Code No: R05410504

R05

Set No. 2

1. What are constraints how they are affecting the work flows?

[16]

[16]

ld
.

2. What constitutes a good software cost estimate?

in

IV B.Tech I Semester Examinations,December 2011


SOFTWARE PROJECT MANAGEMENT
Common to Information Technology, Computer Science And Engineering
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????

3. (a) Define WBS. Describe conventional WBS issues.

(b) What are default agendas for the life-cycle architecture milestone? Explain.
[16]

or

4. Are peer reviews secondary or primary Justify?

[16]

5. (a) Discuss team management in detail.

(b) Define micro process. Discuss about tools.

6. Describe the artifacts captured in the management set.

[8+8]
[16]

uW

7. (a) What were the core metrics collected by CCPDS-R? What is the purpose of
each metric?
(b) How were they analyzed?

[8+8]

8. (a) Explain MTBF and modularity.

(b) Briefly discuss about metrics automation.

Aj

nt

?????

[6+10]

Code No: R05410504

R05

Set No. 4

1. Are peer reviews secondary or primary Justify?

in

IV B.Tech I Semester Examinations,December 2011


SOFTWARE PROJECT MANAGEMENT
Common to Information Technology, Computer Science And Engineering
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
[16]

ld
.

2. (a) Define WBS. Describe conventional WBS issues.

(b) What are default agendas for the life-cycle architecture milestone? Explain.
[16]
3. (a) Explain MTBF and modularity.
(b) Briefly discuss about metrics automation.

or

4. What constitutes a good software cost estimate?

5. What are constraints how they are affecting the work flows?

[6+10]

[16]

[16]

6. (a) Discuss team management in detail.

uW

(b) Define micro process. Discuss about tools.

7. Describe the artifacts captured in the management set.

[8+8]
[16]

8. (a) What were the core metrics collected by CCPDS-R? What is the purpose of
each metric?
(b) How were they analyzed?

Aj

nt

?????

[8+8]

Code No: R05410504

R05

Set No. 1

in

IV B.Tech I Semester Examinations,December 2011


SOFTWARE PROJECT MANAGEMENT
Common to Information Technology, Computer Science And Engineering
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
1. (a) Explain MTBF and modularity.

[6+10]

ld
.

(b) Briefly discuss about metrics automation.

2. (a) What were the core metrics collected by CCPDS-R? What is the purpose of
each metric?
(b) How were they analyzed?

[8+8]

[16]

4. Are peer reviews secondary or primary Justify?

[16]

or

3. Describe the artifacts captured in the management set.

5. (a) Discuss team management in detail.

(b) Define micro process. Discuss about tools.

[8+8]

uW

6. (a) Define WBS. Describe conventional WBS issues.

(b) What are default agendas for the life-cycle architecture milestone? Explain.
[16]
7. What constitutes a good software cost estimate?
8. What are constraints how they are affecting the work flows?

Aj

nt

?????

[16]
[16]

Code No: R05410504

R05

Set No. 3

1. Are peer reviews secondary or primary Justify?

in

IV B.Tech I Semester Examinations,December 2011


SOFTWARE PROJECT MANAGEMENT
Common to Information Technology, Computer Science And Engineering
Time: 3 hours
Max Marks: 80
Answer any FIVE Questions
All Questions carry equal marks
?????
[16]

[16]

ld
.

2. Describe the artifacts captured in the management set.


3. (a) Define WBS. Describe conventional WBS issues.

(b) What are default agendas for the life-cycle architecture milestone? Explain.
[16]

or

4. What constitutes a good software cost estimate?

[16]

5. (a) Explain MTBF and modularity.

(b) Briefly discuss about metrics automation.

[6+10]

uW

6. (a) What were the core metrics collected by CCPDS-R? What is the purpose of
each metric?
(b) How were they analyzed?

7. What are constraints how they are affecting the work flows?

[8+8]
[16]

8. (a) Discuss team management in detail.

(b) Define micro process. Discuss about tools.

Aj

nt

?????

[8+8]