to their additional personnel, bottle
suppliers, delivery schedules, trucking assets, and existing customers, that this can cause,
especially on a weekend when they normally are not working. We will never eliminate this type
of situation, but we as responders need to understand the repercussions to our business partners.
Another re-occurring impact is to the trucking industry. When large numbers of trucks sit for 4
or 5 days at a staging or distribution site without being off-loaded, there is a huge impact on re-
supply, costs, and can result in trucking companies refusing to participate in future efforts. Our
planning efforts must include ways to off-load trucks quickly to free up this limited resource.
It's a lot better for the victims of a disaster to have a little ice melt at a distribution point
than to hold the refrigerated truck and keep it from delivering another load.
4.2 Another key aspect of commodities planning is the understanding of the "pipeline effect."
The need for commodities is directly proportional to commercial power. If the power is out the
need is there. When the power returns (with the exception of a contaminated water supply) the
need is gone. During response operations the power restoration process must be closely
monitored and commodity supplies adjusted. The pipeline is defined as all the commodities
purchased but not yet delivered and all the supply trucks that are in route between the supplier
2
and the distribution points. In large operations this number can be in the hundreds and if the
power grid suddenly comes on line, then the trucks and commodities in the pipeline will
represent excess stockage. The pipeline effect will most always happen, but we as managers
must reduce the effect as much as possible through planning, communications, and coordination.
4.3 Distribution points provide a great place to communicate to the public by means of
informational handouts. Community relations personnel are included in the distribution resource
plan. The key is to have the information packaged in a handout format to prevent people from
exiting their vehicles. Maximum vehicle flow is crucial to reaching as many people as possible.
5. Planning Factors: The following are general information and common planning factors that,
if used by all, will help in coordinating and communicating during the planning and response
process.
Shelters will require a mixed load of commodities consisting of 3 pallets water, 1 pallet ice, 1
pallet MREs per 500 person facility.
Mobile kitchens require 2 trailers water and 1 trailer ice per 10,000 meals per day per site.
5.3 Distribution Point Planning: The following are assumptions used for distribution planning:
- Victims will drive through a distribution point and be served without leaving their vehicles.
- Each car represents an average family of 3.
- Each vehicle passing through a distribution point will receive the following:
2 or 3 bags of ice
1 case of water (9–12 liters)
6 MREs
1 tarp
3
1 truck load of ice and water will serve 1,660 vehicles or about 5000 people
1 truck load of MREs will serve 3,624 vehicles or about 10,000 people
1 truck load of tarps will serve 4,400 vehicles or about 4,400 homes
Distribution points will be open to the public for 12 hours per day.
Re-supply of distribution points will primarily be at night (while the point is closed to the
public).
A loading point is where a stockpile of ice, water, MREs, and tarps are located. Each loading
point has a team of people (1 for water, 1 for ice, and 1 for MREs/tarps) that load these items
into the vehicle as it stops in front of their position (see Figure 2).
Based on past experience, a well planned and operated distribution point with one lane of traffic
and 3 loading points can service 140 cars per hour. Based on a 12 hour work day, about 1,680
vehicles or 1,680 x 3 = 5000 people can be served.
6. Layout plans for distribution points: The following plans provide examples of different
sizes of distribution points and the resources required for operations:
4
Type I Distribution Point
Resources Required
Law Enforcement 4 1
Community Rel. 4 0
Grand Total 78 10
Figure 4
5
Type II Distribution Point
Resources Required
Figure 6
6
Type III Distribution Point
Resources Required
Type III Distribution Point
Manpower Equipment
Type Day Night Type Number
Team Leader 1 0 Forklifts 1
Local Responsibility
Figure 8
7
7. Planning Methods: This section will discuss methods to determine the location and number
of distribution points (DP), provide suggestions for supplying manpower and equipment
resources, and discuss distribution point operations.
7.1 Determining the Location and Number of DP: The number and general location of most
DPs will be determined by population; however most all tribes, municipalities, and/or major
communities will require a DP and, in some cases, several DPs.
The number of DPs can be determined mathematically. The Excel model shown in Figure 9 will
calculate the number of DPs required when the total number of people without commercial
power is entered. The model uses a 40% factor to calculate the estimated number of people that
will visit a DP. This figure is an estimated average percentage based on past experience. The
model also considers only Type III DPs which consist of a one lane operation. A Type III DP
provides for 5000 people and can handle one truck load of ice and water per day along with
MREs and tarps. Therefore, for every truck load of ice or water ordered, there should be a
corresponding DP or lane for off-loading. The number of actual DPs can be lowered if Type I
or Type II DPs are used; however, the number of "lanes" will remain the same. For example: If
the model computes 32 Type III DPs, then that would equal 16 Type III and 8 Type II; or 16
Type III, 4 Type II and 2 Type I; all equaling 32 lanes.
Another method for determining the number and location of DPs is through Geographical
Information Systems (GIS). GIS can produce a dot density map that provides a visual dot for a
selected density of population. To determine the location of DPs, a dot density map should be
produced based on a density of one dot for every 12,500 people (40% of 12,500 = 5000, the
number of people served by a Type III DP). The location of the dot will provide a general start
for locating a DP; however, as stated before, consider all tribes, municipalities, and/or major
communities having at least one DP.
The pre-planning of DP locations is critical to the public. This allows the locations of the DPs to
be known to the public prior to an event before communications are impacted. This also allows
for route clearing priorities and route mapping to be performed during the pre-planning process
in lieu of the response process.
7.2 Resourcing DPs: DP operations, including manpower and equipment, are a local
responsibility. A partnership between the community and response planners is essential for the
establishment of a successful distribution system that serves the public in their time of need. The
most challenging resource to provide is manpower. Most local governments depend on the
National Guard, volunteer fire departments, church groups and other volunteer agencies for
manpower. All of these sources are viable; however, close coordination is needed to assure local
governments are not using a specific resource in multiple locations. One good example of using
a local resource is the use of local churches in the disaster area. Some churches have very large
parking areas that work well for a Type III DP and the church can work with their congregation
to establish a ministry to man and operate the DP. This example uses people from the
community to help people in the community. Figures 4, 6, and 8 show the personnel and
equipment requirements for each type of DP. The Excel model in Figure 9 provides a total roll
up of personnel and equipment for all the DPs required.
8
Each DP requires an equipment package, as shown in Figures 4, 6, and 8. If the disaster receives
a Presidential Declaration, then the costs for renting this equipment will qualify for Federal
reimbursement. It is recommended that the planning agent, city, county, or tribal agency provide
the equipment to the DPs located within their area of responsibility. Planning agents should
work with local vendors and have agreements in place to provide the required equipment. The
rates, either hourly, daily, or weekly, should be discussed with the State Emergency Management
office and FEMA to get guidance on best practices. This suggested method of supplying
equipment helps prevent duplication and allows for easier reimbursement.
Questions on layouts, models or other information in this document should be directed to:
9
This is an active Excel File, simply double click on the face of the sheet, enter the # of people
without power and push the enter key, the data will update with each entry.
USACE
PRE-EVENT Commodities Model
Figure 9
10
This is an active Excel File, simply double click on the face of the sheet, enter the # of active
Distribution Points and push the enter key, the data will update with each entry.
USACE
POST EVENT Ordering Model
Figure 10
11
ORGANIZATION CHART – TYPE II AND III
DISTRIBUTION POINT SITE MANAGEMENT
Site Manager
Law
Enforcement
Community Rel.
Security
12
Ice Tracking Chart
Figure 11
13
Water Tracking Chart
Figure 12
14
MRE Tracking Chart
Figure 13
15
Tarps Tracking Chart
Figure 14
16
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 6
Key Lessons Learned
• Tarps – 1 truck load (4,400 ea.) serves 4000 families with roof damage
– 6 MREs
• A distribution point (DP) with one supply lane can serve 1,660 cars or
5000 people in one day, (Type III Distribution Point).
• A Type II DP has two lanes
• A Type I DP has four lanes
1 Truck Load Ice
1 Truck Load Water
½ Truck Load of MREs Serves 5000 People = One Type III DP
1 Truck Load of Tarps
ply
p
Su
ply
p
Distribution
Su
Points
Distribution
Points
p
Distribution
Su
Points
Distribution
Points
CPoints
Distribution
State Staging Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Points
Distribution
State Staging Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Distribution
Points
Points
LOADING POINT
W I M T W I M T W I M T
100’
Dumpsters
W I M T W I M T W I M T
Pallets
CARS
40’
W W I I M M T T
W W I I M M T T
Water
45’ W W I I M M T T
W W I I M M T T Ice
W W I I M M T T
MRE
20’ Pallets 80’ 3 Persons Per Loading Point
W W I I M MT T - 1 for Water Tarp
15’ - 1 for Ice
W W I I M MT T
W W I I M MT T - 1 for MREs and Tarps
Figure 2
TYPE I - DISTRIBUTION POINT
Serves 20,000 persons per day
12 Loading Points - 560 vehicles per hour
ck
rt u
ly
u pp
S Forklift
TENT Light Set
Toilets
Pallets Pallets
Dumpsters
Dumpsters
W I MT W I MT W I MT W I MT W I MT W I MT
W I MT W I MT W I MT W I MT W I MT W I MT
Dumpsters
Dumpsters
Pallets Pallets
S
TENT u
p
Light Set Toilets p
ly
tr
u
ck
Note: Individual vehicles drive through and Maximum Loads per Day – Type I
Ice & water is loaded into their trunks. Recommend
One case water, 2 or 3 bags of ice per vehicle and
6 MRE’s. Water 4
MRE 2
Figure 3 Tarp 2
Type I Distribution Point
Resources Required
Law Enforcement 4 1
Community Rel. 4 0
Grand Total 78 10
Figure 4
TYPE II - DISTRIBUTION POINT
Serves 10,000 persons per day ck
rt u
ly
6 Loading points u pp
S
280 vehicles per hour Toilets
TENT
Forklift Pallets
Dumpsters
WI T W I MT W I MT
M Light Set
W T
IM W I MT W I MT Toilets
Dumpsters
Pallets TENT
Supply truck
Supply trucks for Ice, Water, MREs and Tarps are to be Ice 2
off-loaded promptly and returned for re-supply.
MRE 1
Figure 5 Tarp 1
Type II Distribution Point
Resources Required
Figure 6
TYPE III - DISTRIBUTION POINT
Serves 5,000 persons per day
3 loading Points rt u
ck
140 vehicles per hour ly
pp
Su
Forklift TENT
Toilets
Pallets
Dumpsters
WI T W I MT W I MT
M
Light Set
Tarp 1/2
Figure 7
Type III Distribution Point
Resources Required
Type III Distribution Point
Manpower Equipment
Type Day Night Type Number
Team Leader 1 0 Forklifts 1
Local Responsibility
Figure 8
ORGANIZATION CHART – TYPE II AND III
DISTRIBUTION POINT SITE MANAGEMENT
Site Manager
Law Enforcement
Note: For a Type I site add
One additional Team Leader
For Labor and one for
Community Rel.
Equipment/Supply
Security
Equipment/Supply
Labor Team Leader
Team Leader
Appendix 7
Source(s) of How many people
Type of Transportation Transportation can fit on each? Required Infrastructure/Routes
Disaster Assistance Response
Team (appr. 6 teams with flood
punts (36) with crews) Coast Guard 10 -15 each
EMAC unknown
airplane, commercial commercial 20 - 300 each
fixed wing, Medi-vac DoD 6 - 100 each
ESF1, commercial,
ambulance, ground EMS 2 each
bus, school owned Parish School Boards 45 each I-10, I-49, I-55, I-59, I-65, US 61
60 - 100 each (DoD
fixed wing, heavy DoD, commercial only)
rail, non-passenge ESF1, commercial 75 - 80 each rail assessment
rail, passenger AmTrac 75 - 80 each rail assessment
rotary wing, heavy DoD 30 each
rotary wing, light PHI(?), EMS, ATC 5 - 7 each
commercial, GSA,
tanker, fuel ESF1, FEMA, DoD
commercial, DoD,
tanker, water DOT
commercial, GSA,
truck, fuel (route) ESF1, FEMA I-10, I-49, I-55, I-59, I-65, US 61
commercial, GSA,
truck, water (bulk) ESF1, FEMA
truck, 2.5 ton LANG, EMAC
truck, 5 ton LANG, EMAC
truck, 4WD GSA, commercial
commercial, GSA,
truck, box with lift gates ESF1, FEMA I-10, I-49, I-55, I-59, I-65, US 61
commercial, GSA,
truck, flat-bed ESF1, FEMA I-10, I-49, I-55, I-59, I-65, US 61
commercial, GSA,
truck, refrigerated ESF1, FEMA I-10, I-49, I-55, I-59, I-65, US 61
vehicles, volunteer Owner/Operator
4-Wheelers GSA, commercial
vehicles, all-terrain (Gators GSA, commercial
REQUIREMENT 500K pax movement
10% = 50K pax treat / 75K pax per
MEDICAL day
Southeast Louisiana
Catastrophic Hurricane Planning Project
Appendix 8
Ice Tracking Chart
Appendix 9
Appendix 9 - Trans-shipment Points (Shuttle
Staging/Reception Areas)
I-55
Shuttle/
Reception
Ascension CP
CP
Bus Staging
CP
Bus Staging
Air CP
Lafayette
Shuttle/ CP
Reception
Bus Staging
Impact Area
Shuttle/
Reception CP
New Iberia
Air
With Appendices
This page intentionally left blank.
Draft Update 2
September 3, 2005
76
Prepared By
IEM, Inc.
Four United Plaza
8555 United Plaza Blvd., Suite 100
Baton Rouge, LA 70809
Prepared For
DHS/FEMA
500 C Street S.W.
Washington, DC 20472
LOHSEP
7667 Independence Boulevard
Baton Rouge, LA 70806
Prepared Under
FEMA BPA HSFEHQ-04-A-0288, Task Order 001
IEM/TEC04-070 r7
September 3, 2005
This document is for reference only. Readers should not construe this document as representing
official policy or regulations. The functional plan contained in this document was produced
initially during the Southeast Louisiana Catastrophic Hurricane Planning Workshops (July 16–
23, 2004 and November 29–December 3, 2004). This document was updated from notes taken at
the Southeast Louisiana Temporary Medical Care Supplementary Planning Workshop (August
23–24, 2005). The update to this functional plan has not been evaluated for the potential
conflicts it may create with other portions of the Southeast Louisiana Catastrophic Hurricane
Plan. This functional plan has been edited for clarity. The information contained herein is
subject to change.
This page intentionally left blank.
TABLE OF CONTENTS
9.0 DEBRIS................................................................................................................. 45
This table of contents is presented to reflect how this update relates to the Southeast Louisiana
Catastrophic Hurricane Plan. Only the bolded section is contained in this document. The page
numbers correspond with the Southeast Louisiana Catastrophic Hurricane Plan to ensure
consistency throughout the document.
i
This page intentionally left blank.
ii
Temporary Medical Care
14.0 Te m p o r a r y M e d i c a l C a r e
1. Situation
a. General
i. A catastrophic hurricane has made landfall in southeast Louisiana. In many affected
Parishes, a high percentage of the population remained at landfall, resulting in high
numbers of fatalities and non-fatal injuries.
b. Assumptions
i. Transportation will be limited due to flooded roadways and a shortage of resources
such as fuel.
ii. There is no medical treatment available within the affected area; therefore, there is a
need for a medical staging area outside the affected area.
iii. Local resources are exhausted and the blood supply will be stressed. Medical staffing
will not be at full capacity.
iv. Communication networks are non-functioning and interoperability among hospitals
may be a problem.
v. Large numbers of people are expected to require treatment for a variety of illnesses,
both related and unrelated to the hurricane, before health care facilities in the affected
areas are returned to operation.
vi. For the purposes of this plan, the following summary of the expected casualties
during pre-landfall, impact, and post-impact is assumed.
vii. Search and rescue missions will need to be supported by medical personnel to do
screening/triage on rescuees prior to transport to shelters or release to families.
viii. Large quantities of hazardous waste, both industrial and household, will have been
released because of hurricane wind and flooding, resulting in potential airborne and
waterborne contamination, and possible combustible/flammable conditions.
ix. Many families seeking shelter will have not brought needed over-the-counter and
prescription medicines with them.
x. Certain large tracts of land enclosed by levee systems will have been flooded due to
storm surge overtopping levee walls beyond the capacity of pumping systems. This
will include the majority of Orleans Parish, much of Jefferson Parish, and parts of St.
Bernard Parish.
xi. All 40 medical treatment facilities in the impacted area are affected by the high-water
levels, loss of electricity, loss of communications, and storm-force winds, rendering
them isolated and useless. At best, they will shelter-in-place whatever patients they
were not able to discharge prior to landfall. In addition, refugees (non-injured or ill
individuals) will come to those treatment facilities for sheltering. All patients, staff,
family members, and refugees will require evacuation from nonfunctional facilities.
These treatment facilities may require restoration of power, as well as medical, water,
and food re-supply, until evacuation is complete.
xii. Some nursing homes will have already been evacuated, per emergency plans, as
required by the State. However, some residents will not be able to evacuate pre-
incident and will require medical evacuation.
xiii. The standard acceptable level of care will not be possible in an extreme emergency
situation.
xiv. Concern about inpatient care will be much greater than concern for outpatient care.
xv. The State will request Federal support and the President will declare a major disaster.
ESF-8 will be activated, including the National Disaster Medical System (Disaster
Mortuary Operational Response Team, Disaster Medical Assistance Team, and
Veterinary Medical Assistance Team).
xvi. Search and rescue will be activated to conduct aerial assessments to determine
Search and Rescue Bases of Operation.
xvii. The Strategic National Stockpile will be activated and the Technical Assistance
Response Unit will be deployed.
xviii. Based on estimates from search and rescue, approximately 75,000 persons will be
transported to medical facilities daily for four days. If a conservative estimate of 10%
requiring medical treatment is applied, receiving 7,500 patients per day in need of
medical care will be anticipated.
xix. The State will establish nine triage lines and special needs shelters.
xx. The Strategic Medical Assistance and Response Team (SMART) and mobile hospital
system will be activated.
xxi. Flexibility for standards of care, EMTALA, HIPPA regulations and liability issues
are relaxed during a disaster and this plan.
c. Organization
i. Federal
1) Lead Agency
a) Department of Health and Human Services
2) Support Agencies
a) DHS/National Disaster Medical System
b) Department of Agriculture (U.S. Forest Service)
c) Department of Defense
c) Department of Energy
d) Department of Justice
f) Department of Transportation
g) Department of Veterans Affairs
h) Agency for International Development
2. Mission
a. The mission is to plan for medical transportation, temporary public health and medical
care, emergency medical care, normal outpatient care (e.g., doctors, dentists, laboratory,
radiology, dialysis clinics, and home nursing), and definitive hospital care to the
population of southeast Louisiana. The mission is also to plan for identification, storage,
and assistance with final disposition of remains and to plan for minimal support of animal
care as needed. These services will be provided until customary medical facilities and
services are returned to operational status in the areas impacted by the catastrophic
hurricane.
3. Execution
a. Concept of Operations
i. Search and Rescue Base of Operations
1) The Louisiana Department of Health and Hospitals will coordinate with search
and rescue efforts to provide decontamination and/or medical care at each Search
and Rescue Base of Operations. Search and rescue will transport victims requiring
medical attention to the Bases of Operations or to acute treatment facilities as
dictated by the patient’s medical condition.
2) It is recommended that Search and Rescue Bases of Operations be located next to
or very near selected rail lines and viable ground transportation routes.
3) The Search and Rescue Bases of Operations will be staffed by local emergency
service and public safety providers (e.g., emergency medical service and fire
departments), as well as Disaster Medical Assistance Team members. Disaster
Medical Assistance Teams, organized into medical strike teams, will be located at
each Search and Rescue Base of Operations.
4) From the Search and Rescue Bases of Operations, refugees in need of medical
care will be transported to one of three Temporary Medical Operations Staging
Areas or more definitive care facilities as determined by patient condition through
a combination of the following assets: emergency medical service, State resources
(including public/private ambulances and helicopters), Emergency Management
Assistance Compact resources, National Mutual Aid and Resource Management
Initiatives resources, Federal assets to be determined by DHS/FEMA, and other
pre-event open-ended-agreement procured modes of transportation. Critical
patients will be tagged “heli” and will be transported by helicopter assets to the
nearest T-MOSA for immediate care, all others will be transferred using land
assets.
5) Refugees not in need of medical care will be transported via various means of
transportation from the Search and Rescue Bases of Operations to nearby shelters
in Baton Rouge, Thibodaux, and Hammond.
6) Within five days of rescue operations, search and rescue assets will switch from
rescue efforts to evacuation of hospitals in the affected area. Hospital evacuation
must be a priority, due to the lack of electricity, number of patients, and the influx
of refugees into the stranded healthcare facilities overwhelming available
resources. Patients will be moved to Temporary Medical Operations Staging
Areas, directly to designated hospitals outside of the affected area, or out of the
State. Refugees will be transported to temporary shelters.
7) Hospitals in the affected areas will be re-supplied with critical supplies within one
to seven days. This supply effort will be accomplished through the use of care
packages. The standard care package includes gowns, linens, towels, water,
medication, food, ice, batteries, generator, fuel, and an extension cord. Special
care packages will be utilized based on patient need.
8) Patients and refugees will be decontaminated at the Search and Rescue Bases of
Operations as needed prior to forward movement to the Temporary Medical
Operations Staging Areas.
9) The standards of care, EMTALA, & HIPPA, regulations and liability issues are
relaxed during a disaster in recognition that patients need shelter first.
10) The following protocol covers the extraction of patients from affected hospitals,
and establishes the priority of patient extraction with a focus on those who can
make the trip. All patients will be prioritized for evacuation based on the triage
colored tag system. First-out patients will be those who are expected to have a
full, quick recovery. Remaining patients will also be identified and prioritized for
evacuation based on the triage colored tag system. Patients will be accompanied
by staff and family. The triage tag system should be initiated during the pre-
landfall phase when the doors to the facility are shut. Any new patients will be
tagged by the emergency department. Case Managers should leave prior to
landfall to assist in patient tracking.
11) Given the limited transportation resources, the following plan will prioritize a
roster for flight/boat extraction:
a) Jefferson Parish hospitals are expected to be evaluated first. Due to the
probability of quickly receding water, the hospitals will probably not need to
be evacuated.
b) Hospitals in Chalmette are expected to be evacuated by air.
c) Lakeland Medical Center is expected to be evacuated by air.
d) Remaining hospitals are expected to be evacuated by boat extraction.
e) Children’s Hospital and Memorial Medical Center are expected to be
evacuated last due to elevated generators.
Prioritization would also be based on damage to facility and patient conditions
with the triage system.
ii. Temporary Medical Operations Staging Areas
1) The State Department of Health and Hospitals has designated Temporary Medical
Operations Staging Areas in the following locations: Southeastern Louisiana
University (Hammond, Louisiana), Nicholls State University (Thibodaux,
Louisiana), and Louisiana State University (Baton Rouge, Louisiana). Alternate
sites have also been designated and will be located outside the affected area (see
Louisiana State Department of Health and Hospitals Emergency Operations Plan,
Annex X).
2) Each Temporary Medical Operations Staging Area will consist of two major
operations.
a) Operation 1: Primary Care/Initial Stabilization
i) From triage, patients requiring further medical care will receive initial
treatment and stabilization by Strategic Medical Assistance and Response
Teams and Disaster Medical Assistance Teams. Those who do not require
additional medical care will be routed to shelters as appropriate. A
waiting/staging area will be provided for those waiting for transport.
Those requiring additional medical care will be routed to definitive care.
b) Operation 2: Definitive Care
i) Patients requiring medical care will be transported to in-state medical
treatment facilities and alternate care sites using the following priorities:
1) State surge capacity hospitals (see Appendix A).
2) Alternate care facilities (see Appendix B).
3) Field mobile assets (see Appendix C).
4) Emergency Management Assistance Compact/National Disaster
Medical System transport out of State (see Appendix D).
ii) Medical augmentation personnel will be provided to hospitals and
alternate care facilities, as requested by the State, through Federal assets
i) Assist in logistics.
ii) Assist in animal control and disposition.
d) The Department of Environmental Quality will perform the following task:
i) Assist the Department of Health and Hospitals in determining protocols
for decontamination of patients at Temporary Medical Operations Staging
Areas sites.
e) The Department of Transportation and Development will perform the
following task:
i) Provide transport of victims from Temporary Medical Operations Staging
Areas to shelters.
f) Volunteer Organizations will perform the following tasks:
i) Coordinate food and clothing distribution and donations.
ii) Coordinate and provide assistance with decontamination at Temporary
Medical Operations Staging Areas.
g) The Louisiana Hospital Association will perform the following task:
i) Communicate twice daily to the Department of Health and Hospitals the
bed and equipment availability of all Louisiana hospitals.
h) The Louisiana Nursing Home Association will perform the following tasks:
i) Communicate evacuation procedures to the Department of Health and
Hospitals.
ii) Provide daily reports of the number of available beds to the Department of
Health and Hospitals.
i) The Department of Economic Development will perform the following tasks:
i) Provide a listing of empty facilities that can be utilized.
ii) Provide plans for job development for evacuees at shelters and temporary
housing facilities.
j) The Department of Social Services will perform the following tasks:
i) Coordinate the special needs shelters in all Temporary Medical Operations
Staging Areas.
ii) Provide assistance with registration, collection of information, and
reporting of information to the State repository at all refugee reception
sites.
k) The Department of Corrections will perform the following task:
i) Feed victims and responders at Temporary Medical Operations Staging
Areas.
l) The Department of Education will perform the following task:
i) Provide school buses for transportation needs.
m) The Louisiana State Police will perform the following tasks:
i) Provide security at Temporary Medical Operations Staging Areas or other
medical treatment locations.
ii) Provide transportation assets as needed.
iii) Provide police escort of patient movement.
iv) Coordinate and assist in the management of hazardous materials teams.
3) Local
a) Public and private hospitals, nursing homes, and assisted living centers will
perform the following tasks:
i) Absorb overflow of patients from the affected area (e.g., from Temporary
Medical Operations Staging Areas and affected hospitals) as able.
ii) Provide daily reports of the number of available beds to the Department of
Health and Hospitals.
b) Volunteer organizations (including churches) will perform the following
tasks:
i) Support relief effort activities as directed by the National Incident
Management System.
ii) Assist in transport of victims from Search and Rescue Bases of Operations
to Temporary Medical Operations Staging Areas under the direction of
authorized command personnel.
iii) Assist feeding of refugees and response personnel as the capability exists
under the direction of authorized command personnel.
c) Other private industries will perform the following tasks:
i) Provide transportation for victims and equipment from Search and Rescue
Bases of Operations under the direction of authorized command personnel.
ii) May be asked to assist in decontamination operations at Search and
Rescue Bases of Operation and other locations as needed under the
direction of authorized command personnel.
d) The Department of Public Safety will perform the following tasks:
i) Process individuals through the decontamination setup at Search and
Rescue Bases of Operations and other locations as needed.
ii) Assist in transporting individuals from Search and Rescue Bases of
Operations to Temporary Medical Operations Staging Areas.
iii) Triage victims at Search and Rescue Bases of Operations.
e) Animal Control will perform the following task:
i) Provide basic animal sheltering and basic veterinary care as available.
c. Coordinating Instructions
i. Requests for assistance, patient treatment information, and other situation report
information will be provided through the National Incident Management System to
the Joint Operations Center.
ii. Further reports will be required as the situation dictates (reference State Emergency
Operations Plan and National Response Plan). For example, under the State
Emergency Operations Plan there is a requirement for E-Team reports twice daily.
Parishes will be operating under Parish Emergency Operations Plans.
1.0 PRE-LANDFALL 1
Appendix A: Incident Action Plans 1
Appendix B: State of Louisiana Hurricane Checklist 26
Appendix C: FEMA Region VI Hurricane Checklist 36
4.0 DEBRIS 51
Appendix A: Organizational Chart 51
Appendix B: Debris Timeline 52
6.0 SHELTERS 63
Appendix A: Materials and Services 63
Only the bolded sections in this table of contents are contained in this document.
i
This page intentionally left blank.
ii
Temporary Medical Care Appendices
Te m p o r a r y M e d i c a l C a r e
Appendix A: Definitive Care Patient Estimates and Associated
Staffing Needs
Primary Care Needs/Estimates
Based on search and rescue estimates, a maximum of 7,750 patients per day will arrive at the
Temporary Medical Operations Staging Areas. If the National Disaster Medical System carries
the full responsibility for medical treatment at these sites, up to 31 Disaster Medical Assistance
Teams operating at full capacity (250 patients per day each) will be needed to adequately meet
the patient load estimates. In order to meet the requirement, 22 operational Disaster Medical
Assistance Teams and nine developmental Disaster Medical Assistance Teams will be deployed.
This will decrease the National Disaster Medical System’s ability to augment area hospital staff
and to provide for personnel rotation after a two-week period.
The amount of patients not counted in U.S. Health Resources and Services Administration bed
numbers (e.g., injured victims streaming into affected hospitals after landfall) needs to be
factored in. Using data from a small sample of local hospitals during Hurricane Ivan (2004), an
average ratio of 1 patient to 4.25 healthcare workers, visitors, and sheltered family members in
the affected hospitals was obtained. Again, one must factor in the effects of the storm, along with
post-landfall effects, that will cause an additional surge of patients from trauma, infections,
snakebites, psychological trauma, and other illnesses. It is unknown how many additional
persons will come to the affected hospitals after landfall, and what supplies (e.g., food, water,
and critical supplies) hospitals will have on hand prior to landfall. These unknown factors add
urgency to the need to define clearly a plan for communications with affected hospitals, and to
define the specific plans for re-supply prior to evacuation.
The consensus of the temporary medical care planning group, confirmed by U.S. Health
Resources and Services Administration participants’ experience in Hurricane Ivan (2004), was
that the estimate of 2,000 patients needing evacuation from affected hospitals was too low. A
total of 926 patients were housed in three of the metropolitan New Orleans area hospitals alone
during Hurricane Ivan.
It is the recommendation of the planning group that licensed beds in affected areas be used as
estimates of the number of patients requiring rescue from affected areas and further inpatient
care. In addition, it is estimated that there would be a minimum of 900 special needs patients,
along with approximately 100 nursing home staff in the affected areas. It should be noted,
however, that nursing home representatives reported a significant problem in obtaining bus and
other transportation for evacuation of ambulatory residents during Hurricane Ivan. It is
recommended that this issue be studied further as part of the planning process. Due to this factor,
the estimate of nursing home staff and residents left in the affected areas could possibly be much
higher.
The total number of inpatients needing evacuation from affected areas is 10,026 and the total
number of staff, family, visitors, victims arriving for refuge after landfall, and others needing
evacuation from affected hospitals and nursing homes is 38,885. This yields a total number of
48,911 for patients, staff, visitors, family, refugees requiring re-supply, and evacuees from
affected hospitals. The 2004 U.S. Health Resources and Services Administration surge capacity
estimate for areas outside of Regions 1, 3, and 9 is 3,116 beds.
The estimated total number of patients requiring inpatient care for the first four days post-
landfall is 11,325. This estimate is the sum of the number of patients from Temporary Medical
Operations Staging Areas (1,299), the number of patients from evacuated hospitals (9,126), and
the number of special needs patients from nursing homes (900).
Using the staffing ratios from Acute Care Center: A Mass Casualty Care Strategy for Biological
Terrorism Incidents,1 the following staff would be required for a 24-hour shift to accommodate
the patient numbers referenced above (for a series of 50 bed nursing units): 434 physicians, 453
nurse practitioners/physician’s assistants, 2718 registered nurses/licensed practical nurses, 1812
nursing assistants/technicians, 906 medical clerks, 453 respiratory therapists, 453 case managers,
453 social workers, 906 housekeepers, and 906 patient transporters.
Recent experiences from the 2004 Florida hurricane season added the need to provide for
housing for staff’s family members, if needed, in order to get staff to report to work.
1
U.S. Army Soldier and Biological Chemical Command. Acute Care Center: A Mass Casualty Care Strategy for
Biological Terrorism Incidents. Department of Defense, December 2001.
All the medical treatment facilities in the area affected by the high-water levels will be virtually
useless. At best, they will shelter in place whatever patients they were not able to discharge prior
to landfall.
In addition, refugees (non-injured or ill individuals) will come to treatment facilities for
sheltering. The Louisiana Hospital Association has provided estimates for the numbers of
population at risk (patients by categories, staff, family members, and refugees) (see Appendix
A). The Nursing Homes Association needs to address their population at risk, specifically those
that have residents with special needs.
Several treatment facilities owned by the State and the Department of Veterans Affairs were
identified in the immediate area (and two Veterans Affairs Medical Centers in Alexandria and
Shreveport) that could provide surge alternate facilities. These facilities are the St. Gabriel
Women’s Correctional Facility, St. Gabriel, Louisiana; Jetson Youth Correctional Facility,
Scotlandville, Louisiana; Veterans Affairs Nursing Home, Clinton, Louisiana; and Carville
Hospital, Carville, Louisiana. The Louisiana Hospital Association will identify other facilities
around the State with surge capacity.
The following are Federal assets that may be requested by the State to fill the need for inpatient
and acute care temporarily.
Department of Defense
• Army Contingency Support Hospital (296 beds)
This is a large medical capability that has eight wards providing intensive nursing care
for up to 96 patients; seven wards providing intermediate care for up to 140 patients; two
wards providing minimal nursing care for up to 40 patients; and one ward providing
neuropsychiatry care for up to 20 patients. Surgical capability is based on eight operating
rooms or 144 operating room hours per day. The unit can be further augmented with
surgical/medical specialty teams to increase its capability. This facility requires several
days’ notification before deployment and two weeks to set up.
• Navy Expeditionary Medical Facility (115 beds)
Buildup begins with deployment of a 25–45 person Mobile Medical Augmentation
Response Team, which can arrive within 12–24 hours. This team provides emergency
care and some psychiatric counseling and can treat 200–250 patients per day on a 24-hour
basis for 72 hours. Re-supply will extend duration of operations.
The Mobile Medical Augmentation Response Team can be the advance element for the
Expeditionary Medical Facility. The Expeditionary Medical Facility can be onsite within
two to three weeks, self-sustaining with food service and lodging for staff. The setup time
is one to two weeks (if tent layout is utilized versus building of opportunity).
The Expeditionary Medical Facility has four operating rooms, 15 intensive care unit beds,
and 115 holding beds. It can perform 20–30 life-saving surgeries per day, and has an x-
ray, lab, and pharmacy capable of self-sustaining for seven days before requiring re-
supply. It also provides ambulance service, patient evacuation, and medical regulating.
• Air Force Expeditionary Medical Support System (builds from 10 beds and up by
increments of 25 beds)
The basic Expeditionary Medical Support System consists of a 10-person team that can
care for 500–2000 patients. It provides primary, preventive, and critical care, including a
field surgical capability (20 patients in 48 hours, including 10 life- or limb-saving
surgeries) with four holding beds. It can deploy within six hours of notification. A 60-
person team can care for 2000–3000 patients with 10 hospital beds, basic radiology,
dental, and laboratory support. An additional 20 personnel increases the number of beds
and care to 3000–5000 patients. Additional increments of 25 beds or medical specialties
can be added.
The following resources are available for patient movement from staging areas to Temporary
Medical Operations Staging Areas or definitive care.
Ground Ambulance
Model Litters Ambulatory Attendants
997 Military Ambulance 4 2 1
998 Military Ambulance 2 2 1
Civilian Ambulance 2 1 1
Helicopters
Model Litters Ambulatory Attendants
UH-60 Blackhawk 4 6 2
CH-43 15 25 2
CH-47 Chinook 20 30 2
State Police TBD TBD TBD
Once the State of Louisiana decides to evacuate patients using the National Disaster Medical
System, at the request of the Department of Health and Human Services, the Department of
Defense coordinates with ESF-1 to provide support for the evacuation of seriously ill or injured
patients to locations where hospital care or outpatient services are available.
The Department of Defense is responsible for regulating and tracking these patients to
appropriate treatment facilities (e.g., National Disaster Medical System non-Federal hospitals,
Veterans Affairs hospitals, and Department of Defense military treatment facilities). Using
available transportation resources, and those from other supporting agencies, if necessary, and in
coordination with the National Disaster Medical System Medical Interagency Coordination
Group, the Department of Defense evacuates and manages victims/patients from the patient
collection point (Baton Rouge Regional Airport) to National Disaster Medical System patient
reception areas, using the Department of Defense’s patient tracking and regulating system. The
Global Patient Movement Requirement Center (part of the U.S. Transportation Command) will
coordinate the required beds (using the Federal Coordinating Centers, Department of Defense,
Department of Veterans Affairs, or contract civilian treatment facilities) and airlift possibilities.
In addition to military aircraft, the Global Patient Movement Requirement Center may use
commercial air ambulance companies.
Under the National Response Plan, the National Disaster Medical System would be activated.
Disaster Medical Assistance Teams have been already incorporated into the plan. The
Department of Defense could be asked to provide temporary field medical treatment facilities to
support the relief and recovery. The National Disaster Medical System, Department of Health
and Human Services, Department of Defense, and Department of Veterans Affairs can quickly
provide temporary medical personnel to augment civilian medical personnel. If needed, field
treatment facilities could be set up at flat, well-drained ground.
The National Disaster Medical System provides primary care medical services in austere
environments. As discussed previously, 22 operational teams exist that can function in a self-
sufficient manner for 72 hours, and support triage and primary care operations at each of the
Temporary Medical Operations Staging Areas. Each team can triage and treat up to 250 patients
per 24-hour period. Patient holding, and even limited critical care patient support, can be
provided, but at the expense of primary care services. If asked to provide care for the estimated
7,750 injured victims at the staging areas, all 22 operational teams must be fielded and
augmented with an additional nine developmental teams. These developmental teams are not
self-sufficient and would require facility and/or material support.
catastrophic incident. Each National Medical Response Team can perform the following
specific functions:
a. Provide mass or standard decontamination.
b. Collect samples for laboratory analysis.
c. Provide medical care to contaminated victims.
d. Provide technical assistance to local Emergency Medical Services.
e. Assist in triage and medical care of chemical, biological, radiological, nuclear, or
explosive events before and after decontamination.
f. Provide technical assistance, decontamination, and medical care at a medical facility.
g. Provide medical care to Federal responders on site.
4. International Medical Surgical Response Team: There is currently one operational
International Medical Surgical Response Team, located in Boston, Massachusetts. The
mission of the International Medical Surgical Response Team is to assist in international
disasters at the request of the Department of State and to augment other U.S. disaster
assets outside the U.S. Each team is comprised of 25 medical and five logistical
personnel. The medical personnel include trauma and general surgeons, physician’s
assistants, registered nurses (some with trauma expertise), anesthesiologists, and
paramedics. The International Medical Surgical Response Team provides triage and
initial stabilization, definitive surgical care, critical care, and evacuation capacity. The
team can deploy in four hours and is self-sustaining for 72 hours.
5. Disaster Mortuary Operational Response Team: There are currently 11 Disaster
Mortuary Operational Response Teams. Each team is comprised of Funeral Directors,
Medical Examiners, Coroners, Pathologists, Forensic Anthropologists, Medical Records
Technicians and Transcribers, Finger Print Specialists, Forensic Odontologists, Dental
Assistants, X-ray Technicians, Computer Professionals, administrative support staff, and
Security and Investigative personnel. During an emergency response, Disaster Mortuary
Operational Response Teams work under the guidance of local authorities by providing
technical assistance and personnel to recover, identify, and process deceased victims.
Capabilities include temporary morgue facilities; victim identification; forensic dental
pathology; forensic anthropology; and processing, preparation, and disposition of
remains. The Disaster Mortuary Operational Response Team program maintains two
Disaster Portable Morgue Units at FEMA Logistics Centers (one is in Rockville,
Maryland, and the other is in Sacramento, California). The Disaster Portable Morgue
Unit is a cache of equipment and supplies for deployment to an incident site. It contains a
complete morgue, including workstations for each processing element and prepackaged
equipment and supplies.
would be activated and could begin arriving on site in an additional 24 hours. Assumptions
include the following:
• Ground and air transportation routes are available to move National Disaster Medical
System assets.
• 24 hours post-activation, teams will be in place, setup, and providing care within their
region (East, Central, and West).
• If an incident occurs in one region (East or West), only one third of the assets will be on-
site and providing care at 24 hours post-activation. All other activated teams will arrive
and initiate care within 48 to 76 hours.
• In the event of catastrophic incident, the standard of care will be minimal life support and
patient holding for two to three days.
Based on the specific treatment plan developed for southeast Louisiana, up to nine teams are
anticipated to be staged in preparation for this event. By the third day post-landfall, an additional
22 teams could be brought in if required to meet the projected casualty estimates. In a
catastrophic event, the entire National Disaster Medical System could be brought to bear by the
third day post-event. The timeline for deployment of the National Disaster Medical System
personnel post-event is anticipated to occur as shown in the table below.
Single Nine 31
Care Provided Team Teams Teams
(Patients per Day)
Treat and Release
250 2250 5000
(Outpatient Facility)
Treat and Limited Holding
160 1440 4500
(Alternate Care Facility)
Standard Medical Holding Facility
50 450 1400
(Hospital Ward)
Mass Casualty Incident
150 1350 4200
(Holding Collection Facility)
The National Disaster Medical System has approximately 1800 medical personnel that could be
deployed for a catastrophic event. It is estimated that between 300 and 1100 personnel can
support the triage and primary care operations at the Casualty Collection Points and Temporary
Medical Operations Staging Areas. The remaining 700 could be made available for definitive
care support. A summary of the National Disaster Medical System force strength is shown in the
table below.
The Commissioned Corps Readiness Force can provide the following approximate staffing:
• 50 total medical personnel in the first 24 hours
• 150 total medical personnel within 48 hours
• Possibly support two rotations of 150 for two-week increments for a total of one month
• Unable to provide long-term support after one month
Commissioned Corps officers can provide a wide variety of public health and medical services
(both domestically and internationally), to include:
1. Providing direct medical and dental care to disaster victims and/or responders:
a. In support of community clinics or hospitals.
b. To augment the National Disaster Medical System Teams.
c. To augment the American Red Cross in shelters and outreach programs.
d. To provide prophylaxis or vaccination teams to communities, to include utilization of
the Strategic National Stockpile.
2. Providing mental health and social work services to victims and/or responders:
a. In support of community clinics or hospitals.
b. To augment the Disaster Medical Assistance and Disaster Mortuary Operational
Response Teams.
c. To augment the American Red Cross in shelters and outreach programs.
d. To support prophylaxis or vaccination clinics.
3. Providing occupational health support to responders. Corps officers can provide
occupational health support to include personal protective equipment, environmental
hazards, hygiene, food, water and sanitation, mental health, and social work services to
victims and/or responders:
a. In support of American Red Cross operations.
1. Purpose
a. The Region 3 Temporary Medical Operations Staging Area (TMOSA) is where persons
who are rescued from the affected areas will be brought to be processed and checked for
medical needs.
b. This appendix will assist Region 3 TMOSA officials located at Nicholls State University,
Thibodeaux, Louisiana, to provide coordinated medical assistance to people coming from
“lily pads”, SARBOOs, and other hurricane affected areas during the post-landfall phase.
3. Concept of Operations
a. The Central Command Post will be located at Nicholls State University.
b. Parking lots may be designated as landing zones.
c. Region 3 TMOSA Operations—Region 3 TMOSA operations are divided into five major
components as listed below:
i. Filter Operations
1) Filter 1: Cleaning Station
2) Filter 2: Meet and Greet
3) Filter: Routing Station (Treat and Street)
ii. Immediate Care Operations
iii. Special Needs Operations
iv. Evacuation Operations
v. Temporary Morgue Operations
d. These five major operations will provide medical assistance are described in detail below.
i. Filter Operations
1) Filter 1 (Cleaning Station) and Filter 2 (Meet and Greet)—Before arriving at
location an affected person will go through the decontamination center located at
John L. Guidry Stadium. Fire trucks with about 500 volunteer fire departments
will be available for decontamination at this location. Portable tents from 6
parishes and 2 mass decontamination trailers with capacities of 50 people/hr and
200 WALKING people/hour respectively, will also be available for
decontamination at Region 3 TMOSA. Barker Hall has been designated as the
“meet and greet” site as this location. This is subject to change based on
coordination with State and Federal agencies.
2) Filter 3: Routing Station (Treat and Street)
Adjoining parking lots will be used for this purpose.
ii. Immediate Care Operations—Disaster Medical Assistance Team (DMAT) will be
placed at the Stopher and Shaver gymnasiums.
iii. Special Needs Operations—Betsy Ayo, Lindsly Hall, and Family Consumer Science
Buildings have been designated as the possible location for special needs population
shelter. Betsy Ayo is the only building that will have a generator in this situation.
iv. Evacuation Operations (Safe Haven)—The student union is the designated safe haven
for evacuation operations. This location will have a generator for lights only.
Thibodaux Civic Center is a potential safe haven if not damaged.
iv. Temporary Morgue Operations—Refrigerated trucks near the Environmental Safety
Building will be used as Temporary Morgue operations.
b) Liaison Officer with Region 3 OEP: The Liaison will be responsible for
maintaining direct chain of communication with his/her counterpart at the
other Regional T-MOSAs and State and Federal agencies. The Liaison officer
is the point of contact for representatives of other governmental agencies, non-
governmental organizations, and/or private entities.
c) Safety Officer (SO): The Fire Department Safety Officer will be the
designated Safety Officer for Region 3 T-MOSA. The SO will be responsible
for monitoring incident operations and advise the ICC on all matters relating
to operational safety, including health and safety of the medical personnel
operating at the T-MOSA.
d) Operations Chief: the PRAT team leader will be the designated Operation
Chief for Region 3 T-MOSA. He/she is responsible to the ICC for the direct
management of all ongoing activities at the site. He/she will be establishing
the tactical objectives of the operational period in coordination with other
section chiefs/personnel including Medical (DHH) and General (DSS).
e) Logistics Chief: The Assumption Parish Manager will be the designated
Logistics Chief for Region 3 T-MOSA. He/she will be responsible for all
support requirements needed to facilitate effective and efficient management
of all activities on going at the site. He/she will be responsible for identifying
the resource needs, gaps and mitigation strategies in regard to reasonable
transportation assets, replenishment of supplies, feeding of volunteers and
evacuees, crowd control etc.
f) Planning Chief: The OPE Assistant is the designated Planning Chief for
Region 3 T-MOSA. He/she will be in charge of collecting, evaluating, and
disseminating the on-going situational updates for the ICC and maintaining
the up-to-date status of the situation at the location. The incident action plan
for the operational periods will be maintained by Planning Chief.
g) Finance and Administration Section: The Assumption Parish
Secretary/Treasurer’s office will function as the finance and administration
section in the Region 3 T-MOSA. This section is responsible for controlling
the finances and other administrative support services.
iv. Support Entities
1) Region 3 TMOSA will coordinate with the following entities for support of the
key designated organization described above. These entities will be located at the
EOC. Each agency will appoint their internal incident command to report to the
appointed person in the Incident Command Center.
a) A Designated Regional Coordinator will be assigned by HHS to the Region 3
T-MOSA, and will be responsible for coordinating with the regional hospitals
and other medical resources.
b) Law Enforcement: The local law enforcement agency will be assigned to the
site. They will work in coordination with ESF #15. They will be responsible
for:
i) Maintaining law and order, including shelter occupancy;
ii) Traffic control, including movement to shelter;
iii) Security of the facility and equipments; and
1. Purpose
a. The Region 9 Temporary Medical Operations Staging Area (TMOSA) is where persons
who are rescued from the affected areas are brought to be processed and checked for
medical needs.
b. This appendix will assist Region 9 TMOSA officials located at Southeastern Louisiana
University (Hammond) to provide coordinated medical assistance to people coming from
“lily pads,” SARBOO’S and other hurricane affected areas during the post-landfall phase.
3. Concept of Operations
a. General
i. Central command post will be located at Pennington Center.
ii. A helipad will be available by University Center. The field to the south of Cefalu
Center may also be used for the same purpose. A field triage officer should be located
near the helicopter landing.
iii. Parking lots may be designated as landing zones.
b. Region 9 TMOSA Operations will be divided into five major components as listed
below:
i. Filter Operations
1) Filter 1: Cleaning Station
2) Filter 2: Meet and Greet
3) Filter: Routing Station (Treat and Street)
ii. Immediate Care Operations
iii. Special Needs Operations
iv. Evacuation Operations
v. Temporary Morgue Operations
c. These five major operations will provide medical assistance as described below.
i. Filter Operations
1) The field triage officer will be responsible for coordinating this operation.
a) Filter 1 (Cleaning Station)
b) Filter 2 (Meet and Greet)
Before arriving at Pennington Center, an affected person will go through the
decontamination center. The fire department currently performs
decontamination for Waterford 3 and may help with decontamination center.
Every hospital in Region 9 has trained decontamination teams and may assist
in the decontamination process, also.
c) Filter 3: Routing Station (Treat and Street)
University Center, Pennington Center, and an old high school building will be
used to screen affected people. All three locations have showers and should be
i. Region 3 TMOSA will coordinate with the following entities for support of the key
designated organization described above. These entities will be located at the EOC.
Each agency will appoint their internal incident command to report to the appointed
person in the incident command center.
1) A Designated Regional Coordinator will be assigned by HHS to the Region 9
TMOSA and will be responsible for coordinating with the regional hospitals and
other medical resources.
2) Law Enforcement: The local law enforcement agency will be assigned to the site.
They will work in coordination with ESF #15. They will be responsible for:
a) Maintaining law and order, including shelter occupancy;
b) Traffic control, including movement to shelter;
c) Security of the facility and equipments; and
d) Assisting in the expedited movement of the evacuees to increase the
throughput of the TMOSA.
3) Fire Department: The local fire department agency will be assigned to the site.
They will work in coordination with local and State ESF #4. They will be
responsible for:
a) Assisting law enforcement in traffic and evacuee control;
b) Helping with the decontamination of vital facilities and thoroughfares; and
c) Containing any fire and/or hazardous materials situations that may arise.
4) Utilities: The local utilities agencies will be designated to work with ICC to
restore and maintain vital facilities and services including, but not limited to,
power, water, sewerage, and debris clearance.
5) Transportation: The local transportation providers will work in coordination with
ESF #1 to provide support in regard to transportation assets for the evacuees,
medical resources, DMAT team logistics needs, supplies transportation, etc.
6) Troop C: This is the designated state police troop for Region 9.
Points of Contact
DHS/FEMA Point of Contact
DHSIFEMA Region VI
Attention: Joe Bearden
800 North Loop 288
Denton, TX 76209 Cell phone numbers and email addresses have been
(940) 898-5470 withheld as allowed by the Freedom of Information Act,
5 U.S.C. 552(b)(2) and (6).
LOHSEP Point of Contact
3. Execution
a. Concept of Operations
i. Pre-disaster group site identification and selection process:
1) The identification of sites by the State and local officials is essential to the
timely implementation of the temporary housing program. Site
identification should be accomplished before hurricane season and
reviewed/updated annually (see Temporary Housing Appendix E:
Temporary Housing Site Data Collection).
a) Partner with the State of Mississippi and Native American Tribes
within the State of Louisiana to identify sites using the Group Site
Data Collection Sheet (Temporary Housing Appendix E: Group Site
Data Collection Sheet Draft) for temporary housing.
b) Request neighboring states to identify any available facilities that can
possibly be used for temporary housing.
c) Find military bases (nationwide) for temporary housing. LOHSEP will
request through FEMA available facilities from DoD. Level of
assistance provided will be based on current situation.
2) Identify areas for mobile homes and other temporary housing in
coordination with local officials.
a) LOHSEP will task Parishes to provide a list of 20 potential publicly-
owned sites of 20 acres or more in their area, updated yearly
(beginning in October) with quarterly reports (funded by EMPG).
Consider negotiating agreements pre-disaster to use publicly-owned
land to avoid leasing agreements for commercial properties. Parishes
will use Temporary Housing Site Data Collection format (Appendix
E).
b) The Louisiana Board of Regents will be contacted by LOHSEP to
identify available resources, using the Temporary Housing Site Data
Collection format (Appendix E).
c) Procedures for identification and inspection of sites.
1) State and local assets will be determined using the Temporary
Housing Site Data Collection checklist for screening of possible
sites (Appendix E).
2) USACE will provide confirmation of site assessment, per mission
assignment from FEMA.
iii. Coordinate with the Individual Assistance Strike Team (Task Force) to assess
any unmet housing needs (wholesale), act as liaisons to locals, and coordinate
with local community relations teams, mobile home teams (retail), and
potential sites.
iv. Execute a multi-faceted phased temporary housing strategy to move people
from emergency shelter to temporary housing on to permanent housing as
quickly as possible. Priorities of effort will go to emergency shelter residence,
giving priority to those individuals from the most heavily impacted areas that
will require long-term temporary housing. Concurrent strategies are as follows
(see Temporary Housing Appendix B: Phases of Housing Requirements and
Programmatic Approaches):
1) Strategy 1: Enable use of existing resources.
2) Strategy 2: Convert existing resources and construct emergency group
sites.
3) Strategy 3: Develop temporary housing sites.
b. Specific Tasks to Lead, Support, and Coordinate Agencies
i. Strategy 1: Enable use of existing resources.
1) Intermediate housing will encompass all alternatives that provide a
minimum family living environment that can be executed quickly,
including local and regional relocation. Possible alternatives will include
college campuses, barracks, hotels and motels, personal travel trailers and
recreational vehicles, adopt-a-family, rental rooms in private homes,
vacation homes, camp facilities (e.g., church, Boy/Girl Scouts, and 4-H),
cruise ships, and all available rental units. This strategy will also include
assistance to survivors moving in with family or friends and/or relocating
to areas outside of the State, and negotiating with hotel chains in and out
of the State. Lump sum payments may be an option.
1.5) Host City concept: refer to Appendix ___ (next)
2) ESF-1 will perform the following tasks:
a) Provide transportation assets to support interim housing transition.
b) Establish a mass transit plan.
c) Augment existing transportation hubs to handle increased traffic.
3) ESF-2 will perform the following tasks:
a) Establish mobile communication units to support temporary housing.
b) Provide sites for survivors to make out-going phone calls and
computers for Internet access.
4) ESF-3 will perform the following tasks:
a) Conduct site assessments.
b) Establish sweep teams.
c) Acquire materials.
d) Provide ice and water to distribution sites.
5) ESF-4 will perform the following tasks:
a) Establish staging areas.
b) Provide material handling personnel and equipment.
6) ESF-5 will perform the following tasks:
a) Manage pre-deployed disaster supplies.
b) Provide management/oversight of temporary housing mission.
c) Manage logistics support.
d) Utilize Mobile Emergency Response Support as required.
e) Establish and maintain a comprehensive national housing resource list.
f) Coordinate with private sector.
g) Provide home recovery kits.
7) ESF-6 will perform the following tasks:
a) Provide congregate feeding to individuals who require it.
b) Provide first aid services.
8) ESF-7 will perform the following task:
a) Provide procurement services through contracting, purchasing, and
leasing.
9) ESF-8 will perform the following task:
a) Provide basic health needs.
10) ESF-10 will perform the following task:
a) Provide hazardous materials assessments.
11) ESF-11 will perform the following tasks:
a) Establish food banks and commodities.
b) Expedite food stamp program.
12) ESF-12 will perform the following task:
a) Provide permanent power restoration in concert with the temporary
housing strategy.
13) Other agencies will perform the following tasks:
a) The Department of Housing and Urban Development and Department
of Veterans Affairs will provide government furnished housing and
rental units.
b) The Department of Treasury will expedite check processing.
c) The U.S. Postal Service will establish postal service to support
temporary housing programs.
d) The American Red Cross will establish/update the Client Assistance
Network.
e) DHS/FEMA will provide security for temporary housing sites until
units are occupied. At that time, property management, who will
coordinate security-related issues with local law enforcement, will
replace private security guards. (Official DHS/FEMA security policy
is currently being developed.)
14) State/local governments will perform the following tasks:
a) Execute the State and Parish plans.
b) Provide local utilities, re-establish utilities as needed, and give support
to temporary housing strategy.
c) Provide law enforcement, fire protective services, and emergency
medical services.
d) The State Real Estate Commission will provide data on available
rental units and properties for purchase.
ii. Strategy 2: Convert existing resources and construct emergency group sites.
1) In this phase, all of the available resources that can be easily converted
without requiring large workforces and that are already tied into existing
infrastructure will be utilized. Examples of these are conversions of
warehouses, office buildings, and large vacant buildings; refurbishing
empty motels and hotels; repairing housing stock with minor or moderate
damage for re-occupancy by former residents; and development of
emergency group sites with use of travel trailers. Prior site selection is
critical to the emergency group site mission.
a) Consult DHS/FEMA Regulation 44 CFR § 60.3 (e) (9)—Regulation
allowing for travel trailers to be placed in flood plain.
b) In accordance with DHS/FEMA Privacy Act Systems of Records,
published in the Federal Register, Vol. 69, No. 219 on November 15,
2004, Notices/Routine Use (f), when an applicant is occupying a
DHS/FEMA temporary housing unit, DHS/FEMA may release only
the location of the DHS/FEMA temporary housing unit to local
emergency managers for the sole purpose of preparing emergency
evacuation plans. DHS/FEMA shall not release any information on an
individual, such as their name or type and amount of disaster
assistance received.
2) ESF-1 will perform the following tasks:
a) Provide material transportation.
b) Increase staging area.
3) ESF-2 will perform the following tasks:
a) Provide communications by restoration of central office facility.
b) Concentrate on industry and commercial.
4) ESF-3 will perform the following tasks:
a) Provide design assistance.
b) Provide construction contracting and management.
c) Conduct site assessments.
d) Conduct structural integrity assessments.
5) ESF-4 will perform the following tasks:
a) Provide personnel and equipment for material handling.
b) Provide construction manpower.
c) Provide logistics support.
d) Provide laundry, shower, and kitchen units.
6) ESF-5 will perform the following tasks:
a) Provide pre-deployed disaster supplies.
b) Provide home recovery kits.
c) Manage donated goods/services.
d) Manage logistics support.
e) Use Mobile Emergency Response Support as required.
f) Provide security for construction sites as requested.
7) ESF-6 will perform the following tasks:
a) Provide congregate feeding.
b) Provide first aid.
8) ESF-7 will perform the following tasks:
a) Provide procurement services to support activities such as the
following:
i) Conducting structural assessments.
ii) Providing public building services for real estate leasing.
iii) Providing communications support.
iv) Providing fleet transportation.
v) Providing showers and sanitation facilities.
9) ESF-8 will perform the following task:
a) Provide basic medical and mental health services.
10) ESF-10 will perform the following task:
a) Provide hazardous materials assessments.
11) ESF-11 will perform the following tasks:
a) Establish food banks and commodities.
b) Expedite the food stamp program.
12) ESF-12 will perform the following task:
a) Provide permanent power restoration in concert with the temporary
housing strategy.
13) Other agencies will perform the following tasks:
a) The Department of Housing and Urban Development/Veterans Affairs
will provide government furnished housing and rental units.
b) The Department of Treasury will expedite check processing.
c) The U.S. Postal Service will establish postal service to support
temporary housing programs.
d) The Department of Defense (Louisiana National Guard and/or Title 10
Forces if available) could conduct housing repair sweeps, support
construction of converted facilities, provide mobile kitchens, and
provide transportation.
e) The Small Business Administration will provide loans for repair of
commercial multi-family or single-family dwellings.
f) The American Red Cross will update the Client Assistance Network.
g) DHS/FEMA will provide security for temporary housing sites until
units are occupied. At that time, property management, who will
coordinate security-related issues with local law enforcement, will
replace private security guards. (Official DHS/FEMA security policy
is currently being developed.)
14) State/local governments will perform the following tasks:
a) The Department of Corrections will provide construction manpower.
b) The Department of Insurance will support expedited claims process.
c) Local utilities will re-establish utilities in support of the temporary
housing strategy.
d) Provide law enforcement, fire protective services, and emergency
medical services.
e) The State Real Estate Commission will provide data on properties
available rental for purchase.
f) Establish and provide warehousing and distribution centers.
g) The Board of State Contractors will develop local workforce
strategies.
h) The Department of Transportation and Development will provide
public work services and infrastructure development.
i) The Department of Social Services will provide crisis-counseling
services.
iii. Strategy 3: Develop temporary housing sites.
1) In this phase, group sites will be established using all available
prefabricated and modular units to create mobile home parks, possibly
including stacking units. The siting of individual mobile units is also
included here, as is the construction of multi-family housing under the
Department of Housing and Urban Development Section 8. This phase
will require a large workforce and establishment of significant
infrastructure.
a) Consult DHS/FEMA Regulation 44 CFR § 60.3 (e) (9)—Regulation
allowing for travel trailers to be placed on individual sites in flood
plain.
b) In accordance with DHS/FEMA Privacy Act Systems of Records,
published in the Federal Register, Vol. 69, No. 219 on November 15,
2004, Notices/Routine Use (f), when an applicant is occupying a
DHS/FEMA temporary housing unit, DHS/FEMA may release only
the location of the DHS/FEMA temporary housing unit to local
emergency managers for the sole purpose of preparing emergency
evacuation plans. DHS/FEMA shall not release any information on an
individual, such as their name or type and amount of disaster
assistance received.
2) ESF-1 will perform the following tasks:
a) Coordinate transportation material and equipment to include material
handling equipment at construction sites.
b) Develop, operate, and maintain a mass transit system.
c) Provide single trips from shelters to temporary housing sites
d) Provide local transportation (shuttles) to shopping, jobs, medical, etc.
3) ESF-2 will perform the following task:
a) Restore wireless communication systems.
4) EFS-3 will perform the following tasks:
a) Provide design assistance.
b) Provide construction contracting.
c) Establish sweep teams.
d) Conduct site assessments.
e) Conduct structural integrity assessment.
f) Engage in site development.
g) Engage utility augmentation including site sewage treatment.
h) Site and install modular units. Haul, install, and recover contracts for
travel trailers.
5) ESF-4 will perform the following tasks:
a) Provide material handling personnel and equipment.
b) Provide construction manpower.
c) Provide logistics support.
d) Provide laundry, showers, and kitchen units.
e) Provide contracting and procurement services.
6) ESF-5 will perform the following tasks:
a) Manage staging areas.
b) Manage housing sites.
c) Manage logistics support.
d) Use Mobile Emergency Response Support as required.
7) ESF-7 will perform the following tasks:
a) Provide procurement services to support activities such as the
following:
i) Procuring travel trailers, other modular units, and prefabricated
structures.
ii) Providing contracting support for transportation.
8) ESF-8 will perform the following task:
a) Establish medical services infrastructures.
9) ESF-10 will perform the following task:
a) Provide hazardous materials assessments.
10) Other agencies will perform the following tasks:
a) The U.S. Postal Service will establish postal service to support
temporary housing programs.
b) The Department of Defense (Louisiana National Guard and/or Title 10
Forces if available) will support construction of utilities for temporary
housing sites, support site development, support staging areas, and
provide transportation.
c) The Federal Protection Service will provide security forces.
d) The Small Business Administration will provide housing and personal
property repair/replacement loans, including vehicles.
e) The American Red Cross will offer support to DHS/FEMA.
f) The Department of Housing and Urban Development will provide
housing support and assistance for construction use and transfer to the
private sector.
g) DHS/FEMA will provide security for temporary housing sites until
units are occupied. At that time, property management, who will
coordinate security-related issues with local law enforcement, will
replace private security guards. (Official DHS/FEMA security policy
is currently being developed.)
11) State/local governments will perform the following tasks:
a) The Department of Corrections will provide construction manpower.
b) The Department of Insurance will support expedited claims process.
c) Local utilities will re-establish utilities and support of temporary
housing strategy.
d) Provide law enforcement, fire protective services, and emergency
medical services.
e) Establish and provide warehousing and distribution centers.
f) The Board of State contractors will develop local workforce strategies.
g) The Department of Transportation and Development will provide
public work services and infrastructure development.
h) Establish community services.
i) The Department of Health will establish hospitals in conjunction to a
medical infrastructure program.
j) The Department of Social Services will provide programs to support
recovery family needs.
iv. The Temporary Group Site Development will estimate a requirement for
200,000 units, based on the following:
1) In “normal” disasters, requirements turn out to be 10% or less of total
affected units.
2) There will be minimal group sites in the southeast Parishes, reflecting
strong cultural desires to return to home sites. Travel trailers and the
placement of mobile homes on individual lots will be the primary means
of meeting temporary housing needs in these areas.
3) The most heavily impacted Parishes in the New Orleans area will generate
the bulk of the group site housing requirement.
4) The estimate of the total displaced households for these Parishes will be
300,000. A requirement to house two-thirds of these households is
estimated.
5) It will be the responsibility of the State and Parish governments to identify
potential sites for group temporary housing sites. Thought should be given
to this well before an event occurs.
6) The maximum site capacity should be 5,000 units.
7) Priority should be given to locating these sites as subdivisions of existing
communities, rather than creating new towns.
8) For some of these sites, temporary may well become long-term.
9) The initial inventory of mobile homes/travel trailers will be placed on
individual sites. While production of units is ramping up, group site
preparation can begin.
10) Pre-fabricated units will be available in stackable configurations, which
can reduce the amount of land required for a group site.
11) A representative timeline is below. This table is an initial estimate needed
to launch operations. It includes the possibility of creating additional units
as required before operations are terminated. (See Temporary Housing
Appendix C.)
Months
1 2 3 4 5 6 7
Travel Trailers:
Individual Sites 400 600 1000 2500 - - -
(Assume 4500)
Mobile Homes/Travel
Trailers:
Existing Sub- - 200 500 1000 800 500 -
divisions/Commercial
Parks (Assume 3000)
Small Group Sites:
500 Units - 100 400 1000 5000 6000 -
(Assume 25)
Medium Group Sites:
1000 Units - - 5000 10,000 15,000 - -
(Assume 30)
Large Group Sites:
5000 Units - - - 25,000 50,000 50,000 25,000
(Assume 30)
Total 200,000
400 900 6900 39,500 70,800 56,500 25,000
(Worst-Case Scenario)
Time
ESF Day 1–5 Day 6–10 Day 10–30 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8
1 125 175 250 300 300 300 300 300 300 300
2 6 6 12 12 12 12 12 12 12 12
3 100 200 800 4880 9750 10050 7800 5930 1460
4 150 150 150 285 1785 1635 1635 1635 1635 1635
5–IA 1000 (*) 1500 3000 3000 3000 3000 3000 3000 3000 3000
5–LOG 275 450 500 500 500 550 650 650 650 650
6 **
7 16 27 30 50 50 50 50 50 50 50
8 ***
10 6 6 12 12 12 12 12 12 12 12
11 150 150 150
12 6 6 12 12 12 12 12 12 12 12
OFA/HUD 6 6 6 6 6 6 6 6 6 6
State**** 264 364 734 734 734 734 734 734 734 734
Total 1104 3040 5656 9791 16161 16361 14211 12341 7871 6411
Prepared by:
Site Name:
Location:
Parish:
Identification:
Latitude/Longitude: