a) 610 mm
b) 460 mm
c) 920 mm
d) 760 mm
e) 1070 mm
2. What is the minimum crossing or parallel clearance between direct buried
cables or conduits and underground piping?
a) 600 mm
b) 300 mm
c) 100 mm
d) 500 mm
e) 1000 mm
3. What is the minimum dept of direct buried Grounding conductor?
a) 600 mm
b) 460 mm
c) 100 mm
d) 500 mm
e) 1000 mm
4. Grounding Rods have the following characteristics:
a) Be copper or copper jacketed steel or aluminium
b) If aluminium, only be used in areas protected by cathodic protection
c) Have a minimum length of 2 meters.
d) For copper or copper jacketed steel rods diameter shall be minimum 16
mm.
e) Only tin coated.
5. In which article of NEC you can find grounding?
a) 250
b) 300
c) 350
d) 400
e) 500
6. The minimum size of grounding cable for grids or interconnection to
ground rods shall be?
a) 25 mm
b) 50 mm
c) 95 mm
d) 70 mm
e) 120 mm
7. Two holes compression terminal connector shall be used for the cable size
__and larger.
a) 4/0
b) 3/0
c) 2/0
d) 1/0
e) 2 AWG
8. For a single grounding rod resistance to ground should be less than ___.
a) 25
b) 10
c) 5
d) 1
e) 15
9. Grounding resistance for substation grid should be less than ___.
a) 25
b) 10
c) 5
d) 1
e) 15
10. Low voltage power system at Saudi Aramco shall be.....
a) Low resistance grounded
b) Solidly grounded
e) Non-hazardous
20. A cad welded connection to a grounding grid can only be used....
a) Above ground
b) Under ground
c) Not allowed
d) Both a and b above
e) None of the above
21. Which of the following statements are true in Saudi Aramco installations
a) Conduit fittings for rigid steel conduit, outdoor may be of aluminium or
steel
b) Direct buried conduit fittings may be field PVC coated to reduce cost
c) Direct buried cables and conduits shall be installed in not more than two
layers
d) Conduit fittings for rigid steel conduit above grade, outdoor, shall be of
cast or forged steel, cast iron or malleable iron
e) None of the above
22. The maximum number of over current devices permitted in a panel board
is...
a) 12
b) 45
c) 42
d) 52
e) 32
23. Explosion proof boxes are...
a) Not required in class 1, Div 1 if the boxes do not contain arcing devices
b) Required in class 1, Div 2 if the boxes contain arcing devices
c) Not required in class 1, Div 1 if seals are provided
d) Not required in class 1, Div 1 if it is made of stainless steel
e) None of the above
24. Rigid PVC conduit is prohibited to be run above ground in all Saudi
Aramco facilities except......
c) NEMA FG 1
d) NEMA TC 6 & 8
e) All of the above
33. Installation of cable tray shall comply with ____
a) NEMA VE 1
b) NEMA VE 2
c) NEMA FG 1
d) NEMA TC 6 & 8
e) All of the above
34. Flanged type covers shall be secured with stainless steel banding, one
band per m of cover length, with a minimum of ____ bands per cover.
a) 1
b) 6
c) 4
d) 5
e) 8
35. The interrupting rating of Circuit Breaker shall not be:
a) Less than half the maximum fault current the CB will be required to
interrupt
b) Less than twice the maximum fault current the CB will be required to
interrupt
c) Less than the maximum fault current the CB will be required to interrupt
d) Less than thrice the maximum fault current the CB will be required to
interrupt
e) None of the above
36. Insulation resistance of MCB pole to pole, line to load, and pole to ground
shall not be less than ______ when test voltage 1000 volts DC is applied.
a) 50 mega-ohms.
b) 100 mega-ohms.
c) 200 mega-ohms.
d) 150 mega-ohms.
e) 500 mega-ohms.
37. Storage batteries used as a source of power for emergency systems shall
be suitable to supply and maintain the total load for a minimum period of:
a) 90 min.
b) 80 min.
c) 120 min.
d) 60 min.
e) 180 min.
38. Storage batteries used as a source of power for emergency systems shall
be suitable to supply and maintain the total load for a minimum period of:
a) 90 min.
b) 80 min.
c) 120 min.
d) 60 min.
e) 180 min.
39. Impressed current systems are not used for:
a) Camel crossing.
b) Buried pipelines.
c) Offshore structures.
d) Well casing.
e) All of the above.
40. The process of supplying an enclosure with a protective gas at a
sufficient flow and positive pressure to reduce the concentration of any
flammable gas or vapour initially present to an acceptable level is known as:
a) Dust-Ignition proof.
b) Combustible gas detection system.
c) Purging and pressurizing.
d) Dust-tight.
e) None of the above.