Table of contents

1. General.
2. Management Organization Chart
3. Sequence of works (beam & slab).
4. Formwork design.
5. Construction joint treatment.
6. Re bars fabrication & setting.
7. Installation of embed item.
8. Placing of concrete.
9. Compaction of concrete.
10.

Removal of formworks

11.

Curing

12.

Protecting against raining

13.

Electricity

14.

Equipment & Manpower

15.

Safety measure

Appendix
A. General plan and elevation
B. Typical formworks & Scaffolding arrangement.
C. Calculation for formwork and support systems
D. Safety Procedure

1. General

This method statement describes how we carry out the concrete works of
superstructure in building works.
Concrete class shall be approved ready-mix concrete Grade 35MN/m 2
Please refer to Appendix A for general plan and elevation of three main
building.
2. Management Organization Chart
Mr. T. UCHIDA
Project Manager

Mr. N.N.Hai
HSE Manager

Mr. A . IKEGAMI
Construction
Manager

Mr. A.M. Cabonce


QA/QC Manager

Mr. K.Miyara
Chief Engineer

Mr. P. C. TRUNG
Chief site
Engineer

Mr. Tran Thanh Minh


Site Engineer

Sub Contractor

2.1 Project Manager

2.2

Mr. Hoang
Hung

Sub Contractor

Mr. Dang Trong


Dung
Site Engineer

Sub Contractor

To oversee and control all aspects of the Piling activities, and dictate
schedule requirements
To ensure that all field staff are fully aware of the requirements of
this method statement, and that these requirements, in all respects,
are fully implemented.
To ensure that Safety and Environmental procedures, particularly,
are in place before activity commences, and strictly complied with,
throughout the duration of concreting works.

Construction Managers, directly reports to Project Manager.


To oversee all construction works, with respect to schedule.
To ensure that all field staff follow the requirements of this method
statement, including quality control and HSE.

2.3

2.4

2.5

2.6

2.7

Chief Engineer, reports to Construction Manager


To ensure that all relevant preparations have been made.
To ensure that all provisions of this method statement are followed.
To ensure that all quality inspection is carried out and record taken,
if required.
To ensure that all necessary safety and environmental precautions
are in place and that all workers under their direct control are fully
aware of all procedure requirements
To control execution of the entire activity
Site Engineer
To assist Chief Engineer to control the Subcontractor for all activities
relative to this method statement.
To ensure safe working environment at all times, during
Subcontractor execution of concreting works.
Surveyor
To give control points & grid line to Subcontractor for concreting
works.
To supervise Subcontractor and conduct survey checks from time to
time.
To carry out all surveying work and to ensure all required records are
taken and maintained.
QA/QC department
To oversee construction activity with respect to quality control.
To ensure quality procedures has been followed.
To ensure that all required inspections have been carried out and
that records, if required have been taken and properly stored.
Advise the laboratory and Site Engineers to control the quality of
works.
Health, Safety & Environmental department
To monitor that all the working activities are executed in accordance
with site safety procedures.
To ensure that precautions with respect to Environmental matters
have been implemented on site.

3. Sequence of works (beam & slab).

Setting Staging for


Construction Area

Setting Support & Bottom


Formwork
Construction Joint Treatment
Inspection for Construction
Joint
Assembling re bar

Inspection of re bar

Setting Side Formwork

Inspection for casting


concrete
Placing Concrete
Curing

Stripping of Form

Stripping Support and Prop after


Getting Design Strength 100%

4. Formworks Design
Formwork shall be set in correct position following specification and the
approved structure drawings.
Please refer to Appendix B for Typical formworks & support for 2nd floor slab.
Formworks and support is calculated as shown in Attachment C
Approved form oil will be applied to form surface prior to installation of form.
5. Construction joint treatment

All construction joints will be chipped to remove cement sand surface to


make rough surface.
In some cases, approved retarder for concrete surface will be used as another
method to make construction joint properly.
6. Rebar fabrication & setting
Approved re-bar type will be delivered to site and it will be inspected & tested
prior to use.
Re-bar shall be cut and bent according to the approved schedule at the site
workshop and transported to site by truck. After delivery to the site re-bars
shall be fixed according to specification and approved drawings by Engineer
or Consultant.
Rebar shall be inspected by Engineer or Consultant prior to install of next
layer or formworks.
Any mistake rebar will be replaced or repaired by approved method.
Approved concrete spacer shall be used; its concrete grade shall be 35
MN/m2.
7. Installation of embed item
All the embed item showing in the drawings shall be firmly installed in correct
position.
8. Placing of Concrete
Approved ready-mix concrete will be transported from batching plant to the
site by mixer truck. During transportation & waiting time the concrete shall
be kept continuously agitated.
From mixer truck concrete will be poured to casting location by concrete
pump or by bucket. The height from discharge position to casting level shall
not be over 1.5m.
On each concreting day and for each grade of concrete mix, samples shall be
taken. When samples are taken at sites, samples shall be taken for every
24m3 of concrete or part thereof, of each grade of concrete.
Minimum requirement of sample
-

Each concreting day

Each part of structure (each building)

After filling above condition, samples shall be taken for every four
mixer or agitating truck (20~24m2).

9. Compaction of Concrete.

Concrete after pouring to position shall be compacted by immersion vibrator.


Proper staging for vibration works will be arranged.
Wooden or rubber hammer also will be used as external vibrator in some
cases.
10. Removal of formworks
Form works removal shall be accordance with specification Clause 4.20 or as
proposal hereunder.
-

All vertical or side formworks : 12 hrs (The period shall commence from
the time of last pour of concrete)

Soffit formworks to slabs & beams : 3 days ((The period shall


commence from the time of last pour of concrete)

Props to slabs & beams: Requirement in Specification is 14 days. We


propose that before remove props we will carry out testing for cube
sample, whenever if we get 100% designed strength of concrete we will
remove props (After skirting of formworks, props shall be immediately
put up to support the structure)

Props to cantilever slabs & cantilever beams: Requirement in


Specification is 21 days. We propose that before remove props we will
carry out testing for cube sample, whenever if we get 100% designed
strength of concrete we will remove props (After skirting of formworks,
props shall be immediately put up to support the structure)

* Testing for purpose of removal formworks will be carried out at 7th days
after finish casting concrete.
All tie rod holes & defects on surface will be repaired following approved
method.
11. Curing.
After removal of form works, concrete shall be cured minimum of 6 days
according to TCXDVN 391:2007 Requirements for Natural Moist Curing,
apply for Area C of Viet Nam.
Curing of concrete will be carried out by spraying water periodically to the
surface of the newly placed concrete. Jute bag or nylon sheet shall be used to
cover the concrete surface for keeping wet.
Water to be used for curing and cleaning works is portable water from local
authority.
Approved curing compound also will be used in several cases.

12. Protecting against raining.


Against raining, plastic sheet shall be prepared to cover over the concrete
area before concreting.
13. Electricity
Electricity will be supplied by generators on site.
14. Equipment & Manpower
a)Equipment
Equipment

Unit

Quantity

Mixer truck

Nos

04

Vibrator

Nos

03

Concrete Pump

No

01

Generator 15KVA

No

01

Generator 10KVA

Nos

02

Bucket

Nos

10

Showel

Nos

05

Nos

05

Unit

Quantity

Supervisor

No

01

Surveyor

Nos

02

Foreman

No

01

Electrician

No

01

Worker

Nos

10

Trowel
b)Manpower
Description

15. Safety measure


Please refer to Appendix D for Safety Procedure when working at high
position

APPENDIX A
GENERAL PLAN & ELEVATION

APPENDIX B
FORMWORKS &
SCAFFOLDING ARRANGEMENT

APPENDIX C
CALCULATION FOR FORMWORKS & SUPPORT

APPENDIX D
SAFETY PROCEDURE