Académique Documents
Professionnel Documents
Culture Documents
PROJECT
MANAGEMENT
(5577)
MBA Executive
ZAHID NAZIR
Roll # AB523655
Semester: Autumn 2009
QUESTION 1
2
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
PROJECT
3
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Construction of a building
Manufacturing of product
Computerization of a office
PROJECT MANAGEMENT
4
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
5
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
WHY A PROJECT
Planning is the determining in advance of what is to be done, how it is
to be done, when it is to be done and who will do it. It encompasses
setting objectives, and making day-to-day decisions on how these
objectives can best be achieved.
Projects never go according to plan. Things arrive late, there are
deviations, and production falls behind schedule and resources are
suddenly not available. This is not a reason not to plan. In fact, it is a
good reason to plan.
Planning gives direction to leaders and teams. It focuses on the
objectives of the Project and/or the organization. If the team is aware
of the objectives for which the project strives, coordination, co-
operation and team work will most likely be enhanced.
Planning can reduce duplication of work and unnecessary activities.
When team members know exactly what to do, inefficiencies become
more apparent.
rationale;
goal;
objective;
strategy;
outputs and targets;
activities;
inputs;
6
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
7
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
1. Project Initiation
The initiation phase essentially involves the project ‘start-up’. It is the
phase within which the business problem or opportunity is identified, the
solution is agreed, a project formed to produce the solution and a project
team appointed. The following diagram depicts the activities undertaken:
8
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
At any stage during (or after) the development of a Business Case, a formal
Feasibility Study may be commissioned. The purpose is to assess the
likelihood of a particular solution option’s achieving the benefits outlined in
the Business Case. The Feasibility Study will also investigate whether the
forecast costs are reasonable, the solution is achievable, the risks are
acceptable and/or any likely issues are avoidable.
9
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
After the solution has been agreed and funding allocated, a project is
formed. The Project Charter defines the vision, objectives, scope and
deliverables for the project. It also provides the organization structure (roles
and responsibilities) and a summarized plan of the activities, resources and
funding required to undertake the project. Finally, any risks, issues, planning
assumptions and constraints are listed.
1.4 Appoint Project Team
At this point the scope of the project has been defined in detail and the
project team are ready to be appointed. Although a Project Manager can be
appointed at any stage of the project, s/he will need to be appointed prior to
the establishment of the project team. The Project Manager documents a
detailed Job Description for each project role and appoints a human resource
to each role based on his/her relevant skills and experience. Once the team
are ‘fully resourced’, the Project Office is ready to be set-up.
1.5 Set up Project Office
The Project Office is the physical environment within which the team will be
based. Although it is usual to have one central project office, it is possible to
have a ‘virtual project office’ environment, with project team members in
various locations around the world. Regardless of the location, a successful
project office environment will comprise the following components:
Location (either physical or virtual)
Communications (telephones, computer network, email, internet
access, file storage, database storage and backup facilities)
Documentation (methodology, processes, forms and registers)
Tools (for accounting, project planning and risk modeling).
10
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
2. Project Planning
By this stage, the benefits and costs of the project have been clearly
documented, the objectives and scope have been defined, the project
team has been appointed and a formal project office environment
established. It is now time to undertake detailed planning to ensure that
the activities performed in the execution phase of the project are properly
sequenced, resourced, executed and controlled.
The first step is to document the Project Plan. A ‘Work Breakdown Structure’
(WBS) is identified, which includes a hierarchical set of phases, activities and
tasks to be undertaken on the project. After the WBS has been agreed, an
assessment of the effort required to undertake the activities and tasks is
made. The activities and tasks are sequenced, resources are allocated and a
11
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
detailed project schedule is formed. This project schedule will become the
primary tool for the Project Manager to assess the progress of the project.
2.2 Develop Resource Plan
12
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
The foreseeable project risks are then documented within a Risk Plan and a
set of actions to be taken formulated to both prevent each risk from
occurring and reduce the impact of the risk should it eventuate. Developing
a clear Risk Plan is an important activity within the planning phase as it is
necessary to mitigate all critical project risks prior to entering the Execution
phase of the project.
13
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
The key to a successful project is gaining acceptance from the customer that
each deliverable produced meets (or exceeds) his/ her requirements. To
clarify the criteria used to judge each deliverable for customer acceptance, an
Acceptance Plan is produced. The Acceptance Plan provides the criteria for
obtaining customer acceptance, a schedule of acceptance reviews within
which customer acceptance will be sought and a summary of the process
used to gain acceptance of each deliverable from the customer.
2.7 Develop Communications Plan
Prior to the Execution phase, it is also necessary to identify how each of the
stakeholders will be kept informed of the progress of the project. The
Communications Plan identifies the types of information to be distributed,
the methods of distributing information to stakeholders, the frequency of
distribution and responsibilities of each person in the project team for
distributing information regularly to stakeholders.
2.8 Develop Procurement Plan
The last planning activity within the Planning phase is to identify the
elements of the Project which will be acquired from external suppliers to the
project. The Procurement Plan provides a detailed description of the
Products (i.e. goods and services) to be procured from suppliers, the
justification for procuring each product externally, as opposed to from
within the business, and the schedule for procurement. It also references the
process for the selection of a preferred supplier (“Tender Process”) and the
14
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
process for the actual order and delivery of the procured products
(“Procurement Process”).
2.9 Contract Suppliers
3. Project Execution
The Execution phase is typically the longest phase of the project (in terms
of duration). It is the phase within which the deliverables are physically
constructed and presented to the customer for acceptance. To ensure that
the customer’s requirements are met, the Project Manager monitors and
15
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
16
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Whilst the Project Team are physically producing each deliverable, the
Project Manager implements a series of management processes to
monitor and control the activities being undertaken.
An overview of each management process follows.
Time Management
Time Management is the process within which time spent by staff
undertaking project tasks is recorded against the project. As time is a scarce
resource on projects, it is important to record the time spent by each
member of the team on a Timesheet to enable the Project Manager to
control the level of resource allocated to a particular activity. A Timesheet
Register provides a summary of the time currently spent on the project and
enables the Project Plan to be kept fully up to date.
Cost Management
Cost Management is the process by which costs (or expenses) incurred on
the project are formally identified, approved and paid. Expense Forms are
completed for each set of related project expenses such as labor, equipment
and materials costs. Expense Forms are approved by the Project Manager
and recorded within an Expense Register for audit purposes.
Quality Management
Quality is defined as “the level of conformance of the final deliverable to the
customer’s requirements”. Quality Management is the process by which the
quality of the deliverables is assured and controlled for the project, using
17
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Change Management
Change Management is the process by which changes to the project’s scope,
deliverables, timescales or resources are formally defined, evaluated and
approved prior to implementation. A core aspect of the Project Manager’s
role is to manage change within the project successfully. This is achieved by
understanding the business and system drivers requiring the change,
documenting the benefits and costs of adopting the change and formulating
a structured plan for implementing the change. To formally request a change
it is often necessary to complete a Change Form. The change request details
may then be recorded within a Change Register.
Risk Management
Risk Management is the process by which risks to the project (e.g. to the
scope, deliverables, timescales or resources) are formally identified,
quantified and managed during the project. A project risk may be identified
at any stage of the project by completing a Risk Form and recording the
relevant risk details within the Risk Register.
Issue Management
Issue Management is the method by which issues currently affecting the
ability of the project to produce the required deliverable are formally
managed. After completion of an Issue Form (and logging the details within
the Issue Register), each issue is evaluated by the Project Manager and a set
of actions undertaken to resolve the issue at hand.
18
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Procurement Management
Procurement Management is the process by which product is sourced from
an external supplier. To request the delivery of product from a supplier, a
Purchase Order must be approved by the Project Manager and sent to the
supplier for confirmation. The status of the purchase is then tracked using a
Procurement Register until the product has been delivered and accepted by
the project team.
Acceptance Management
Acceptance Management is the process by which deliverables produced by
the project are reviewed and accepted by the customer as meeting his/her
specific requirements. To request the acceptance of a deliverable by the
customer, an Acceptance Form is completed. The Acceptance Form
describes the criteria from which the deliverable has been produced and the
level of satisfaction of each criterion listed.
Communications Management
Communications Management is the process by which formal
communications messages are identified, created, reviewed and
communicated within a project. The most common method of
communicating the status of the project is via a Project Status Report. Each
communication item released to the project stakeholders is captured within
a Communications Register.
3.3 Perform Phase Review
19
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
4. Project Closure
Following the completion of all project deliverables and acceptance by the
customer, a successful project will have met its objectives and be ready for
formal closure. Project Closure is the last phase in the project and must
be conducted formally so that the business benefits delivered by the
project are fully realized by the customer.
20
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
References:
www.scribd.com
www.method123.com
Fundamentals of Project Management by James Lewis
Project Management AIOU
####################
21
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
QUESTION 2
Every business activity as carried out for
profit making and one of the principles of
profit making is cost minimization and
effective cost management. All the business
activities need strong financial support for its
smooth and effective completion. Financial
resources are the key factors among all the
given resource of any business organization,
therefore the success of a project depends on
effective cost management. You are required
to write a detailed note on project cost
management.
(20)
22
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
23
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
1. Resource Planning
Resource planning involves determining what physical resources (people,
equipment, materials) and what quantities of each should be used to
24
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
25
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
26
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
2. Cost Estimating
Cost estimating involves developing an approximation (estimate) of the costs
of the resources needed to complete project activities.
When a project is performed under contract, care should be taken to
distinguish cost estimating from pricing. Cost estimating involves
developing an assessment of the likely quantitative result—how much will it
cost the performing organization to provide the product or service involved.
Pricing is a business decision—how much will the performing organization
charge for the product or service—that uses the cost estimate as but one
consideration of many.
Cost estimating includes identifying and considering various costing
alternatives. For example, in most application areas, additional work during
a design phase is widely held to have the potential for reducing the cost of
the production phase. The cost estimating process must consider whether
the cost of the additional design work will offset the expected savings.
27
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
28
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
29
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
The project management team must weigh the additional accuracy against
the additional cost.
4. Computerized tools: Computerized tools such as project management
software and spreadsheets are widely used to assist with cost estimating.
Such products can simplify the use of the tools described above and thereby
facilitate rapid consideration of many costing alternatives.
30
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
3. Cost Budgeting
Cost budgeting involves allocating the overall cost estimates to individual
work items in order to establish a cost baseline for measuring project
performance.
1. Cost estimates.
2. Work breakdown structure. The work breakdown structure identifies
the project elements that costs will be allocated to.
3. Project schedule. The project schedule includes planned start and
expected finish dates for the project elements that costs will be allocated to.
31
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
This information is needed in order to assign costs to the time period when
the cost will be incurred.
1. Cost estimating tools and techniques: The tools and techniques already
described used for developing project cost estimates are used to develop
budgets for work items as well.
1. Cost baseline: The cost baseline is a time-phased budget that will be used
to measure and monitor cost performance on the project. It is developed by
summing estimated costs by period and is usually displayed in the form of an
S-curve, as illustrated in Figure.
Many projects, especially larger ones, may have multiple cost baselines to
measure different aspects of cost performance. For example, a spending plan
or cash flow forecast is a cost baseline for measuring disbursements.
32
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
4. Cost Control
Cost control is concerned with (a) influencing the factors which create
changes to the cost baseline to ensure that changes are beneficial, (b)
determining that the cost baseline has changed, and (c) managing the actual
changes when and as they occur. Cost control includes:
Monitoring cost performance to detect variances from plan.
Ensuring that all appropriate changes are recorded accurately in the
cost baseline.
Preventing incorrect, inappropriate, or unauthorized changes from
being included in the cost baseline.
Informing appropriate stakeholders of authorized changes.
Cost control includes searching out the “whys” of both positive and negative
Variances. It must be thoroughly integrated with the other control processes
(scope change control, schedule control, quality control). For example,
inappropriate responses to cost variances can cause quality or schedule
problems or produce an unacceptable level of risk later in the project.
33
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
1. Cost baseline.
2. Performance reports: Performance reports provide information on cost
performance such as which budgets have been met and which have not.
Performance reports may also alert the project team to issues which may
cause problems in the future.
3. Change requests: Change requests may occur in many forms—oral or
written, direct or indirect, externally or internally initiated, and legally
mandated or optional. Changes may require increasing the budget or may
allow decreasing it.
4. Cost management plan.
1. Cost change control system. A cost change control system defines the
procedures by which the cost baseline may be changed. It includes the
paperwork, tracking systems, and approval levels necessary for authorizing
changes. The cost change control system should be integrated with the
overall change control system.
2. Performance measurement. Performance measurement techniques help
to assess the magnitude of any variations which do occur. Earned
value analysis is especially useful for cost control. An important part of cost
control is to determine what is causing the variance and to decide if the
variance requires corrective action.
3. Additional planning. Few projects run exactly according to plan.
Prospective changes may require new or revised cost estimates or analysis of
alternative approaches.
4. Computerized tools. Computerized tools such as project management
software and spreadsheets are often used to track planned costs vs. actual
costs, and to forecast the effects of cost changes.
34
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Each of the above approaches may be the correct approach for any given
work item.
5. Lessons learned: The causes of variances, the reasoning behind the
corrective action chosen, and other types of lessons learned from cost
35
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
References:
www.method123.com
A Guide to the Project Management Body of Knowledge
Condensed GSAM Handbook
####################
36
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
QUESTION 3
37
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
38
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Quality must be viewed on an equal level with scope, schedule and budget. If
a project donor is not satisfied with the quality of how the project is
delivering the outcomes, the project team will need to make adjustments to
scope, schedule and budget to satisfy the donor’s needs and expectations. To
deliver the project scope on time and on budget is not enough, to achieve
stakeholder satisfaction the project must develop a good working
relationship with all stakeholders and understand their stated or implied
needs.
Project quality management consists of four main processes:
Quality Planning
Quality Assurance
39
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Quality Control
Quality Improvements
These processes interact with each other as well as with the processes
of other knowledge areas
Each process involves an effort of one or more individual or group of
individuals based on the need of the project.
Each process occurs at least once in every project phase during the
project life cycle.
1. QUALITY PLANNING
40
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Scope Statement
The scope statement is a key input to quality planning because it
documents major project deliverables as well as project objectives
which serve to define important stakeholder requirements.
41
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Product description
Although the elements of the product description may be embodied in
the scope statement, the product description often contains details of
technical issues and other concerns that may affect quality planning.
Benchmarking
Benchmarking involves comparing actual or planned project practices
to those of other projects to generate ideas to:
1- Generate ideas for improvement
2- provide a standard for measurement of performance
42
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Note: other projects compared may be within the same organization or out
side and may be within the same application area or in another.
Flow charting
The flowcharting techniques in quality management generally include
cause and effect diagram.
System or process flow charts.
Flowcharting can help in anticipating probable quality problems and
thus helps to develop approaches for dealing with them.
Design of Experiments
This is an analytical technique which aims to define variables that have
most influence on the overall outcome.
This technique is commonly applicable to the product of the project
issues.
However this technique can also be used in project management issues
such as cost and schedule tradeoffs to allow for optima solutions.
43
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Note: the project quality plan can be highly detailed or broadly framed based
on the needs of the project.
Operational Definitions
An operational definition describes what something is and how it is
measured by the quality control process. For example:
the project management team must indicate the start and end of every
activity in a detailed schedule.
Weather the whole activity or certain deliverables are to be measured.
Operational definitions are also called Metrics in some areas of application.
Checklists
A checklist is a structured tool used to verify that a set of required
steps or requirements have been performed.
Many organizations have standard checklists to ensure consistency of
frequently performed activities.
2. QUALITY ASSURANCE
44
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
45
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
46
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
3. QUALITY CONTROL
47
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
48
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Control Charts
These charts are graphical representations that display the result of a
process over time and are used to determine if the process is “in
control”.
When in control the process should not be adjusted , however it may
be changed in order to provide improvements.
Control charts may be used to monitor any type of output variable.
Control charts are most often used to monitor repetitive activity in
production but can also be used to monitor cost and schedule
variances.
49
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Pareto Charts
Pareto Charts based on Pareto’s rule, which states that 80 percent of the
problems are often due to 20 percent of the causes. The assumption is that
most of the results in any situation are determined by a small number of
causes and helps identify the vital few contributors that account for most
quality problems. The chart is a form of histogram that orders the data by
frequency of occurrence; it shows how many defects were generated by a
type of category of identified cause. For example to determine the errors in
the collection of beneficiary data the project team identified five causes and
for each cause the frequency they contained errors, the data is plotted as
shown in the chart below, the bars represent each category and the line the
cumulative percentage of the errors, the chart allows to identify that 80% of
the errors could be reduced just by improving the collection of data in two
categories instead of focusing efforts to correct all categories.
Statistical Sampling
Statistical sampling involves choosing a part of a population of interest
for inspection.
Appropriate sampling can effectively reduce the cost of quality control.
50
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
51
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
4. QUALITY IMPROVEMENT
Identify what you want to improve; the project using the data found
in the quality control process identifies the areas that need
improvement.
Analyze the problem or system, the team then investigates the causes
for the problem and its implications to the project, the causes may be
internal or external to the project.
Develop potential solutions or changes that appear likely to improve
the problem or system, the team brainstorms ideas and potential
solutions to the problem, taking in consideration its impact to the
52
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Cost of Quality
The cost of quality is the sum of costs a project will spend to prevent poor
quality and any other costs incurred as a result of outputs of poor quality.
Poor quality is the waste, errors, or failure to meet stakeholder needs and
project requirements. The costs of poor quality can be broken down into the
three categories of prevention, appraisal, and failure costs:
53
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
References:
www.pm4dev.com
PMI body of knowledge
####################
54
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
QUESTION 4
There are different levels of management
in an organization and every level tries to
meet its assigned goals. In every project
all the levels of management act jointly for
the successful completion of the project.
Compare and evaluate the role of these
levels, also explain the conflict that can
arise between these levels with your
proposed solutions of these problems.
(20)
55
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
56
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
1. Project Initiation
2. Project Planning
The second phase of the process involves defining clear, distinct activities
and work required to complete the activities for each individual project.
Examples of activities at this phase are defining the project scope,
defining the work breakdown structure, estimating resource
requirements, outlining communication procedures among managers,
57
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
team members, and the customer, identifying and evaluating risk, and
developing a Baseline Project Plan.
3. Project Execution
The third phase of the process involves implementing the plans created in
the earlier phases, Project Initiation and Project Planning. Examples of
activities at this phase are executing the baseline plan, managing changes
to the baseline plan, monitoring project progress, and communicating
project status to managers, team members, and the customer.
4. Project Closedown
The final phase of the process involves bringing the project to an end.
Examples of activities at this phase are evaluating team members,
conducting final project reviews, and closing the customer contract.
The project manager is responsible for carrying out the initiation, planning,
execution, and closedown phases of a project. The success of a project relies
strongly on the project manager. The role of this person is to evaluate project
feasibility and to create the plan of activities required to meet the objectives.
This individual must be able to build an environment in which the project
can be executed while protecting the environment from factors that could
impede progress, planning the work that has to be completed to reach the
goal, and keeping the course of the project in control. It is important for a
project manager to possess a diverse set of skills - management, leadership,
technical, customer relationship, and conflict management.
Managers spend 42% of their time on reaching agreement with others when
conflict occurs. Conflict management within a team environment requires
the ability to solve problems, set goals, compromise, settle personality
58
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
differences, and resolve conflicts. Training for project managers in this area
is necessary for their success, as they are typically responsible for handling
conflict during a project. The remainder of this paper will address conflict
and its resolution in project management.
Understanding Conflict
“A process that begins when one party perceives that another party has
negatively affected, or is about to negatively affects something that
first cares about.”
“Is a process that begins when one party perceives that has negatively
affected, or is about to negatively affect, something that the first party
cares about.”
Conflict is viewed as a cycle: "As with any social process, there are causes;
also, there is a core process, which has results or effects. These effects feed
back to effect the causes." To understand conflict further, the situation must
include elements of interdependence, emotions, perceptions, and behaviors.
For example, conflict occurs between parties whose tasks are
interdependent, who are angry with each other, who perceive the other party
as being at fault, and whose actions cause a business problem.
59
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Deconstructive conflict occurs when a decision has not been found and the
problem remains, energy is taken away from more important activities or
issues, morale of teams or individuals is destroyed, and groups of people or
teams are polarized.
60
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
61
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Whether we feel like we want to fight or flee when a conflict arises, we can
deliberately choose a conflict mode. By consciously choosing a conflict mode
instead of to conflict, we are more likely to productively contribute to
solving the problem at hand.
Larson and Gray’s list of five strategies for managing dysfunctional conflict
provides a good summary of approaches.
Mediation:
The goal is to identify multiple possible alternatives and to mutually select
one that is acceptable to all involved parties and in the interest of project
objectives.
Arbitration:
This strategy requires the project manager to provide a safe and productive
opportunity for the conflicted parties to air their disagreements. After careful
attention and fully listening to each party, the project manager should
formulate, define, and provide a solution to the parties. This strategy is
based on the forcing approach to conflict described earlier. Arbitration can
often be effectively combined with mediation by forcing an initial conflict
solution and then allowing the parties to negotiate to a more mutually
acceptable alternative.
Control:
Based on the smoothing approach described earlier, this strategy seeks to
bring tension and emotions down to a level at which productive discussion
62
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
and negotiation can occur. Humour is often an effective tool, as well as the
use of temporary breaks or time-outs in the discussions between conflicted
parties.
Acceptance:
The decision can be made that the conflict consequences are negligible
relative to project objectives and, therefore, require no action. This strategy
carries significant risk of later escalation and should be combined with
specific plans for monitoring the situation to ensure that the conflict
remains at an acceptable level.
Elimination:
Finally, the elimination strategy is reserved for those conflicts that have
become so dysfunctional that the project can no longer tolerate any impacts
from them. Often a last resort, elimination involves the removal of the
conflicted parties from involvement with the project.
Gender
Self-concept
Expectations
Situation
Position (Power)
Practice
Determining the best mode
Communication skills
Life experiences
63
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
situations when they are best utilized are identified. These modes are
Confronting, Compromising, Smoothing, Forcing, and Avoiding.
64
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
65
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Conclusion
Conflict in project management is not necessarily unfavorable when properly
managed. Several advantages have been identified such as increasing
personal growth and morale, enhancing communication, and producing
better project outcomes. However, conflict can be the decline of an
organization if it is not effectively managed. The challenge for organizational
leaders and project managers is to try to maintain the right balance and
66
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
References:
http://www.pmi.org/projectmanagement/success.htm
http://itprojmngt.8m.net/projman/pm_what.html
http://www.newgrange.org/FTP/pm.ppt
####################
67
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
QUESTION 5
Discuss the following in detail:
i). PERT
ii). GANNT Charts
iii). WBS
(20)
68
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
PERT
69
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
70
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
GANTT Charts
Gantt Charts (Gant Charts) are useful tools for analyzing and planning more
complex projects. They:
71
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Give you a basis for scheduling when these tasks will be carried out
Allow you to plan the allocation of resources needed to complete the
project, and
Help you to work out the critical path for a project where you must
complete it by a particular date.
When a project is under way, Gantt Charts help you to monitor whether the
project is on schedule. If it is not, it allows you to pinpoint the remedial
action necessary to put it back on schedule.
72
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Gantt charts give a clear illustration of project status, but one problem with
them is that they don't indicate task dependencies - you cannot tell how one
task falling behind schedule affects other tasks. The PERT chart, another
popular project management charting method, is designed to do this.
Automated Gantt charts store more information about tasks, such as the
individuals assigned to specific tasks, and notes about the procedures. They
also offer the benefit of being easy to change, which is helpful. Charts may be
adjusted frequently to reflect the actual status of project tasks as, almost
inevitably, they diverge from the original plan.
73
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Importance of WBS
It defines and breaks down the work on a project into manageable
chunks, often called work packages.
It tells us what activities or tasks have to be done in order to complete
the project.
It serves as the foundation for the development of schedules, budgets,
and resource requirements.
74
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
WBS Role
It is the basis for
Estimating
Budgeting
Pricing
Controlling Costs
Assigning Responsibility
Scheduling
Allocating Resources
75
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
Level Description
1 Total Program
Managerial Project
2
Levels 3 Task
4 Subtask
Technical 5 Work Package
Levels 6 Level of Effort
Benefits of WBS
Risk and
Contingency
Plans
Estimates
Schedule
WBS
Risk Control
Project
Control Change
Control
Activity List
Communication Control
Progress
Project Plan Reports
76
ZAHID NAZIR AB523655
PROJECT MANAGEMENT
References:
www.mindstool.com
PMBOK Guide
####################
77
ZAHID NAZIR AB523655