Académique Documents
Professionnel Documents
Culture Documents
PO.
84
Marios Papalexandrou
Mott MacDonald
Abstract
This paper examines the development of costs in offshore wind industry from the first pilot projects, to the current and future costs of different available and future technologies. The study is based on a cost model developed to calculate capital and operational expenditures, supported
by an updated offshore wind cost database, based on Mott MacDonald experience. For this study, a number of scenarios are developed, based on different water depths and technologies to be deployed Current costs are based on monopile and jacket foundations using 3+ and 5+ MW
turbines for water depths up to 30 meters using HVAC transmission technology. Future costs are based on jacket foundations using 6+ to 10MW turbines for water depths up to 50 meters using HVAC and HVDC transmission technologies. Future costs take into account inflation rate,
material intensity, technology maturity and predicted market conditions. The paper examines how new technologies, new markets and market players may affect the future costs of offshore wind.
The past
The future
The Present
Middelgrunden
Bligh Bank
Alpha Ventus
The high increase in offshore costs the last decade is justified due to:
1. A Sellers market dominated by two turbine manufacturers (3+MW) till
recently
2. Scarcity of capable vessels to provide installation services, having high
charting rates
3. A growth of the market that has not been followed by strong supply
chain growth due to supplier/contractor uncertainty
4. High risks that contractors have to include in their prices
5. Going to challenging sites, further offshore and to deeper waters
increases CAPEX costs considerably
6. High complexity leading to additional contingencies to ensure project
completion
7. Inflation rate and material price increase.
Modeling Results
COE cost for each period examined
Foundations
Rest Costs
Turbines
Scenarios
Scenarios
Rest Costs
Present: 3+MW/20m/30km
Present: 3+MW/20m/30km
OPEX
Turbines
Foundations
Electrical Infrastructure
30
60
90
120
150
180
Conclusions
Offshore wind is continuously evolving with an increased pace at present and with an expected big momentum from 2015 onwards where the UK Round 3 projects will start being constructed together with German, French, Danish and
other offshore wind developments. We have seen that project costs have increased significantly the past decade due to supply chain restrictions and industry immaturity. Prices are expected to continue to rise in the short term up to 2015
due to challenging site conditions. The volume of the market in conjunction with technology improvements and supply chain competition will stabilize the costs between 2015 and 2017. The involvement of large industrial groups (Alstom,
Areva, Mitsubishi and others) will bring to the market financial and engineering capabilities larger than ever before. The competition will increase during this period in the supply chain that would also see Asian manufacturers entering the
European market. This increased competition together with the industrialization of the market and the establishment of long term agreements between supply chain players would bring further costs down and increase confidence of
financing parties towards offshore wind.
In real cost terms current prices of CAPEX are 3.0-3.5 million per MW with expectations to further rise in the short term up to 4million due to moving to deeper waters further offshore. Then market is expected to stabilize at 3.6million
in mid term and fall to 3.2million and even more in the long term after 2020. OPEX costs will decrease while moving to larger turbines from 100/kW today to 80/KW beyond 2020. Cost of energy is currently at 150-180/MWh. It is
expected to stabilize at 165/MWh in the mid term and fall at 145/MWh in the long term due to increased turbine reliability and more efficient capture of energy.