Académique Documents
Professionnel Documents
Culture Documents
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
1.
GENERAL DESCRIPTION
The KWU design machine are supplied with four bearings out of which three are
the journal bearing and one is combined thrust and journal bearing on H.P.
rear end of the shaft. All the turbine bearing are self aligning type and they
adjust themselves as per the catenary of the machine.
The function of a journal bearing is to support the turbine shaft , but the
thrust bearing support the shaft as well as work as a fix point for the turbine
shaft. The contact arrangements between bearing and bearing supports are of
two types i.e. sphere to sphere in HP front and HP rear bearing and torus to
cylindrical in other bearings.
The bearings are supplied to site after ensuring their contact at works. During
erection all the bearing are supplied to site in aligned and assemble condition in
their individual pedestal from the works. After alignment of the bearing in
their pedestal the seat of the bearing are doweled before dispatch to site.
In case of Thrust and Journal bearing the seat of the bearing neither doweled
from the works nor it is recommended to be doweled at site. The bearings
need preparation before placement of module in position at site. This can be
done even before the placement of pedestal in position for grouting.
1.2.
ASSEMBLY PROCEDURE
1.2.1. After opening the pedestal remove and clean the bearing including
its spherical/ cylindrical seat.
1.2.2. Remove oil guard ring and its duct and keep them in proper place
for their storage at site.
T1-08-0801G
Page No. 1of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
T1-08-0801G
Page No. 2of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
and a feeler gap is noticed on center then the bearing may not
be accepted.
In such cases if the gap
is upto 0.03 mm then
the
matching/lapping may be carried out at site. But in case of higher
gap the matter may be referred to designers. In case of reverse
case if the feeler gap of 0.03 is noticed on both sides of the
bearing the bearing may not accepted at site and matter may be
referred to designers.
1.2.7. Before checking the contact between torus and its seat ensure that
the seat is feeler tight to 0.03 mm without tightening of any bolts
with the pedestal. If necessary this may be corrected with
consultation of designers. Similarly ensure contact between torus\
spherical piece with bearing and in case of variation the matter be
referred to designers and no correction is to be carried out at site
without the approval of manufacturing unit.
1.2.8. Before checking the contact between torus/spherical piece with
bearing and in case of variation the matter may be referred to
designers and no correction is to be carried out at site without
their recommendations.
1.2.9. The sizes of all the shims may be punched in bearing body and
spherical/torus piece of the bearing. The number of shims are to
be limited to 3-4 numbers only even after complete alignment of
machine. A protocol for number of shims may be prepared.
1.2.10.Torus/spherical should not have any radial movement over its
bearing.
This can be seen after opening the torus from the
bearing.
1.2.11. Check jacking oil lines of the bearing and clean them thoroughly.
Ensure jacking oil lines fittings also for their male female threads
etc otherwise this may create the oil leakage through these lines
during operation of the machine. The jacking oil pocket in the
bearing may be checked if necessary they may be corrected at
site as per the drawings.
1.2.12. When ever JOP is not available, use always thick oil during
rotation of shaft over bearing.The type of oil may be used as
servo cylinder 1000 grade of IOC.
1.2.13.After installation of bearing in position the oil clearances may
be checked after few rotation of the shaft. But the final oil
clearances are to be checked after final coupling of the shaft. In
case of variation in side oil clearances no cutting of babbitt metal
is permitted at site. Any variation in clearances may be counter
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0801G
Page No. 3of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
T1-08-0801G
Page No. 4of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
by moving
spherical
seat of
the
axially.
T1-08-0801G
Page No. 5of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
Before deciding axial position of the bearing the axial position of the
rotor is to be determined. If necessary the H.P. rear pedestal as a
whole may be shifted axially to ensure correct position of the
thrust bearing.
Align the thrust bearing in such a way that the thrust pad gap
achieved are prallel and no difference are noticed in front and rear
pad thicknesses.
After ensuring the perfect alignment of the bearing the axial keys
are fitted after assembly of upper half bearing. These axial keys
are to be fitted in perfect parallel slots without any clearances.
The keys are to be fitted in such a way that there is no movement
to the bearing during fitting of these axial keys. Necessary dial
gauges are to be installed on bearing during fitting of these keys.
After completion of axial key works of the bearing the thrust pads
may be fitted in the bearing with a clearance of about 0.10/0.15
mm.
Install lower half bearing in position along with their pads and put
very small quantity of oil on journal then rotate the rotor and put
T1-08-0801G
Page No. 6of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
blue color on the thrust collar of the rotor on both front and rear
side.
Install upper half bearing along with all pads and fix their axial keys.
Rotate the rotor and move + direction axially with the help of
wooden planks. Remove both halves of the bearing and see the
blue contact on thrust pads. If necessary some cutting may be
carried out
on
the
color contact.
This
position the both halves may be bolted out side and their pads
may be checked for color contact over a surface plate also in
front and rear both sides.
carrying out the color contact of the bearing with the rotor.
In spherical
corrected
can
heavy pitting marks are also noticed on same of the bearing and
these need correction by machining it.
T1-08-0801G
Page No. 7of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
T1-08-0801G
Page No. 8of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
T1-08-0801G
Page No. 9of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
ERECTION
T1-08-0801G
Page No. 10of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(BUMP CHECK)
ERECTION
2.
BUMP TEST
The axial clearance check
is determined after
radial clearance
Note: Enter the measured values ( actual dimensions ) on the record sheet
and compare them with the specified dimensions.
Note : Based on the readings of bump check, axial position of the shaft wrt
casing is not to be altered.
T1-08-0802G
Page No. 11of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
3.
ROLL CHECK
3.1.
GENERAL DESCRIPTION
In KWU machine the minimum radial clearances HP, IP and LP casing are
measured by actually by moving the casing radially at site while rotor is rotated
by hand. This is a very accurate and fast method of measuring the minimum
radial clearance of any of the casing.
The major variation in these reading may cause vibration in the machine
and obstruction in barring gear operation etc. Such facilities are not available
in many other designs of machine and causes longer duration in erection and
overhauling of the units.
After completing the alignment of rotors the casing alignments are carried out by
roll check method but equal importance should also be given to the centering of
HP and IP casing.
The centering of casing may not be fully sacrificed in comparison of rolling
test readings and a compromise between these two readings should be made.
The rolling test should be carried out in cold machine only.
3.2. PROCEDURE
ROLL CHECK OF HP AND IP CASING
3.2.1. Alignment and coupling of HP-IP and LP rotors are to be
completed before starting the rolling test of the casing in normal
case but this can be done without coupling of LP rotor also.
T1-08-0803G
Page No. 12of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
T1-08-0803G
Page No. 13of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
rotor and lifting of casing continued till it becomes little bit tight
on the seals of the casing
After this the casing is lowered by about 0.05mm and rotor is
rotated again if it is completely free. In case the rotor is still tight on
its manual rotation the casing is further lowered by 0.05 mm on
all four corners. After ensuring the freeness of rotor it is again
rotated and casing is lifted simultaneously on front end till the
rotor rotation becomes tight on seals portion of the casing.
As soon as the shaft becomes tight the lifting
of casing and
casing on front and rear end for deciding the top clearance in front
and rear end of the
of the
casing,
but
kept
the
casing
on
its
original position by
T1-08-0803G
Page No. 14of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
in up/downand
left/right
direction
final
Immediately after this the final radial key of the casing are fixed
and the locked of the casing are released for fitting of the final
casing packers. The final spigot dial reading are repeated and
confirmed with the earlier readings.
3.2.10.After doing the full rolling test and fixing of a final radial keys
and packers of one of the casing the rolling test of another casing
is done including the fitting of final keys and packers.
3.2.11.Necessary offset in the radial clear-ance is also kept before
fitting of final packers of the casing toward the lift of the shaft
during operation of the unit.
3.2.12.No inlet and outlet pipes are to be welded with the casing till
completion of rolling test and installation of final keys and packer
of the casing.
T1-08-0803G
Page No. 15of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
T1-08-0803G
Page No. 16of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(ROLL CHECK)
ERECTION
3.3.
T1-08-0803G
Page No. 17of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
ERECTION
4.
General Description
The catenary of the machine is very important for a turbine and Generator
assembly to achieve proper alignment of various rotors and loading on their
bearing. Any
deviation may
problem
in the
the catenary
and subsequent
During first few years of the operation of the unit the possibility to the
disturbance of the catenary are much more due to settlement of the foundation
frame.
In each overhaul of the unit the catenary of the machine is to be corrected.
The L.P. front and L.P. rear pedestal are directly grouted
lowered with respect to pedestal seal bore and required catenary may be
achieved. In extreme cases these pedestals may be
T1-08-0804G
Page No. 18of 40
STEAM TURBINE
500 MW
ERECTION
4.2.
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
Procedure
4.2.1. Install a bench mark plate near L.P. rear pedestal as height of
the machine center line with the consultation of civil Engrs at site.
A plate of 200 m.m x 300 m.m size with 20 m.m thickness
machined/ground on top side may be welded over a I Beam or a
channel in level condition. This plate is to be installed very carefully
as this will be a future reference for setting up the all elevation of
the machine.
4.2.2. Record half bore error of all the four pedestals and confirm the
readings with the factory records also. The half bore error may be
checked in both upper half and lower half of the pedestal and
same may be punched on both halves in left and right side for
all future references of the machine.
4.2.3. During alignment of pedestal at the time of grouting with
conbextra cement set the height of the pedestals as per required
catenary of the machine considering +value for the half bore error
of the pedestals. While setting the height of the pedestals it should
be kept in mind that the height for the center of the pedestal bore
are to be kept as per the catenary of the machine not the
parting plane of the pedestal.
4.2.4. For better results four water level jar connected to each other
with a polythene pipe may be installed on each pedestal. The
D.M., water may be used here and leakage through polythene
tubes should be avoided fully while making the connections. These
jars may be fabricated at site by about 125 mm. dia pipe with a
plate welded in bottom and then machined for better seating on
pedestal base. The height of the jar may be kept as about 175
mm. A depth micrometer installed and clamped over a magnetic
base is also required for measurement of the water level in the jar.
The micrometer point is to be made very sharp by grinding it.
Here the magnetic base of the 0-10mm dial gauge may be used.
4.2.5. .During measurement of water level in the jar the micrometer is to
be kept approximately in center of the jar. The micrometer along
with the magnetic base to be transferred from one pedestal to
another pedestal very carefully so there is no disturbance to the
height of the micrometer. All the necessary care are to be taken
during this measurement i.e. there should not be any air bubble in
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0804G
Page No. 19of 40
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
5.
General description
T1-08-0804G
Page No. 20of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(HORN DROP TEST)
ERECTION
By horn drop test the loading of the casing on each corner is determined. The
horn drop test is repeated at various stages in individual casing i.e. first
without connection of any pipe lines the horn drop readings are recorded then it
is compared after welding of inlet, outlet and extraction pipe lines etc. The horn
drop readings are very important in HP & IP casing. First the proper horn drop
readings are made without connection of any pipe lines and then the reading
are taken after welding of all pipe lines on HP & IP casing. As such the
influence of these major pipe lines are notices on each corner of HP/IP
casing by comparing the horn drop
indicate the quality of work during assembly/welding of pipe lines with the HP &
IP casing.
This is a very important check and may cause serious problem in operation of
the machine like high vibration in the machine failure of barring gear in hot/cold
machine, obstruction during expansion of machine etc. In horn drop test a drop
is measured
the casing.
T1-08-0806G
Page No. 21of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(HORN DROP TEST)
ERECTION
5.1.1. Procedure
5.1.2. After placement of HP and IP casing on four temporary packers
ensure that the each corner of the casing is loaded on temporary
packer and if necessary the shims may be given on packer for
loading of the casing. The load of shaft is also taken on transport
device during this stage.
5.1.3. After transferring the load of the rotor on bearing and ensuring the
casing centering with respect to shaft the horn drop check may be
carried out.
5.1.4. Before taking the horn drop reading ensure that the enough
clearance is available on front & rear portion of the shaft with their
seals in the casing inside. After completing the centering of the
casing the some may be lifted by 0. 20 mm on all four corners by
providing shims. This will help in avoiding the touching of seals
with the rotor during the horn drop test readings.
5.1.5. No adjustment on packer of the HP front and HP rear pedestals
are to be carried out after taking the horn drop test of the casing
In case if any adjustment is carried out on these pedestal
packers then horn drop test are to be repeated again.
5.1.6. No piping may be connected to HP & IP casing till initial horn drop
readings are over. The piping work should not be postponed for
want of horn drop the only thing the last joint with HP/IP casing
may be left free till completion of horn drop check.
5.1.7. While recording the horn drop readings the casing must be
absolutely free and even the radial and axial key of front and
rear portion of the casing are either to be removed fully or these
are to be made completely free by removing their shims etc.
Actually during this stage of erection only temporary axial and
radial keys are fitted in the casing and even they carry some
shims also. Before making the casings free on axial and radial
key portion the dial gauges are to be installed to monitor the
movement of the casing on radial and axial direction.
Immediately after the completion of the horn drop test these
keys/shims may be installed back and centering of casing may
be rechecked before further works.
5.1.8. In HP casing the initial horn drop test may be done even after
fitting of breach nut assembly and HP exhaust elbow of both sides.
T1-08-0806G
Page No. 22of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(HORN DROP TEST)
ERECTION
5.1.9. In IP casing the initial horn drop test may also be done after fitting
of IP inlet pipe lower half assembly but this pipe of upper half
casing should not be fitted till completion of the horn drop test.
5.1.10.All the four Jacking screw and hydraulic jack on each corner of
the casing are to be installed for the horn drop test readings. A dial
indicator is also to be installed on each corner of the casing for
measuring the drop of the casing.
5.1.11.After initial centering of the casing the each corner packer may
be fitted with a shim of about 1 mm. for further adjustment during
the horn drop test.
5.1.12.During the horn drop test the individual packer of the casing
is removed and the load of that corner is supported over the
jacking screw of the casing. Now gradually the jacking screw is
also relieved with the help of hydraulic jack on that corner and
drop reading is recorded. This is repeated for each corner of the
casing. In case of variation in left and right side reading the
drop is adjusted by + adjustment of shims from left to right side
or vise-versa. No subtraction / addition in shim sizes from outside
is done here and only the shims are adjusted from left to right or
vise versa till equal loading are achieved in left/right side of
individual casing. The sizes of these casing packers are recorded
after completion of horn drop to avoid any confusion at a later
date while fitting the final packers.
5.1.13.While recording the horn drop readings the drop on each
individual corner may be controlled with the help of Jacking
screw so that during this test the casing is not touching with the
shaft in gland portion of the seals at all and enough clearance is
left there to avoid damage to the seals inside the casing.
5.1.14.During the initial horn drop the best reading within 0.05/0.06
may be achieved by fine adjustment of the packer shims. The
comparison in horn drop value should always be made in left and
right side only of an individual casing.
5.1.15.In case of HP casing the drop on rear end is so high that unless
the casing is locked on diagonally opposite end the horn drop
check is not possible. Therefore while recording drop on HP rear
end the front end of the casing diagonally opposite to it should
be locked with casing clamp. The pedestal is also required to be
locked on all four side with its sole plate with the help of the
clamps. In case of IP casing no locking of any corner of the casing
is necessary during the horn drop test.
Bharat Heavy Electricals Limited
T1-08-0806G
Rev 00,
7-98
Page No. 23of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(HORN DROP TEST)
ERECTION
T1-08-0806G
Page No. 24of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
6.
SWING CHECK
6.1.
GENERAL DESCRIPTION
The swing
coupling face geometric form of the two rotor coupled together. This is
measured on opposite end of the coupling and at the free end of the rotor. The
higher swing check value
shell temperature etc. The value of swing check depends on axial runout of
coupling faces, the diameter of the coupling and the length of the rotor. During
the machining of
Designer's on the coupling faces of the rotor resulting to some swing check
values. The maximum swing
above tolerance
can be
worked out from the enclosed graph. However it is recommended to keep the
minimum swing check values for better results during operation of the machine.
Generator and
static excitation system the swing check values are measured on HP rotor front
end only. In 500 M.W. machine the swing check values are measured in H.P.
front end and on exciter rear end. After having general experience of number of
200 MW & 500 MW units, a necessity is felt to measure swing check value on
IP rotor front end also for better results during operation of the units. This can
be done initially during
variation in swing
check
T1-08-0806G
Page No. 25of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
erection
during
operation of the unit and any correction becomes much more tedious a later
stage. The correction
may
coupling position
by correcting
or
be
carried
out
the
either
by interchanging
coupling
faces
the
by
6.2.
PROCEDURE
T1-08-0806G
Page No. 26of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
6.2.4. During coupling with temporary bolts the higher plane of one of
the rotor face is to be coupled with lower plane of another
coupling face of the rotor.
6.2.5. During coupling on temporary bolts the uniform tightening on all the
four temporary bolts are to be ensured otherwise it will disturb
the swing check value of the rotor.
6.2.6. First IP-LP coupling is to be made with temporary bolts and swing
check on IP rotor front end is recorded. After this only HP-IP rotor
is to be coupled with temporary bolts and the swing check value
on HP front rotor is recorded.
6.2.7. During swing check of IP rotor its front end is to be supported
on lifting tackle without making any connection between HP-IP
rotor.
6.2.8. While recording swing check of HP rotor the front end of the rotor
is to be supported on lifting tackle.
6.2.9. During swing check the lifting tackle are to be fitted properly. The
tie rod of lifting tackle should be ensured for correct fitting of its
spherical bearing and Molykote should be applied on these
spherical bearing for their free movement. These spherical
bearing should not obstruct the movement of shaft radially during
checking of its swing check value.
6.2.10.After taking the load of the rotor on lifting tackle ensure that the
rotor is not disturb radially due to fitting of lifting tackle.
6.2.11.During checking of swing check measure radial movement of rotor
on parting plane and rotate the rotor either on jacking oil with hand
barring or with the help of E.O.T crane with thick oil on bearings.
Avoid jerk during rotation of rotor while recording the swing check
values.
6.2.12.After ensuring the swing check values as per the graph with on
temporary coupling bolts, the HP-IP and LP-IP coupling may be
cleared for reaming / honing of the coupling holes. Any variation
need correction of the coupling before reaming/honing of the holes.
6.2.13.The final swing check value of HP front rotor is to be recorded
after fitting/ elongation of all the coupling bolts of HP-IP & LP-IP
rotors. Any variation in readings may be referred to the Designer's.
For improvement of the swing check values, the indifferent
tightening and non-sequential
Bharat Heavy Electricals Limited
Rev 00,
7-98
T1-08-0806G
Page No. 27of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
T1-08-0806G
Page No. 28of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
T1-08-0806G
Page No. 29of 40
STEAM TURBINE
500 MW
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
ERECTION
7.
GENERAL DESCRIPTION
The coupling on turbine shaft are generally rigid coupling but in case of L.P.
rotor sometime the coupling head are shrunk fit and remachined. The basic
function of any coupling is to connect two or more shaft together to form a
shaft assembly. The number of shaft mainly depend upon the rating of the
machine.
A very high accuracy is required during manufacturing of these rotor shaft
at works. The axial runout on the coupling face may not exceed 0.02 mm.
and an additional check is also made at works/site to ensure that the geometry
of the entire coupling surface does not deviate by more then the 0.02 mm.
except the concavity on the coupling face which is permitted upto 0.03/0.04
mm.
The radial and axial alignment of the various shafts are to be completed
before their coupling and alignments are to be done in such a way that the
entire shaft assembly follow the continuous deflection curve given over the
drgs. for a particular machine. The coupling checks determines both the radial
and axial position of the two adjacent coupling flanges relative to one another.
The radial
measurement
are
performed
on
couplings and the axial measurement are performed on outer most diameter
of the coupling. During coupling of the two shafts it should be ensured that the
no stresses are exerted as a results of the coupling each other shaft.
After completion of the alignment and coupling of the shaft the casings are
aligned radially and axially. Here equal importance is given to the radial & axial
T1-08-0807G
Page No. 30of 40
STEAM TURBINE
500 MW
ERECTION
alignment
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
by
the
influence of the axial & radial runout present in the shaft caused due to the
machining.
7.2.
PROCEDURE
T1-08-0807G
Page No. 31of 40
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
T1-08-0807G
Page No. 32of 40
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
H.P. front and HP rear pedestal may be moved with the help of
their radial keys.
7.2.10.The final packers of the pedestal and base plates are fitted before
the grouting of the pedestal itself and here no adjustment is
necessary during erection of the machine. But during overhauling of
the machine the adjustment may be carried out in these packers
for correction of catenary of the machine.
7.2.11.During alignment of rotor make HP/IP and IP/LP coupling gap
parallel. After completion of final alignment no adjustment of
packers and keys etc are permitted on pedestals and bearing the
final alignment of HP/IP & IP/LP rotors should be checked after
fitting of all the final keys and packers of the pedestals.
7.2.12.After alignment couple the HP-IP & IP-LP rotors on temporary
bolts. Record coupled runout of the rotor and ensure that the
coupled runout is not more then 0.03 mm. in any where in the
journal as well as in coupling area. Before coupling of rotor on
temporary bolts record their spigot clearances by actually moving
the rotor radially.
7.2.13.During erection IP-LP swing check on IP front and HP-IP swing
check on HP front are to be recorded on temporary bolts. These
reading are to be ensured within the design limit.
7.2.14.Before alignment/coupling position the two shaft adjustment to
each other depending upon the higher and lower point of the shaft
with respect to their axial face measurement values.
7.2.15.The HP-IP & IP-IP coupling may be cleared for reaming/honing
after ensuring the runout and swing check values of the rotors.
In case of variation the cause of the error may be identified and
corrected before further work of reaming and honing of the
coupling.
7.2.16.During coupling of rotors two taper pins may be used for
proper alignment of coupling holes so that there is minimum
enlargement of holes are done at site during reaming/honing.
Unnecessary enlargement of holes may be fully avoided during
reaming/honing at site as this may cause serious problem at a later
date during overhauling of the unit.
7.2.17.As for as possible ream/hone all the coupling bolts holes to
same size. In exceptional cases only the variation in hole
sizes are permitted. Each hole during honing should be checked
Bharat Heavy Electricals Limited
Rev 00,
7-98
T1-08-0807G
Page No. 33of 40
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
for bananas shape with the help of a parallel ground straight pin
of 0.02/0.03 undersize. No banana shape is permitted in any of
the hole. The hole should be made to 0.005 mm accuracy.
7.2.18.All the coupling bolts are to be machined and ground by
0.02/0.03 mm undersize then the hole dia. These bolts are to
be fitted with thumb pressure only and no additional force is
recommended while fitting these bolts.
7.2.19.A very thin layer of molykote may be applied on all the
coupling bolts during their fitting. The molykote should not be
applied on seating face of the coupling bolts. This may cause
in breaking of their locking pin during elongation of coupling
bolts.
7.2.20.All the coupling bolts are to be balanced before finally
fitting/tightening in position. These are to be balanced within an
accuracy of 5 gms each along with their nuts. In case all these
bolts are of equal size then their weight must be equal. In
exceptional cases the 180o opposite bolts may be made of equal
weight.
7.2.21.During tightening of coupling at any stage first tighten four bolts
on 90o location. Always tighten bolts in proper sequence
with 180o opposite bolts. These bolts are to be elongated to the
value given over drgs.
7.2.22.During tightening of coupling the radial runout on journal and
coupling may be checked at various stages during tightening of
bolts. The final coupled runout should not be more then 0.03 mm.
on coupling and journal of the shaft.
7.2.23.After final tightening of LP-IP and HP-IP coupling the swing
check value on HP front rotor is to be rechecked. In case of
variation in value a proper correction is
to be made with
consultation of designer's.
The indifferent
or unsequential
tightening for achieving the swing check value or coupled runout
value may be fully avoided. this may cause unnecessary stresses
on the coupling.
7.2.24.After completing the coupling work the casing radial and axial
alignment may be done.
T1-08-0807G
Page No. 34of 40
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
in erection / welding of the pipelines at site along with the Piping Engineers. The
piping connection between I.P. casing to L.P. casing i.e. cross around piping
also need proper care but due to its construction with number of bellows in the
system. Present method of erection / welding much of the problems are not
faced during operation of the machine. However if proper care is not taken here
then that may cause the unnecessary loading on the various bellows of the
piping and reduction in their life. In case, if proper care is not taken during
erection / welding of MS inlet, CRH & HRH connections with HP & IP casing, a
load will be transfer from the pipe line to the casing. Which may cause vibration
in the machine, obstruction in expansion of the machine, obstruction of barring
gaer operation in hot / cold machine, higher babbit metal temperature and failure
of brg. babbit etc. during operation of the machine.
8.
PROCEDURE
8.1.
The following points are to be taken care while welding MS, CRH, HRH
pipelines with HP & IP casing and control valves / strainers.
8.1.1. The HP & IP casings are to be cleared in all respects after fitting of
final packers and axial / radial keys of the casing.
8.1.2. The ESV & IV valves are to be cleared after fitting of their
servomotors and then levelling including the correct elevation etc.
8.1.3. The equivalent insulation weight is to be given on each control
valve befor connection of any pipeline with the valve. The change
in hanger value of the control valve is to be adjusted back by lifting
the valve with the help of hangers. The control valve hanger reading
should remain same as before and after installation of equivalent
insulation weight on the valve. After this all the three hangers of
each valve are to be locked to avoid any movement of the valve in
upward direction, in case the equivalent insulation weight is
removed or any of the servomotor is removed. Before starting of
any welding with the control valve the valves are to be locked for
their movement.
8.1.4. Erection and welding of MS line upto MS strainer and HRH strainer
are to be completed first including either their insulation or
T1-17-0808G
Page No. 36of 40
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
T1-17-0808G
Page No. 37of 40
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
8.2.1. If possible keep the insulation weight and servomotors on ESV and
I V control valves during erection /welding of these MS & HRH
lines from strainers to the valve and casing . If the above condition
are fulfilled then there no need of any locking of the valves during
the welding of any pipe lines.
8.2.2. The control valves hanger readings are to be measured with the
inside micrometer in various stages and changes are to be
monitored properly . The readings are to be measured in the
following stages : After complete leveling of ESV and IV control valves with their
servomotors
After putting the equivalent insulation weight on the control
valves.
After readjustements of control valve height equivalent to
insulation weight.
After connection of MS &HRH lines with the strainers .
After connection of MS & HRH lines with the HP & IP casing .
After complete insulation of control valve and pipings.
T1-17-0808G
Page No. 38of 40
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
T1-17-0808G
Page No. 39of 40