Owner:
Contract No 13B1A25
EPC Contractor:
REVISON
Name
Kind Of Change
Date
Signature
A
ACTION
Name
Title
Date
Prepared by
PT.BBB
Irfan Hariansyah
ISSUED FOR
REVIEW
04-February 2014
Reviewed By
PT.IOT
Approved By
OT
Signature
Subcontractor:
Owner:
Contract No 13B1A25
EPC Contractor:
Page 2 of 7
Effective
Date
04-Feb-14
Status
Issued For Review
Description of Change
Owner:
Subcontractor:
Contract No 13B1A25
EPC Contractor:
Page 3 of 7
Contents
1. SCOPE ................................................................................................
................................
........................................................ 4
2. REFERENCE ................................................................................................
................................
.............................................. 4
3. EQUIPMENT AND MATERIALS ................................................................
................................................. 4
4. PROCEDURE................................................................................................
................................
.............................................. 5
5. ACCEPTANCE CRITERIA ................................................................
.......................................................... 6
6. REPAIRS................................
................................................................................................
..................................................... 6
7. VACCUM BOX TEST SKETCH ................................................................
.................................................. 6
8. Report ................................................................................................
................................
......................................................... 7
Attachment (Form Report) ................................................................
.............................................................. 7
Subcontractor:
Owner:
Contract No 13B1A25
EPC Contractor:
Page 4 of 7
1.
SCOPE
1.1. This Procedure contains detail employed by PT BANGUN BEJANA BAJA personnel
for carrying out of leak testing welds by the vacuum box method for OIL TANK
STORAGE TERMINAL AT KARIMUN Project Project.
1.2. The Vacuum box testing will be used
use for testing of welds in the Bottom and Roof only
2.
REFERENCE
3.
API 650 Eleventh Edition: Welded Steel Tank for Oil Storage
plastic
3.3. Vacuum Box: The box shall be constructed to produce and hold a pressure differential
of at least 8 psi (55
(5 kPa gauge). A gauge shall be placed in the system to verify the
required pressure differential. Keep the transparent window on vacuum box clean to
ensure good visibility
visib
while performing the test.
3.4. Dimension of Vacuum Box to be used shall be of convenient size [e.g. 6 in (150 mm)
wide by 30 in (770 mm) long) with a clear window in the top.
3.5. Flashlight or brighter light source.
3.6. Clean dry rags or towels.
Subcontractor:
Owner:
Contract No 13B1A25
EPC Contractor:
4.
Page 5 of 7
PROCEDURE
4.1
Remove all weld slag, mud, dirt, standing water and other debris, which may prevent
bubble formation from areas to be leak tested.
4.2
Performing a visual examination of the bottom and welds prior to performing the
vacuum box test
4.3
4.4
Provide adequate lighting for this examination. For example, daylight or illumination
from a standard 3 volt (2 D Cells) flashlight is sufficient.
4.5
4.6
Apply the leak detector solution to the welds to be tested in a continuous film relatively
free or bubbles.
4.7
Seat the vacuum box. The vacuum box must reach a minimum gauge pressure
reading of 3 psi (20 kPa gauge) or larger.
4.8
4.9
The vacuum
acuum shall be maintained for the greater of either at least 5 seconds or the time
required to view the
th area under test
4.10 The vacuum box test shall have at least 50 mm overlap of previously viewed surface
on each application.
4.11 The presence of a through-thickness
through thickness leak indicated by continuous formation or growth
of a bubble or foam, produced by air passing through
through the thickness is unacceptable.
The presence of a large opening leak, indicated by a quick bursting bubble or spitting
response at the initial setting of the vacuum box is unacceptable. Leak shell be
repaired and retested.
4.12 A record or report of the test
test including a statement addressing temperature and light
intensity shall be complete.
Subcontractor:
Owner:
Contract No 13B1A25
EPC Contractor:
Page 6 of 7
5.
ACCEPTANCE CRITERIA
All leaks located by vacuum box testing are unacceptable.
6.
REPAIRS
7.1. After repairs have been made, the repaired area shall be retested by the applicable
steps in 5.0.
7.2. In addition, the repaired area shall be re-examined
re examined by all other methods
originally
required for the affected
7.
Vacuum Box
Vacuum Gauge
(range 0 ~ -30)
)Psi)
Vacuum Box
Lap weld joint
yang akan di uji
Subcontractor:
Owner:
Contract No 13B1A25
EPC Contractor:
8.
Page 7 of 7
Report
After completion of Vacuum Box test PT. BBB will prepare the report
eport Vacuum Box test for
customer approval.