Vous êtes sur la page 1sur 1

EXTENSION OF TIME occurring to more than 28 days EXTENSION OF TIME

CLAIM PROCEDURES after causation. - LIQUIDATED DAMAGES


AND ASSESSMENT In any event, it is distinctly AND DELAY DAMAGES
possible that these time Under AS4902 (Clause 34.7), the
David Fabian and Ian Briggs
requirements are not time bars. superintendent is obliged to
Minter Ellison That possibility arises because of certify liquidated damages as due
the wording of Clause 41.2. and payable to the principal. This
will create greater certainty as to
There are a number of areas of EXTENSIONS OF TIME - the principal's ability to recover
change to the extension of time ASSESSMENT liquidated damages from the
claim provisions: Assessment of claims is dealt with contractor.
EXTENSION OF TIME under Clause 34.4. According to
the terms of that clause: Delay costs were dealt with in
- QUALIFYING CAUSES Clause 36 of AS4300.They are
OF DELAY • If both qualifying and non- dealt with in Clause 34.9 of
Clause 35.5 of AS4300 contained qualifying causes of delay overlap, AS4902, and AS4902 will lead to
quite complicated references to AS4902 obliges the recovery of greater amounts than
the types of delays that would superintendent to apportion delay AS4300. Under AS4902,'delay
entitle contractors to claim to WUC according to whether it is damages' are payable for
extensions of time. These lengthy non-qualifying or qualifying cause extensions of time arising from a
provisions have been replaced of delay. This is a change in risk 'compensable cause' (i.e. a matter
with a statement that the which operates in favour of the within the control of the principal
contractor will be entitled to claim contractor, as it leaves open the or superintendent). The 'damages'
an extension of time if (inter alia) possibility of the contractor being are to be assessed by the
the contractor 'is or will be granted an extension of time even superintendent and (unlike
delayed in reaching practical if it was also delaying the works to AS2124 or AS4300) will include
completion by a qualifying cause some extent. This concept loss of profit and fixed overheads
of delay' (Clause 34.3). 'Qualifying replaces the concept of recovery.
cause of delay' is widely defined to 'concurrency' (Clause 35.5)
be anything other than a breach provisions of AS4300 and AS2124,
or omission by the contractor, or which have been notoriously
industrial conditions/inclement difficult to apply. However it
weather occurring after the Date remains to be seen whether the
for Practical Completion. new 'apportionment' approach is
any easier to administer.
EXTENSION OF TIME CLAIM
• It is the committee's intention
-TIME BAR that the contractor still 'owns the
Under Clause 34.3, the contractor float' although the relevant clause
is only entitled to extension of time is not ideal and may give rise to
claims if it submits a written claim differing interpretations.
for an extension of time 'within 28
days of the time when the • If the superintendent does not
contractor should reasonably respond to an extension of time
have become aware of that claim within 28 days of receiving it,
causation occurring'. then the extension of time is
deemed to be granted as an
AS4300 contained a similar time assessment and direction (Clause
bar, with the contractor being 34.5). To challenge the claim, the
obliged to give a notice within 28 principal will be forced to go
days 'after the delay occurs'. through the claim provisions (i.e.
Although the new standard avoids challenge a direction of the
the difficulties with establishing superintendent). This is likely to
when the delay 'occurs' it is not cause difficulties where the
clear whether difficulties will now superintendent complains that
arise as to when the 'causation' the claim lacks sufficient detail to
occurs, and there is risk of delay enable a proper assessment.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #77 MAY/JUNE 2001 23

Vous aimerez peut-être aussi