Académique Documents
Professionnel Documents
Culture Documents
Andrew Steinhubl
John Van Leeuwen
William Rogers
Contact Information
Houston
Andrew Steinhubl
Partner
713-650-4183
andrew.steinhubl@booz.com
John Van Leeuwen
Principal
713-530-5503
john.vanleeuwen@booz.com
William Rogers
Senior Associate
713-650-4100
william.rogers@booz.com
EXECUTIVE
SUMMARY
WRENCH
TIME
Exhibit 1
Observed Maintenance Wrench Time, Power Industry
Industry Leading
65%
55%
Good
45%
35%
25%
15%
5%
Rigorous assessment of
jobs
Work force empowerment
Disciplined use of IT
enablers
Work orders and parts
list pre-loaded in
Computerized Maintenance
Management System
Parts pre-staged
Typical
Legacy maintenance
practices
Maintenance staff on
standby for potential
outage events
Wrench time
measured
Efficiency and
effectiveness a
planning focus
Stages of Excellence
Source: Booz & Company
Exhibit 2
Typical Maintenance Workers Wrench Time Analysis
100%
80%
60%
40%
20%
0%
Total
Job
Close
Rework
Meetings Other
Prep.
Time
Travel
Break
Waiting
Wrench
Time
Work Type
Source: Booz & Company
KEY FACTORS
PRODUCTIVITY GAINS
Here are some examples of performance improvements that process-intensive
companies have achieved using the framework outlined in this article.
Operations
A chemicals unit was responsible for desulfurizing the by-products in an industrial process and disposing of the materials. To improve productivity, the area
supervisorwith the input of a set of operatorsidentified work tasks for each
position and allocated time to each task. The company also eliminated a number
of steps, including duplicate pH testing. Wireless controls were installed, freeing
control-room operators to monitor and troubleshoot equipment. By selectively
installing SO2 monitors, the company was able to eliminate a weekly manual
monitoring round. Further, upgrades to mill controls, along with increased working capacity in slurry tanks, enabled the plant to scale back sludge-plant operation from daily to every other day. Overall productivity improved by 25 percent,
and the company saved more than $1 million a year in unit operating costs.
Contract Services
The exploration and production operations of an oil company had invested in
a number of improvement efforts. However, it realized that the contractors employed to service production sites were taking eight hours to complete tasks that
could be done in half that time. When company representatives were on-site,
activities usually took the estimated time, but the company didnt have enough
staff to monitor all the contract work. To fix the problem, it stopped paying the
contractors by the hour and instead established a menu of standard tasks,
with the preset time allotments and prices. Total contractor hours dropped
by 15 to 20 percent.
Maintenance
A large, regulated utility faced significant maintenance budget overruns. Repeated staffing reductions to rein in costs did not solve the problem. Analysis
revealed that the work management systemidentifying, planning, and executing work and closing out the work ordersneeded to be revamped. Through
direct observation of maintenance work orders relative to existing and best
practice processes, the organization focused on streamlining the process.
Changes included clarifying lock-out/tag-out procedures, linking the work schedule to activity lists, and training the existing staff in work order management and
materials planning practices. Improvements resulted in a productivity increase of
20 percent.
Supervisory
At a chemicals company, the workforce lacked sufficient training and guidance.
The fundamental issue was that supervisors were being pulled away from their
direct staff responsibility by administrative tasks. An assessment of each supervisors workday revealed large blocks of time spent attending meetings, completing paperwork, and doing data entry. (Union workers were considered not
qualified.) To address this problem, much of the administrative and data entry
work was offloaded to junior staffers. The approval process was automated,
which freed up foremen and supervisors to spend more time with the workforce
and ultimately improve plant operations and workforce effectiveness. Some 30
percent of weekly administration time was ultimately eliminated or reassigned.
ANALYSIS
AND
MEASUREMENT
applies to all of the activities of maintenance employees, operators, contractors, and supervisors. Personnel
dataincluding capabilities, years of
experience, shift patterns, and time
offis factored in. To help determine
a baseline, jobs should also be benchmarked against industry standards.
Workout sessions are conducted
with line staff and supervisors to
identify unnecessary steps or wasted
time, along with possible solutions.
Its critical that the plant workforce
participates in measurement and
baselining, so that they understand the
process and begin to see how it will
Exhibit 3
Productivity Losses in Operations and Maintenance Workflow
Work Identification
Work Coordination
Work Execution
Operations
Planning /
Scheduling
Maintenance
Facility design/layout
Shift/personnel alignment to
specific plant areas without
cross-training
Staff sized to respond to
high-impact low -probability
(HILP) events
Delineations between Operations
and Maintenance staffs
Non-value-add
If you were the customer, would
you be willing to pay for the task?
Could the task be categorized
as waste?
Finally, this kind of analysis must be
applied to all facets of the plantnot
just routine operations and maintenance but also outages and turnarounds (which can be complex, given
the number of workers on-site and
the need to get the facility back online
quickly). In addition, on-site contractors involved in technical services
such as maintenance, environmental
management, predictive measurements, and the likeshould be evaluated as thoroughly as full-time staff.
Many facilities hire contractors on
time-and-materials agreements, which
do not give contractors incentives for
improving productivity.
SOLUTIONS
Improving productivity is a
continuous journey. Its not a binary
before-and-after proposition.
CONTINUOUS
IMPROVEMENT
Conclusion
Worldwide
Offices
Asia
Beijing
Hong Kong
Mumbai
Seoul
Shanghai
Taipei
Tokyo
Australia,
New Zealand &
Southeast Asia
Adelaide
Auckland
Bangkok
Brisbane
Canberra
Jakarta
Kuala Lumpur
Melbourne
Sydney
Europe
Amsterdam
Berlin
Copenhagen
Dublin
Dsseldorf
Frankfurt
Helsinki
London
Printed in USA
2009 Booz & Company Inc.
Madrid
Milan
Moscow
Munich
Oslo
Paris
Rome
Stockholm
Stuttgart
Vienna
Warsaw
Zurich
Middle East
Abu Dhabi
Beirut
Cairo
Dubai
Riyadh
North America
Atlanta
Chicago
Cleveland
Dallas
Detroit
Florham Park
Houston
Los Angeles
McLean
Mexico City
New York City
Parsippany
San Francisco
South America
Buenos Aires
Rio de Janeiro
Santiago
So Paulo