WEEKLY REPORT OF
18th Apr 2016 24th Apr 2016
Prepared by DELUGE
Page 1 of 6
1.
1.1
a.
SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.
QA/ QC
- No Issued
4. PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission
4.2 Update Construction Progress
4.2.1 Fire System
4.2.2 Mechanical
Under Ground;
a.
Parking Area;
Progress :
- Jointing Hydrant Line between Parking area Line (Admin Building) with North Line to
Pipe Bridge under the Drainage is done.
- Jointing Hydrant Line at Crossing Road area is done.
Cikarang Power Station Project Babelan,
Bekasi, Indonesia
Page 2 of 6
b.
c.
d.
e.
f.
Above Ground;
a.
Piperack
WTP area;
Piping Progress :
Boiler 1 Area;
Piping Progress :
Fit-Up Progress
Welding Progress
: 0 Joints
: 5 Joints
Fit-Up Progress
Welding Progress
: 0 Joints
: 4 Joints
Pump House
Power Island:
Fire Pumps Leveling & Centering Internally is done.
Daily Fuel Diesel Tank Internal Leveling and Centering is done.
FHS:
Fire Pumps Leveling & Centering Internally still on going.
Daily Fuel Diesel Tank Internal Leveling and Centering still on going.
Boiler Cable Basement Unit 1;
Piping Progress :
Install Control Valve Header
Internal Line Check is done
Install temporary Test Flange.
Page 3 of 6
d.
e.
f.
g.
-
Page 4 of 6
g.
Above Ground;
a.
Pipe Rack;
- WTP Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- Boiler 1 Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- FHS Cable Bridge:
Progress Target : Erection pipe to the Cable Bridge for 20 Lengths Pipe.
b.
Boiler Cable Basement Unit 1;
Progress Target: Install Control Valve Header, Official Joint Line Check and Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Install Control Valve Header, Official Joint Line check and Hydrotest
d. CAB Cable Basement;
Progress Target: Complete piping installation, Install Control Header.
e.
Switchgear Cable Basement:
Progress Target: Complete piping installation, Install Control Header.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
GIS Basement
Progress Target: Piping installation, Install Control Header.
h.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
i.
Fire Pump House
Power Island;
Progress Target: Joint Inspection for Leveling and Centering Pump Installation, Internal
Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Internal check continue to Joint Inspection Centering and Leveling
Pump Installation.
j.
BC-09
Progress Target: Install Piping Sprinkler System
k.
Workshop
- Fabrication;
Control Valve Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication,
Threading Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.
Page 5 of 6
Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Laying and Buried the Pipe under the drainage (Crossing Area).
Tanks Area : Continue Spreading and Joint pipe to Dust Suppression Pump.
MATERIAL DELIVERIES
- Raw Piping Material; 1 Truck
7. TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.
Other Issues
- No Issues
Page 6 of 6