Onshore Pigging Facilities Upgrade Batch 1; EPC-2

PT Sarku Enjinering Utama


Contract No: CS-16509677
DAILY PROGRESS REPORT
(From 06:00 AM to 06:00PM)
Report no.
: SEU-005-DPR-1401-0200
Reported date : 12-04-2015
Issued date
: 13-04-2015
1.0
1.1.

GENERAL
Weather Update
Location
Suban #6 Well
Inlet Suban Plant
Suban #11 Well
Suban #4 Well

1.2

Time (WIB)
06.00 - 18.00
06.00 - 18.00
06.00 - 18.00
06.00 - 18.00

Weather
Cloudly
Cloudly
Cloudly
Cloudly

Remark

Permit to Work (PTW)


HOT WORK QUANTITY
NO.

ID CODE PTW NUMBER

1
2
3
4
5
6
7
8
9
10
11
12
13

C
C

1.3.

C 1411498
C 1411509
C 1411508
H 0043910
H 0043906
H 0043909
H 0043904
H 0043912
C 1411501
C 1411505
C 1411502
C 1411506
H 0043908

Rig Up / Rig Down dan Modifikasi Scaffolding di area


Pemasangan New Pipe Spool, Valve dan Support Pipa
Pemasangan New Pipe Spool, Valve dan Support Pipa
Remove Blind Flange Existing & Install New Pipe Spool
Mechanical Digging dan back fill untuk Demolish dan
Brushing, Paintiing dan Coating di Well Suban #11
Mechanical Lifting menggunakan crane 45 ton di Well
Stake out / Site Survey titik koordinat elevasi diarea well
Lean Congcrete Pondasi diarea Well Suban #6
Pemasagan dan Pembongkaran Scaffolding diarea Well
Grouting Minor Pondasi diarea Well Suban #4
Rig Up / Rig Down Scaffolding & Modifikasi Scaffolding
Pengeboran dan pemasangan anchor bolt menggunakan

COLD WORK QUANTITY

UNDER
OPEN CLOSED REVIE
W

OPEN

CLOSED

Yes
Yes
Yes

TIME
TIME
APPRO
ISSUED
VED
(WIB)
(WIB)
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30
05:30

Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes

06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30
06:30

LOCATION

REMARKS

Inlet Suban
Well Suban #11
Well Suban #4
Inlet Suban
Well Suban #6
Well Suban #11
Well Suban #6
Well Suban #6
Well Suban #6
Well Suban #6
Well Suban #6
Well Suban #4
Well Suban #6

Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
Revalidation
New

Total Number of Personnel On Board (POB)

Remarks

COPI PMT (Pax) Contractor (Pax)


8
168
2.0

UNDER
REVIE
W

WORK DESCRIPTION

Health, Safety and Environment


HSE Incident/Nearmiss Description :
HSE Significant Issue/Activity

Manhour
Sarku Previous
Manhours

Today
Sarku
Manhour
s

STOP
COPI Previous
Manhours

Today Sarku
Subcontractor

248040
84
1932
TOTAL SARKU MANHOURS
250056
TOTAL PROJECT MANHOURS

Today COPI
Manhours

14340
96
TOTAL COPI MANHOURS
14436
264492

Recordable Cases

Positive

Today

Total

Today

Total

Nearmi
ss

2045

290

FAC

MTC

RWC

LWC

FAT

TRR
0

3.0 SITE DOCUMENTATION


Site Query
NCR
Site Instruction
PTW - New
PTW - Revalidated
PTW - Hold
PTW - Closed
4.0

Prev. Today
-

Cumm.
-

353

10

12

17

17

357

359

RESOURCE - MANPOWER
JAKARTA OFFICE ( INDIRECT STAFF ) AT SITE
Mech / Piping Engineer
Material Coordinator
Project Manager
Project Planner
CRO / Customer Relation Officer

354
-

:
:
:
:
:

Sub total:
Sub total Manhours :
SITE TEAM ( INDIRECT STAFF )
Site Manager
Superintendent
Construction Supervisor
HSE Coordinator
Project Engineer
HRD Staff
QC Coordinator
Project Admin
Material Clerk
Safety Officer
HSE standby
PTW Coordinator
PLC
Construction Engineer

:
:
:
:
:
:
:
:
:
:
:
:
:
:
Sub total:
Sub total Manhours :

SITE TEAM ( SUMPAL JUNCTION )


Superintendent
Site Planner
QC Civil
QC Piping
HSE Coordinator
Material Coordinator

:
:
:
:
:
:

O/S Boundary
0
0
0
0
0

pax
pax
pax
pax
pax

0
0

pax
Mhr

O/S Boundary
0
0
0
0
0
0
0
0
0
0
0
0
0
0

pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax

0
0

pax
Mhr

O/S Boundary
0
0
0
0
0
1

pax
pax
pax
pax
pax
pax

I/S Boundary
1
pax
1
pax
0
pax
1
pax
0
pax
3
0

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

pax
Mhr

I/S Boundary
1
pax
2
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
2
pax
2
pax
3
pax
1
pax
1
pax
1
pax
19
0

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

pax
Mhr

I/S Boundary
1
pax
1
pax
1
pax
1
pax
1
pax
0
pax

Material Clerk
Safety Officer
HSE standby
PTW Coordinator
Construction Engineer
IT
Supervisor Civil
Rigger / Scaffolder Spv.
Rigger / Scaffolder
Civil Worker
Welder
Helper
Operator TMC
Helper TMC
Driver (SRB)
Mechanic
Paramedic
Pipe Fitter
Surveyor
Ast. Surveyor
E/I Tech.
CRO
Security

:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
Sub total:
Sub total Manhours :

INDIRECT WORKER
Car Driver
Car Driver (Subcontractor - SRB)
Surveyor
Assistant Surveyor
Satgas
Office Girl
Camp boy
Crane Operator
Helper Crane
Operator TMC (subcontractor)
Assistant Operator TMC (Subcontractor)
Operator Excavator (Subcontractor)
Paramedic

:
:
:
:
:
:
:
:
:
:
:
:
:

Sub total:
Sub total Manhours :
CIVIL / GROUPS
Supervisor Civil
Quality Control
Work Leader Civil
Civil Worker
Helper
Mechanic

:
:
:
:
:
:
Sub total:
Sub total Manhours :

PIPING GROUPS
Quality Control
Welder Supervisor
Welder
Blaster / Painter
Painting Inspector
Piping Supervisor
Pipe Fitter Work Leader
Pipe Fitter
Flange Management Tech.
NDT Technician
CMS
Hydrotest Tech

:
:
:
:
:
:
:
:
:
:
:
:
Sub total:
Sub total Manhours :

STRUCTURE & SCAFFOLDER GROUPS


Supervisor Rigger/Scaff.
Fitter Structure
Work leader Rigger/Scaffolder
Rigger / Scaffolder
HILTI Technician

:
:
:
:
:

Sub total:
Sub total Manhours :
ELECTRICAL / INSTRUMENT
Work Leader
Electrician
QC. Electrician
Safety Standby
Helper

:
:
:
:
:

Sub total Manhours :

COMPANY REPRESENTATIVES
Company Site Supt.
Construction Suv.
HSE Rep
Planner
QC Piping
Piping Engineer
QC Civil
QS / PIMS/ CMS
Electrical / Instrument / Control

Sub total:

pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax

0
1
0
1
1
0
1
1
4
7
0
6
1
1
2
1
1
2
1
1
1
0
5

pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax

5
0

pax
Mhr

43
0

pax
Mhr

O/S Boundary
0
0
0
0
0
0
0
0
0
0
0
0
0

pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax

0
0

pax
Mhr

O/S Boundary
0
0
0
0
17
0

pax
pax
pax
pax
pax
pax

17
0

pax
Mhr

O/S Boundary
0
0
0
0
0
0
0
0
0
0
0
0

pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax
pax

0
0

pax
Mhr

O/S Boundary
0
0
0
0
0

pax
pax
pax
pax
pax

0
0

pax
Mhr

O/S Boundary
0
0
0
0
0

pax
pax
pax
pax
pax

0
0

pax
Mhr

2
0

pax
Mhr

0
0
0
0
0
0
0
0
0

pax
pax
pax
pax
pax
pax
pax
pax
pax

Site
1
1
2
0
0
0
2
1
1

pax
pax
pax
pax
pax
pax
pax
pax
pax

0
0

pax
Mhr

8
96

pax
Mhr

O/S Boundary
0
0
0

pax
pax
pax

Shop
:
:
:
:
:
:
:
:
:
Sub total:
Sub total Manhours :

Night Shift
Project Manager
Site Manager
Superintendent

1
0
0
0
0
1
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
1
0

:
:
:

I/S Boundary
2
pax
2
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
1
pax
15
0

Working Hours
0
hrs
0
hrs
0
hrs
0
hrs
24
hrs
0
hrs
0
hrs
0
hrs
12
hrs
0
hrs
0
hrs
0
hrs
0
hrs

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

Working Hours Standby Hours


0
hrs
hrs
0
hrs
hrs
0
hrs
hrs

Reason for Standby (If any)

pax
Mhr

I/S Boundary
1
pax
0
pax
2
pax
6
pax
0
pax
9
0

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

pax
Mhr

I/S Boundary
1
pax
1
pax
3
pax
0
pax
0
pax
2
pax
1
pax
6
pax
1
pax
3
pax
1
pax
1
pax
20
0

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

pax
Mhr

I/S Boundary
1
pax
2
pax
3
pax
12
pax
16
pax
1
pax
35
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

pax
Mhr

I/S Boundary
0
pax
2
pax
0
pax
0
pax
0
pax

I/S Boundary
0
pax
0
pax
0
pax

PTW Coordinator
Foreman
Welder
Pipe Fitter
Helper
HSE
Logistic / Mecanic
Construction Engineer
Driver

:
:
:
:
:
:
:
:
Sub total:
Sub total Manhours :

5.0

146

6.0
6.1

LIGHT VEHICLES & HEAVY EQUIPMENTS


VEHICLE
REG. NO.
Ford Everest
BG 1530 PO
Ford Ranger
B 9762 SBA
Ford Ranger
B 9764 SBA
Ford Everest
BG 1012 RW
Ford Everest
BG 1318 RC
Ford Everest
BG 1134 NN
Ford Everest
BG 1132 NN
Ford Everest
BG 1822 NN
Ford Everest
BG 1749 NL
Mitsubishi Strada
BG 9542 NM
ISUZU ELF
BG 7609 AU
Ford Everest
BG 1743 NL
Ford Everest
BG 1012 RW
Total Mileage

pax
pax
pax
pax
pax
pax
pax
pax

0
0
0
0
0
0
0
0

pax
pax
pax
pax
pax
pax
pax
pax

0
0

pax
Mhr

0
0

pax
Mhr

PREV. MILEAGE
11,138 Km
25,011 Km
22,769 Km
20,483 Km
15,278 Km
5,501 Km
- Km
479 Km
14,834 Km
12,814 Km
6,044 Km
298 Km
4,260 Km
134,649 Km

CURRENT MILEAGE
- Km
172 Km
149 Km
Km
Km
Km
- Km
Km
96 Km
Km
71 Km
- Km
- Km
488 Km

0
0
0
0
0
0
0
0

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

TOTAL MILEAGE
11,138
Km
25,183
Km
22,918
Km
20,483
Km
15,278
Km
5,501
Km
Km
479
Km
14,930
Km
12,814
Km
6,115
Km
298
Km
4,260
Km
135,137
Km

Remarks
SRB - Used by SEU (Services)
Owned SEU
Owned SEU
SRB - Returned to Sarku 03 Jan '15
SRB - Returned to Sarku 31 Dec '14
Off
Off
SRB -Used by SEU
SRB - Used by SEU
SRB - Returned to Sarku 25 Jan '15
On Duty 05 February 2015
On Duty 25 February 2015
On Duty 25 February 2015-for Sumpal

SITE CONSTRUCTION NARRATIVE


TODAY ACTIVITIES
No

3
4
5
6

9
10
6.2

0
0
0
0
0
0
0
0

Description of work
Workshop Sarku - Suban
Review Fit-up visual report, Welding tracebility report, NDT Report, Dwg. IDHydrotest, Dwg. ID-N-SB-LL0-ISO-WL-3L-0059, 2"-DC-AA2-3M-2797 (
Line check / punch List Suban 4 Plant
Modification spool Suban 4 Well, Fit - Uo Visual, and NDT
Top Coat pipe spool system 3A Pipe Support PS-3M-KAA-001-008/009/011
Workshop Palembang (Precast)
Suban 6 Well
- Delivery Foundation Type 4
Sumpal Junction Receiver
- Curing time Foundation Type 4 (Pedestal)
- Curing time Foundation Type 7 (Pedestal)
Sumpal Junction Launcher
- Delivery Foundation Type 4
- Curing time Foundation Type 7 (Pedestal)
Suban Condensate
- Pouring concrete Pig Launcher Foundation (Footing)
- Pouring concrete Pig Launcher Foundation (Pedestal)
Suban #6 ROW
- Re-position for grounding rod position
Suban #4 Plant
-Remove Blind Flange Existing & Install New Pipe Spool 2", Valve dan
Suban #11 Plant
- Grouting work for Pig Receiver Foundation Suban 11 Plant
- Remove Blind Flange Existing & Install New Pipe Spool 2", Valve
Suban #4 Well
- Grouting Foundation Pig Launcher
Suban #11 Well
- Grouting Foundation Pig Launcher at suban Well #11
- Manual digging & backfill for Foundation Suban Well #11
- Install New Pipe Spool, Valve and Support Pipa at Suban Well #11
Suban #6 Well
- Compacting work pipe support foundation type all area
Hilti Foundation Pig Trap
Hilti minor Foundation
Lean concrete for minor foundation
Loading pipe spool
Condensate Plant
- Compacting work FoundationType 4
- Lean concrete FoundationType 4
Sumpal Junction
- Manual digging for Around Pig Trap Foundation

Qty

UOM

1
1
1
1
1

Lot
Lot
Lot
Lot
Lot

4
5
1

Installation progres
Cumm.
Cumm. Today
Today
(%)
Today

REMARKS

Prev
90
90
90
65
90

10
10
10
35
10

Ea

Ea
Ea

95
80

3
1

Ea
Ea

2
2

Target : 11/04/15
Target : 11/04/15
Target : 9/04/15
Target : 9/04/15
Target : 9/04/15

100
100
100
100
100

100%
100%
100%
100%
100%

50%

0
0

95
80

95%
80%

Target : 07/04/15
Target : 07/04/15

0
45

0
0

0
45

0%
45%

ETA (02-04-15)(Already Delivery from Palembang)


Target : 05/04/15

Ea
Ea

1
1

0
0

1
1

50%
50%

Target : 07/04/15
Target : 07/04/15

Lot

50

50

50%

Target : 06/04/15

Lot

75

25

100

100%

2
1

Ea
Lot

2
0

0
0

2
0

100%
0%

Target : 05/04/15
Target : 05/04/15

Ea

100%

Target : 07/04/15

6
6
4

Ea
Ea
Lot

6
5
4

0
0
0

6
5
4

100%
83%
100%

Target : 10/04/15
Target : 10/04/15
Target : 10/04/15

9
2
2
12
1

Ea
Lot
Lot
Ea
lot

0
2
0
8
0

5
0
1
2
1

5
2
1
10
1

56%
100%
50%
83%
100%

Target : 13/04/15
Target : 12/04/15
Target : 12/04/15
Target : 12/04/15
Target : 12/04/15

5
5

Ea
Ea

4
4

0
0

4
4

80%
80%

Target : 15/04/15 (1 Ea Waiting Installation Pig Launcher


Target : 15/04/15 (1 Ea Waiting Installation Pig Launcher

Ea

25%

Target: 28/03/15

Qty

UOM

1
1
1
1

Lot
Lot
Lot
Lot

Ea

5
1

Ea
Ea

75
60

3
1

Ea
Ea

0
45

2
2

Ea
Ea

Next Day Plan Activity

No

3
4

5
6
7

Description of work
Workshop Sarku - Suban
Review Fit-up visual report, Welding tracebility report, NDT Report, Dwg. IDHydrotest, Dwg. ID-N-SB-LL0-ISO-WL-3L-0059, 2"-DC-AA2-3M-2797 (
Red line mark modification steel support all drawing
Line check / punch List Suban 4 Plant
Workshop Palembang (Precast)
Suban 6 Well
- Delivery Foundation Type 4
Sumpal Junction Receiver
- Curing time foundation Type 4 (pedestal)
- Curing time Foundation Type 7
Sumpal Junction Launcher
- Delivery Foundation Type 4
- Curing time Foundation Type 7 (Pedestal)
Suban Condensate
- Pouring concrete Pig Launcher foundation (Pedestal)
- Pouring concrete Pig Launcher Foundation (Pedestal)
Suban #6 ROW
- Install grounding rod
Suban #4 Plant
- Pipe Support adjusment
- Pipe Spool Reinstatement
Suban 11 Plant
- Pipe Support adjusment
- Pipe Spool Reinstatement
Suban 4 Well
- Pipe Support adjusment
Suban 11 Well

Installation progres
Cumm.
Cumm. Today
Today
(%)
Today

REMARKS

Prev

100
100
100
90

100%
100%
100%
90%

Target : 11/04/15
Target : 11/04/15
Target : 9/04/15
Target : 9/04/15

100%

Target: 06/04/15

15
15

90
75

90%
75%

Target : 07/04/15
Target : 07/04/15

3
15

3
60

100%
60%

Target : 30/3/15
Target : 09/04/15

1
1

1
1

2
2

100%
100%

Target: 07/04/15
Target : 07/04/15

75
75
75
75

25
25
25
15

Ea

100%

Target : 06/04/15

12
2

Ea
Ea

3
20

3
10

6
30

50%
30%

Target 03/04/15
Target 03/04/15

1
2

Lot
Ea

20
20

10
10

30
30

30%
30%

Target 03/04/15
Target 03/04/15

Lot

10

10

20

20%

Target 03/04/15

9
10

- Pipe Support adjusment


- Pipe Spool Reinstatement
Suban #6 Well
- Unloading Pig Launcher and Precast foundation from WS
- Compacting work for minor foundation
- Lean concrete for minor foundation
Condensate Plant
- Waiting precast foundation delivery
Sumpal Junction
- Manual digging for Around Pig Trap Foundation

Equipment
Diesel driven generator 10 KVA, HARTECH
Welding Machine Miller Big Blue 600X
Cutting Wheel 14", MAKITA 2414NB
Grinding machine 7"
Grinding machine 5"
Drlling Machine
Blasting & Painting Equipment
Flange Management Equipment
Cutting torch c/w Regulator
Handwheel / Cutting
Hand Drill Machine
Hand Compactor
Theodolet
Molen - Hercules / YANMAR engine
Leveling
Manual digging hand tools
Mini Excavator
Stamper, MIKASA MT 76D
Dewatering Pump
TMC
Crane 45 Ton
Dark room (NDE Equipment)

CONCERNS / NOTES
Review ITR Suban 4 Plant and Suban 11 plant

POTENTIAL CHANGE OF WORK

No

Qty
2
7
0
0
0
0
1
1
0
0
8
2
1
2
1
1
1
2
1
1
1
1

Description Of Work

1
2

Lot
Ea

20
20

10
10

30
30

30%
30%

Target 28/03/15
Target 03/04/15

1
14
14

Lot
Ea
Ea

0
9
12

1
4
1

1
13
13

100%
93%
93%

Target : 05/04/15
Target: 12/04/15
Target: 12/04/15

Ea

50%

Target: 28/03/15

4
Unit
Unit
Unit
Ea
Unit
Unit
Unit
Unit
Unit
Set
Unit
Unit
Ea
Set
Unit
Unit
Lot
Unit
Ea
Unit
Unit
Unit
Unit

Working Hours
24
0
0
0
0
0
0
0
0
0
12
24
12
0
12
12
0
0
0
0
12
0

Man Power
Today
Mhr

Position

Standby Hours
hrs
0
hrs
hrs
84
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
0
hrs
hrs
12
hrs
hrs
12
hrs
hrs
0
hrs
hrs
0
hrs
hrs
84
hrs
hrs
0
hrs
hrs
0
hrs
hrs
24
hrs
hrs
0
hrs
hrs
0
hrs
hrs
12
hrs
hrs
24
hrs
hrs
12
hrs
hrs
12
hrs
hrs
0
hrs
hrs
12
hrs

Tool Equipment
Accum.
Descipti Today
Mhr
on
Hrs

Material
Accum.
Descript
Hrs
Qty
ion

1.
2.
10

REMARK

11

COMPANY COMMENTS

12

PROGRESS PICTURES

12.1 Hilti minor foundation at Suban #6 Well

12.2 Hilti minor foundation at Suban #6 Well

Reason / Remarks

Accum
Qty

DN No. CAR No

Status

12.3 Loading pipe spool & Valve to clear area at Suban #6 Well

12.5 Soil back filling for minor foundation at Suban #6 Well

12.4 Loading pipe spool & Valve to clear area at Suban #6 Well

12.6 Soil back filling for minor foundation at Suban #6 Well

Prepared by,
(Contractor's Site Planner)

Approved by,
(EPC Contractor Site Manager)

Arief Bagus Permadi

M. Irsyadi

Acknowledged by,
COPI Site Representative