Académique Documents
Professionnel Documents
Culture Documents
WORKBOOK
Detailed Explanations of
T1 : Solution
6
H
D
A
B
11
P
12
C
L
10
T2 : Solution
D
4
A
1
7
E
12
17
Q
I
8
15
11
18
14
19
20
C
3
9
K
13
16
L
10
www.madeeasypublications.org
Copyright
Workbook
T3 : Solution
L
G
Copyright
www.madeeasypublications.org
T1 : Solution
3 4
tE
=3
tE
=
5
0 0
7 8
tE = 4
tE
=5
5
13 13
tE = 8
3
5 5
Total float = TL j t i j TE i
Free float = TE j TE i + t i j
www.madeeasypublications.org
12
13
13
13
Copyright
Workbook
T2 : Solution
Network,
TE = 11
TL = 12
TE = 7
TL = 8
D
6
t=4
H
TE = 13
t=8
TL = 13 I
T = 20
5
8 E
TL = 20
t=7
t=2
J
t=3
7
G
TE = 14
TL = 18
3
TE = 0
TL = 0
1
B
A
t=5
t=
t=4
2
tE = 5
C
TL = 6 t =
6
t=2
F
4
TE = 11
TL = 11
t0
tm
tp
te
10
22
22
20
20
20
20
20
10
16
10
14
32
15
25
20
10
14
20
14
12
16
11
5.4
2.32
16
38
18
28.4
5.33
14
Variance ( )
S=0
TE TL
S=0
TE TL
0 0
S=0
TE TL
20 20 d (15) 35 35
5
2
)
20 TE TL
10)
(
(
e
a
20 25
f (14)
b (20)
3
1
g(
4)
c
(1
0)
6
4
h (11)
10 25
24 45
S = 15
S = 21
TE TL
TE TL
i (1
8)
S=0
TE TL
7 53 53
)
j (8
2a + d2 + i2 =
4 + 25 + 28.4 = 7.576
www.madeeasypublications.org
TS TE
Probability factor,
z=
z = 1.5 +
2.0 1.5
(95 93.92) = 1.635
97.92 93.92
Ts 53
Ts = 65.38 66 days
7.576
Time for 95% probability completion is 66 days.
1.635 =
T4 : Solution
16 16
6 6
20 20
29 29
0 0
Dummy
B
3
20 20
t 0 + 4t m + t p
6
www.madeeasypublications.org
,=
tp t0
6
Activity
t0
tm
tp
te
1-2
2-3
11
20
12
2-4
16
2-5
20
10
2.67
3-4
3-7
13
1.67
4-6
10
13
10
5-6
17
2.33
6-7
10
1.33
7-8
0.67
Copyright
Workbook
Calculation of TE, TL and slack has been done in network diagram below:
S=0
TE = 17
TL = 17
S=0
TE = 31
TL = 31
S=0
TE = 5
TL = 5
12
S=0
TE = 0
TL = 0
S=0
TE = 35
TL = 35
10
4
S=0
TE = 17
TL = 17
10
S=0
TE = 27
TL = 27
5
S=4
TE = 15
TL = 19
=
Z =
For 95% pr
obability
probability
obability,,
Z = 1.6 +
1.647 =
0.1
0.48 = 1.647
95.54 94.52
TS 35
D0
0
7
A5
5
12
0
7
B3
5
12
5
12
H4 9
16
9
16
L6 15
22
3 G 7
7
16
12
9
20
J2
16
16
K6 22
22
3 F 9
6
9
3
0
1
C8
8
9
8
9
9
9
I7
11
22
22
22
F0
16
16
E7 15
16
Calculation of EST, EFT, LST, LFT and FT are done in table below:
Copyright
www.madeeasypublications.org
LFT
FT
12
15
16
12
16
12
16
16
16
11
20
22
11
16
22
16
22
15
16
22
F0
22
22
22
22
Activity
ti
EST
EFT
LST
D0
Ramarks
Critical path
Critical path
Critical path
Critical path
Activity
ti
EST
EFT
LST
LFT
FT
D0
A
B
14
10
10
15
14
15
10
15
15
17
14
23
K
L
14
20
17
23
15
23
15
23
F0
23
23
23
23
Ramarks
Critical path
Critical path
Critical path
www.madeeasypublications.org
Copyright
Workbook
15 15
C
10
1
0 0
A
5
L
8
G
10
3
5 5
E
9
5
14 17
K
6
7
23 23
H
9
4
8
Copyright
www.madeeasypublications.org
T1 : Solution
Total direct cost (normal) of the project = 250 + 350 + 300 + 700 = ` 1600
Cost slope of P =
350 250
= `100/ day
76
Cost slope of Q =
500 350
= ` 75/ day
10 8
Cost slope of R =
400 300
= ` 50/ day
53
950 700
= ` 250/ day
98
Normal duration, crash duration and cost slope of each activity is indicated on the arrow diagram as shown
below.
Cost slope of S =
7
7
6
6
7
7
6
6
2
P
0
0
0
0
0
0
0
0
www.madeeasypublications.org
100
1
50
Q
75
250
12
10
9
9
12
10
9
9
21
19
18
17
21
19
18
17
Copyright
Workbook
Duration Indirect
(Days) Cost (`)
11
S.No
Description
All Normal
21
3990
1600
5590
Crashing R
by 2 days
19
3610
1700
5310
Crashing P
and Q each
by 1 day
simultaneously
18
3420
1875
5295
Optimum
duration
Crashing S
by 1 day
17
3230
2125
5355
Minimum
duration
Normal
duration
0
D0
LF = 0
10
LF = 2 LF = 6 LF = 16
LF = 26
LF = 33
LF = 20
LF = 42
LF = 25
8
LF = 44
0
F0
4
K
LF = 38
5
LF = 25
LF = 33
LF = 44
LF = 38
Copyright
www.madeeasypublications.org
12
T3 : Solution
The mathematical modelling of CPM network is shown in the figure below:
13
12
11
10
10
9
9
9
8
9
9
9
9
9
9
9
9
8
2
6)
9(
20
15(10)
30
8(
5)
10
(6
15 )
25
3
8
8
8
8
8
8
7
6
5
Sl. No.
Description
20
19
18
17
16
15
14
13
12
10
0
0
0
0
0
0
0
0
0
3)
5(
0
0
0
0
0
0
0
0
0
8
8
8
8
8
8
7
6
5
4
18
17
16
15
15
14
13
12
11
2(1)
40
18
17
16
15
15
14
13
12
11
20
19
18
17
16
15
14
13
12
Total cost
(`)
1200
1.
All normal
2.
Crashing (3-4)
by 1 day
19
1140
15
1155
3.
Crashing (3-4)
by 1 day
18
1080
30
1110
4.
Crashing (3-4)
by 1 day
17
1020
45
1065
5.
Crashing (4-5)
by 1 day
16
960
85
1045
6.
Crashing (3-4)
and (1-4) by 1 day
15
900
130
1030
7.
14
840
195
1035
8.
13
780
260
1040
9.
12
720
335
1055
www.madeeasypublications.org
Remarks
Normal
Length
Optimum
Length
Minimum
Length
Copyright
Workbook
13
5(2)
TE = 0
TL = 0
4(2)
7(5)
TE = 13
TL = 13
TE = 4
TL = 4
7(5)
D
4(2)
5(2)
4(2)
10
11 12
13
Duration
(weeks)
Cost slope
Crash
Normal
Activity
Cost
Duration
(weeks)
Cost
(C/T)
1- 2
(`)
4000
(`)
12000
8000
4000
2- 3
3000
7500
4500
1500
2-4
3600
6000
2400
1200
3-4
5000
10000
5000
2500
Total pr
oject cost at nor
mal duration
project
normal
Normal duration = 13 weeks
Direct cost = 4000 + 3000 + 36000 + 5000 = 15600
Indirect cost = 13 2000 = 26000
Total cost = 15600 + 26000 = 41600
Copyright
www.madeeasypublications.org
14
4(2)
3(2)
4(2)
10
11
4(2)
2(2)
4(2)
10
Again we have two critical path and hence combination of crashing of activities have to be checked for
minimum cost slope.
1. C/S 1 2 = 4000/week
2. C/S 2 4 + C/S 3 4 = 1200 + 2500 = 3700/week
So, 2 3 and 3 4 has to be crashed by 1 week as its cost slope being minimum.
New project duration is 9 weeks.
Direct cost = 21300 + 3700 = 25000
www.madeeasypublications.org
Copyright
Workbook
15
4(2)
2(2)
3(2)
2(2)
2(2)
3(2)
13
11
10
Direct cost
15600
18600
21300
25000
33000
Indirect cost
26000
22000
20000
18000
14000
Total cost
41600
40600
41300
43000
47000
Copyright
www.madeeasypublications.org
Engineering Economy
T1 : Solution
The cash flow diagram is
1
24
25
12000
13000
14000
35000
36000
The given series is an equivalent to superposition of a uniform annual series with a = `12000 and a
gradient series with g = `1000. Hence the present worth of the maintenance cost is
p
= 12000
(1 + 0.09)25 1
+ 1000
0.09(1 + 0.09)25
1
0.09
25
25
(1 + 0.09) 1
25
25
+
+
0.09(1
0.09)
(1
0.09)
www.madeeasypublications.org
3000
1000 2000
2
3
4
A=?
P=?
4000
5
i=
5000
6
6000
7
7000
8
20%
= 10%
2
Copyright
Workbook
17
i = 10%, n = 8
We know that
1 n
i
A = g
n
i i (1 + i ) 1
A = 1000(3.0045) = ` 3004.50
Now,
(1 + i )n 1
P = 3004.50
i (1 + i )n
Copyright
www.madeeasypublications.org
Concreting Equipments
T1 : Solution
Adjusted output due to angle of swing=120 0.88 = 105.6 m3/hr
Taking loss due to job conditions = 40%
63.36
= 57.6 m3/hr
1.1
50 60
27
Output of the shovel = Bank measure vol. in one cycle in cum No. of cycle/hr
=
www.madeeasypublications.org
1.8 50 60
= 200 m 3 /hr
27
Copyright
Workbook
19
T3 : Solution
Time required per trip in minutes (or cycle time) =
=
D D
+ +G
F R
30
30
+
+ 0.3 ( assume) minutes
2.4 1000 6.0 1000
60
60
3
45
= 80 cum/hr
T4 : Solution
Here, S = 4.5 kmph or 4500/60 m/min
h = 45 min., l = 2.4 m, n = 1, p = 1/8, t = 0.4 m and N = 5
Therefore,
Q=
1 0.4
Shl n pt 4500
=
45 2.4 1
= 81 m 3
N
60
8
5
Copyright
www.madeeasypublications.org