Vous êtes sur la page 1sur 13

(1990). Proc.

ISRM International Symposium on Static and Dynamic Considerations in Rock Engineering,


Mbabane, Swaziland, pp. 91-101.

Use of Forward Probe Coring Methods and Rexote Sensing


for Investigation of Geological Conditions ahead of
Drill and Blast and TBM Tunnel Drivages

T.G. Carter
Colder Associates, Toronto, Canada

ABSTRACT Design of tunnels and mine openings through areas of fractured and faulted
ground demands attention to detail in unravelling the geology of the area through which
the tunnel is to be excavated. For pressure tunnels in particular, where high static and
dynamic water pressure conditions can exist, detailed attention to local site geology is
imperative to ensuring that design requirements of minimal leakage and resistance to
hydrofracture are maintained.

Forward probe drilling and long angled underground diamond core drilling methods provide
useful tools that can aid prediction of major fracture intersections ahead of tunnel
drivages. These methods, coupled with effective pre-design use of remote sensing and
geophysical techniques provide a rational means by which the tunnel engineer can gain
information necessary for design of both temporary and permanent support elements.

INTRODU~TI0N

Compiling adequate investigation data on mainly by prediction or avoidance of mixed-


ground conditions ahead of an advancing face conditions. Secondly, it would allow
excavation face poses a commonplace problem prediction of any offsets in the strata
in tunnelling. Collection of accurate pre- which could indicate zones of faulting or
design and pre-excavation information is disturbance where grouting or localized
especially critical where significant extra rock support might be required to
natural (static) or induced (dynamic) water suit encountered ground conditions.
pressure problems are anticipated.

For the TBM drivage of the twin submarine


access tunnels for the new Donkin-Morien
Coal Mine off Cape Breton Island, Nova S

Scotia, Canada, (Figure 1), it was NOAS 0 A

recognized that detailed prediction ahead


of the drivages would help early
recognition of problem ground conditions
that could give rise to inflows of seawater
at static heads in excess of 180 psi. The
acquisition of reliable stratigraphic data
ahead of the tunnelling advance was also
ATL ANTIC
seen as a useful means for optimizing
OCEA N
tunnel drivage lengths to within horizons
of better quality rock.
0 0 00 30 •0 5O~

As a full face TBM drivage was envisaged NOVA


SCOTIA
for the tunnels, such optimization was seen
to serve two purposes. Firstly, it would Figure 1 Location Plan
likely help in minimizing cutter changes Donkin-Morien Mine Access Tunnels
and excavation problems during drivage,
For the waterways for the Drakensberg Hydro
Power Scheme, on the borders between Natal,
South Africa and Lesotho, (Figure 2),
acquisition of geological data on rock
conditions ahead of the various drill and
blast tunnels was deemed critical not only
for rock support design but also from the
hydraulic design viewpoint. Accurate,
detailed geological information was sought
specifically for optimizing the locations
of the necessary transition zones between
the concrete-lined pressure tunnels and the
steel-lined penstocks in order to resist
hydrofracture under the high dynamic water
5~ALA 0 400 800 k,~
pressure heads imposed on the tunnels
during operation. Figure 2 Site Location of the
Drakensberg Pumped Storage Scheme
DRAKENSBERG SCHEME
of the overall scheme, the maximum internal
hydraulic pressure head at the downstream
The Drakensberg Pumped Storage Scheme, end of the pressure tunnels was envisaged
comprises an upper reservoir, twin headrace to vary from 500m.(static) to more than
and pressure tunnels and a single tailrace 600m. (static plus water-hammer). Thus, as
tunnel connecting the main cavern complex rock cover in the vicinity of the main
to a lower reservoir; (Pyzikowski, 1982). caverns was only 180m. at the proposed
The works have been constructed within elevation of the scroll casings of the
essentially horizontally bedded sedimentary turbines, part of the original layout of
rocks comprising mudstones, siltstones and the scheme envisaged that a section of the
sandstones which in places are transected pressure tunnels would be steel-lined to
by dolerite infilled faults and dykes and obviate hydrofracture problems (De \Jitt,
by steep angle shear and normal faults. 1983; Sharp and Gonano, 1982).

At the design stage, the locations of the In order to achieve the maximum possible
tunnels, and the elevations of the crowns cover immediately upstream of the power
and intersections for the main caverns were station and hence minimise hydrofracture
optimized on the basis of an evaluation of potential within the concrete-lined part of
the available site investigation geological the tunnel while also limiting the required
data within the constraints imposed by length of steel lining, a ruling minimum
hydraulic and construction requirements. grade of 1 in 20 was adopted from the main
cavern complex, as far upstream as the
Hydraulic considerations were of extreme initially proposed end of the steel-lined
importance for the layout of the pressure penstocks (Figure 3). Upstream of this
tunnels and penstocks. Due to the geometry transition, a maximum grade of 1 in 10 was

HEADRACE TUNNELS
-SURGE SHAFTS
~800-
7m. TO HEADRACE INTAKE 163L+m. TO TAILRACE OUTFALL
290

MACHINE HALL
bOO-
A

z
0
400-
-j
w

200 —

P ENS TO C K S HALL

000 i LOCATION OF FAULTS


A AND B
SCALED ZOO 40Dm.

Figure 3 Arrangement of Waterways adjacent to the Main Cavern Complex at Drakensberg


selected to ensure efficient tunnelling and sandstone units recognized from detailed
concrete lining operations (Eastwood and de stratigraphic correlation of the deep
Witt, 1982). surface diamond drillhole core log data;
(ie. in the Delta Sandstone horizon, refer
Elimination of areal hydrofracture of the to Figure 3).
tunnel lining and rock mass by the elevated
pressures in the concrete lined pressure Similar geological optimization was carried
tunnels was central to the design concept. out to position the cavern crowns. In order
Accordingly, considerable effort was to assist crown excavation and avoid shear
expended during the project design phase in overstress problems at the haunches, the
determining the onset of hydrofracture crowns were selected to follow thin, but
under different stress regimes and for distinct sandstone units, (Sharp et al.,
different rock materials, (Bowcock et 1979, Mellors and Sharp, 1982). The machine
al.,1976; Gonano and Sharp, 1983). To this and valve pits were also carefully laid out
end, a full scale test chamber was to maximize excavation within sandstone.
constructed in an area of weak rock and Detailed design layout of the total complex
tested in order to refine pertinent design was also optimized to avoid intersecting
parameters, (Sharp and Gonano, 1982). dykes or unfavourably oriented structural
discontinuities. As a further design aid,
In parallel with this work, all available summary 3D geological compilation diagrams
geological site investigation data was were prepared for critical intersection
evaluated to optimize the location for the areas and for the overall main cavern
transition from the steel-lined penstocks complex (Figure 4). These diagrams, and
to the concrete lined pressure tunnels. detailed longitudinal and cross-section
Considerable emphasis was placed in this geological compilation drawings were used
evaluation on ensuring that the transition throughout construction to check excavation
section would be located in the most compliance with design crown elevations.
massively bedded, highest modulus, least Stringent blasting control was also
hydrofracture prone rock a thickly bedded
- maintained to ensure minimal damage to the
sandstone unit if possible. At the tender thin sandstone or interbedded sandstone-
stage, therefore, the transition zone was siltstone units selected to constitute the
laid out to fall within one of the thickest cavern crowns. (Hallier et al., 1982.)

UN 43

~UN 45

UN 48

TRANSFORMER HALL

MHTE

GROUP

NTERSEOOEO SAI~STDNE AND SILTSTDNE GROUP I

GROUP III

GROUP V

Figure 4 Isometric Diagram showing Summary Geology of Power Station Complex


Within the main caverns and access tunnels, o Surface geological maps and traverse
detailed mapping disclosed no major information; and,
discrepancies between as-predicted and
as-encountered geology. This was not the o Detailed geophysical data, (from
case upstream of the main cavern complex, surface seismic and magnetometer
however. Here, over several discrete traversing, down-hole logging and
stretches of the twin Pressure Tunnels, the cross-hole seismic work).
strata was disrupted by two major faults,
the attitude and disposition of which were Originally, the layout, in plan, of the
only fully established as a result of a twin pressure tunnels and four penstocks,
comprehensive programme of underground were symmetrical with the centre-line of
probe drilling and exploratory excavations. the Power Station Complex (as shown on
Figure 2 in Bowcock et al., 1976). However,
Unlike the tailrace and main cavern section because of faulting, this needed some
of the scheme, where exploratory headings modification in plan (refer to Figure 5).
had been driven as part of the pre-design Alterations were also required in vertical
phase investigations; prior to driving the alignment to ensure that the critical
Penstock tunnels, no pre-construction steel- to concrete-lined transition zones
exploratory works had been advanced would remain in high modulus sandstone as
upstream of the Power Station Complex. The a precaution against areal hydrofracture
tunnel alignment geology for the Pressure under high operating water pressure heads.
Tunnels was therefore entirely based on
correlation between surface drillholes,
with structural geological interpretation o CONSTRUCTION STAGE INVESTIGATIONS
based on terrain evaluation and remote
sensing data from: The requirement for additional geological
investigations of the Penstock/Pressure
o Low and high level aerial photographs Tunnel transition area only really became
and Landsat satellite mosaics; apparent when excavation of the Drainage

Figure 5 General arrangement of Pressure Tunnels and Penstocks showing locations


of Exploratory Pilot Headings and Diamond Cored Probe Hole Fans.
Access Tunnel (DAT.) was well advanced. At these drawings had been found remarkably
this stage, slight discrepancies were accurate throughout the entire Power
becoming evident between actual mapped Station Complex, when detailed correlation
elevations of discrete stratigraphic marker was attempted with some of the deep surface
horizons compared with those predicted from holes to the north of the caverns several
the original site investigation data. stratigraphic correlation discrepancies
were identified.
Stratigraphic dips were a few degrees
steeper than the surface holes would have In particular, in the area of the proposed
suggested. This suggested that either a Pressure Tunnel/Penstock Transition Zone,
significant roll or fault existed or the comparison suggested that either there
something was wrong with the original core was an error in the data or some form of
logging or borehole survey data. With over structural disturbance existed in the
3000m. of diamond drilling and in excess of vicinity of one of the original surface
iSOOm. of seismic and magnetometer boreholes ( hole GP22 see Figures 3 and
-

traversing having been carried out over the 5 for location). All of the other data in
Pressure Tunnel alignment, checking all of the immediate area, including that from the
the base data proved time consuming. excavation of the Main Cavern Complex and
Nevertheless, checks were made of all from some 2 km of tunnelling, supported the
obvious correlation inconsistencies in an hypothesis of undisturbed horizontally
attempt to sort out the geology. bedded sedimentary rocks. In consequence,
the collar location, elevation and attitude
Stratigraphic Correlation (from Sperry Sun multishot surveys) of hole
GP22 were rechecked and the core relogged.
As the basis for evaluating the likelihood Sedimentary analysis techniques and pain-
of some major geological anomaly (fault or staking refitting of core fragments were
fold structure) affecting the strata in employed to check right-way-up structures
the area immediately upstream of the main and verify the correctness of the core
cavern complex, the detailed stratigraphic within the boxes. Despite detailed re-
correlation diagrams prepared for the whole logging of the core and thorough survey re-
scheme alignment were re-assessed. Although levelling of the collar elevation of the

CURBONACEOUS MUDDY
SIUTTOONE MYLONITE

- CALCITE t GREY CLAY


-~ INEILL ON FAULT PLANE

& NODULES (~ / ---‘


SMALL SCULE ODEURS
S / V WITHIN FAULT ZONE
~,
~ ,~ooLn5

DETAIL OF FAULT A

FAULT ZONE COnSINtIOg Of


200mm -300mm thick brecc,a
dipping ~O49R towards
32Oo~36Oo magnetic

Figure 6 Drainage Access Tunnel and Extension showing mapped geology and drillholes
hole, the data still suggested a vertical - Satellite Imagery Assessment : Field
offset of 26 metres in the stratigraphy mapping of the major sandstone horizons on
when compared with the Main Cavern area. the escarpment hillslope yielded little
additional information because of the lack
Investigation Rationale of continuity of good outcrop. However,
some of the jointing trends mapped in the
As it was deemed critical that the steel- sandstones did suggest parallelism of major
concrete transition zone be located within elements of the structural fabric with the
high modulus ‘unfractured’ sandstone away escarpment face and with the axis of the
from faulting, a decision was reached to re-entrant valleys.
evaluate further the hypothesis that
unanticipated geological structural The black and white Landsat image scans
controls were responsible for the lack of were therefore critically re-examined to
stratigraphic correlation between the Power assess whether any further light could be
Station Complex and the borehole CP22 area. shed on possible regional scale features
paralleling the scheme alignment.
Accordingly, with much of the upstream
tunnelling close to the caverns already Although one north-south Landsat lineation
completed, it was decided that the DAT. paralleling the scheme alignment had been
should be continued as a pilot heading recognized at Pre-Tender stage, it had
(Figure 5) as thiswould provide additional never been found possible to confirm this
geological data while not significantly on the ground from detailed trenching or
compromising construction schedules. outcrop mapping, or from magnetometer or
seismic traversing. Nevertheless, it was
Remote Sensing Evaluation because of this possible lineation that
borehole CP22 had originally been drilled.
In parallel with the re-evaluation of the Thus, the conundrum remained that, based on
GP22 data, the available Landsat imagery the recovered core, the lithological
and air-photos were re-assessed and the sequence at the hole was inconsistent in
surface geophysical traverse information elevation with that now proven at the Main
re-interpreted. Cavern Complex. The decision was therefore
made to temporarily stop Pressure Tunnel
- Air-photo Interpretation : Although the construction and embark on a comprehensive
aerial photographs had been critically programme of underground probe drilling and
examined prior to the start of the original pilot heading development aimed at:
surface investigations, it was considered
worthwhile to completely re-examine them to a) verifying the extent of the geological
specifically check for structural features problem at the Transitions,
crossing the alignment in the area between
borehole CP22 and the Main Cavern Complex. b) resolving the stratigraphy along the
Pressure Tunnels sufficient that design
In general, most of the geological features decisions could be made, and,
evident on the photographs crossed the
scheme almost at right angles. Some c) using this data, establishing viable
dolerite dykes however obliquely traversed geological conditions for locating the
the tunnel alignment (Figure 5). These had steel/concrete Pressure Tunnel Tran-
all been identified during the initial site sition Zones in non-hydrofracture prone
investigations, Bowcock et al, 1976; Golder stratigraphy.
Associates, 1977).

When the photographs were re-examined but Strata Control Drilling


with specific focus on the area around
hole GP22, no definitive correlation could Immediately that full face excavation of
be established that could explain the the DAT. and Penstocks were stopped,
anomaly within the stratigraphy. It was drilling cubbies were slashed into the
noted, however, that topographically, the sidewalls at critical locations along the
scheme alignment in the area of the hole DAT. so that excavation of 2m square pilot
passed adjacent to a re-entrant valley headings could be continued while core
where the escarpment ridge formed something drilling was initiated. This drilling
of a promontory. In consequence, attention programme was laid out to rapidly establish
was addressed to checking whether the the stratigraphy above the twin Pressure
overall face of the escarpment as well as Tunnels. The initial holes were therefore
the re-entrant valleys were structurally drilled as fans of upward inclined cross-
controlled. strata holes radiating outwards from
several locations following the advancing that the transition zones:
face of the DAT Pilot Heading, (Figures 5
and 6). a) avoided the low-modulus fractured rock
conditions associated with the faults,
Drilling was started on a 24-hour shift and,
operation using one air-powered screw-feed
underground rig and one skid-mounted b) if possible, could be preferentially
converted surface rig. The results obtained located within high-modulus sandstone.
from the holes were analysed and plotted on
site during each day shift. Once data began The detailed configuration of Fault A,
to be acquired and it was realized that the which dips at 450 to the north and trends
geology was fairly complex and involved east-west across the scheme alignment about
multiple fault intersections, additional 430m. upstream of the Machine Hall, is
rigs were mobilized. It was found that the shown on Figure 6. The fault, is actually
demands of long uphole drilling could only comprised of two main shear planes separ-
be met using conventional skid mounted ated by 2 m. to 4 m. of downwarped strata.
high-torque surface rigs. The small bar- It is bounded on either side by a zone of
and-arm mounted air-powered underground disturbance up to 30 metres wide. Based on
rigs were soon proved incapable of coring stratigraphic correlation a combined down-
the 100 - 150 m. long upwards inclined throw of some 9m to the north occurs across
holes required in order to explore outwards the two planes.
from the pilot excavations. These long
holes were drilled at 250 upwards in order Fault B, which trends sub-parallel to
to optimize the cross-cutting of sufficient penstock 1/2 and intersects Pressure Tunnel
strata to allow stratigraphic correlation 1/2 at an oblique angle some 680 m upstream
from one hole to the next. Although the of the Machine Hall, was found to be much
larger, skid mounted, rigs were found well more complex than Fault A. It was found to
capable of drilling these raker holes, they vary in character along the scheme
were found to be of limited capability when alignment, comprising two well developed
drilling vertical up-holes in excess of parallel shear planes approximately 1 metre
about 60m. However, by careful planning of apart bounding a brecciated and mylonitized
hole layouts, this limitation did not zone in the Pilot Heading driven east of
unduly compromise the investigation data. Penstock 1/2, (refer Figure 5) but changing
to series of discrete planes and thin
From start to completion of the two month, brecciated zones where it crosses the re-
24 hour per day, fast track programme of aligned Pressure Tunnel, (Figure 7). Based
drilling, which resulted in the discovery
and delineation of two major, previously SANDSTONE 25 % SOISTONEI
unidentified faults, over 40 underground V NVSBEODEO SANDSTONE 555 5575 XLV
S57S~ONE 25%SANOSrONE,
drillholes varying in length to 160m., were 5555550
drilled and logged. Some 250m. of explor- V 050<5 BEDDED

atory adits were also developed and all of


the tunnel sidewalls were mapped to assist
in correlation of the drillholes.

Excavation of first the Pilot Tunnels and


then the full-face Penstock drivages,
confirmed the core-drilling data that two
major faults and several minor cross-shears
existed all within a 60m wide band crossing
the scheme alignment (Figure 5). The
detailed mapping also confirmed the
stratigraphic offsets suggested by the hole
GP22 data.

Because of the stratigraphic disruption Figure 7 Composite Isometric Drawing


created by these two major fault zones, of Face Happing Records for Pressure
which are shown in detail on Figures 6 and Tunnel 1/2 through Fault B
7, several design changes were necessary to
the locations of the Pressure Tunnels and on sidewall mapping and the results of the
the steel-concrete transition zones. These diamond core drilling, it was found that
changes were made to minimize risk of overall, the fault dips to the east at
hydrofracture induced cracking by between 55 and 7Q0 and down throws the
optimizing the tunnel alignments to ensure strata approximately 20m. also to the east.
Furthermore, complete correlation was found dipping sedimentary rocks into ground
between this area and the core logging of within which, based on offshore geophysical
the old surface hole CP22, thus confirming surveying there was some possibility of
the anomalous stratigraphic interpretation structural disturbance. As only limited
that originally led to the probe drilling offshore drilling had been feasible, for -

programme. submarine coal reserves a 1km. exclusion


barrier is required around each exploration
Although the details of the geometry of the hole the decision was reached to conduct
-

faults was only fully appreciated once they underground core drilling ahead of the
were exposed in the Pilot Headings, without tunnel drivages to provide information for
the data from the inclined core drilling it stratigraphic control and grade prediction
would have been impossible to complete the purposes as well as data on possible gas or
stratigraphic and structural correlations water problems.
necessary for revising the Pressure Tunnel
layouts to those shown on Figure 5. In Onshore portalling was completed for the
fact, to avoid intersection with Fault B in two required drivages (#2 and #3 Slopes) by
the critical area of the steel to concrete drill and blast methods and tunnelling was
transition section, the alignment of both initiated also using drill and blast
the Penstock and Pressure Tunnel 1/2 were methods on Slope #3, with upward inclined
adjusted and the steel to concrete tran- forward strata control holes, similar to
sition section was moved further upstream those laid out for the Drakensberg tunnels,
to an area away from the direct influence being drilled from the tunnel face at
of the faults (Figures 5 and 6). weekends. This, #3 tunnel, was driven drill
and blast to ch. 1027m. during which tine,
TBM trials were carried Out on Slope #2
DONKIN-MORIRN TEN DRIVAGES using a 4m. diameter prototype hard rock
TBM. The success of this trial led to
design and construction of a full face
The sub-seabed tunnels required for access 7.6m. diameter TBM (Hunter and Lovat, 1984,
to the productive coal horizon to be mined Marsh et al., 1986). As both probe hole
at Donkin (Cillman, 1982), necessitated an drilling for gas and water prediction was
initial pair of parallel tunnels to be a requirement, and contingency schemes for
driven for 3km offshore at a decline of up grout-hole drilling and rock-bolt
to 20% (Figure 8). The twin tunnels were to installation needed to be developed for the
be excavated through a sequence of gently full-face TBM design, it was decided to

ArLAf%r,c OCeAN MARSOUR COAL SEAM—


_ T22 MIStO 125 1

S£WM£NTS

PORTAL SAPIOSTONE
1O7%
£2-I E2-2
£2-S
£241
j • £2-S r2~4
£2-S £2-?
£2-S
4I
0 boo I500
3500 I

CH.3579 n,.
T2 - I STRATA CONTROL AND
- 2~ EXTENSOMETER HOLES

STRATA CONTROL HOLE STRATA CONTROL HOLE


BH ~T 142D6-02m r ELEV2T
81-s - I53.739m
I5~8
ELEV. 39.

B4SE OF EMERy SEAM


BASE OF MCRURYSE OH. I ~ 500 MINoR_SEAM
350

DETAIL IN OH. 1000 AREA SHOWING . POF?TAI SAND


CONFIGURATION OF VERTICAL UP HOLE - -‘-‘‘ONE
- . . ... - . - -.

~35 FORWARD STRATA CONTROL . - - -

HOLES

Figure 8 General Arrangement of Donkin-Horien Mine Access Slopes and Summary Geology
mount a full capability coring rig onto
the machine so that strata control holes
could be executed directly from the TBM.

a TBM - mounted drill-rig

The rig position on the TBN, as shown on


Figures 9 and 10, was optimized to allow:

- forward on-axis probe drilling,


- radial holes, including vertical holes
up and down, for bolts or instruments,
- 350 raked upward and forward holes for

cross-strata geological coring, and Figure 9 Modified Longyear EHS 38 Rig


- fan pattern radial holes for grouting Rod Aligmment Arrangement for drilling
350 upwards Strata Control Holes

UPWARDS CROSS STRATA HOLE

RIC;

~UTFR
HFAD 0.48 m

MACHINE

~—F-
I.42m

Figure 10 Access Port Arrangements for Use of the Coring Rig for Drilling Strata
Control, Instrumentation and Probe Holes through the TEN Head and Shield Assembly

Prior to selection of the rig for use on


the TBM, several underground trials of
different types of rigs were carried out.
These were aimed at establishing both the
suitability and efficiency of various rigs
for achieving good core recovery in typical
coal measures strata. The trials were also
directed towards checking whether it was
possible to achieve the desired setup, rod
handling and coring rates necessary to
guarantee drilling an upwards raked strata
control hole to at least 30 metres ahead of
and above the face within the limited four
hour daily TBM maintenance period.

Rod-tripping was seen generally as the most


time consuming operation, however coring
speeds in different materials also affected
rig performance, especially for the lower Figure 11 View of trailing edge of TEN
torque types tested. Conventional top-head shield showing Modified Longyear ERS 38
chuck machines were compared to flat-bed mounted for Strata Control Drilling
feed rigs in order to check maximum coring It also helped significantly by providing
and rod-handling speeds in a forward and excellent forewarning of coal and muds tone
upward mode. Various thin kerf and non- intersections that tended to affect the
coring bits were also tested to evaluate cutter performance of the Lovat TBM.
maximum penetration rates. After some
initial evaluations, and following Conclusions
comparative field trials of a Diamec 251
(flat-bed feed) and a Longyear EHS 38, the Probe hole drilling ahead of tunnelling
decision was made to use a modified Long- need not be considered only as a percussion
year rig incorporated onto the tail section drilled hole advanced the regulatory 3m. or
of the TBM. (Figure 9). The decision was other required distance to check for water
based not only on the performance of the and gas occurrences. With modern equipment,
rig, but also on the availability of cored hole drilling is both practical and
service/backup to the tunnel location and quick and can provide vital information on
on the compatibility of the drillrig’s ground conditions unattainable by open hole
hydraulics with the power-pack components techniques even with recourse to use of
of the Lovat M-300 TBM. down-hole geophysical tools.

The primary purpose for building the drill- 25~35o upward inclined diamond cored probe
rig right onto the TBM was for forward holes ahead of sub-horizontal tunnels in
geological prediction. However, in addition bedded sedimentary rock can be of immense
to the requirements of drilling for core value for predicting geological conditions
retovery and strata prediction, the rig was ahead of the face. For such probe holes to
equipped for rapid probe drilling using be both drillable and analyzable within the
non-coring synthetic diamond “Chrisset” tight time frames required to keep up with
bits, penetration rates for which are modern TBM drivage rates, careful choice of
comparable to normal air-rotary percussion. drills and coring equipment is vital. With
This allowed the rig to be also used for the increasing availability of small, but
on-axis drilling of forward probe holes for high torque flat feed rigs for underground
gas or water intersection control purposes. use and improved thin kerf coring
Further, because of the rig’s placement at equipment, such probe holes can be viably
the rear of the main shielded section of executed and evaluated within limited tine
the TEN, (Figure 11) it was suitably windows in a tunnelling schedule (such as
placed, if the need arose, for drilling weekends or maintenance shifts). This makes
radial, forward-raked grout-holes, or for their use feasible and attractive for both
drilling rockbolt holes for placing support TEN and drill and blast drivages where
behind the shield section, or for drilling geological conditions are not entirely
instrumentation holes as required. certain or where potential geological or
water inflow problems may be disruptive.
After some initial trials of the Longyear
EHS 38 rig mounted on the TBM, a schedule Geophysical and remote sensing techniques
of weekend core drilling was developed to including satellite imagery can aid
allow forward geological prediction without understanding of structural geological
interference to normal TBM operating shift conditions, but must be correlated to hard
requirements. In general, one 45m. long 350 drillhole data in order to be of value to
upwards inclined diamond BQ cored strata the tunnelling engineer. It is suggested
control hole was drilled over the tunnel that integration of surface remote sensing
crown every two weeks and one lOOm. long techniques with well planned strata control
uncored probe hole was drilled every week and forward cored probe drilling layouts
directly along the tunnel axis ahead of the constitutes possibly the best approach for
face for gas and water control. investigating long tunnel alignments.

Other holes which were drilled with the


rig, including those for extensometers and Acknowledgements
vertical upwards strata investigation holes
were also drilled at weekends or within The author wishes to thank the Electricity
scheduled maintenance breaks or other Supply Commission of South Africa and the
programmed shutdowns so as not to interfere Cape Breton Development Corporation of
with tunnelling advance, which peaked at Canada for their permission to publish the
about 30m/day (Marsh et al.,1985). The material presented in this paper. The
data obtained from the drilling was timely contribution of the author’s colleagues
and like the Drakensberg probe drilling, from within Golder Associates and other
helpful in optimizing tunnel grades to organizations who were involved with the
maximize excavation within good sandstone. projects is also acknowledged. Specific
7.6m. Full-Face Tunnel Boring Machine. CIM,
recognition is due to Dr.T.W.Mellors and Bulletin Vol. 77, No. 865, pp.47-54.
Mr.P.J.Terbrugge for their contributions to
the successful completion of the drilling Marsh J.C., Landry J.G., Currie D. and
studies for the Drakensberg Pressure Tunnel Lamb T., (1985). The Cape Breton
Transition Design and to Mr.R.C.F.King for Development Corporation’s Experience with
his contribution to the execution and
a Tunnel Boring Machine in Coal Measures.
implementation of the strata control C.I.M. Bulletin. Vol 79. No.891. pp.49-56.
programme in the Donkin-Morien Tunnels.
Mellors T.W. and Sharp J.C. (1982)
References Investigations for the Drakensberg Power
Station Complex in Weak Sedimentary Rock.
Proc. ISRM Symposium on Caverns and
Bowcock J.B., Boyd J.M., Hoek E., and Sharp Pressure Shafts, Aachen. pp. 105-116
J.C. (1976) Drakensberg Pumped Storage
Scheme -Rock Engineering Aspects. Proc.
Palmer J.H.L., Lovat R.P., and Marsh J.C.,
Symposium on Exploration for Rock Engin-
(1985). Performance of a 7.6m Diameter Full
eering, Johannesburg. Vol.2.pp.121-139 Face Tunnel Boring Machine Designed for a
Canadian Coal Mine. Proc. 4th International
De Witt N.J. (1983) Constructing the
Tunnelling Symposium, Brighton, England.
Drakensberg Pressure Tunnels. Water Power
and Dam Construction. 15 pp. Sharp J.C and Gonano, L.P.,(1982) Rock
Engineering Aspects of the Concrete Lined
Gilby J.L, Yuen C.M.K and Aston T.R.C.
Pressure Tunnels of the Drakensberg Pumped
(1985) Ceotechnical Monitoring of Tunnel
Storage Scheme. Proc. ISRM Symposium Rock
-
Boring Machine Drivages at the Donkin- Mechanics Related to Caverns and Pressure
Morien Mine Nova Scotia. Canadian Inst. Shafts. Aachen. Vol 2., pp.717-733.
Mining Bulletin. Vol 81. pp.60-72.
Gillman J.J. (1982) Donkin-Morien Sharp J.C., Endersbee L.A. and Mellors T.W.
Development Project. Canadian Inst. Mining (1984) Design and Observed Performance of
Bulletin. Vol. 75 No.845. pp. 133-140 Permanent Cavern Excavations in weak,
bedded strata. Proc. ISRM. Conf. Cambridge
Golder Associates, (1977) Geotechnical pp.493-507
Report for Drakensberg Pumped Storage
Scheme. 10 Volumes. Sharp .3.C., Pine R.J., Moy D., and Byrne
R.J. (1979) The Use of a Trial Enlargement
Gonano L.P. and Sharp. J.C. (1983) Rock for the Underground Cavern Design of the
Engineering Design and Construction of High Drakensberg Pumped Storage Scheme. Proc.
Head Pressure Tunnels for the Drakensberg 4th Congress Tnt. Soc. Rock. Mechanics,
Scheme. Proc. Rapid Excavation & Tunnelling Montreaux.
Conf. l8pp
Sharp J.C. and Mellors T.W. (1982) Rock
Hallier P.A.C. ,Weehuizen P.B. ,and Holl G.W. Engineering Investigation and Design
(1982). Construction of the Main Civil Studies for the Drakensberg Pumped Storage
Works of the Drakensberg Pumped Storage Scheme. Civ. Engr. in South Africa. Vol 24,
Scheme. Civ. Engr. S.A., Vol 24, No 8 #8 pp.399-416
pp. 421-433
Whiteway P. (1985) TEN Drives to Coal Seam
Hunter J.A., and Lovat R.,(1984). Design, under the Atlantic. The Northern Miner,
Development and Verification of a Lovat March 21st. pp B3-B7.
-

\ •
, \ I
\
\
M-300 Tunnel Boring Machine

The M-300 is a fully shielded open face rock Technical Specifications


boring machine fabricated for driving a 14.5 KM
(9 mile) access decline at the Donkin-Morien The machine is propelled by 24 pushing jacks
Development Project on Cape Breton Island in with a 1.7 meter (5’ 8”) stroke and is equipped
Nova Scotia, Canada. The design and develop- with a mechanical rib erector and rib expander to
ment of this innovative tunnelling equipment was facilitate lining operations.
funded by Canada’s National Research Council, The machine has a 11.5 meter (38’) long
the Cape Breton Development Corporation and primary conveyor with a 1.2 meter (4’) wide belt
Supply and Services Canada for July 1983 and a 170.0 meter (560’) long trailing conveyor
delivery. with a 1.2 meter (4’) wide belt. The trailing con-
veyor consists of detachable and interchangeable
Design Features sections that are post supported on pipe skates.

The cuttinghead is equipped with inter- Bore Diameter: 7.6 meters (25’) (Nominal)
changeable roller disc cutters and drag type car- Overall Length: 6.3 meters (20’ 9”) (Nominal)
bide teeth to facilitate the most efficient cutter Total Connected Horse Power: 2050 H P
selection for the varying rock conditions. Estimated Overall Weight: 350 tonne (344 tons)
The cuttinghead can be rotated clockwise or
counter-clockwise at variable speeds not ex-
ceeding 92 meters/minute (302 feet/minute) to This project is another example of Lovat’s con-
minimize the possibility of a methane explosion tinuing commitment to innovation and leadership
initiated by sparks created by the cutters. in the design and manufacture of tunnelling
The machine has been designed for a gassy equipment.
mine application and is equipped with intrinsical-
ly safe electrics and flame resistant hydraulics to
meet the requirements of Canmet certification
and Labour Canada standards. The unit also LOVAT TUNNEL
features a ventilation system to control dust and
mix methane with air to acceptable levels in an
efficient manner.
Equipment Inc.
The machine has a back-up system for main- 441 Carlingview Drive,
taining all required services including electrics, Rexdale, Ontario M9W 5G7
hydraulics, ventilation, dust control, cooling, Telephone (416)675-3293
storage, repair, etc. Telex 06-989167

Vous aimerez peut-être aussi