Académique Documents
Professionnel Documents
Culture Documents
NO ID
AREA
TEAM
Proposed
DRAWING
PERMIT
CABLE BASEMENT
119 Cable Basement, Boiler-1
B-1
27-Jan-16
- Branch Pipe Sprinker installation &
- Mainline Istallation to header
Line Check (Prepared by QC, Welding & Painting Report Required)
Hydrotest (Prepared by QC, Test Package Submitted)
- Control Valve Header Installation
Line Check (Prepared by QC, Welding & Painting Report Required)
Hydrotest (Prepared by QC, Test Package Submitted)
4-Apr-16
VOLUME
TRAFO
PIPE
dia-mtr
LOCATION Unit
OK
FINISHED
4-Apr-16
6-Apr-16
8-Apr-16
15-Apr-16
18-Apr-16
20-Apr-16
20-Apr-16
20-Apr-16
Completed
Missed
Progress Target
Progress Target
Progress Target
Progress Target
Progress Target
14-Apr-16
18-Apr-16
18-Apr-16
20-Apr-16
20-Apr-16
6-Apr-16
8-Apr-16
15-Apr-16
18-Apr-16
20-Apr-16
20-Apr-16
20-Apr-16
Completed
Missed
Progress Target
Progress Target
Progress Target
Progress Target
Progress Target
8-Apr-00
13-Apr-16
20-Apr-16
20-Apr-16
20-Apr-16
22-Apr-16
22-Apr-16
10-Apr-00
16-Apr-16
20-Apr-16
20-Apr-16
22-Apr-16
22-Apr-16
22-Apr-16
Completed
Re-Scheduled
Progress Target
Progress Target
Progress Target
Progress Target
Progress Target
6-Apr-00
21-Apr-16
21-Apr-16
21-Apr-16
23-Apr-16
23-Apr-16
8-Apr-00
10-Apr-16
21-Apr-16
21-Apr-16
23-Apr-16
23-Apr-16
23-Apr-16
15-Apr-16
18-Apr-16
22-Apr-16
22-Apr-16
22-Apr-16
24-Apr-16
24-Apr-16
18-Apr-16
20-Apr-16
22-Apr-16
22-Apr-16
24-Apr-16
24-Apr-16
24-Apr-16
15
2
14-Apr-16
18-Apr-16
18-Apr-16
20-Apr-16
20-Apr-16
4-Apr-16
OK
4-Apr-16
OK
4-Apr-16
OK
OK
REMARKS
START
4-Apr-16
AREA
TEAM
Proposed
DRAWING
PERMIT
B-2
4-Apr-16
VOLUME
TRAFO
PIPE
dia-mtr
LOCATION Unit
OK
START
FINISHED
12-Apr-16
13-Apr-16
13-Apr-16
23-Apr-16
23-Apr-16
25-Apr-16
25-Apr-16
25-Apr-16
23-Apr-16
23-Apr-16
23-Apr-16
25-Apr-16
25-Apr-16
REMARKS
Progress Target
Progress Target
Progress Target
Progress Target
Progress Target
OK
30-Apr-16
22-Apr-16
15-Apr-16
9-May-16
15-Apr-16
AD
OK
AE
4-Apr-16
OK
AG
AA
4-Apr-16
18-Apr-16
14
8-Apr-16
OK
OK
44
1-Apr-16