Vous êtes sur la page 1sur 6

Ref. No.: BPS-121081-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia
No. 031

WEEKLY REPORT OF
18th Apr 2016 24th Apr 2016

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 1 of 6

1.
1.1

a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 11
PT Surabaya Prakarsa Fire Service (Fire Alarm)
: 10
PT Piping System Indonesia (Aboveground)
: 74 (Add 2 Welder & 4
Scaffolder)
PT Valvtrol Global Flowsystem (Underground)
: 15
Total Manpower
: 110

1.2 Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
2.
3.

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Yaakop
Joey
Rahman

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Engineer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)

SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.
QA/ QC
- No Issued

4. PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission
4.2 Update Construction Progress
4.2.1 Fire System
4.2.2 Mechanical
Under Ground;
a.
Parking Area;
Progress :
- Jointing Hydrant Line between Parking area Line (Admin Building) with North Line to
Pipe Bridge under the Drainage is done.
- Jointing Hydrant Line at Crossing Road area is done.
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 2 of 6

b.
c.
d.
e.

f.

- Jointing Hydrant Line to Gate 01 area is continue on goin.


- Excavation and Back Fill is pending waiting Apecos Pipe ready to laid the pipe into the
trench.
BC-07A Inside Coal Yard;
Progress : Internal Line Check
BC-07B Inside Coal Yard
Progress : Internal Line Check
BC-08.1 & BC-08.2 Southern Coal Yard
Progress : Internal Line Check
Oil Pump Area;
Progress : Official Line check is done. Excavation and Hydrotest preparation is on
progress.
Raw Water Electrical Building
Progress: Stringing and Jointing Hdpe Pipe to next reservation. Install 6 Hydrant HDPE
Pipe for future reservation into Raw Water Valve Pit is done.

Above Ground;
a.
Piperack
WTP area;
Piping Progress :
Boiler 1 Area;
Piping Progress :

Fit-Up Progress
Welding Progress

: 0 Joints
: 5 Joints

Fit-Up Progress
Welding Progress

: 0 Joints
: 4 Joints

Summary To Date Fit-Up Progress


Summary To Date Welding Progress
b.
c.
-

: 33 Joints of Estimate 109 Joints


: 21 Joints of Estimate 109 Joints

Pump House
Power Island:
Fire Pumps Leveling & Centering Internally is done.
Daily Fuel Diesel Tank Internal Leveling and Centering is done.
FHS:
Fire Pumps Leveling & Centering Internally still on going.
Daily Fuel Diesel Tank Internal Leveling and Centering still on going.
Boiler Cable Basement Unit 1;
Piping Progress :
Install Control Valve Header
Internal Line Check is done
Install temporary Test Flange.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 3 of 6

d.
e.
f.
g.
-

Boiler Cable Basement Unit 2;


Piping Progress :
Install Deluge Valve Header
Internal Line Check is done
Install temporary Test Flange.
Switchgear Cable Basement;
Piping Progress :
Fabrication Control Valve Header & Continuing install Main Line to Header is continue
on going.
CAB Cable Basement
Fabrication Deluge Valve Header & Continuing install Main Line to Header is continue
on going.
Workshop
Fabrication;
Progress : Fabrication Header Control Valve, Pipe Support, Threading pipe.
Painting;
Progress : Painting and Sandblasting is continue on going.

4.3 Fire Alarm


a.
Turbine Building; Continuing Install Cable Conduit.
4.4 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Excavation and Back Fill is pending waiting Apecos Pipe laid into the trench.
5 Action Plan for this Week (April, 25th 2016 May, 01st 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area:
- Excavation and Back Fill activities at Crossing to Pipe Bridge Line.
- Closing jointing under the U-ditch for Section - 01 (Crossing Area).
b.
BC-07A Inside Coal Yard; Jointing HDPE Pipe
Progress Target: Official Line Check.
c.
BC-09 Area;
Partially official Line Check section -01
Install tee pieces for future reservation near raw water electrical building.
d. Raw Water Electrical Building Area:
Stringing and jointing HDPE Pipe.
e.
BC-07B Southern Area; Internal Line Check & Hydrotest preparation
f.
Oil Pump Area; Hydrotest, Excavation and Back Fill, Install Valve Pit, Install Hydrant
Post, Install Outdoor Hydrant Box.
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 4 of 6

g.

West Side Boiler Area; Spreading and jointing HDPE Pipe

Above Ground;
a.
Pipe Rack;
- WTP Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- Boiler 1 Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- FHS Cable Bridge:
Progress Target : Erection pipe to the Cable Bridge for 20 Lengths Pipe.
b.
Boiler Cable Basement Unit 1;
Progress Target: Install Control Valve Header, Official Joint Line Check and Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Install Control Valve Header, Official Joint Line check and Hydrotest
d. CAB Cable Basement;
Progress Target: Complete piping installation, Install Control Header.
e.
Switchgear Cable Basement:
Progress Target: Complete piping installation, Install Control Header.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
GIS Basement
Progress Target: Piping installation, Install Control Header.
h.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
i.
Fire Pump House
Power Island;
Progress Target: Joint Inspection for Leveling and Centering Pump Installation, Internal
Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Internal check continue to Joint Inspection Centering and Leveling
Pump Installation.
j.
BC-09
Progress Target: Install Piping Sprinkler System
k.
Workshop
- Fabrication;
Control Valve Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication,
Threading Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 5 of 6

5.2 Fire Alarm


a.
Turbine Building; Continue install cable conduit
b.
ACC Building : Install cable Conduit
5.3
a.
b.
c.
6.

Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Laying and Buried the Pipe under the drainage (Crossing Area).
Tanks Area : Continue Spreading and Joint pipe to Dust Suppression Pump.
MATERIAL DELIVERIES
- Raw Piping Material; 1 Truck

7. TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.

Other Issues
- No Issues

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 6 of 6

Vous aimerez peut-être aussi