Vous êtes sur la page 1sur 7

CRANE LIFT STUDY CHECK

LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER

Page 1 of
7

PROJECT TITLE
SITE MANAGER
DATE

PROPOSED WORK METHODOLOGY


WORK PARTY
LOCATION
DESCRIPTION
REVIEW

OF

PROPOSED PROCEDURES & EQUIPMENT

MANDATORY REQUIREMENTS
HAZARD
Unidentified Job
Specific
Hazards

CONTROL MEASURE
JHA to be carried out by staff detailing on the day
hazards that could not be practically assessed prior to
attending site in addition to this CHECK LIST. All staff
to sign on to JHA accepting this form and the on the day
hazards and controls. JHA has been completed and
approved by the relevant personnel in accordance with
the JHA Procedure

Hydro HazardsLack of
awareness of
local asset and
other
simultaneous
operations
Unlisted
Specific Lift
Hazards

Works Manager to notify work party of ALL Hydro


Tasmania Assets in area (including Protection PLC,
Mechanical, Electrical and Civil Assets). Work party to
inspect and make safe

CHECKED

No crane works are to take place until the lift study has
been completed in full
Riding load or hook is prohibited
Load never lifted over workers or plant

Unknown Crane
Type
Unknown Crane
Owner
Unknown
Capacity
Unknown Crane
Driver /
Operator
Unknown
Rigger(s)

Ticket No
Ticket No(s)

DOCUMENT REFERENCE: CL
07 02

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Unknown
Designed Lifting
Points

Page 2 of
7

PROJECT TITLE
SITE MANAGER
DATE

Ensure design drawings and or Maintenance Manuals


are available that designate / specify correct and
certified lifting points and their designed lifting capacity

GENERAL REQUIREMENTS
HAZARD
Unacceptable
lifting
Equipment
and
arrangement

Incorrect
operation of
Crane
Unsuitable
Crane Position

Unsuitable
Crane
Condition
Unsuitable
Landing Area

Soft or
Unsuitable
Ground

Overhead
Hazards
Faulty
Communicatio
ns

CONTROL MEASURE
Weight of Load to be lifted
(see page
4)
Weight of Lifting Equipment
(see page
4)
Total Weight
(see page
4)
Load Slinging Arrangement Agreed
Slinging Points Assessed as Suitable
The Need for Load Control Assessed
Review daily crane operational check list
Control and slinging / rigging by certified
rigger / dogman
Radius from Centre of Crane to Centre of
Load
From Crane Chart - Capacity of Crane as per
Radius
Location of crane confirmed

N/A

CHECKED

Crane Operating Correctly (Limits, Faults,


Remotes, Speed, Brakes etc)
Area Clear for Lift and no Obstructions in Lift
Path
Landing Floor Clear & Prepared
Floor Loading Confirmed Acceptable
Ground condition checked and suitable
Location of underground services checked
and marked
Stable operating surface and levelling blocks
Area checked for powerlines and other
obstructions and adequate clearance
available
Communication system checked and
operational

DOCUMENT REFERENCE: CL
07 02

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER

Page 3 of
7

PROJECT TITLE
SITE MANAGER
DATE

GENERAL REQUIREMENTS
HAZARD
Fences or
Buildings in
Close
Proximity
High Winds,
Snow,
Electrical
Storms Etc
Unsuitable
Lifting Gear
Selection
Unauthorised
Access

CONTROL MEASURE

N/A

CHECKED

Working Radius established and marked

Weather conditions checked and favourable


Lifting Gear adequate, inspected & tagged,
certified with SWL, suitable for task, checked
and in good condition. E.g. Shackles, Strops,
Slings, Chains, Lifting / Spreader Beams etc
Restrict Access to work area. Signs /
barricades
Warning siren

Falls From
Heights
Lack of Coordination

SLING
PLANT ID
NUMBER

Provision of fixed access scaffold


Elevated work platform or similar
Safety Harness and Lanyard
Works Manager to supervise or delegate
responsibility
Works Manager to notify Production manager
of date and time of lifts
Works Manager to notify Generation
Operations of date and time of lifts
Contractor to have direct communication
with Works Manager

S.W.L

DOCUMENT REFERENCE: CL
07 02

WITHIN
CURRENT
CERTIFICATIO

VISUALLY
INSPECTED

N/A

CHECKED

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER

Page 4 of
7

PROJECT TITLE
SITE MANAGER
DATE

DESCRIPTION
Does the task require the use of multiple cranes

NO

YES

Location on Site of Lift


Date of Lift
Person Supervising the Lift
Position
CRANE

AND

PERSONNEL DETAILS

CRANE 1
Crane Type
Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)

Ticket No(s)
Ticket No(s)
CRANE 2

Crane Type
Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)

Ticket No(s)
Ticket No(s)
CRANE 3

Crane Type
DOCUMENT REFERENCE: CL
07 02

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER

PROJECT TITLE
SITE MANAGER
DATE

Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)

CRANE
NUMBER
CRANE 1
CRANE 2
CRANE 3

ESTIMATED
SHARE OF
LOAD
(%)

Page 5 of
7

Ticket No(s)
Ticket No(s)
RADIUS FROM
CRANE TO
LOAD
(M)

CAPACITY OF
CRANE FROM
CHARTS
(T)

ADJUSTED
CAPACITY
(SEE NOTE)
(T)

ESTIMATE
LOAD FOR
EACH CRANE
(T )

TOTAL
CAPACITY
NOTE: For Multiple crane lifts, it is a statutory requirement that the capacity
of each crane at the require boom or jib length be as follows.

For Two Cranes: 20 percent in excess of calculated load share

For Three Cranes: 33 percent in excess of calculated load share


SKETCH

OF

LIFT

DOCUMENT REFERENCE: CL
07 02

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER

Page 6 of
7

PROJECT TITLE
SITE MANAGER
DATE

SITE REGISTRATION (Note: Applies to all Work Parties and personnel working
on site)
REQUIREMENT
CHECKED
Permit To Work issued
Visitors register sheet or emergency board being used. Site Map
issued (showing emergency assembly areas and fire equipment)
Hydro Tasmania Level 2 O H & S Induction complete
Hydro Tasmania Level 3 Site induction complete
S

ADDITIONAL PERSONAL PROTECTIVE EQUIPMENT (COMPLIANT WITH AUSTRALIAN


STANDARDS)
CHECKE
REQUIREMENT
REQUIREMENT
CHECKED
REQUIREMENT
CHECKED
D

CERTIFICATION
I have personally checked and verified all items on all pages of this check list
Works Manager Name
Signature
Date
I acknowledge and agree that all items are detailed on all pages of this check list. I
agree to ensure that all employees and sub-contractors engaged in this work will
fully comply with all control measures indicated
DOCUMENT REFERENCE: CL
07 02

REVISION: 4

HYDRO-285-68

DATE: 19/06/2012

CRANE LIFT STUDY CHECK


LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Manager of Work Party
Name

DAILY REVIEW
IF THERE IS A SIGNFICANT
REQUIRED
DATE AND TIME

DOCUMENT REFERENCE: CL
07 02

Page 7 of
7

PROJECT TITLE
SITE MANAGER
DATE
Signature

CHANGE IN

WORK

Date

AND OR

REVIEWED / COMMENT

REVISION: 4

CONDITIONS

A NEW

CHECK LIST

IS

NEW CHECK LIST REQUIRED

HYDRO-285-68

DATE: 19/06/2012

Vous aimerez peut-être aussi