Académique Documents
Professionnel Documents
Culture Documents
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
1 of 22
Rev.
Date 19/02/13
I.D.
SPECIAL CONDITIONS
0
Rev.
First Issue
Description
Prepared
Checked
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
Approved
19/01/2013
Date
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
2 of 22
Rev.
Date 19/02/13
I.D.
INDEX
1 INTRODUCTION
1.1
Definitions
1.2
Abbreviations
1.3
Reference documents
SITE INFORMATION
2.1
Plant location
2.2
Working Conditions
WORK DESCRIPTION
4.1
4.2
4.3
10
4.4
CONTRACTOR facilities for SUBCONTRACTOR use (free issue facilities/services) Errore. Il segnalibro
non definito.
4.5
11
4.6
Working conditions
12
4.7
12
4.8
Safety requirements
12
4.9
Working time
12
4.10
12
4.11
Interface
13
4.12
Quality
13
4.13
Photography
13
TENDER PROCESS
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
14
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
3 of 22
Rev.
Date 19/02/13
I.D.
5.1
Documents Examination
14
5.2
Gathering of Information
14
5.3
Confidentiality of Documents
15
5.4
15
16
6.1
16
6.2
16
6.3
16
6.4
16
6.5
Meals
17
6.6
17
6.7
17
6.8
Field diary
19
6.9
Distribution of documents
20
6.10
20
6.11
21
6.12
Subcontracting
22
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
4 of 22
Rev.
Date 19/02/13
I.D.
1 INTRODUCTION
Whereas, BP IRAQ NV (hereinafter referred to as COMPANY) has requested to
SAIPEM (hereinafter referred to as CONTRACTOR) to perform a bid for integrated
execution of engineering, procurement, supply, construction, pre-commissioning,
commissioning of RUMAILA 150 MW EARLY POWER PLANT.
The works of the 150 MW Early Power Plant comprises three packages, as follow:
-
Disciplines
Civil Works
132 kV
Interconnecting
Overhead
Transmission Lines
A3_Civil_PP&BOP
A3_Civil_OHTL
1000520C0_CIV_Overall
A3_Mechanical_OHTL
1000520_M0_Mechanical_Overall
00-CA-E-11101_00 Attachment F
Building Works
Mechanical Works
A3_Mechanical_PP&BOP
Piping Fabrication
A3_Mechanical_PP&BOP
1000520_MP_Piping Fabrication
Overall
Pipelines
Electrical Works
1000520_A0_Pipeline_Overall
A3_Electrical_PP&BOP
A3_Electrical_OHTL
1000520_D0_ELE_Overall
Instrument Works
A3_Instrument_PP&BOP
1000520_E0_Instrument_Overall
Telecomm works
A3_Telecomm_PP&BOP
1000520_T0_TLC_Overall
A3_Painting_PP&BOP
1000520_G0_Painting_Overall
Painting Works
Insulation Works
A3_Insulation_PP&BOP
The final selection of the successful Bidder will be at our sole discretion and we shall be
under no obligation whatsoever to accept the LOWEST of any tender or to give any
reason for the rejection of any or all Tenders
1.1
Definitions
COMPANY
BP IRAQ NV
CONTRACTOR
SAIPEM SPA
SUBCONTRACTOR
Firm or person with whom CONTRACTOR has
contracted with for the construction of the plants, scope of work of this tender.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
1.2
Rev.
Date 19/02/13
I.D.
Abbreviations
BOQ
EPC
HSE
QA
QC
TCF
1.3
5 of 22
Bill of Quantities
Engineering, Procurement and Construction
Health, Safety and Environment
Quality Assurance
Quality Control
Temporary Construction Facilities
Reference documents
N.A.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
2
2.1
6 of 22
Rev.
Date 19/02/13
I.D.
SITE INFORMATION
Plant location
Working Conditions
The SUBCONTRACTOR shall work and will strictly adhere to security and safety
regulation; moreover SUBCONTRACTOR shall work in full cooperation with all the
other SUBCONTRACTORs present in the Project Areas.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
7 of 22
Rev.
Date 19/02/13
I.D.
WORK DESCRIPTION
The scope of the work here-below listed is described in the hereto attached documents
and in all others documents therein mentioned and/or referred. SUBCONTRACTOR
shall provide all resources, services and whatever necessary to carry out the realization
of the scope of work.
Without any obligation and expenses to CONTRACTOR and/or COMPANY,
SUBCONTRACTOR is requested to submit the best commercial and technical proposal
for:
-
Civil Works
Building Works
Mechanical Works
Pipelines
Electrical Works
Instrument Works
Telecomm works
Painting Works
Insulation Works
as CONTRACTOR request.
Any other reference and/or attached document to the above mentioned specification
shall be complied as well.
SUBCONTRACTOR shall provide to CONTRACTOR documentation as per SPC.00ZA-E-02203. Furthermore SUBCONTRACTOR shall quote according to
SPC.00.ZA.E.02204, PRE.GC.CC.8020, and related BOQs.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
4
4.1
8 of 22
Rev.
Date 19/02/13
I.D.
SUBCONTRACTOR shall provide, install, distribute and maintain all necessary HVAC,
electrical, telephone, communications, gas, compressed air, potable water, raw water,
fire water, fuels, sewage and any other utilities as required to perform the work.
Such utilities shall be fit for this purpose and meet the appropriate COMPANY
specifications and standards as for the permanent system.
SUBCONTRACTOR shall plan and supply all utilities required for its site construction
works including power, water, communications and waste water collection and
transport to the COMPANY sewage treatment plant and/or other approved treatment
and disposal facilities. SUBCONTRACTOR shall dispose of sewage water and any
excess construction water using approved and certified means.
-
Water: SUBCONTRACTOR shall determine its construction water needs and quality
for work areas, temporary facilities and construction camp and shall source and
supply the water including transport, storage and distribution.
SUBCONTRACTOR shall
construction facilities.
SUBCONTRACTOR shall provide all first-aid and medical services required for its
manpower.
Land within the Rumaila Oil Field shall be provided by COMPANY for allocation of
Laydown areas, workshops and other temporary facilities. SUBCONTRACTOR
shall provide any earth works, grading, levelling and fencing at its care and
expenses.
provide
temporary
fence
around
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
its
temporary
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh.
RUMAILA - IRAQ
9 of 22
Rev.
Date 19/02/13
I.D.
its care and expenses, in accordance with all local authorities and CONTRACTOR
regulation.
-
4.2
SUBCONTRACTOR is requested to specify his own needs as per SPC.00-ZA-E02203, for the supplies mentioned at the aforesaid paragraph:
Water consumption;
Power consumption;
Area for temporary facilities (square meters) to be minimised in consideration
that the areas allocated by COMPANY are specified for all discipline
SUBCONTRACTORs.
SUBCONTRACTOR temporary site facilities shall include, but be not limited to, the
following:
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 10 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
SUBCONTRACTOR will build its own dedicated Camp facilities within the Rumaila Oil
Field (land shall be provided by COMPANY for allocation of Accommodation Camp)
and it will provide all the required facilities generally associated with camps in
compliance with COMPANYs requirements.
SUBCONTRACTOR shall provide accommodation for all its own personnel at its own
charge including catering and housekeeping.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 11 of 22 Rev.
RUMAILA - IRAQ
4.4
Date 19/02/13
I.D.
SUBCONTRACTOR is responsible for the dust and pollution control in the construction
area, temporary facilities area and camps.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 12 of 22 Rev.
RUMAILA - IRAQ
4.5
Date 19/02/13
I.D.
Working conditions
First aid facilities such as infirmary, ambulances and doctors will be provided by the
SUBCONTRACTOR in accordance with the COMPANYs standards.
4.7
Safety requirements
SUBCONTRACTOR shall comply at all times with all applicable Local Municipality
Safety Regulations, health and environmental regulations and all COMPANY General
Instructions, and other related rules and regulations.
Particularly, the SUBCONTRACTOR, performing his job in all involved areas, shall
adhere to CONTRACTOR and local authorities safety procedure and to all safety
regulations contained on the safety programme and to good construction safety
practice.
Should SUBCONTRACTOR fail to comply with any of the COMPANY and
CONTRACTOR requirements, SUBCONTRACTOR shall immediately take all
necessary corrective actions. Any corrective action shall be taken at
SUBCONTRACTOR expense. If SUBCONTRACTOR fails to take prompt corrective
action, the CONTRACTOR Representative may direct SUBCONTRACTOR to suspend
all or part of the work until satisfactory corrective action has been taken. Costs
incurred by SUBCONTRACTOR, as a result of such work suspension, shall be solely
SUBCONTRACTOR responsibility, and any resultant SUBCONTRACTOR
performance delays shall not be deemed excusable hereunder.
4.8
Working time
Normal construction contractor work hours are sixty (60) hours per week, ten (10)
hours per day, six (6) days per week, Saturday through Thursday, including work in the
month of Ramadan. Normal contractor holidays are observed in accordance with a
calendar issued annually by COMPANY (Contractor Operational Calendar).
However, SUBCONTRACTOR shall work whatever hours are necessary to maintain
the WORK Schedule and/ or meet special requirements including, but not limited to,
road crossing, shutdowns, tie-ins, testing and Pre-commissioning at no additional cost
to CONTRACTOR. All WORK shall be in accordance with Iraq Labor Law.
4.9
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 13 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
4.10 Interface
N.A.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 14 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
TENDER PROCESS
Documents Examination
In submitting the bid, SUBCONTRACTOR assumes all responsibility for examining the
complete tender package attached hereto and for gathering all useful information in
order to establish the cost and the conditions for the execution of the work. Any error in
the evaluation due to an improper or superficial examination of the attached
documents shall be at SUBCONTRACTORs sole risk with no recourse open toward
COMPANY or CONTRACTOR. The successful SUBCONTRACTOR shall have the
obligation to report any error, inconsistency or omission to the tender documents prior
to contract award, and failure to do so shall not entitle the SUBCONTRACTOR to any
claim after award of the contract. Any variation, modification and/or deviation with
respect to the requirements, terms and conditions of the tender documents, made by
SUBCONTRACTOR at the bidding stage, shall be clearly expressed and listed
separately. SUBCONTRACTOR shall outline the items of documents to which each
variation refers.
It is understood that otherwise the documents of this inquiry shall be considered
fully accepted by SUBCONTRACTOR.
Shall CONTRACTOR documents be in conflict with COMPANY documents, it is
understood that COMPANY documents prevail.
5.2
Gathering of Information
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 15 of 22 Rev.
RUMAILA - IRAQ
5.3
Date 19/02/13
I.D.
Confidentiality of Documents
Tender documents, including all attachments, are strictly confidential and shall not be
released to any third party. In case of declination to submit a bid for this inquiry,
SUBCONTRACTOR shall also undertake to return to CONTRACTOR or destroy the
above documents on request and in accordance with CONTRACTOR instruction.
SUBCONTRACTOR shall comply with the security and confidentiality requirements of
COMPANY, which covers handling, control, transmission, confidentiality, security,
storage, protection against unauthorized disclosure, modification, reproduction and
eventual destruction of COMPANY engineering data.
5.4
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 16 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
The site is included into the boundary limits of the enclosed preliminary drawings and
technical documents.
For the execution of the Construction Site activities, the construction area is divided
into two areas:
- CONSTRUCTION AREA (CA)
- TEMPORARY SITE FACILITIES AREAS utilized by SUBCONTRACTOR to install
offices, warehouses and workshops.
6.2
Access to site for all personnel and for equipment is from the gate of the Plant
controlled by the security personnel.
6.3
COMPANY will make available the area in "as it is" conditions for
SUBCONTRACTOR's site temporary facilities. COMPANY and/or CONTRACTOR
have no responsibility over the all SUBCONTRACTOR's working areas or over the
materials and equipment owned by SUBCONTRACTOR or in SUBCONTRACTOR's
custody. Site preparation including SUBCONTRACTOR's lay down area,
SUBCONTRACTOR's temporary facilities area, access road from/to temporary
facilities area and any other site preparation necessary for SUBCONTRACTOR's
activities, are at total SUBCONTRACTOR's charge and care. The SUBCONTRACTOR
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 17 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
shall prepare and submit to CONTRACTOR, for approval, a layout of the service area
showing the set-up, the water and electric power distribution and the sanitary facilities.
SUBCONTRACTOR shall indicate foreseen consumption, monthly wise, of water,
electricity and steam. SUBCONTRACTOR shall provide connections and temporary
distribution, at total SUBCONTRACTOR's charge and care. SUBCONTRACTOR shall
provide telephones, sewer system and whatever necessary for temporary facilities for
the execution of work, at total SUBCONTRACTOR's charge and care.
SUBCONTRACTOR will observe all site safety and security regulations and equip with
extinguishers and whatever necessary (in adequate numbers) all his working
areas/facilities, at total SUBCONTRACTOR's charge and care.
6.5
Meals
Daily meals can be consumed only in those areas prepared for the purpose. No meal
can be consumed on the job site.
SUBCONTRACTOR shall arrange lunch provision for its workforce.
Local Construction Site Area allocations are intended to allow SUBCONTRACTOR to
establish local canteen facilities for preparing, storing and otherwise providing suitable
meals to the workforce thereby avoiding personnel transfer to and from camps. All
arrangements must be approved by COMPANY.
6.6
All services and supplies required for the execution of the work shall be at the
SUBCONTRACTOR's care and expense, with the only exception of those explicitly
stated to be at CONTRACTORs charge. As an example but not limited thereto, in
addition to the obligations stated in other Annexure or in the contract documents, the
following shall be at the SUBCONTRACTOR's care and expense:
a.
b.
c.
d.
e.
f.
g.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 18 of 22 Rev.
RUMAILA - IRAQ
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
Date 19/02/13
I.D.
Supply of all fuels and lubricants required for the complete execution of the
SUBCONTRACTORs work.
Supply of compressed air (where required), gases, oxygen, acetylene, graphitic oil for
bolts, tie rods and nuts, and of Teflon for coupling, where required for the complete
execution of the SUBCONTRACTORs work.
Clear-up and cleaning of worksite and service areas upon completion of
SUBCONTRACTORs work.
Dimensional checks required for the complete execution of the SUBCONTRACTORs
work. Direct and indirect personnel, equipment necessary to execute all tests in
accordance to drawings, specifications and local laws, applicable for the complete
execution of the SUBCONTRACTORs work.
Mobilization, provisions for keeping the worksite in full working conditions, and
demobilization of the worksite after completion of the SUBCONTRACTORs work,
leaving the areas in the original conditions.
Preparation and issue of all certificates and reports, in full compliance to drawings,
specifications and local laws, applicable for the complete execution of the
SUBCONTRACTORs work.
SUBCONTRACTOR Personnel's individual equipment necessary to carry out the entire
SUBCONTRACTORs work required by contract documents and annexure.
Necessary supervision and adequate various staff during the execution of the
SUBCONTRACTORs work, in full compliance to drawings, specifications and local
laws, applicable for the complete execution of SUBCONTRACTORs work.
Any necessary scaffolding as per schedule requirement and in accordance with the
drawings, specifications and local laws, applicable for the complete execution of the
SUBCONTRACTORs work.
Board and lodging expenses for both local and expatriated personnel required for the
complete execution of SUBCONTRACTORs work.
Sanitary facilities, in full compliance to drawings, specifications and local laws,
applicable for the complete execution of the SUBCONTRACTORs work.
Temporary site facilities such as workshop, storehouses, furnished office, etc. as well
as their transport and transport costs from the SUBCONTRACTOR's facilities area to
the worksite and back, including loading and unloading, in accordance with the
drawings, specifications and local laws, applicable for the complete execution of the
SUBCONTRACTORs work.
Transport of the SUBCONTRACTOR's personnel from the lodgings to the site and
back, travelling time included, for all the time necessary to the complete execution of
SUBCONTRACTORs work, including any necessary escort.
Round trip expenses for SUBCONTRACTOR's personnel from SUBCONTRACTOR's
headquarters to the worksite and back.
Possible partial suspensions of the work entailing idle times that might be necessary
during the execution of SUBCONTRACTOR's work for safety reasons.
The charges that might result from the need for an increase of SUBCONTRACTOR's
personnel and construction plants and/or overtime on working days, on nights and on
Sunday necessary to complete SUBCONTRACTOR's work in accordance with the
work schedule.
The charges that might result from re-works caused by SUBCONTRACTORs works
and/or change works not performed in full compliance to drawings, specifications and
local laws, applicable for the complete execution of SUBCONTRACTORs work.
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 19 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
y.
All personal site equipment, vehicles and all construction equipment tools, with the
relevant charges from SUBCONTRACTOR's factory to the site and vice versa,
including the various loading and unloading operations of the same, required for the
complete execution of SUBCONTRACTORs work.
z.
Any other charge necessary in connection with any measures to prevent pollution of
soil, water courses during the execution of SUBCONTRACTOR's work.
aa. All temporary vents to the atmosphere to prevent air pollution during the execution of
the SUBCONTRACTOR's work.
bb. The installation of a first-aid station in the site for SUBCONTRACTOR's personnel
according to the drawings, specifications and local laws, applicable for the complete
execution of the SUBCONTRACTORs work.
cc. The expenses for medical care and hospitalisation for SUBCONTRACTOR's personnel
in case of disease or accident on worksite during the execution of the
SUBCONTRACTOR's work.
dd. Provisions for safety at worksite during the execution of SUBCONTRACTOR's work.
ee. Provision for the security of the SUBCONTRACTOR's working areas and for the
goods, during all the time necessary to the complete execution of
SUBCONTRACTORs work.
ff.
The request for work permits, necessary for the execution of SUBCONTRACTOR's
work, and standstill for their obtaining and for safety reasons.
gg. Flood lighting and lighting system, wherever necessary and for all the time necessary
to the complete execution of SUBCONTRACTORs work.
hh. SUBCONTRACTOR's garbage collection during the execution of the
SUBCONTRACTOR's work.
ii.
The protection, with adequate means, of machinery, special equipment,
instrumentation valves and all items that can get damaged during the execution of the
SUBCONTRACTOR's work.
jj.
The execution of detailed construction sketches for minor items in connection with
drawings and standards supplied by CONTRACTOR, necessary to the complete
execution of the SUBCONTRACTORs work.
kk. The execution of "As-Built" drawings, according to SPT.GC.QUA.02010, for all the
minor modifications done directly at site (blue print master copy). These master copies
will be submitted to CONTRACTOR at the complete execution of
SUBCONTRACTORs work.
ll.
Regular SUBCONTRACTOR's waste water disposal at designated area during the
execution of the SUBCONTRACTOR's work.
mm. Prevention measures, working clothes and individual safety equipment in accordance
with the applicable COMPANY and/or CONTRACTOR regulations and Local
Authorities rules.
nn. Visa for SUBCONTRACTORs personnel.
oo. Insulation materials as per COMPANY specifications and requirements
pp. Painting materials as per COMPANY specifications and requirements
6.8
Field diary
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 20 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
Distribution of documents
Upon award of the contract, SUBCONTRACTOR shall prepare a detailed quality plan
(inspection and test plan) for the work and submit this to CONTRACTOR for approval
or for possible imposition of hold/witness points. Upon award of the contract and
maximum within one month, SUBCONTRACTOR shall prepare its safety plan and
detail execution plan for the work and submit these to CONTRACTOR for approval.
SUBCONTRACTOR shall be responsible for providing to CONTRACTOR, all
drawings, calculations and any other information necessary for and prepared by
SUBCONTRACTOR for the proper execution of the work (well in advance).
Documents issued by SUBCONTRACTOR to CONTRACTOR for approval shall
within twenty-one (21) working days be either:
a) Confirmed as approved.
b) Returned to SUBCONTRACTOR for review/inclusion of any comments considered
necessary by CONTRACTOR.
Approval of any document by CONTRACTOR is not intended to be a complete check
and does not relieve the SUBCONTRACTOR from any responsibilities contained
within the contract and in relation of good construction practice.
SUBCONTRACTOR
shall
prepare
in
accordance
with
contract
and
CONTRACTOR/COMPANY procedure requirements and submit to CONTRACTOR at
his main site office, the following documents:
c)
d)
e)
f)
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
SP Doc. No.
BP IRAQ NV
00-ZA-E-02504
PROJECT
LOCATION
Sh. 21 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
The SUBCONTRACTOR's representative at the site shall be qualified, shall have good
experience in the same position for similar work and shall be full powered for
technical/economical decision to be taken within the frame of contract. The staff that
will be employed shall be qualified and with good experience for similar works.
The SUBCONTRACTOR's organization chart shall clearly indicate the following
information:
a) Extent of autonomy of the SUBCONTRACTOR site management for the managing
of the contract in relation to:
Employment of manpower.
Purchase of construction materials and consumable materials.
Programming of works.
Taking technical and economical decision.
Connection
between
SUBCONTRACTOR's
site
organization
SUBCONTRACTOR's head office.
and
This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law.
SP Job No.
COMPANY
BP IRAQ NV
SP Doc. No.
00-ZA-E-02504
PROJECT
LOCATION
Sh. 22 of 22 Rev.
RUMAILA - IRAQ
Date 19/02/13
I.D.
c) Number of total working man-hours for the performance of the works, divided into
the above listed categories, and the maximum number of individuals foreseen
during peak period of the SUBCONTRACTORs work, the total man-months and
the relevant break down.
Constructional data provided by the SUBCONTRACTOR is accepted as indicative only
as a basic plan for the execution of the contract works. SUBCONTRACTOR shall
without exception be responsible to provide all resources at the required time to fulfil
his responsibilities and obligations under the terms and conditions of the contract and
its annex.
6.12 Subcontracting