Improvements and
Redevelopment Program
Presentation Outline
Opening Remarks
MAINTENANCE PROGRAMS
Reserve Maintenance
(Annual/Ongoing)
Terminal Optimization
Program
Central Terminal
Redevelopment Program
(Including
Predecessor/Enabling
Projects)
CAPITAL PROGRAMS
TOP Phase 1
Central Terminal
Redevelopment
Includes Concourse E
Renovations & Central Terminal
Baggage System Automation
TOP Phase 2
Includes Central Base and South Terminal Hardstand Expansion
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2030
TOP Phase 1
Central Terminal
Redevelopment
Includes Concourse E
Renovations & Central Terminal
Baggage System Automation
TOP Phase 2
Includes Central Base and South Terminal Hardstand Expansion
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2030
Implementation Readiness
Identifying and removing utility system dependencies to the North and South Terminals
from the Central Terminal Area
Operational Readiness
MIAs growth has significantly increased gate utilization and gate demand
Sufficient capacity to accommodate traffic demand must be ensured before beginning a
construction program that reduces gate capacity during construction
Financial Considerations
Adequate traffic capacity during construction will ensure that revenues continue to be
robust
Enabling projects that facilitate robust revenues will positively influence capital markets
10
11
Central Base
Hardstand Expansion
South Terminal
Hardstand Expansion
Central Terminal South (New
Concourse G, Terminal and
Apron)
Predecessor projects to the Central Terminal Redevelopment Program, including D West and D East extensions, need to be completed prior to the
commencement of the Program.
12
13
TOP Phase 1
Central Terminal
Redevelopment
Includes Concourse E
Renovations & Central Terminal
Baggage System Automation
TOP Phase 2
Includes Central Base and South Terminal Hardstand Expansion
2015
14
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2030
KEY GOALS
Implement projects
that enable the
long-term plan
15
Ensure improvements
optimize benefits given
the investment
Reassess value-added
(i.e., solution to
problems or needs)
projects that reduce
existing/increasing
maintenance
16
TOP Phase 1
TOP Phase 2
$1.2 Billion
(Both Phases)
GSE
Storage
Area
17
Phase 2
Thru 2018
Thru 2025
Ticket Counters Replacement
Concourse E Program
Terminal Landside
Improvements (D to F)
18
PHASE 1
Design and construction of a
new two-train self propelled
APM system to replace the
aging and damaged existing
APM system for the
continued operation of E
Satellite International Gates.
19
Lower E Renovations
PHASE 1
Design and construction of
renovations to Lower Concourse
E including lighting, flooring,
and finishes.
Construction
99% Complete
20
Lower E Renovations
21
Satellite E Renovations
PHASE 1
Construction
Completion
September 2017
22
Concourse E to F Connector
PHASE 2
Design and construction of a post-security passenger connector bridge between
Concourses E and F to improve and expedite passenger connectivity
beyond the security checkpoints.
23
Programming
Design FY 2019
PHASE 2
Design and construction of renovations to the Concourse E FIS.
24
Programming/Design FY 2019
Programming Complete
Working with FAA to secure funding
Design FY 2019
25
26
TOP Phase 1
Central Terminal
Redevelopment
Includes Concourse E
Renovations & Central Terminal
Baggage System Automation
TOP Phase 2
Includes Central Base and South Terminal Hardstand Expansion
2015
27
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2030
28
Elevator Modernization
Escalator Modernization
CC-F Carpet Replacement
29
the Concourse E scope of work under the Terminal Optimization Program (Phase 1) and the
FY2016 Reserve Maintenance Program
Concourse E scope of work under the Terminal Optimization Program (Phase 1) and the
FY2016 Reserve Maintenance Program
30
Predecessor/Enabling Projects/Procurement
Initial Phases of Central Terminal
Redevelopment Programming
and Design
Central Terminal
Utilities Infrastructure
Inventory and Central
Terminal
Redevelopment
Master Plan
TOP Phase 1
Central Terminal
Redevelopment
Includes Concourse E
Renovations & Central Terminal
Baggage System Automation
TOP Phase 2
Includes Central Base and South Terminal Hardstand Expansion
2015
31
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2030
Thank You
32
E-Satellite
2034
Terminal
2029
Lower E
2035
Concourse F
2036
Concourse G and Terminal
2025
Sources: MIA 2014 Aerial Photography, Miami-Dade Aviation Department, December, 2014; MIA Central Terminal Program Definition Document Analysis
(Refined with Air Carriers 11/01/2013), Ricondo & Associates, November 2013; Project Cost and Duration Estimates, URS Corp., November 2013.
33