Académique Documents
Professionnel Documents
Culture Documents
1.
GENERAL INFORMATION
Spice Homes is looking to support in the development of a Griham- Low cost housing
project. The Company is currently procuring the design cum Project management
consultancy services to undertake Design, Supervision and Quality Assurance, etc., for
the construction of phase-I of proposed Griham-low cost housing project, on
Hapur Bypass Road, Meerut, U.P. at distance of 2.5 kms. from Delhi.
2.
PROJECT BACKGROUND
Spice Homes Pvt. Ltd. is a joint ventures formed by One City Group and Spice Jet Pvt.
Ltd. with the vision to develop affordable housing at Meerut. Spice Homes will be
undertaking the design, construction and sale of Griham project. Griham will consist of
construction of E.W.S units, L.I.G. units and Villas (duplex independent homes) with
conventional construction technology. The project is developed in two phases. Phase-I of
the project is spread over an area of 10.33 Acres, with 73% of the area as open spaces.
Each tower is G+3 buildings with four apartments at each floor.
3.
3.1. The main objectives of this consulting assignment is to procure project management
services for all the project phases pre construction, construction and post construction.
Works shall include but not limited to:
a) Construction Planning, Co-ordination and commissioning of the project.
b) Site co-ordination and quality Control during the construction of the project.
_________________________________________________________________________________________________
4.
SCOPE OF WORK
The scope of work shall include conceptual design, detailed design of building along with
services complete and project management services from the initial site survey to final
handover of building to employer.
The estimated cost of building is xxx crores and consultant shall have to ensure that the
project is designed and undertaken within this amount. The various activities broadly
involved in the above said services are:
4.1.11.
The Employer will call for tenders for the construction of building inclusive of
all facilities and amenities. The Consultant shall also assist in the preparation of the
_________________________________________________________________________________________________
comparative statement of the offers received from building firms. Assist the Employer in
identifying the contractor.
4.1.12.
implementation at site.
4.2.2. Shall physically verify all dimensions of site and ensure that they are as per drawings.
Discrepancies shall be notified to contractor immediately for remedying. Shall be
responsible to maintain the dimension at site as per the drawing.
4.2.3. Will be responsible for overall monitoring of the construction works and should be
available at site everyday (including nights if the contractor carries out work in shifts to
achieve the project completion schedule) for supervision & coordination of site work
with the Employer and Contractors.
_________________________________________________________________________________________________
4.2.4. Will ensure deployment of requisite number of qualified and experienced Engineers
(Civil, Plumbing and Electrical, HVAC) at site on full time basis to supervise the day
to day works and also shall be responsible for monitoring of the progress of work as
per approved drawings, construction procedures and practices and to ensure quality in
day to day work as per specifications and standards.
4.2.5. Shall be responsible to maintain the records of day-to-day works
4.2.6. Shall be responsible for checking the levels, steel reinforcement, centring, shuttering and
scaffolding, etc.
4.2.7. Shall be responsible to supervise the day to day works like earth work, PCC, RCC,
brick masonry, joinery, floorings and all Civil, PH and Electrical works (Internal and
External), HVAC and all other items as stipulated in the bill of quantities in
Agreement with contractors.
4.2.8. Checking all the measurements recorded in the bill prepared by contractor at site with
respect to approved drawings and to certify the accuracy. If in case, it is necessary to
take measurements at site and record and finalize the bills, the consultant shall also do
so to make timely payment for the works done.
(a)
The consultant shall verify the progressive bills submitted by the builder with
reference to the work carried out on the project. Hundred percent verification of the
quantum of work done shall be carried out before recommending for passing the bill
and making payment. The Employers representative shall be present while taking such
measurement. The consultant shall certify the accuracy within three to four days from
the date of receipt of bill from contractor / by the Officer designated by the Employer.
Minimum ten percent of such measurements will be checked by Officer designated by
the Employer.
4.2.9. For bills / measurements not submitted by the contractor, the consultant shall take
measurements jointly with contractors representative, record them in measurement
books (MBs) supplied by Employer and obtain contractors signature in token of
acceptance & prepare bills. Care shall be taken to take timely measurement of such
items which may get embedded or hidden measurements and not susceptible for
_________________________________________________________________________________________________
_________________________________________________________________________________________________
4.2.18. Shall ensure that contractors have taken requisite All Risk Insurance Policies to
cover workman under Workman Compensation Act, loss / damage caused by natural
calamities / accident / accidental collapse of partially completed work, materials and
plant at site and for third party claims for injury / damages. Consultant shall ensure
that all such policies remain in force throughout the execution of project.
4.2.19. Shall ensure that all instructions to the contactors are issued in writing to the
contractor. Consultant shall maintain the record of all such instructions for verification
at any time. It will be consultant responsibility to regularize all verbal instructions
given by competent authority in unavoidable circumstances by obtaining written
confirmations/ratifications. Consultant shall ensure that extra/deviated items are not
executed unless approved by Employer and rates are finalized. A register for
extra/substituted items shall be maintained by Consultant.
4.2.20. Shall ensure safety of structure by taking all necessary precautions and by not allowing
excessive construction loads such as dumping of excessive materials, overcrowding on
floors and shall avoid such other factors which will endanger the safety of structure
during construction.
4.2.21. Shall take custody of objects of value and antiquity found on site during excavation or
otherwise and hand over to Employer official.
4.2.22. Shall keep a track of permissions required from local authorities and get revalidated
whenever necessary.
4.2.23. Shall ensure that safety of personnel working at site/inspecting the site by taking
precautions by putting barricades, night lamps, near trenches, pits, open shafts, lift
shafts, edge of floors, terraces and such other places and to insist on compliance of
safety code such as use of helmets, etc, on work site.
4.2.24. The consultant shall make their own arrangements at no extra cost to the Employer
for instruments/equipment such as theodolites, levelling instruments, prismatic
compass, chain, measuring tapes, plain tables and ranging rods, such other equipment /
instruments including tents for shelter for the staff of consultant, etc.
4.2.25. Suggest modification, if any, due to site conditions and advice reasoned justification of
_________________________________________________________________________________________________
cost variations on account of resultant extra items and excess supported by proper
analysis.
4.2.26. The consultant shall see that advance action is taken by the builder to make suitable
provisions for inserts during construction of civil works for various services like
electricity, air conditioning, water supply, sewage system ventilation etc.
4.2.27. If the work done by the builder is found to not satisfactory, consultant can instruct
the builder to suspend the work intimating at the same time about the suspension of
work to the officer designated by the Employer. The work can be resumed only with
the approval of the officer designated by the Employer.
4.2.28. Prepare necessary snag list after virtual completion of work (before contractors leave
site).
4.3. Quality Control
4.3.1. Submission of Detailed schedules technical formats for inspection and testing of
materials, indicating the test/inspections procedures and applicable acceptance limits at
works/test house and site for materials and equipment well in advance and got approved
by the employer. Monitor the quality of the work and control the quality as per
specification, relevant codes and as per sound engineering practices.
4.3.2. Maintain the registers for mandatory tests to be conducted for all materials before
incorporation in work. The guidelines may be taken from the officer designated by the
Employer regarding the registers to be maintained.
4.3.3. Inspect and approve the materials at site as per specifications before they are used in
work.
4.3.4. Shall be responsible for obtaining good workmanship with respect to lines, levels,
plumb, finish, etc. Shall check all centre-lines, dimensions, levels and plumb at all
stages of work with reference to working drawings and shall ensure correct dimensions
of all elements.
4.3.5. Shall ensure that work proceeds as per tender conditions and specifications. All
material brought to site shall be of approved quality and make, rejected material is
_________________________________________________________________________________________________
removed from site and work executed is of high standard, good workmanship and
desired quality. Consultant shall also submit weekly reports of materials used. Any
compromise of quality in materials or workmanship shall be brought to the notice of the
officer designated by the employer in writing for taking necessary action. Consultant
shall also bring to the notice of the Employer any slippage in the progress of work as
per schedule and any likely slippage due to constraints like short supply of
construction materials, labour problems, non-availability of drawings etc.
4.3.6. Inspection and certification of equipment at manufacturers works for HVAC,
Electrical, Communication, Fire- fighting systems or any other equipment will be
planned in coordination with the officer designated by the Employer who may depute
his representative for the inspection.
the matter of approving such bills, the consultant shall conform adherence to the rules
and instructions issued by Employer and intimate to the Employer, guarantee and
correctness of all such certificates and shall hold themselves responsible for the
correctness of all bills and certificates issued, scrutinized or checked by them, as to
the quality of the work concerned as well as the quantities of various items of
works. Before certifying any bill consultant shall ensure that the work being certified
is, in general in accordance with the designs.
4.4.7. Shall check periodically the quantities recorded for various items and keep watch on
excess / shortage. Consultant shall account for all variations in tender quantities with
respect to execution drawings and submit a report. Consultant shall assess impact of
excessive quantities on the cost of project and wherever felt necessary by Employer,
prepare a Running Summary of Cost for perusal of Employer. Consultant shall obtain
approval from Employer if the quantities put to tender are likely to exceed by 10%
prior to giving green signal to contractor to go ahead with the work
4.4.8. Shall prepare Running Summary of Cost for the project once in six months or as
desired by Employer and ensure that there will be no cost overrun. Consultant shall
help Employer in preparing a note of revised sanction for the project.
Consultant shall ensure that following are not recommended for payment in interim
bills / final bills.
Payment for the work done in extended period without sanction for the time
extension.
4.4.9. Shall co-ordinate with all agencies working at site, liaison with local authorities
/government agencies for proper permissions / commencement certificate / completion
certificate, etc.
4.4.10. Shall ensure that work proceeds smoothly and not hampered for want of decisions /
drawings / clarifications.
_________________________________________________________________________________________________
4.4.11. Shall submit physical and financial progress reports once every month or as desired by
Employer in standard preform approved by Employer.
4.4.12. Shall anticipate time overruns, well before completion date and obtain requests for
extensions from contractors. Consultant shall submit contractors request for extension
of time along with his recommendations well within time. Bill for work done in
extended time, yet to be sanctioned, shall not be recommended. consultant will note
that only competent authority in Employer namely officer designated by the
Employer/ Project Engineer/Project Administrator / Dean / Director of Employer only
have authority to grant permissions for extensions.
4.4.13. Shall advise Employer with regard to extra claims / disputes / arbitration cases
between Employer and the Contractors, if any and assist Employer in case of any
dispute till the cases are resolved either by mutual negotiation or through arbitration
or court, as the case may be.
4.4.14. Shall suggest modifications, if any, due to site conditions and advise reasoned
justification of cost variations on account of resultant extra items and excess supported
by proper analysis.
4.4.15. To forecast issues ahead in time that would delay the project and caution clients for
appropriate action.
4.4.16. To provide value engineering service that will result in economical and quality end
product.
4.5. Commissioning
4.5.1. The consultant shall submit detailed schedule for commissioning of the various
subsystems, equipment and the whole integrated facility, in consultation with the
employer. This schedule will cover the checks/tests/ inspection proposed, and the target
dates for completion.
4.5.2. After commissioning the entire facility, a commissioning report containing (i) salient
specifications of materials/equipment/systems along with applicable standards (ii)
Reports of inspection/testing carried at works and test houses (iii) Results of site tests
_________________________________________________________________________________________________
(iv)Defects noticed and rectified during commissioning and (v) warranty details of
equipment and systems shall have to be submitted
4.5.3. Arrange for finalizing As Built Drawings of all the facilities including architectural,
structural and services and submit the same to Employer. Consultant shall co-ordinate
with all the parties who might be responsible for making their respective drawings.
5.
5.1.1. Consultant shall carry out detailed inspection on completion of project and get rectified
all defects noticed during inspection. Consultant shall also carry out detailed
inspection during defects liability period and get rectified all defects noticed during
such inspection before the end of defects liability period.
5.1.2. Consultant shall advise Employer with regards to extra claims or disputes /
arbitration cases between Employer and the contractor/s, if any, and assist in case of any
dispute till the cases are resolved either by mutual negotiation or through arbitration or
court as the case may be.
5.1.3. Consultant should collect the Guarantee Bond for Water Proofing & Anti Termite
Treatment and as built drawings and it should be handed over to the Employer.
Defect Liability period shall be one year after the completion or shall pass one rainy
season whichever is later
5.
DELIVERABLES
The consultant will deliver the following:
Progress reports relating time, cost and quality including verification of bills,
fortnightly.
_________________________________________________________________________________________________
The quarterly Budget requirement forecast over the whole project period at the
beginning and updated every quarter.
Shall maintain cement register, steel register, daily labor register, drawing register,
hindrance register, register for payment of advances and recoveries, register for
reconciliation of materials to facilitate recoveries, register for movement of field
books / measurement books, site instructions book, diary of work,
Registers for mandatory tests to be conducted for all materials before incorporation
in work.
He shall submit periodic reports concerning quality standard and progress of the
project
Consultant shall maintain account for all variations in tender quantities with respect
to execution drawings and shall submit a report on it
Running Summary of Cost for the project once in six months or as desired
by Employer.
6. REPORTING
1. The Consultant will report directly to Project coordinator from Spice Homes Pvt. Ltd.
who will supervise the assignment.
_________________________________________________________________________________________________
2. All reports are to be written in English. The Consultant will provide an electronic
version of all the required deliverables. The reporting will be completed in form and
substance acceptable to Spice Homes Pvt. Ltd.
8. QUALIFICATIONS
The successful candidate will have the following qualifications:
Capacity to think creatively in dealing with policy and operational issues while
maintaining a strong client and results orientation;
9.1.Consultant is expected to ensure that men of proven ability and adequately qualified
are only employed at site and they work diligently. In case, Employer finds any
Engineer/s not up to the mark, consultant will have to withdraw him / them from
site and replace him / them by posting new one/s in his / their position. Employer
reserves the right to remove such personnel and ask for a substitute of required
calibre. In case an Engineer/s resigns from their employment, consultant shall
immediately provide a substitute of equivalent calibre. Consultant shall not make any
changes in the personnel deployed by them on work site without prior permission.
_________________________________________________________________________________________________
9.2. The consultant shall furnish the list of Engineers and Supervisors (Civil and Electrical)
with details of their qualifications, experience, etc., to the Employer.
9.3. The Employer undertakes no responsibility in respect of any life, health, accident,
travel and any other insurance for the personnel deployed by consultant.
9.4. The consultant shall be responsible for any damage or loss on account of neglect of
professional duty or conduct on the part of such staff or Engineers or others. To this
effect, the consultant shall indemnify Employer.
9.5.The consultant shall not have any objection to Employer maintaining any Engineering
staff at its own cost at the site of work to carry out work and duties allotted to them by
employer, in respect of all the work at site or other areas outside the scope of
consultant works for overall surveillance, security and verification
9.6.Consultant shall provide manpower at site timely and only experienced persons will be
provided at site.
9.7.
( CIVIL )
practical Experience.
Two full time Diploma CIVIL holder
with 3 to 5 years minimum practical
Experience.
_________________________________________________________________________________________________
Electrical / Communication,
Planner
The above requirement is the visualized minimum. However, more Engineers and other
categories of staff may have to be appointed, if necessary, for satisfactory supervision
and co-ordination, it is specifically agreed that the Employer shall have no
responsibility for any Staff / Officers / Engineers engaged by the consultant and the said
consultant alone shall be responsible as employer.
9.8. Confidentiality
Except with the prior written consent by the Employer, the consultant and their
representatives shall not any time communicate to any person or entity any confidential
information disclosed to them for the purpose of the services. The consultant shall not
publicize any information pertaining to Employer which is discussed with them
during course of execution of work in the interest of project completion.
9.9. Exclusions:
All exclusions if any not included in the scope of work should be spelt out in the offer
which will be subjected to review by the Employer.
10.
_________________________________________________________________________________________________
Lights, Fan, PC. Etc. For the site office will have to be arranged by consultant. It shall
be open to the employer to abandon or give up at any stage of the construction of any of
the site buildings or any part thereof. In the event of such abandonment or giving up or
in the event of termination of the agreement, the consultant shall be paid fees up to
duration worked by them.
11.
PROFESSIONAL INDEMNITY
Consultant warrant that it shall exercise high degree of care and diligence in rendering
the services pursuant to this agreement and that such services shall be of a high
quality and standard satisfactory to employer. The consultant shall indemnify employer
from any damage or loss arising from such lack of care and diligence or arising out
of any unsatisfactory performance of service by consultant. For this purpose,
consultant shall subscribe to a professional liability insurance policy with a
nationalized insurance company for an amount equivalent to 20% of the total fee
payable by employer to the consultant. Consultant shall provide adequate evidence to
employer, if asked for, showing that such insurance has been taken and being maintained
and that all the premium thereon have been paid.
12.
DISPUTE SETTLEMENT
In case of any dispute or difference arising between the parties during the progress of or
after construction or abandonment of the work as to the meaning of construction of this
contract or touching or relating either to the said buildings or works, or to any other
matter or thing arising directly or indirectly under this contract, then and in such an
event the same shall be referred to the director Spice Homes Pvt. Ltd. who shall alone be
empowered to refer the said dispute to a sole arbitrator of his choice. The decision of
director shall be binding and conclusive upon both the said parties and this clause
shall be deemed a submission within the meaning of Arbitration and Conciliation Act
1996.
_________________________________________________________________________________________________
It is specifically agreed that the consultant shall continue to render its services provided
herein with all due diligence, professional skill and tact not withstanding that any matter,
question or dispute has been referred to the director for his decision.
it is further agreed between the parties that the decision of the arbitrator on all matters of
dispute is final and binding and questionable only in the court of law hereto that the
Meerut courts alone shall have the exclusive jurisdiction.
13. CONFIDENTIALITY STATEMENT
All data and information received from Spice Homes Pvt. Ltd. for the purpose of this
assignment are to be treated confidentially and are only to be used in connection with the
execution of these Terms of Reference. All intellectual property rights arising from the
execution of these Terms of Reference are assigned to Spice Homes Pvt. Ltd. The
contents of written materials obtained and used in this assignment may not be disclosed
to any third parties without the expressed advance written authorization of the Spice
Homes Pvt. Ltd
_________________________________________________________________________________________________