Académique Documents
Professionnel Documents
Culture Documents
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
2 OF 9
TABLE OF CONTENT
No.
Descriptions
Page
1.
GENERAL
2.
PILING WORKS
3.
4.
1. GENERAL
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
3 OF 9
1.1 Scope
This procedure covers the basic requirement of the piling work of PC
Spun piles and the method for driving vertical concrete pile either
precast pre-stressed or precast reinforced concrete
1.2 Applicable Code and Standard
The following codes and standard shall be used together with
technical specification :
ACI MCP 4-1980
ASTM D 1143-87
AWS D1.1-86
Welding
Practice
and
Qualifications
of
Fabricator and Erectors of Welded Construction
2. PILING WORKS
2.1 General
Description of Pile, PC spun piles used for this project.
2.2 Material
2.2.1 The piles shall be either precast pre-stressed or precast
reinforced concrete piles of approved design.
2.2.2 The concrete shall conform to the grade C-70 using type II
cement.
2.2.3 In case of precast concrete piles the prestressing cables shall
conform to AASHTO
2.2.4 The piles shall have a standard arrangement for splicing either
at one end or in case of sections other than end sections at
both ends. When such a splicing arrangement is made of
structural steel the structural steel & welding shall conform to
the AWS D1.1 .
2.2.5 The piles shall be straight, free from any surface defects such
as cracks, fissures, exposed loose aggregate or any other
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
4 OF 9
L/4
L/2
L
L/4
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
5 OF 9
1/3 L
2/3 L
Driving Rig
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
6 OF 9
Auto Level
Measuring Tape.
Service Crane.
Trailer Truck.
Supporting Equipment :
1
WxH
x
FS S (0.5 xK )
where :
Ra
FS
= Safety Factor
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
7 OF 9
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
8 OF 9
2.9.12
Piles shall be driven to a specified 'set' (final set is less
than 5 cm per 3 x 10 blows), total blows per 0.5 m not exceed
500, total blows for total length not exceed 1800 or to a
length as specified on the design drawings provided by Client /
Engineer. The pile should be driven up to the pile driving
elevation as specified on the drawings. All such levels shall be
checked and approved by the Engineer.
2.9.13
If a pile is cracked, broken, or otherwise damaged or
driven out of plumb or designed angel, extra pile(s) shall be
driven as directed by the Client representatives at the Subcontractors own expense.
2.9.14
Welding of pile joint shall be inspected and rectified by
Engineer before epoxy and driving into appropriate depth or
set.
2.9.15
After a pile group is driven the contractor shall clear all his
equipment, material, wood scantlings or any other debris from
the pile group location.
2.9.16
The contractor shall carry out a pile load test either static
or dynamic 3 % from total pile driven.
3. MEASUREMENT AND RECORD
The following shall be measured and reported for every pile at the
designed driving length or near to it.
3.1 Rebound.
3.2 Final set.
3.3 Penetration with relevant information as follows but not limited to :
3.3.1 Identification number of pile (as shown in piling plan).
3.3.2 Type and length of pile.
3.3.3 Type of hammer.
DOCUMENT NO:
P-T3113-QC-CW-003
DATE :
PAGE
UNIT ISSUING :
REVISI
9 OF 9