Académique Documents
Professionnel Documents
Culture Documents
Guidance Note
FIDIC Book Claims Procedure
Summer Edition 2014
Introduction
Although the current FIDIC Books all reflect a distinct and consistent policy of encouraging the early
determination of claims, the precise actions of the Engineer (or the Employer under the Silver Book and
Gold Book) following the referral of a Contractors claim are unclear.
Korean construction and engineering contractors working outside
Korea still tend to be shy about notifying and claiming additional
time and/or money. So what we often see is the ethos of
engineering before commercial, and so the storing-up of problems
under a contractual regime that actually demands timely
notification and the real-time ventilation of claims to adjust the
Time for Completion and/or the Contract Price.
In the case of the Red Book, there are 15 such provisions see Sub-Clauses 1.9, 2.1, 4.7, 4.12, 4.24, 7.4, 8.4, 8.9, 10.2, 10.3, 13.7, 16.1, 17.4, 18.1 and 19.4. For the Yellow Book, there are 17 see
Sub-Clauses 1.9, 2.1, 4.7, 4.12, 4.24, 7.4, 8.4, 8.9, 10.2, 10.3, 12.2, 12.4, 13.7, 16.1, 17.4, 18.1 and 19.4. For the Silver Book, there are 13 see Sub-Clauses 2.1, 4.24, 7.4, 8.4, 8.9, 10.3, 12.2, 12.4, 13.7,
16.1, 17.4, 18.1 and 19.4. For the Pink Book, there are 16 - see Sub-Clauses 1.9, 2.1, 4.7, 4.12, 4.21, 4.24, 7.4, 8.4, 8.9, 10.2, 10.3, 13.7, 16.1, 17.4, 18.1 and 19.4. For the Gold Book, there are 15 - see
Sub-Clauses 1.10, 2.1, 4.7, 4.12, 4.24, 7.4, 9.3, 9.8, 10.2, 10.4, 10.7, 13.6, 13.7, 16.1 and 18.4.
The FIDIC Contracts Guide on the 1999 Conditions for Construction, Plant & DB and EPC/T
7049
Schedule 1
Sub-Clause 20.1
1. If the Contractor considers himself to be entitled to any extension of
the Time for Completion and/or any additional payment, under any
Clause of these Conditions or otherwise in connection with the
Contract, the Contractor shall give notice to the [Engineer 3/
Employer4 ], describing the event or circumstance giving rise to the
claim. The notice shall be given as soon as practicable, and not later
than 28 days after the Contractor became aware, or should have
become aware, of the event or circumstance.
2. If the Contractor fails to give notice of a claim within such period of
28 days, the Time for Completion shall not be extended, the
Contractor shall not be entitled to additional payment, and the
Employer shall be discharged from all liability in connection with
the claim. Otherwise, the following provisions of this Sub-Clause
shall apply.
3. The Contractor shall also submit any other notices which are
required by the Contract, and supporting particulars for the claim,
all as relevant to such event or circumstance.
4. The Contractor shall keep such contemporary records as may be
necessary to substantiate any claim, either on the Site or at another
location acceptable to the [Engineer/Employer]. Without admitting
the Employers liability, the [Engineer/Employer] may, after
receiving any notice under this Sub-Clause, monitor the record This applies to the Red Book and the Yellow Book.
Schedule 2
Deadline 1
As soon as reasonably practicable, and not
later than 28 days after the Contractor
became aware, or should have been aware,
of the event or circumstance (20.1, [1])
Deadline 2
42 days after the Contractor became aware
(or should have become aware) of the
event or circumstance giving rise to the
claim, or within such other period as may
be proposed by the Contractor and
approved by the Employer (20.1, [5])
Yes
Engineer requires
further particulars?
No
Deadline 3
42 days after receiving a claim or any
further particulars supporting a previous
claim, or within such other period as may
be proposed by the Employer and approved
by the Contractor (20.1, [8])
Yes
No
Yes
Deadline 4
Not unreasonably delayed (1.3)
Engineer makes a
determination and gives
notice of his determination
of the claim with supporting
particulars (3.5)
Payment process
7049
Andrew Denton
Partner
T: +44 (0)20 7418 7000
E: andrew.denton@pinsentmasons.com
Jon Howes
Partner
T: +65 (0)63 050 913
E: jon.howes@pinsentmasons.com
Mark Raymont
Partner
T: +971 (0)4 373 9630
E: mark.raymont@pinsentmasons.com
Nicholas Turner
Senior Associate
T: +852 (0)2294 3393
E: nicholas.turner@pinsentmasons.com
Mohammed Talib
Solicitor
T: +852 (0)2294 3453
E: mohammed.talib@pinsentmasons.com
This note does not constitute legal advice. Specific legal advice should be taken before
acting on any of the topics covered.
Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority and the
appropriate regulatory body in the other jurisdictions in which it operates. The word partner, used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the
LLP or any affiliated firm of equivalent standing. A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLPs registered office:
30 Crown Place, London EC2A 4ES, United Kingdom. We use Pinsent Masons to refer to Pinsent Masons LLP, its subsidiaries and any affiliates which it or its partners operate as separate
businesses for regulatory or other reasons. Reference to Pinsent Masons is to Pinsent Masons LLP and/or one or more of those subsidiaries or affiliates as the context requires.
Pinsent Masons LLP 2014.
For a full list of our locations around the globe please visit our websites:
www.Out-Law.com
7049
www.pinsentmasons.com