Vous êtes sur la page 1sur 3

1

Piling

Nos

88

5/13/2016

5/28/2016

1.i

Pile head breaking

Nos

88

5/14/2016

6/28/2016

1.ii

Pile cap

Cum

150

5/21/2016

7/10/2016

Plinth Beam

Cum

70

7/2/2016

8/16/2016

3a

1st Floor EL +3.95m (31 x 19.5m)

3a.i

Column (29 nos)

3a.ii

Reinforcement

MT

7/27/2016

8/4/2016

3a.iii

Shuttering

Sqm

168

8/1/2016

8/14/2016

3a.iv

Casting

Cum

28

8/6/2016

8/21/2016

3b

Slab EL +3.45 (31 x 19.5)

3b.i

Shuttering

Sqm

1176

8/12/2016

9/1/2016

3b.ii

Reinforcement

MT

24

8/15/2016

9/9/2016

3b.iii

Casting

Cum

196

9/10/2016

9/10/2016

PCC flooring at 0.0m LVL

Cum

7/12/2016

8/21/2016

Slab EL +7.95m (31 x 19.5) Control room, Aes Room, Office room & toilet

5a

Column 29nos

5a.i

Reinforcement

MT

9/12/2016

9/22/2016

5a.ii

Shuttering

Sqm

252

9/15/2016

9/27/2016

5a.iii

Casting

Cum

42

9/18/2016

10/1/2016

5b

Slab +7.95 m

5b.i

Shuttering

Sqm

462

9/24/2016

10/2/2016

5b.ii

Reinforcement

MT

9.24

9/30/2016

10/8/2016

5b.iii

Casting

Cum

77

10/9/2016

10/9/2016

Column

6a.i

Reinforcement

MT

1.68

11/5/2016

11/7/2016

6a.ii

Shuttering

Sqm

84

11/6/2016

11/9/2016

6a.iii

Cum

14

11/7/2016

11/10/2016

6b

Casting
Slab +10.95m LVl

6b.i

Shuttering

Sqm

336

11/10/2016

11/22/2016

6b.ii

Reinforcement

MT

6.72

11/19/2016

11/29/2016

6b.iii

56

11/30/2016

11/30/2016

7a

Casting
Cum
Column upto EL +12.45m (23nos)

7a.i

Reinforcement

MT

3.6

10/12/2016

10/20/2016

7a.ii

Shuttering

Sqm

180

10/16/2016

10/28/2016

7a.iii

Casting

Cum

30

10/22/2016

11/1/2016

7b

Slab EL +12.45m Lvl (28m x 19.5m)

7b.i

Shuttering

Sqm

588

10/25/2016

11/6/2016

7b.ii

Reinforcement

MT

11.76

10/29/2016

11/12/2016

7b.iii

Casting

Cum

98

11/13/2016

11/13/2016

Finishing

8.i

Brick work, Plaster & Painting & Finishing

8.ii

Ground floor

10/15/2016

11/14/2016

8.iii

1st Floor EL

11/13/2016

12/13/2016

8.iv

3rd Floor

12/20/2016

1/9/2017

9/12/2016

11/30/2016

Equipment and other Foundation

Dormitory ( 7 x 20m)
1

Excavation

360

7/10/2016

7/15/2016

PCC

13.5

7/15/2016

7/19/2016

Foundation

3.i

Reinforcement

5.237

7/19/2016

7/28/2016

3.ii

Shuttering

261.864

7/24/2016

8/5/2016

3.ii

Casting

43.644

7/30/2016

8/7/2016

Column up to Ground level

4.i

Reinforcement

0.304

8/4/2016

8/6/2016

4.ii

Shuttering

15.188

8/6/2016

8/10/2016

4.iii

Casting

2.531

8/11/2016

8/16/2016

Plinth beam

43.512

8/14/2016

8/29/2016

37.275

8/31/2016

9/6/2016

Backfilling
Slab EL +3.75m (17.75 x 6.88)

7a

Column GL to +3.75M (22 nos)

7a.i

Reinforcement

0.875

9/2/2016

9/9/2016

7a.ii

Shuttering

43.740

9/6/2016

9/12/2016

Dec-16

Pilling- 28-may

1st Floor slab - 10-Sep

2nd Floor slab - 10

Slab EL +10.95 (19.5 x 11m)

6.a

Nov-16

Finish Date

Oct-16

Start Date

Sep-16

Quantity
(Approx)

Aug-16

Unit

Jul-16

Activities

Jun-16

Sl. No

May-16

132KV GIS SONAKHALI


DETAIL WORKING SCHEDULE

3rd Floor slab - 10-Oct

GIS ROOM NOV-16

7a.iii
7b

Casting
Slab EL +3.75m

7b.i

Shuttering

7b.ii

Reinforcement

3.043

9/16/2016

9/21/2016

7b.iii

Casting
Slab EL +6.3m (17.75 x 6.88)

25.356

9/22/2016

9/22/2016

7.290

9/9/2016

9/14/2016

152.137

9/13/2016

9/17/2016

8.a

Column

8.a.i

Reinforcement

0.648

9/24/2016

9/27/2016

8.a.ii

Shuttering

32.414

9/26/2016

10/3/2016

8.a.iii

5.402

10/1/2016

10/6/2016

8.b

Casting
Slab EL +6.3m

8.b.i

Shuttering

152.137

10/4/2016

10/8/2016

8.b.ii

Reinforcement

3.043

10/7/2016

10/14/2016

8.b.iii

Casting

25.356

10/15/2016

10/15/2016

Slab EL +9.9m (16.75 x 6.88)

9.a

Column

9.a.i

Reinforcement

0.913

10/17/2016

10/24/2016

9.a.ii

Shuttering

45.644

10/22/2016

10/31/2016

9.a.iii

Casting

7.607

10/28/2016

11/4/2016

152.137

11/3/2016

11/6/2016

9.b

Slab EL +9.3m

9.b.i

Shuttering

9.b.ii

Reinforcement

3.043

11/4/2016

11/9/2016

9.b.iii

Casting

25.356

11/10/2016

11/10/2016

10

Momty room (2.75 x 4.58m)

10.a

Column

10.a.i

Reinforcement

0.185

11/12/2016

11/14/2016

10.a.ii

Shuttering

9.261

11/14/2016

11/16/2016

10.a.iii

Casting

1.544

11/15/2016

11/17/2016

10.b

Slab 12.25m

10.b.i

Shuttering

11.157

11/17/2016

11/18/2016

10.b.ii

Reinforcement

0.223

11/18/2016

11/20/2016

10.b.iii

Casting
Brick work, Plaster, Painting

1.860

11/21/2016

11/21/2016

11
11.a

Ground floor

11.b

1st floor

10/27/2016

11/26/2016

11.c

2nd floor

11/19/2016

12/19/2016

11.d

3rd Floor

12/6/2016

1/5/2017

11.e

4th Floor

12/27/2016

1/26/2017

Manpower Deployment Plan


MONTH
Area

Unit

Average
Peak
Reqmnt. Per Reqmnt. Per
Day
Day

May/16

Jun/16

Jul/16

Aug/16

Sep/16

Oct/16

Nov/16

Dec/16

Jan/17

Quantities
Concrete
Reinforcement Steel
Shuttering + Scaffolding

CuM
MT
SqM

5
0.5
28

11
1.1
66

117
12
704

284
28
1,704

275
29
1,652

180
18
1,083

2
5

2
10

283
28
1,700

169
18
1,013

260
26
1,562

2
5

2
4

MANPOWER PLAN MONTH WISE

Manpower
Charge Hand/ Supervisor
Mason
Stagging & Shuttering Carpenter & Helper
(Making+Fixing)
Steel Fixer (Cutting/Bending + Binding)
Unskilled Helper
TOTAL MANPOWER

No.s/ Day
No.s/ Day

2
5

2
10

No.s/ Day

16

No.s/ Day
No.s/ Day
No.s/ Day

4
8
23

9
22
51

1
2

1
4
7

4
3
17

16
9
7
38

16

2
10
10

9
7
39

6
5
33

16
9
7
45

10
6
4
37

2
4
15

2
2
-

8
22
51

0
20
26

0
15
19

App. Shuttering Material Requirement

Note:
1) Single Shift Working/ Day is considered
2) Average Procutivity of Shuttering Carpenter for making & fixing shutters is considered as 4 SqM/Day per person
3) Average Procutivity of Steel Fixer for cutting, bending & fitting is considered as 100 Kg/Day per person

Steel Pipe
in Nos.

4) The number of masons and other labour may vary as per requirement/ nature of concrete pour, brick work

Shutttering

3mt
6mt
Clamp

1000 nos
1900 Nos
6000 nos
9450

60
Unskilled Helper
50
Steel Fixer (Cutting/Bending + Binding)
7

40
Stagging & Shuttering Carpenter & Helper
(Making+Fixing)

7
5

30
Mason

Charge Hand/ Supervisor

10

4
16

20
3
4

16

16

10

6
20
10

10

22

15

10

15

04

0
2-

May/16
May/16
3

Jun/16
Jun/16
7

Jul/16
Jul/16
7

Aug/16
Aug/16
5

Sep/16
Sep/16
7

Oct/16
Oct/16
4

Nov/16
Nov/16
22

Dec/16
Dec/16
20

Jan/17
Jan/17
15

Steel Fixer (Cutting/Bending + Binding)

Stagging & Shuttering Carpenter & Helper


(Making+Fixing)

16

16

10

16

10

15

Mason

10

10

Charge Hand/ Supervisor

Unskilled Helper

Vous aimerez peut-être aussi