1. General.
2. Management Organization Chart
3. Sequence of works (beam & slab).
4. Formwork design.
5. Construction joint treatment.
6. Re bars fabrication & setting.
7. Installation of embed item.
8. Placing of concrete.
9. Compaction of concrete.
10.
Removal of formworks
11.
Curing
12.
13.
Electricity
14.
15.
Safety measure
Appendix
A. General plan and elevation
B. Typical formworks & Scaffolding arrangement.
C. Calculation for formwork and support systems
D. Safety Procedure
1. General
This method statement describes how we carry out the concrete works of
superstructure in building works.
Concrete class shall be approved ready-mix concrete Grade 35MN/m 2
Please refer to Appendix A for general plan and elevation of three main
building.
2. Management Organization Chart
Mr. T. UCHIDA
Project Manager
Mr. N.N.Hai
HSE Manager
Mr. A . IKEGAMI
Construction
Manager
Mr. K.Miyara
Chief Engineer
Mr. P. C. TRUNG
Chief site
Engineer
Sub Contractor
2.2
Mr. Hoang
Hung
Sub Contractor
Sub Contractor
To oversee and control all aspects of the Piling activities, and dictate
schedule requirements
To ensure that all field staff are fully aware of the requirements of
this method statement, and that these requirements, in all respects,
are fully implemented.
To ensure that Safety and Environmental procedures, particularly,
are in place before activity commences, and strictly complied with,
throughout the duration of concreting works.
2.3
2.4
2.5
2.6
2.7
Inspection of re bar
Stripping of Form
4. Formworks Design
Formwork shall be set in correct position following specification and the
approved structure drawings.
Please refer to Appendix B for Typical formworks & support for 2nd floor slab.
Formworks and support is calculated as shown in Attachment C
Approved form oil will be applied to form surface prior to installation of form.
5. Construction joint treatment
After filling above condition, samples shall be taken for every four
mixer or agitating truck (20~24m2).
9. Compaction of Concrete.
All vertical or side formworks : 12 hrs (The period shall commence from
the time of last pour of concrete)
* Testing for purpose of removal formworks will be carried out at 7th days
after finish casting concrete.
All tie rod holes & defects on surface will be repaired following approved
method.
11. Curing.
After removal of form works, concrete shall be cured minimum of 6 days
according to TCXDVN 391:2007 Requirements for Natural Moist Curing,
apply for Area C of Viet Nam.
Curing of concrete will be carried out by spraying water periodically to the
surface of the newly placed concrete. Jute bag or nylon sheet shall be used to
cover the concrete surface for keeping wet.
Water to be used for curing and cleaning works is portable water from local
authority.
Approved curing compound also will be used in several cases.
Unit
Quantity
Mixer truck
Nos
04
Vibrator
Nos
03
Concrete Pump
No
01
Generator 15KVA
No
01
Generator 10KVA
Nos
02
Bucket
Nos
10
Showel
Nos
05
Nos
05
Unit
Quantity
Supervisor
No
01
Surveyor
Nos
02
Foreman
No
01
Electrician
No
01
Worker
Nos
10
Trowel
b)Manpower
Description
APPENDIX A
GENERAL PLAN & ELEVATION
APPENDIX B
FORMWORKS &
SCAFFOLDING ARRANGEMENT
APPENDIX C
CALCULATION FOR FORMWORKS & SUPPORT
APPENDIX D
SAFETY PROCEDURE