Académique Documents
Professionnel Documents
Culture Documents
S K KODANDARAMAIAH
Director(BD) & CEO
Sunil Hi Tech Engrs Ltd
Plant Engg
Engg Drgs
Owners
Engr
Owner/EPC
Contractor
Fab. Drawings
Cranes
Welding eqpt
Skilled/Unskilled
Painting
Bought out items
Structural
Raw Mats
From
Steel Plants
OR
Civil & Str
BTG & BOP
Civil
Batching plant
Other equipment
Sand & Metal
BOIs,Cement & Steel
Bar bending
Labour
Detailer
Excavation
Fabrication
concreting
Erection
Architectural
& Buildings
50
40
30
20
10
0
NDCT /
Chimney
Buildings
Flooring Foundation
work
Super Str.
Description(
Boiler)
Event
Remarks
LU & CF
Syn & CF
Foundations
Mat feeding issues
Prob of erecting coal pipes
CHP & AHP Civil work problems
Full Load
LU & CF shortfalls
from the beginning
LU & CF
Sl
No
Description
Others)
Event
Remarks
Mismatch between
TG Deck and TG
building Readiness
TG
Erection
Start
Full
Load
BOF to ESP
Foundations & Str
For Ducts
For FD/PA Fans
Fan Handling str
TPs of CHP
PAPH Str
LU/CF/F
ull Load
Pipe rack
Foundations
Structures
LU/CF
Problem Areas:
TG Island Side
Interfacing of CEP Pit, CW Piping along the A and B row of TG
Building
Aux column foundation work and structural work around the
TG Deck & Operating Floor completion with TG Building work
Project
DB
Power
(600 MW)
Koradi
(660
MW)
Vallur
(500MW)
Unit
TG Deck
casting
comp. in
TG Bldg
with TG
floor
readiness
EOT Crane
readiness
TG Bldg. Structure
with floors
readiness
(In months)
(In months)
MT
(In months)
MT
#1
13 months
15 Months
11 Months
2900 MT
18 months
6500 MT
#2
18 months
(Anticipate
d)
21 Months
(Anticipated)
17 months
(Anticipate
d)
2900 MT
23 months
(Anticipate
d)
6000 MT
#8
14 months
18 months
12 Months
3000 MT
21 months
(Anticipate
d)
5200 MT
#9
21 months
(Anticipate
d)
23 months
(Anticipated)
18 Months
2500 MT
27 months
(Anticipate
d)
5200 MT
# 10
26 months
Anticipated
28 months
Anticipated
24months
Anticipated
2500 mt
32months
Anticipated
5200mt
#1
14 Months
750 MT
27 Months
6500 MT
#2
19 Months
2000 MT
40 Months
6500 MT
Area
250mw
500/600mw
660mw
Remarks
5000
6500
7500
Bunker Str
3500
5000
6000
Pipe Racks
600
1500
2500
Common
Service Building
750
1800
2000
Common
250
400
500
Comp House
100
150
200
Common
150
200
250
Common
200
350
400
Common
CWP House
500
1000
1200
Common
11050
16900
20350
FOR MULTIPLE
UNITS
Capacity in MW
500
Total Structures
19900
28500
76350
5000
9000
15000
24900
37500
91350
50
31
28
1000/1200
3300
30000m2 to 50000m2
BUNKER
SHELL
BUNKER
HOPPER
FEEDER
FLOOR
22.4m
M
N
Bunker Shell
SS Hopper
Deck Sheet
Cladding for Bunker Sealing
RCC
Tripper floor
Bunker
supporting
str
22.0 mtr
feeder
floor
Tripper floor
Bunker
supporting
str
22.0 mtr
feeder
floor
M
N
Tripper floor
Bunker
supporting
str
22.0 mtr
feeder
floor
N
Advantages
Factory made work, better quality
Erection can be faster
No need for large infrastructure at site
No burden of raw material procurement
Welding work can be eliminated
Saving in cycle time if properly managed
work can be done with less work force
CENVAT benefits can be taken
Disadvantages
Fab + Ern cost go up by 20 to 25%
ED on factory dispatch's on site work
Transportation cost extra on large components
No flexibility on managing matching items
Non sequential supplies can delay the site work
can nullify the advantages if shipments are non sequential
Addl cost for site storage and MM
High levels of accuracy for manufacturing & tolerances
High levels of erection accuracy reqd
Detailing to be done by Customer
Total cost per MT can go up by 10-12%
FOCUS AREAS
KEY ACTIONS
Boiler Foundations
Labour arrangement
Shuttering & staging material
Drgs
Clearances
SAFETY RECORD
Civil & structure package
LOOKING AHEAD
Engg inputs to be ahead for 3 to 5 months progress of site work
Adequate and timely investment in Roads, Drains, Const Power & Infra
Improve mechanization and reduce dependence on labour
- More Use of Boom placers, concrete pumps
- Use of Deck sheeting for floor work
- Use of RMC wherever it is feasible
- Use of higher capacity cranes and more in nos
- Use of Tower cranes for Building works
Pre pone CHP Civil works between Boiler and ESP by 6 months
Better integration of Civil and Structural works of TG Building
Invest in Monsoon preparation on temporary works
Switch over to Bolted structure for major structural work
HR initiatives for Strengthening Civil and Structural Supervision
Improving Construction safety records
Provide differential rates for concreting of Buildings & Floor works
Proper escalation clauses for Cement and Steel price volatility
Prioritize Bunker work on RHS and LHS
Plan for LU with Coal firing instead of Coal firing for Full load operation