Académique Documents
Professionnel Documents
Culture Documents
Example-I
You are constructing your home with a target budget of
100,000 USD. You are halfway to completion, and you
feel that you may have to spend more than what you had
planned. Therefore, you ask your contractor to give you a
fresh estimate for the remaining work.
Your contractor calculates the cost of the remaining work
and tells you that from now it will take 70,000 USD to
finish building your home.
This 70,000 USD is the Estimate to Complete.
Example-II
You are working with a project that is 30% completed,
Example-III
There is another scenario in which you may want to
calculate the Estimate to Complete.
Suppose that youre building a five story building and,
due to a financial crisis, you cannot complete the project.
Therefore, you decide to cut your building to three stories
from five stories to save some money.
In this case, the Estimate to Complete will help you
calculate your savings.
So the Estimate to Complete (etc) is a forecasting tool in
project management that tells you the expected amount
of money that will be spent to complete the remaining
part of the project.
I hope this concept is clear to you.
However, there is another forecasting tool that is often
confused with the Estimate to Complete. This tool is the
Estimate at Completion (EAC).
There is a difference between Estimate to Complete and
estimate at completion.
Estimate at completion is the total cost of the project at
the end. On the other hand, Estimate to Complete is the
amount of money required to complete the remaining
work from a given date.
Moreover, when the project starts, the EAC is equal to
the ETC. As the project progresses, the ETC starts
decreasing, and at the end of the project it becomes
zero.
Complete
1
2
= 50,000 USD
Earned Value (EV) = 40% of 100,000 USD
= 40,000 USD
To determine ETC first we have to find the EAC.
And, EAC = BAC/CPI
Hence, Cost Performance Index (CPI) = EV / AC
= 40,000 / 60,000
= 0.67
Therefore, Cost Performance Index (CPI) = 0.67
Now, Estimate at Completion (EAC) = BAC/CPI
= 100,000/0.67
= 149,253
Estimate at Completion (EAC) = 149,253 USD
Now, Estimate to Complete (ETC) = EAC AC
= 149,253 60,000
= 89,253 USD
Hence the Estimate to Complete (ETC) for this project is
89,253 USD.
Summary
The Estimate to Complete is the anticipated cost that you
will need to complete the remaining part of the project.
This is a forecasting tool and you will use it when the
previous estimate is no longer valid and you need a fresh
estimate for the rest of the work. Tracking ETC gives you
information on the projected cost of the remaining work.
You will use this tool whenever something goes wrong
and the cost baseline deviates. You will use this tool as
quickly as possible and communicate to stakeholders to
get the new budget approved.
This is the end of this blog post on Estimate to Complete.
If you have something to share, you can do so through
the comments section. Now, you can move on to the next