Académique Documents
Professionnel Documents
Culture Documents
Keynote Lecture
Michael Kavvadas
Assoc. Professor of Civil Engineering
Historic buildings
Street level
Soft clay
First sand layer
Soft silt
Timber piles
Adv
anc
e
Tu
nn
el
TUNNEL
Pre-convergence
SUPPORT IS INSTALLED
Face
extrusion
Conclusion :
In non-TBM tunnels,
control of pre-convergence
(face extrusion) is critical
in urban tunnelling
Calculation of deformations
requires numerical modelling
(important in urban tunnels)
Support load
Minimisation of
pre-convergence
Minimization of
convergence
Control cutter-head overcut
TBM
NATM
(North of Alps)
SATM
(South of Alps)
and
tail-void grouting
Multiple drifts
(uR D)
Face pre-treatment
Stiff support
Early closure of ring
Slurry shield
p
EPB shield
screw
conveyor
p=0
bentonite
(pressure p)
excavated soil
(pressure p)
1
1
Steel sets
Forepoles
Fiber-glass nails
Shotcrete
application
1
1
open face
geostatic
arch
ATHENS
METRO
FG-nails
3 =
n Fy
P
=
A ( FS F ) A
FSo =
Ns =
(1 ) N s
2 po
cm
1 = (1-) po
po = geostatic stress
Factor of safety with FG-nails :
FS = FSo +
1 3 2
tan 45 +
(1 ) po
2
Face improvement
using grouting
Grouting : increases cohesion (c)
Factor of safety before grouting :
FSo =
Ns =
FS = FSo +
2 po
cm
(1 ) N s
1 = (1-) po
2 c
tan 45 +
(1 ) po
2
Athens Metro
Athens Metro : Ground improvement ahead of TBM (via a pilot tunnel)
using fiber-glass anchors and TAM grouting
Continuum models
Intact rock strength
controls response
Discrete models
Structural features
control response
Continuum models
Rockmass strength
controls response
2-D analysis of
tunnel face
stability:
UDEC Results
Kamata & Mashimo
(2003)
However :
Input preparation and output
presentation is often complicated
Analysis is time consuming
Improved accuracy may be
incompatible with the level of
knowledge of ground conditions
1.4
uy,max / D (%)
L=1m , t=10cm
L=1m , t=20cm
L=1m , t=30cm
1.2
Spyropoulos, 2005
unlined tunnel
1.0
u y ,max
0.8
0.6
= 0.0004 M s2.25
Ms =
0.4
0.2
E
1000 H 0.90 D 0.10
0.0
0.00
0.20
0.40
0.60
0.80
0.90
Ms = E / 1000H
1.00
1.20
1.40
0.10
Maximum extrusion uy,max (at tunnel face) as a function of the controlling ground
parameter Ms. Extrusion is not influenced by the installation of shotcrete lining
(thickness t) behind the face (distance L) correlation uy,max & Ms is useful E
2.0
1.8
L=1m , t=10cm
L=1m , t=20cm
L=1m , t=30cm
1.6
1.4
Spyropoulos, 2005
1.2
unlined tunnel
uz ,max
= 0.001 M s1.80
D
1.0
0.8
0.6
unlined tunnel
Ms =
0.4
E
1000 H 0.90 D 0.10
0.2
0.0
0.0
0.2
0.4
0.6
Ms = E / 1000H
0.8
0.90
1.0
1.2
1.4
0.10
Crown settlement uz,max (at tunnel face) as a function of the controlling ground
parameter Ms. Crown settlement is strongly influenced by the installation of shotcrete
lining (thickness t) behind the face (distance L).
Crown settlement cannot be used to assess the value of Ms ahead of the tunnel face
0.8
uy / uy,max
0.7
Spyropoulos, 2005
0.6
uy
0.5
0.4
u y ,max
0.3
= (1 + e
2
x R
R
0.2
0.1
0.0
0.00
0.25
0.50
0.75
1.00
x/ R
1.25
1.50
1.75
2.00
Extrusion uy as a function of the distance from tunnel face. Since the value of uy,max
is related to Ms correlation uy & Ms (for any x/R) is useful
Spyropoulos, 2005
uy,max / D (%)
1.4
1.2
n = number of FG-nails
F = mean axial force in FG-nails
A = tunnel section area
H = vertical overburden
without FG-nails
unsupported or supported with shotcrete
1.0
0.8
fG = 1000
fG = 4000
0.6
fG = 8000
f |G =
0.4
nF
A H
Ms =
E
1000 H 0.90 D 0.10
0.8
1.0
0.2
0.0
0.0
0.2
0.4
0.6
Ms
1.2
without FG-nails
unsupported
0.7
u z (x=0) / D (%)
n = number of FG-nails
F = mean axial force in FG-nails
A = tunnel section area
Spyropoulos, 2005
0.6
H = vertical overburden
without FG-nails
supported with shotcrete
0.5
f |G =
nF
A H
fG = 4000
0.4
0.3
fG = 8000
0.2
Ms =
E
1000 H 0.90 D 0.10
0.8
1.0
0.1
0.0
0.0
0.2
0.4
0.6
1.2
Ms
Spyropoulos, 2005
2.5
without forepoles
fF1 =1
uy,max / D (%)
2.0
fF1 =5
1.5
fF1 = I / S (cm3),
I = moment of inertia of a forepole tube
S = axial distance between forepoles
L = length of forepole overlap
D = tunnel diameter
fF1 =10
Ms =
fF1 =25
1.0
fF1 =50
E
1000 H 0.90 D 0.10
fF1 =100
L / D = 0.40
0.5
0.0
0.0
0.1
0.2
0.3
0.4
0.5
0.6
Ms
0.7
fF1 = I / S (cm3),
I = moment of inertia of a forepole tube
S = axial distance between forepoles
L = length of forepole overlap
D = tunnel diameter
unsupported
without forepoles
only shotcrete
0.8
uz(x=0) / D (%)
fF1 =1
fF1 =5
0.6
fF1 =10
fF1 =25
fF1 =50
0.4
Ms =
E
1000 H 0.90 D 0.10
fF1 =100
0.2
L / D =0.40
Spyropoulos, 2005
0.0
0.0
0.1
0.2
0.3
0.4
0.5
0.6
Ms
fF1 < 20
0.7
=1
=0
Zone 1
unsupported
Zone 2
supported
()
()
()
= deconfinement ratio
= 1
p
p = po (1 )
po
=1
=0
0<<1
()
()
()
p = (1 ) po
po = geostatic stress (isotropic)
Example :
=0.70 p = 30% po
Deconfinement using
section modulus reduction :
(1 2 ) (1 )
E=
Eo
(
)
1
2
Eo = ground E-modulus
Example :
=0.70 E = 10% Eo
Advantage : Good in anisotropic fields
p/po
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0.80
0.70
0.60
0.50
0.40
0.30
0.20
0.10
= 1 - p/po
= 0.25
0.571
0.438
0.333
0.250
0.182
0.125
0.077
0.036
Values of / for
= 0.30
0.533
0.400
0.300
0.222
0.160
0.109
0.067
0.031
= 0.35
0.480
0.350
0.257
0.187
0.133
0.090
0.054
0.025
E (1 2 ) (1 )
=
(1 2 ) +
Eo
uR(p)
2-D model
Calculation method :
3-D model : uR = uR(x)
2-D model : uR = uR (p)
or uR = uR ()
Thus :
= (x)
uR(x)
-0.1
-0.2
-0.3
-0.4
-0.5
-3
-2
-1
x/R 4
K +1
u
2
R
1
= 1
(k 1)N s u R
FLAC3D
Chern, 2000
uR
x
= 1 + exp 2.2 M s0.37
u R
R
Unlu, 2003
-0.6
-0.7
x
R
= f ; Ms
Panet, 1995
Ms =
-0.8
-0.9
TUNNEL
1.2
E
1000 H 0.90 D 0.10
-1
Conclusions
1. Ground deformations are critical
2. Estimates of ground deformations require 3-D numerical
analyses ( + ground model + ground properties)
3. Relevant ground properties (mainly E) can be obtained by
measurement of face extrusion & numerical back-analyses
(or use of the normalised graphs)
4. For many tunnel designers, 3-D analyses may seem too
sophisticated :
Methods exist to analyse the problem in 2-D using the
deconfinement method ()
Normalised graphs are available to estimate () in
tunnels without / with face pre-treatment