Académique Documents
Professionnel Documents
Culture Documents
1]INTRODUCTION
2]DAMAGES UNDER INDIAN CONTRACT ACT 1872
3]MEANING OF LIQUIDATED DAMAGES
4]PROVISIONS
INTRODUCTION
If the party before entering into the contract already decides that
if any non- performance of duty or a breach of contract occurs
between the parties, then the amount of damages that were
decided before coming to contract would be compensated by
aggrieved party. These damages are so called as Liquidated
damages or ascertained damages.
For an order of liquidated damages, the following two conditions
must be met. Firstly, the amount of the damages identified must
roughly approximate the damages likely to fall upon the party
seeking the benefit of the term. Secondly, the damages must be
relatively vague at the time the contract is made that such a
clause will likely save both parties in the future while estimating
damages.
Often the term liquidated damages is mistaken or rather
confused with the term penalty. Thus, understanding the terms,
we can clearly distinguish between the two. A penalty can be said
to be a sum so stipulated in terrorem (with the object of coercing
the party into performing the contract), and thus an amount
qualifies to be a penalty if the sum named is extravagant and
unconscionable. It is also a penalty if the breach consists in
paying of money and the sum stipulated is greater than the sum
which ought to have been paid. However, liquidated damages are
a genuine, covenanted pre-estimate of damages as seen above.
They are both to be so judged on the facts of each case.
The question whether a particular stipulation in a contract is in
the nature of the penalty has to be determined by the court
against the background of various relevant factors, such as the
character of transaction and its special nature, if any, the relative
situation of the parties, the rights and obligations accruing from
such a transaction under the law and the intention of the parties
incorporating in the contract, the particular stipulation which is
contended to be penal in nature. If on such a comprehensive
consideration, the court finds that the real purpose for which the
MEANING OF LIQUIDATED
DAMAGES
As per black law dictionary liquidated damages means, an
amount contractually stipulated as a reasonable estimation of
actual damages to be recovered by one party if the other party
breaches the contract. i.e., When the terms of a contract are
broken, if a sum is named in the contract as the amount to be
paid in case of breach, the party complaining of the breach is
entitled, whether or not actual damage or loss is proved to have
PROVISIONS
UNDER INDIAN CONTRACT ACT 1872
In India, liquidated damages are dealt under Indian Contract Act,
1872 within section 73 and section 74. Sec. 73 states that when
a contract has been broken, the aggrieved party is entitled to get
compensation or any loss or damages which has been inflicted to
him/her naturally during the usual course of breach of contract or
about which the parties to the contract has prior knowledge when
they entered the contract.
Sec 74 states When a contract has been broken, and if a sum is
named in the contract as the amount to be paid for such breach,
or if the contract contains any other stipulation by way of penalty,
the party complaining of the breach is entitled, whether or not
actual damage or loss is proved to have been caused thereby, to
receive from the party who has broken the contract reasonable
compensation not exceeding the amount so named or, as the
case may be, the penalty stipulated for.
When the provision is read it implies that in Indian laws there is
no distinguish between the liquidated damages and the penalty,
as has been done in U.K. and USA. The word penalty was
introduced in Indian Contract Act by way of amendment in 1899.
Nature of transaction,
Right sand other obligation arising from the contract and the
transaction
TEST OF DISTINGUISHING
LIQUIDATED DAMAGES
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd
This is an English contract law case, concerning the extent to
which damages may be sought for failure to perform of a contract
when a sum is fixed in a contract. It held that only if a sum is of
an unconscionable amount will it be considered penal and
unenforceable.
It should not be confused with Dunlop Pneumatic Tyre Co Ltd v
Selfridge & Co Ltd, which held that the same resale price
maintenance practice was unenforceable against a third party
reseller as a matter of the English rule of privity of contract.
FACTS
Dunlop sued its tyre retailer, New Garage, for breaching an
agreement to not resell Dunlop tyres at a price lower than that
listed in the contract. The agreement then said if that did happen,
which was used in the case of Fateh Chand, the court made
observation in relation to Sec.74 that the damages to be provided
should be based on the concept of reasonable compensation
apart from it court also stated that it is of no importance in
characterising the damage as penalty or as a requisite.
In this case the court also stated that the liquidated damages
serve the purpose of avoiding litigation which is very useful and
promotes certainty in commercial cases.
Kailash Nath Associates v. DDA
The judgement in the case of Kailash Nath Associates v. DDA[5],
new perspective of Sec.74 was discussed,where the Court
declared that under Sec.74, in case of breach of contract the
party will be entitled to damages in form of reasonable
compensation which must not exceed the sum which has been
pre-determined in the contract. The question which was
determined in this case was whether forfeiture is barred under
Sec.74, where as in the common law penalty rule is basically not
applied in the case of forfeiture. Before the amendment of 1899
all Indian cases follow the common law perspective, but the
amendment broadened the purview of Sec.74. The amendment
inserted the clause any other stipulation by way of penalty in
Sec.74, which was first addressed in the case of Fateh Chand v.
Bal Kishan Das. In the present case of Kailash Nath, the apex
court held that Sec.74 does not extend to the jurisdiction of
granting relief in cases of penalty when the provision of the
section does not apply in terms. Where in earlier cases the court
stated that Sec.74 extends to those cases where there are
unavoidable circumstances.
Conclusion
Hence, liquidated damages are easy to impose when compared
with penalty. Also penalty can be imposed on limited events like
delay in completion of the work or when there is delay in supply.
Also in Indian Contract Act, there is no specific differentiation in
REFERENCES
BOOKS REFFERED
1) AVTAR SINGH STUDY OF CONTRACT ACT AND SPECIFIC RELIEF
1872
2) R.K. BANGIA - LAW OF CONTRACTS I
OTHER SOURCES
Adjudication of claim for damages under Sec.73, 74 and 75 of
Indian Contract
Act http://www.manupatra.co.in/newsline/articles/Upload/30C28D
5D-262B-4A4A-AE17-C4D86F92BCE0.pdf
http://indiacorplaw.blogspot.in/2010/12/supreme-court-inbsnl-v-reliance.html.
http://www.lawteacher.net/free-law-essays/contractlaw/damages-under-indian-contract-act-law-essays.php
Cases Citation
[1]
[2]
[3]
[4]
[5]