Académique Documents
Professionnel Documents
Culture Documents
SECT. A
SCOPE OF WORK
1.0
1.1
GENERAL
The Contract shall include the complete supply, installation, testing and
putting into commission, handing-over in approved working order and
maintenance thereafter for the period of the Contract works as detailed
hereafter and as shown on the drawings.
The works to be carried out under this Contract shall include the whole of the
materials and all necessary labour for the complete installation strictly in
accordance with the current edition of the FOC rules, the British Standard
Specification, the British Standard Code of Practice, the requirements of the
local Fire Authority and all other relevant Authorities having jurisdiction over
the installation, together with all incidental works pertaining thereto even
though not specifically mentioned herein or shown on the drawings.
1.2
DESCRIPTION OF WORKS
The works to be carried out under this Contract shall include but not limited,
to the following items: -
1.3
WORK INSTALLED
All work installed, equipment and materials used shall be in full compliance to
the relevant British Standard, the Requirements of Chief Inspectorate of Fire
Services (CIFS) Malaysia and all other relevant authorities having jurisdiction
over the installation.
On completion of the installation, the Contractor shall certify in writing to the
Consultant and the Fire Authority that the installation is in full compliance with
the CIFS requirements and shall take all necessary steps, including the
payment of all the testing fees and getting the receipt in order to obtain the
approval of the installation from the Fire Authority.
The Contractor shall be fully responsible to obtain the approval of the
proposed fire prevention and detection system from the Jabatan Bomba Dan
Penyelamat Malaysia. Any other costs of works that are deemed necessary
and required by the Jabatan Bomba Dan Penyelamat Malaysia for approval
should be cost and appeared on the Summary of Prices as Other works not
listed above but deemed necessary for the approval of Jabatan Bomba Dan
Penyelamat Malaysia.
The Contractor shall have in their employment, a professional engineer
registered with the Board of Engineers, Malaysia to sign, endorse and submit
all the necessary drawings as instructed by the Consultant to the CIFS in order
Part 3
PLS-140032-C/M&E/DPE
FF 1
1.4
WORKMANSHIP
The following specific requirements shall apply to this service:
If the above are not done due to whatever reason, civil contractor shall
provide the same to the best of his ability and charge to the contractor,
the penetrations to be cored by specialist and costs to be borne by the
contractor.
All surface mounted items such as break glass, switch plates unless in
surface conduit shall be set flush with wall.
Part 3
PLS-140032-C/M&E/DPE
FF 2
SECT. B
2.0
2.1
GENERAL
The Contractor shall supply, install, test and commission the complete fire
alarm system. The design and installation of all components and the system
shall comply with the requirement of the following bodies or standards:
Part 3
PLS-140032-C/M&E/DPE
FF 3
2.3
ALARM BELL
The alarm bell shall be of surface mounting type with 6 inches diameter gongs
made of pressed steel and stove enamelled red. The bells shall be suitable for
24 volts D.C. operation and the current consumption shall be limited to 50 mA.
They shall be similar to Gent Model 505 (D.C.). The sound level shall be
of minimum 85 decibel at 3 meters. The alarm bells shall comply with B.S.
5839: Part 1: 1988.
2.4
SMOKE DETECTORS
Smoke detectors shall be of the ionization chamber type radioactive source
and fitted with a built-in light emitting diode as per specification described in
MS1176 Part 7 and approved by the Fire Authority and suitable for flush
finishing to the ceiling. The detectors shall contain an LED, which is lighted up
when the detector is in alarm. Detectors mounted within ceiling voids
shall have remote indicator lights mounted on adjacent wall to indicate when
the detector has been operated.
Each detector shall have individual sensitivity adjustment so that unnecessary
alarm due to small amount of product in the air shall not occur.
2.5
2.6
2.7
CODE OF PRACTICE
The fire alarm system to be installed shall comply with the B.S. Code of
Practice C.P. 1019:1972 Fire Office committee latest edition and of the fire
authorities having jurisdiction over the installation.
2.8
WIRING SYSTEM
All above ground inside the building wiring shall be in G.I. conduit to B.S.31
Part 3
PLS-140032-C/M&E/DPE
FF 4
and concealed cables shall not be smaller than 1.5mm PVC insulated and
rated at 250 volts to B.S. 2004.
Fittings and accessories shall be galvanised and manufactured from steel or
malleable cast iron to B.S. 31.
Conduits shall be concealed throughout. Screwed conduits buried in concrete
shall have the thread coated with approved jointing compound during
assembly and joints treated with a rust inhibiting paint after jointing. All
conduit and accessories shall also be painted with a rust inhibiting paint
wherever the exposed galvanised surface has been cut or otherwise damaged.
Conduits shall be fixed securely to prevent movement and all ends, boxes
shall be effectively plugged to prevent the ingress of water and dirt before
concrete is poured. All bends must be made with the proper conduit bending
machine so that the inner radius of any bend is not less than 2 times the
outside diameter of the conduit. Where condensation is likely to take place,
provision shall be made for the water to drain off without entry into
terminations. The detailed layout of conduit will be the responsibility of the
Contractor. Conduit shall be run neatly in straight lines parallel to walls, floors
and ceilings wherever possible.
Where multiple conduit runs occur, metal brackets multi-way saddles fixed by
means of metal threads shall be used. The ends of conduits shall be cut
square, filed and reamed out after screwing and care shall be taken to ensure
removal or cutting oil and swaf.
Conduit terminations at switches,
switchboards, distribution boards, etc. are to be properly secured with coupler
and male brass bushes.
Conduit terminations to apparatus subject to
vibration or movement shall be made of flexible metallic conduit with brass
adaptors for connection to the rigid conduit system at each end. Where
conduits cross expansion joints they shall be installed so as not to resist
relative movement of the sections.
A suitable crossing shall comprise conduits telescoped one inside the other
with the free end or ends projecting immediately to one side of the crossing.
Where long runs of conduit are unavoidable, adaptable boxes shall be
provided for ease of drawing-in of cables. Draw-in wires shall be provided
inside each conduit to facilitate the drawing-in of cables. Where exposed,
conduits shall be painted orange.
Conduit sizes shall be selected so as to allow removal or replacement of any
one cable without disturbing the others and shall not be less than diameter
without the permission of the Engineer. In no circumstances, the number of
cables drawn into any one conduit shall exceed that stated in tables B5 and
B6 of the 14th Edition of the I.E.E. Regulations. All conduits shall be swabbed
out and free from moisture to the Engineers satisfaction before wiring is
commenced.
2.9
Part 3
PLS-140032-C/M&E/DPE
FF 5
EXCAVATION OF TRENCHES
The Engineer will settle the exact location of each cable trench on the site
when work is ready to commence.
Trenches shall be kept as straight as possible and shall be excavated to
approval formation and dimensions, and shall generally by 30 inches deep.
Trenches shall have vertical sides and are to be timbered and sheeted where
necessary to prevent subsidence.
The excavation of trenches shall include, by way of amplification but not of
limitation, all timbering, pumping and baling required and the provision of all
necessary labour, plant, tools additional soil, fuel and motive power for such
purposes and the cost of this service and of the expendable materials shall be
included.
Before the cables are laid, the bottom of the trench is to be lined with sand or
sifted soil, which is to be punned down to a thickness of 3 inches to form a
bed. After the cables are laid, the first 3 depth of cover backfill shall consist
of sand or sifted soil over which shall be placed protective covers.
Backfilling and reinstatement of open trenches after placing of the cable
protective covers shall also be carried out.
Particular attention shall be taken to ensure that trenches are evenly graded
prior to placing the bedding materials.
Cables passing under roadways shall be installed in duct buried to a minimum
depth of 30 inches.
Cables shall be snaked at every joints or junction box and cables shall not
cross in straight runs of trench or in any other position except where a cross
may be permitted if it is impossible to avoid by advance planning of the day of
cables in a trench.
Routing and excavation of all trenches shall be carried out correctly and
satisfactorily and at such times and places to suit the program of cable
installation work.
Only enough ground shall be opened at a time such that cable laying and
backfilling may proceed without delaying order to avoid having trenches
opened for long periods.
2.11
PROTECTIVE COVERS
Cable covers shall consist of good quality house bricks and shall be laid over
all cables in ground so that there shall be no gap between the covers.
The Supply and lying of cable protective covers are to be included in the rate
for cable laying.
2.12
Part 3
PLS-140032-C/M&E/DPE
FF 6
2.13
CABLE MARKERS
Cable markers shall be provided and installed with the top surface flush with
ground level to identify cable routes and joints positions, other than tee joints
at street lighting columns, or cables laid direct in the ground. Markers shall be
inscribed with indented lettering reading Fire Alarm Cable and shall be
installed at every 100 feet along the route and at any changes in direction.
Part 3
PLS-140032-C/M&E/DPE
FF 7
SECT. C
3.0
3.1
GENERAL
The Contractor shall supply, install, test and commission the necessary
equipment as generally shown on the drawings and to the Specification of
Local Fire Authorities. Samples of equipment before installation shall be
submitted for the Engineers approval.
3.2
3.3
Part 3
PLS-140032-C/M&E/DPE
FF 8
control
of
the
stream
of
chemical
powder.
The dry chemical portable fire extinguishers shall conform to MS 1539.
The finishing colour shall be light blue.
3.4
Part 3
PLS-140032-C/M&E/DPE
FF 9
SECT. D
4.0
4.1
GENERAL
The contractor shall supply, install, commission and maintain for one year of
an automatic CO2 fire extinguishing agent system at locations as specified in
the drawings.
Generally, the Automatic Carbon Dioxide Extinguishing System shall consist of
but not limited to the following:
Smoke and heat detectors for detection and actuation of carbon dioxide
system.
Control panel complete with battery charger, booster charger, 24 D.C NiCd battery, alarm bell, gas discharging system, ammeter, voltmeter,
function indicators and alarm test switches, etc. The control panel must be
approved by the Jabatan Bomba dan Penyelamat Malaysia.
The extinguishing agent shall be carbon dioxide gas. The system shall be
designed for TOTAL FLOODING. The capacity of the system shall be as
specified and shown on the drawing.
4.2
OPERATION
The system shall be arranged to detect smoke and heat and actuate the
system automatically. Manual actuation through a "PULL BOX" Station and
Manual Break Glass complete with key switch shall be provided.
The heat/smoke detector shall be of the dual circuit system whereby two
numbers of neighbouring detectors have to be activated before the release of
the gas. The activation of only one detector shall raise the alarm.
The system shall conform generally to the recommendation of the National
Fire Protection Association (NFPA) - 12.
Part 3
PLS-140032-C/M&E/DPE
FF 10
4.3
LOCATION
Heat/Smoke detectors, gas cylinders shall be installed within locations
specified. The CO2 cylinders shall be completely enclosed by the provision of a
metal wire guard.
4.4
CO2 CYLINDERS
Each cylinder shall be supported in an upright position by a mild steel cylinder
support frame suitable for wall and floor mounting. The frame shall include
facilities for convenient individual servicing.
Each bank of cylinders shall be connected to a common header. Automatic
means shall be provided to prevent the loss of gas from manifold if the system
is operated when any cylinder is removed for maintenance.
Each cylinder shall be fitted with a lever valve. The valve shall incorporate in a
safety outlet being designed to burst and release the gas should the pressure
in the cylinder rise to a dangerous level.
The cylinder shall be of the rechargeable type, as constructed and tested to
conform with ASME code and to hold pressurized carbon dioxide in liquid form
at atmospheric temperature, corresponding to a nominal pressure of 850 psi
at 70oF.
The cylinder shall be fabricated to satisfy the relevant Factory and Machinery
Act, Malaysia. Certificate of fitness for such cylinder shall be presented to the
Engineer when required.
4.4.1 NOTICE
An approved notice in English DO NOT ENTER THE ROOM, WHEN CO 2
SYSTEM IS ACTIVATED shall be provided on the door of the room protected
by CO2 system. Red and green lights shall be provided at every door to
indicate the status of the equipment.
Each cylinder shall be provided with a notice containing the following
information:
4.5
DISTRIBUTION SYSTEM
4.5.1 Piping
All pipes below 20mm diameter shall be Schedule 40 and 20 mm diameter
and above shall be Schedule 80 or other materials when approved by the
manufacturer's manual and the authority having. All pipes shall be reamed
before treading. All lubricant and chips shall be removed from the inside of
pipe before assembly. All fittings shall be standard weight galvanised
Part 3
PLS-140032-C/M&E/DPE
FF 11
malleable steel. All unions shall be the ground joint type with both seating
areas matched.
The extinguishing system cylinders and valves shall not be relied upon the
support of piping. All piping shall be rigidly secured by means of 10 mm rod to
the building structure. Pipe supports shall be spaced at intervals not
exceeding 1800 mm for 6mm to 31 mm diameter pipe, 2400 mm for 40 to
75mm diameter pipe.
There shall be a support on the horizontal run with 150 mm or less of any
vertical drop. Lateral bracing shall be provided at nozzles where required to
absorb forces developed during discharge. There shall be a least 15 mm
clearance around pipe or fittings where they pierce floors or ceilings. A
one-piece escutcheon shall be provided to dress the opening.
4.5.2 Discharge Nozzles
The discharge nozzles shall consist of an orifice and any associated horn,
shield or baffle. They shall be rated for use with the expected working
pressure, be able to resist normal mechanical damage, and withstand
expected temperatures without deformation. Corrosion resistant metal shall
be used. All nozzles shall be protected with capes so as to prevent the
entrance of foreign object, such as insert. These devices shall provide an
unobstructed opening upon system operation. The discharge nozzles shall
have the discharge characteristics as listed in the N.F.P.A. No. 12.
4.5.3 Cylinder Valve
The cylinder valves shall be operated either manually by the trip mechanism
in the mount or electrically by the smoke/heat detectors. Valves may be also
arranged to fire by agent pressure from another cylinder.
The cylinder discharge valve shall be of brass with a mittered seat and steam
held closed against pressure by a mechanical quick-release can and level
system. All valves shall be suitable for the intended use, particular in regard to
flow capacity and operation shall be located so as to be safe from mechanical,
chemical or other damages and shall have a minimum bursting pressure of
6000 psi.
4.6
OPERATING DEVICES
All devices shall be designed for the service they will encounter and shall not
be readily rendered inoperative or susceptible to accidental operation.
All devices shall be located, installed or suitably protected so that they are not
subjected to mechanical, chemical or other damage, which would render them
inoperative. All manual operating devices shall be identified as to the hazard
they protect.
4.7
AUDIBLE ALARM
Continuously rated 6 inch bell audible alarms shall be installed as shown to
warn personnel within the protected area.
4.8
CONTROL PANEL
The panel shall have the following:-
Part 3
PLS-140032-C/M&E/DPE
FF 12
4.10
POWER SUPPLY
The control and indication equipment shall be adaptable or operation either on
the mains electrical supply, or storage battery exclusive for this system. The
power supply equipment shall also include battery charger, rectifier,
transformer, protective circuit fuses, ammeter, voltmeter and fault warning
devices.
The contractor shall supply, install and connect a D.C. battery supply system,
complete with all accessories for the satisfactory operation of the fire
detection system, fire alarm and detection system.
The system should preferably operate on 24V supply. The battery shall be of
the nickel cadmium type of sufficient capacity to maintain the standing loss or
losses of the system for a continuous period of at least 4 days. The battery
provided shall be able to supply the maximum alarm load at an adequate
voltage for at least one hour. The need for battery charging shall be indicated
automatically by a short flashing signal.
The battery shall be mounted in the lower compartment of the cubicle. The
charging equipment shall be mounted above the battery and readily
accessible. The charged shall incorporate dual charging, rate, one for quick
boosting and the other for trickle charge. The unit shall be completed with
output voltmeter, charging ampere meter(s), D.C. fuses, switches and relays.
Transformer shall be full wave and of the semi conductor type. Fault warning
devices shall be included to indicate any charging failure or mains failure.
Part 3
PLS-140032-C/M&E/DPE
FF 13
4.12
WIRING CABLES
All wiring to each point shall be of PVC/PVC in GI. The wiring shall be exclusive
to the fire alarm, installation and shall be completely separated from the
wiring of any other circuit.
4.13
REUSING
All parts of the extinguishing system shall be capable of being tested and
reused. The entire extinguishing system shall be capable of being refilled and
rearmed on site without disassembly or replacement of parts.
4.14
4.15
CONSTRUCTION OF CUBICLES
After fabrication the cabinet shall be treated with two coats of rust inhibiting
primer and finished with at least two coats of spray enamel of selected colour,
to be approved by the Engineer, applied and dried in accordance with the
paint manufacturer's recommendations. For outdoor installation, the cabinet
shall be splash proof type.
4.16
DESIGN OF PANEL
All equipment not required for warning or indicator shall be concealed in the
cabinet but shall be readily accessible for maintenance.
Indicators shall be of neon lamp and shall be installed in such a way that they
cannot be tempered with by unauthorised persons while at the same time,
Part 3
PLS-140032-C/M&E/DPE
FF 14
leaving them exposed to view. Indication lamps are to include two lamps in
parallel, each mounted behind a separate bezel for each indicator. The lamps
are to be mounted in such a way that they may be changed from the front of
the board.
4.17
MAINTENANCE
The complete installation is to be maintained in accordance with the following
schedule:
4.18
The type of detector proposed, the factory testing procedure and the
area of coverage as approved by the Fire Underwriters' Association.
The number of detectors offered indicating to what extent (if any) this
differs from the plans.
A complete sample detector unit together with a second cut-away
sample, or alternatively, a detailed drawing, if this is necessary to show
the detailed operation of the detector.
Details of the Main Indicator Board showing relays, testing facilities and
terminal arrangements together with details of the normal and minimum
operating voltages for the system and the method of obtaining this
voltage.
Details of the testing procedure recommended for the complete
installation together with details of how the equipment offered complies
with the testing and maintenance provisions of this specifications.
Typical wiring diagrams for the system offered.
Details of maintenance agreement. Such details are to include a
description of the service afforded, the fee charged, the currency of the
Part 3
PLS-140032-C/M&E/DPE
FF 15
agreement at this fee, the extent of service covered by the fee and
provision for renewal.
4.19
4.20
PRESSURE GAUGE
A pressure gauge shall be fitted at each CO 2 cylinder provided. The gauge
shall have marking to indicate low pressure or loss of gas.
SECT. E
5.0
Part 1 General
5.1.1 SUMMARY
This section includes Total-Flooding extinguishing systems and the following:
Extinguishing-agent containers.
Extinguishing agent.
Accessories.
Connection devices for power and integration into buildings fire alarm
system.
Part 3
PLS-140032-C/M&E/DPE
FF 16
i.
ii.
i.
ii.
iii.
5.1.3 SUBMITTALS
i.
Extinguishing-agent containers.
ii.
Extinguishing agent.
iii.
Control panels.
iv.
Detection Devices.
v.
vi.
Part 3
PLS-140032-C/M&E/DPE
FF 17
i.
ii.
iii.
Design Calculations:
For weight, volume, and
extinguishing agent required for each hazard area.
iv.
concentration
of
Part 2
Products
5.2.1 MANUFACTURERS
In other Part 2 articles were titles below introduce lists, the following
requirements apply to product selection:
Part 3
PLS-140032-C/M&E/DPE
FF 18
include, but are not limited to, Manufacturers specified in the following
paragraphs, or Approved Equal.
b. Manufacturers: Subject to compliance with requirements, provide products
by one of the manufacturers specified in the following paragraphs, or
Approved Equal.
5.2.2 EXTINGUISHING-AGENT CONTAINERS
Description:
i.
ii.
Description:
FM approved and/or NRTL listed, including equipment
and features required for testing, status supervision and operation of fire extinguishing system.
Power Requirements:
240V single-phase AC supply; with electrical
contacts for connection to system components and fire alarm system, and
transformer or rectifier as needed to produce power at voltage required
for accessories and alarm devices.
i.
Mounting: Surface.
Supervised Circuits:
area.
i.
i.
ii.
iii.
i.
Annunciator Panel:
Graphic type showing protected, hazard-area plans and locations of
detectors, abort, EPO, and manual stations. Include lamps to indicate
Part 3
PLS-140032-C/M&E/DPE
FF 19
Standby Power:
ii.
2.5
DETECTION DEVICES
A.
Description: Comply with NFPA 2010, NFPA 72 or AFP 1781, of the same
manufacture as those in the building and include the following
type:
2.6
1.
2.
3.
B.
Manual Release:
and
high.
discharge
that
remains
ALARM DEVICES
A.
Description:
B.
Bells:
C.
Horns:
D.
Part 3
PLS-140032-C/M&E/DPE
FF 20
2.8
Part 3 Execution
3.1
EXAMINATION
A.
3.2
3.3
3.4
B.
C.
D.
The units are linked together for activation via parallel wiring in loops.
Each unit shall be wired through junction box.
E.
CONNECTIONS
A.
B.
C.
LABELLING
A.
B.
Install signs at entry doors for protected areas to warn occupants that
they are entering a room protected with fire extinguishing system.
C.
Install signs at entry doors to advise persons outside the room the
meaning of the horn(s) , bell(s), and strobe light(s) outside the
protected space.
Part 3
PLS-140032-C/M&E/DPE
FF 21
3.5
B.
C.
D.
Part 3
PLS-140032-C/M&E/DPE
FF 22
GENERAL
The Fire Indicating Panel shall be type approved by Jabatan Bomba Dan
Penyelamat, Malaysia and certified by approving authority (e.g. SIRIM) to BS
5839 Part 4: 1988 and to be located at the position as indicated on the
drawings. The panel shall have the most up to date design and can
accommodate a wide variety of detectors, sounding devices with line
supervised outputs provided for zone and bell circuits. The design shall be
modular. The panel shall be mounted at eye level and of console type to the
approval of the Engineer and shall include the following equipment.1.1)
1.2)
Zone indicating units with the following lamp indicators:Red to signal a fire in the zone
Amber to indicate a fault
Green to indicate normal
Each zone indicating unit shall be self-contained incorporating a
tamper-proof, key-operated rotary selector switch with provisions for
testing circuit fault and alarm condition and also for circuit isolation.
1.3)
1.4)
1.5)
1.6)
1.7)
1.8)
Key operated switches for isolation of 24 volts D.C. fire alarm signal
risers. Keys shall be withdrawable only at "ON" position.
1.9)
1.10)
1.11)
1.12)
FF 23
All lamp indicators shall be neon lamps and duplicated for zone indication,
arranged for easy replacement from the front.
The casing for the indicating panel shall be dustproof console type fabricated
from 16 swg sheet steel with hinged lockable door upon which are mounted
the indicator lamps and all other external control.
All metal work shall be treated against corrosion, painted with primer,
undercoat and furnished outside with light grey synthetic enamels all as
specified elsewhere in these Specifications.
Wiring shall be neatly bundled and secured by means of self-locking nylon
cable ties. Cable terminations involving different voltages shall be properly
segregated and labelled to the approval of the Engineer.
A suitable perspex with colour reversed engraved diagram showing in reduced
scale the areas covered by the fire alarm system, escape corridors, staircase,
heat/smoke detectors, manual call points, zone delineations etc., shall be
provided and mounted on this panel.
2.
3.
Wiring System
All wiring shall be enclosed in conduit run in the following manner:3.1)
3.2)
Part 3
PLS-140032-C/M&E/DPE
FF 24
Fire alarm circuits shall be separated from other circuit runs and
conduit/trunking for fire alarm system shall not in any circumstances contain
wiring other than that associated with the fire alarm system. Wiring shall be
multi-strand of sizes to suit the system but shall not be less than 1.5 Sq. min
section, of tinned high conductivity copper wire insulated with 250/440 volt
grade fire resistance.
4.
5.
4.1)
4.2)
Visual indication of the activated fire zone on the central fire display
and control panel.
Part 3
PLS-140032-C/M&E/DPE
FF 25
undercoat
(b)
(c)
All screw heads, wing nuts and other means of fixing shall be painted
at the time of installation and refinished after the final testing and
commissioning is completed.
(d)
All cut ends of galvanised steel or sheet metal works shall be prepared
as mentioned above and painted 2 coats of zinc chromate paint.
(e)
(f)
All items that are considered liable to oil or grease splashes shall be
finished painted using 2 coats of appropriate oil proof paint.
FF 26
2.
Labelling
Lettering on piping shall be painted in contrasting colours and shall be in
centre of bands. The lettering shall be in block letters with minimum
dimension of in. high for pipes 2 ins. and under and 1 ins. High for pipes
over 2 ins.
Directional arrows shall be in black on two visible sides of all pipings at each
valve, firings and long runs at 6 ft. centres. The size of arrow shall be 3 ins.
long on pipes up to and including 2 ins. diameter and 6 ins. long on pipes over
2 ins. diameter.
Part 3
PLS-140032-C/M&E/DPE
FF 27
General
All necessary balancing, testing, calibrating and setting of the equipment and
controls associated with this installation shall be done and all instruments and
labour necessary for this shall be supplied by this Contractor.
The Sub-Contractor shall provide all notices and pay all fees in connection
with all necessary tests to be carried out to the approval of the Jabatan Bomba
Dan Penyelamat, Malaysia and any Authority having jurisdiction over the
installation.
If tests are not specified in any clause of the Specification such tests shall be
carried out when the Consulting Engineer may deem necessary without any
extra charge.
All tests shall be done in the presence of and certified by the Engineer.
Completion Certificates including a brief description of the test method and
instrumentation used shall be submitted to the Consulting Engineer.
Only competent and experienced personnel shall be employed to carry out all
the tests.
The cost for these tests including electricity and necessary instruments and
labour shall be included and at all times the testing instruments and
accessories shall remain the property of the Owner. These apparatus shall be
handed over to the Owner in good condition at the expiry of the Defects
Liability Period.
2.
Part 3
PLS-140032-C/M&E/DPE
FF 28
SECTION I MAINTENANCE
1.
Contract Maintenance
The Contractor shall guarantee against fault, or defects, all materials and work
as set out in this Specification from the date of issue of the Certificate of
Practical Completion. The Contractor shall at his own expense pay for spare
parts and other items necessary for the operation of the pumps.
Contract maintenance shall consist of servicing of equipment installed
including attention to emergency call for the warranty period before release of
final retention sum.
The Engineer may issue the Certificate of Practical Completion at his
discretion provided that:(a) All required testing has been completed and approved by the Consulting
Engineer and Jabatan Bomba Dan Penyelamat, Malaysia.
(b) All adjustment to equipment, which may be necessary to ensure
satisfactory operation, has been made.
(c) All operation instruction, wiring diagrams and layouts have been
received.
(d) A Maintenance Schedule setting out the proposed program of
maintenance inspection and servicing, together with advice of
arrangements of prompt attention to emergency call has been submitted
to and approved by the Engineer.
At the beginning of the Maintenance Period the Contractor shall provide a
logbook, which shall be lodged with a person nominated by the Engineer. The
log book shall remain at the site and shall be used to accurately record all
service calls, whether emergency or routine, setting out the work performed,
the date, the duration of each visit, the repairs or adjustments made. All
entries to the logbook shall be handed over to the Inspecting Engineer on
completion of the Maintenance Period.
At the conclusion of the Maintenance Period a complete check over and if
necessary a re-adjustment of the installed equipment shall be made in the
presence of the Engineer.
During the Maintenance Period, the Contractor shall train maintenance
personnel nominated by the Owner in all aspects of operation and
maintenance of the whole installation.
2.
Service Contract
The Owner shall have the option to enter into an annual service Contract,
after the Contractor has fulfilled the Contract Maintenance and guarantee
obligations. The service Contract shall include emergency service and regular
maintenance. The cost of spare parts shall be charged to the Owner.
Part 3
PLS-140032-C/M&E/DPE
FF 29
General
The following items of equipment shall be provided at the completion of the
installation. The equipment and spares shall include:(a)
1 no. spare smoke detector for each different type of detector used.
(b)
1 no. spare heat detector for each different type of detector used.
(c)
2 nos. key for each different padlock used. Each key shall be provided
with a tag with identification clearly written.
(d)
(e)
(f)
(g)
Part 3
PLS-140032-C/M&E/DPE
FF 30