Académique Documents
Professionnel Documents
Culture Documents
I.
INTRODUCTION
In developing countries like India, a mismatch between
power generation and power demand necessitates load
shedding to sustain system stability. In such a scenario of
increasing power demand, effective power utilization and
effective power distribution to the consumers plays a vital role.
Due to generation deficiency, load shedding becomes
unavoidable. Hence, it is better to reduce the impact of load
shedding from both distribution company and consumers
perspective by incorporating intelligent load shedding
techniques thereby improving the efficacy of power
distribution.
Load dispatch centre (LDC) is responsible for power
allotment to each substation based on the availability of power.
Whenever, there is deficiency of power generation intimation
is sent to the substation to shed a particular amount of load. In
current load shedding scheme, entire feeder is disconnected
regardless of the type of the loads connected to it, whose
power consumption is almost equal to the amount of load to be
shed. Currently, round robin technique is employed for load
shedding by dividing the entire load shedding duration into
blocks of half an hour or one hour. This technique causes over
shedding in most of the cases reducing the effective utilization
of available power. However, it is to be noted that a single
feeder contains mixed loads such as domestic, industrial,
2
TABLE I.
CATEGORIZATION OF LOADS INTO TARIFFS
Tariff
Type of loads
LT1
LT2
Residential, Institutions
LT3
Commercial
LT4
LT5
Industrial
LT6
LT7
Temporary connections
HT1
Water works
HT2
Industrial ,Commercial
HT3
Weight
< 1 M.U.
0.9-1
0.8-0.9
0.7 -0.8
10,000- 1,00,000
0.6-0.7
1000-10000
0.5-0.6
500-1000
0.4-0.5
100-500
0.2-0.4
< 100
0-0.2
3
TABLE III
WEIGHTS FOR REVENUE LOSS TO THE POWER DISTRIBUTION COMPANY
Tariff paid by the consumer/unit
(Rs)
Grading example,
1. Consider an automobile industry with power
requirement of 2, 50, 000 units per month and pays a
tariff of Rs 6 per unit. Revenue of the company in one
hour is estimated to be Rs 1, 20, 000.
Weight
6-7
0.9-1.0
4-6
0.75-0.9
2.5-4
0.4-0.75
<2.5
0-0.4
Grade Point
G=5*0.85+10*0.68+15*0.9+15*0.82+5*0.8
=40.9
(* Weights for social impact and other considerations
have to be given on the impact of the load such as
environmental, job generation and considerations of the
utility etc)
2. Consider a domestic load with power consumption of
250 units per month, pays a tariff of Rs 3 per unit.
The estimated revenue per hour is about Rs 250.
Grade point
G=5*0.3+15*0.5+15*0.15+10*0.3+5*0.5
=16.8
TABLE IV
WEIGHTS FOR REVENUE LOSS TO THE CONSUMER
Revenue Generated/Hour ( Rs)
Weight
<2,00,000
0.9-1
1,00,000-2,00,000
0.8-0.9
50,000-1,00,000
0.65-0.8
20,000-50,000`
0.5-0.65
10,000-20,000
0.4-0.5
5000-10,000
0.3-0.4
1000-5000
0.15-0.3
<1000
0-0.2
The base value given above can be decided by the utility and
assigned a value in the range 0-50, depending on the type of
load, time of day, requirements of utility, tariff considerations
etc. The base values assigned can be dynamic and even change
during the day, depending on time of the day pricing.
A load pattern of % base value v/s time of the day is created
for each category of loads indicating the priority time for each
load. Load pattern is created on hourly basis for 24 hours of
the day. At each hour of the day relative importance is given
to a particular type of load. The importance assignment should
be based on the customer requirement and the availability of
power. Typical load patterns for domestic and industrial loads
are shown in Fig. 1 and Fig. 2 respectively.
TABLE V
WEIGHTS FOR SEVERITY OF LOAD SHEDDING
Weight
0.9-1.0
0.8-0.9
0.7-0.8
0.5-0.7
0.3-0.5
% of base value
Utilities
200
150
100
50
load pattern
for
0
2 3 4 5 6 7 8 9 101112131415161718192021222324
time of the day
0-0.3
200
150
100
50
0
2
load pattern
for Industrial
loads
10 12 14 16 18 20 22 24
time of the day
B. Flowchart of Implementation
A detailed flowchart explaining the method adopted
for developing the load shedding program is as shown
in the Fig. 3.
A. Algorithm Developed
The sum of the grade points of loads being shed is 865. The
load shedding error is 0.8976 kW. The best possible solution
for loading is as shown in Table IX.
TABLE IX.
LOAD SHEDDING SOLUTION AT 2:00 P.M.
The sum of grade points of all loads shed is 739. The loads
to be shed are computed using GA and the error in load
shedding is 0.6994 kW. The best possible solution with the
specified requirements for load shedding is as shown in
Table VII.
Table VII.
LOAD SHEDDING SOLUTION AT 9:00 A.M.
% error
0.05
Case (ii): Load shedding requirement is 700 kW at 2:00
p.m.
The grade points of 100 loads at 2:00 p.m. are as shown in
the Table VIII.
TABLE VIII.
GRADE POINTS AT 2:00 P.M.
0 10 20 30 40 50 60 70 80 90 100
Fig. 4 Graph of minimization of load shedding error
The graph shown in Fig. 4 shows that, the efficiency of
algorithm in minimizing the load shedding error is well within
0.05 % of amount load to be shed. This is an exceptionally
good result for the optimization of load shedding error. The
algorithm is also tested for efficiency in cost optimization in
load shedding. The ratio of cost of loads being shed to the total
grade points of all the loads at that instant of time is always
lesser than the ratio of amount of load being shed to the total
load before shedding. Hence the efficiency in cost
optimization is high.
Power consumption
interval(MW)
10:00 a.m.
in
specified
11:00 a.m.
VII. CONCLUSION
The algorithm provides a unique opportunity to control the
loads individually in smart grid environment and also
optimizes the value of load to be shed during a particular time
of the day based on the priority assigned to it. By the
application of this algorithm exact amount of load can be shed
based on requirement so that available power is utilized to the
maximum extent. Available power is supplied to the
consumers in need at their priority time even if there is a
shortage of power and power supply is made unavailable to
those consumers to whom power supply at that time is not
absolutely necessary. The algorithm tries to reduce the impact
of load shedding using grading scheme. The algorithm
developed tries to improve the customer satisfaction and
customer participation in the load management. The scheme
improves efficacy of power distribution. It reduces the revenue
loss to the distribution company and also to the consumers as
they get power at their priority time. Continuous supply can be
maintained to critical loads like hospitals and health care
systems, data centres, cold storages etc. The public utilities are
given more importance. The amount of power to be purchased
from other utilities to power continuously to the important
consumer can be minimized, by supplying power to those
consumers in need and by not wasting power in supplying non
critical loads. The flexibility of the method lies in the fact that,
the grades can be changed depending on the priorities dictated
by the control centre. The grades can even be dynamic, by
assuming different values in different periods of the day, to
reflect time of day pricing, if it is adopted.
time
12:00 p.m.
F1
2.9
3.1
2.8
F2
1.5
1.6
1.5
F3
3.4
3.3
F4
1.5
1.6
1.5
F5
2.0
2.2
2.1
F6
1.3
1.4
1.4
F7
2.3
2.6
2.7
F8
2.7
2.7
2.6
Block of time
Feeder
disconnected
F1
2.9-2.6=0.3
F3
3-2.6=0.4
F2,F4
3.2-2.6=0.6
F5,F6
3.6-2.6=1.0
F8
2.6-2.6=0
F7
2.7-2.6=0.1
VIII. REFERENCES
[1]. ShervinShokooh, TanujKhandelwal, Dr. FarrokhShokooh,Jacques
Tastet, Dr. JJ Dai, Intelligent Load Shedding Need for a Fast and
Optimal Solution,IEEE PCIC Europe 2005
[2]. David Mayne, How the smart grid will energise the world-white
paper, Digi international inc.