Académique Documents
Professionnel Documents
Culture Documents
Sir,
Sub:- Construction of Class Room- Detailed Estimate - Technical Sanction - Rs 128.81 Lakhs - Reg.
Ref :- 1. GO Rt No. 345 dated 06-07-2012 of School Education (SE-PROG 1) Dept, Andhra Pradesh, Hyd,
2. Lr. No: AE1/SE/APEWIDC/HYD/MS-GH/WGL, Dtd 18.9.2012 of the Superintending Engineer,
APEWIDC.
*******
*******
The Principal Secratary to Government, Education(SE-PROG.I) Dept., Government of Andhra Pradesh,
Hyderabad have accorded Administrative Sanction for Construction of (355) Girls hostel Buildings in the
premises of Model Schools through G.O.Rt. No. 345, Dated 06-07-2012 with a unit cost of Rs. 1.288 Crores in
various Places in Andhra Pradesh, includingConstruction of Class Room
The Funding Pattern is : 90% of the capital cost will be borne by the Central Government and the
balance 10 % will be provided by the State Government. While planning and designing the building and other
infrastructure for the model school attached Girls hostel buildings all standard norms were adopted thous
altogether 32 rooms are to be constructed with following provisions:
Description
Living rooms with sit-out
Bath rooms with WCs
No of
Rooms
25
16
6.22
Room
Size
x
3.65
1.38
2.31
Area in
Sqm
567.58
51.00
2.38
1.51
3.59
6.10
5.08
30.99
Dining Hall
6.10
6.10
37.21
6.10
3.65
22.27
3.55
3.76
13.35
1
1
6.10
6.10
3.05
x
x
x
Generator Room
3.05
2.43
3.05
3.05
3.05
18.61
18.61
9.30
3.05
9.30
3.65
8.87
790.68
The total plinth area of the builidng including walls & circulation area is arrived as 1097.00 Sqmt
are 11803.00 Sft.
Civil works include construction of security room , Generator room, compound wall and gate, septic tank,
drinking water facilities, electrification including fixtures. This estimate is prepared adopting the type design
communicated . The total plinth area is 1117.14 Sft
Vide reference 2nd cited the Superintending Engineer has submitted the detailed estimate duly adopting
the type design.
crushed graded metal for Footings, Pedestals, Plinth beams and Columns up to plinth level.
Superstructure:
1. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed graded metal
2. Providing HYSD bars Fe 415 for all diameters more than 6mm for VRCC & RCC work.
3. Providing Mild Steel Fe 250 for 6mm bars for VRCC & RCC work.
4. P.C.C (1:3:6) prop: nominal mix for Bed Blocks and Hold Fasts.
5. RCC (1:2:4) prop. Nominal mix using 12mm HBG machine crushed graded metal for Lintels, 50mm
thick platforms.
6. RCC M 25 grade design mix ( by weigh batching), using 20mm HBG machine crushed graded metal
for sun shades, 7.5cm thick at fixed end and 5.0 cm thick at free end, of any width as per approved
plan.
7. PCC M20 grade Design Mix ( by weigh batching), using 20mm HBG machine crushed graded metal
for steps .
8. Brick masonry in CM(1:8) prop. using 2nd class traditional bricks for Superstructure.
9. Reinforced Brick masonry 115mm thick in CM(1:4) prop. using 2nd class traditional bricks for
Partition walls.
10. Plastering 12 mm thick in two coats, base coat 8mm thick in CM(1:6) and top coat 4mm thick in
11. Plastering 20 mm thick in two coats, base coat 16mm thick in CM(1:6) and top coat 4mm thick in
14. Flooring with Polished Black Kadapa slabs minimum of 15 mm thick (0.457M x 0.457M) set over a
base coat of CM (1:8), 12mm thick over already laid C.C. bed or R.C.C. roof slabs.
15. Flooring with Ceramic non-skid tiles of 7.3 mm thick 1st. quality of any shade set over a base coat of
16. Providing Skirting to internal walls to 12.5 cm height with Rough Kadapa slabs of minimum 40 mm
thick, size not less than (0.457 x 457M) slabs 15mm to 18mm thick.
17. Dadooing to walls with coloured glazed tiles 1st. quality of size not less than 300mm x 200mm.
18. Flooring with 15 to 18mm thick high polished granite stone slabs of blue colour.
19. Whiting to new walls and ceiling in two coats with Birla white or equavalent quality for internal walls.
20. Painting with Plastic emulsion grade -1 paint to exterior faces of new walls with 3 coats of approved
of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood black board type with
commercial ply on both faces of 35mm thick including all fixtures.
24. Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with Sal wood Frame
of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood black board type with
commercial ply on both faces of 35mm thick including all fixtures.
25. Supply and Fixing of Door with Double leaf shutter, Door Size 1.00x2.13 mtrs with Sal Wood Frame
of sections size 75mm x 100mm with Flush Door Shutters Solid Bond Wood black board type with
commercial ply on both faces of 35mm thick including all fixtures.
26. #REF!
27. #REF!
28. NCL or Equivalent Eco 3000 Series Windows with Galvalume Corrugated sheet with
AMENITIES:
1. The Superintending Engineer has submitted the sub-estimate for Water supply and Sanitary
Arrangements as per the requirements based on approved plan and the same may be allowed.
2. The Superintending Engineer has submitted the sub-estimate for Internal Electrification as per
the requirements based on approved plan and the same may be allowed.
The Data of all the items are adopted as per the Revised Standard Data Part-III (Buildings) and
the rates are worked out based on current SSR i.e Building SSR 2011-2012. Cement and Steel rates are
adopted as approved by the committee of the Chief Engineers for the month of August 2012.
SPECIFICATIONS:
The Standard specifications as per APSS are adopted and the work will be carried out true to the
relevant standard specification of APSS and as per the agreement conditions.
Quarries:
The Superintending Engineer has proposed 25 % on labour charges towards Municipal area allowence and
necessaey certificate is enclosed in the lead chart, hence the same may be allowed on the responsibilty of the SE,
APEWIDC Guntur
Overhead Charges & Contractors Profit:
14% towards overhead charges and contractors profit put together has been proposed by the SE
APEWIDC Guntur in the estimates which is as per the Revised Standard Data - Part-III (Buildings),
ordered by the Government of A.P vide G.O.Ms.No.49, IRRIGATION & CAD (PW-REFORMS)
DEPARTMENT Dated: 2-3-2009, for adoption by all Engineering /Public Works Departments and
other organizations. Hence the same may be allowed.
VAT:
Lump sum amounts at the rate of 5% towards VAT has been added in the Abstracts of all the estimates
by the SE APEWIDC,Guntur, which is as per the Revised Standard Data - Part-III (Buildings), and the
same will be allowed at 5% of ECV.
The SE has proposed following other provisions in the estimate
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
:
:
:
:
:
:
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
:
:
#REF!
#REF!
#REF!
#REF!
The Estimate is scrutinized and here-with put up for kind perusal and for according technical sanction for
Rs128.81 Lakhs. The Draft 'Bill of Quantites' and BID document is also here-with put for kind perusal and
approval.
AE/AEE
Dy. EE
EE
SE
CE
Estimate
Section
: Badangi
Sub-Division
: Vizianagaram
Division
: Vizianagaram
Circle
: Guntur
SPECIFICATION REPORT
Estimated cost Rs. 128.81 Lakhs.
Name of work:
Authority:
The Principal Secratary to Government, Education(SE-PROG.I) Dept., Government of
Andhra Pradesh, Hyderabad have accorded Administrative Sanction for Construction of
(355) Girls Hostels attached to Model Schools vide G.O.Rt. No. 345, Dated 06-07-2012
with a unit cost of Rs. 1.288 Crores
includingConstruction of Class Room, with a funding pattern of 90% of Central Share and
10% of State Share
While planning and designing the building and other infrastructure for the model
schools specification as stipulated by GOI, specified norms are adopted. A
Model Plan is preprared as per the scheme norms of Girls Hostel. The hostel is
proposed to accommodate 100 students in G+1 with following accommadation.
As per the Girls hostel norms, altogether, 34 rooms are to be constructed as
follows:
Living Rooms with sitout &drying space
Library cumReading room
:
:
25 nos
1 nos
Recreation room
1 nos
:
:
:
:
:
:
:
:
:
1 nos
1 no.
1 no.
1 no.
1 no.
1 no.
1 no.
16 no.
1 no.
The estimate is prepared dully adopting the type design prepared by the
APEWIDC and approved by the Govt. of India. The required accomdation is
propoaed in Ground floor and first floor
Provisions:
The Detailed Estimates are prepared with the following common provisions:
A)
Superstructure:
1. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine
crushed graded metal for Columns, Roof Beams, Roof Slabs.
2. Providing HYSD bars Fe 415 for all diameters more than 6mm for VRCC & RCC
work.
3. Providing Mild Steel Fe 250 for 6mm bars for VRCC & RCC work.
4. P.C.C (1:3:6) prop: nominal mix for Bed Blocks and Hold Fasts.
5. RCC (1:2:4) prop. Nominal mix using 12mm HBG machine crushed graded
metal for Lintels, 50mm thick platforms.
6. RCC M 25 grade design mix ( by weigh batching), using 20mm HBG machine
crushed graded metal for sun shades, 7.5cm thick at fixed end and 5.0 cm thick
at free end, of any width as per approved plan .
7. PCC M20 grade Design Mix ( by weigh batching), using 20mm HBG machine
crushed gradedmetal for steps .
8. Brick masonry
Superstructure.
in
CM(1:8)
prop.
using
2nd
class
traditional
bricks
for
28. #REF!
29. NCL or Equivalent Eco 3000 Series Windows with Galvalume Corrugated sheet
with
i) Centre fixed both side openable shutter (1500 mm x 1350mm ) (W1)
ii) Double shutter 900 mm x 1350 mm outer frame (W3).
30. Supply and fixing of MS Ventilators with sections made of MS angles of 25mm
X 25mm X 3mm and 10mm X 10mm square rods ( Sizes: 1200 mm x 450 mm
& 900 mm x 450 mm).
AMENITIES:
1) Sub-Estimate is prepared for Water supply and Sanitary Arrangements as per
the requirements based on approved plan.
2) Sub-Estimate is prepared for Internal Electrification as per the requirements
based on approved plan.
Lump sum amounts at the rate of 5% towards VAT has been added in the
Abstracts of all the estimates by the SE APEWIDC,Guntur, which is as per the
Revised Standard Data - Part-III (Buildings), and the same will be provided at
5% of ECV.
LUMP SUM PROVISIONS:
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
PRSD Kothagudem
0
0
SPECIFICATION REPORT
Specification Report accompanying the work " Special Repairs to ZPHS in Tekulapalli (V) and
Tekulapalli (M) in Khammam District " Was administratively sanctioned for Rs. 12.00Lakhs vide
proceedings RC No. 767/C4/2012 Dt: 16.04.2013 by DEO Khammam Maintenance of High schools in
Khammama District.
The estimate is prepared with following provisions
1
DISMANTLING clearing away and carefully stacking materials useful for reuse. Brick Masonary including
Cost and conveyence of all charges for clearing away the debris etc.,
DISMANTLING clearing away and carefully stacking materials useful for reuse old cement plastering
including Cost and conveyence of all charges for clearing away the debris etc.,
Reinforced Cement Concrete M25 Grade corresponding to IS 456 using 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate, water etc., complete for Lintels
Lintels
Sunshades
Roof Beams
Roof Slab 115 mm Thick
Roof Slab 100 mm Thick
Wearing Coat 50 mm Thick
5
6
7
8
9
10
Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of size 23 x 11 x 7 Cm from
approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all
materials etc., complete for finished item of work.
11
Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) dubara sponge finish including cost and conveyance of all materials , etc., for Uneven Surfaces
of Brick Wall complete for finished item of work. (APSS 901,903 & 904)
12
Plain Cement Concrete (1:5:10) proportion (cement: fine aggregate: Coarse aggregate) using 40mm size
Hard Broken Granite (IS383, 1970) machine crushed metal from approved quarry including cost and
conveyance of all materials like etc., complete for finished item of work. (APSS No. 402).
13
Flooring with Polished Black Kadapa slabs minimum of 15 mm thick (0.457M x 0.457M) set over a base
coat of CM (1:8), 12mm thick (joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof
slab only after it is properly cured, etc., complete for finished item of work.(APSS No.703 & 701)
14
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1979) of different
diameters for RCC works, including labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and size and tying and lapsplicing with
binding wire of 18 SWG, etc., complete for finished item of work in all floors. (APSS No.126)
15
17
#REF!
#REF!
#REF!
18
#REF!
16
Asst. Engineer
TW/ Gundala
Executive Engineer
TW/ Division/Bhadrachalam
Asst. Engineer
TW/ Gundala
Executive Engineer
TW/ Division/Bhadrachalam
Description
Amount
Ground Floor
5,159,285
Terrace Floor
400,000
3
4
5
Total
5,559,285
Total
170,000
350,000
6,079,285
303,964
10
11
12
13
14
15
60,793
16
13,819
55,593
303,964
1,045,135
70,000
500,000
20,000
5,000
8,457,553
GOVERNMENT OF TELANGANA
PANCHAYAT RAJ ENGINEERING DEPARTMENT
Khammam
Khammam
Kothagudem
Kothagudem
Kothagudem
Estimate Cost
Rs. 10.00
SOR
2015-16
Page 17
Lakhs
Name of the Work : Construction of Building to English Medium School in Patha Kothagudem in
Kothagudem Mandal in Khammam District
GENERAL ABSTRACT
Sl. No.
1
Description of item
Amount( in Rs )
630799.00
315234.00
18921.00
18921.00
Total
4730.00
1935.00
946033.00
47302.00
Grand Total Rs
Assistant Engineer
PR Kothagudem
Page 18
1,000,000.00
Executive Engineer
PRI Division Kothagudem
Page 19
Item of work
2
No
3
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 x 23
2.00
2.00
2.05
188.60
Verandah columns
Long walls
1 x 9
1.40
1.40
1.65
29.11
1 x 3
31.37
0.45
0.45
19.06
Crosswalls
1 x 5
7.28
0.45
0.45
7.37
1 x 5
2.00
0.45
0.45
2.03
246.17 266.15 cum
65518.00
1 x 23
2.00
2.00
0.10
Verandah columns
1 x 9
1.40
1.40
0.10
9.20
1.76
10.96 1026.70 cum
11253.00
1 x 23
1 x 9
1 x 3
2.00
1.40
31.37
2.00
1.40
0.45
0.15
0.15
0.15
13.80
2.65
6.35
Crosswalls
Verandah cross walls
1 x 5
1 x 5
7.28
2.00
0.45
0.45
0.15
0.15
2.46
0.68
25.94 3740.10 cum
Page 20
97018.00
S.NO
Item of work
No
Measurement
B
D
5
6
4
Footings
Room columns
Verandah columns
1 23
1 9
Quantity
Rate
per
Amount
10
1.80
1.20
1.8
1.2
0.500
0.400
37.26
5.18
42.44 8739.25 cum
370894.00
Pedestals
Room columns
1 23
0.60
0.75
0.600
6.21
Verandah columns
1 9
0.60
0.6
0.450
1.46
7.67 9158.75 cum
70248.00
Columns
Upto GL
Room columns
1 23
0.23
0.3
0.400
0.63
Verandah columns
1 9
0.23
0.23
0.100
0.05
1 23
0.23
0.3
2.100
3.33
Verandah columns
1 9
0.23
0.23
2.100
1.00
1 23
0.23
0.3
1.200
1.90
Verandah columns
1 9
0.23
0.23
0.900
0.43
7.34
Page 21
### cum
79645.00
S.NO
Item of work
1
c
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Plinth Beam
Long walls
1 x 3
31.15
0.23
0.30
6.45
Crosswalls
Verandah cross walls
1 x 5
1 x 5
7.50
2.00
0.23
0.23
0.30
0.30
2.59
0.69
9.73
1 x 3
31.15
0.23
0.30
6.45
1 x 5
2.30
0.23
0.30
0.79
7.240
Over Doors
1.50
0.23
0.15
0.207
Over Windows W1
1.80
0.23
0.15
0.745
75014.00
### cum
10563.00
885.95 Sqm
27296.00
Verandah sunshade
1 32.35
Verandah sunshade
1.80
2.30
0.6
8.640
0.6
19.410
0.6
2.760
30.810
### cum
Lintels
0.952
f
105489.00
Breasumer beam
Long beam
### cum
Roof Beams
Cross beams
Long beams
Verandah cross beams
1 9
1 2
7.96
31.15
0.23
0.23
0.40
0.30
6.591
4.299
1 5
2.23
0.23
0.23
0.590
11.480
Page 22
### cum
118945.00
S.NO
Item of work
1
h
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
342.583
31.75 10.79
259.35 cum
44349.00
1
1
1
3
5
31.15
7.5
0.23
0.23
0.23
0.600 12.896
0.600 5.175
0.600 1.380
1
1
3
5
31.15
7.5
0.23
0.23
2.100 45.136
2.100 18.113
1
4
1.2
0.23
1.5
0.23
2.100 -2.318
1.350 -5.589
Long walls
31.15
0.23
0.900 19.344
7.5
0.23
0.900
7.763
7.5
0.23
0.900
3.105
Page 23
531829.00
S.NO
Item of work
1
6
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
655.00
7.50 7.500
225.000
Verandah
30.69 2.000
61.380
Slab projection
31.75 2.000
127.000
10.19 2.000
20.380
433.76
### 1mt
343.82 Sqm
149134.00
236.55 Sqm
119345.00
7.50
3.300 396.000
Verandah
30.69
3.300 101.277
Verandah
30.69
1.200 36.828
2.00
Doors D1
1.2
2.100 -10.080
Windows W1
1.5
1.350 -24.300
1.200
4.800
Deductions
504.53
Page 24
S.NO
Item of work
1
9
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
31.15
3.300 102.795
Front wall
31.15
1.200 37.380
side walls
7.73
3.30 51.018
side walls
2.23
1.20
5.352
196.55
Page 25
347.20 Sqm
68240.00
S.NO
Item of work
1
10
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
7.50
7.5
Verandah
31.15
2.23
225.000
69.465
294.47 1648.95 sqm
11
7.50
Verandah
31.15
0.100 12.000
0.100
3.115
15.12 1648.95 sqm
14
485558.00
24924.00
433.76
504.53
938.29
Page 26
87.83 sqm
82410.00
S.NO
Item of work
1
15
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
196.55
196.55
16
177.99 sqm
34982.00
1.5
1.350 24.300
Ventilators
0.9
0.600
8.640
32.94 5200.00 sqm
Page 27
171288.00
Item of work
S.NO
1
17
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
4.000
27406.00
3198810.00
Assistant Engineer
PR Kothagudem
Page 28
Executive Engineer
PR Division Kothagudem
2
PART- A (WORKDONE)
Rate
4
per
5
Amount
6
Qty
7
Less
16
###
34015.92
18656.1
###
58496.16
83931.8
Item of work
S.NO
1
Vibrated
reinforced
cement
concrete
corresponding M20 grade
as per IS 456 equivalent to
(1:1.5:3) prop: nominal
mix
(Cement:
fine
aggregate:
coarse
aggregate using 20mm
size Hard Broken Granite
(IS383, 1970) machine
crushed
metal
from
approved quarry including
cost and conveyance of all
materials like cement, fine
aggregate (Sand), coarse
aggregate, water etc. to
site including seigniorage
charges, sales & other
taxes on all materials, all
operational,
incidental,
Footings
and labor charges such as
Providing
Centring,
shuttering and scaffolding
Pedestals
with props and steel plate
as per the approved
shuttering
Columnsplan and other
accessories as per the
norms
and
stability
calculations including cost
and conveyance of all
accessories
Using
Cashewrina Ballies and
Wooden runners & staging
including
all
bracings,
cross
members
etc
complete for finished item
of work, lift charges,
machine mixing, laying
concrete, vibrating, curing
concrete etc, complete but
excluding cost of steel and
its fabrication charges etc
complete for finished item
of work (APSS No.402 &
403)
39.00
14.70
Rate
4
per
5
Amount
6
Qty
7
### cum
###
### cum
0.00
7311 cum
###
Less
16
190578.43
63352.6
23049.12
23049.1
59729.30
47737.7
Item of work
S.NO
1
Qty
3
Rate
4
per
5
Amount
6
Qty
7
Less
16
Plinth Beam
15.20
### cum
###
98017.18
23982.8
###
### cum
###
13977.55
87817.5
2.200
### cum
###
7765.13
8443.87
###
25.590
528.05 Sqm
13512.80
2329.2
###
### cum
###
94912.54
0.46
###
183603
###
2278 cum
###
13803.3
###
13.90 cum
3155.00
3155
Verandah Beam
Lintels
Roof Beams
Roof Slab 125 mm thick
Random
Rubble
stone
masonry, in CM (1:8) prop:
(Cement:
Sand)
using
Granite
stones
from
approved quarry including
cost and conveyance of all
materials
like
Granite
stones,
cement,
sand,
water,
etc.,
to site
including
seigniorage
charges, sales & other
taxes on all materials, all
operational,
incidental,
Filling
with
sand
in
and labour charges such
trenches,
sides
of
as
cutting
stones
to
foundations and basement
required size and shape,
with initial lead in layers
mixing of cement mortar,
not exceeding 15 cm
constructing
masonry,
thick, consolidating each
curing etc., complete for
deposited at layer by
finished item of work for
watering and ramming
foundation and basement
including all operational,
###
86713.25
Item of work
S.NO
1
Rate
4
per
5
5 Filling
with
sand
in
trenches,
sides
of
foundations and basement
with initial lead in layers
not exceeding 15 cm
thick, consolidating each
deposited at layer by
### 142.70 cum
watering and ramming
6 Brick
masanory
in
super
including all operational,
structure
(1:8)
incidental, with
labourCM
charges,
prop.
Using second
hire charges
of T&P class
etc.,
bricks
approved
complete from
for finished
item
source
minimum
of work having
(APSS No.309
&
crushing
strenght of 40kgs
310)
per sqm., including cost &
conveyance
of
all
materials
like
cement,sand,
bricks,
water
etc.,
to
site
### cum
including
scingniorage 70.87
charges, sales & other
taxes on all materials, all
Providing
High
Yield
operational, incidental and
Strength Deformed (HYSD)
labour
charges
such
steel bars (Fe 415 grade
mixing cement mortar,
as per IS 1786-1985) of
constructing
masanory,
8mm to 40mm diameters,
scaffolding charges, lift
cutting,
bending,
to
charges,
curing
etc.,
required sizes and shapes
complete for finished item
placing in position with
of work. APSS No.501 &
cover blocks of approved
504 for panel walls in
size and binding wire of
super structure
20SWG, forming grills for
reinforcement work as per
approved
designs
and
drawings including cost
and conveyance of bars 8767 50715 1mt
from approved sources to
site of work, including cost
PARTB (WORK of
TObinding
BE DONE)
and conveyance
wire, cover blocks, chairs,
overlaps, spacers, dowels,
wastage etc., and all
operational,
incidental,
and labour charges such
as
cutting,
bending,
Amount
6
Qty
7
###
147.25
###
###
142.70 cum
Less
16
21013.15
3245.85
251315.64
0.36
444614.12
1603515.54
Item of work
S.NO
1
2
7 Celing Plastering 12mm
thick in two coats with
base coat of 8mm thick in
CM (1:6) and top coat of
4mm thick in CM (1:4)
dubara
sponge
finish
including
cost
and
conveyance
of
all
materials
like
cement,
sand, water etc., to site,
seigniorage charges, sales
& other taxes on all
materials,all operational,
incidental
and
labour
Plastering 12mm thick in
charges such as mixing
two coats with base coat
mortar,
scaffolding
of 8mm thick in CM (1:6)
charges,
lift
charges,
and top coat of 4mm thick
including
cutting
of
in CM (1:4) dubara sponge
Grooves
wherever
finish including cost and
necessary as directed by
conveyance
of
all
Engineer - in - charge,
materials
like
cement,
finishing,
curing, etc.,
sand, water etc., to site,
complete for
finished
seigniorage charges, sales
item
of
work.
(APSS
& other taxes on all
901,903 & 904)
materials,all operational,
incidental
and
labour
charges
such
as
mixing
Plastering 20mm thick in
mortar,
two coats with scaffolding
base coat
charges,
lift in CM
charges,
of 16mm thick
(1:6)
including
cutting
of
and top coat of 4mm thick
Grooves
wherever
in CM (1:4) dubara sponge
necessary
as directed
by
finish including
cost and
Engineer
in
charge,
conveyance
of
all
finishing,
curing,
etc.,
materials
like
cement,
complete
foretc., to
finished
sand, water
site,
item
of
work.
seigniorage charges, (APSS
sales
901,903
& other& 904)
taxes on all
materials, all operational,
incidental and
labour
charges such as mixing
mortar,scaffolding
charges,
lift
charges,
finishing,including cutting
of
Grooves
wherever
necessary as directed by
Rate
4
per
5
Amount
6
Qty
7
Less
16
246.29
343.82 Sqm
84678.00
84678
622.47
236.55 Sqm
147245.00
147245
197.32
347.20 Sqm
68511.00
68511
Item of work
S.NO
1
2
Plain Cement Concrete
corresponding to M5 grade
as per IS 456 equivalent to
(1:5:10)
proportion
nominal mix (cement: fine
aggregate:
Coarse
aggregate) using 40mm
size Hard Broken Granite
(IS383, 1970) machine
crushed
metal
from
approved quarry including
cost and conveyance of all
materials
like
cement,
sand, coarse aggregate,
water
etc.
to
site,
including
seigniorage
Flooring
with & Rough
charges, sales
other
Tandur
/ shahabad
stone
taxes on
all materials,
all
of
minimum incidental,
thickness
operational,
40mm
thick, charges
set over base
and labour
such
coat
of cement
as mixing,
layingmortar
and
(1:8)
12mm concrete
thick over CC
ramming
in
bed
laid or RCC
layersalready
in position
not
roof
slab,
exceeding
15cm, including
finishing
pointing
with
cement
top
surface,
curing
mortar
filling
concrete,1:3
etc.,duly
complete
joints
nearly,
for finished
item including
of work
cost
of all Bed
materials like
for
Flooring
No.
Flooring
with (APSS
Rough
flooring
stone, cement,
402)
Tandur / shahabad stone
sand and water etc.,
of
minimum
thickness
complete,
including
40mm thick, set over base
seigniorage
charges,
coat of cement mortar
labour
charges
for
(1:8) 12mm thick over CC
dressing of flooring stones
bed already laid or RCC
etc., complete for finished
roof
slab,
including
item of work.
pointing
with
cement
mortar 1:3 duly filling
joints nearly, including
cost of all materials like
flooring stone, cement,
sand and water etc.,
complete,
including
seigniorage
charges,
labour
charges
for
dressing of flooring stones
Rate
4
per
5
Amount
6
Qty
7
Less
16
77757.00
77757
342718.00
342718
2139.00
2139
Item of work
S.NO
1
2
Painting to new internal
walls with two (2) coats of
ready mixed oil bound
washable
distemper
acrylic base of approved
brand and shade over a
base coat of
cement
primer water base interior
Grade-I of approved brand,
makind three (3) coats in
all to give an even shade
after thourughly brushing
the surface to remove all
dirt and remains of loose
powderedto Newmaterials,
9 Painting
External
including
costcoatsand
Walls
with two
of
conveyance
Plastic
Emulsion ofpaint all
of
materials
to work
site and/
Asian
/ Berger
/ Nerolac
all
operational,
incidental,
Saicoat
/ Endocem
or
labour
charges
equalent
quality etc.,
of
complete brand
for finished
item
approved
and shade
of
in all floors
for
as work
approved
by
the
internal walls
911) over
Engineer
- in -(SS
Charge
base coat of cement
primer water base grade
-II exterior making three
coats in all to give an even
shade after thoroughly
brushing the surface to
remove all loose powdered
materials, including cost
and conveyance of all
materials, including cost
and conveyance of all
materials, cost of brushes,
water to site, etc., sales &
other
taxes,
all
operational, incidental and
labour charges such as
scaffolding charges, lift
charges,
curing
etc.,
complete for finished item
of work in all floors for
external Walls.(APSS No.
911)
Rate
4
per
5
Amount
6
Qty
7
Less
16
868.76
95.38 Sqm
82862.00
82862
197.32
141.35 Sqm
27892.00
27892
Item of work
S.NO
1
2
Painting to New wood work
with two coats of ready
mixed first
quality
synthetic enamel paint of
approved brand and shade
over primary coat of wood
primer grade I making
three coats in all to give
an even shade
after
thoroughly brushing the
surface to remove all loose
powdered
materials,
including
cost
and
conveyance
of
all
materials, including cost
Supply
and
fixing
of
and conveyance
of all
18guage
sheet
materials,M.S.
cost plain
of brushes,
DOOR
of site,
size etc.,
1.05x2.10m
water to
sales &
(Double
Shutters)with
other
taxes,
all
outer
angle frame
of rolled
operational,
incidental
and
steel
angle ISA
labourequal
charges
such4040
as
of
size 40mmx
40mmx
scaffolding
charges,
lift
6mm
and curing
inner shutter
charges,
etc.,
angle
frame
rolled steel
complete for of
finished
item
equal
3535
angle
of
of workISA
in all
floors
(APSS
size
35mm
x 35mm x
No. 1201
&1208)
6mm
and welded with
fixtures and
Supply
such fixing
as
P.S.
of
18guage
M.S. plain300mm
sheet
Powder coated
DOOR
of size
1.05x2.10m
long aldrop
and
2No.s of
100mmShutters)with
(Single
long tower bolts,
outer
angle
frame of
rolled steel
door handles
including
red
oxide angle
equal
primer ISA
of 4040
grade-1
of
quality
size
40mmx
including
40mmx
coat6mm
and
and
inner ofshutter
angle
convence
all materials
and fabrication
frame
of rolled charges
steel equal
for
ISA
3535
of size
finished
itemangle
of work
35mm x 35mm x 6mm
and welded with fixtures
such as P.S. Powder coated
300mm long aldrop and
2No.s of 100mm long
tower bolts, door handles
including red oxide primer
of
grade-1
quality
including
coat
and
Rate
4
per
5
Amount
6
Qty
7
Less
16
317.00
317
52813.00
52813
8850.00
8850
3.51
90.30 Sqm
Item of work
S.NO
1
Qty
3
Rate
4
Supply
and
fixing
of
18guage M.S. plain sheet
WINDOW
of
size
1.50x1.35m
(Triple
Shutters)with outer angle
frame of rolled steel equal
angle ISA 4040 of size
40mmx 40mmx 6mm and
inner shutter angle frame
of rolled steel equal ISA
2525 angle of size 55mm
x 25mm x 6mm
and
welded with fixtures such
as P.S. Powder coated
300mm long aldrop and
2No.s
Add 5% of
VAT 100mm long
tower bolts, door handles
Add LS Amount for Roundoff
including red oxide primer
of
grade-1
quality
including
coat
and
convence of all materials
and fabrication charges for
finished item of work
Asst. Engineer
TW/ Gundala
per
5
Amount
6
Qty
7
122290.00
Less
16
122290
131079.00
131079
4820.46
4820.46
2621587.54
2757487.00
Executive Engineer
TW/ Division/Bhadrachalam
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Remarks
17
Item of work
No
L
4
Measurement
B
D
5
Columns
Columns up to Roof Leve1 19
0.23
0.38
3.000
Quantity
Rate
per
Amount
10
4.98
4.98
Over Doors
1.50
0.23
0.15
0.414
Over Windows W1
1.80
0.23
0.15
0.311
1.50
0.23
0.15
0.155
### cum
10085.00
1.80
0.6
5.400
1.50
0.6
2.700
8.100
56182.00
Lintels
0.880
f
### cum
Roof Beams
Long Beams
A1 to A6, B1 to B6
C1 to C6
A1, B1 to A4, B4
1 2
1 1
16.21
16.21
0.23
0.23
0.45
0.30
3.355
1.118
1
3
8.34
4.56
0.23
0.23
0.30
0.30
0.575
0.944
1
1
4.27
6.23
0.23
0.23
0.30
0.30
0.294
0.430
1 4
6.63
0.23
0.30
1.830
1 2
9.85
0.23
0.30
1.359
1 2
1 1
6.68
0.23
4.58
0.23
Page 47
0.45
0.30
1.383
0.316
0.30
0.989
1
D1 to D2, E1 to E2, G1 to G 1
C5, D5 to C6, D6
1
D2, G2 to D5, F5
1
Roof beam cross walls
A1 to C1, A3 to C3, A4 to
C4, A6 to C6
G1 to G1, C2 to G2
C4 to E4
E4 to G4
C5 to F5, C6 to F6
1 2
7.17
0.23
917.90 Sqm
7435.00
S.NO
1
1
No
3
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 28
2.2
2.7
2.15
357.59
A1 to A4, C1 to C4, D1 to
D4, F1 to F4, G1 to G4
1 4
15.77
0.45
0.15
4.258
1 2
4.66
0.45
0.15
0.629
Pantry
1 1
4.43
0.45
0.15
0.299
A2 to C2,A3 to C3,
1 2
9.53
0.45
0.15
1.287
D2 to F2
1 1
6.45
0.45
0.15
0.435
2.2
2.7
0.15
24.95
A1 to A4, C1 to C4, D1 to
D4, F1 to F4, G1 to G4
1 4
15.77
0.45
0.15
4.258
1 2
4.66
0.45
0.15
0.629
1 1
4.43
0.45
0.15
0.299
9.53
0.45
0.15
1.287
6.45
0.45
0.15
0.435
4.88
1.83
2.82
4.88
4.88
2.21
15.09
4.88
7.62
2.13
2.13
9.98
7.62
2.13
2.44
4.23
Page 48
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
3.719
0.390
0.601
4.870
3.719
0.941
3.682
2.064
97011.00
S.NO
1
Item of work
2
Pantry
General waiting
Portico
No
3
1 1
1 1
1 1
Quantity Rate
per
Measurement
B
D
5
6
7
8
9
4
4.88
2.44
0.100 1.191
9.98
6.9
0.100 6.886
15.09
5.22
0.100 7.877
67.80 3740.10 cum
Amount
Page 49
10
253571.00
S.NO
Item of work
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Footings
1 28
2.00
2.5
0.400
56.00
56.00 8739.25 cum
489398.00
Pedestals
1 28
0.60
0.75
0.600
7.56
7.56 9158.75 cum
69240.00
Columns
Upto GL
1 28
0.23
0.38
0.900
2.20
0.23
0.38
2.100
5.14
0.23
0.38
0.900
2.20
9.54
c
### cum
103517.00
### cum
74894.00
### cum
17009.00
Plinth Beam
For Plinth beam long walls
A1 to A4, C1 to C4, D1 to
D4, F1 to F4, G1 to G4
Toilets & Anti room
Pantry
1 4
15.77
0.45
0.15
4.258
1 2
4.66
0.45
0.15
0.629
1 1
For Plinth beam cross walls
A2 to C2,A3 to C3,
1 2
D2 to F2
1 1
4.43
0.45
0.15
0.299
9.53
6.45
0.45
0.45
0.15
0.15
1.287
0.435
6.91
Lintels
Over Doors
1 14
1.50
0.23
0.15
0.725
Over Windows W1
1.80
0.23
0.15
0.497
1.50
0.23
0.15
0.311
1.533
Page 50
S.NO
1
f
Item of work
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
1.80
0.6
7.560
1.50
0.6
5.400
12.960
Page 51
885.95 Sqm
11482.00
Item of work
S.NO
1
Roof Beams
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Long Beams
A1 to A4, B1 to B4, C1 to
C4, D1 to D4, E1 to E4, F1 1 7
to F4, G1 to G4
15.77
0.23
0.45
11.425
25.46
0.23
0.45
10.540
1 4
21.965
h
### cum
227580.00
420.869
16.15 26.06
1
1
1
4.88
7.62
1
1
1.83
2.82
2.13
2.13
1
1
1
1
1
1
4.88
4.88
9.98
7.62
2
1
2.21
15.09
2.13
2.44
1
1
1
1
1
1
1
4.88
4.88
9.98
4.23
2.44
6.9
15.09
5.22
0.600 22.311
0.600 2.339
0.600 3.604
0.600 29.221
0.600 22.311
0.600 5.649
0.600 22.092
0.600 12.385
0.600 7.144
0.600 41.317
0.600 47.262
215.64
1 4
15.77
0.23
0.60
8.705
1 2
4.66
0.23
0.60
1.286
1 1
4.43
0.60
0.60
0.611
0.23
0.23
9.53
0.23
0.60
2.630
Page 52
259.35 cum
55925.00
S.NO
Item of work
2
D2 to F2
No
3
1 1
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
6.45
0.23
Page 53
0.60
0.890
Item of work
S.NO
1
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
15.77
0.23
2.10
30.468
1 2
Pantry
1 1
For Plinth beam cross walls
4.66
4.43
0.23
0.23
2.10
2.10
4.502
2.140
A2 to C2,A3 to C3,
D2 to F2
1 2
9.53
0.23
0.23
2.10
2.10
9.206
1 1
6.45
0.23
2.10
3.115
Deductions
Doors D1
Windows W1
Windows W2
Above Lintel level
1 4
1 14
1 8
1 6
1.2
1.5
0.23
0.23
1.2
0.23
2.100 -8.114
1.350 -3.726
1.350 -2.236
Long
walls
A1 to A4,
C1 to C4, D1 to
D4, F1 to F4, G1 to G4
1 4
15.77
0.23
0.90
13.058
1 2
4.66
0.23
0.90
1.929
Pantry
1 1
4.43
0.23
0.90
0.917
0.23
0.90
1 2
9.53
0.23
0.90
3.945
D2 to F2
1 1
6.45
0.23
0.90
1.335
70.66 5064.80 cum
357884.00
4.88
7.62
37.186
Toilet
1.83
2.13
3.898
Anti room
2.82
2.13
6.007
Page 54
### 1mt
655272.00
Item of work
S.NO
1
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Office
4.88
9.98
48.702
VIP Waiting
4.88
7.62
37.186
Toilets
2.21
2.13
9.415
Passage
15.09
2.44
36.820
Dining
4.88
4.23
20.642
Pantry
4.88
2.44
11.907
General waiting
9.98
6.9
68.862
Portico
15.09
5.22
78.770
359.40
343.82 Sqm
123566.00
236.55 Sqm
70357.00
4.88
3.450 16.836
7.62
3.450 26.289
1.83
3.450
6.314
2.13
3.450
7.349
2.82
3.450
9.729
2.13
3.450
7.349
4.88
3.450 16.836
9.98
3.450 34.431
4.88
3.450 16.836
7.62
3.450 26.289
2.21
3.450
7.625
2.13
3.450
7.349
15.09
2.44
3.450
4.88
3.450 16.836
4.23
3.450 14.594
4.88
3.450 16.836
2.44
3.450
9.98
3.450 34.431
6.90
3.450 23.805
Doors D1
1 14
1.2
2.100 -35.280
Windows W1
1.5
1.350 -16.200
Windows W2
1.2
1.350 -9.720
Office
Toilet
Anti room
Office
VIP Waiting
Toilets
Passage
Dining
Pantry
General waiting
3.450 52.061
8.418
8.418
Deductions
297.43
Page 55
Item of work
S.NO
1
9
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
15.55
3.450 107.295
side walls
20.24
3.45 139.656
246.95
10
347.20 Sqm
2.82
2.13
6.007
Office
4.88
9.98
48.702
VIP Waiting
4.88
7.62
37.186
Passage
15.09
2.44
36.820
Dining
4.88
4.23
20.642
Pantry
4.88
2.44
11.907
General waiting
9.98
6.9
68.862
267.31 1648.95 sqm
11
85741.00
4.88
0.100
0.488
7.62
0.100
0.762
2.82
0.100
0.282
2.13
0.100
0.213
Page 56
440784.00
Item of work
S.NO
1
2
Office
VIP Waiting
Passage
Dining
Pantry
General waiting
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
3
1
4.88
0.100
0.488
9.98
0.100
0.998
4.88
0.100
0.488
7.62
0.100
0.762
15.09
0.100
1.509
2.44
0.100
0.244
4.88
0.100
0.488
4.23
0.100
0.423
4.88
0.100
0.488
2.44
0.100
0.244
9.98
0.100
0.998
6.90
0.100
0.690
8.88 1648.95 sqm
12
2.21
3.898
9.415
2.13
13.31
13
14634.00
917.00 sqm
12208.00
551.05 sqm
10461.00
1.83
2.100
3.843
2.13
2.100
4.473
2.21
2.100
9.282
2.13
2.100
8.946
1.20
2.100 -7.560
18.98
4.88
7.62
Page 57
37.186
Item of work
S.NO
1
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Anti room
2.82
2.13
6.007
Office
4.88
9.98
48.702
VIP Waiting
4.88
7.62
37.186
Passage
15.09
2.44
36.820
Dining
4.88
4.23
20.642
Pantry
4.88
2.44
11.907
General waiting
9.98
6.9
68.862
267.31
14
111838.00
177.99 sqm
116905.00
359.40
297.43
656.83
15
418.38 sqm
246.95
246.95
Page 58
87.83 sqm
21689.00
Item of work
S.NO
1
16
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
1.5
1.350 16.200
Windows W2
1.2
1.350
9.720
Ventilators
0.9
0.600
3.240
29.16 5200.00 sqm
17
151632.00
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
1 14
14.000
14.00 6851.55 each
95922.00
4192860.00
524108.00
419286.00
5136254.00
Page 59
S.NO
1
Item of work
2
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
Page 60
Item of work
1
1
No
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 6
2.15
51.60
5.33
0.45
0.15
1.079
5.38
0.45
0.15
0.726
1 1
2.74
0.45
0.15
0.185
53.59
266.15 cum
14263.00
3740.10 cum
31118.00
2.00
5.33
5.38
2.00
0.45
0.45
0.15
0.15
0.15
3.60
1.079
0.726
1 1
2.74
0.45
0.15
0.185
Sub grade
Bed
Kitchen
Living
1
1
1
4.88
2.9
0.100
1
1
1.83
2.97
2.74
2.74
0.100
0.100
1.415
0.501
0.814
8.32
Page 61
S.NO
Item of work
No
Measurement
B
D
5
6
4
Footings
1 6
Quantity
Rate
per
Amount
10
2.00
2.00
0.40
9.60
9.60 8739.25 cum
83897.00
Pedestals
1 6
0.60
0.6
0.600
1.30
1.30 9158.75 cum
11906.00
Columns
Upto GL
1 6
0.23
0.3
1.000
0.41
0.23
0.38
2.100
1.10
0.23
0.38
0.900
0.47
1.98
Page 62
### cum
21485.00
S.NO
Item of work
1
c
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Plinth Beam
For Plinth beam long walls 1 3
For Plinth beam cross walls 1 2
1 1
5.33
0.23
0.30
1.103
5.38
2.74
0.23
0.23
0.30
0.30
0.742
0.189
0.93
Over Doors
1.50
0.23
0.15
0.207
Over Windows W1
1.80
0.23
0.15
0.248
### cum
5048.00
885.95 Sqm
5422.00
### cum
9646.00
1.50
0.6
1.800
1.80
0.6
4.320
6.120
10094.00
Lintels
0.455
f
### cum
Roof Beams
Roof beam long walls
Roof beam cross walls
1 3
1 2
5.33
5.38
0.23
0.23
0.30
0.30
1.103
0.742
1 1
2.74
0.23
0.30
0.189
0.931
Page 63
S.NO
Item of work
1
h
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
40.481
5.94 6.815
1
1
1
1
1.83
2.97
2.74
2.74
0.500
0.500
50433.00
7.076
2.507
4.069
13.65
259.35 cum
3541.00
3
2
5.11
2.9
0.23
0.23
0.600
0.600
2.74
0.23
0.600
1
1
1
1
2
1
4.88
0.23
5.11 0.115
2.100
2.100
2
1
6.215
0.23
2.74 0.115
2.100
2.100
1
1
1
1.2
2
4
1.2 0.115
1.5
0.23
4.88
0.23
0.900
Long walls
1
1
5.11 0.115
0.900
2.020
0.529
Cross walls
0.23
0.900
2.573
Cross walls
2.74 0.115
0.900
0.284
Long walls
Cross walls
Cross walls
Upto lintel lavel
Long walls
Long walls
Cross walls
Cross walls
Deductions
Doors D1
Windows W1
Above Lintel level
Long walls
6.215
0.23
2.116
0.800
0.756
4.714
1.234
6.004
0.662
2.100 -1.159
2.100 -0.580
1.350 -1.863
Page 64
91622.00
Item of work
S.NO
1
6
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
131054.00
4.88
2.9
14.152
Kitchen
1.83
2.74
5.014
Living
2.97
2.74
8.138
27.30
### 1mt
343.82 Sqm
9388.00
236.55 Sqm
26459.00
4.88
3.6 35.136
2.90
3.6 20.880
1.83
3.6 13.176
2.74
3.6 19.728
2.97
3.6 21.384
2.74
3.6 19.728
Doors D1
1.2
2.100 -10.080
Windows W1
1.5
1.350 -8.100
Bed
Kitchen
Living
Deductions
111.85
Page 65
S.NO
Item of work
1
9
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
5.34
3.450 36.846
side walls
6.215
3.45 42.884
79.73
Page 66
347.20 Sqm
27682.00
Item of work
S.NO
1
10
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
1.83
2.74
5.014
Living
2.97
2.74
8.138
27.30 1648.95 sqm
11
4.88
0.100
0.976
2.90
0.100
0.580
1.83
0.100
0.366
2.74
0.100
0.548
2.97
0.100
0.594
2.74
0.100
0.548
3.61 1648.95 sqm
14
45023.00
5956.00
27.30
111.85
139.16
Page 67
177.99 sqm
24768.00
Item of work
S.NO
1
15
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
79.73
79.73
16
87.83 sqm
1.5
1.350
8.100
8.10 5200.00 sqm
17
7002.00
42120.00
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
1 12
12.000
12.00 6851.55 each
82219.00
740146.00
92518.00
Page 68
S.NO
Item of work
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
74015.00
LS Amount
906679.00
Page 69
Item of work
No
L
4
Measurement
B
D
5
Columns
Columns up to Roof Leve1 6
0.23
0.3
3.000
Quantity
Rate
per
Amount
10
1.24
1.24
Over Doors
1.50
0.23
0.15
0.155
Over Windows W1
1.80
0.23
0.15
0.124
Over Windows W1
1.80
0.6
1.080
1.50
0.6
1.800
Cross Beams
1 3
1 3
6.48
7.32
0.23
0.23
0.30
0.30
949.80 Sqm
2735.00
1.341
1.515
### cum
31323.00
73852.00
2.856
3299.00
Roof Beams
Long Beams
### cum
2.880
g
14523.00
Lintels
0.279
f
### cum
7.08
7.92
56.074
Item of work
2
PART- A (WORKDONE)
No
3
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 80
1.2
1.2
1.20
138.24
Long walls
1 2
55.20
0.45
0.15
7.45
Cross walls
1 3
42.20
0.45
0.15
8.55
41051.00
1 80
1.2
1.2
0.15
17.28
1 2
1 3
55.20
42.20
0.45
0.45
0.15
0.15
7.45
8.55
33.28 3740.10 cum
Footings
Page 71
124471.00
S.NO
1
Item of work
2
No
3
1 80
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
1.2
1.2
0.20
23.04
23.04 8739.25 cum
Page 72
201352.00
S.NO
Item of work
1
b
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
Pedestals
1 80
0.4
0.4
0.40
5.12
5.12 9158.75 cum
Columns
Upto GL
1 80
0.23
0.23
0.250
1.06
Above GL
1 80
0.23
0.23
1.800
7.62
### cum
94185.00
### cum
177369.00
481865.00
8.68
d
Plinth Beam
Long walls
Cross walls
1 2
1 3
55.20
42.20
0.23
0.23
0.30
0.30
7.62
8.74
16.36
46893.00
1 2
55.20
0.23
1.80
45.71
Cross walls
1 3
42.20
0.23
1.80
52.41
Deduct Gate
1 2
3.60
0.23
1.80
-2.98
2 2
55.20
1.800 397.440
Cross walls
2 3
42.20
1.800 455.760
Page 73
### 1mt
218424.00
Item of work
S.NO
1
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Deductions
Gates
3.6
1.800 -25.920
827.28
236.55 Sqm
195693.00
87.83 sqm
72656.00
827.28
827.28
1653959.00
8 Provision for Gates
206745.00
1860704.00
Page 74
Item of work
No
L
4
Measurement
B
D
5
Columns
Quantity
Rate
per
Amount
10
Upto GL
1 10
0.23
0.525
0.900
1.09
1 5
0.23
0.38
0.900
0.39
1 10
0.23
0.525
2.100
2.54
1 5
0.23
0.38
2.100
0.92
1 10
0.23
0.38
0.900
0.79
1 5
0.23
0.38
0.900
0.39
6.12
d
2.47
0.23
0.45
2730.00
### cum
8309.00
917.90 Sqm
8426.00
Lintels
Over Doors
1.50
0.23
0.15
0.104
Over Windows W1
1 10
1.80
0.23
0.15
0.621
0.725
1.80
0.6
1.080
1.50
0.6
8.100
9.180
### cum
0.256
0.256
69042.00
Landing beam
1
### cum
Roof Beams
Page 75
Item of work
S.NO
1
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
Long Beams
Portico, front & Rear long
walls
Middile long walls
Cross walls
In portico
Hall
1 3
7.55
0.23
0.45
2.343
1 3
7.55
0.23
0.60
3.126
1 3
5 3
2.47
3.43
0.23
0.23
0.30
0.30
0.511
3.548
9.528
Page 76
### cum
101608.00
S.NO
Item of work
1
h
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
132.578
7.55 17.56
1.20
2.93
3.516
Landing
3.00
1.20
3.600
2nd flight
3.00
1.20
3.600
10.716 1609.90 Sqm
7.545
0.23
2.100
17.09
0.23
2.100
Doors D1
Windows W1
Above Lintel level
Long walls
1 2
1 10
1.2
1.5
0.23
0.23
2.100 -1.159
1.350 -4.658
Rear
wallrobe long
Toiletlong
& ward
wall
7.545
0.23
0.900
1.562
17.09
0.23
0.900
3.538
Cross walls
Deductions
1
1
3.644
8.254
17252.00
59430.00
Page 77
### 1mt
355680.00
Item of work
S.NO
1
7
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
7.09
14.4
Portico
3.05
2.7
102.096
8.235
110.33
372.32 Sqm
41078.00
261.70 Sqm
30500.00
372.35 Sqm
60079.00
7.09
3.300 46.794
14.40
3.300 95.040
Doors D1
1.2
2.100 -5.040
Windows W1
1 10
1.5
1.350 -20.250
Hall
Deductions
116.54
9
7.55
side walls
14.86
3.600 54.360
3.60 106.992
161.35
Page 78
Item of work
S.NO
1
10
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
3.55
9.585
2.7
7.09
0.100
1.418
14.40
0.100
2.880
4.30 1673.10 sqm
14
186853.00
7191.00
110.33
116.54
226.88
Page 79
177.99 sqm
40380.00
Item of work
S.NO
1
15
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
161.35
161.35
16
87.83 sqm
1 10
1.5
1.350 20.250
Ventilators
1 12
0.9
0.600
6.480
26.73 5200.00 sqm
17
14171.00
138996.00
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
2.000
13703.00
1325320.00
Page 80
S.NO
1
Item of work
2
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
Page 81
Item of work
2
No
3
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 x 13
2.00
2.00
2.05
106.60
Verandah columns
Long walls
1 x 5
1.40
1.40
1.65
16.17
1 x 3
15.58
0.45
0.45
9.46
Crosswalls
1 x 5
7.28
0.45
0.45
7.37
1 x 5
2.00
0.45
0.45
2.03
141.63 266.15 cum
37695.00
1 x 13
2.00
2.00
0.10
Verandah columns
1 x 5
1.40
1.40
0.10
5.20
0.98
6.18
1026.70 cum
6345.00
1 x 13
1 x 5
1 x 3
2.00
1.40
30.97
2.00
1.40
0.45
0.15
0.15
0.15
7.80
1.47
6.27
Crosswalls
Verandah cross walls
1 x 5
1 x 5
7.28
2.00
0.45
0.45
0.15
0.15
2.46
0.68
146.83 3740.10 cum
Page 82
549159.00
S.NO
Item of work
No
Measurement
B
D
5
6
4
Footings
Kitchen and dining
Verandah columns
1 13
1 5
Quantity
Rate
per
Amount
10
1.80
1.20
1.8
1.2
0.500
0.400
21.06
2.88
23.94 8739.25 cum
0.00
Pedestals
Kitchen and dining
1 13
0.60
0.75
0.600
3.51
Verandah columns
1 5
0.60
0.6
0.450
0.81
4.32 6831.47 cum
29512.00
Columns
Upto GL
Kitchen and dining
1 13
0.13
0.3
0.400
0.20
Verandah columns
1 5
0.13
0.13
0.100
0.01
1 13
0.13
0.3
2.100
1.06
Verandah columns
1 5
0.13
0.13
2.100
0.18
1 13
0.13
0.3
1.200
0.61
Verandah columns
1 5
0.13
0.13
0.500
0.04
2.10
Page 83
### cum
22787.00
S.NO
Item of work
1
c
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Plinth Beam
Long walls
1 x 3
15.65
0.13
0.30
1.83
Crosswalls
Verandah cross walls
1 x 5
1 x 5
7.60
2.00
0.13
0.13
0.30
0.30
1.48
0.39
1.83
1 x 3
15.65
0.13
0.30
1.83
1 x 5
2.30
0.13
0.30
0.45
2.280
Over Doors
1.50
0.13
0.15
0.12
Over Windows W1
1.80
0.13
0.15
0.42
23623.00
### cum
5991.00
Verandah sunshade
1 16.85
Verandah sunshade
1.80
2.30
0.6
4.320
0.6
10.110
0.6
2.760
17.190
### cum
Lintels
0.540
f
19840.00
Breasumer beam
Long beam
### cum
885.95 Sqm
15229.00
### cum
35953.00
Roof Beams
Cross beams
Long beams
Verandah cross beams
1 5
1 2
7.96
15.65
0.13
0.13
0.40
0.30
2.07
1.22
1 5
2.13
0.13
0.13
0.18
3.470
Page 84
S.NO
Item of work
1
h
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
172.561
16.45 10.49
259.35 cum
44349.00
1
1
1
3
5
15.65
7.5
0.13
0.13
0.600
0.600
0.13
0.600
3.66
2.93
0.78
0.00
12.82
1
1
3
5
15.65
7.5
0.13
0.13
2.100
2.100
1
4
1.2
0.13
2.100
1.5
0.13
1.350
-1.31
-3.16
Long walls
15.65
0.13
0.500
3.05
7.5
0.13
0.500
2.44
7.5
0.13
0.500
0.98
Deductions
Doors D1
Windows W1
Above Lintel level
Long walls
10.24
Page 85
164251.00
S.NO
Item of work
1
8
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
349478.00
343.82 Sqm
110124.00
648.79 Sqm
154202.00
7.50 7.500
112.500
Verandah
30.39 2.000
60.780
Slab projection
31.71 2.000
126.840
10.09 2.000
20.180
320.30
10
### 1mt
7.50
3.300 198.000
Verandah
15.39
3.300 50.787
Verandah
15.39
1.200 18.468
2.00
Doors D1
1.2
2.100 -10.080
Windows W1
1.5
1.350 -24.300
1.200
4.800
Deductions
237.68
Page 86
S.NO
Item of work
1
11
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
15.65
3.300 51.645
Front wall
15.65
1.200 18.780
side walls
7.63
3.30 50.358
side walls
2.13
1.20
5.112
125.90
Page 87
347.20 Sqm
43711.00
S.NO
Item of work
1
12
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
7.50
7.5
Verandah
15.65
2.13
112.500
33.335
145.84 1648.95 sqm
13
7.50
0.100
6.000
Verandah
30.65
0.100
3.065
9.07 1648.95 sqm
14
240475.00
14948.00
320.30
237.68
557.98
Page 88
177.99 sqm
99311.00
S.NO
Item of work
1
15
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
125.90
177.99 sqm
22407.00
75660.00
125.90
16
1.5
1.350 12.150
Ventilators
0.5
0.600
Page 89
2.400
Item of work
S.NO
1
17
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
2.000
13703.00
2293738.00
Assistant Engineer
PR Paloncha
Page 90
Executive Engineer
PR Division Kothagudem
Item of work
2
No
3
L
4
Measurement
B
D
5
Quantity
Rate
per
Amount
10
1 x 6
1.80
1.80
2.00
38.88
Verandah columns
1 x 3
1.20
1.20
1.20
5.18
Long walls
1 x 2
6.68
0.45
0.45
2.71
1 x 2
4.78
0.45
0.45
1.94
1 x 2
2.00
0.45
0.45
0.81
49.52
266.15 cum
13180.00
3740.10 cum
17878.00
1 x 6
1 x 3
1.80
1.20
1.80
1.20
0.15
0.15
2.92
0.65
Long walls
Rooms cross walls
1 x 2
1 x 2
6.68
4.78
0.45
0.45
0.10
0.10
0.60
0.43
1 x 2
2.00
0.45
0.10
0.18
4.78
Page 91
S.NO
Item of work
No
Measurement
B
D
5
6
4
Footings
Room columns
Verandah columns
1 6
1 3
Quantity
Rate
per
Amount
10
1.35
0.90
1.5
1.00
0.380
0.300
0.9
4.62
0.81
5.43 8739.25 cum
47454.00
Pedestals
Room columns
1 6
0.45
0.45
0.500
0.61
Verandah columns
1 3
0.30
0.3
0.350
0.09
0.70 6831.47 cum
4782.00
Columns
Upto GL
Room columns
1 6
0.23
0.3
0.900
0.37
Verandah columns
1 3
0.23
0.23
0.650
0.10
1 6
0.23
0.3
2.100
0.87
Verandah columns
1 3
0.13
0.23
2.100
0.19
1 6
0.23
0.3
1.200
0.50
Verandah columns
1 3
0.23
0.23
0.500
0.08
2.11
22895.00
### cum
14528.00
### cum
7978.00
Plinth Beam
Long walls
Crosswalls
Verandah cross walls
1 x 3
1 x 2
1 x 2
6.46
5.00
2.00
0.23
0.23
0.23
0.30
0.30
0.30
1.34
0.69
0.28
1.34
### cum
Breasumer beam
Long beam
Verandah cross walls
1 x 1
6.46
0.23
0.30
0.45
1 x 2
2.30
0.23
0.30
0.32
0.770
Page 92
S.NO
Item of work
1
e
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
Lintels
Over Doors
1 1
1.50
0.23
0.15
0.05
Over Windows W1
1 3
1.80
0.23
0.15
0.19
0.240
Page 93
### cum
2663.00
S.NO
Item of work
1
f
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Verandah sunshade
Verandah sunshade
0.6
2.160
6.46
0.6
3.876
2.30
0.6
2.760
1.80
8.796
g
Long beams
1 2
1 3
6.46
7.23
0.23
0.23
0.30
0.40
0.89
2.00
### cum
29943.00
46709.00
2.890
7.06
42.784
6.06
1 x 1
6.00
2.00
0.900
27.00
10.80
37.80
7793.00
Roof Beams
Cross beams
885.95 Sqm
1
1
1
1
1
1
3
2
6.46
5.00
0.23
0.23
0.600
0.600
2.00
0.23
0.600
3
2
6.46
5.00
0.23
0.23
2.100
2.100
2.00
0.23
2.100
Page 94
2.67
1.38
0.55
0.00
9.36
4.83
1.93
259.35 cum
9803.00
S.NO
Item of work
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Deductions
Doors D1
Windows W1
Above Lintel level
Long walls
1
1
1
3
1.2
1.5
0.23
0.23
2.100
1.350
-0.58
Long walls
6.46
0.23
0.800
3.57
5.00
0.23
0.800
1.84
2.00
0.23
0.900
0.83
-1.40
126519.00
Class rooms
6.00 5.000
30.000
Verandah
6.00 2.000
12.000
Slab projection
8.29 0.600
9.948
7.06 0.600
8.472
60.42
### 1mt
74264.00
343.82 Sqm
20773.00
Page 95
S.NO
Item of work
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
In side
Rooms
1 (6.0+5.0)
3.200 70.400
Verandah
6.00
3.200 19.200
Verandah
6.00
1.200
7.200
2.00
1.200
4.800
Doors D1
1.2
2.100 -2.520
Windows W1
1.5
1.350 -6.075
Deductions
93.01
10
22000.00
347.20 Sqm
42365.00
608.70 sqm
25565.00
6.45
3.200 20.640
Front wall
6.45
1.200
side walls
7.63
side walls
2.13
Basement
6.45
1.200 15.480
10.09
1.20 24.216
7.740
3.20 48.832
1.20
5.112
122.02
11
236.55 Sqm
6.00
5.00
30.000
Verandah
6.00
2.00
12.000
42.00
Page 96
S.NO
1
14
Item of work
2
No
3
Measurement
B
D
5
6
4
Quantity
Rate
per
Amount
10
60.42
93.01
153.43
15
177.99 sqm
27307.00
177.99 sqm
21718.00
122.02
122.02
Page 97
Item of work
S.NO
1
16
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
1.5
1.350
6.075
Ventilators
0.5
0.600
1.200
7.28 5200.00 sqm
17
37830.00
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
1.000
6852.00
630799.00
Assistant Engineer
PR Kothagudem
Executive Engineer
PRSD Kothagudem
PR Division Kothagudem
Page 98
Toilet Block
Item of work
S.
NO
No
Measurement
B
D
L
Quantity Rate
per
Amount
1.00
1.00
1.50
9.00
Long walls
2.23
2.15
2.15
0.30
0.30
0.30
0.10
0.10
0.10
0.13
0.13
0.19
9.46
Cross walls
1 2
1 2
1 3
266.15 cum
2517.00
9062.00
1.00
1.00
0.30
1.80
Long walls
Cross
walls : C1 to C4, C2 to C5, 1 4
C3 to C6
1 3
3.00
2.92
0.30
0.30
0.10
0.10
0.36
0.26
2.42
### cum
1.45
1 6
0.90
0.90
0.30
Item of work
S.
NO
Long
Crosswalls
walls:: C1
C1 to
to C3,
C4, C4
C2 to
to C6
C5,
C3 to C6
No
Measurement
B
D
L
1 2
6.69
0.23
0.23
1 3
2.92
0.23
0.23
Quantity Rate
per
Amount
0.70
0.46
1.16
Columns
upto Ground level C1 to C6
1 6
0.23
0.23
0.65
0.206
1 6
0.23
0.23
2.70
0.85
2 3
0.23
0.23
0.59
0.18
1.24
Varandha beam
1 1
6.69
0.23
0.23
0.35
### Cum
3667.00
Sunshade 0.6m
1 1
6.69
0.60
4.01
885.95 Sqm
3556.00
1 1
7.29
3.98
29.01
1 1
6.69
0.23
0.23
0.35
1 3
2.92
0.23
0.23
0.46
0.82
### Cum
8468.00
Item of work
S.
NO
No
Measurement
B
D
L
Quantity Rate
per
Amount
9.00
Deduction
PCC (1:5:10)
-1.80
Footings
-1.45
Columns upto GL
-0.206
5.54
18.45 Cum
102.00
1 4
3.00
0.23
0.40
1.65
1 3
2.92
0.23
0.40
1.20
Long
Crosswalls
walls:C4
C1totoC5,
C4,C5
C2totoC6
C5,
C3 to C6
1 2
3.00
0.23
2.10
2.89
1 3
2.92
0.23
2.10
4.23
1 2
0.76
0.23
1.98
-0.69
C1 to C2, C2 to C3
1 2
3.00
0.23
0.59
0.81
C4
to C5,
C5C1
to C6
Cross
walls:
to C4, C2 to C5,
C3 to C6
1 2
3.00
0.23
0.29
0.40
1 3
2.92
0.23
0.82
1.65
C3 to C6
Upto Lintel level
12.15
1 2
3.00
2.92
0.80
8 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415
grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting,
bending, to required sizes and shapes placing in position with cover
blocks of approved size and binding wire of 20SWG, forming grills for
reinforcement work as per approved designs and drawings including
cost and conveyance of bars from approved sources to site of work,
including cost and conveyance of binding wire, cover blocks, chairs,
overlaps, spacers, dowels, wastage etc., and all operational,
incidental, and labour charges such as cutting, bending, placing in
position, tying etc., and sales & other taxes,on cost of all materials
complete for finished item of work (APSS No.126) in all floors
14.01
450.60 Cum
6313.00
Item of work
S.
NO
No
Measurement
B
D
L
Quantity Rate
0.9
###
per
Amount
Kgs 39316.00
9 Ceiling Plastering 12mm thick in two coats with base coat of 8mm
thick in CM (1:3) including cost and conveyance of all materials like
cement, sand, water etc., to site, seigniorage charges, sales & other
taxes on all materials,all operational, incidental and labour charges
such as mixing mortar, scaffolding charges, lift charges, including
cutting of Grooves wherever necessary as directed by Engineer - in charge, finishing, curing, etc., complete for finished item of work.
(APSS 901,903 & 904)
In rooms
1 2
3.00
2.92
17.52
1 3
2.92
0.69
6.04
1 1
6.00
0.69
4.14
1 2
7.29
0.30
4.37
Longwall side
1 2
6.70
0.30
4.02
Front sunshade
1 2
3.40
0.30
2.04
38.14
Item of work
S.
NO
No
Measurement
B
D
L
Quantity Rate
per
Amount
10 Plastering 20mm thick in two coats with base coat of 16mm thick in
CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, sand,
water etc., to site, seigniorage charges, sales & other taxes on all
materials, all operational, incidental and labour charges such as
mixing mortar,scaffolding charges, lift charges, finishing,including
cutting of Grooves wherever necessary as directed by Engineer - in charge, curing, etc., for Uneven Surfaces of Brick Wall
(external) complete for finished item of work. (APSS 901,903 &
904)
Crosswalls
1 1
6.69
3.59
24.01
1 1
6.69
3.29
22.01
1 2
3.38
3.52
23.79
69.81
11 Plastering 12mm thick in two coats with base coat of 8mm thick in
CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish
including cost and conveyance of all materials like cement, sand,
water etc., to site, seigniorage charges, sales & other taxes on all
materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge,
finishing, curing, etc., for Even Surfaces of brick wall (internal
walls) complete for finished item of work. (APSS 901,903 & 904)
1 2
3.00
2.99
17.94
1 2
3.00
1.98
11.88
1 2
3.00
2.39
14.34
1 2
1.40
2.92
8.17
1 2
1.40
1.98
5.54
1 2
1.40
2.39
8.17
1 6
1.40
1.98
16.63
1 4
0.75
1.98
-5.94
76.74
12 Painting to new internal walls with two (2) coats of ready mixed oil bound
washable distemper acrylic base of approved brand and shade over a base
coat of cement primer water base interior Grade-I of approved brand,
makind three (3) coats in all to give an even shade after thourughly brushing
the surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials to work site and all
operational, incidental, labour charges etc., complete for finished item of
work in all floors for internal walls (SS 911)
In rooms
1 2
3.00
2.92
17.52
1 3
2.92
0.69
6.04
1 1
6.00
0.69
4.14
1 2
7.29
0.30
4.37
Longwall side
1 2
6.70
0.30
4.02
Front sunshade
1 2
3.40
0.30
2.04
1 2
3.00
2.99
17.94
1 2
3.00
1.98
11.88
1 2
3.00
2.39
14.34
1 2
1.40
2.92
8.17
Item of work
S.
NO
No
Measurement
B
D
L
1 2
1.40
2.39
1 6
0.75
1.98
Quantity Rate
per
Amount
8.17
-8.91
89.73
13 Painting to New Iron work with two coats of ready mixed synthetic enamel
paint first quality all shades over red oxide primer Grade-I making three (3)
coats in all to given and even shade after thourughly brushing the surface to
remove all dirt and remains of loose powered materials, including cost and
conveyance of all materials to site, sales & other taxes, incidental,
operational and all labour charges etc., complete for finished item of work.
(APSS No. 1201, 1207 & 1212).in All Floors
Backside wall
1 1
0.75
2.99
2.24
2.24
401.28 Sqm
900.00
6.69
3.29
22.01
Crosswalls
1 2
3.38
3.52
23.79
1 1
22.54
0.13
2.81
72.62
1 4
4.00
###
Each
###
Item of work
S.
NO
No
Measurement
B
D
L
Quantity Rate
per
Amount
Flooring with ceramic tiles 7.3mm thick of 1st quality all shades of
makes Jhonson & Jhonson, Kajaria, Nitco and Marbonite, set over
base coat of cement mortar (1:8), 12 mm thick over CC bed already
laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white
cement paste to full depth mixed with pigment of matching shade,
including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc., complete for finished
item of work.
Toilets
1 2
3.00
1.40
8.40
Front carridor
1 4
1.40
1.40
7.84
16.24
###10sqm 13177.00
###
Asst. Engineer
TW/ Gundala
Executive Engineer
TW/ Division/Bhadrachalam
Item of work
No
L
4
Measurement
B
D
5
Columns
Quantity
Rate
per
Amount
10
1 10
0.23
0.3
2.100
5.80
0.13
0.23
2.100
0.63
0.23
0.3
1.200
3.31
0.23
0.23
0.500
0.26
1 10
10.00
d
1 x 1
54.42
0.23
0.30
3.75
1 x 2
2.30
0.23
0.30
0.32
4.070
Over Doors
1 5
1.50
0.23
0.15
0.26
Over Windows W1
5 3
1.80
0.23
0.15
0.93
43403.00
### cum
13638.00
917.90 Sqm
42418.00
Verandah sunshade
1 54.42
Verandah sunshade
1.80
2.30
0.6
10.800
0.6
32.652
0.6
2.760
46.212
### cum
Lintels
1.190
f
112815.00
Breasumer beam
Long beam
### cum
Roof Beams
Cross beams
1 6
7.96
0.23
Page 106
0.40
4.39
S.NO
Item of work
2
Long beams
Verandah cross beams
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
3
1 2
1 6
54.42
2.13
0.23
0.23
0.30
0.13
7.51
0.38
12.280
### cum
130956.00
577.160
55.02 10.49
7.50
-54.000
3.6
1.50
3.00
4.500
Landing
3.00
1.80
5.400
2nd flight
1.50
3.00
4.500
14.400 1609.90 Sqm
0.00
1 3
1 2
1 10
54.79
3.60
0.23
0.23
2.100
2.100
7.5
0.23
2.100
0.00
79.39
-3.48
36.23
1
5
1.2
0.23
2.100
1.5
0.23
1.350
-4.06
-6.99
Long walls
54.79
0.23
0.800
30.24
Deduct staircase
3.60
0.23
2.100
-3.48
7.5
0.23
0.800
6.90
7.5
0.23
0.900
3.11
Windows W1
Above Lintel level
Long walls
Page 107
732767.00
Item of work
S.NO
1
3
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
622440.00
372.32 Sqm
175909.00
261.70 Sqm
176187.00
7.50 7.500
281.250
Toilets
7.50 3.600
54.000
Verandah
53.74 2.000
107.480
Slab projection
39.48 0.300
23.688
10.09 0.300
6.054
472.47
### 1mt
5 (7.5+7.5)
3.200 480.000
Verandah
53.74
3.200 171.968
Verandah
53.74
1.200 64.488
2.00
Doors D1
1.2
2.100 -17.640
Windows W1
1.5
1.350 -30.375
1.200
4.800
Deductions
673.24
Page 108
S.NO
Item of work
1
6
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
54.19
3.200 173.408
Front wall
54.19
1.200 65.028
side walls
7.63
3.20 48.832
side walls
2.13
1.20
Basement
54.19
1.200 130.056
10.09
1.20 24.216
5.112
446.65
Page 109
372.35 Sqm
166311.00
S.NO
Item of work
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
Deduct Staircase
577.160
55.02 10.49
7.50
-54.000
3.6
523.16
205079.00
629.75 sqm
286593.00
629.75 sqm
15664.00
7.50
7.5
281.250
Stair case
7.50
3.6
54.000
Verandah
53.74
2.23
119.840
455.09
392.00 Sqm
7.50
0.100 15.000
Verandah
53.74
0.100
5.374
Staircase
7.50
0.100
4.500
24.87
Page 110
Item of work
S.NO
1
9
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
7.50
3.6
54.000
54.00
10
50836.00
177.99 sqm
203920.00
177.99 sqm
79498.00
472.47
673.24
###
11
941.40 sqm
446.65
446.65
Page 111
Item of work
S.NO
1
12
Measurement
B
D
5
6
4
No
Quantity
Rate
per
Amount
10
1.5
1.350 30.375
Ventilators
0.5
0.600
2.400
32.78 5200.00 sqm
13
170430.00
Supply and Fixing of Door with Double leaf shutter, Door Size
1.22x2.13 mtrs with Sal wood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood black board
type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long
2 Nos, 300mm long M.S.Powder Coated Aldrops 1No, 125mm
long M.S.Powder Coated butt hinges 6Nos, 300 mm long
M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance
of all materials to site all Labour charges such as Fixing of
Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work.
Doors
7.000
47961.00
3930827.00
Assistant Engineer
PR Kothagudem
Executive Engineer
PRSD Kothagudem
PR Division Kothagudem
Page 112
Name of the Work : Construction of ZPHS Building (First Floor) in Patha Kothagudem in Kothagudem
Mandal in Khammam District
SEPTIC TANK
DETAIL CUM ABSTRACT ESTIMATE
Sl.
No.
1
DESCRIPTION OF ITEM
NO'S
D/H
Quantity
UNIT
Rate
Amount
2013-14
10
Earth work excavation for foundations and depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental, seigniorage charges, labour charges such as
shoring ,sheeting, planking, strutting, dewatering etc. complete for finished item of work as
per SS - 20 B (APSS 308). for Septic Tank
1 X 1
2.10
45.45
45.45 cum
248.80
11309
1 X 1
5.85
3.70
0.30
6.49
6.49 cum
3324.95
21591
5449.50
7079
Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:2:4)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG
(SS5) metal from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labour charges such as mixing,
laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface,
curing concrete, etc., complete for finished item of work (APSS No. 402)
for septic tank Ist side
plotform
3.70
Plain Cement Concrete (1:5:10) proportion (cement: fine aggregate: Coarse aggregate) using
40mm size Hard Broken Granite (IS383, 1970) machine crushed metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc.
to site, mixing concrete in concrete mixer including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete,
etc., complete for finished item of work. (APSS No. 402).
5.85
1 X 1
1 X 1
5.15
5.85
3.00
1.80
0.05
0.05
0.77
0.53
1.30 cum
Vibrated Reinforced Cement Concrete M25 Grade corresponding to IS 456 using 20mm size
graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content
@ 380Kgs/Cum from standard suppliers approved by the department including centering,
shuttering, laying concrete, vibrating, curing etc. complete for Slab of 125mm thick
312918434.xls
1 X 1
5.85
3.70
SEPTIC TANK
21.65
113of228
Sl.
No.
DESCRIPTION OF ITEM
NO'S
D/H
Quantity
UNIT
21.65 Sqm
5
1084.75
23479
4358.70
71114
61420.45
24568
Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from
approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, sand, bricks, water etc., to site, including
seigniorage charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work.
for Septic tank L/W
for septic tank C/W
Septic tank Baffle wall
Amount
2013-14
Rate
1 X 2
1 X 2
1 X 2
5.85
3.00
3.00
0.35
0.35
0.115
2.50
2.50
1.20
10.24
5.25
0.83
16.32 Cu.M.
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 17861979) of different diameters for RCC works, including labour charges for straightening,
cutting, bending to required sizes and shapes, placing in position with cover blocks of
approved materials and size and tying and lapsplicing with binding wire of 18 SWG, forming
grills for reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer
bars including cost and conveyance of binding wire, cover blocks and all incidental,
operational, laour charges such as cutting, bending placing in position, tying including sales
and other taxes on all materials etc., complete for finished item of work in all floors. (APSS
No.126)
0.400 Mts
TOTAL AMOUNT
Asst. Engineer
PR Kothagudem
312918434.xls
Dy.Executive Engineer
PR.SD. Kothagudem
SEPTIC TANK
159140
Executive Engineer
PR Div. Kothagudem
114of228
LEAD CHART
Construction of Class Room
RATES AS PER COMMON SSR OF 2014-15 with cement and steel rates of November 2014
Lead in KM
Sl. No.
(1)
1
Description
Avg.
SSR Sl.No. Thickness
in mm
Total
Convence
Charges
Area
allowence on
unloading loading &
charges
unloading
charges @
25 %
MR
CT
(5)
Godavari
(6)
45.00
(7)
0.00
(8)
45.00
(9)
488.25
(10)
462.00
(11)
45.00
(12)
0.00
(13)
0.00
(14)
8.00
(15)
2.00
(2)
Sand for Mortar
(3)
M-005
M-004
Godavari
45.00
0.00
45.00
488.25
342.00
45.00
0.00
0.00
8.00
M-006
Godavari
45.00
0.00
45.00
488.25
606.00
45.00
0.00
0.00
8.00
Gravel
M-008
Local
5.00
0.00
5.00
73.77
103.00
22.00
0.00
0.00
R.R. Stone(Granite,
Dolamite &Trap variety)
M-148
Thogudem
27.00
0.00
27.00
316.93
252.00
50.00
0.00
R.R. Stone(Granite,
Dolamite &Trap variety)
M-148
Thogudem
27.00
0.00
27.00
316.93
252.00
50.00
R.R. Stone(Granite,
Dolamite &Trap variety)
M-148
Thogudem
27.00
0.00
27.00
316.93
252.00
Thogudem
27.00
0.00
27.00
316.93
Thogudem
27.00
0.00
27.00
Thogudem
27.00
0.00
Thogudem
27.00
Thogudem
8
9
10
11
12
13
(4)
Source of Material
Initial Cost
including
Add
Stacking
Differenc in 1% towards Loading
Charges
Seigniostorage
charges
wherever rage Charges
necesssary
14
15
16
BMT-B.06
Total
Unit per
(16)
1005.25
(17)
Cum.
2.00
885.25
Cum.
2.00
1149.25
Cum.
8.00
2.00
208.77
Cum.
32.00
15.90
3.98
670.81
Cum.
0.00
32.00
15.90
3.98
670.81
Cum.
50.00
0.00
32.00
15.90
3.98
670.81
Cum.
845.00
50.00
0.00
0.00
0.00
0.00
1211.93
Cum.
316.93
1365.00
50.00
0.00
0.00
0.00
0.00
1731.93
Cum.
27.00
316.93
1097.00
50.00
0.00
0.00
0.00
0.00
1463.93
Cum.
0.00
27.00
316.93
935.00
50.00
0.00
0.00
0.00
0.00
1301.93
Cum.
27.00
0.00
27.00
316.93
735.00
50.00
0.00
0.00
0.00
0.00
1101.93
Cum.
Anisettipally
15.00
0.00
15.00
296.67
4700.00
0.00
0.00
44.00
44.00
11.00
5095.67
1000 Nos
Local
10.00
0.00
10.00
475.99
11000.00
0.00
0.00
100.87
100.87
25.22
11702.95
1000 Nos
Local
1.00
0.00
1.00
229.38
24000.00
0.00
0.00
226.96
226.96
56.74
24740.03
1000 Nos
400.00
0.00
400.00
83.17
137.90
4.00
0.00
0.48
0.24
0.06
225.85
2.29249
15
Batchamcherla
Page 115
1Sqm.
Lead in KM
Sl. No.
17
Description
Avg.
SSR Sl.No. Thickness
in mm
BMT-B.01
Rough Kadapa slabs of
minimum 40 mm thick, size
not less than (0.457 x 457M)
Source of Material
MR
CT
Total
Convence
Charges
Initial Cost
including
Add
Stacking
Differenc in 1% towards Loading
Charges
Seigniostorage
charges
wherever rage Charges
necesssary
Area
allowence on
unloading loading &
charges
unloading
charges @
25 %
Total
Unit per
40
Batchamcherla
300.00
0.00
300.00
Page 116
167.41
96.00
4.00
0.00
1.28
0.64
0.16
269.49
1Sqm.
Lead in KM
Sl. No.
Description
Avg.
SSR Sl.No. Thickness
in mm
18
18
BMT-B.11
17
19
20
water
21
Cement
22
Source of Material
MR
CT
Total
Convence
Charges
Initial Cost
including
Add
Stacking
Differenc in 1% towards Loading
Charges
Seigniostorage
charges
wherever rage Charges
necesssary
Local
300.00
0.00
300.00
75.33
729.00
0.00
Local
5.00
0.00
5.00
1.84
2178.00
0.00
M-189
Local
0.50
0.00
0.50
0.00
77.00
CSSR-A.05
At Site
0.00
0.00
0.00
0.00
5800.00
0.00
0.00
0.00
M-126
At Site
0.00
0.00
0.00
0.00
44000.00
0.00
0.00
23
CSSR-A.62
At Site
0.00
0.00
0.00
0.00
28000.00
0.00
24
CSSR-A.68
At Site
0.00
0.00
0.00
0.00
44500.00
25
M.S. Plates
CSSR-A.69
At Site
0.00
0.00
0.00
0.00
43000.00
Assistant Engineer
PR Kothagudem
Page 117
Total
Unit per
0.58
0.29
0.07
805.27
1Sqm.
0.54
0.27
0.07
2180.73
1Sqm.
0.00
77.00
KL
0.00
0.00
5800.00
M.T
0.00
0.00
0.00
44000.00
M.T
0.00
0.00
0.00
0.00
28000.00
M.T
0.00
0.00
0.00
0.00
0.00
44500.00
M.T
0.00
0.00
0.00
0.00
0.00
43000.00
M.T
Executive Engineer
PR Division Kothagudem
0.00
Area
allowence on
unloading loading &
charges
unloading
charges @
25 %
DATA
Construction of Class Room
Overheads
14%
COMMON STANDARD SCHEDULE OF RATES FOR THE YEAR 2014-15
25%
DATA
Construction of Class Room
Qty
1
Rate
Per
Amount
1.05 Cum
720 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
4176.00
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
5456.46
1.05 Cum
480 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
2784.00
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
4064.46
1.05 Cum
360 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
2088.00
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
3368.46
1.05 Cum
288 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
1670.40
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
2950.86
1.05 Cum
240 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
1392.00
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
2672.46
1.05 Cum
180 Kgs
1149.25
5800.00
1 Cum
1000 Kgs
1206.71
1044.00
0.20 Nos
25%
295.00
59.00
1 Day
59.00
14.75
2324.46
Page 118
0.6
0.15
0.15
0.10
Cum
Cum
Cum
Cum
1731.93
1463.93
1301.93
1101.93
1
1
1
1
1
2
3
4
a)
Description of machinery
concrete mixer300/200 (diesel)
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
Units
Cum
Cum
Cum
Cum
1039.16
219.59
195.29
110.19
Total
1564.23
303.10
503.90
152.20
0.00
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey
Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour
charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc.,
complete for Foundation of Building.(APSS No. 308)
Light Mazdoor
Muncipal area alloence
Add 75% for excavation of foundation
of
addbuilding
seigniorage charges
Add 14% over heads
Rate per 1 cu.m.
Hour
Hour
Hour
54.60
120.30
7.80
0.364
25%
1
1
209.92
Nos
cu.m.
cum
cu.m.
74.30
114.10
19.00
total
295.00
107.38
80.535
22.00
0.14
174.20
269.50
125.40
1 Day
1 cu.m.
1 cum
1 cu.m.
Total
107.38
26.85
80.54
22.00
29.39
266.15
b) Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey
Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour
charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc.,
complete for Pipe line where the depth is more than 1.5 times width.(APSS No. 308)
Light Mazdoor
Add 120 % for excavation of Pipe line
add seigniorage charges
Add 14% over heads
Rate per 1 cu.m.
0.364
1
1
258.24
Nos
cu.m.
cum
cu.m.
295.00
128.856
22.00
0.14
1
1
1
1
Day
cu.m.
cum
cu.m.
Total
107.38
128.86
22.00
36.15
294.40
C) Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey
Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour
charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc.,
complete for Septic tank soak pit and sump.(APSS No. 308)
Light Mazdoor
0.364 nos
25%
1 cum
295.00
1 nos
107.38
22.00
107.38
26.85
1 cum
22.00
156.23
156.23
0.14
21.87
Total
178.10
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and basement with
initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including
cost and conveyence of water to work site and all operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
Light Mazdoor
Muncipal area alloence
Add 14% over heads
Rate per 1 cu.m.
0.052 Nos
25%
15.34
295.00
15.34
0.14
1 Nos
1
Total
Page 119
15.34
3.84
2.15
21.35
Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm
thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the
work site and all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310)
Cost of Gravel
Light Mazdoor
Muncipal area alloence
Add 14% over heads
1 cu.m.
0.052 Nos
25%
224.11 cu.m.
208.77
295.00
15.34
0.14
Cost of Sand
Light Mazdoor
Add 14% over heads
1 cu.m.
0.052 Nos
900.59 cu.m.
885.25
295.00
0.14
1 cu.m.
1 Nos
208.77
15.34
3.84
1 cu.m.
31.38
Rate per Cu.m.
Total
259.35
Filling with Sand Cushion under footings with initial lead in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational
& incidental charges, labour charges, seignorage charges, hire and opertaional charges of T & P etc., complete for
finished item of work. (APSS NO. 309 & 310)
1 cu.m.
885.25
1 Nos
15.34
1 cu.m.
126.08
Rate per Cu.m.
Total
1026.70
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix
(cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including
seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as
mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete,
etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)
material
Metal 40mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor
Muncipal area alloence
0.9
0.45
129.6
1.2
cu.m.
cu.m.
Kgs.
KL
1211.93
1005.25
5800.00
77.00
1 Hour
25%
1
1
1000
1
cu.m.
cu.m.
Kgs.
KL
1090.74
452.36
751.68
92.40
303.10
174.20
1 Hour
1
303.10
43.55
0.1 Nos.
1.39 Nos.
385.00
295.00
1 Each
1 Each
38.50
410.05
25%
448.55
112.14
3182.38 cu.m.
0.14
1 cu.m.
445.53
Rate per Cu.m.
Total
3740.10
Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nominal mix
(cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including
seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as
mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete,
etc., complete for finished item of work for Foundations (APSS No. 402)
material
Metal 40mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor
Muncipal area alloence
Add 14% over heads
Rate per Cu.m.
0.9
0.45
162
1.2
cu.m.
cu.m.
Kgs.
KL
1211.93
1005.25
5800.00
77.00
1 Hour
25%
0.1 cu.m.
1.39 Nos.
25%
3370.30 cu.m.
1
1
1000
1
cu.m.
cu.m.
Kgs.
KL
1090.74
452.36
939.60
92.40
303.10
174.20
1 Hour
1
303.10
43.55
385.00
295.00
448.55
0.14
1 cu.m.
1 Each
38.50
410.05
112.14
471.84
3954.30
1 cu.m.
Total
Page 120
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix
(cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed
graded metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational,
incidental, and labour charges such as mixing, laying concrete, finishing top surface, curing concrete, etc., complete
for finished item of work for Dummy Columns. (APSS No. 402)
materal
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor
Muncipal area alloence
0.9
0.45
129.6
1.2
cu.m.
cu.m.
Kgs.
KL
1564.23
1005.25
5800.00
77.00
1 Hour
25%
0.1 cu.m.
1.39 Nos.
25%
1
1
1000
1
cu.m.
cu.m.
Kgs.
KL
1407.81
452.36
751.68
92.40
303.10
174.20
1 Hour
1
303.10
43.55
385.00
295.00
448.55
1 cu.m.
1 Each
38.50
410.05
112.14
3611.59
Total
GF
FF
SF
TF
3611.59
3611.59 3611.59
3611.59
341.00
341.00
341.00
341.00
1603.00
1763.30 1923.60
2083.90
25%
400.75
440.83
480.90
520.98
0.00
44.86
89.71
134.57
5956.34
6201.57 6446.80
6692.03
Add 14% over heads
0.14
833.89
868.22
902.55
936.88
Rate per cu.m.
Total
6790.25
7069.80 7349.35
7628.95
Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6) proportion nominal mix
(cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed
graded metal from from approved quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing, laying, curing concrete, etc., complete for finished item of work for
Bed Blocks and Hold Fasts (APSS No. 402)
Rate for other Floors
Basic Rate of P.C.C(1:5:10) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Material
Graded Metal 20 to 6 mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor
Muncipal area alloence
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:3:6) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Add 14% over heads
Rate per cu.m.
0.9
0.45
220
1.2
cu.m.
cu.m.
Kgs.
KL
1564.23
1005.25
5800.00
77.00
1 Hour
25%
0.1 cu.m.
1.39 Nos.
25%
GF
4135.91
277.00
446.00
25%
111.50
0.00
4970.41
0.14 #VALUE!
Total #VALUE!
Page 121
cu.m.
cu.m.
Kgs.
KL
1407.81
452.36
1276.00
92.40
303.10
174.20
1 Hour
1
303.10
43.55
385.00
295.00
448.55
1 Each
1 Each
38.50
410.05
112.14
4135.91
FF
4135.91
277.00
490.60
122.65
44.86
5071.02
140.74
Err:522
1
1
1000
1
SF
4135.91
277.00
535.20
133.80
89.71
5171.62
0.14
Err:522
Total
TF
4135.91
277.00
579.80
144.95
134.57
5272.23
#VALUE!
#VALUE!
Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:2:4) proportion nominal mix
(cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed
graded metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing, laying, curing concrete, etc., complete for finished item of work (APSS
No. 402)
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
men &women Mazdoor
Muncipal area alloence
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:2:4) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
10
0.9
0.45
331.2
1.2
cu.m.
cu.m.
Kgs.
KL
1564.23
1005.25
5800.00
77.00
1 Hour
25%
0.1 cu.m.
1.39 Nos.
25%
1
1
1000
1
cu.m.
cu.m.
Kgs.
KL
1407.81
452.36
1920.96
92.40
303.10
174.20
1 Hour
1
303.10
43.55
385.00
295.00
448.55
1 cu.m.
1 Each
38.50
410.05
112.14
4780.87
Total
GF
FF
SF
TF
4780.87
4780.87 4780.87
4780.87
277.00
277.00
277.00
277.00
446.00
490.60
535.20
579.80
25%
111.50
122.65
133.80
144.95
0.00
44.86
89.71
134.57
5615.37
5715.98 5816.58
5917.19
Add 14% over heads
0.14
786.15
800.24
814.32
828.41
Rate per cu.m.
Total
6401.55
6516.25 6630.90
6745.60
Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine
crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of cement per
1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including steel centering, shuttering,
machine mixing, laying concrete, lift charges, curing etc., complete for finished item of work for steps (APSS No. 402
)
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
Labour
1st class Masons
Man and Mazdoor
Muncipal area alloence
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:1.5:3) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Add 14% over heads
Rate per cu.m.
0.8
0.4
380
1.2
cu.m.
cu.m.
kgs
KL
1564.23
1005.25
5800.00
77.00
1.333 Hour
1.333 Hour
25%
0.1 Nos.
1.39 Nos.
25%
25%
0.14
Total
Page 122
GF
5516.75
277.00
446.00
111.50
0.00
6351.25
889.18
7240.45
cu.m.
cu.m.
kgs
KL
1251.38
402.10
2204.00
92.40
503.90
152.20
526.40
1 Hour
1 Hour
1
671.70
202.88
131.60
385.00
295.00
448.55
1 Each
1 Each
38.50
410.05
112.14
5516.75
FF
5516.75
277.00
490.60
122.65
44.86
6451.86
903.26
7355.15
1
1
1000
1
SF
5516.75
277.00
535.20
133.80
89.71
6552.46
917.34
7469.85
TF
5516.75
277.00
579.80
144.95
134.57
6653.07
931.43
7584.55
11
Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones from
approved quarry including cost and conveyance of all materials like Granite stones, cement, sand, water, etc., to site
including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such
as cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc., complete for
finished item of work for foundation and basement (APSS No. 601 & 615)
cost of cement
59.4 Kgs
RR Stone
CR
Through stones 25 x 25x 45 to 60
cms
Sand
1st Class Mason
Light Mazdoor
Muncipal area alloence
0.5
0.44
0.16
0.33
1.2
2.0
25%
5800.00
1000 Kgs
Cum
Cum
Cum
cu.m.
Nos
Nos
670.81
670.81
670.81
1005.25
385.00
295.00
1052.00
1
1
1
1
1
1
2466.14 cu.m.
0.14
Cum
Cum
Cum
cu.m.
Each
Each
1 cu.m.
335.40
295.15
107.33
331.73
462.00
590.00
263.00
2729.14
345.26
3074.40
Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance of all materials like cement, sand,
water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental
charges and labour charges such as mixing mortar, finishing, curing, etc., complete for finished item of work. (APSS
901,906)
cost of cement
Sand
1st Class Mason
Man mazdoor
Muncipal area alloence
14
344.52
1.44
0.003
0.05
0.074
25%
Kgs
cu.m.
Nos.
Nos.
5800.00
1149.25
345.00
295.00
39.08
Material
Graded Metal 20mm to 6mm
Sand
Cement
0.8 cu.m.
0.4 cu.m.
380 kgs
1564.23
1005.25
5800.00
Water
1.2 KL
77.00
1.333 Hour
503.90
1 Hour
671.70
1.333 Hour
152.20
1 Hour
202.88
526.40
131.60
1000
1
1
1
Kgs
cu.m.
Each
Each
8.35
3.45
17.25
21.83
9.77
#REF!
Add 14% over heads
50.88 cu.m.
0.14
1 sqm
7.12
Rate per 1 Sqmt.
Or say
#REF!
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of
380 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using
Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine
mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and its fabrication
charges for finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403)
1 cu.m.
1 cu.m.
1000 kgs
1 KL
1251.38
402.10
2204.00
92.40
Machinery
LA on crew charges
manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Basic rate per Cum.
a) VRCC M20 grade design mix for footi
Basic Rate per Cum.
Centering Charges per Cum.
25%
0.133 Nos.
0.267 Nos.
4.6 Nos.
25%
385.00
345.00
295.00
1500.32
1 Each
1 Each
1 Each
Total
51.21
92.12
1357.00
375.08
6831.47
1 cu.m.
6831.47
1 cu.m.
6831.47
1 cu.m.
723.00
1 cu.m.
723.00
Page 123
25%
7665.97 cu.m.
446.00
0.14
Say
111.50
1073.24
8739.25
Say
6831.47
2410.00
268.75
1331.43
10841.65
1 cu.m.
15
1 cu.m.
1 cu.m.
25%
9510.22 cu.m.
6831.47
2410.00
1075.00
0.14
1 cu.m.
1 cu.m.
1 cu.m.
1 cu.m.
6831.47
1 cu.m.
6831.47
1 cu.m.
1025.00
1 cu.m.
1025.00
0.8
0.4
380
1.2
cu.m.
cu.m.
kgs
KL
1564.23
1005.25
5800.00
77.00
1.333 Hour
1.333 Hour
25%
0.167 Nos.
0.167 Nos.
5.6 Nos.
25%
1
1
1000
1
cu.m.
cu.m.
kgs
KL
1251.38
402.10
2204.00
92.40
503.90
152.20
526.40
1 Hour
1 Hour
1
671.70
202.88
131.60
385.00
345.00
295.00
1773.91
1 Each
1 Each
1 Each
64.30
57.62
1652.00
443.48
7173.45
Total
25%
GF
7173.45
341.00
1603.00
400.75
0.14
9518.20
1332.55
FF
SF
7173.45 7173.45
341.00
341.00
1763.30 1923.60
440.83
480.90
177.39
354.78
9895.97 10273.73
1385.44 1438.32
Total
10850.80
11281.45 11712.10
TF
7173.45
341.00
2083.90
520.98
532.17
10651.50
1491.21
12142.75
b) For Lintels
Rate for other Floors
GF
FF
7173.45
1133.00
1141.00
285.25
7173.45
1133.00
1255.10
313.78
25%
Page 124
SF
7173.45
1133.00
1369.20
342.30
TF
7173.45
1133.00
1483.30
370.83
177.39
0.14
Total
9732.70
1362.58
11095.30
Page 125
354.78
532.17
10052.72 10372.73
1407.38 1452.18
11460.15 11824.95
10692.75
1496.99
12189.75
16
Vibrated Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of
380 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using
Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine
mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402 & 403) For beams and slabs
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Basic rate per Cum.
a) For Roof Beams
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each floor
Add 14% over heads
Rate per cu.m.
0.8
0.4
380
1.2
cu.m.
cu.m.
kgs
KL
1564.23
1005.25
5800.00
77.00
0.308 Hour
0.308 Hour
25%
0.067 Nos.
0.133 Nos.
3.077 Nos.
25%
1
1
1000
1
cu.m.
cu.m.
kgs
KL
1251.38
402.10
2204.00
92.40
503.90
152.20
121.63
1 Hour
1 Hour
1
155.20
46.88
30.41
385.00
345.00
295.00
979.40
1 Each
1 Each
1 Each
25.80
45.89
907.72
244.85
5406.61
Total
25%
GF
5406.61
2002.00
1344.00
336.00
0.14
Total
9088.61
1272.41
10361.05
FF
SF
5406.61 5406.61
2002.00 2002.00
1478.40 1612.80
369.60
403.20
97.94
195.88
9354.55 9620.49
1309.64 1346.87
10664.20 10967.40
TF
5406.61
2002.00
1747.20
436.80
293.82
9886.43
1384.10
11270.55
0.075 cu.m.
25%
GF
405.50
227.00
152.00
38.00
0.14
Total
822.50
115.15
937.65
0.1 cu.m.
25%
GF
540.66
227.00
152.00
38.00
0.14
957.66
134.07
Page 126
5406.61
FF
405.50
227.00
167.20
41.80
7.35
848.85
118.84
967.70
5406.61
FF
540.66
227.00
167.20
41.80
9.79
986.45
138.10
1 cu.m.
SF
405.50
227.00
182.40
45.60
14.69
875.19
122.53
997.75
TF
405.50
227.00
197.60
49.40
22.04
901.54
126.22
1027.80
1 cu.m.
SF
540.66
227.00
182.40
45.60
19.59
1015.25
142.14
405.50
TF
540.66
227.00
197.60
49.40
29.38
1044.04
146.17
540.66
Total
1091.75
0.11 cu.m.
1124.60
1157.40
5406.61
25%
GF
594.73
227.00
152.00
38.00
0.14
Total
1011.73
141.64
1153.40
FF
594.73
227.00
167.20
41.80
10.77
1041.50
145.81
1187.35
1190.25
1 cu.m.
SF
594.73
227.00
182.40
45.60
21.55
1071.28
149.98
1221.30
594.73
TF
594.73
227.00
197.60
49.40
32.32
1101.05
154.15
1255.20
0.12 cu.m.
5406.61
25%
GF
648.79
227.00
152.00
38.00
0.14
Total
1065.79
149.21
1215.05
FF
648.79
227.00
167.20
41.80
11.75
1096.54
153.52
1250.10
1 cu.m.
SF
648.79
227.00
182.40
45.60
23.51
1127.30
157.82
1285.15
648.79
TF
648.79
227.00
197.60
49.40
35.26
1158.05
162.13
1320.20
0.12 cu.m.
5406.61
1 cu.m.
648.79
GF
648.79
FF
648.79
SF
648.79
TF
648.79
227.00
152.00
227.00
167.20
227.00
182.40
227.00
197.60
38.00
1065.79
41.80
11.75
1096.54
45.60
23.51
1127.30
49.40
35.26
1158.05
149.21
1215.05
153.52
1250.10
157.82
1285.15
162.13
1320.20
25%
0.14
Total
0.125 cu.m.
5406.61
1 cu.m.
675.83
GF
FF
SF
675.83
227.00
675.83
227.00
675.83
227.00
675.83
227.00
152.00
38.00
167.20
41.80
182.40
45.60
197.60
49.40
12.24
24.48
36.73
25%
Page 127
TF
0.14
Total
1092.83
1124.07
1155.31
1186.56
153.00
1245.85
157.37
1281.45
161.74
1317.05
166.12
1352.70
0.14 cu.m.
5406.61
1 cu.m.
756.93
GF
FF
SF
756.93
227.00
152.00
756.93
227.00
167.20
756.93
227.00
182.40
756.93
227.00
197.60
25%
38.00
41.80
13.71
45.60
27.42
49.40
41.13
0.14
1173.93
164.35
1206.64
168.93
1239.35
173.51
1272.06
178.09
Total
1338.30
1375.60
1412.90
1450.15
5406.61
TF
1 cu.m.
621.76
GF
621.76
FF
621.76
SF
621.76
TF
621.76
227.00
152.00
227.00
167.20
227.00
182.40
227.00
197.60
25%
38.00
41.80
11.26
45.60
22.53
49.40
33.79
0.14
1038.76
145.43
1069.02
149.66
1099.29
153.90
1129.55
158.14
Total
1184.20
1218.70
1253.20
1287.70
0.1 cu.m.
5406.61
1 cu.m.
540.66
GF
540.66
227.00
FF
540.66
227.00
SF
540.66
227.00
TF
540.66
227.00
152.00
167.20
182.40
197.60
38.00
41.80
45.60
49.40
9.79
19.59
29.38
25%
0.14
957.66
134.07
986.45
138.10
1015.25
142.14
1044.04
146.17
Total
1091.75
1124.60
1157.40
1190.25
0.05 cu.m.
5406.61
1 cu.m.
270.33
GF
270.33
FF
270.33
SF
270.33
TF
270.33
270.33
270.33
270.33
270.33
25%
Page 128
0.14
Total
37.85
308.20
0.175 cu.m.
25%
0.14
Total
GF
946.16
233.00
157.00
39.25
5406.61
37.85
308.20
37.85
308.20
1 cu.m.
1375.41
FF
946.16
233.00
172.70
43.18
17.14
1412.18
SF
946.16
233.00
188.40
47.10
34.28
1448.94
TF
946.16
233.00
204.10
51.03
51.42
1485.71
192.56
1568.00
197.70
1609.90
202.85
1651.80
208.00
1693.75
0.18 cu.m.
25%
GF
973.19
233.00
157.00
39.25
0.14
Total
1402.44
196.34
1598.80
0.2 cu.m.
25%
GF
1081.32
233.00
157.00
39.25
0.14
Total
1510.57
211.48
1722.10
0.225 cu.m.
25%
GF
1216.49
233.00
157.00
39.25
0.14
Total
1645.74
230.40
1876.15
Page 129
37.85
308.20
5406.61
FF
973.19
233.00
172.70
43.18
17.63
1439.70
201.56
1641.30
5406.61
FF
1081.32
233.00
172.70
43.18
19.59
1549.79
216.97
1766.80
5406.61
FF
1216.49
233.00
172.70
43.18
22.04
1687.41
236.24
1923.65
1 cu.m.
SF
973.19
233.00
188.40
47.10
35.26
1476.95
206.77
1683.75
1081.32
TF
1081.32
233.00
204.10
51.03
58.76
1628.21
227.95
1856.20
1 cu.m.
SF
1216.49
233.00
188.40
47.10
44.07
1729.06
242.07
1971.15
973.19
TF
973.19
233.00
204.10
51.03
52.89
1514.21
211.99
1726.25
1 cu.m.
SF
1081.32
233.00
188.40
47.10
39.18
1589.00
222.46
1811.50
946.16
TF
1216.49
233.00
204.10
51.03
66.11
1770.73
247.90
2018.65
1216.49
17
Reinforced Cement Concrete M 25 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite
machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand),
coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using
Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine
mixing, laying concrete, lift charges, curing etc., complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402 & 403)
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
Batchingplant 0.5 cum
LA on crew charges
manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Basic rate per Cum
a) For Lintels
Rate for other Floors
18
0.8
0.4
380
1.2
cu.m.
cu.m.
kgs
KL
1564.23
1005.25
5800.00
77.00
1.333 Hour
25%
0.167 Nos.
0.167 Nos.
5.6 Nos.
25%
cu.m.
cu.m.
kgs
KL
1251.38
402.10
2204.00
92.40
503.90
359.24
1 Hour
1
671.70
89.81
385.00
345.00
295.00
1773.91
1 Each
1 Each
1 Each
64.30
57.62
1652.00
443.48
6928.78
GF
FF
6928.78
6928.78
1133.00
1141.00
285.25
1
1
1000
1
SF
TF
6928.78
6928.78
1133.00 1133.00
1133.00
1255.10 1369.20
1483.30
25%
313.78
342.30
370.83
177.39
354.78
532.17
9488.03
9808.05 10128.06
10448.08
Add 14% over heads
0.14
1328.32
1373.13 1417.93
1462.73
Rate per Cum.
Total 10816.40
11181.20 11546.00
11910.85
Reinforced cement concrete with M 25 grade Design mix ( by weigh batching ) using 20mm size (SS 5) machine
crushed hard blasted granite graded metal (coarse aggregate) from approved quarry using a minimum quantity of
380 Kg of cement per 1 Cum of concrete including cost and conveyance of all materials like cement, fine aggregate
(sand) ,coarse aggregate, water etc. to site and cost of seigniorage charges on all materials including centering
using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering,
machine mixing, laying concrete, 7.5cm thick at fixed end and 5cm thick at free end with an average thickness of
6.25cm including labour charges for mixing, laying, curing etc., complete but excluding cost of steel and its
fabrication charges for finished item of work
for sun-shades of any width as per approved plan / design and of average thickness of 62.50mm ( thickness at
support 75mm and thickness at edge 50mm) (APSS No. 402, 403)
material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
Batchingplant 0.5 cum
LA on crew charges
manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Basic rate per Cu.m
a) Chajja / Sunshade
Cost of RCC for 62.5 mm thick
sunshade
0.8
0.4
380
1.2
cu.m.
cu.m.
kgs
KL
1564.23
1005.25
5800.00
77.00
0.308 Hour
25%
0.067 Nos.
0.133 Nos.
3.077 Nos.
25%
0.0625 cu.m.
Page 130
cu.m.
cu.m.
kgs
KL
1251.38
402.10
2204.00
92.40
503.90
83.01
1 Hour
1
155.20
20.75
385.00
345.00
295.00
979.40
1 Each
1 Each
1 Each
Total
25.80
45.89
907.72
244.85
5350.08
1 cu.m.
334.38
5350.08
1
1
1000
1
GF
FF
SF
25%
334.38
224.00
175.00
43.75
334.38
224.00
192.50
48.13
6.12
334.38
224.00
210.00
52.50
12.24
334.38
224.00
227.50
56.88
18.36
0.14
Total
777.13
108.80
885.95
805.13
112.72
917.90
833.12
116.64
949.80
861.12
120.56
981.70
TF
20
0.05 cu.m.
25%
GF
267.50
227.00
152.00
38.00
0.14
Total
684.50
95.83
780.35
0.025 cu.m.
GF
133.75
227.00
152.00
25%
38.00
0.14
Total
550.75
77.11
627.90
5350.08
1 cu.m.
FF
267.50
227.00
167.20
41.80
4.90
708.40
99.18
807.60
SF
267.50
227.00
182.40
45.60
9.79
732.29
102.52
834.85
5350.08
FF
133.75
227.00
167.20
41.80
2.45
572.20
80.11
652.35
1 cu.m.
SF
TF
133.75
133.75
227.00
227.00
182.40
197.60
45.60
49.40
4.90
7.35
593.65
615.10
83.11
86.11
676.80
701.25
267.50
TF
267.50
227.00
197.60
49.40
14.69
756.19
105.87
862.10
133.75
Pointing to Cuddapah / Shahabad slabs in CM(1:3) Prop: including cost and conveyance of all materials like
cost of cement for Cement Mortar (1:3)
0.96 Kgs
5.80
1 Kgs
5.57
cost of sand for Cement Mortar (1:3)
0.002 cu.m.
1005.25
1 cu.m.
1st Class Mason
0.048 Nos.
385.00
1 Each
18.48
2nd Class Mason
0.112 Nos.
345.00
1 Each
38.64
Man mazdoor
0.05 Nos.
295.00
1 Each
14.75
Woman mazdoor
0.11 Nos.
295.00
1 Each
32.45
Rate per 1 Sqmt.
Total
109.85
Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from approved source having
minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand, bricks,
water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc.,
complete for finished item of work. (APSS No. 501 & 504).
wall thickness
Material
Cement
Second class Bricks
sand for mortor
B Labour
1st class mason
2nd class mason
Man Mazdoor
0.225
36 kgs
512 Nos
0.2 cu.m.
5800.00
5095.67
1005.25
1000 kgs
1000 Nos
1 cu.m.
208.80
2608.98
201.05
0.24 Nos.
0.56 Nos.
385.00
345.00
1 Each
1 Each
92.40
193.20
1.89 Nos.
295.00
1 Each
557.55
Page 131
21
843.15
210.79
4072.77
FF
SF
TF
4072.77 4072.77
4072.77
44.13
44.13
44.13
369.02
477.29
585.60
25%
92.26
119.32
146.40
84.32
168.63
252.95
4442.79
4662.50 4882.14
5101.85
Add 14% over heads
0.14
621.99
652.75
683.50
714.26
Rate per Cum.
Total
5064.80
5315.30 5565.65
5816.15
Reinforced Brick Masonry 11.5cm (4 1/2") thick for partition walls in CM (1:4) prop: using second class bricks
from approved source having minimum crushing strength of 40 Kg/Sqcm. and placing 2nos. of 6mm dia MS bars
embedded in every 3rd layer with free ends of reinforcement keyed into mortar joints of the main brick work
whereever applicable including cost and conveyance of all materials like cement, sand, bricks, water etc., to site,
seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing
cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., but excluding cost and conveyance
of steel and its fabrication charges complete for finished item of work. (APSS No. 501 & 504).
wall thickness
Material
Cement
Second class Bricks
sand for mortor
B Labour
1st class mason
22
25%
GF
4072.77
44.13
260.71
65.18
0.115
7.56 kgs
51.2 Nos
0.021 cu.m.
5800.00
5095.67
1005.25
1000 kgs
1000 Nos
1 cu.m.
43.85
260.90
21.11
0.06 Nos.
385.00
1 Each
23.10
0.06 Nos.
0.275 Nos.
25%
345.00
295.00
124.93
1 Each
1 Each
20.70
81.13
31.23
482.01
Wall thickness
Material
0.225
FF
SF
TF
482.01
482.01
482.01
9.93
9.93
9.93
83.03
107.39
131.76
25%
20.76
26.85
32.94
12.49
24.99
37.48
565.27
608.22
651.17
694.12
Add 14% over heads
0.14
79.14
85.15
91.16
97.18
Rate per One Sqmt.
Total
644.45
693.40
742.35
791.35
Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with
compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement,
sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges,
lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
GF
482.01
9.93
58.66
14.67
110 Nos
18 Kgs
0.1 cu.m.
0.42
0.92
0.7
2.1
25%
cu.m.
Nos.
Nos.
Nos.
GF
4557.70
44.13
260.71
Page 132
24740.03
5.80
1005.25
1000 Nos
1 Kgs
1 cu.m.
385.00
345.00
295.00
295.00
1305.10
1
1
1
1
FF
4557.70
44.13
369.02
SF
4557.70
44.13
477.29
cu.m.
Each
Each
Each
TF
4557.70
44.13
585.60
2721.40
104.40
100.53
161.70
317.40
206.50
619.50
326.28
4557.70
65.18
0.14
Total
4927.72
689.88
5617.65
92.26
130.51
5193.62
727.11
5920.75
119.32
261.02
5459.46
764.32
6223.80
146.40
391.53
5725.36
801.55
6526.95
Brick Masonry in superstructure with CM (1:6) prop: using Fly ASH Bricks of size 290x225x140mm with
compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement,
sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges,
lift charges, curing, etc., complete for finished item of work. for basement (APSS No. 501 & 504).
Wall thickness
Material
Fly Ash Bricks 290x225x140mm
Cement for Cement Mortar (1:8)
Sand for Cement Mortar (1:8)
Labour
1st class mason
2nd class mason
Man Mazdoor
Woman Mazdoor
Muncipal area alloence
total
Add 14% over heads
Basic Rate per Cum.
24
25%
0.225
110 Nos
24 Kgs
0.1 cu.m.
0.42
0.92
0.7
2.1
25%
cu.m.
Nos.
Nos.
Nos.
24740.03
5.80
1005.25
385.00
345.00
295.00
295.00
1305.10
1000 Nos
1 Kgs
1 cu.m.
1
1
1
1
cu.m.
Each
Each
Each
0.14
2721.40
139.20
100.53
161.70
317.40
206.50
619.50
326.28
4592.50
642.95
5235.50
Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop: Fly Bricks of size
290x100x140mm with compressive of 50 Kgs / Sqcm from approved source and placing 2nos. of 6mm dia MS bars
embedded in every 3rd layer with free ends of reinforcement keyed into mortar joints of the main brick work
whereever applicable including cost and conveyance of all materials like cement, sand, bricks, water etc., to site,
seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing
cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., but excluding cost and conveyance
of steel and its fabrication charges complete for finished item of work. (APSS No. 501 & 509).
Material
Fly Ash Bricks 290x100x140mm
24 Nos
11702.95
1000 Nos
280.87
7.2 Kgs
5.80
Kgs
41.76
25
0.02 cu.m.
1005.25
1 cu.m.
20.11
0.06 cu.m.
0.06 Nos.
0.275 Nos.
385.00
345.00
295.00
1 cu.m.
1 Each
1 Each
23.10
20.70
81.13
467.66
GF
467.66
9.93
58.66
14.67
FF
SF
TF
467.66
467.66
467.66
9.93
9.93
9.93
83.03
107.39
131.76
25%
20.76
26.85
32.94
12.49
24.99
37.48
550.92
593.87
636.82
679.77
Add 14% over heads
0.14
77.13
83.14
89.15
95.17
Rate per One Sqmt.
Total
628.10
677.05
726.00
774.95
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to 40mm
diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and
binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost
and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover
blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as
cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished
item of work (APSS No.126) in all floors.
Page 133
Material
Cost of steel including 5% wastage and
overlaps
cost of binding wire
Labour
Blacksmith/Tin Smith/Rivetor
Light mazdoor
Muncipal area alloence
Rate per MT
Rate for other Floors
Basic rate per MT
Lift Charges per MT @10% extra on
labour per floor
26
28000.00
1 MT
29400.00
6 Kg
70.00
1 Kg
420.00
10 Nos
10 Nos
25%
GF
38320.00
385.00
295.00
6800.00
1 Nos
1 Nos
FF
SF
38320.00 38320.00
680.00 1360.00
Total
TF
38320.00
2040.00
3850.00
2950.00
1700.00
38320.00
27
1.05 MT
1.05 MT
44000.00
1 MT
46200.00
6 Kg
70.00
1 Kg
420.00
10 Nos
10 Nos
25%
GF
55120.00
0.14
Total
55120.00
7716.80
62836.80
385.00
295.00
6800.00
1 Nos
1 Nos
FF
SF
55120.00 55120.00
680.00 1360.00
62895.00 56481.00
8805.30 7907.34
71700.30 64388.35
Total
TF
55120.00
2040.00
57160.00
8002.40
65162.40
3850.00
2950.00
1700.00
55120.00
Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick
in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site,
seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in
- charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 &
904)
Material
Base coat 8mm thick in C.M. (1:5)
Cement
3.17 kgs
5800.00
0.011 cu.m.
1149.25
1.92 kgs
5800.00
0.004 cu.m.
1149.25
1 cu.m.
4.60
Labour
1st Class Mason
2nd Class Mason
Light mazdoor
Muncipal area alloence
Basic rate per 1 Sqmt.
0.063 Nos.
0.147 Nos.
0.39 Nos.
25%
385.00
345.00
295.00
190.02
1 Each
1 Each
1 Each
24.26
50.72
115.05
47.51
284.29
1000 kgs
1 cu.m.
18.39
12.64
Page 134
1000 kgs
11.14
28
GF
284.29
2.37
FF
284.29
2.37
SF
284.29
2.37
TF
284.29
2.37
11.95
16.75
21.54
26.33
2.99
4.19
19.00
5.39
38.00
6.58
57.01
301.60
326.60
351.59
376.58
Add 14% over heads
0.14
42.22
45.72
49.22
52.72
Rate per 1 Sqmt.
Total
343.82
372.32
400.81
429.30
Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM
(1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site,
seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in
- charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 &
904)
Material
Base coat 8mm thick in C.M. (1:6)
Cement
cost of sand for mortor
Top Coat 4mm thick in C.M. (1:4)
Cement
cost of sand for mortor
Labour
1st Class Mason
2nd Class Mason
Light mazdoor
Muncipal area alloence
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of access scafflding pers
qm
Labour charges for access scaffolding
per sqm
Add LA on Labour for scaffolding
Lift charges @ 10% extra on each floor
25%
2.64 kgs
0.011 cu.m.
5800.00
1149.25
1000 kgs
1 cu.m.
15.31
12.64
1.44 kgs
0.004 cu.m.
5800.00
1149.25
1000 kgs
1 cu.m.
8.35
4.60
0.04 Nos.
0.1 Nos.
0.26 Nos.
25%
385.00
345.00
295.00
126.60
1 Each
1 Each
1 Each
15.40
34.50
76.70
31.65
199.15
GF
199.15
0.99
FF
199.15
0.99
SF
199.15
0.99
TF
199.15
0.99
5.87
8.30
10.74
13.18
25%
1.47
2.08
19.00
2.69
38.00
3.30
57.01
0.14
Total
207.48
29.05
236.55
229.52
32.13
261.70
251.57
35.22
286.80
273.63
38.31
311.95
Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4mm thick in CM
(1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site,
seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing
mortar,scaffolding charges, lift charges, finishing,including cutting of Grooves wherever necessary as directed by
Engineer - in - charge, curing, etc., complete for Uneven Surfaces of Brick Wall for finished item of work.
(APSS 901,903 & 904)
Base coat 16 mm thick in C.M. (1:6)
Cement
cost of sand for mortor
Top Coat 4mm thick in C.M. (1:4)
Cement
cost of sand for mortor
Labour
4.32 kgs
0.018 cu.m.
5800.00
1149.25
1000 kgs
1 cu.m.
25.06
20.69
1.44 kgs
0.004 cu.m.
5800.00
1149.25
1000 kgs
1 cu.m.
8.35
4.60
0.063 Nos.
0.147 Nos.
385.00
345.00
1 Each
1 Each
24.26
50.72
Page 135
30
31
Light mazdoor
Muncipal area alloence
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of access scafflding pers
qm
Labour charges for access scaffolding
per sqm
Add LA on Labour for scaffolding
Lift charges @ 10% extra on each floor
0.39 Nos.
25%
5.4 kg
0.015 cu.m.
0.06 Nos.
0.096 Nos.
25%
295.00
190.02
1 Each
115.05
47.51
296.22
GF
296.22
0.99
FF
296.22
0.99
SF
296.22
0.99
TF
296.22
0.99
5.87
8.30
10.74
13.18
25%
1.47
2.08
2.69
3.30
19.00
38.00
57.01
304.55
326.59
348.64
370.70
Add 14% over heads
0.14
42.64
45.72
48.81
51.90
Rate per 1 Sqmt.
Total
347.20
372.35
397.45
422.60
Ornamental Plastering with CM(1:4) Prop: 12mm thick in single coat including cost and conveyance of all
materials like cement, sand, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete for finished
item of work. (APSS 901,906)
5.80
1149.25
385.00
295.00
51.42
31.32
kg
1 cu.m.
1 Each
1 Each
17.24
23.10
28.32
12.86
112.85
Total
FF
SF
TF
112.85
112.85
112.85
0.99
0.99
0.99
8.30
10.74
13.18
25%
2.08
2.69
3.30
5.14
10.28
15.43
121.18
129.36
137.55
145.75
Add 14% over heads
0.14
16.97
18.11
19.26
20.41
Rate per 1 Sqmt.
Total
138.15
147.50
156.85
166.20
Plastering with CM(1:4) Prop: 20mm thick in single coat including cost and conveyance of all materials like
cement, sand, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational,
incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906)
cost of cement for Cement Mortar (1:4)
GF
112.85
0.99
5.87
1.47
7.56 kg
5.80
0.021 cu.m.
0.094 Nos.
0.16 Nos.
25%
25%
GF
172.25
0.99
5.87
1.47
0.14
Total
180.58
25.28
205.90
Page 136
1149.25
385.00
295.00
83.39
FF
172.25
0.99
8.30
2.08
8.34
191.96
26.87
218.85
43.85
kg
1 cu.m.
1 Each
1 Each
SF
172.25
0.99
10.74
2.69
16.68
203.35
28.47
231.85
Total
TF
172.25
0.99
13.18
3.30
25.02
214.74
30.06
244.80
24.13
36.19
47.20
20.85
172.25
32
33
34
Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average)
mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-in-charge at
1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement, sand,
water proofing compound, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar, laying, rounding off at junctions of wall and slab, rendering
smooth with thread lining, curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903).
cost of cement for Cement Mortar (1:3)
sand for Cement Mortar (1:3)
Water proof compound
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each floor
10.08
0.021
0.2
0.066
0.154
0.37
25%
0.14
Say
kg
cu.m.
Kgs
Nos.
Nos.
Nos.
GF
327.61
327.61
45.87
373.50
5.80
1149.25
52.00
385.00
345.00
295.00
187.69
1
1
1
1
1
1
FF
327.61
16.23
343.84
48.14
392.00
SF
327.61
32.46
360.07
50.41
410.50
kg
cu.m.
Kgs
Each
Each
Each
58.46
24.13
10.40
25.41
53.13
109.15
46.92
327.61
TF
327.61
48.68
376.29
52.68
429.00
Page 137
35
2.16 kg
1048.00
5.80
0.012 cu.m.
1 Sqmt.
0.096
0.224
0.22
0.11
0.14
Total
Nos.
Nos.
Nos.
Nos.
GF
1446.43
1446.43
202.50
1648.95
1005.25
109.85
1 Sqmt.
1
12.53
kg
1 cu.m.
1 Sqmt.
385.00
345.00
295.00
295.00
1
1
1
1
FF
1446.43
21.16
1467.59
205.46
1673.10
SF
1446.43
42.32
1488.75
208.43
1697.20
1100.40
Each
Each
Each
Each
12.06
109.85
36.96
77.28
64.90
32.45
1446.43
TF
1446.43
63.48
1509.91
211.39
1721.35
with length
equal to flooring
set over
basewithPolished
coat of CM (1:3),
cementof
slurry
of honey
Providing
skirting
internal stones
walls 12.5
Cm ahigh
Black 12mm
Kadapathick
slabswith
minimum
15 mm
thick like
consistency
spread @with
3.3 length
Kgs per
sqmtoand
jointedstones
with neat
cement
paste
mixed
with
pigment
matching
shade to
(0.457M x 0.457M)
equal
flooring
set over
a base
coat
of CM
(1:3),
12mmofthick
with cement
full depth
(jointslike
of stone
shouldspread
be flushed),
costand
andjointed
conveyance
of allcement
materials
like
cement,
water,
slurry
of honey
consistency
@ 3.3 including
Kgs per sqm
with neat
paste
mixed
withsand,
pigment
of
flooring stones
to site,
seigniorage
charges,
salesbeand
other taxes
on allcost
materials,
all operational,
and
matching
shadeetc.
to full
depth
(joints of stone
should
flushed),
including
and conveyance
of all incidental
materials like
labour
such as
dressing
of flooring
stones
to the required
sizes,
mixing
of cement
laying, jointing,
cement,charges
sand, water,
flooring
stones
etc. to site,
seigniorage
charges,
sales
and other
taxes mortar,
on all materials,
all
curing, lift charges
etc.,and
complete
finished
of work.(APSS
No.701
& to
707)
operational,
incidental
labour for
charges
suchitem
as dressing
of flooring
stones
the required sizes, mixing of cement
mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.701 & 707)
Material
Cost of Polished Black Kadapa slabs
minimum of 15 mm thick (0.457M x
0.457M)
sand for Cement Mortar (1:3)
cement for Cement Mortar (1:3) base
coat
Cement for slurry
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Add water charges @1% on labour
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each floor
36
1.05 Sqmt.
1.1 Sqmt.
225.85
1 Sqmt.
248.44
0.012 cu.m.
5.76 Kgs
3.3 Kgs
1005.25
5800.00
5800.00
1 cu.m.
1000 Kgs
1000 Kgs
12.06
33.41
19.14
0.096 Nos.
0.224 Nos.
0.31 Nos.
25%
1%
385.00
345.00
295.00
205.69
205.69
1 Each
1 Each
1 Each
36.96
77.28
91.45
51.42
2.06
572.22
GF
572.22
FF
572.22
20.77
592.99
83.02
676.05
SF
572.22
41.55
613.77
85.93
699.70
TF
572.22
62.32
634.54
88.84
723.40
572.22
Add 14% over heads
0.14
80.11
Rate per 1 Sqmt.
Total
652.35
in Single piece with the edges flat fixing of
nosed and and
set fixing
over aofbase
coat of
CMKadapa slabs minimum of 15 mm thick (0.457M x 0.457M) in Single piece
Supplying
Polished
Black
(1:3),the12mm
thick,
fixing
with
edges flat
nosedand
and set
over ainbase coat of CM (1:3), 12mm thick, and fixing in position with neat cement
position
with cost
neat
cement paste
paste including
and conveyance
of all materials like cement, sand, water, stones etc. to site, seigniorage charges,
including
cost taxes
and on
conveyance
of all operational, incidental and labour charges such as dressing of stones to the
sales
and other
all materials,
materialssizes,
likemixing
cement,
sand, mortar,
water, fixing in position, curing, lift charges etc., complete for finished item of
required
of cement
stones
etc.raisers
to site,
seigniorage
work For
(APSS
No.701 charges,
& 707)
sales and other taxes on all materials, all
operational, incidental and labour
For
Raisers
Mt. of
Height
charges
such of
as 0.15
dressing
stones to the
Material
required sizes, mixing of cement
1.1 Sqmt.
225.85
1 Sqmt.
248.44
Cost
of fixing
Polished
Black Kadapa
mortar,
in position,
curing,slabs
lift
minimum
of complete
15 Mortar
mm thick
(0.457M
x
charges
for
finished
item
sand for etc.,
Cement
(1:3)
0.012 cu.m.
1005.25
1 cu.m.
12.06
0.457M)
of
work for
ForCement
raisers Mortar
(APSS No.701
&
5.76 Kgs
5800.00
1000 Kgs
33.41
cement
(1:3) base
707)
coat
Cement for slurry
3.3 Kgs
5800.00
1000 Kgs
19.14
Page 138
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Flat nosing edges as per BMM-V.14
Add water charges @1% on labour
Basic rate per 1 Sqmt.
Rate for other Floors
0.096
0.224
0.31
13.33
1%
Nos.
Nos.
Nos.
Rmt.
37
1
1
1
1
GF
FF
SF
627.44
627.44
20.77
648.21
90.75
738.96
627.44
41.55
668.99
93.66
762.65
627.44
87.84
715.28
0.14
385.00
345.00
295.00
8.00
205.69
Each
Each
Each
Rmt.
36.96
77.28
91.45
106.64
2.06
627.44
TF
627.44
62.32
689.76
96.57
786.33
0.1 day
0.00
1 day
25%
0.00
0.00
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Flat nosing edges
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each floor
38
0.31
0.11
0.086
6.67
Nos.
Nos.
Nos.
Rmt.
385.00
345.00
295.00
8.00
1
1
1
1
Each
Each
Each
Rmt.
119.35
37.95
25.37
53.36
588.20
FF
SF
TF
588.20
588.20
588.20
18.27
36.53
54.80
588.20
606.47
624.73
643.00
Add 14% over heads
0.14
82.35
84.91
87.46
90.02
Rate per Sqmt.
Say
670.55
691.38
712.19
733.02
In - situ - Granolithic Concrete Flooring 20mm thick with CC(1:1:2) Prop: using 6mm to 12mm size HBG machine
crushed metal laid monolithically over 100mm thick CC flooring bed (1:5:10) with 40mm HBG metal in alternate
panels of size not exceeding 1.50m x 1.50m and finishing the top surface to required smoothness and slopes, thread
lining as directed by the Engineer - in - charge including cost and conveyance of all materials like cement, sand, water,
etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges
such as mixing of cement concrete, laying, curing, lift charges etc., complete for finished item of work (APSS
No.701 & 710)
6mm to 12mm HBG metal
Sand
Cement
PCC bed (1:5:10) 100mm thick
1st Class Mason
2nd Class Mason
Manand women Mazdoor
Add 14% over heads
GF
588.20
0.017
0.0085
12
0.10
0.125
0.006
0.3
cum
cum
Kgs
cum
Nos.
Nos.
Nos.
0.14
Page 139
1289.26
1005.25
5800.00
3182.38
385.00
345.00
295.00
557.00
1
1
1000
1
1
1
1
cum
cum
Kgs
cum
Each
Each
Each
21.92
8.54
69.60
318.24
48.13
2.07
88.50
557.00
77.98
39
1.05
0.012
2.16
3.3
0.2
Sqmt.
cum
Kgs
Kgs
Kgs
465.00
1005.25
5800.00
5800.00
29.00
1
1
1000
1000
1
Sqmt.
cum
Kgs
Kgs
Kgs
488.25
12.06
12.53
19.14
5.80
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Muncipal area alloence
Add water charges @1% on labour
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each floor
40
0.096 Nos.
0.224 Nos.
0.33 Nos.
25%
1%
GF
804.38
385.00
345.00
295.00
211.59
211.59
FF
804.38
21.37
1 Each
1 Each
1 Each
SF
804.38
42.74
36.96
77.28
97.35
52.90
2.12
804.38
TF
804.38
64.11
804.38
825.75
847.12
868.49
Add 14% over heads
0.14
112.61
115.61
118.60
121.59
Rate per Sqmt.
917.00
941.40
965.75
990.10
Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by Engineer - in - charge
and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with
white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like
cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as mixing
of cement mortar, laying in position, curing, lift charges etc., complete for finished item of work (APSS No.701 &
707) in All Floors
white glazed tiles
1.05 Sqmt
Grey cement
White cement
Cement for Cement Mortar CM (1:5)
Sand Mortar CM (1:5)
0.33
0.6
3.45
0.012
348.00
Kgs
Kgs
Kgs
Cum
5800.00
29.00
5.80
1005.25
0.077 Nos.
Man Mazdoor
Muncipal area alloence
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each floor
0.08 Nos.
25%
0.14
1 Sqmt
1000
1
1
1
365.40
Kgs
Kgs
Kgs
Cum
1.91
17.40
20.01
12.06
385.00
1 Each
29.65
295.00
53.25
1 Each
23.60
13.31
483.34
Labour
1st Class Mason
GF
483.34
483.34
67.67
FF
483.34
5.32
488.66
68.41
SF
483.34
10.65
493.99
69.16
TF
483.34
15.97
499.31
69.90
551.05
557.10
563.15
569.25
Supplying and fixing of false ceiling using Plaster of Paris Boards 10 mm thick with standard GI ceiling angles,
sections perimeter channels including cost and conveyance of all materials and labour charges etc complete
Initial Rate as per MBT-M.54
Add 14% over heads
1 Sqm
367.00
Page 140
367.00
0.14
1 Sqm
1
367.00
51.38
418.38
Painting to Internal Walls with two coats of Plastic Emulsion paint of Asian / Berger / Nerolac / Saicoat / Endocem or
equalent quality of approved brand and shade as approved by the Engineer - in - Charge over HI-BOND Wall Putty
Super Fine (Water Resistant) or Smooth crack free, water resistant finish plaster Wall strong WP/ Zoritek WP or
Equivalentand base coat of cement primer water base grade -II exterior making three coats in all to give an even shade
after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all
materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all
operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished
item of work in all floors for external Walls.(APSS No. 911)
Primary coat
Lappum
0.1
Kg 300.00
1 kg
30.00
0.07
ltrs 255.00
1 ltr
17.85
0.021
Nos 385.00
each
8.09
2 nd class painter
0.049
Nos 345.00
each
16.91
0.25
24.99
6.25
0.09
ltrs 261.00
1 ltr
23.49
1 st class painter
0.036
Nos 385.00
each
13.86
2 nd class painter
0.084
Nos 345.00
each
28.98
0.25
42.84
10.71
156.13
0.14
21.86
total
177.99
Painting with weather proof plastic emulson grade -1 paint to interior and exterior faces of 2 coats of approved make
shade and colour including self prime coat including cost and conveyence of all materials like plastic emulsinn paint
of Grade-1 to site including cost of brushes scaffolding charges, lifiting charges and labour charges such as preparing
the wall applying three coats of plastik emlsion etc., complete for finished item of work (APSS No 910,911 7 1201) in
all floors
Plastic emulsion paint Grade-1
0.09
ltrs 261.00
1 ltr
23.49
1 st class painter
0.036
Nos 385.00
each
13.86
2 nd class painter
0.084
Nos 345.00
each
28.98
0.25
42.84
10.71
77.04
0.14
Assistant Engineer
Kothagudem
10.79
total
Page 141
87.83
Executive Engineer
PR Division Kothagudem
Qty
Description of Item
Rate
Unit
Per
Amount
1.22
2.13
2.6
=
=
0.03195
0.00915
cum
cum
0.04110
cum
2.28
sqm
a)MATERIAL
0.03195 Cost of Sal wood scantling of size 2.0 to 3.0 M
48543.00
Cum
1550.95
48543.00
Cum
444.17
2.28
6.00
Flush door shutters, solid bond wood block board type with commercial ply on
both faces.: 35 mm thick conforming to IS:2202 of ANAND/ RAAVILA/ KUTTY/
STANDARD/ SHUBHDWAR/ ITP (BMT-N.17)
MS Hold Fasts
844.00
15.00
1
1
Sqm
Each
1924.32
90.00
1.00
164.00
Each
164.00
2.00
68.00
Each
136.00
2.00
46.00
Each
92.00
6.00
31.00
Each
186.00
1.00
56.00
Each
56.00
2.00
46.00
Each
92.00
0.22
Carpenter class I
380.00
day
82.93
0.51
Carpenter class II
320.00
day
162.95
0.36
Light mazdoor
280.00
day
101.27
2.28
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
Add 25% agency allowence
295.00
Sqm
672.60
1019.75
Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door
Shutter Solid Bond Wood black board type with commercial ply on both faces
of 35mm thick including cost of fixtures such as M.S.Powder Coated Tower
Bolts 250mm long 2 Nos, Alluminimum Handles 150mm long 2 Nos, 300mm
1
long M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt
hinges 6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of
all materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
DOOR SIZE 1.22 x 2.13 mtrs : Area = 2.60 Sqm
Sal Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
Horizental 1 x 1.22 x 0.075 x 0.10
0.25
Add overheads @
Rate per / Each
Page 142
14%
254.94
6010.13
841.42
6851.55
Supply and Fixing of Door with Single leaf shutter, Door Size 0.76x2.13 mtrs
with Sal Wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 150mm
long 1 Nos, M.S.Powder Coated Handels 150mm long 1 No, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt
hinges 3 Nos, 250 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Fixing in position of M.S.Powder Coated Sheet 24
guage of full width of shutter to a height of 0.60 mtrs for interior face and 0.15
mtrs to external face , Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complte for finsihed item of
work.
DOOR SIZE 0.76 x 2.13 mtrs : Area =
0.76
Salwood Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
0.03195
Horizental 1 x 0.76 x 0.075 x 0.10
=
0.00570
Total
=
0.03765
35mm thick flush door shutter of soild wood block board type with commercial
play on both faces
1x0.63x2.05 = 1.30 Sqm
1.29
ABSTRACT
a)MATERIAL
0.03195 Cost of Sal wood scantling of size 2.0 to 3.0 M
48543.00
0.00570 Cost of Sal wood scantling of size up to 2.0 M
48543.00
1.29
6.00
1.00
1.00
2.00
3.00
1.00
0.48
0.20
0.47
0.33
1.29
0.25
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of MS-Powder Coated Tower Bolt-10 mm Bolt (IS:204) 150 mm Long
(BMT-G.15)
Cost of MS-Powder Coated Aldrop (IS:2681) 250 mm long(BMT-G.44)
Cost of 150mm Long M.S.Powder Coated Handles (BMT-G.36)
Cost of 125mm long M.S.Powder Coated but hinges (BMT-G29)
Cost of MS-Powder Coated Flat Latches: 250 mm long (BMT-G.51)
Cost of 24 guage Alluminium Sheet (BMS-W.18)
a) LABOUR
Carpenter class I
Carpenter class II
Light mazdoor
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
Add 25% agency allowence
Add overheads @
2.13
1.62
1
1
Cum
Cum
1550.95
276.70
844.00
10.00
1
1
Sqm
Each
1088.76
60.00
27.00
104.00
34.00
23.00
39.00
262.00
1
1
1
1
1
1
Each
Each
Each
Each
Each
Sqm
27.00
104.00
68.00
69.00
39.00
125.76
380.00
320.00
280.00
1
1
1
day
day
day
75.97
149.27
92.77
295.00
Sqm
380.55
698.56
174.64
4282.37
599.53
4881.90
48543.00
48543.00
1
1
2020.91
2117.14
8287.30
706.45
706.45
176.61
5021.11
cum
cum
cum
sqm
14%
Supply and Fixing of Window with Double leaf shutter, Window Size 1.20x1.35
mtrs with Sal Wood Frame and shutters including cost of fixtures such as
M.S.Powder Coated Tower Bolts 150mm long 6 Nos, 125mm long
M.S.Powder Coated butt hinges 6 Nos, including cost and convenyance of all
materials to site all Labour charges such as Fixing of Window Frame on shutter
Fixing in position , with Hardware fixtures etc., complte for finsihed item of
work.
Wood
0.04163 Salwood(Frames) (1.61C.Ft/35.31=0.046Cum)
0.04361 Salwood(Shutters) (2.1C.Ft/35.31=0.059Cum)
Labour
0.08524 Labour, wrought and putup in position frames & shutters altogether(vide
Standarad
Specifivcation)
0.25
Add 25% agency
allowence
Furniture
31.22
4.00
6.00
6.00
43.00
52.00
35.00
31.00
Add overheads @
Page 143
14%
1
1
1
1
1342.46
208.00
210.00
186.00
6967.57
975.46
7943.03
4
1
2
Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13 mtrs
with Sal Wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS Powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt
hinges 6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of
all materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
DOOR SIZE 1.05 x 2.13 mtrs : Area =
1.05
Sal Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
0.03195
Horizental 1 x 1.05 x 0.075 x 0.10
=
0.00788
Total
=
0.03983
35mm thick flush door shutter of soild wood block board type with commercial
play on both faces
1x0.95x2.05 = 1.947 Sqm
1.95
ABSTRACT
a)MATERIAL
0.03195 Cost of Sal wood scantling of size 2.0 to 3.0 M
48543.00
0.00788 Cost of Sal wood scantling of size up to 2.0 M
48543.00
3
4
5
6
7
8
9
10
1.95
6.00
1.00
2.00
2.00
6.00
1.00
2.00
11
12
13
0.21
0.49
0.35
1.95
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long M.S.Powder Coated Aldrops(BMT-G.45)
Cost of 250 long M.S.Powder Coated Towerbolts (BMT-G.17)
Cost of 150mm Long M.S.Powder Coated Handles (BMT-G.36)
Cost of 125mm long M.S.Powder Coated but hinges (BMT-G29)
Cost of Flat latch M.S.Powder Coated 300long (BMT-G.52)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Carpenter class I
Carpenter class II
Light mazdoor
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
Add overheads @
2.13
2.24
1
1
Cum
Cum
1550.95
382.28
844.00
10.00
124.00
51.00
34.00
23.00
50.00
34.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
1645.80
60.00
124.00
102.00
68.00
138.00
50.00
68.00
380.00
320.00
280.00
1
1
1
day
day
day
80.36
157.90
98.13
295.00
Sqm
575.25
cum
cum
cum
sqm
5100.67
714.09
5814.80
14%
Page 144
0.9
0.03195
0.00750
0.03945
cum
cum
cum
1.79
sqm
48543.00
2.13
1.92
Cum
1550.95
3
4
5
1.79
6.00
1.00
6
7
8
2.00
1.00
6.00
9
10
1.00
2.00
11
12
13
0.21
0.49
0.35
1.79
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long M.S.Powder Coated Aldrops(BMT-G.45)
Cost of MS-Powder Coated Tower Bolt-10 mm Bolt (IS:204) 200 mm Long
(BMT-G.16)
Cost of 150mm Long M.S.Powder Coated Handles (BMT-G.36)
Cost of 125mm long M.S.Powder Coated but hinges (BMT-G29)
Cost of Flat latch M.S.Powder Coated 300long (BMT-G.52)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Carpenter class I
Carpenter class II
Light mazdoor
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
14
Add overheads @
48543.00
Cum
364.07
844.00
10.00
134.00
1
1
1
Sqm
Each
Each
1510.76
60.00
134.00
41.00
37.00
25.00
1
1
1
Each
Each
Each
82.00
37.00
150.00
54.00
37.00
1
1
Each
Each
54.00
74.00
380.00
320.00
280.00
1
1
1
day
day
day
79.60
156.41
97.20
295.00
Sqm
528.05
4878.04
682.93
5561.00
14%
1 rmt
303.00
Add overheads @
Rmt
303.00
14%
303.00
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have
a coat of steel primers of approved make and manufacture. M.S. frame shall
be covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail &
bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC
sheet as gap insert for top rail & bottom rail. Panelling of 10mm thick PVC
sheet to be fitted in the M.S. frame welded / sealed to the stiles & rails with
30mm wide x 5mm thick PVC sheet beading on either side, and joined together
with solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm
width is to be stuck on the interior side of the C Channel using PVC solvent
adhesive. Complete as per direction of Engineer-in-charge, manufacturers
specification & drawing for finished item of work .
2205.00
14%
sqm
2205.00
2205.00
Page 145
a)
4450
SQM
Total
14%
b)
4450.00
-427.00
400.00
4423.00
4423.00
5050.00
-427.00
400.00
5023.00
Total
14%
5023.00
Supply and Fixing of Ventilator of size 1.22 x 0.45 with 25mm x 25mm x 3mm
thick equal L angles and 10mm square rods @ 150mm c/c fixing in position
,complete for finsihed item of work
1.2
0.45
0.54
0.90
2.40
0.30
3.60
m
m
m
3.96
Kgs
Kgs
=
=
total
3.15
2.40
5.55
4.357
44.50
Cum
370.10
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
149.70
29.11
548.91
76.85
625.75
ABSTRACT
a)MATERIAL
8.32
a) LABOUR
8.32
8.32
Page 146
Page 147
Supply and Fixing of Ventilator of size 1.00 x 0.45 with 25mm x 25mm x 3mm
thick equal L angles and 10mm square rods @ 150mm c/c fixing in position
,complete
for finsihed item
of1.00
workx 0.45 mtrs : Area = 0.45
VENTILATOR
SIZE
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 0.45
=
Horizental 1 x2 x 1.00
=
For Hold fasts 1 x 2 x 0.15 =
Total
=
10
0.45
0.45
0.90
2.00
0.30
3.20
m
m
m
3.52
Kgs
Kgs
=
=
total
2.25
2.00
4.25
3.336
44.50
Cum
305.10
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
123.41
24.00
452.51
63.35
515.86
0.9
0.45
0.405
0.90
1.80
0.30
3.00
m
m
m
3.3
Kgs
Kgs
ABSTRACT
a)MATERIAL
6.86
a) LABOUR
6.86
6.86
Supply and Fixing of Ventilator of size 0.90 x 0.45 with 25mm x 25mm x 3mm
thick equal L angles and 10mm square rods @ 150mm c/c fixing in position
,complete for finsihed item of work
11
=
=
total
2.25
1.80
4.05
3.179
44.50
Cum
288.33
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
116.63
22.68
427.63
59.87
487.50
3.6
1.5
5.4
3.00
7.20
0.30
10.50
m
m
m
11.55
Kgs
ABSTRACT
a)MATERIAL
6.48
a) LABOUR
6.48
6.48
Supply and Fixing of Balcony Grill of size 3.60 x 1.50 with 25mm x 25mm x
3mm thick equal L angles and 10mm square rods @ 150mm c/c fixing in
position ,complete for finsihed item of work
GRILL SIZE 3.60x1.50 mtrs : Area = 5.40
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 1.50
=
Horizental 1 x2 x 3.60
=
For Hold fasts 1 x 2 x 0.15 =
Total
=
12
=
=
total
28.50
32.40
60.90
47.81
Kgs
44.50
Cum
2641.36
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
1068.42
207.75
3917.53
548.45
4465.98
ABSTRACT
a)MATERIAL
59.36
a) LABOUR
59.36
59.36
Page 148
Supply and fixing Sintex or equivalen PVC door frames made from extruded
sections in overall dimensions of 40 X 48mm having a wall thickness of 1.5mm
with usual process variation of 0.3mm, complete, for finished item of work t.
13
1 rmt
228.00
14%
Rmt
14
228.00
228.00
PVC Door shutter conforming to IS: 10151-1982, the infill panel made of seamless one piece multi chamber PVC extruded
sections having overall dimensions of 610 mm x 20 mm with wall thickness of 1mm + 0.2mm with the top and bottom edges
of the shutter covered with end cap of the size 20 mm x 11 mm with the door shutter to be reinforced with special polymeric
reinforcements as per drawing for hardwares and fixtures. Stickers indicating the locations of hardware will be pasted at
appropriate places.for finished item of work.
1.4
2
3
2
1
1.4
1100.00
37.00
25.00
29.00
86.00
1
1
1
1
1
1 Sqm
Sqm
Each
Each
Each
Each
1540.00
74.00
75.00
58.00
86.00
1.4
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
295.00
Sqm
413.00
14%
Engineer
(R&B) Kothagudem
2246.00
1604.00
224.56
1829.00
Page 149
Supply and Fixing of non teak wood door of size 1.05 x 1.95 with fully pannealed including cost and conveyence of
all charges
Size : 1.05 x 1.95
Vertical port
1X
2 X
1.95 X
0.075 X 0.10 = 0.02925
Horizontal Port
1X
2 X
1.05 X
0.075 X 0.10 = 0.01575
0.0449
Styels
2X
2 X
1.8 X
0.10 X 0.030 =
0.021
Rails
2X
3 X
0.5 X
0.10 X 0.030 =
0.009
Planks
2x
2x
0.80 x
0 .40 x
0.025
0.032
0.06200
0.0449 cost of wood for frames x 48543
0.062 cost of for planks x 65512
2,179.58
4,061.74
969.00
500.00
300.00
242.25
360.00
8,612.57
Supply and Fixing of non teak wood Window Shutters of size 0.45 x 1.06 with fully pannealed including cost and
conveyence of all charges
Size : 0.45 x 1.06
0.47
Vertical styles
Horizontal Rails
Planks
1
1
1
2
2
2
1.06
0.45
0.45
0.1
0.1
0.35
0.03
0.03
0.025
0.0064
0.0027
0.0079
0.01700
1,113.70
282.47
300.00
70.61
180.00
1,946.78
Supply and Fixing of non teak wood Window shutters of size 0.40x1.22 with fully pannealed including cost and
conveyence of all charges
Size : 1.22 x 0.40
0.48
Vertical styles
Horizontal Rails
Planks
1
1
1
2
3
2
1.22
0.44
0.35
0.10
0.10
0.50
0.03
0.03
0.025
0.0073
0.0040
0.0088
0.0201
1,316.79
288.48
120.00
72.31
120.00
1,917.58
Supply and Fixing of G.I. Sheet doors of size 0.70 x 1.65 mtrs for toilets.
Size : 0.70 x 1.65
Vertical port
Horizontal Port
1
1
2
2
1.65
0.7
0.10
0.10
0.03
0.03
0.0099
0.0042
0.0141
697.11
299.00
221.95
200.00
120.00
55.48
1593.54
Supply and fixing of 18guage M.S. plain sheet DOOR of size 1.05x2.10m (Single Shutters)with outer
angle frame of rolled steel equal angle ISA 4040 of size 40mmx 40mmx 6mm and inner shutter angle
frame of rolled steel equal ISA 3535 angle of size 35mm x 35mm x 6mm and welded with fixtures
such as P.S. Powder coated 300mm long aldrop and 2No.s of 100mm long tower bolts, door handles
including red oxide primer of grade-1 quality including coat and convence of all materials and
fabrication charges for finished item of work
DOOR SIZE
AREA OF THE DOOR
THEORITICAL REQUIREMENT
1.05
2.2050
X
Sqm
2.10
OUTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA 4040- 40mm x
1 40mm x 6mm
Verticals (L - Angle)
2
2.10
4.20
Hrizontel (L - Angle)
2
1.05
2.10
Hold fasts
6
0.23
1.38
7.68
Rmt
Equalent weight
3.50
Kgs/ Rmt
7.68
3.50
26.88
Kgs
INNER SHUTTER ANGULAR FRAME OF ROLLED STEEL EQUAL ANGLE ISA
2 3535- 35mm x 33mm x 6mm
Verticals (L - Angle)
4
2.085
8.34
Hrizontel (L - Angle)
6
1.035
6.21
14.55
Rmt
Equalent weight
3.00
Kgs/ Rmt
14.55
3.00
43.65
Kgs
3 18 Guage MS Sheet
1.035
2.09
2.158
9.80
Kgs/ Sqm
2.16
9.80
21.15
Kgs
Total Weight
62.58
Kgs
0.6
0.21
0.49
25%
Lit
No.s
No.s
130.00
440.00
345.00
261.45
78.00
92.40
169.05
65.36
404.81
10Sqm
ABSTRACT
QTY
26.88
Kgs
44.50
Kgs
1196.16
43.65
Kgs
44.50
Kgs
1942.43
18 Guage MS Sheet
21.15
Kgs
43.00
Kgs
909.37
4.41
10Sqm
40.48
Sqm
178.52
62.58
Kgs
20.00
Kgs
1251.56
RATE
25%
1251.56
14%
5790.93
AMOUNT
312.89
5790.93
810.73
6601.66
Supply and fixing of 18guage M.S. plain sheet DOOR of size 0.75x2.10m (single Shutters)with outer
angle frame of rolled steel equal angle ISA 4040 of size 40mmx 40mmx 6mm and inner shutter angle
frame of rolled steel equal ISA 3535 angle of size 35mm x 35mm x 6mm and welded with fixtures
such as P.S. Powder coated 300mm long aldrop and 2No.s of 100mm long tower bolts, door handles
including red oxide primer of grade-1 quality including coat and convence of all materials and
fabrication charges for finished item of work
DOOR SIZE
AREA OF THE DOOR
THEORITICAL REQUIREMENT
40mm x 6mm
Verticals (L - Angle)
Hrizontel (L - Angle)
Hold fasts
0.75
1.5750
2.10
4.20
1.50
1.38
7.08
Rmt
Equalent weight
3.50
Kgs/ Rmt
7.08 STEEL
3.50EQUAL24.78
Kgs
INNER SHUTTER ANGULAR FRAME OF ROLLED
ANGLE ISA
3535- 35mm x 33mm x 6mm
Verticals (L - Angle)
2
2.085
4.17
Hrizontel (L - Angle)
3
0.735
2.21
6.38
Rmt
Equalent weight
3.00
Kgs/ Rmt
6.38
3.00
19.13
Kgs
18 Guage MS Sheet
0.735
2.09
1.532
9.80
Kgs/ Sqm
1.53
9.80
15.02
Kgs
Total Weight
Data For Red Oxide Primer
Cost of Red Oxide Grade 1 quality
Painter 1st Class
Painter 2nd Class
Municipal area allowence
2
2
6
X
Sqm
0.6
0.21
0.49
0.25
Lit
No.s
No.s
2.10
0.75
0.23
130.00
440.00
345.00
261.45
46.17
Kgs
78.00
92.40
169.05
65.36
404.81
10Sqm
ABSTRACT
QTY
24.78
Kgs
44.50
Kgs
1102.71
19.13
Kgs
44.50
Kgs
851.06
15.02
3.15
Kgs
10Sqm
43.00
40.48
Kgs
Sqm
645.78
127.52
46.17
Kgs
20.00
Kgs
923.47
RATE
25%
923.47
14%
3881.41
AMOUNT
230.87
3881.41
543.40
4424.80
Supply and fixing of 18guage M.S. plain sheet WINDOW of size 1.50x1.35m (Triple Shutters)with
outer angle frame of rolled steel equal angle ISA 4040 of size 40mmx 40mmx 6mm and inner shutter
angle frame of rolled steel equal ISA 2525 angle of size 55mm x 25mm x 6mm and welded with
fixtures such as P.S. Powder coated 300mm long aldrop and 2No.s of 100mm long tower bolts, door
handles including red oxide primer of grade-1 quality including coat and convence of all materials and
fabrication charges for finished item of work
WINDOW SIZE
AREA OF THE DOOR
THEORITICAL REQUIREMENT
40mm x 6mm
Verticals (L - Angle)
Verticals (T - Angle)
Hrizontel (L - Angle)
Hold fasts
1.50
2.0250
X
Sqm
2
2
2
6
1.35
1.35
1.50
0.23
9.78
3.50
3.50
2.70
2.70
3.00
1.38
9.78
Kgs/ Rmt
34.23
6
9
1.335
0.490
Equalent weight
3535- 35mm x 33mm x 6mm
Verticals (L - Angle)
Hrizontel (L - Angle)
Equalent weight
18 Guage MS Sheet
12.42
0.490
1.96
14
18.90
Total Weight
Data For Red Oxide Primer
Cost of Red Oxide Grade 1 quality
Painter 1st Class
Painter 2nd Class
Municipal area allowence
0.6
0.21
0.49
0.25
ABSTRACT
QTY
Lit
No.s
No.s
1.40
1.40
1.34
9.80
9.80
1.35
0.78
0.78
130.00
440.00
345.00
261.45
RATE
8.01
4.41
12.42
Kgs/ Rmt
17.39
1.962
Kgs/ Sqm
19.23
18.90
Kgs/ Rmt
14.74
1.35
Rmt
Kgs
Rmt
Kgs
Kgs
Kgs
80.62
Kgs
78.00
92.40
169.05
65.36
404.81
10Sqm
AMOUNT
Asst. Engineer
TW/ Gundala
34.23
Kgs
44.50
Kgs
1523.24
17.39
Kgs
44.50
Kgs
773.77
19.23
14.74
4.05
Kgs
Kgs
10Sqm
43.00
44.50
40.48
Kgs
Kgs
Sqm
826.98
656.02
163.95
80.62
Kgs
20.00
Kgs
1612.48
25%
1612.48
14%
5959.56
403.12
5959.56
834.34
6793.90
Executive Engineer
TW/ Division/Bhadrachalam
Asst. Engineer
TW/ Gundala
Executive Engineer
TW/ Division/Bhadrachalam
e Engineer
Bhadrachalam
e Engineer
Bhadrachalam
Qty
Description of Item
Rate
Unit
Per
Amount
1.52
2.13
3.24
0.03195
0.01140
0.04335
cum
cum
cum
2.89
sqm
40012.00
40012.00
1
1
Cum
Cum
1278.38
456.14
734.00
10.00
124.00
51.00
34.00
23.00
50.00
34.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
2121.26
60.00
124.00
102.00
68.00
138.00
50.00
68.00
385.00
345.00
295.00
1
1
1
day
day
day
88.62
185.30
112.54
324.00
Sqm
936.36
2.13
0.03195
0.01500
cum
cum
Supply and Fixing of Door with Double leaf shutter, Door Size 1.52x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, M.S.Powder Coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt
hinges 6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of
all materials to site all Labour charges such as Fixing of Door Frame and
shutter Fixing in position , with Hardware fixtures etc., complete for finsihed
1
2
utem of work.
DOOR SIZE 1.52 x 2.13 mtrs : Area = 3.24 Sqm
Sal Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
= 0.0319
Horizental 1 x 1.52 x 0.075 x 0.10
= 0.00864
Total
= 0.04054
35mm thick flush door shutter of soild wood block board type with commercial
play on both faces
1x1.41x2.05 = 2.89 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of Sal wood scantling of any size BMT-E-015 Item Sl No 122
0.01140 Cost of Sal wood scantling of any size BMT-E-015
3
4
5
6
7
8
9
10
2.89
6.00
1.00
2.00
2.00
6.00
1.00
2.00
11
12
13
0.23
0.54
0.38
2.89
Flush door shutters, solid bond wood block board type with commercial ply on
both faces.: 35 mm thick conforming to IS:2202 of ANAND/ RAAVILA/ KUTTY/
STANDARD/ SHUBHDWAR/ ITP (BMT-N.17)
MS Hold Fasts
Cost of 300mm Long M.S.Powder Coated Aldrops(BMT-G.45)
Cost of 250 long M.S.Powder Coated Towerbolts (BMT-G.17)
Cost of 150mm Long M.S.Powder Coated Handles (BMT-G.36)
Cost of 125mm long M.S.Powder Coated but hinges (BMT-G29)
Cost of Flat latch M.S.Powder Coated 300long (BMT-G.52)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Carpenter class I
Carpenter class II
Light mazdoor
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
14
Add overheads @
14%
long M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt
hinges 6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of
all materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
DOOR SIZE 2.00 x 2.13 mtrs : Area = 4.26 Sqm
Sal Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 2.00 x 0.075 x 0.10
=
4.26
P No 168
Total of soild
= wood block board type with commercial
35mm thick flush door shutter
play on both faces
1x1.89x2.05 = 3.87 Sqm
ABSTRACT
0.04695
cum
3.87
sqm
a)MATERIAL
1
40012.00
Cum
1278.38
40012.00
Cum
600.18
3.87
Flush Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick
734.00
Sqm
2840.58
6.00
MS Hold Fasts
10.00
Each
60.00
1.00
134.00
Each
134.00
2.00
55.00
Each
110.00
2.00
37.00
Each
74.00
6.00
25.00
Each
150.00
1.00
54.00
Each
54.00
10
2.00
37.00
Each
74.00
11
0.22
Carpenter class I
385.00
day
84.02
12
0.51
Carpenter class II
345.00
day
175.68
13
0.36
Light mazdoor
295.00
day
106.70
3.87
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
324.00
Sqm
1253.88
14
Add overheads @
6995.42
979.36
7974.80
14%
hinges 6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers
2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of
all materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
DOOR SIZE 1.22 x 2.13 mtrs : Area = 2.60 Sqm
Sal Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.22 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with commercial
play on both faces
1x1.11x2.05 = 2.28 Sqm
ABSTRACT
1.22
0.03195
0.00915
0.04110
cum
cum
cum
2.28
sqm
2.13
2.6
a)MATERIAL
0.03195 Cost of Sal wood scantling of size 2.0 to 3.0 M
40012.00
Cum
1278.38
3
4
2.28
6.00
Flush door shutters, solid bond wood block board type with commercial ply on
both faces.: 35 mm thick conforming to IS:2202 of ANAND/ RAAVILA/ KUTTY/
STANDARD/ SHUBHDWAR/ ITP (BMT-N.17)
MS Hold Fasts
1.00
40012.00
Cum
366.11
734.00
10.00
1
1
Sqm
Each
1673.52
60.00
134.00
Each
134.00
P No 169
2.00
55.00
Each
110.00
2.00
37.00
Each
74.00
6.00
25.00
Each
150.00
1.00
54.00
Each
54.00
10
2.00
37.00
Each
74.00
11
0.22
Carpenter class I
385.00
day
84.02
12
0.51
Carpenter class II
345.00
day
175.68
13
0.36
Light mazdoor
295.00
day
106.70
2.28
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
324.00
Sqm
738.72
14
Add overheads @
5079.13
711.08
5790.25
14%
0.9
2.13
1.92
0.03195
cum
0.00675
cum
0.03870
cum
1.6
sqm
Total
35mm thick flush door shutter of soild wood block board type with commercial
play on both faces
1x0.78x2.05 = 1.599
ABSTRACT
a)MATERIAL
1
40012.00
Cum
1278.38
0.00675 Cost
Sal wood
scantling
size up
2.0 wood
M
Cost of
35mm
thick flush
doorofshutter
of to
soild
block board type with
commercial play on both faces
1.6
(BMT-N.17)
40012.00
Cum
270.08
734.00
Sqm
1174.40
3
4
6.00
MS Hold Fasts
10.00
Each
60.00
1.00
134.00
Each
134.00
2.00
55.00
Each
110.00
1.00
37.00
Each
37.00
3.00
25.00
Each
75.00
1.00
54.00
Each
54.00
10
1.00
37.00
Each
37.00
11
0.21
Carpenter class I
385.00
day
79.12
12
0.48
Carpenter class II
345.00
day
165.43
13
0.34
Light mazdoor
295.00
day
100.47
1.60
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
324.00
Sqm
518.40
a) LABOUR
4093.28
14
Add overheads @
14%
573.06
P No 170
4666.35
Supply and Fixing of Door with Double leaf shutter, Door Size 1.00x2.13 mtrs
with Sal Wood Frame of sections size 75mm x 100mm with Flush Door
Shutters Solid Bond Wood black board type with commercial ply on both faces
of 35mm thick including cost of fixtures such as M.S.Powder Coated Tower
Bolts 200mm long 2 Nos, M.S.Powder Coated Handels 150mm long 1 No,
4
1
2
3
4
5
1.79
6.00
1.00
6
7
8
2.00
1.00
6.00
9
10
1.00
2.00
11
12
13
0.21
0.49
0.35
1.79
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long M.S.Powder Coated Aldrops(BMT-G.45)
Cost of MS-Powder Coated Tower Bolt-10 mm Bolt (IS:204) 200 mm Long
(BMT-G.16)
Cost of 150mm Long M.S.Powder Coated Handles (BMT-G.36)
Cost of 125mm long M.S.Powder Coated but hinges (BMT-G29)
Cost of Flat latch M.S.Powder Coated 300long (BMT-G.52)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Carpenter class I
Carpenter class II
Light mazdoor
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
14
Add overheads @
0.9
2.13
1.92
0.03195
0.00750
0.03945
cum
cum
cum
1.79
sqm
40012.00
40012.00
1
1
Cum
Cum
1278.38
300.09
734.00
10.00
134.00
1
1
1
Sqm
Each
Each
1313.86
60.00
134.00
41.00
37.00
25.00
1
1
1
Each
Each
Each
82.00
37.00
150.00
54.00
37.00
1
1
Each
Each
54.00
74.00
385.00
345.00
295.00
1
1
1
day
day
day
80.65
168.63
102.41
324.00
Sqm
579.96
4414.98
618.10
5033.10
14%
1 rmt
303.00
Add overheads @
Rmt
303.00
14%
303.00
P No 171
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have
a coat of steel primers of approved make and manufacture. M.S. frame shall
be covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail &
bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC
sheet as gap insert for top rail & bottom rail. Panelling of 10mm thick PVC
sheet to be fitted in the M.S. frame welded / sealed to the stiles & rails with
30mm wide x 5mm thick PVC sheet beading on either side, and joined together
with solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm
width is to be stuck on the interior side of the C Channel using PVC solvent
adhesive. Complete as per direction of Engineer-in-charge, manufacturers
specification & drawing for finished item of work .
2205.00
14%
sqm
2205.00
2205.00
a)
b)
4450
SQM
Total
14%
4423.00
4450.00
-427.00
400.00
4423.00
5050.00
-427.00
400.00
5023.00
Total
14%
5023.00
Supply and Fixing of Ventilator of size 1.22 x 0.45 with 25mm x 25mm x 3mm thick equal L angles and 10mm square rods
@ 150mm c/c fixing in position ,complete for finsihed item of work
VENTILATOR SIZE 1.20 x 0.45 mtrs : Area = 0.54
1.2
0.45
0.54
P No 172
0.90
2.40
0.30
3.60
m
m
m
3.96
Kgs
=
=
total
3.15
2.40
5.55
4.357
Kgs
44.50
Cum
370.10
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
149.70
29.11
548.91
76.85
625.75
ABSTRACT
a)MATERIAL
8.32
a) LABOUR
8.32
8.32
Supply and Fixing of Ventilator of size 1.00 x 0.45 with 25mm x 25mm x 3mm thick equal L angles and 10mm square
rods @ 150mm c/c fixing in position ,complete for finsihed item of work
VENTILATOR SIZE 1.00 x 0.45 mtrs : Area = 0.45
1
X
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 0.45
=
0.90
m
Horizental 1 x2 x 1.00
=
2.00
m
For Hold fasts 1 x 2 x 0.15 =
0.30
Total
=
3.20
m
10 mm square rods @ 150 mm c/c
Verticals 1 x 5 x 0.45
Horizental 1 x2 x 1.00
0.45
0.45
3.52
Kgs
=
=
total
2.25
2.00
4.25
3.336
Kgs
44.50
Cum
305.10
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
123.41
24.00
452.51
63.35
515.86
ABSTRACT
a)MATERIAL
6.86
a) LABOUR
6.86
6.86
10
Supply and Fixing of Ventilator of size 0.90 x 0.45 with 25mm x 25mm x 3mm thick equal L angles and 10mm
@ 150mm c/c fixing in position ,complete for finsihed item of work
VENTILATOR SIZE 0.90 x 0.45 mtrs : Area = 0.41
0.9
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 0.45
=
0.90
Horizental 1 x2 x 0.90
=
1.80
For Hold fasts 1 x 2 x 0.15 =
0.30
Total
=
3.00
10 mm square rods @ 150 mm c/c
Verticals 1 x 5 x 0.45
Horizental 1 x2 x 0.90
square rods
X
0.45
0.405
3.3
Kgs
m
m
=
=
total
2.25
1.80
4.05
3.179
Kgs
44.50
Cum
288.33
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
116.63
22.68
427.63
59.87
487.50
ABSTRACT
a)MATERIAL
6.48
a) LABOUR
6.48
6.48
11
Supply and Fixing of Balcony Grill of size 3.60 x 1.50 with 25mm x 25mm x 3mm thick equal L angles and 10mm square
rods @ 150mm c/c fixing in position ,complete for finsihed item of work
GRILL SIZE 3.60x1.50 mtrs : Area = 5.40
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 1.50
=
3.6
3.00
1.5
5.4
P No 173
Horizental 1 x2 x 3.60
=
For Hold fasts 1 x 2 x 0.15 =
=
Total
7.20
0.30
10.50
m
m
11.55
Kgs
=
=
total
28.50
32.40
60.90
47.81
Kgs
44.50
Cum
2641.36
18.00
3.50
1
1
Kg
Kg
Add overheads @
Rate per / Each
14%
1068.42
207.75
3917.53
548.45
4465.98
ABSTRACT
a)MATERIAL
59.36
a) LABOUR
59.36
59.36
12
Supply and fixing Sintex or equivalen PVC door frames made from extruded sections in overall dimensions of 40 X 48mm
having a wall thickness of 1.5mm with usual process variation of 0.3mm, complete, for finished item of work t.
1 rmt
228.00
14%
Rmt
13
228.00
228.00
PVC Door shutter conforming to IS: 10151-1982, the infill panel made of seamless one piece multi chamber PVC extruded
sections having overall dimensions of 610 mm x 20 mm with wall thickness of 1mm + 0.2mm with the top and bottom edges
of the shutter covered with end cap of the size 20 mm x 11 mm with the door shutter to be reinforced with special polymeric
reinforcements as per drawing for hardwares and fixtures. Stickers indicating the locations of hardware will be pasted at
appropriate places.for finished item of work.
1.4
2
3
2
1
1.4
1100.00
37.00
25.00
29.00
86.00
1
1
1
1
1
1 Sqm
Sqm
Each
Each
Each
Each
1540.00
74.00
75.00
58.00
86.00
1.4
Labour charges for fixing flush door shutter of any thickness fixing the door
shutter to the frame and fixtures to the door shutter
324.00
Sqm
453.60
2286.60
1633.00
228.62
14%
1862.00
PRSD Kothagudem
Badangi
Vizianagaram
Vizianagaram
0
Guntur
P No 174
Sl.
No
1
AREA ALLOWENCE
0%
14%
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
Supplying and laying, filling, jointing and testing SWG SP-1 pipes of ISI make confirming to IS 1651 & 4127 1st quality with air tight
Cement joints in CM (1.5:1)prop. including excavation of trenches and socket pits in any soil (except rock requiring blasting) and
refilling with watering and tamping including cost and conveyance of all materials to site and all labour charges for finished item of work
(APSS NO 1301 & 1318)
BMW-A.02
BMW-A.05
1.00
Rmt
0%
193.00
1.00 Rmt
102.00
1.00
193.00
0.00
0.00
193.00
add overheads @
14.00%
27.02
220.05
BMW-A.03
BMW-A.06
1.00
Rmt
0%
471.00
1.00 Rmt
138.00
1.00
471.00
0.00
0.00
471.00
add overheads @
14.00%
65.94
536.95
BMW-A.01
BMW-A.06
1.00
Rmt
0%
348.00
1.00 Rmt
138.00
1.00
348.00
0.00
0.00
348.00
add overheads @
14.00%
48.72
396.75
BMW-A.04
BMW-A.05
1.00
Rmt
0%
319.00
1.00 Rmt
102.00
1.00
319.00
0.00
0.00
319.00
add overheads @
14.00%
44.66
363.70
Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop
using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including
plastering with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and frames including
excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick
using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental
and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of
work as per Standard specification.
basic rate as per ssr item
Area allowence on labour charges
BMW-B.03
1.00
0%
Nos
4814.00
0.00
1.00 Nos
1.00
4814.00
0.00
0.00
4814.00
WS-DATA
P No 175
Sl.
No
DESCRIPTION
ITEM CODE
add overheads @
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
14.00%
673.96
5488.00
Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop
using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including
plastering with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and frames including
excavating pits up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick
using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental
and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of
work as per Standard specification.
basic rate as per ssr item
BMW-B.04
1.00
Nos
7455.00
0.00
0%
1.00 Nos
1.00
7455.00
0.00
0.00
7455.00
14.00%
add overheads @
1043.70
8498.70
Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6)
prop using fly ash blocks of 225mm thick from approved source having a minimum crushing strength of 10 N/sq.mm including plastering
with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and frames including excavating
pits up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm
HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operational,
labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as per
Standard specification.
basic rate as per ssr item
BMW-B.02
1.00
Nos
8288.00
0.00
0%
1.00 Nos
1.00
8288.00
0.00
0.00
8288.00
14.00%
add overheads @
1160.32
9448.35
Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6)
prop using fly ash blocks of 225mm thick from approved source having a minimum crushing strength of 10 N/sq.mm including plastering
with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and frames including excavating
pits up to a depth of 1524 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm
HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operational,
labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as per
Standard specification.
basic rate as per ssr item
BMW-B.01
1.00
Nos
5246.00
0.00
0%
1.00 Nos
1.00
5246.00
0.00
0.00
5246.00
14.00%
add overheads @
734.44
5980.45
Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 4127 with CI grating and constructing
single brick masonry wall chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed, and fitted with 304.8 mm x
225.6 mm(12" x 9") CI frame and hinged cover and plastering 12mm thk. in CM (1:4) prop. both inside and outside surfaces and
including cost and conveyance of all materials to site, labour charges etc., complete for finished item of work. SSR ITEM NO.527
Basic rate as per ssr item
BMW-A.72
BMW-A.74
1.00
Nos
0%
530.00
1.00 Nos
23.00
1.00
530.00
0.00
0.00
530.00
14.00%
add overheads @
74.20
604.20
Supplying and fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neycer) 1st quality conforming to IS:2556-Part4:1972 of size 550mm x 400mm with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/
Esso or equivalent complete with standard CI brackets including wooden block ,1 No.12.70mm PVC connection with brass union nuts
CP coated , 1 No.12.70mm NP bib tap 300 gms Seiko or equivalent including cost and conveyance of all materials to site, labour
charges etc. complete for finished item of work
BMW-D24
BMW-D28
1.00
0%
Nos
1323.00
1.00 Nos
288.00
1.00
1323.00
0.00
0.00
1323.00
WS-DATA
P No 176
Sl.
No
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
14.00%
add overheads @
185.22
1508.25
BMW-I.48
BMW-I.49
1.00
Nos
0%
85.00
1.00 Nos
16.00
1.00
85.00
0.00
0.00
85.00
14.00%
add overheads @
11.90
96.90
BMW-E 05
BMW-E 06
1.00
Nos
0%
403.00
1.00 Nos
35.00
1.00
403.00
0.00
0.00
403.00
14.00%
add overheads @
56.42
459.45
BMW-E31
BMW-E32
1.00
Nos
0%
201.00
1.00 Nos
23.00
1.00
201.00
0.00
0.00
201.00
14.00%
add overheads @
28.14
229.15
BMW-G05
1.00
Nos
0%
21.00
1.00 Nos
0.00
1.00
21.00
0.00
0.00
21.00
14.00%
add overheads @
2.94
23.95
2317.70
Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screws etc., complete including cost and
conveyance of all materials, labour charges for fixing etc., complete for finished item of work in all floors as per ssr item no 598
Basic rate as per ssr item
BMW-I.28
BMW-I.29
1.00
Nos
0%
206.00
1.00 Nos
10.00
1.00
206.00
0.00
0.00
206.00
14.00%
add overheads @
28.84
234.85
Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back with NP screws 1st quality
including cost and conveyance of all materials, labour charges etc., complete for finished item of work in all floors.
Basic rate as per ssr item
BMW-I 105
BMW-I.106
1.00
Nos
0%
435.00
1.00 Nos
95.00
1.00
435.00
0.00
0.00
435.00
14.00%
add overheads @
60.90
495.90
Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets and aluminium screws including
cost and conveyance of all materials, labour charges etc., complete for finished item of work.
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 20
BMW-I 21
1.00
0%
Nos
139.00
1.00 Nos
36.00
1.00
139.00
0.00
0.00
139.00
add overheads @
Total rate per 1 Nos
WS-DATA
14.00%
19.46
158.50
P No 177
Sl.
No
DESCRIPTION
11
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
Supplying and fixing NP bib taps of size 12.70mm dia of Indian make Seiko or equivalent including cost and conveyance of all
materials, labour charges etc., complete for finished item of work in all floors.
a)
300 grams
Basic rate as per ssr item
BMW-E 09
BMW-E 10
1.00
Nos
0%
219.00
1.00 Nos
23.00
1.00
219.00
0.00
0.00
219.00
14.00%
add overheads @
30.66
249.70
400 gms
Basic rate as per ssr item
BMW-E 07
BMW-E 08
1.00
Nos
0%
345.00
1.00 Nos
23.00
1.00
345.00
0.00
0.00
345.00
14.00%
add overheads @
48.30
393.30
Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special
such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary
with required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished
item of work at all floor levels. (APSS No. 1302 1319 & 1326)
(a) 90mm dia 3 Mts single socket
Basic rate as per ssr item
BMW-G12
BMW-G.152
1.00 RM
0%
368.00
3.00 RMT
58.00
1.00
122.67
0.00
0.00
122.67
14.00%
add overheads @
17.17
139.85
BMW-G13
BMW-G.152
1.00 RM
440.00
3.00 RMT
RM
58.00
1.00 RM
0%
146.67
0.00
146.67
14.00%
add overheads @
20.53
167.20
Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI fittings in ground or on wall including
cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils
except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS
clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work.
a) 15mm Nominal bore
Basic rate as per ssr item
BMW-F79
BMW-F80
1.00 Rmt
151.00
1.00 Rmt
Rmt
33.00
1.00
0%
151.00
0.00
151.00
14.00%
add overheads @
21.14
172.15
BMW-F81
BMW-F82
1.00 Rmt
168.00
1.00 Rmt
Rmt
33.00
1.00 Rmt
0%
168.00
0.00
168.00
14.00%
add overheads @
23.52
191.55
BMW-F83
BMW-F84
1.00 Rmt
220.00
1.00 RMT
Rmt
33.00
1.00 Rmt
0%
220.00
0.00
220.00
add overheads @
14.00%
30.80
250.80
WS-DATA
BMW-F87
1.00 Rmt
346.00
1.00 RMT
346.00
P No 178
Sl.
No
DESCRIPTION
Area allowence on labour charges
ITEM CODE
BMW-F88
COEF.
0%
UNIT
Rmt
RATE
36.00
PER
UNIT
Amount (Rs.)
1.00 Rmt
0.00
346.00
add overheads @
14.00%
48.44
394.45
BMW-F89
BMW-F90
1.00 Rmt
373.00
1.00 RMT
Rmt
55.00
1.00 Rmt
0%
373.00
0.00
373.00
14.00%
add overheads @
52.22
425.25
BMW-F91
BMW-F90
1.00 Rmt
661.00
1.00 RMT
Rmt
55.00
1.00 Rmt
0%
661.00
0.00
661.00
14.00%
add overheads @
92.54
753.55
Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make heavy type including cost and
conveyance of all materials , labour charges etc. complete for finished item of work.
15 mm dia nominal bore
Basic rate as per ssr item
BMW-F21
BMW-F22
1.00
Nos
0%
306.00
1.00 Nos
36.00
1.00
306.00
0.00
0.00
306.00
14.00%
add overheads @
42.84
348.85
BMW-F19
BMW-F20
1.00
Nos
0%
414.00
1.00 Nos
36.00
1.00
414.00
0.00
0.00
414.00
14.00%
add overheads @
57.96
472.00
BMW-F17
BMW-F18
1.00
Nos
0%
610.00
1.00 Nos
36.00
1.00
610.00
0.00
0.00
610.00
14.00%
add overheads @
85.40
695.40
BMW-F25
BMW-F26
1.00
Nos
1243.00
55.00
0%
1.00 Nos
1.00
1243.00
0.00
0.00
1243.00
14.00%
add overheads @
174.02
1417.05
BMW-F27
BMW-F28
1.00
Nos
1795.00
74.00
0%
1.00 Nos
1.00
1795.00
0.00
0.00
1795.00
14.00%
add overheads @
251.30
2046.30
65 mm nominal bore
Basic rate as per ssr item
Area allowence on labour charges
BMW-F29
BMW-F30
1.00
0%
Nos
3424.00
92.00
1.00 Nos
1.00
3424.00
0.00
0.00
3424.00
WS-DATA
P No 179
Sl.
No
DESCRIPTION
ITEM CODE
add overheads @
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
14.00%
479.36
3903.40
Supply and fixing of white glazed flat back bowl urinals of size 440 mm x 265 mm x 315 mm with internal rim flushing mm fixied with
screws complete inidan make (HS W/Parry/Neycer) conforming to IS 2556 -1995 as approved be Engineer - in - charge 12.7 mm PVC
connection with brass plumber union nuts CM Coated. including 12.70 mm push cock 1st qulaity of approved make including supply &
fixing 31.75 m dia PVC flexible waser pipe of 914.40 mm lenght of 1st including cost and conveyance of all materials to site labour
charges etc., complete for finished item of work for all floors
Basic rate as per ssr item
BMW-D33
BMW-D36
1.00
Nos
0%
690.00
1.00 Nos
115.00
1.00
690.00
0.00
0.00
690.00
14.00%
add overheads @
96.60
786.60
Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm in CM (1:8) prop including
plastering and finishing with 12mm thick in CM (1:5) including cost and conveyance of all materials and all labour charges etc. complete
Basic rate as per ssr item
BMW-i63
BMW-i64
1.00
Nos
0%
62.00
1.00 Nos
18.00
1.00
62.00
0.00
0.00
62.00
14.00%
add overheads @
8.68
70.70
Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 4127with CI grating and constructing single
brick masonry wall chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed, and plastering 12mm thk. in CM (1:4)
prop. both inside and outside surfaces and fitted with 304.8MM X 288.6 MM (12"X9") CI frame and hinged cover including labour for
fixing and laying the SWG junctions/plugs/bends with air tightcement joints etc., complete including cost and conveyance of all materials
to site, labour charges etc., complete for finished item of work as directed by Engineer-in-charge.
Basic rate as per ssr item
BMW-A72
BMW-A74
1.00
Nos
0%
530.00
1.00 Nos
23.00
1.00
530.00
0.00
0.00
530.00
14.00%
add overheads @
74.20
604.20
Supplying and fixing CI Nahani traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI marked conforming to IS:1729-1979
with C.P. Grating fixing with white cement as per site requirements with standard practice for all floors including cost and conveyance of
all materials to site, labour charges etc., complete for finished item of work.
A
BMW-C42
1.00
Nos
0%
279.00
1.00 Nos
45.00
1.00
279.00
0.00
0.00
279.00
14.00%
add overheads @
39.06
318.10
BMW-i12
BMW-i13
1.00
Nos
0%
26.00
1.00 Nos
15.00
1.00
26.00
0.00
0.00
26.00
14.00%
add overheads @
3.64
29.65
347.75
Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water Closet 1st qualityISI marked confirming to IS:2556-Part-31981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, CC squatting plate and fixing 12.70mm dia NP Push
cock 1st quality , P trap or S trap of Indian W.C. shall be encased on CC (1:2:4) 150mm alround well above the joint to stop leakage at
the joint etc., complete including cost and conveyance of all materials to site, cost of CC bed, labour charges and seigniorage charges
etc., complete for finished item of work.
Basic rate as per ssr item
BMW-D04
BMW-D06
BMW-D09
1.00
Nos
0%
1.00
Nos
1052.00
1.00 Nos
288.00
1.00
253.00
1.00 Nos
1052.00
0.00
0.00
253.00
1305.00
add overheads @
WS-DATA
14.00%
182.70
P No 180
Sl.
No
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
1487.70
Providing and placing on terrace (at all floor levels) polyetheylene water storage tank with double layer approved brand and manufacture
with cover and suitable locking arrangement and making necessary holes for inlet and outlets and over flow pipes but without fittings and
base support for tanks including cost and conveyance of all materials and labour charges for placing and fixing in position as directed by
Engineer-in-Charge.
Basic rate as per ssr item
BMW-G01
BMW-G02
1.00
Lit
0%
5.00
1.00 Lit
0.00
1.00
5.00
0.00
0.00
5.00
14.00%
add overheads @
0.70
5.70
Supplying and fixing 609.6 mm x 457.2 mm x 254 mm RCC terrazo finished sink (or constructed at site with 50.80 mm thick) brass plug
and chain incluiding CI cantilever brackets, 31.75 mm dia PVC flexible waste pipe 914.4 mmm length of 1st quality including cost and
conveyance fo all materials labour charges etc., complete for finished item of work
Basic rate as per ssr item
BMW-D40
BMW-D41
1.00
Nos
0%
587.00
1.00 Nos
184.00
1.00
587.00
0.00
0.00
587.00
14.00%
add overheads @
82.18
669.20
Supply and fixing of stainless steel sink with drain board of size 914.4 mm x 457.2 mm 1 mm thick of indian make on cantilever brackets
including 32 mm CP waste coupling including supply & fixing of 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of 1st quality,
chasing brick masonry wall and making good after construction i.e., restoring to original srufaces etc., complete including cost and
conveyance of all materials and labour charges for all operations etc., complete for finished item of work in all floors
Basic rate as per ssr item
BMW-I119
BMW-I120
1.00
Nos
0%
5826.00
1.00 Nos
414.00
1.00
5826.00
0.00
0.00
5826.00
14.00%
add overheads @
815.64
6641.65
Supply & Fixing of 22" dia RCC Cover for manhole with nominal reinforecement 3" thick with hooks for lfifting including cost and
conveyance of all materials, labour charges etc., complete for finished tiem of work
Basic rate as per ssr item
BMW-I130
1.00
Nos
598.00
0.00
0%
1.00 Nos
1.00
598.00
0.00
0.00
598.00
14.00%
add overheads @
83.72
681.75
Supply and fixing of 100 mm dia CI Vent pipe of 3 mts length double socket fitted with AC cowl and mosquito proof wire mesh including
cost and conveyance of all materials to site and labour charges for placing and fixing in position etc., complete for finished item of work.
BMW-H05
1.00
Nos
1765.00
0.00
0%
1.00 Nos
1.00
1765.00
0.00
0.00
1765.00
14.00%
add overheads @
247.10
2012.10
Supply and fixing of 75 mm dia CI Vent pipe of 3 mts lenth fitted with AC cowl and mosquito proof wire mesh including cost and
conveyance of all materials to site and labour charges for placing and fixing in position etc., complete for finished item of work.
Basic rate as per ssr item
BMW-H04
1.00
Nos
1308.00
0.00
0%
1.00 Nos
1.00
1308.00
0.00
0.00
1308.00
14.00%
add overheads @
183.12
1491.15
Supply and fixing of CI pipes 101.6mm Single socket ISI marked confirming to IS: 1729 - 1979 of reputed make with cement caulked
joints and paintaed black with japan paint and fixing with necessary woden blocks fixed in the masoery walls in CM (1.5:1) including
fixing of MS clamps of necessary size and required no of Bombay nails etc., complete including cost and conveyance of all materials to
site all labour charges sales and other taxes on all materials etc.,, complete for finished item of work all Floors
a
Basic rate as per ssr item
BMW-CO2
BMW-CO7
1.00
0%
Nos
737.00
1.00 Nos
173.00
1.00
737.00
0.00
0.00
737.00
WS-DATA
P No 181
Sl.
No
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
14.00%
add overheads @
103.18
840.20
Supply and fixing of CI pipes 76.2 mm Single socket ISI marked confirming to IS: 1729 - 1979 of reputed make with cement caulked
joints and paintaed black with japan paint and fixing with necessary woden blocks fixed in the masoery walls in CM (1.5:1) including
fixing of MS clamps of necessary size and required no of Bombay nails etc., complete including cost and conveyance of all materials to
b
site all labour charges sales and other taxes on all materials etc.,, complete for finished item of work all Floors
Basic rate as per ssr item
BMW-CO1
BMW-CO7
1.00
Nos
0%
645.00
1.00 Nos
173.00
1.00
645.00
0.00
0.00
645.00
14.00%
add overheads @
90.30
735.30
Constructing 457.2mm x 457.2mm (1'-6" x 1'-6") brick in CM (1:6) prop. Masonry inspection chamber upto 914.4mm (3'-0") and fitted
with light weight 457.2mm x 457.2mm (1'-6" x 1"-6") frame and cover of 20kg., including cost and convenyance of all materials to site, all
labour charges, sales and otehr taxes on all materials etc., complete for finished item of work
Basic rate as per ssr item
BMW-B06
1.00
Nos
0%
3020.00
0.00
1.00 Nos
1.00
3020.00
0.00
0.00
3020.00
add overheads @
14.00%
422.80
3442.80
Supply and Fixing of AC Cowls 88.9 mn dia with all necessary requirements including all operational , incidental sales and other taxes
and all labour charges etc., complete including cost and convenyance of all materials complete for finished item of work for all Floors.
Basic rate as per ssr item
Area allowence on labour charges
BMW-I36
BMW-I37
1.00
Nos
0%
60.00
1.00 Nos
12.00
1.00
60.00
0.00
0.00
60.00
add overheads @
14.00%
8.40
68.40
Supply and Fixing of AC Cowls 63.50 mn dia with all necessary requirements including all operational , incidental sales and other taxes
and all labour charges etc., complete including cost and convenyance of all materials complete for finished item of work for all Floors.
Basic rate as per ssr item
BMW-I38
BMW-I39
1.00
Nos
0%
41.00
1.00 Nos
9.00
1.00
41.00
0.00
0.00
41.00
add overheads @
14.00%
5.74
46.75
Construction of 50.8mm thick RCM Baffle wall with 2.267 Kg steel and rabit wire mesh in CM (1:3) prop: with fine rendering in neat
cement in septic tank including cost and convenyance of all materials to site, seigonarage charges sales and othe taxes on all materials ,
and all labour charges etc., complete for finished item of work.
Basic rate as per ssr item
BMW-I95
BMW-I97
1.00
Nos
0%
213.00
1.00 Nos
36.00
1.00
213.00
0.00
0.00
213.00
14.00%
add overheads @
29.82
242.85
Supply and Fixing of C.I. (Spun ) Soil waste and ventilating pipe of 3.00 Mt length of 100mm dia with double socket for vent over septic
tank including cost and convenyance of all materials to site, all labour charges sales and all other taxes on all materials etc., complete
for finished item of work.
Basic rate as per ssr item
BMW-H05
1.00
Nos
0%
BMW-I36
BMW-I37
1.00
0%
Nos
1765.00
1.00 Nos
0.00
1.00
60.00
1.00 Nos
12.00
1.00
1765.00
0.00
0.00
60.00
0.00
0.00
1825.00
add overheads @
Total rate per 1 No
WS-DATA
14.00%
255.50
2080.50
P No 182
Sl.
No
33
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
Supply and Fixing of 914.4mm x 457.2mm Light Weight CI Manhole Frame and Cover (30 Kgs) complete for finished item of work
including cost and conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc., complete for
finished item of work.
Basic rate as per ssr item
BMW-I86
BMW-I88
1.00
Nos
1645.00
115.00
0%
1.00 Nos
1.00
1645.00
0.00
0.00
1645.00
14.00%
add overheads @
230.30
1875.30
Supply and Fixing of CI Steps for Septic Tank / Manhole complete for finished item of work including cost and conveyance of all
materials to site, all labour charges, sales and other taxes on all materials etc., complete for finished item of work.
Basic rate as per ssr item
BMW-I89
BMW-I90
1.00
Nos
0%
53.00
1.00 Nos
9.00
1.00
53.00
0.00
0.00
53.00
14.00%
add overheads @
7.42
60.45
Supply and Fixing 10 Litres capacity Single Flush white PVC low level flushing system parryware, slimline with internal components and
short bend including cost and conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc.,
complete for finished item of work for all floors.
Basic rate as per ssr item
BMW-G08
1.00
Nos
1323.00
0.00
0%
1.00 Nos
1.00
1323.00
0.00
0.00
1323.00
14.00%
add overheads @
185.22
1508.25
Supply & Fixing 4" dia (101.6 mm) CI Plug (Door) bends 1st quality ISI marked conforming to IS : 1729-1979 with cement caulked joints
and fixing as per site requirements with standard practice including cost and conveyance of all materials to site, all labour charges, sales
and other taxes on all materials etc., complete for finished item of work for all floors.
Basic rate as per ssr item
Area allowence on labour charges
BMW-C12
BMW-C14
1.00
Nos
0%
332.00
1.00 Nos
55.00
1.00
332.00
0.00
0.00
332.00
14.00%
add overheads @
46.48
378.50
Supply & Fixing 3" dia (76.2 mm) CI Plug (Door) bends 1st quality ISI marked conforming to IS : 1729-1979 with cement caulked joints
and fixing as per site requirements with standard practice including cost and conveyance of all materials to site, all labour charges, sales
and other taxes on all materials etc., complete for finished item of work for all floors.
Basic rate as per ssr item
BMW-C11
BMW-C14
1.00
Nos
0%
284.00
1.00 Nos
55.00
1.00
284.00
0.00
0.00
284.00
14.00%
add overheads @
39.76
323.80
Manufacture, supply & delivery of 50mm of outer dia HDPE pipes of 6Kg/Sqcm. conforming to IS 4984 - 1995 including transportation to
site including laying and jointing of HDPE pipes as per BIS No.7634 Part -II/75 including fixing required specials /fittings including
excavation of trenches up to 0.50 mts depth in all soils except rock requires blasting and refilling trenches after laying and jointing of
pipes as per standard specifications including cost and conveyance of all materials to site, all labour charges, sales and other taxes on
all materials etc., complete for finished item of work.
Basic rate as per ssr item
Table 17.1/PH
1.00
RMT
49.00
1.00 RMT
49.00
RMT
1.00
0%
RMT
21.00
1.00
21.00
21.00
0.00
70.00
add overheads @
Total rate per 1Rmt
39
14.00%
9.80
79.80
Construction of 60,000 liters capacity OHSR(VRCC) with 12.7 mts staging without seismic analysis including fixtures OF rcc OR
ALLUMINIUM LADDER INSIDE 0.45 Mtrs wide, MS ladder on the outside . Lighting including condutor & earthing etc., RCC ventilators
with copper or stainless steel skyproof mesh, Manhole frame and cover 0.75x0.75mts with frame as per IS specifications (light duty - 2
Nos), Ralling with 32mm dia GI pipes (A class in 2 nos alround OHSR fixed in RCC (1:2:4) poles of size 100x75x75mm with 1.50mts
intervals alround periphery on top of the OHSR for smaller capacities,Water level indicator of good quality with ebonite /copper float
approved pattern - 1 no
WS-DATA
P No 183
Sl.
No
DESCRIPTION
ITEM CODE
COEF.
UNIT
RATE
PER
UNIT
Amount (Rs.)
1.00
(5400-5500)*0.00007
(42000-41000)*0.00002
Lt
20.94
1.00 Lt
20.94
-0.01
0.02
20.95
add overheads @
3.23
26.30
1.00
Kg
58.00
1.00 Kg
14.00%
8.12
66.15
Kg
58.00
1.00 Kg
8.12
66.15
Kg
58.00
1.00 Kg
8.12
66.15
1.00
nos
4468.00
1.00 nos
14.00%
625.52
f)
4468.00
5093.55
58.00
14.00%
58.00
14.00%
58.00
1.00
14.00%
Kg
88.00
1.00 Kg
88.00
12.32
100.35
WS-DATA
P No 184
Sl.
No
DESCRIPTION
ITEM CODE
Table 36-4 / PH
COEF.
UNIT
1.00
RATE
kg
77.00
PER
UNIT
1.00 kg
Amount (Rs.)
77.00
Add overheads @
14.00%
10.78
87.80
1.00
Kg
93.00
1.00 Kg
14.00%
13.02
106.05
93.00
Cost of Bricks
322.50
654 Nos.
5095.67
1000 Nos.
3332.57
98.10 Nos.
5095.67
-1000 Nos.
-499.89
Brick layer
1.28 Each
385.00
1 Each
492.80
Man Mazdoor
0.64 Each
295.00
1 Each
188.80
Women Mazdoor
1.93 Each
295.00
1 Each
569.35
WS-DATA
4083.63
P No 185
0%
0%
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
1.4.2
(C)
Amount Rs.
ohr
Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK) concealed in Roof Slabs with all
required accessories including masonary work and labour charges etc., complete. Make : Sudhakar/
Maco Plast / Modi
Taking Output = 100 M
a) Material
elec-1.2.4
100 M
3030.00
3030.00
ele-1.2.39
Each
12
24.00
288.00
Each
12
6.00
72.00
3390.00
Add contr profit @14% on material
0.00
0.00
3390.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
400.00
800.00
day
320.00
640.00
elec-8.1.85 Helpers
day
320.00
640.00
0%
0%
0.00
2080.00
1.4.2
(b)
0.00
5470.00
54.70
elec-1.2.3
100 M
2420.00
100 Nos
40.00
2420.00
80.00
Each
44.00
88.00
ele-1.2.39
Each
12
24.00
288.00
Each
12
6.00
72.00
kg
50
5.60
280.00
3228.00
Add contr profit @14% on material
0.00
0.00
3228.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
400.00
800.00
day
320.00
640.00
elec-8.1.85 Helpers
day
320.00
640.00
day
350.00
700.00
0%
0%
El Data
0.00
2780.00
0.00
6008.00
60.10
P No 186
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
2.1.1
Amount Rs.
ohr
Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant (FR) P.V.C. insulated flexible copper cable
(ISI MARK) in existing pipe with 6A switch, Ceiling rose and 3mm thick hylam sheet covering to switch
control box including all labour charges etc., comp
Make : Million / RPG/ paragon
Taking Output = 6 Points
a) Material
elec-1.5.1
elec-1.7.1
100 M
1001.00
1001.00
each
18.00
108.00
each
21.00
126.00
no
44.00
44.00
1279.00
0.00
0.00
1279.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.6
400.00
240.00
day
1.2
320.00
384.00
elec-8.1.85 Helpers
day
0.6
320.00
192.00
0%
0%
0.00
816.00
0.00
2095.00
349.20
Wiring with 2 runs of1.0 Sqmm PVC insulated flexible copper cable,(phase,neutral) in the metalic/nonmetalic conduit
pipe with 6A flush type two way switch control, ceiling rose and 3mm thick hylam sheet covering to MS switch control
box including all labour charges etc., complete for staircase in Residential buildings as required. Make: Finolex L&T.
2.1.4
1.5
327.40
491.10
Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a common switch board with earth continuity
including wire leads, earth connections along with all labour charges etc., complete.
Makes : Anchor / Gold Medal Olive /Million Zoom
Taking Output = each
a) Material
elec-1.7.4
each
27.00
27.00
elec-1.7.1
each
18.00
18.00
45.00
0.00
0.00
45.00
b) Labour charges :
day
0.067
400.00
26.80
elec-8.1.85 Helpers
day
0.067
320.00
21.44
0%
0%
0.00
48.24
0.00
93.25
El Data
P No 187
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
Amount Rs.
ohr
wiring with 2 runs of 14/0.3(1.0 Sqmm) PVC insulated FR flexible copper cable,(phase,neutral) in the
metalic/nonmetalic conduit pipe with 6A flush type switch control, switch control box including all labour
Charges etc., complete. Make : Phinolex / L&T
14/0.3(1.0Sqmm)FRLS
copper wire
elec 1.7.1
elec 1.7.4
PVC
insulated
flexible 100M
1001.00
1001.00
each
15
18.00
270.00
each
15
27.00
405.00
0.00
0.00
1676.00
Labour charges :
elec 8.1.77 Skilled Electrician
day
1.5
400.00
600.00
day
1.5
320.00
480.00
elec 8.185
day
1.5
320.00
480.00
Helpers
Add area allowence on labour charges @
Add contractor profit @ 14% on labour.
2.1.5
0%
0.00
0%
0.00
3236.00
215.73
Supply and Fixing of 16A 3pin and 6A 3pin plug socket with and 16A switch control duly recessed in
wall with MS switch deep box of 6" x8" x2 1/2" size covered with hylam sheet including earth
connections and all labour charges etc., complete. Plug Socket.
Makes : Gold Medal / ANCHOR/ OLIVE/Million ZOOM.
Taking Output = each
a) Material
elec-1.3.5
each
162.00
162.00
each
26.40
26.40
each
146.00
146.00
334.40
0.00
0.00
334.40
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.1
400.00
40.00
day
0.1
320.00
32.00
elec-8.1.85 Helpers
day
0.1
320.00
32.00
0%
0%
0.00
104.00
0.00
438.40
a) Material
elec-7.1.5
340.00
340.00
elec-1.3.1
MS box
54.00
54.00
0.00
394.00
El Data
P No 188
Index Specific
-code
ation No.
Description
2
Add contr profit @14% on material
Unit
QTY
Rate Rs.
0.00
Amount Rs.
ohr
6
0.00
394.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.2
400.00
80.00
day
0.2
320.00
64.00
elec-8.1.85 Helpers
day
0.12
320.00
38.40
0%
0%
0.00
182.40
0.00
Sundries
C) Cost for each
3.1.2
576.40
Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated flexible copper cable in existing pipe
for earth continuity including all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material
elec-1.5.1
100 M
1001.00
0.00
1001.00
0.00
1001.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.34
400.00
136.00
day
320.00
320.00
elec-8.1.85 Helpers
day
0.34
320.00
108.80
0%
0%
0.00
564.80
0.00
1565.80
15.70
10
3.1.4.a
Supply and run of 2 of 2.5 Sq mm PVC insulated flexible copper cable and 1 run of 1.00 Sq mm flexible
PVC insulated flexible copper cable in the existing conduit pipe for run of mains from main panel board
to TPN DB'S to swithc boards connections etc.,
Taking Output = 100 M
a) Material
elec-1.5.3
100 M
2389.20
4778.40
elec-1.5.1
100 M
1001.00
1001.00
5779.40
0.00
0.00
5779.40
b) Labour charges :
elec-8.1.77 Skilled Electrician (2.0 + 0.5)
day
1.005
400.00
402.00
day
320.00
960.00
day
1.005
320.00
321.60
0%
0%
0.00
1683.60
0.00
Sundries
El Data
P No 189
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
1
C) Cost for 100 RM
3.1.5
ohr
6
7463.00
11
Amount Rs.
74.65
Supply and 2 runs of 4.0 sq mm PVC insulated flexible copper cable and 1 run of 2.5 sq.mm flexible
PVC insulated copper cable for earthing in the existing conduit pipe for power point including labour
charges for 16A sockets. Make: Finolex / L&T
elec- 1.5.4
3650.00
7300.00
elec- 1.5.3
2390.00
2390.00
9690.00
0.00
9690.00
Labour Charges
Skilled Electrician (1.0 + 0.34)
day
1.34
400.00
536.00
day
320.00
1280.00
Helpers(1.0 + 0.34)
day
1.34
320.00
428.80
0%
0%
0.00
0.00
11934.80
12
3.3.7
119.35
Supply and run of 4 of 10 Sq mm PVC insulated flexible copper cable and 1 run of 4 Sq mm PVC
insulated flexible copper cable in the existing conduit pipe for run of mains from main panel board to
TPN DB'S with pin type lugs and connections etc.,complete
Taking Output = 100 M
a) Material
elec-1.5.6
1.5.4
100 M
8600.00
34400.00
3650.00
3650.00
0.00
38050.00
b) Labour charges :
elec-8.1.77 Skilled Electrician (2.0 + 0.5)
day
400.00
800.00
day
320.00
1920.00
day
320.00
640.00
0%
0%
0.00
3360.00
0.00
Sundries
C) Cost for 100 RM
41410.00
414.10
13
8.2.2
Supply, Transportation and fixing of 4' - 40 Watt box type flourescent single Tube Light fitting with Energy
saving electronic ballast, consuming 28 W suitable for 40 Watt tube on varnished teak wood round
blocks with flexible 3 core wire etc.,, complet Makes : Chowk: Trinic , tube : Philips / crompton
a) Material
elec-3.6.8 4' x 40 watts box type flourscent light fitting.
elec-3.7.16 Lamp cost of 40W
elec-8.1.35 Tw Round blocks
Rate per each
Add contr profit @14% on material
El Data
each
each
each
0.00
1
1
2
850.50
45.00
6.00
850.50
45.00
12.00
907.50
0.00
P No 190
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
Amount Rs.
ohr
6
907.50
a) Labour charges
day
0.10
400
day
0.10
320
40.00
32.00
979.50
Labour for 1 No
Supply and fixing of batten holder / slanting holder in lieu of ceiling rose of light point complete with all
connections and all labour charges with 40W bulb (for new installation).
Makes : Gold Medal /Million / Vimal
14
each
20.00
20.00
elec-3.7.1
each
12.00
12.00
each
21.00
-21.00
40W bulb
11.00
Add contr profit @14% on material
0.00
0.00
11.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.05
400.00
20.00
elec-8.1.85 Helpers
day
0.05
320.00
16.00
0%
0%
0.00
36.00
0.00
47.00
15
a) Material
elec-5.1.1
each
16
33
1600.00
1%
16.00
220.00
1600
16.00
1616.00
Add contr profit @14% on material
0.00
0.00
Total material cost
1616.00
Supply and erecting Electronic type regulator for ceiling fans 1200 mm sweep complete erected on
existing board.Make : Anchor / Gold Medal Olive / Million Zoom
a) Material
M
0.00
220.00
0.00
220.00
b) Labour charges.
elec-8.1.78 Semi skilled Electrician
day
Sundries.
Add area allowence on labour charges @
El Data
0.1
320.00
32.00
21.20
0%
0.00
P No 191
Index Specific
-code
ation No.
Description
2
Add contr profit @14% on Labour
Unit
QTY
Rate Rs.
Amount Rs.
ohr
0%
0.00
273.20
17
a) Material
elec-1.6.8
9.90
9.90
LS
3.00
3.00
12.90
0.00
0.00
12.90
b) Labour charges.
elec-8.1.77 Skilled Electrician
day
0.125
400.00
50.00
elec-8.1.85 Helper
day
0.125
320.00
40.00
0%
0%
0.00
90.00
0.00
102.90
18
a) Material
elec-5.1.14 300mm (12") 900 RPM H.D. Exhaust Fan
each
2645.00
1%
26.45
26.45
2671.45
0.00
0.00
19
2645.00
2671.45
Labour charges for fixing of Exhaust fan in wall with necessary connections and masonary work of
making hole, finishing etc., complete
a) Material
elec-1.6.8
elec-8.1.54 Cement
9.90
9.90
kg
25
5.60
140.00
149.90
0.00
0.00
149.90
b) Labour charges.
elec-8.1.77 Skilled Electrician
day
0.25
400.00
100.00
elec-8.1.85 Helper
day
0.25
320.00
80.00
elec-8.1.79 Mason
day
0.25
350.00
87.50
0%
0%
LS
El Data
0.00
267.50
0.00
24.34
24.34
441.75
P No 192
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
Amount Rs.
ohr
20
a) Material
elec-3.1.1
each
1400.00
each
45.00
1400.00
45.00
1445.00
0.00
0.00
1445.00
Fixing of 40W street light luminaire to the wall with 1.0 Mtr., 25mm dia GI pipe bracket and anti tilting MS
flat etc., including giving connections and labour charges etc., complete.
21
a) Material
elec-8.1.59 25mm dia G.I pipe light grade
elec-1.6.8
205.00
205.00
LS
9.90
19.80
25.00
LS
25.00
35.00
35.00
284.80
0.00
0.00
284.80
b) Labour charges
elec-8.1.77 Skilled Electrician/carpenter
day
0.2
400.00
80.00
elec-8.1.79 Mason
day
0.2
350.00
70.00
day
0.2
320.00
64.00
0%
0%
0.00
214.00
0.00
498.80
22
Nos
9100.00
9100.00
elec-2.8.2
Nos
7194.00
0.00
elec-2.9.6
Nos
1477.00
1477.00
elec-2.9.1
Nos
24
201.00
4824.00
15401.00
0.00
15401.00
b) Labour charges :
El Data
day
400.00
400.00
day
320.00
320.00
elec-8.1.85 Helpers
day
320.00
320.00
P No 193
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
ohr
6
0.00
Amount Rs.
1040.00
LS
19.00
0.00
19.00
16460.00
Say
16460.00
4.4.8
proposed
concealing,
a
1No.
Semifor
skilled
mason add the following:
b
1/4 bag
cement
Supply and fixing TPN Distribution board with IP-43 protection (Metal Door) suitable for 3 phase ELCB /
RCCB / FP Isolator as incomer and 10kA SP MCBs as outing going including internal connection and
labour charges for flush mounting etc., complete. 40A 4 Pole isolater 1 No 10KA 6-32 A range SPMCBS
8Nos for Outgoing. Make: MDS/GE/L&T Hanger/SIEMANS/SCHNEIDERS.
23
each
2491.00
2491.00
each
814.00
814.00
elec-2.9.1
each
12
201.00
2412.00
0.00
5717.00
0.00
5717.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.5
400.00
200.00
day
320.00
320.00
elec-8.1.85 Helpers
day
320.00
320.00
0%
0.00
0%
840.00
0.00
LS
14.00
14.00
6571.00
24
each
2491.00
2491.00
each
890.00
890.00
elec-2.9.1
each
201.00
1608.00
0.00
4989.00
0.00
4989.00
b) Labour charges :
El Data
day
0.5
400.00
200.00
day
320.00
320.00
P No 194
Index Specific
-code
ation No.
Description
elec-8.1.85 Helpers
Unit
QTY
Rate Rs.
day
320.00
Amount Rs.
ohr
6
320.00
0%
0.00
0%
840.00
0.00
LS
14.00
14.00
5843.00
25
SSR rateRs.246.20.
246.20
Providing independent earthling by excavating a trench to a depth of 2.1 M in all soils, as per size
specified in the Data, using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with necessary accessories
with hume pipe ring duly providing staggered holes
26
a) Material
Earth Work Excavation of Hard gravel Soil with
small boulder for trench 1st step of size 1.5 x 0.9 x
0.9 m
cum
1.21
122.11
147.75
cum
0.9
150.00
135.00
25.00
25.00
25% extra for narrow trench & pit and back filling
with Sand, Coke, Salt etc., and leveling
40mm dia 'B' Class G.I pipe
Mtr
2.5
301.00
752.50
Each
75.00
75.00
Each
16
5.00
80.00
Set
12.00
48.00
Each
100.00
100.00
Kg
20
8.00
160.00
elec-8.1.17 Salt
Kg
20
4.00
80.00
1603.25
0.00
0.00
1603.25
Each
day
0.5
320.00
160.00
Helpers
day
0.5
320.00
160.00
0%
0%
0.00
320.00
0.00
Sundries
Rate per each
Say
1923.30
Supply and Fixing of 3 phase meter Box, 3 Nos 100 A fuse units, Neutral link, on T.W block with all
accessaries etc., complete for finished items of work.
27
a) Material
elec-2.6.4
elec-1.4.7
each
484.00
1452.00
each
118.00
118.00
each
99.00
99.00
1669.00
El Data
P No 195
Index Specific
-code
ation No.
Description
2
Add contr profit @14% on material
Unit
QTY
Rate Rs.
Amount Rs.
ohr
0.00
0.00
1669.00
b) Labour charges
elec-8.1.77 Skilled Electrician
day
400.00
400.00
elec-8.1.85 Helper
day
320.00
1280.00
0%
0%
0.00
1680.00
0.00
50.00
3399.00
28
100 M
1010.00
1010.00
0.00
0.00
1010.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.34
315.00
107.10
day
285.00
285.00
day
0.34
285.00
96.90
0%
0%
0.00
489.00
0.00
Sundries
C) Cost for 100 RM
1499.00
15.00
29
48.00
48.00
elec-1.3.1
54.00
54.00
13.20
13.20
MS box
115.20
Add contr profit @14% on material
0.00
0.00
115.20
b) Labour charges :
El Data
day
0.1
315.00
31.50
day
0.1
285.00
28.50
elec-8.1.85 Helpers
day
0.1
285.00
28.50
P No 196
Index Specific
-code
ation No.
Description
Unit
QTY
Rate Rs.
0%
0%
Amount Rs.
ohr
6
0.00
88.50
0.00
Sundries
C) Cost for each
30
elec3.7.26 Supply
203.70
Lamp
of
115.00
115.00
Supply and laying of LAN cable Cat-6(A) UTP CABLE in the existing metallic/non metallic conduit pipe
with connections etc.,complete
Makes:D Link/Finolex
31
100 M
2580.00
0.00
2580.00
0.00
2580.00
b) Labour charges :
elec-8.1.77 Skilled Electrician
day
0.34
315.00
107.10
day
285.00
285.00
elec-8.1.85 Helpers
day
0.34
285.00
96.90
0%
0%
0.00
489.00
0.00
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
3069.00
30.70
El Data
P No 197
Name of the work : Sub Estiate for the work Providing Electrification to Model School
S.
NO
.
Quantity
Description of Work
Unit
Rate (Rs.)
in fig.
Amount
(Rs.)
CONDUIT PIPE
1 1250 RM
#REF!
ONE
RM
#REF!
#REF!
#REF!
ONE
RM
#REF!
#REF!
500 RM
WIRING
3
POINT
#REF!
#REF!
82 PTS #REF!
POINT
#REF!
#REF!
Supply and fixing of 3 Nos 6A 3 pin wall plug socket with 3 Nos. 6A EACH
switch control on a common switch board with earth continuity
including wire leads, earth connections along with all labour charges
etc., complete.
Makes : Anchor / Gold Medal Olive /Million Zoom
#REF!
#REF!
57
207 PTS Wiring with three runs of 1.0 sq.mm insulated PVC flexible
copper conductor cable (phase, neutral, earth) in the existing
conduit pipe with 6 Amps flush type switch, and 6 A 3/2 pin
socket on Separate switch board etc.,complete as required
Make:Million / Gold Medal
POINT
#REF!
#REF!
6
7
27 NOS #REF!
7 NOS Supply and fixing single phase DB in sheet steel enclosure
with metalic plug and socket with 1 No. 20/32A,10KA
SPMCB ( Motor characteristics MCBs) control including
making connections etc., complete concealing in wall.
Makes : MDS / L&T Hager.
EACH
EACH
#REF!
#REF!
#REF!
#REF!
57 NOS Supply and fixing of cat-6 RJ-45information outlets including dual EACH
#REF!
#REF!
face plate with MS box with modular plate cover with screws
connections etc., Makes: Belden/D link/Legrand
RUN OF MAINS
9
628 RM
ONE
RM
#REF!
#REF!
10 1985 RM
ONE
RM
#REF!
#REF!
11
420 RM
ONE
RM
#REF!
#REF!
12
44 RM
ONE
RM
#REF!
#REF!
13
50 RM
ONE
RM
#REF!
#REF!
14
224 RM
ONE
RM
#REF!
#REF!
ONE
RM
#REF!
#REF!
Makes: million/payal/goldmedal/powerflex
15
538 RM
Supply and laying of LAN cable Cat-6(A) UTP CABLE in the existing
metallic/non metallic conduit pipe with connections etc.,complete
Makes:D Link/Finolex
16
50 NOS Supply of 3feet length patch cords of make D link make / Beldan / EACH
200.00
10000.00
17
11 NOS Supply and fixing of telephone jack type socket with top on MS box EACH
#REF!
#REF!
Krone
with modular plate cover with screws connections etc., Makes: Gold
Medal Olive / Million zoom
LIGHT FITTINGS
18
306 NOS Supply, Transportation and fixing of 4' - 40 Watt box type flourescent EACH
#REF!
#REF!
19
85 NOS Supply and fixing of batten holder / slanting holder in lieu of ceiling EACH
#REF!
#REF!
20
157 NOS Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan with 3 EACH
#REF!
#REF!
21
157 NOS Supply and erecting Electronic type regulator for ceiling fans 1200 EACH
#REF!
#REF!
rose of light point complete with all connections and all labour
charges with 40W bulb (for new installation).
Makes : Gold Medal /Million / Vimal
Blades and double ball bearings with all standard accessories.
Makes: Crompton Aura / Bajaj R Gold / Havells Festiva / Usha
Premium.
22
157 NOS Labour charges for Fixing of Ceiling fan and regulator including EACH
#REF!
#REF!
23
14 NOS Supply of fresh air exhaust fan of heavy duty 250V A.C.50Hz.. EACH
#REF!
#REF!
24
14 NOS Labour charges for fixing of Exhaust fan in wall with necessary EACH
#REF!
#REF!
25
#REF!
#REF!
26
12 NOS Fixing of 40W street light luminaire to the wall with 1.0 Mtr., 25mm EACH
#REF!
#REF!
27
1 NOS Supply of Integral street light luminaire of 150W HPSV lamp fitting EACH
#REF!
#REF!
28
1 NOS Fixing of MV / SV/MH luminaire on wall with 1.0mt 40mm dia GI EACH
#REF!
#REF!
dia GI pipe bracket and anti tilting MS flat etc., including giving
connections and labour charges etc., complete.
DISTRIBUTION BOARDS
29
2 NOS Supply and fixing TPN - Vertical type Distribution board with IP -43 EACH
#REF!
#REF!
30
EACH
#REF!
#REF!
ONE
RM
#REF!
#REF!
#REF!
#REF!
31
32
33
34
250 RM
2 Nos Supply and fixing of 24 port switches of D link make including EACH
making connections and etc., complete
2 Nos Supply of 17U floor mounting net work rack with power spike
including all accessries of make HCL / Vall
2 Nos Supply and fixing TPN - Vertical type Distribution board with IP -43 EACH
Protection with 1 No. 63A TP MCB as incomer with 24 Nos. 10 kA
SPMCBs as outgoing including internal connection and labour
charges for flush mounting etc., complete.
Makes: MDS/ L&T Hager
CABLES
#REF!
#REF!
#REF!
35
100 Mtrs Supply of 3.5 Core 95 Sq. mm PVC XLPE armoured cable 1100 V.
36
upto 50 Sq,mm
200 Mtrs Earth work excavation of Trench in hard ground soil, laying of U.G cables
1 Mtr
#REF! on sand cushion
#REF! covering th
1 Mtr
#REF!
#REF!
EARTHING
37
38
1 NO
EACH
Supply and Fixing of 3 phase meter Box, 3 Nos 100 A fuse units, EACH
Neutral link, on T.W block with all accessaries etc., complete for
finished items of work.
#REF!
2521.00
TOTAL:
#REF!
2521.00
#REF!
Sl.
No
##
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
PCC
Rubble/Size Cement/Steel/RC
Earth/Sand/
Slabs/Shabad
Lead in
Stone/Cut
C poles/A.C & G.I
Gravel/Murru
Slabs/CC &
Kms
Stone/Coarse
Sheets/Packed
m/Lime/Surki
Laterite
aggregates
materials
Blocks/Wood
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
33.00
34.00
35.00
36.00
37.00
38.00
39.00
40.00
41.00
42.00
43.00
44.00
45.00
46.00
47.00
48.00
49.00
50.00
51.00
52.00
53.00
54.00
27.63
38.68
51.67
62.72
73.77
84.82
95.88
106.93
117.98
129.04
140.09
151.14
162.19
173.25
184.30
195.35
206.40
217.46
228.51
239.56
250.61
261.67
272.72
283.77
294.82
305.88
316.93
327.98
339.04
350.09
359.30
368.51
377.72
386.93
396.14
405.35
414.56
423.77
432.98
442.19
451.40
460.61
469.82
479.04
488.25
497.46
506.67
515.88
525.09
534.30
543.51
552.72
561.93
571.14
26.67
37.37
51.67
62.72
73.77
84.82
95.88
106.93
117.98
129.04
140.09
151.14
162.19
173.25
184.30
195.35
206.40
217.46
228.51
239.56
250.61
261.67
272.72
283.77
294.82
305.88
316.93
327.98
339.04
350.09
359.30
368.51
377.72
386.93
396.14
405.35
414.56
423.77
432.98
442.19
451.40
460.61
469.82
479.04
488.25
497.46
506.67
515.88
525.09
534.30
543.51
552.72
561.93
571.14
0.00
7.60
17.80
25.70
33.60
41.50
49.40
57.30
65.20
73.10
81.00
88.90
96.80
104.70
112.60
120.50
128.40
136.30
144.20
152.10
160.00
167.90
175.80
183.70
191.60
199.50
207.40
215.30
223.20
231.10
237.70
244.30
250.90
257.50
264.10
270.70
277.30
283.90
290.50
297.10
303.70
310.30
316.90
323.50
330.10
336.70
343.30
349.90
356.50
363.10
369.70
376.30
382.90
389.50
39.21
54.91
75.96
92.19
108.51
124.74
140.96
157.19
173.42
189.65
205.88
222.11
238.33
254.56
270.79
287.02
303.25
319.47
335.70
351.93
368.16
384.39
400.61
416.84
433.07
449.30
465.53
481.75
497.98
514.21
527.81
541.40
555.00
568.60
582.19
595.79
609.39
622.98
636.58
650.18
663.77
677.37
690.96
704.56
718.16
731.75
745.35
758.95
772.54
786.14
799.74
813.33
826.93
840.53
Water
16.49
23.07
30.70
37.28
43.86
50.44
57.02
63.60
70.18
76.75
83.33
89.91
96.49
103.07
109.65
116.23
122.81
129.39
135.96
142.54
149.12
155.70
162.28
168.86
175.44
182.02
188.60
195.18
201.75
208.33
213.86
219.39
224.91
230.44
235.96
241.49
247.02
252.54
258.07
263.60
269.12
274.65
280.18
285.70
291.23
296.75
302.28
307.81
313.33
318.86
324.39
329.91
335.44
340.96
Bricks
44.47
62.28
82.98
100.61
118.60
136.40
154.21
172.02
189.82
207.63
225.44
243.25
261.05
278.86
296.67
314.47
332.28
350.09
367.89
385.70
403.51
421.32
439.12
456.93
474.74
492.54
510.35
528.16
545.96
563.77
578.60
593.42
608.25
623.07
637.89
652.72
667.54
682.37
697.19
712.02
726.84
741.67
756.49
771.32
786.14
800.96
815.79
830.61
845.44
860.26
875.09
889.91
904.74
919.56
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
55.00
56.00
57.00
58.00
59.00
60.00
61.00
62.00
63.00
64.00
65.00
66.00
67.00
68.00
69.00
70.00
71.00
72.00
73.00
74.00
75.00
76.00
77.00
78.00
79.00
80.00
81.00
82.00
83.00
84.00
85.00
86.00
87.00
88.00
89.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
97.00
98.00
99.00
100.00
101.00
102.00
103.00
104.00
105.00
106.00
107.00
108.00
109.00
110.00
111.00
112.00
113.00
114.00
115.00
580.35
589.56
598.77
607.98
617.19
626.40
635.61
644.82
654.04
663.25
672.46
681.67
690.88
700.09
709.30
718.51
727.72
736.93
746.14
755.35
764.56
773.77
782.98
792.19
801.40
810.61
819.82
829.04
838.25
847.46
856.67
865.88
875.09
884.30
893.51
902.72
911.93
921.14
930.35
939.56
948.77
957.98
967.19
976.40
985.61
994.82
1004.04
1013.25
1022.46
1031.67
1040.88
1050.09
1059.30
1068.51
1077.72
1086.93
1096.14
1105.35
1114.56
1123.77
1132.98
580.35
589.56
598.77
607.98
617.19
626.40
635.61
644.82
654.04
663.25
672.46
681.67
690.88
700.09
709.30
718.51
727.72
736.93
746.14
755.35
764.56
773.77
782.98
792.19
801.40
810.61
819.82
829.04
838.25
847.46
856.67
865.88
875.09
884.30
893.51
902.72
911.93
921.14
930.35
939.56
948.77
957.98
967.19
976.40
985.61
994.82
1004.04
1013.25
1022.46
1031.67
1040.88
1050.09
1059.30
1068.51
1077.72
1086.93
1096.14
1105.35
1114.56
1123.77
1132.98
396.10
402.70
409.30
415.90
422.50
429.10
435.70
442.30
448.90
455.50
462.10
468.70
475.30
481.90
488.50
495.10
501.70
508.30
514.90
521.50
528.10
534.70
541.30
547.90
554.50
561.10
567.70
574.30
580.90
587.50
594.10
600.70
607.30
613.90
620.50
627.10
633.70
640.30
646.90
653.50
660.10
666.70
673.30
679.90
686.50
693.10
699.70
706.30
712.90
719.50
726.10
732.70
739.30
745.90
752.50
759.10
765.70
772.30
778.90
785.50
792.10
854.12
867.72
881.32
894.91
908.51
922.11
935.70
949.30
962.89
976.49
990.09
1003.68
1017.28
1030.88
1044.47
1058.07
1071.67
1085.26
1098.86
1112.46
1126.05
1139.65
1153.25
1166.84
1180.44
1194.04
1207.63
1221.23
1234.82
1248.42
1262.02
1275.61
1289.21
1302.81
1316.40
1330.00
1343.60
1357.19
1370.79
1384.39
1397.98
1411.58
1425.18
1438.77
1452.37
1465.96
1479.56
1493.16
1506.75
1520.35
1533.95
1547.54
1561.14
1574.74
1588.33
1601.93
1615.53
1629.12
1642.72
1656.32
1669.91
346.49
352.02
357.54
363.07
368.60
374.12
379.65
385.18
390.70
396.23
401.75
407.28
412.81
418.33
423.86
429.39
434.91
440.44
445.96
451.49
457.02
462.54
468.07
473.60
479.12
484.65
490.18
495.70
501.23
506.75
512.28
517.81
523.33
528.86
534.39
539.91
545.44
550.96
556.49
562.02
567.54
573.07
578.60
584.12
589.65
595.18
600.70
606.23
611.75
617.28
622.81
628.33
633.86
639.39
644.91
650.44
655.96
661.49
667.02
672.54
678.07
934.39
949.21
964.04
978.86
993.68
1008.51
1023.33
1038.16
1052.98
1067.81
1082.63
1097.46
1112.28
1127.11
1141.93
1156.75
1171.58
1186.40
1201.23
1216.05
1230.88
1245.70
1260.53
1275.35
1290.18
1305.00
1319.82
1334.65
1349.47
1364.30
1379.12
1393.95
1408.77
1423.60
1438.42
1453.25
1468.07
1482.89
1497.72
1512.54
1527.37
1542.19
1557.02
1571.84
1586.67
1601.49
1616.32
1631.14
1645.96
1660.79
1675.61
1690.44
1705.26
1720.09
1734.91
1749.74
1764.56
1779.39
1794.21
1809.04
1823.86
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
116.00
117.00
118.00
119.00
120.00
121.00
122.00
123.00
124.00
125.00
126.00
127.00
128.00
129.00
130.00
131.00
132.00
133.00
134.00
135.00
136.00
137.00
138.00
139.00
140.00
141.00
142.00
143.00
144.00
145.00
146.00
147.00
148.00
149.00
150.00
151.00
152.00
153.00
154.00
155.00
156.00
157.00
158.00
159.00
160.00
161.00
162.00
163.00
164.00
165.00
166.00
167.00
168.00
169.00
170.00
171.00
172.00
173.00
174.00
175.00
176.00
1142.19
1151.40
1160.61
1169.82
1179.04
1188.25
1197.46
1206.67
1215.88
1225.09
1234.30
1243.51
1252.72
1261.93
1271.14
1280.35
1289.56
1298.77
1307.98
1317.19
1326.40
1335.61
1344.82
1354.04
1363.25
1372.46
1381.67
1390.88
1400.09
1409.30
1418.51
1427.72
1436.93
1446.14
1455.35
1464.56
1473.77
1482.98
1492.19
1501.40
1510.61
1519.82
1529.04
1538.25
1547.46
1556.67
1565.88
1575.09
1584.30
1593.51
1602.72
1611.93
1621.14
1630.35
1639.56
1648.77
1657.98
1667.19
1676.40
1685.61
1694.82
1142.19
1151.40
1160.61
1169.82
1179.04
1188.25
1197.46
1206.67
1215.88
1225.09
1234.30
1243.51
1252.72
1261.93
1271.14
1280.35
1289.56
1298.77
1307.98
1317.19
1326.40
1335.61
1344.82
1354.04
1363.25
1372.46
1381.67
1390.88
1400.09
1409.30
1418.51
1427.72
1436.93
1446.14
1455.35
1464.56
1473.77
1482.98
1492.19
1501.40
1510.61
1519.82
1529.04
1538.25
1547.46
1556.67
1565.88
1575.09
1584.30
1593.51
1602.72
1611.93
1621.14
1630.35
1639.56
1648.77
1657.98
1667.19
1676.40
1685.61
1694.82
798.70
805.30
811.90
818.50
825.10
831.70
838.30
844.90
851.50
858.10
864.70
871.30
877.90
884.50
891.10
897.70
904.30
910.90
917.50
924.10
930.70
937.30
943.90
950.50
957.10
963.70
970.30
976.90
983.50
990.10
996.70
1003.30
1009.90
1016.50
1023.10
1029.70
1036.30
1042.90
1049.50
1056.10
1062.70
1069.30
1075.90
1082.50
1089.10
1095.70
1102.30
1108.90
1115.50
1122.10
1128.70
1135.30
1141.90
1148.50
1155.10
1161.70
1168.30
1174.90
1181.50
1188.10
1194.70
1683.51
1697.11
1710.70
1724.30
1737.89
1751.49
1765.09
1778.68
1792.28
1805.88
1819.47
1833.07
1846.67
1860.26
1873.86
1887.46
1901.05
1914.65
1928.25
1941.84
1955.44
1969.04
1982.63
1996.23
2009.82
2023.42
2037.02
2050.61
2064.21
2077.81
2091.40
2105.00
2118.60
2132.19
2145.79
2159.39
2172.98
2186.58
2200.18
2213.77
2227.37
2240.96
2254.56
2268.16
2281.75
2295.35
2308.95
2322.54
2336.14
2349.74
2363.33
2376.93
2390.53
2404.12
2417.72
2431.32
2444.91
2458.51
2472.11
2485.70
2499.30
683.60
689.12
694.65
700.18
705.70
711.23
716.75
722.28
727.81
733.33
738.86
744.39
749.91
755.44
760.96
766.49
772.02
777.54
783.07
788.60
794.12
799.65
805.18
810.70
816.23
821.75
827.28
832.81
838.33
843.86
849.39
854.91
860.44
865.96
871.49
877.02
882.54
888.07
893.60
899.12
904.65
910.18
915.70
921.23
926.75
932.28
937.81
943.33
948.86
954.39
959.91
965.44
970.96
976.49
982.02
987.54
993.07
998.60
1004.12
1009.65
1015.18
1838.68
1853.51
1868.33
1883.16
1897.98
1912.81
1927.63
1942.46
1957.28
1972.11
1986.93
2001.75
2016.58
2031.40
2046.23
2061.05
2075.88
2090.70
2105.53
2120.35
2135.18
2150.00
2164.82
2179.65
2194.47
2209.30
2224.12
2238.95
2253.77
2268.60
2283.42
2298.25
2313.07
2327.89
2342.72
2357.54
2372.37
2387.19
2402.02
2416.84
2431.67
2446.49
2461.32
2476.14
2490.96
2505.79
2520.61
2535.44
2550.26
2565.09
2579.91
2594.74
2609.56
2624.39
2639.21
2654.04
2668.86
2683.68
2698.51
2713.33
2728.16
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
177.00
178.00
179.00
180.00
181.00
182.00
183.00
184.00
185.00
186.00
187.00
188.00
189.00
190.00
191.00
192.00
193.00
194.00
195.00
196.00
197.00
198.00
199.00
200.00
201.00
202.00
203.00
204.00
205.00
206.00
207.00
208.00
209.00
210.00
211.00
212.00
213.00
214.00
215.00
216.00
217.00
218.00
219.00
220.00
221.00
222.00
223.00
224.00
225.00
226.00
227.00
228.00
229.00
230.00
231.00
232.00
233.00
234.00
235.00
236.00
237.00
1704.04
1713.25
1722.46
1731.67
1740.88
1750.09
1759.30
1768.51
1777.72
1786.93
1796.14
1805.35
1814.56
1823.77
1832.98
1842.19
1851.40
1860.61
1869.82
1879.04
1888.25
1897.46
1906.67
1915.88
1925.09
1934.30
1943.51
1952.72
1961.93
1971.14
1980.35
1989.56
1998.77
2007.98
2017.19
2026.40
2035.61
2044.82
2054.04
2063.25
2072.46
2081.67
2090.88
2100.09
2109.30
2118.51
2127.72
2136.93
2146.14
2155.35
2164.56
2173.77
2182.98
2192.19
2201.40
2210.61
2219.82
2229.04
2238.25
2247.46
2256.67
1704.04
1713.25
1722.46
1731.67
1740.88
1750.09
1759.30
1768.51
1777.72
1786.93
1796.14
1805.35
1814.56
1823.77
1832.98
1842.19
1851.40
1860.61
1869.82
1879.04
1888.25
1897.46
1906.67
1915.88
1925.09
1934.30
1943.51
1952.72
1961.93
1971.14
1980.35
1989.56
1998.77
2007.98
2017.19
2026.40
2035.61
2044.82
2054.04
2063.25
2072.46
2081.67
2090.88
2100.09
2109.30
2118.51
2127.72
2136.93
2146.14
2155.35
2164.56
2173.77
2182.98
2192.19
2201.40
2210.61
2219.82
2229.04
2238.25
2247.46
2256.67
1201.30
1207.90
1214.50
1221.10
1227.70
1234.30
1240.90
1247.50
1254.10
1260.70
1267.30
1273.90
1280.50
1287.10
1293.70
1300.30
1306.90
1313.50
1320.10
1326.70
1333.30
1339.90
1346.50
1353.10
1359.70
1366.30
1372.90
1379.50
1386.10
1392.70
1399.30
1405.90
1412.50
1419.10
1425.70
1432.30
1438.90
1445.50
1452.10
1458.70
1465.30
1471.90
1478.50
1485.10
1491.70
1498.30
1504.90
1511.50
1518.10
1524.70
1531.30
1537.90
1544.50
1551.10
1557.70
1564.30
1570.90
1577.50
1584.10
1590.70
1597.30
2512.89
2526.49
2540.09
2553.68
2567.28
2580.88
2594.47
2608.07
2621.67
2635.26
2648.86
2662.46
2676.05
2689.65
2703.25
2716.84
2730.44
2744.04
2757.63
2771.23
2784.82
2798.42
2812.02
2825.61
2839.21
2852.81
2866.40
2880.00
2893.60
2907.19
2920.79
2934.39
2947.98
2961.58
2975.18
2988.77
3002.37
3015.96
3029.56
3043.16
3056.75
3070.35
3083.95
3097.54
3111.14
3124.74
3138.33
3151.93
3165.53
3179.12
3192.72
3206.32
3219.91
3233.51
3247.11
3260.70
3274.30
3287.89
3301.49
3315.09
3328.68
1020.70
1026.23
1031.75
1037.28
1042.81
1048.33
1053.86
1059.39
1064.91
1070.44
1075.96
1081.49
1087.02
1092.54
1098.07
1103.60
1109.12
1114.65
1120.18
1125.70
1131.23
1136.75
1142.28
1147.81
1153.33
1158.86
1164.39
1169.91
1175.44
1180.96
1186.49
1192.02
1197.54
1203.07
1208.60
1214.12
1219.65
1225.18
1230.70
1236.23
1241.75
1247.28
1252.81
1258.33
1263.86
1269.39
1274.91
1280.44
1285.96
1291.49
1297.02
1302.54
1308.07
1313.60
1319.12
1324.65
1330.18
1335.70
1341.23
1346.75
1352.28
2742.98
2757.81
2772.63
2787.46
2802.28
2817.11
2831.93
2846.75
2861.58
2876.40
2891.23
2906.05
2920.88
2935.70
2950.53
2965.35
2980.18
2995.00
3009.82
3024.65
3039.47
3054.30
3069.12
3083.95
3098.77
3113.60
3128.42
3143.25
3158.07
3172.89
3187.72
3202.54
3217.37
3232.19
3247.02
3261.84
3276.67
3291.49
3306.32
3321.14
3335.96
3350.79
3365.61
3380.44
3395.26
3410.09
3424.91
3439.74
3454.56
3469.39
3484.21
3499.04
3513.86
3528.68
3543.51
3558.33
3573.16
3587.98
3602.81
3617.63
3632.46
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
238.00
239.00
240.00
241.00
242.00
243.00
244.00
245.00
246.00
247.00
248.00
249.00
250.00
251.00
252.00
253.00
254.00
255.00
256.00
257.00
258.00
259.00
260.00
261.00
262.00
263.00
264.00
265.00
266.00
267.00
268.00
269.00
270.00
271.00
272.00
273.00
274.00
275.00
276.00
277.00
278.00
279.00
280.00
281.00
282.00
283.00
284.00
285.00
286.00
287.00
288.00
289.00
290.00
291.00
292.00
293.00
294.00
295.00
296.00
297.00
298.00
2265.88
2275.09
2284.30
2293.51
2302.72
2311.93
2321.14
2330.35
2339.56
2348.77
2357.98
2367.19
2376.40
2385.61
2394.82
2404.04
2413.25
2422.46
2431.67
2440.88
2450.09
2459.30
2468.51
2477.72
2486.93
2496.14
2505.35
2514.56
2523.77
2532.98
2542.19
2551.40
2560.61
2569.82
2579.04
2588.25
2597.46
2606.67
2615.88
2625.09
2634.30
2643.51
2652.72
2661.93
2671.14
2680.35
2689.56
2698.77
2707.98
2717.19
2726.40
2735.61
2744.82
2754.04
2763.25
2772.46
2781.67
2790.88
2800.09
2809.30
2818.51
2265.88
2275.09
2284.30
2293.51
2302.72
2311.93
2321.14
2330.35
2339.56
2348.77
2357.98
2367.19
2376.40
2385.61
2394.82
2404.04
2413.25
2422.46
2431.67
2440.88
2450.09
2459.30
2468.51
2477.72
2486.93
2496.14
2505.35
2514.56
2523.77
2532.98
2542.19
2551.40
2560.61
2569.82
2579.04
2588.25
2597.46
2606.67
2615.88
2625.09
2634.30
2643.51
2652.72
2661.93
2671.14
2680.35
2689.56
2698.77
2707.98
2717.19
2726.40
2735.61
2744.82
2754.04
2763.25
2772.46
2781.67
2790.88
2800.09
2809.30
2818.51
1603.90
1610.50
1617.10
1623.70
1630.30
1636.90
1643.50
1650.10
1656.70
1663.30
1669.90
1676.50
1683.10
1689.70
1696.30
1702.90
1709.50
1716.10
1722.70
1729.30
1735.90
1742.50
1749.10
1755.70
1762.30
1768.90
1775.50
1782.10
1788.70
1795.30
1801.90
1808.50
1815.10
1821.70
1828.30
1834.90
1841.50
1848.10
1854.70
1861.30
1867.90
1874.50
1881.10
1887.70
1894.30
1900.90
1907.50
1914.10
1920.70
1927.30
1933.90
1940.50
1947.10
1953.70
1960.30
1966.90
1973.50
1980.10
1986.70
1993.30
1999.90
3342.28
3355.88
3369.47
3383.07
3396.67
3410.26
3423.86
3437.46
3451.05
3464.65
3478.25
3491.84
3505.44
3519.04
3532.63
3546.23
3559.82
3573.42
3587.02
3600.61
3614.21
3627.81
3641.40
3655.00
3668.60
3682.19
3695.79
3709.39
3722.98
3736.58
3750.18
3763.77
3777.37
3790.96
3804.56
3818.16
3831.75
3845.35
3858.95
3872.54
3886.14
3899.74
3913.33
3926.93
3940.53
3954.12
3967.72
3981.32
3994.91
4008.51
4022.11
4035.70
4049.30
4062.89
4076.49
4090.09
4103.68
4117.28
4130.88
4144.47
4158.07
1357.81
1363.33
1368.86
1374.39
1379.91
1385.44
1390.96
1396.49
1402.02
1407.54
1413.07
1418.60
1424.12
1429.65
1435.18
1440.70
1446.23
1451.75
1457.28
1462.81
1468.33
1473.86
1479.39
1484.91
1490.44
1495.96
1501.49
1507.02
1512.54
1518.07
1523.60
1529.12
1534.65
1540.18
1545.70
1551.23
1556.75
1562.28
1567.81
1573.33
1578.86
1584.39
1589.91
1595.44
1600.96
1606.49
1612.02
1617.54
1623.07
1628.60
1634.12
1639.65
1645.18
1650.70
1656.23
1661.75
1667.28
1672.81
1678.33
1683.86
1689.39
3647.28
3662.11
3676.93
3691.75
3706.58
3721.40
3736.23
3751.05
3765.88
3780.70
3795.53
3810.35
3825.18
3840.00
3854.82
3869.65
3884.47
3899.30
3914.12
3928.95
3943.77
3958.60
3973.42
3988.25
4003.07
4017.89
4032.72
4047.54
4062.37
4077.19
4092.02
4106.84
4121.67
4136.49
4151.32
4166.14
4180.96
4195.79
4210.61
4225.44
4240.26
4255.09
4269.91
4284.74
4299.56
4314.39
4329.21
4344.04
4358.86
4373.68
4388.51
4403.33
4418.16
4432.98
4447.81
4462.63
4477.46
4492.28
4507.11
4521.93
4536.75
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
299.00
300.00
301.00
302.00
303.00
304.00
305.00
306.00
307.00
308.00
309.00
310.00
311.00
312.00
313.00
314.00
315.00
316.00
317.00
318.00
319.00
320.00
321.00
322.00
323.00
324.00
325.00
326.00
327.00
328.00
329.00
330.00
331.00
332.00
333.00
334.00
335.00
336.00
337.00
338.00
339.00
340.00
341.00
342.00
343.00
344.00
345.00
346.00
347.00
348.00
349.00
350.00
351.00
352.00
353.00
354.00
355.00
356.00
357.00
358.00
359.00
2827.72
2836.93
2846.14
2855.35
2864.56
2873.77
2882.98
2892.19
2901.40
2910.61
2919.82
2929.04
2938.25
2947.46
2956.67
2965.88
2975.09
2984.30
2993.51
3002.72
3011.93
3021.14
3030.35
3039.56
3048.77
3057.98
3067.19
3076.40
3085.61
3094.82
3104.04
3113.25
3122.46
3131.67
3140.88
3150.09
3159.30
3168.51
3177.72
3186.93
3196.14
3205.35
3214.56
3223.77
3232.98
3242.19
3251.40
3260.61
3269.82
3279.04
3288.25
3297.46
3306.67
3315.88
3325.09
3334.30
3343.51
3352.72
3361.93
3371.14
3380.35
2827.72
2836.93
2846.14
2855.35
2864.56
2873.77
2882.98
2892.19
2901.40
2910.61
2919.82
2929.04
2938.25
2947.46
2956.67
2965.88
2975.09
2984.30
2993.51
3002.72
3011.93
3021.14
3030.35
3039.56
3048.77
3057.98
3067.19
3076.40
3085.61
3094.82
3104.04
3113.25
3122.46
3131.67
3140.88
3150.09
3159.30
3168.51
3177.72
3186.93
3196.14
3205.35
3214.56
3223.77
3232.98
3242.19
3251.40
3260.61
3269.82
3279.04
3288.25
3297.46
3306.67
3315.88
3325.09
3334.30
3343.51
3352.72
3361.93
3371.14
3380.35
2006.50
2013.10
2019.70
2026.30
2032.90
2039.50
2046.10
2052.70
2059.30
2065.90
2072.50
2079.10
2085.70
2092.30
2098.90
2105.50
2112.10
2118.70
2125.30
2131.90
2138.50
2145.10
2151.70
2158.30
2164.90
2171.50
2178.10
2184.70
2191.30
2197.90
2204.50
2211.10
2217.70
2224.30
2230.90
2237.50
2244.10
2250.70
2257.30
2263.90
2270.50
2277.10
2283.70
2290.30
2296.90
2303.50
2310.10
2316.70
2323.30
2329.90
2336.50
2343.10
2349.70
2356.30
2362.90
2369.50
2376.10
2382.70
2389.30
2395.90
2402.50
4171.67
4185.26
4198.86
4212.46
4226.05
4239.65
4253.25
4266.84
4280.44
4294.04
4307.63
4321.23
4334.82
4348.42
4362.02
4375.61
4389.21
4402.81
4416.40
4430.00
4443.60
4457.19
4470.79
4484.39
4497.98
4511.58
4525.18
4538.77
4552.37
4565.96
4579.56
4593.16
4606.75
4620.35
4633.95
4647.54
4661.14
4674.74
4688.33
4701.93
4715.53
4729.12
4742.72
4756.32
4769.91
4783.51
4797.11
4810.70
4824.30
4837.89
4851.49
4865.09
4878.68
4892.28
4905.88
4919.47
4933.07
4946.67
4960.26
4973.86
4987.46
1694.91
1700.44
1705.96
1711.49
1717.02
1722.54
1728.07
1733.60
1739.12
1744.65
1750.18
1755.70
1761.23
1766.75
1772.28
1777.81
1783.33
1788.86
1794.39
1799.91
1805.44
1810.96
1816.49
1822.02
1827.54
1833.07
1838.60
1844.12
1849.65
1855.18
1860.70
1866.23
1871.75
1877.28
1882.81
1888.33
1893.86
1899.39
1904.91
1910.44
1915.96
1921.49
1927.02
1932.54
1938.07
1943.60
1949.12
1954.65
1960.18
1965.70
1971.23
1976.75
1982.28
1987.81
1993.33
1998.86
2004.39
2009.91
2015.44
2020.96
2026.49
4551.58
4566.40
4581.23
4596.05
4610.88
4625.70
4640.53
4655.35
4670.18
4685.00
4699.82
4714.65
4729.47
4744.30
4759.12
4773.95
4788.77
4803.60
4818.42
4833.25
4848.07
4862.89
4877.72
4892.54
4907.37
4922.19
4937.02
4951.84
4966.67
4981.49
4996.32
5011.14
5025.96
5040.79
5055.61
5070.44
5085.26
5100.09
5114.91
5129.74
5144.56
5159.39
5174.21
5189.04
5203.86
5218.68
5233.51
5248.33
5263.16
5277.98
5292.81
5307.63
5322.46
5337.28
5352.11
5366.93
5381.75
5396.58
5411.40
5426.23
5441.05
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
360.00
361.00
362.00
363.00
364.00
365.00
366.00
367.00
368.00
369.00
370.00
371.00
372.00
373.00
374.00
375.00
376.00
377.00
378.00
379.00
380.00
381.00
382.00
383.00
384.00
385.00
386.00
387.00
388.00
389.00
390.00
391.00
392.00
393.00
394.00
395.00
396.00
397.00
398.00
399.00
400.00
401.00
402.00
403.00
404.00
405.00
406.00
407.00
408.00
409.00
410.00
411.00
412.00
413.00
414.00
415.00
416.00
417.00
418.00
419.00
420.00
3389.56
3398.77
3407.98
3417.19
3426.40
3435.61
3444.82
3454.04
3463.25
3472.46
3481.67
3490.88
3500.09
3509.30
3518.51
3527.72
3536.93
3546.14
3555.35
3564.56
3573.77
3582.98
3592.19
3601.40
3610.61
3619.82
3629.04
3638.25
3647.46
3656.67
3665.88
3675.09
3684.30
3693.51
3702.72
3711.93
3721.14
3730.35
3739.56
3748.77
3757.98
3767.19
3776.40
3785.61
3794.82
3804.04
3813.25
3822.46
3831.67
3840.88
3850.09
3859.30
3868.51
3877.72
3886.93
3896.14
3905.35
3914.56
3923.77
3932.98
3942.19
3389.56
3398.77
3407.98
3417.19
3426.40
3435.61
3444.82
3454.04
3463.25
3472.46
3481.67
3490.88
3500.09
3509.30
3518.51
3527.72
3536.93
3546.14
3555.35
3564.56
3573.77
3582.98
3592.19
3601.40
3610.61
3619.82
3629.04
3638.25
3647.46
3656.67
3665.88
3675.09
3684.30
3693.51
3702.72
3711.93
3721.14
3730.35
3739.56
3748.77
3757.98
3767.19
3776.40
3785.61
3794.82
3804.04
3813.25
3822.46
3831.67
3840.88
3850.09
3859.30
3868.51
3877.72
3886.93
3896.14
3905.35
3914.56
3923.77
3932.98
3942.19
2409.10
2415.70
2422.30
2428.90
2435.50
2442.10
2448.70
2455.30
2461.90
2468.50
2475.10
2481.70
2488.30
2494.90
2501.50
2508.10
2514.70
2521.30
2527.90
2534.50
2541.10
2547.70
2554.30
2560.90
2567.50
2574.10
2580.70
2587.30
2593.90
2600.50
2607.10
2613.70
2620.30
2626.90
2633.50
2640.10
2646.70
2653.30
2659.90
2666.50
2673.10
2679.70
2686.30
2692.90
2699.50
2706.10
2712.70
2719.30
2725.90
2732.50
2739.10
2745.70
2752.30
2758.90
2765.50
2772.10
2778.70
2785.30
2791.90
2798.50
2805.10
5001.05
5014.65
5028.25
5041.84
5055.44
5069.04
5082.63
5096.23
5109.82
5123.42
5137.02
5150.61
5164.21
5177.81
5191.40
5205.00
5218.60
5232.19
5245.79
5259.39
5272.98
5286.58
5300.18
5313.77
5327.37
5340.96
5354.56
5368.16
5381.75
5395.35
5408.95
5422.54
5436.14
5449.74
5463.33
5476.93
5490.53
5504.12
5517.72
5531.32
5544.91
5558.51
5572.11
5585.70
5599.30
5612.89
5626.49
5640.09
5653.68
5667.28
5680.88
5694.47
5708.07
5721.67
5735.26
5748.86
5762.46
5776.05
5789.65
5803.25
5816.84
2032.02
2037.54
2043.07
2048.60
2054.12
2059.65
2065.18
2070.70
2076.23
2081.75
2087.28
2092.81
2098.33
2103.86
2109.39
2114.91
2120.44
2125.96
2131.49
2137.02
2142.54
2148.07
2153.60
2159.12
2164.65
2170.18
2175.70
2181.23
2186.75
2192.28
2197.81
2203.33
2208.86
2214.39
2219.91
2225.44
2230.96
2236.49
2242.02
2247.54
2253.07
2258.60
2264.12
2269.65
2275.18
2280.70
2286.23
2291.75
2297.28
2302.81
2308.33
2313.86
2319.39
2324.91
2330.44
2335.96
2341.49
2347.02
2352.54
2358.07
2363.60
5455.88
5470.70
5485.53
5500.35
5515.18
5530.00
5544.82
5559.65
5574.47
5589.30
5604.12
5618.95
5633.77
5648.60
5663.42
5678.25
5693.07
5707.89
5722.72
5737.54
5752.37
5767.19
5782.02
5796.84
5811.67
5826.49
5841.32
5856.14
5870.96
5885.79
5900.61
5915.44
5930.26
5945.09
5959.91
5974.74
5989.56
6004.39
6019.21
6034.04
6048.86
6063.68
6078.51
6093.33
6108.16
6122.98
6137.81
6152.63
6167.46
6182.28
6197.11
6211.93
6226.75
6241.58
6256.40
6271.23
6286.05
6300.88
6315.70
6330.53
6345.35
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
421.00
422.00
423.00
424.00
425.00
426.00
427.00
428.00
429.00
430.00
431.00
432.00
433.00
434.00
435.00
436.00
437.00
438.00
439.00
440.00
441.00
442.00
443.00
444.00
445.00
446.00
447.00
448.00
449.00
450.00
451.00
452.00
453.00
454.00
455.00
456.00
457.00
458.00
459.00
460.00
461.00
462.00
463.00
464.00
465.00
466.00
467.00
468.00
469.00
470.00
471.00
472.00
473.00
474.00
475.00
476.00
477.00
478.00
479.00
480.00
481.00
3951.40
3960.61
3969.82
3979.04
3988.25
3997.46
4006.67
4015.88
4025.09
4034.30
4043.51
4052.72
4061.93
4071.14
4080.35
4089.56
4098.77
4107.98
4117.19
4126.40
4135.61
4144.82
4154.04
4163.25
4172.46
4181.67
4190.88
4200.09
4209.30
4218.51
4227.72
4236.93
4246.14
4255.35
4264.56
4273.77
4282.98
4292.19
4301.40
4310.61
4319.82
4329.04
4338.25
4347.46
4356.67
4365.88
4375.09
4384.30
4393.51
4402.72
4411.93
4421.14
4430.35
4439.56
4448.77
4457.98
4467.19
4476.40
4485.61
4494.82
4504.04
3951.40
3960.61
3969.82
3979.04
3988.25
3997.46
4006.67
4015.88
4025.09
4034.30
4043.51
4052.72
4061.93
4071.14
4080.35
4089.56
4098.77
4107.98
4117.19
4126.40
4135.61
4144.82
4154.04
4163.25
4172.46
4181.67
4190.88
4200.09
4209.30
4218.51
4227.72
4236.93
4246.14
4255.35
4264.56
4273.77
4282.98
4292.19
4301.40
4310.61
4319.82
4329.04
4338.25
4347.46
4356.67
4365.88
4375.09
4384.30
4393.51
4402.72
4411.93
4421.14
4430.35
4439.56
4448.77
4457.98
4467.19
4476.40
4485.61
4494.82
4504.04
2811.70
2818.30
2824.90
2831.50
2838.10
2844.70
2851.30
2857.90
2864.50
2871.10
2877.70
2884.30
2890.90
2897.50
2904.10
2910.70
2917.30
2923.90
2930.50
2937.10
2943.70
2950.30
2956.90
2963.50
2970.10
2976.70
2983.30
2989.90
2996.50
3003.10
3009.70
3016.30
3022.90
3029.50
3036.10
3042.70
3049.30
3055.90
3062.50
3069.10
3075.70
3082.30
3088.90
3095.50
3102.10
3108.70
3115.30
3121.90
3128.50
3135.10
3141.70
3148.30
3154.90
3161.50
3168.10
3174.70
3181.30
3187.90
3194.50
3201.10
3207.70
5830.44
5844.04
5857.63
5871.23
5884.82
5898.42
5912.02
5925.61
5939.21
5952.81
5966.40
5980.00
5993.60
6007.19
6020.79
6034.39
6047.98
6061.58
6075.18
6088.77
6102.37
6115.96
6129.56
6143.16
6156.75
6170.35
6183.95
6197.54
6211.14
6224.74
6238.33
6251.93
6265.53
6279.12
6292.72
6306.32
6319.91
6333.51
6347.11
6360.70
6374.30
6387.89
6401.49
6415.09
6428.68
6442.28
6455.88
6469.47
6483.07
6496.67
6510.26
6523.86
6537.46
6551.05
6564.65
6578.25
6591.84
6605.44
6619.04
6632.63
6646.23
2369.12
2374.65
2380.18
2385.70
2391.23
2396.75
2402.28
2407.81
2413.33
2418.86
2424.39
2429.91
2435.44
2440.96
2446.49
2452.02
2457.54
2463.07
2468.60
2474.12
2479.65
2485.18
2490.70
2496.23
2501.75
2507.28
2512.81
2518.33
2523.86
2529.39
2534.91
2540.44
2545.96
2551.49
2557.02
2562.54
2568.07
2573.60
2579.12
2584.65
2590.18
2595.70
2601.23
2606.75
2612.28
2617.81
2623.33
2628.86
2634.39
2639.91
2645.44
2650.96
2656.49
2662.02
2667.54
2673.07
2678.60
2684.12
2689.65
2695.18
2700.70
6360.18
6375.00
6389.82
6404.65
6419.47
6434.30
6449.12
6463.95
6478.77
6493.60
6508.42
6523.25
6538.07
6552.89
6567.72
6582.54
6597.37
6612.19
6627.02
6641.84
6656.67
6671.49
6686.32
6701.14
6715.96
6730.79
6745.61
6760.44
6775.26
6790.09
6804.91
6819.74
6834.56
6849.39
6864.21
6879.04
6893.86
6908.68
6923.51
6938.33
6953.16
6967.98
6982.81
6997.63
7012.46
7027.28
7042.11
7056.93
7071.75
7086.58
7101.40
7116.23
7131.05
7145.88
7160.70
7175.53
7190.35
7205.18
7220.00
7234.82
7249.65
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
482.00
483.00
484.00
485.00
486.00
487.00
488.00
489.00
490.00
491.00
492.00
493.00
494.00
495.00
496.00
497.00
498.00
499.00
500.00
501.00
502.00
503.00
504.00
505.00
506.00
507.00
508.00
509.00
510.00
511.00
512.00
513.00
514.00
515.00
4513.25
4522.46
4531.67
4540.88
4550.09
4559.30
4568.51
4577.72
4586.93
4596.14
4605.35
4614.56
4623.77
4632.98
4642.19
4651.40
4660.61
4669.82
4679.04
4688.25
4697.46
4706.67
4715.88
4725.09
4734.30
4743.51
4752.72
4761.93
4771.14
4780.35
4789.56
4798.77
4807.98
4817.19
4513.25
4522.46
4531.67
4540.88
4550.09
4559.30
4568.51
4577.72
4586.93
4596.14
4605.35
4614.56
4623.77
4632.98
4642.19
4651.40
4660.61
4669.82
4679.04
4688.25
4697.46
4706.67
4715.88
4725.09
4734.30
4743.51
4752.72
4761.93
4771.14
4780.35
4789.56
4798.77
4807.98
4817.19
3214.30
3220.90
3227.50
3234.10
3240.70
3247.30
3253.90
3260.50
3267.10
3273.70
3280.30
3286.90
3293.50
3300.10
3306.70
3313.30
3319.90
3326.50
3333.10
3339.70
3346.30
3352.90
3359.50
3366.10
3372.70
3379.30
3385.90
3392.50
3399.10
3405.70
3412.30
3418.90
3425.50
3432.10
6659.82
6673.42
6687.02
6700.61
6714.21
6727.81
6741.40
6755.00
6768.60
6782.19
6795.79
6809.39
6822.98
6836.58
6850.18
6863.77
6877.37
6890.96
6904.56
6918.16
6931.75
6945.35
6958.95
6972.54
6986.14
6999.74
7013.33
7026.93
7040.53
7054.12
7067.72
7081.32
7094.91
7108.51
2706.23
2711.75
2717.28
2722.81
2728.33
2733.86
2739.39
2744.91
2750.44
2755.96
2761.49
2767.02
2772.54
2778.07
2783.60
2789.12
2794.65
2800.18
2805.70
2811.23
2816.75
2822.28
2827.81
2833.33
2838.86
2844.39
2849.91
2855.44
2860.96
2866.49
2872.02
2877.54
2883.07
2888.60
7264.47
7279.30
7294.12
7308.95
7323.77
7338.60
7353.42
7368.25
7383.07
7397.89
7412.72
7427.54
7442.37
7457.19
7472.02
7486.84
7501.67
7516.49
7531.32
7546.14
7560.96
7575.79
7590.61
7605.44
7620.26
7635.09
7649.91
7664.74
7679.56
7694.39
7709.21
7724.04
7738.86
7753.68
Total
Per
456.20
280.70
140.40
877.30
Hour
519.70
322.20
153.10
995.00
Hour
411.00
280.70
140.40
832.10
Hour
424.50
239.10
117.00
780.60
Hour
Hour
2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @
0.00 Rs.
add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Per
Hour
Hour
Hour
36.85
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @
0.00 Rs.
add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
4 Lead up to 4 Km:
Out put
=
Rate
456.20
280.70
140.40
29.48
Rate
456.20
280.70
140.40
39.31
Per
Hour
Hour
Hour
49.13
Hour
1.00 Cum
5.00 Cum
Rate
Per
0.00%
0.00%
0.00%
0.00%
14.00%
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
68.43
42.11
21.06
0.00
131.60
26.32
3.68
Rs.
30.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
95.80
58.95
29.48
0.00
184.23
36.85
5.16
Rs.
42.01
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
127.74
78.60
39.31
0.00
245.65
49.13
6.88
Rs.
56.01
Amount
0.34
0.34
0.34
0.00
Hour
Rate
456.20
280.70
140.40
56.16
Per
Hour
Hour
Hour
70.18
Hour
Rate
456.20
280.70
140.40
8.42
Per
Hour
Hour
Hour
10.53
Hour
1.00 Cum
59.66
1.00 Cum
Hour
Hour
Hour
1.00 Cum
5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @
0.00 Rs.
add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
456.20
280.70
140.40
47.74
Rate
456.20
280.70
140.40
7.02
Per
Hour
Hour
Hour
8.77
1.00 Cum
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
155.11
95.44
47.74
0.00
298.29
59.66
8.35
Rs.
68.01
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
182.48
112.28
56.16
0.00
350.92
70.18
9.83
Rs.
80.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
27.37
16.84
8.42
0.00
52.63
10.53
1.47
Rs.
12.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.81
14.04
7.02
0.00
43.87
8.77
1.23
Rs.
10.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
68.43
42.11
21.06
0.00
131.60
26.32
3.68
Rs.
28.90
Rate
456.20
280.70
140.40
21.06
26.32
Per
Hour
Hour
Hour
2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @
0.00 Rs.
add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Rate
456.20
280.70
140.40
39.31
Per
Hour
Hour
Hour
49.13
Hour
Rate
456.20
280.70
140.40
47.74
Per
Hour
Hour
Hour
59.66
Hour
Rate
456.20
280.70
140.40
56.16
Per
Hour
Hour
Hour
70.18
Hour
1.00 Cum
Hour
1.00 Cum
5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
36.85
1.00 Cum
4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Per
Hour
Hour
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @
0.00 Rs.
add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Rate
456.20
280.70
140.40
29.48
1.00 Cum
Rate
456.20
280.70
140.40
8.42
Per
Hour
Hour
Hour
10.53
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
95.80
58.95
29.48
0.00
184.23
36.85
5.16
Rs.
40.40
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
127.74
78.60
39.31
0.00
245.65
49.13
6.88
Rs.
56.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
155.11
95.44
47.74
0.00
298.29
59.66
8.35
Rs.
68.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
182.48
112.28
56.16
0.00
350.92
70.18
9.83
Rs.
80.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
27.37
16.84
8.42
0.00
52.63
10.53
1.47
Rs.
12.00
Rate
456.20
280.70
140.40
7.02
Per
Hour
Hour
Hour
8.77
1.00 Cum
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.81
14.04
7.02
0.00
43.87
8.77
1.23
Rs.
10.00
Per
Hour
Hour
Hour
16.45
Rate
456.20
280.70
140.40
29.48
Per
Hour
Hour
Hour
23.03
Hour
1.00 MT
3 Lead up to 3 Km:
Out put
=
8.00 MT
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Rate
456.20
280.70
140.40
21.06
Rate
456.20
280.70
140.40
39.31
Per
Hour
Hour
Hour
30.71
Hour
1.00 MT
4 Lead up to 4 Km:
Out put
=
8.00 MT
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
Rate
456.20
280.70
140.40
47.74
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
68.43
42.11
21.06
0.00
131.60
16.45
2.30
Rs.
18.75
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
95.80
58.95
29.48
0.00
184.23
23.03
3.22
Rs.
26.25
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
127.74
78.60
39.31
0.00
245.65
30.71
4.30
Rs.
35.01
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
155.11
95.44
47.74
0.00
298.29
37.29
Per
Hour
Hour
Hour
43.87
Hour
Rate
456.20
280.70
140.40
8.42
Per
Hour
Hour
Hour
6.58
Hour
1.00 MT
Rate
456.20
280.70
140.40
56.16
1.00 MT
Hour
1.00 MT
5 Lead up to 5 Km:
Out put
=
8.00 MT
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
37.29
Rate
456.20
280.70
140.40
7.02
Per
Hour
Hour
Hour
5.48
1.00 MT
Rs.
5.22
Rs.
42.51
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
182.48
112.28
56.16
0.00
350.92
43.87
6.14
Rs.
50.01
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
27.37
16.84
8.42
0.00
52.63
6.58
0.92
Rs.
7.50
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.81
14.04
7.02
0.00
43.87
5.48
0.77
Rs.
6.25
Rate
456.20
280.70
140.40
21.06
Per
Hour
Hour
Hour
38.71
Rate
456.20
280.70
140.40
29.48
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
68.43
42.11
21.06
0.00
131.60
38.71
5.42
Rs.
42.40
Rs.
Rs.
Rs.
Rs.
Amount
95.80
58.95
29.48
0.00
Rate for
3.40 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
72.25
Hour
Rate
456.20
280.70
140.40
47.74
Per
Hour
Hour
Hour
87.73
Hour
Rate
456.20
280.70
140.40
56.16
Per
Hour
Hour
Hour
103.21
Hour
1.00 Cum
Per
Hour
Hour
Hour
1.00 Cum
5 Lead up to 5 Km:
Out put
=
3.40 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Rate
456.20
280.70
140.40
39.31
1.00 Cum
4 Lead up to 4 Km:
Out put
=
3.40 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
3.40 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
54.19
Rate
456.20
280.70
140.40
8.42
Per
Hour
Hour
Hour
15.48
Hour
1.00 Cum
Rate
456.20
280.70
140.40
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
184.23
54.19
7.59
Rs.
59.40
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
127.74
78.60
39.31
0.00
245.65
72.25
10.12
Rs.
82.40
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
155.11
95.44
47.74
0.00
298.29
87.73
12.28
Rs.
100.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
182.48
112.28
56.16
0.00
350.92
103.21
14.45
Rs.
117.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
27.37
16.84
8.42
0.00
52.63
15.48
2.17
Rs.
17.60
Rs.
Rs.
Rs.
Amount
22.81
14.04
7.02
7.02
12.90
1.00 Cum
Rs.
Rs.
Rs.
Rs.
0.00
43.87
12.9
1.81
Rs.
14.70
Rate
411.00
Per
Hour
Rs.
Amount
61.65
280.70
Hour
Rs.
42.11
140.40
Hour
Rs.
21.06
21.06
Rs.
Rs.
Rs.
Rs.
0.00
124.82
15.60
2.18
Rs.
17.80
2 Lead up to 2 Km:
Out put
=
8000 Ltrs
0.21 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
15.60
Rate
411.00
Per
Hour
Rs.
Amount
86.31
280.70
Hour
Rs.
58.95
140.40
Hour
Rs.
29.48
29.48
Rs.
Rs.
Rs.
Rs.
0.00
174.74
21.84
3.06
Rs.
24.90
3 Lead up to 3 Km:
Out put
=
8000 Ltrs
0.28 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
21.84
Rate
411.00
Per
Hour
Rs.
Amount
115.08
280.70
Hour
Rs.
78.60
140.40
Hour
Rs.
39.31
39.31
Rs.
Rs.
Rs.
Rs.
0.00
232.99
29.12
4.08
Rs.
33.20
Rs.
Amount
139.74
4 Lead up to 4 Km:
Out put
=
8000 Ltrs
0.34 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
29.12
Rate
411.00
Per
Hour
280.70
Hour
Rs.
95.44
140.40
Hour
Rs.
47.74
47.74
Rs.
Rs.
Rs.
Rs.
0.00
282.92
35.37
4.95
Rs.
40.30
5 Lead up to 5 Km:
Out put
=
8000 Ltrs
0.40 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
35.37
Rate
411.00
Per
Hour
Rs.
Amount
164.40
280.70
Hour
Rs.
112.28
140.40
Hour
Rs.
56.16
56.16
Rs.
Rs.
Rs.
Rs.
0.00
332.84
41.61
5.83
Rs.
47.40
41.61
Rate
411.00
Per
Hour
Rs.
Amount
24.66
280.70
Hour
Rs.
16.84
140.40
Hour
Rs.
8.42
8.42
Rs.
Rs.
Rs.
Rs.
0.00
49.92
6.24
0.87
Rs.
7.10
6.24
Rate
411.00
Per
Hour
Rs.
Amount
20.55
280.70
Hour
Rs.
14.04
140.40
Hour
Rs.
7.02
7.02
Rs.
Rs.
Rs.
Rs.
0.00
41.61
5.20
0.73
Rs.
5.90
5.20
Out put
=
3000 Nos
0.15 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
Rate
424.50
Per
Hour
Rs.
Amount
63.68
239.10
Hour
Rs.
35.87
117.00
Hour
Rs.
17.55
17.55
Rs.
Rs.
Rs.
Rs.
0.00
117.10
39.03
5.46
Rs.
48.10
2 Lead up to 2 Km:
Out put
=
3000 Nos
0.21 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
39.03
Rate
424.50
Per
Hour
Rs.
Amount
89.15
239.10
Hour
Rs.
50.21
117.00
Hour
Rs.
24.57
24.57
Rs.
Rs.
Rs.
Rs.
0.00
163.93
54.64
7.65
Rs.
67.30
3 Lead up to 3 Km:
Out put
=
3000 Nos
0.28 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
54.64
Rate
424.50
Per
Hour
Rs.
Amount
118.86
239.10
Hour
Rs.
66.95
117.00
Hour
Rs.
32.76
32.76
Rs.
Rs.
Rs.
Rs.
0.00
218.57
72.86
10.20
Rs.
89.80
4 Lead up to 4 Km:
Out put
=
3000 Nos
0.34 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
72.86
Rate
424.50
Per
Hour
Rs.
Amount
144.33
239.10
Hour
Rs.
81.29
117.00
Hour
Rs.
39.78
39.78
Rs.
Rs.
Rs.
Rs.
0.00
265.40
88.47
12.39
Rs.
109.00
88.47
5 Lead up to 5 Km:
Out put
=
3000 Nos
0.40 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
Rate
424.50
Per
Hour
Rs.
Amount
169.80
239.10
Hour
Rs.
95.64
117.00
Hour
Rs.
46.80
46.80
Rs.
Rs.
Rs.
Rs.
0.00
312.24
104.08
14.57
Rs.
128.30
104.08
Rate
424.50
Per
Hour
Rs.
Amount
25.47
239.10
Hour
Rs.
14.35
117.00
Hour
Rs.
7.02
7.02
Rs.
Rs.
Rs.
Rs.
0.00
46.84
15.61
2.19
Rs.
19.20
15.61
Rate
424.50
Per
Hour
Rs.
Amount
21.23
239.10
Hour
Rs.
11.96
117.00
Hour
Rs.
5.85
5.85
Rs.
Rs.
Rs.
Rs.
0.00
39.04
13.01
1.82
Rs.
16.00
13.01
LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
345.00
0.25 day Mazdoor
295.00
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
77.20
Per
day
day
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
77.20
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.005 day Head mazdoor
0.125 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 Cum
14.04
Rate
Per
345.00
295.00
day
day
38.61
7.02
Rs.
Rs.
14.04
1.97
Rs.
15.20
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
1.73
36.88
38.61
0.00
38.61
38.61
7.02
0.98
Rs.
7.60
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for masonry work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 Cum
C) For Cement (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate
Per
345.00
295.00
day
day
154.40
28.07
Rate
Per
345.00
295.00
day
day
77.20
14.04
Rate
Per
345.00
295.00
day
day
463.20
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
6.90
147.50
154.40
0.00
154.40
154.40
28.07
3.93
Rs.
32.00
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
77.20
14.04
1.97
Rs.
16.01
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
20.70
442.50
463.20
0.00
463.20
463.20
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 MT
D) For Structural steel, Steel bars (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.14 add overheads and contractors profit at 14%
on Rs.
Total rate for
1.00 MT
46.32
Rate
Per
345.00
295.00
day
day
463.20
46.32
Rate
Per
345.00
295.00
day
day
555.15
55.52
Rate
Per
345.00
295.00
day
day
555.15
55.52
77.20
Rs.
Rs.
46.32
6.48
Rs.
52.80
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
20.70
442.50
463.20
0.00
463.20
463.20
46.32
6.48
Rs.
52.80
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
24.15
531.00
555.15
0.00
555.15
555.15
55.52
7.77
Rs.
63.29
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
24.15
531.00
555.15
0.00
555.15
555.15
55.52
7.77
Rs.
63.29
Per
day
day
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
77.20
38.60
38.60
Rate
Per
345.00
295.00
day
day
77.20
38.60
Rs.
5.40
Rs.
44.00
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
77.20
38.60
5.40
Rs.
44.00
LOADING & UNLOADING CHARGES BY MANUAL MEANS (INCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
345.00
0.25 day Mazdoor
295.00
Per
Amount
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
424.50
Hour
Rs.
212.25
239.10
Hour
Rs.
119.55
117.00
Hour
Rs.
58.50
58.50
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
390.30
467.50
467.50
85
11.90
Rs.
96.90
77.20
85.00
Rate
Per
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
1.73
36.88
38.61
0.00
38.61
424.50
Hour
Rs.
70.47
239.10
Hour
Rs.
39.69
38.61
Amount
117.00
19.42
Hour
30.58
Rs.
19.42
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
129.58
168.19
168.19
30.58
4.28
Rs.
34.86
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
Rate
Per
Amount
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
6.90
147.50
154.40
0.00
154.40
154.40
424.50
Hour
Rs.
212.25
239.10
Hour
Rs.
119.55
117.00
Hour
Rs.
58.50
58.50
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
390.30
544.70
544.70
99.04
13.87
Rs.
112.91
99.04
Rate
Per
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
424.50
Hour
Rs.
106.13
239.10
Hour
Rs.
59.78
117.00
Hour
Rs.
29.25
29.25
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
195.16
272.36
272.36
49.52
6.93
77.20
49.52
Amount
1.00 Cum
Rs.
56.45
Rate
Per
Amount
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
20.70
442.50
463.20
0.00
463.20
463.20
424.50
Hour
Rs.
424.50
239.10
Hour
Rs.
239.10
117.00
Hour
Rs.
117.00
117.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
780.60
1243.80
1243.80
124.38
17.41
Rs.
141.79
124.38
Rate
Per
Amount
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
24.15
531.00
555.15
0.00
555.15
555.15
424.50
Hour
Rs.
424.50
239.10
Hour
Rs.
239.10
117.00
Hour
Rs.
117.00
117.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
780.60
1335.75
1335.75
133.58
18.70
Rs.
152.28
133.58
Rate
Per
345.00
295.00
day
day
555.15
Amount
Rs.
Rs.
Rs.
Rs.
24.15
531.00
555.15
0.00
Rs.
555.15
424.50
Hour
Rs.
424.50
239.10
Hour
Rs.
239.10
117.00
Hour
Rs.
117.00
117.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
780.60
1335.75
1335.75
133.58
18.70
Rs.
152.28
133.58
Rate
Per
Amount
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
24.15
531.00
555.15
0.00
555.15
555.15
424.50
Hour
Rs.
424.50
239.10
Hour
Rs.
239.10
117.00
Hour
Rs.
117.00
117.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
780.60
1335.75
1335.75
133.58
18.70
Rs.
152.28
133.58
Per
Amount
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.45
73.75
77.20
0.00
77.20
424.50
Hour
Rs.
140.09
239.10
Hour
Rs.
78.90
117.00
Hour
Rs.
38.61
38.61
Rs.
0.00
77.20
167.40
Rs.
Rs.
Rs.
Rs.
Rs.
257.60
334.80
334.80
167.40
23.44
Rs.
190.84
Rate
Per
Amount
345.00
295.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
20.70
442.50
463.20
0.00
463.20
463.20
424.50
Hour
Rs.
424.50
239.10
Hour
Rs.
239.10
117.00
Hour
Rs.
117.00
117.00
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
780.60
1243.80
1243.80
621.9
87.07
Rs.
708.97
621.90
Per
Amount
Hour
Rs.
57.17
322.20
Hour
Rs.
35.44
153.10
Hour
Rs.
16.84
422.80
Hour
Rs.
25.37
280.70
Hour
Rs.
16.84
140.40
Hour
Rs.
8.42
25.26
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
160.08
160.08
29.11
4.08
Rs.
33.19
29.11
Rate
Per
519.70
Hour
Rs.
41.58
322.20
Hour
Rs.
25.78
153.10
Hour
Rs.
12.25
12.25
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
79.61
79.61
14.47
2.03
Rs.
16.50
14.47
Amount
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Machinery:
0.17 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.
Rate
Per
519.70
Hour
Rs.
88.35
322.20
Hour
Rs.
54.77
153.10
Hour
Rs.
26.03
422.80
Hour
Rs.
50.74
280.70
Hour
Rs.
33.68
140.40
Hour
Rs.
16.85
42.88
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
270.42
270.42
49.17
6.88
Rs.
56.05
49.17
Amount