Académique Documents
Professionnel Documents
Culture Documents
Abstract
This paper describes the development and design of a
computer controlled hybrid coiled tubing unit used for
workover, re-entries, casing exits, coiled tubing underbalanced drilling, running & cementing liners and logging &
perforating. Key components of the unit were a purpose-built
bottom hole assembly and a companion control cabin.
The primary goal was to design a unit that could drill wells
under-balanced using either jointed pipe or coiled tubing. The
units were to be modular and capable of being shipped and
either lifted onto an offshore platform or used on a land
location. Rig control was to be based on fly by wire
technology either onsite or remote and there were to be a
minimal number of lines for hook up.
Introduction
In 1994, following a comprehensive market study, Baker
Hughes INTEQ embarked on a program to build the surface
package to supplement the slim-hole drilling bottom hole
assembly (BHA) it had developed in 1991.
The coiled tubing industry had changed quite dramatically
in the mid 80s. This was the transition period when coiled
tubing became a device for carrying out other functions such
as drilling out scale and milling downhole tools that could no
longer be retrieved on wireline. Also, monitoring systems
changed from simple devices such as a Martin Decker gauge
to a multi-pen recorder or a computerized data acquisition
device with large data storage capabilities.
By the late 80s and early 90s, CT (coiled tubing)
companies had changed to larger control cabins with various
modular structure also meant that all wiring and services had
to be done independently within each module
Copernicus proved to be labor intensive for the electronic
technicians. Moreover, the multiple connectors caused some
reliability problems. Hook up and wiring of the following rigs,
the Galileo series units, were changed to overcome the
limitations experienced with the Copernicus design.
Drilling Support Structure A modular structure was
designed and constructed for the Copernicus unit to
accommodate deploying the BHA in under-balanced
conditions. The unit was to be able to handle casing, drill pipe,
tubing (up to 6 5/8) and coiled tubing (up to 3). It
combined a rig-assist snubbing unit, a coiled tubing injector
mounted below the jack and a drill floor to replace the usual
snubbing basket. The drill floor also had a fifteen-foot radius
guide arch, which guided the coiled tubing from the storage
reel into the injector, through the jack slip-bowls. The guide
arch also could be parked off well center to allow the
deployment of jointed tubulars via the gin pole.
The injector position meant the drive modules had to be a
unique design that would allow all tubulars to pass through but
it could be used as a back-up to the jack if required. The
injector drive modules could be opened to a maximum 12 ID,
which allowed the jacking unit to handle all tubular sizes up to
6-5/8 casing complete with hanger.
The BHA could be deployed in one or two pieces through
the injector head and snubbing unit into the lubricator above
the upper swab valve or safety head BOP ram. Its main
disadvantages were that the coiled tubing had to be rigged up
over the large tubing arch, above the drill floor. The tubing
arch was hydraulically operated for traversing over well
center. Vertically mounted hydraulic cylinders within the arch
provide a compensation system between the coiled tubing reel
and the injector head. This process was monitored by the
control system.
Benefits of Automation One of the driving forces behind
the degree of computer based automation on the CT drilling
rigs was the need to allow automatic control system reaction
to potential problems where there is little time for an operator
to react. There are many parameters that can provide warnings
of imminent failure or other problems.
One area where this was implemented successfully was the
injector drive hydraulic pump and motors. Charge pressure,
drive pressure, skate/chain tension pressures, setpoint versus
output and actual speed of motors versus pipe speed are all
compared and analyzed within the software, to detect possible
pump failures, motor failures, slipping pipe, operator error,
etc.
SPE 68440
SPE 68440
SPE 68440
The second rig was also a flexible, quick rig-up unit. It was
designed for land use. Although the same modular approach
and architecture was used, the control cabin design was
different. Due to space and weight requirements, the cabin was
split in two. A smaller cabin was placed on the rig floor, with
the central control and operation equipment. A second cabin
was located behind the substructure. All of the electrical
distribution, network hubs, UPS equipment and injector
control equipment were located here. The injector control
equipment was placed here because of limited space within the
injector module. The injector module was designed to travel
up and down within the mast, for jointed pipe operations.
Instrumentation was cabled back to this cabin using multi-pair
cables with Zone 1 connectors, for quick rig up. Also, the
control equipment for the mud system was within this cabin.
This allowed for some flexibility in mud system selection,
which could be rental or owned equipment. All the mud
system instrumentation was also run back to this control
equipment using multi-pairs.
The third system required a major architecture rethink.
This rig was a permanent installation on a drilling barge, no
longer requiring some of the architecture used for a quick rig
up. All PLCs were located inside the control cabin and
multipair cables were run to junction boxes on each
component. At this point, the number of PLCs could have
been reduced, as each PLC (Hydraulic Power Unit, Mud
Pumps, CT Reel, etc) were under-utilized. The decision was
made to leave the division of PLCs alone as consolidating
these into common PLCs would have required a substantial
software re-write, along with increased commissioning time.
The fourth system was a land rig designed for the Middle
East. The rig was once again a quick rig up unit. Due to the
benefits realized on the previous rig and with the centrally
located PLCs, this same architecture was selected again. Since
multiple components were trailer-mounted together, the multipair solution involved minimal effort. Zone 1-rated connectors
were used between trailers and the overall rig design and
layout was optimized to keep the connector quantity to a
minimum.
As with previous designs, the control cabin was positioned
on the rig floor. The number of controlled components
increased with this system. The Drawworks was added to the
control system. As the Drawworks shared the same hydraulic
power supply with the injector, the system was set up so that
the same control hardware (joystick, touchscreen, PLC) was
used for both components, by selecting the mode of operation
on the screen and crossing over the hydraulic connections
(Fig. 4).
There were three CT reels. Instrumentation on each reel
was identical, allowing all three reels to be controlled using
one PLC and multi-pair bundle. Two connectors and the
hydraulic hoses were changed over with each reel change.
This rig also had its own generators and switchroom. These
SPE 68440
Nomenclature
A60
ARCNET
BHA
BOP
CT
C/W
CTES
HAZOP
HMI
HUB
ID
I/O
IS
MWD
PCs
PLC
UPS
Acknowledgments
The authors are grateful to Baker Hughes INTEQ, Baker
Hughes Process and Baker Hughes Inc., for supporting the
publication of this paper. The authors also wish to thank the
staff of OPTO 22, California for allowing us to publish
information about the control system. Thanks to everyone
within Hydra Rig Inc., CTES, Zone Power and National
Oilwell, Dreco, who have all been involved in this Hybrid
Coiled Tubing unit development program. Finally, the authors
thank the staff of Baker Hughes INTEQ at all levels for the
support throughout the project. Editorial contributions of
Frank Radez, Baker Hughes Inc., are gratefully acknowledged.
References
1.
2.
Attachments
SPE 68440
CT REEL PLC
INJECTOR PLC
KEY:
HUB LINK
ETHERNET CABLING
ARCNET CABLING
DRILL BYTE
TERMINAL
ARCNET HUB 2
ARCNET HUB 1
BOP /
ACCUMULATOR
CTES /
COMMUNICATIONS
INJECTOR / REEL /
DRAWWORKS
MDS / SPARE
HPU / MUD
PUMPS
UNDERBALANCED /
MUD SYSTEM
SPE 68440
DEVELOPMENT OF COMPUTER-CONTROLLED HYBRID CT DRILLING UNITS
7
SPE 68440
SPE 68440
10
SPE 68440
Fig. 5Example OPTO 22 CYRANO flowchart, demonstrating the graphical nature of the control system programming method. The actual
attachments to the hardware are made within each bock of the chart. The logical progression can be followed online in a debugging mode
where the flow is demonstrated actively on the screen.