Académique Documents
Professionnel Documents
Culture Documents
July 2014
page 357
Post-installed rebar
page 358
July 2014
Post-installed rebar
Contents
1.
334
1.1
Definition of rebar
334
1.2
334
1.3
Application examples
335
1.4
337
1.5
338
1.6
339
2.
340
2.1
340
2.2
341
2.3
342
342
343
3.
344
4.
358
July 2014
page 359
Basics of post-installed
rebar connections
anchor situation
This section of the Fastening Technology Manual deals with reinforcement connections designed according to structural
reinforced concrete design principles. The task of structural rebars is to take tensile loads and since concrete failure is always
brittle, reinforced concrete design assumes that concrete has no tensile strength. Therefore structural rebars can end / be
anchored in only two situations:
- the bar is not needed anymore (the anchorage is a node in equilibrium without tensile stress in concrete)
- another bar takes over the tensile load (overlap splice)
Situations where the concrete needs to take up tensile load from the anchorage or where rebars are designed to carry shear
loads should be considered as rebar used as anchors and designed according to anchor design principles as given e.g. in the
guidelines of EOTA [3]
Unlike in anchor applications, reinforcement design is normally done for yielding of the steel in order to obtain ductile behaviour
of the structure with a good serviceability. The deformations are rather small in correlation to the loads and the crack width
limitation is around wk ~0.3mm. This is an important factor when considering resistance to the environment, mainly corrosion of
the reinforcement.
In case of correct design and installation the structure can be assumed as monolithic which allows us to look at the situation as
if the concrete was poured in one. Due to the allowed high loads the required embedment depth can be up to 80d (diameter of
rebar).
page 360
July 2014
Basics of post-installed
rebar connections
Slab connections
Misplaced bars
Vertical/horizontal connections
July 2014
page 361
Basics of post-installed
rebar connections
Joint strengthening
Cantilevers/balconies
Structural upgrade
Slab strengthening
Sidewalk upgrade
page 362
July 2014
Basics of post-installed
rebar connections
Overlap splices
In case that the equilibrium of a node cannot be established
without using the tensile capacity of the concrete, the tensile force
of a (ending) bar must be transmitted to other reinforcement bars.
A common example is starter bars for columns or walls. Due to
practical reasons foundations are often built with rebars much
shorter than the final column height, sticking out of the concrete.
The column reinforcement will later be spliced with these. The
resulting tension load in the column reinforcement due to bending
on the column will be transferred into the starter bars through an
overlap splice.
Forces are transmitted from one bar to another by lapping the bars. The detailing of laps between bars shall be such that:
the transmission of the forces from one bar to the next is assured
spalling of the concrete in the neighbourhood of the joints does not occur
large cracks which affect the performance of the structure do not develop
July 2014
page 363
Basics of post-installed
rebar connections
Splitting failure
Bond splitting failure is decisive if the radial cracks propagate through the
entire cover. In that case the maximum bond stress follows from the maximum
concrete confinement, which is reached when the radial cracks have penetrated
the cover for about 70%. Further crack propagation results in a decrease of the
confining stresses. At reaching the outer surface these stresses are strongly
reduced, which results in a sudden drop of the bond stress.
Splitting
page 364
Basics of post-installed
rebar connections
3. Wet concrete
5. Freeze-thaw conditions
6. Installation directions
- If the bond strength obtained in tests does not fulfil the specified requirements, then bond strengths lower than those
given by Eurocode 2 shall be applied. These values are given in the respective ETA.
- If it cannot be shown that the bond strength of rebars post-installed with a selected product and cast-in rebars in cracked
concrete (w=0.3mm) is similar, then the minimum anchorage length lb,min and the minimum overlap length l0,min shall be
increased by a factor 1.5.
July 2014
page 365
Design of post-installed
reinforcement
Crack limitation
Joint to be
roughened
Fsl =
My
z
N x Vz cot
+
2
2
Truss model in modern codes
page 366
July 2014
Design of post-installed
reinforcement
All other applications lead to tensile stress in the concrete. Therefore, the principle works like cast-in would not be true any
more. Such cases must be considered with specific models exceeding the approval based approach to post-installed rebar
connections
July 2014
page 367
Design of post-installed
reinforcement
(1)
This function is adapted and extended for post-installed reinforcement for the HIT-Rebar design concept: Eurocode 2 limits the
2 value to 2 0.7. This can be interpreted as follows: as long as 2 exceeds 0.7, spalling of the concrete cover or splitting
between bars will be the controlling mode of failure. If 2 is less than 0.7, corresponding to cover dimensions of cd / > 3, the
cover is large enough so that splitting cannot occur any more and pullout will control. Assuming an infinitely strong adhesive,
there would be no such lower limit on 2 and the bond stress, at which splitting occurs can be expressed as:
For cover dimensions exceeding the range of Eurocode 2, i.e. for cd / > 3 (bonded-in bars only), an adapted factor 2 is used
to create a linear extension of the bond strength function:
where is a factor defining the growth of the linear function for fbd,spl,2; it is calibrated on the basis of tests.
In order to avoid unreasonably low values of 2, its value is limited to 2 0.25
page 368
July 2014
Design of post-installed
reinforcement
Lsy.tb =
0.5k1 k3 fsy db
k2 fc
29k1 db
where,
K1 =1.3 for a horizontal bar with more than 300mm of concrete cast below the bar;
or
= 1.0 otherwise
K2 = (132 db) / 100, and
K3 = 1.0 - 0.15 x (cd db) / db (within the limits 0.7 k3 1.0)
K3 =
1
cd 3db
1
+
0.7
db
is the reduction factor for splitting with large concrete cover Hilti additional data, based on further testing.
The confinement Cd is defined as:
s/2
s
cd min {c; 2}
July 2014
page 369
Benefits
Static mixer
h
igh loading capacity
odourless epoxy
rebar
Concrete
Fire
rated
European
Technical
Approval
DIBt
approval
Drinking
water
approved
Corrosion
tested
PROFIS
rebar design
software
SAFEset
approved
automatic
cleaning
Approvals / certificates
Description
Authority / Laboratory
DIBt, Berlin
ETA-08/0105 / 2008-07-30
DIBt, Berlin
ETA-04/0027 / 2009-05-20
DIBt approval
DIBt, Berlin
Z-21.8-1790 / 2009-03-16
IBMB Braunschweig
3357/0550-5 / 2002-07-30
Warringtonfire
WF 166402 / 2007-10-26
page 370
July 2014
Setting details
For detailed information on installation see instruction for use given with the package of the product.
Temperature of the
base material
5 C TBM < 10 C
2h
18 h
72 h
10 C TBM < 15 C
90 min
12 h
48 h
15 C TBM < 20 C
30 min
9h
24 h
20 C TBM < 25 C
20 min
6h
12 h
25 C TBM < 30 C
20 min
5h
12 h
30 C TBM < 40 C
12 min
4h
8h
TBM = 40 C
12 min
4h
4h
For dry concrete curing times may be reduced according to the following table. For installation temperatures below +5 C all
load values have to be reduced according to the load reduction factors given below.
Temperature of the
base material
TBM = -5 C
4h
36 h
72 h
0,6
TBM = 0 C
3h
25 h
50 h
0,7
TBM = 5 C
2h
18 h
36 h
July 2014
TBM = 10 C
2h
12 h
24 h
TBM = 15 C
1h
9h
18 h
TBM = 20 C
30 min
6h
12 h
TBM = 30 C
20 min
4h
8h
TBM = 40 C
12 min
2h
4h
page 371
Setting instructions
Bore hole drilling
a) Hilti hollow drill bit (for dry and wet concrete only)
Drill hole to the required embedment depth with an appropriately sized Hilti
TE-CD or TE-YD hollow drill bit with Hilti vacuum attachment. This drilling
system removes the dust and cleans the bore hole while drillin when used in
accordance with the users manual.
After drilling is complete, proceed to the injection preparation step in the
instructions for use.
b) Hammer drilling (dry or wet concrete and installation in flooded holes (no sea water))
Drill Hole to the required embedment depth with a hammer drill set in
rotation-hammer mode using an appropriately sized carbide drill bit.
Bore hole cleaning Just before setting an anchor, the bore hole must be free of dust and debris.
a) Manual Cleaning (MC) for bore hole diameters d0 20mm and bore hole depth h0 20d or h0 250 mm (d = diameter of element)
The Hilti manual pump may be used for blowing out bore holes up to
diameters d0 20 mm and embedment depths up to hef 10d.
Blow out at least 4 times from the back of the bore hole until return air
stream is free of noticeable dust
Brush 4 times with the specified brush size (brush bore hole ) by inserting the
steel brush Hilti HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if not the
brush is too small and must be replaced with the proper brush diameter.
Blow out again with manual pump at least 4 times until return air stream is
free of noticeable dust.
b) Compressed air cleaning (CAC) for all bore hole diameters d0 and all bore hole depth h0
Blow 2 times from the back of the hole (if needed with nozzle extension) over the
hole length with oil-free compressed air (min. 6 bar at 6 m/h) until return air stream is
free of noticeable dust. Bore hole diameter 32 mm the compressor must supply a
minimum air flow of 140 m/hour.
Brush 2 times with the specified brush size by inserting the steel brush Hilti HIT-RB to
the back of the hole (if needed with extension) in a twisting motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if not the
brush is too small and must be replaced with the proper brush diameter.
Blow again with compressed air 2 times until return air stream is
free of noticeable dust.
page 372
July 2014
Setting instructions
Bore hole cleaning Just before setting an anchor, the bore hole must be free of dust and debris.
c) Cleaning for under water for all bore hole diameters d0 and all bore hole depth h0
Flush 2 times the hole by inserting a water hose (water-line pressure) to the back of
the hole until water runs clear.
Brush 2 times with the specified brush size (brush bore hole ) by inserting the
steel brush Hilti HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if not the
brush is too small and must be replaced with the proper brush diameter.
Flush the hole again 2 times by inserting a water hose (water-line pressure) to the
back of the hole until water runs clear.
d) Cleaning of hammer drilled flooded holes and diamond cored holes for all bore hole diameters d0 and all bore hole depth h0
Flush 2 times the hole by inserting a water hose (water-line pressure) to the back of
the hole until water runs clear.
Brush 2 times with the specified brush size (brush bore hole ) by inserting the
steel brush Hilti HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if not the
brush is too small and must be replaced with the proper brush diameter.
Flush 2 times the hole by inserting a water hose (water-line pressure) to the back of
the hole until water runs clear.
Blow 2 times from the back of the hole (if needed with nozzle extension) over the hole
length with oil-free compressed air (min. 6 bar at 6 m3/h) until return air stream is free
of noticeable dust and water
Bore hole diameter 32 mm the compressor must supply a minimum air flow of
140 m/hour.
Brush 2 times with the specified brush size (brush bore hole ) by inserting the
steel brush Hilti HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if not the
brush is too small and must be replaced with the proper brush diameter.
Blow again with compressed air 2 times until return air stream is
free of noticeable dust.
July 2014
page 373
Setting instructions
Injection preparation
Tightly attach new Hilti mixing nozzle HIT-RE-M to foil pack manifold (snug
fit). Do not modify the mixing nozzle. Observe the instruction for use of the
dispenser. Check foil pack holder for proper function. Do not use damaged
foil packs / holders. Swing foil pack holder with foil pack into HIT dispenser.
The foil pack opens automatically as dispensing is initiated. Discard initial adhesive.
Depending on the size of the foil pack an initial amount of adhesive has to be
discarded.
Discard quantities are:
3 strokes for 330 ml foil pack,
4 strokes for 500 ml foil pack
65 ml for 1400 ml foil pack
Inject adhesive from the back of the borehole without forming air voids
Inject the adhesive starting at the back of the hole, slowly withdrawing the
mixer with each trigger pull. Fill holes approximately 2/3 full. It is required that the
annular gap between the anchor and the concrete is completely filled with adhesive
along the embedment length.
Overhead installation and/or installation with embedment depth hef > 250mm.
For overhead installation the injection is only possible with the aid
of extensions and piston plugs. Assemble HIT-RE-M mixer, extension(s)
and appropriately sized piston plug HIT-SZ. Insert piston plug to back of the hole
and inject adhesive. During injection the piston plug will be naturally
extruded out of the bore hole by the adhesive pressure.
Under water application: fill bore hole completely with mortar
page 374
July 2014
resistant
+
Alkaline products
Non resistant
Benzyl alcohol
Ethanol
Ethyl acetate
Solvents
Trichlor ethylene
Xylol (mixture)
Concrete plasticizer
Engine oil
Diesel
Petrol
+
+
Sslt water
De-mineralised water
Electrical Conductivity
HIT-RE 500 in the hardened state does not conduct electrically. Its electric resistivity is 661012 .m
(DIN IEC 93 12.93). It is adapted well to realize electrically insulating anchorings (ex: railway applications,
subway).
Drilling diameters
Drill bit diameters d0 [mm]
Rebar (mm)
a)
Diamond coring
Compressed air
drill (CA)
Wet (DD)
Dry (PCC)
10
14 (12 )
14 (12 )
12
16 (14 )
17
16 (14 )
16
20
20
20
20
25
26
25
24
32
32
32
35
28
35
35
35
35
32
40
40
40
47
36
45
45
47
47
40
55
57
52
52
a
a
a
a
July 2014
814
375
09page
/ 2012
N10
N12
N16
N20
N24
N28
N32
N36
N40
79
113
201
314
452
616
804
1018
1257
40
57
101
157
226
308
402
509
629
6.24
5.76
f*bd,po (MPa)
Required Length based on
ETA Bond (mm) Lsb
8.57
149
8.0
176
251
7.43
312
404
471
538
721
869
919
1200
1.20
191
227
384
525
741
*Design bond strength in N/mm according to ETA 04/0027 fbd,po = Rk/Mp), then increased by 20% for dry concrete.
Valid for temperature range : 40C / 24C
**For wet diamond coring, the anchors shall not be installed in flooded hole.
20
25
32
40
50
1.02
1.048
1.07
1.09
The final required length Lsb,f shall be equal: Lsb,f = Lsb / fB,p
page 376
July 2014
Step 2: Calculate of the basic anchorage depth Lsy, tb (mm) to develop yield of
post-installed rebar in tension as per AS 3600-2009. Extension Approach
With the Reduction factor for splitting with large concrete cover / confinement: = 0.306 (HILTI additional data), applicable for
both HILTI products HIT-RE 500 and HIT-HY 200, K3 shall be calculated from:
K3 =
1
0.25 for Cd > 3db
1 + Cd - 3db
0.7
nndbnnnn
The basic anchorage depth Lsy,tb can therefore be taken from the following tables:
Lsy,tb for diameter of rebar = 10mm
Confinement cd
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
389
348
308
275
246
3.db
321
287
254
227
203
4.db
264
236
209
187
167
5.db
225
201
178
159
142
6.db
195
175
154
139
137
7.db
173
155
142
8.db
155
146
9.db
149
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
475
425
376
336
301
3.db
391
350
309
277
247
4.db
322
288
255
228
204
5.db
274
245
217
194
173
6.db
238
213
188
164
161
7.db
211
188
168
8.db
189
173
9.db
176
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
July 2014
655
586
518
463
415
3.db
540
483
427
382
341
4.db
445
398
351
314
281
5.db
378
338
299
267
239
6.db
329
294
260
235
230
7.db
291
260
240
8.db
261
246
9.db
251
page 377
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
849
759
671
600
537
3.db
699
625
552
494
442
4.db
575
515
455
407
364
5.db
489
438
387
346
309
6.db
425
380
336
301
286
7.db
376
337
298
292
8.db
337
306
9.db
312
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1056
944
835
747
668
3.db
870
778
687
615
550
4.db
716
641
566
506
453
5.db
609
545
481
430
385
6.db
529
474
419
378
371
7.db
468
419
385
8.db
420
396
9.db
404
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1279
1144
1011
905
809
3.db
1054
942
833
745
666
4.db
868
776
686
614
549
5.db
738
660
583
522
466
6.db
641
574
507
454
432
7.db
567
507
449
440
8.db
509
462
9.db
471
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1521
1360
1202
1075
962
3.db
1252
1120
990
885
792
4.db
1031
922
815
729
652
5.db
877
784
693
620
554
6.db
762
682
603
539
494
7.db
674
603
533
503
8.db
605
541
513
9.db
548
527
10.db
538
page 378
July 2014
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1782
1594
1409
1260
1127
3.db
1467
1313
1160
1038
928
4.db
1209
1081
955
855
764
5.db
1027
919
812
726
661
6.db
893
799
706
674
7.db
790
707
688
8.db
721
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
2066
1848
1633
1461
1307
3.db
1701
1522
1345
1203
1076
4.db
1401
1253
1108
991
886
5.db
1191
1065
942
842
797
6.db
1036
926
829
812
7.db
916
852
8.db
869
Step 3: Determine the basic anchorage depth Lsy (mm) to develop yield of post-installed
rebar shall be:
Lsy { Lsb,f ; Lsy,tb }
July 2014
page 379
inst
Maximum force in rebar in conjunction with HIT-RE 500 as a function of embedment depth for the fire
resistance classes F30 to F180 (yield strength fyk = 500 N/mm) according EC2a).
Bar
Drill hole
Max. Fs,T
[mm]
[mm]
[kN]
10
16,19
10
12
14
16
10 / 2011
page 380
12
16
18
20
25,29
36,42
49.58
64,75
inst
[mm]
80
95
115
150
180
205
220
265
100
120
140
165
195
220
235
280
120
150
180
210
235
250
295
140
170
195
225
250
265
310
160
190
210
240
265
280
325
R30
2.4
3.9
7.3
16.2
R60
1.0
1.7
3.1
8.2
16.2
R90
0.5
0.3
1.7
4.6
10.0
16.2
R120
0.3
0.6
1.1
3.1
6.7
12.4
16.2
5.7
10.7
17.6
25.3
2.5
4.4
7.8
15.1
25.3
1.3
2.5
4.4
8.5
17.6
25.3
0.8
1.7
3.0
5.8
12.2
20.7
25.3
12.8
25.2
36.4
5.3
12.2
24.3
36.2
3.0
6.9
15.0
27.4
36.4
2.0
4.7
10.1
20.6
31.0
36.4
24.6
39.1
49.6
10.9
23.5
35.6
49.6
6.1
13.5
24.7
39.2
49.6
4.2
9.2
17.1
31.3
43.4
49.6
39.2
55.8
64.8
21.3
37.9
49.0
64.8
11.9
25.5
36.5
53.1
64.8
8.1
17.3
27.5
44.1
57.9
64.8
R180
0
0.1
0.4
1.4
2.9
5.1
7.0
16.2
0.2
0.7
1.3
2.6
5.1
8.7
11.8
25.3
0.8
2.1
4.4
8.5
14.2
19.1
36.4
1.9
4.1
7.2
13.5
22.3
29.5
49.6
3.6
7.3
11.3
20.9
33.7
42.0
64.8
60
July 2014
Bar
Drill hole
Max. Fs,T
[mm]
[mm]
[kN]
20
25
101,18
25
28
32
40
a)
30
35
40
47
158,09
198.3
259,02
404,71
inst
[mm]
200
240
270
295
310
355
250
275
305
330
345
390
280
295
330
350
370
410
320
325
360
380
395
440
400
415
440
455
500
R30
76,6
101,2
R60
54,3
82,0
101,2
R90
38,7
66,4
87,1
101,2
R120
27,5
55,1
75,9
93,2
101,2
139,0
158,1
111,1
132,7
158,1
91,6
113,2
139,1
158,1
77,6
99,2
125,1
146,7
158,1
184,7
198,3
153,4
168,0
198,3
131,6
146,1
180,0
198,3
115,9
130,4
164,3
183,6
198,3
255,3
259,0
219,6
225,1
259,0
194,7
200,2
238,9
259,0
176,7
182,2
220,9
243,1
259,0
404,7
385,1
404,7
353,9
374,6
404,7
331,5
352,2
386,8
404,7
R180
11,4
26,1
45,6
62,9
73,2
101,2
39,9
61,3
87,2
108,8
121,8
158,1
73,5
88,0
121,9
141,2
160,6
198,3
128,2
133,8
172,5
194,6
211,2
259,0
270,9
291,6
326,2
346,9
404,7
For tables according the standards to DIN 1045-1988, NF-ENV 1991-2-2(EC2), sterreichische Norm B 47002000, British-, Singapore- and Australian Standards see Warringtonfire report WF 166402 or/and IBMB
Braunschweig report No 3357/0550-5.
July 2014
page 381
T,
depending on actual clear concrete cover for classifying the fire resistance.
It must be verified that the actual force in the bar during a fire, Fs,T , can be taken up by the bar connection of the
selected length,
Fs, T
inst
cf)
inst.
where: (
inst
cf)
s;
= lap length
s,
Critical temperature-dependent bond stress, c, concerning overlap joint for Hilti HIT-RE 500 injection
adhesive in relation to fire resistance class and required minimum concrete coverage c.
Clear concrete cover c
Max. bond stress, c [N/mm]
[mm]
R30
R60
R90
R120
R180
30
0,7
0
35
0,8
0,4
40
0,9
0,5
0
0
45
1,0
0,5
50
1,2
0,6
55
1,4
0,7
0,5
0
60
1,6
0,8
0,5
65
1,9
0,9
0,6
0,4
70
1,0
0,7
0,5
75
1,2
0,7
0,5
80
1,4
0,8
0,6
85
1,5
0,9
0,7
90
1,7
1,1
0,8
0,5
95
2,0
1,2
0,9
0,5
100
1,4
1,0
0,6
105
1,6
1,1
0,6
110
1,7
1,2
0,7
115
2,0
1,4
0,7
120
1,6
0,8
2,2
125
1,7
0,9
130
2,0
1,0
135
1,1
2,2
140
1,2
145
1,3
2,2
150
1,4
155
1,6
2,2
160
1,7
165
1,9
170
2,1
175
2,2
page 382
09 / 2012
July 2014
819
July 2014
page 383
Benefits
Static mixer
rebar
Concrete
Fire
rated
European
Technical
Approval
Corrosion
tested
PROFIS
rebar design
software
H
Y 200-R version is formulated for
best handling and cure time
specifically for rebar applications Suitable for concrete C 12/15 to C
50/60
S
uitable for dry and water
saturated concrete
F
or rebar diameters up to 32 mm
N
on corrosive to rebar elements
G
ood load capacity at elevated
temperatures
S
uitable for embedment length up
to 1000 mm
S
uitable for applications down to
-10 C
SAFEset
approved
automatic
cleaning
Approvals / certificates
Description
European technical approval
Fire test report
page 384
a)
Authority / Laboratory
DIBt, Berlin
ETA-12/0083 / 2013-06-26
(HIT-HY 200-R)
ETA-11/0492 / 2013-06-26
(HIT-HY 200-A)
CSTB, Paris
26033756
July 2014
Setting details
For detailed information on installation see instruction for use given with the package of the product.
July 2014
HIT-HY 200-R
Working time twork
-10 C to -5 C
3 hour
20 hour
-4 C to 0 C
2 hour
7 hour
1 C to 5 C
1 hour
3 hour
6 C to 10 C
40 min
2 hour
11 C to 20 C
15 min
1 hour
21 C to 30 C
9 min
1 hour
31 C to 40 C
6 min
1 hour
page 385
Drill hole to the required embedment depth with an appropriately sized Hilti
TE-CD or TE-YD hollow drill bit with Hilti vacuum attachment. This drilling
method properly cleans the borehole and removes dust while drilling.
After drilling is complete, proceed to the injection preparation step in the
instructions for use.
Drill hole to the required embedment depth using a hammer-drill with
carbide drill bit set in rotation hammer mode, a Hilti hollow drill bit or a
compressed air drill.
Bore hole cleaning Just before setting an anchor, the bore hole must be free of dust and debris by one of two
cleaning methods described below
b) Compressed air cleaning (CAC)
For all bore hole diameters d0 and all bore hole depth h0
Blowing 2 times from the back of the hole with oil-free compressed air
(min. 6 bar at 100 litres per minute (LPM)) until return air stream is free of
noticeable dust. Bore hole diameter 32 mm the compressor must supply
a minimum air flow of 140 m/hour.
If required use additional accessories and extensions for air nozzle and
brush to reach back of hole.
Brushing 2 times with the specified brush size (brush borehole ) by
inserting the round steel brush to the back of the hole in a twisting motion.
The brush shall produce natural resistance as it enters the anchor hole. If
this is not the case, please use a new brush or a brush with a larger
diameter.
Blowing 2 times again with compressed air until return air stream is free of
noticeable dust.
page 386
July 2014
4 strokes with Hilti blow-out pump from the back of the hole until return air
stream is free of noticeable dust.
Injection preparation
July 2014
page 387
Hilti
HIT-HY 200
post-installed
rebars
post-installed rebars
Inject adhesive from the back of the borehole without forming air voids
HDM 330
HDM 500
HDE 500-A22
Before use, verify that the element is dry and free of oil and other
contaminants.
Mark and set element to the required embedment depth until working time
twork has elapsed.
After installing the rebar the annular gap must be completely filled with
mortar.
Proper installation can be verified when:
Desired anchoring embedment is reached v:
Embedment mark at concrete surface.
Excess mortar flows out of the borehole after the rebar has been fully
inserted until the embedment mark.
Overhead application: Support the rebar and secure it from falling till
mortar started to harden.
Observe the working time twork, which varies according to temperature of
base material. Minor adjustments to the rebar position may be performed
during the working time. After tcure preparation work may continue.
For detailed information on installation see instruction for use given with the package of the product.
page 388
826
July 2014
09 / 2012
Resistance
Chemical
Resistance
Gasoline
Glycole
Acetone
Ammonia 5%
Benzyl alcohol
Maschinery oil
Methylethylketon
Concrete plasticizer
Sea water
Demineralized water
Sewage sludge
Diesel fuel
Sodium hypochlorite 2%
Ethanol 96%
Ethylacetate
Toluene
Formwork oil
Xylene
Air
+
resistant
o
resistant in short term (max. 48h) contact
not resistant
Electrical Conductivity
HIT-HY 200 in the hardened state is not conductive electrically. Its electric resistivity is 15,5 109 cm
(DIN IEC 93 12.93). It is adapted well to realize electrically insulating anchorings (ex: railway applications,
subway).
July 2014
09 / 2012
page 389
827
Drilling diameters
Drill bit diameters d0 [mm]
Rebar (mm)
a)
10
14 (12 )
12
16 (14a)
17
16
20
20
20
25
26
24
32
32
28
35
35
32
40
40
temperature range
N10
N12
N16
N20
N24
N28
N32
79
113
201
314
452
616
804
40
57
101
157
226
308
402
312
375
438
500
f*bd,po (MPa)
Required Length based on
ETABond (mm) Lsb
8.0
159
189
251
20
25
32
40
50
1.02
1.048
1.07
1.09
The final required length Lsb,f shall be equal: Lsb,f = Lsb / fB,p
page 390
July 2014
Step 2: Calculate of the basic anchorage depth Lsy, tb (mm) to develop yield of
post-installed rebar in tension as per AS 3600-2009. Extension Approach
With the Reduction factor for splitting with large concrete cover / confinement: = 0.306 (HILTI additional data), applicable for
both HILTI products HIT-RE 500 and HIT-HY 200, K3 shall be calculated from:
K3 =
1
0.25 for Cd > 3db
1 + Cd - 3db
0.7
nndbnnnn
The basic anchorage depth Lsy,tb can therefore be taken from the following tables:
Lsy,tb for diameter of rebar = 10mm
Confinement cd
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
389
348
308
275
246
3.db
321
287
254
227
203
4.db
264
236
209
187
167
5.db
225
201
178
159
146
6.db
195
175
152
149
7.db
173
156
8.db
159
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
475
425
376
336
301
3.db
391
350
309
277
247
4.db
322
288
255
228
204
5.db
274
245
217
194
173
6.db
238
213
189
177
7.db
211
185
180
8.db
189
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
655
586
518
463
415
3.db
540
483
427
382
341
4.db
445
398
351
314
281
5.db
378
338
299
267
239
6.db
329
294
260
235
230
7.db
291
260
240
8.db
261
246
9.db
251
July 2014
page 391
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
849
759
671
600
537
3.db
699
625
552
494
442
4.db
575
515
455
407
364
5.db
489
438
387
346
309
6.db
425
380
336
301
286
7.db
376
337
298
292
8.db
337
306
9.db
312
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1056
944
835
747
668
3.db
870
778
687
615
550
4.db
716
641
566
506
453
5.db
609
545
481
430
385
6.db
529
474
419
374
344
7.db
468
419
370
350
8.db
420
375
358
9.db
381
368
10.db
375
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1279
1144
1011
905
809
3.db
1054
942
833
745
666
4.db
868
776
686
614
549
5.db
738
660
583
522
466
6.db
641
574
507
454
402
7.db
567
507
449
409
8.db
509
455
418
9.db
461
429
10.db
438
fc,cy = 20MPa
fc,cy = 25MPa
fc,cy = 32MPa
fc,cy = 40MPa
fc,cy = 50MPa
2.db
1521
1360
1202
1075
962
3.db
1252
1120
990
885
792
4.db
1031
922
815
729
652
5.db
877
784
693
620
554
6.db
762
682
603
539
482
7.db
674
603
533
477
459
8.db
605
541
477
467
9.db
548
490
10.db
500
page 392
July 2014
Step 3: Determine the basic anchorage depth Lsy (mm) to develop yield of post-installed
rebar shall be:
Lsy { Lsb,f ; Lsy,tb }
July 2014
page 393
Post-installed rebar
Detection
Drilling
Cleaning
Hilti HIT Profi Rebar sets keep all the required cleaning
accessories conveniently at hand.
Cutting
Setting
page 394
July 2014