On 19th July 2015 there was a Landslide at Km 41.280 near Adoshi Tunnel at 12.00 PM
on Mumbai Corridor which led to the traffic block on both Mumbai and Pune Corridor
forcing to close the Mumbai corridor completely and Pune Corridor for 1.00 Hr and
further utilize Pune Corridor for diverting the traffic towards Mumbai.
Now please find herewith the chronology of the events as below:
1. Landslide occurred at KM 41.280 near Adoshi Tunnel at 12.00PM on Mumbai
Corridor. The Rockfall debris was spread on Mumbai and partly on Pune
Corridor.
2. A Car Indigo MH 04 EQ 8241 was badly damaged due to Rock fall and led to 3
Fatal and 1 Major injury. The Rock fall also damaged the front glass of the trailer
RJ 09 GB 9197. The victims were shifted to the Lokamanya Hospital.
3. One Loader and Poclain with 2 Dumpers was immediately deployed at the
location for removing the Rockfall debris.
4. Rockfall from Pune corridor was cleared and by 1.20 PM the Pune corridor was
cleared.
5. 2 lanes were utilized for the traffic towards Pune and 1 lane was dedicated for
the traffic towards Mumbai.
6. The traffic towards Mumbai was resumed at 2.30PM and was diverted from
Mumbai corridor vides the median opening present at KM 41.540.
7. Due to the big size boulders present a Poclain with breaker arrangement was
also deployed at the site in-order to break the boulders. Three (3) nos used for
shifting of muck from the site. The muck was unloaded near the khopoli exit
down ramp of NH4.
8. List of Machineries / Equipments present at the location:
JCB 1no.
Loader 1no.
Poclain 1no.
Breaker 1 no.
Tippers/dumpers 3nos.
Patrolling Vehicle 3 nos.
9. Approximately 400-500 Cum of muck was cleared from 12.00 pm to 8.45 PM i.e.
approximately 9 hours. Mumbai corridor was not functioning during this time.
10. The muck was cleared by 8.45 PM and the traffic in Mumbai corridor was
resumed in 2 lanes keeping the slow lane closed as a part of safety measure.
Drums, blinkers, cautionary sign boards and reflective stickers on drums were
arranged.
11. Visits :
Honorable Minister and team were present at the location till the
completion of the work.
Honorable Minister Shiv Tare also visited the site.
e) Various photographs matching the site conditions of Khandala and Adoshi were
shown by J Kumar.
f) The approximate cost for 100mt length extension and 5.7m height for both
carriageway mentioned was Rs 30 cr.
g) J K
A) Costing details
Sr. No
Name of Work
Project
Remarks
Cost
(Crores)
3.
110.00
110.00
The Scheme was principally agreed by Hon Minister Shree Eknath Shinde and will be
further processed once the proposal is submitted by J Kumar.