Académique Documents
Professionnel Documents
Culture Documents
For
Public Private Partnership
(PPP)
In
Haryana
PPP Cell
Finance Department
Government of Haryana
private sector entity for a specified time period, where there is a substantial
risk sharing with the private sector and the private sector receives
performance linked payments that conform (or are benchmarked) to specified,
pre-determined and measurable performance standards.
(Department of Economic Affairs, Ministry of Finance, Government of India,
2010).
The earlier definition was A partnership between a public sector entity
(sponsoring authority) and a private sector entity (a legal entity in which 51%
or more of equity is with the private partner/s) for the creation and/or
management of infrastructure for public purpose for a specified period of time
(concession period) on commercial terms and in which the private partner has
been procured through a transport and open procurement system.
The International Monetary Fund (IMF):
Public-private partnerships (PPPs) refer to arrangements where the private
sector supplies infrastructure assets and services that traditionally have been
provided by the government. (IMF 2004,)
The World Bank:
PPP programs are projects that are for services traditionally provided by the
public sector, combine investment and service provision, see significant risks
being borne by the private sector, and also see a major role for the public
sector in either purchasing services or bearing substantial risks under the
project. (World Bank 2006, p13)
The Asian Development Bank (ADB):
PPPs broadly refer to long-term, contractual partnerships between the public
and private sector agencies, specifically targeted towards financing, designing,
implementing, and operating infrastructure facilities and services that were
traditionally provided by the public sector (ADB 2006, p15)
The European Union:
A PPP is the transfer to the private sector of investment projects that
traditionally have been executed or financed by the public sector (European
Commission 2003, p96)
potential risks associated with the project are identified and each party adopts those
which it is best equipped to manage. The public sector can therefore transfer
appropriate risks to the private partner, who has the necessary skills and experience to
manage them. The delegation of risks depends on the type of mode adopted for PPP
as depicted in Fig. 1.
Fig. 1: Delegation of Risk in PPP
Enabler/
100% private
regulator
Divestitures
BuildOperateOwn
Concessions
Build-Operate-Transfer
Role of Government
(back to Government)
Ownership
Leases
Management
Contracts
Provider
Service contracts
100% public
5
10
15
20
30
years
3.4
Flexible ownership: PPPs enable flexible arrangements between public and
private bodies, where the public body may or may not retain ownership of the project
or facility that is produced. In some cases, the private organisation may be contracted
only to construct facilities or supply equipment, leaving the public body as owners,
operators and maintainers of the service. Alternatively, the public sector may decide it
is more cost-effective not to own directly and operate assets, but to purchase these
instead from the private entity. Services may be purchased for use by the government
itself, as an input to provide another service, or on behalf of the end user.
3.5
The information given on historical background to PPP in Appendix II, on
lessons learnt from PPP programmes in Appendix III, on some facts about PPP in
Appendix IV, on strength and weakness on PPP in Appendix V, on common
misconceptions on PPP in Appendix VI, on PPP and conventional procurement in
Appendix VII, on enabling environment for PPP in Appendix VIIII, on project
financing in Appendix IX may be referred for further details. Various models of PPP,
generally in practice, are given in Appendix X which may provide guidance in
selection of appropriate model.
3.6
4. PPP IS NOT
Simple outsourcing where substantial financial, technical and operational
risks retained by the Institutions
Donation by Private Party for Public good
Privatisation or Divesture of State assets and/or liabilities
Commercialistion of a public function by creation of a state owned enterprise
Constitute borrowing by the state
5. DEVELOPMENT OF PPP PROGRAMME
Follow specific guidelines should be considered before launching PPP program:
5.1 When starting from a low base of PPP development, the aim should be to
incorporate key principles of good governance but not necessarily to have a complete
PPP framework in place. A complete PPP framework can be worked towards while
some projects are being developed and experience gained.
5.2 Develop a proper PPP policy and consult widely on it. Take into account views
where they do not ultimately endanger the key concepts of transparency/ competition
and benefits.
5.3 Build capacity in the public sector institutions and help develop capacity in the
private sector. Convince the private sector that doing PPPs well means more and
better business for them.
5.4 The policy should encompass a flexible approach that fits the political, financial,
economic social situation/conditions in each country. A comprehensive and rigid
approach from day one is neither desirable nor essential.
5.5 If, in the initial stages, a pipeline of PPP projects is difficult to prepare, ring fence
several good projects and develop as PPPs, flexibly, but incorporating key minimum
conditions for PPP.
5.6 Work towards a pipeline of good i.e. bankable PPP projects.
5.7 Develop good projects, with help of multilaterals/good advisors, with the basic
PPP principles of;
Good project preparation including sound draft tender documents
incorporating the principles of competition and transparency.
Consider a range of highway projects; bridges, tunnels, new motorways,
Brown field upgrading, maintenance, rural roads, port and airport accesses.
Consider a range of PPP modalities PBC, Concessions, BOT, Annuities etc.
Select projects that are reasonably large but not too complex or risky and if
possible those that need little or no government financial support.
Understand and integrate risk management (identification, allocation and
mitigation) principles in the selected projects.
5.8 Obtain commitment at all levels, starting at the most senior across the board and
within the line Departments/ Local Bodies/ Public Undertakings.
5.9 Prepare projects on a realistic schedule-keep up pressure but not cutting corners to
fast track.
5.10 Work towards, have a view to the development of, in the medium-term a more
comprehensive framework of laws, regulations and regulatory bodies. Regulate by
contract initially.
5.11 Appropriately and effectively address the major concerns of concessionaires and
investors, which are:
Cost, time, and quality of the PPP bid process.
Availability of required land and environmental clearances
Clarity and stability of the legal and regulatory framework
Criteria for evaluating bids
Quality of the public sector project team, its advisers and decision making
Security of the projects income stream (demand, bankability of public
sector obligations)
Deliverables and assessment of performance: What are they expected to
deliver, and how will their performance be measured?
Status and availability of connecting infrastructure and availability of
inputs and terms of supply
Effectiveness and enforceability of the PPP contract and related
agreements
Wider operating environment for private capital
Returns commensurate with the risks they are asked to assume
Effectiveness with which the public sector will manage the contract and
make decisions
Opportunities to refinance the debt or sell the investment.
Public Sector
Committee under FCF
in consultation with
concerned
Departments and
assisted by PPP Cell
FD may engage
consultant for above
exercise
Sector Focused Units
Action on LA etc
Standardization of
documents
Consultation with
client and marketing
Approval of CoSI for
PQ documents
Approval of CoSI for
RFP document
Constitution of
Evaluation Committee
Approval of CoSI or
CCI, depending Upon
the size of project
Appointment of
Independent
Consultant if required
Private Sector
Identification of Sector for Focus and
Preparation of Long List of Possible Projects
Possible
Investors
Conference
Bidders
Apply for PQ
Bidders
attend and
seek
clarification
Bidders
Submit
Proposal
Agreement Signing
before CoSI for approval, to be taken up on PPP. A meeting of the CoSI will be
convened within one month to consider the proposal(s) for 'in principle' approval.
Prioritised list of possible PPP projects shall then be sent to the concerned
Administrative Departments or State Public Sector Undertaking(s) or
Municipalities or Urban Local Bodies or other Government statutory authorities or
other entities under their administrative control (Authority) for taking forward the
process of implementation of project(s) on PPP in accordance with the Policy.
Authority shall identify an officer or team for implementing the identified
project(s).
Authority would engage a Transaction Advisor (TA) through competitive
selection process and with the approval of the concerned Administrative
Secretary. The Template of the RFP for engagement of TA as available on the
web site: pppinharyana.gov.in should be used with modifications done to meet the
sector specific requirements.
The TA shall prepare Feasibility Study (also including project structuring,
financial analysis, bid process), RFQ, RFP and Concession Agreement, and assist
the Authority in procurement of private partner. For initiating the procurement,
RFQ document shall be submitted by the sponsoring Authority, to the PPP Cell,
for seeking approval of CoSI. The meeting of CoSI would be fixed within a month
time, on submission of the document to PPP Cell. The Authority would then
circulate the agenda and memoranda (giving brief of the project particulars) to the
members of CoSI. CoSI will either approve or request the Authority to make
necessary changes for further consideration of CoSI.
After the requisite approval, the Authority would invite applications for
Qualification (RFQ) for two stage bid process. Prequalification would involve
pre-proposal conference for any clarification etc, issue of response to them,
receipt of RFQ application, and their evaluation and due intimation to prequalified
applicants. TA shall assist the Authority in these exercises. The Authority shall
constitute an Evaluation Committee with members, keeping in view the
requirements of the project. It would be advisable to have at least one sector
expert as one of the members.
The TA shall also prepare RFP with draft Agreement. The Authority shall submit
these bid documents to the PPP Cell for seeking approval of CoSI. The meeting of
CoSI shall be convened within one month. On approval, these documents,
Authority shall issue them to the qualified applicants for bid submission. For
single stage bid process, RFP with draft Agreement shall be submitted to CoSI,
through PPP Cell, and got approved as above and bids invited through open
invitation
After evaluation and selection of bidders the final proposals with finalized bid
shall be submitted to PPP Cell for seeking approval of CoSI/ CCI ( as the case
may be, depending upon the project cost and period of concession, according to
the provisions of PPP Policy).
The Authority shall take further action to award the work, shall sign the
Agreement and implement the project.
for sectors of water supply, sanitation, solid waste management, urban transport, rural
infrastructure got done by the State with assistance from Department of Economic
Affairs (DEA) Ministry of Finance, Government of India and Asian Development
Bank (ADB). The PPP Toolkit for Improving Decision Making Process developed by
the PPP Cell in DEA, (pppinindia) provides guidance for project identification and
can be utilised. The project identification would also depend on the priority that the
specific sector requires and possible candidate PPP projects based on an assessment of
viability, affordability and provision of value for money compared to other options. It
may be advisable to have a pre-feasibility study/ assessment got done, for the
availability of some of the necessary requirements such as land, shifting of utilities if
any, possibility of getting environmental clearances etc. It would be desirable that
shelf of projects are created which could be offered on PPP. A committee under FCF
shall identify sectors for focus and possible projects on PPP. These shall be brought
before CoSI for approval and for taking further actions. The list of such projects then
shall be passed on to the Administrative Departments or State Public Sector
Undertaking(s) or Municipalities or Urban Local Bodies or other Government
statutory authorities or other entities under their administrative control (Authority) for
taking forward the process of implementation of project(s) on PPP in accordance with
the Policy.
6.4 Setting up the project team
PPP projects generally need complex skills and therefore it is advisable to have a team
base management approach. The team may not necessarily be a large one. The
Authority should identify an officer at middle level for project handling and
implementation. This action should also be accompanied by capacity building efforts
in the Authority. System should be developed whereby officers regularly participate
in trainings, seminars and workshops etc so that nuances of the PPP project are well
appreciated in the Authority for smooth and speedy project implementation
6.5 Mistakes to be Avoided
While developing a project on PPP, following common mistakes should be avoided
Lack of clarity by the Authority regarding what it wants from the project
Selection of advisers on the basis of cost rather than quality and experience
Lack of understanding of and contact with the private sector at senior levels
and poorly conducted market sounding
Expectations that the private sector will deal with issues, such as the
acquisition of land, that are better handled by the public sector
Lack of clarity about the public authoritys legal powers to enter into the
public-private partnership contract
private partner. This can be done either in-house or outsourced. PPP projects require
inputs and expertise in the disciplines of finance, legal and sector specific technical.
Since such skills may not necessarily be available within the Authority, it would be
advisable to engage a consultancy firm as Transaction Advisor (TA). The Authority
would undertake the procurement of services of TA in a transparent manner through
competitive bidding process with the approval of the Administrative Head. The
advertisement for this should be published in at least one National and one Regional
newspaper. A Template of the RFP for engagement of TA is available on the website;
pppinharyana.gov.in, which should be used after doing the project specific
modifications. The composition of core team or key personnel from TA would depend
upon project specific requirements (The Key Personnel and their respective maximum
marks may be suitably modified to address project-specific requirements). Since the
composition of the team and its key members is crucial for successful implementation
of the project, the quality-cum-cost base selection (QCBS) should be adopted where
by a weight age of 70/30 or 80/20 (where the intellectual and design content is
comparatively higher). should be given. The TA is expected to perform/ assist the
client in, main activities in project implementation as discussed in succeeding
paragraphs.
6.7 Preparation of Feasibility Report
TA would produce a comprehensive Feasibility Study Report, in close liaison with the
Authority. For most of the PPP projects, Feasibility Report should meet the
requirements (it also provides window for innovation and application of new concepts
and technologies); however, depending upon the project requirement, venturing into
altogether new area and its complexity, Authority may choose to have a Detailed
Project Report (DPR) to fine tune the spelling out of the core requirements of the
project. The Feasibility Report should provide answer to following key questions:
Is the project affordable?
What of the key risks and their managements strategy.
Would the project offer value for money.
What would be financing sources?
Is the project viable on PPP. The viability of a PPP project depends on
revenue generation along with expected growth, user fee rates and on
estimated project cost which normally includes cost of civil works, interest
during construction, financing charges, contingencies, expenses on operation,
maintenance and management etc. (excluding cost of land, as, cost of land
and other pre-construction activities are to be borne by the Implementing
Agency), operation & maintenance cost and VGF.
The Feasible Report would essentially indicate project structuring, mode of PPP to
be adopted, cost estimation, risk allocations, commercial and financial analyses,
optimal procurement methodology. Value for Money (VfM) assessment, and
identification of the issues to be addressed by the Authority. The feasible study
prepared by TA would be appropriately considered by the Authority and accepted for
taking further procurement steps. It may be helpful to have power point presentation
of the main features of the Report and issues for consideration of Authority in order to
facilitate process. The Feasibility Report should either be provided along with the RFP
or at least 45 days prior to the Bid Due Date.
10
11
comprises:
Instruction to Bidders
Draft Concession Agreement (DCA)
Schedules to DCA
In deciding on the bid parameter in the RFP, it needs to appreciate that three factors
are important; one is the period of Concession (Agreement, based on financial
analysis of the project), the other is return on investment through user fee through
directly or through user based payment (shadow fee); the third factor is the financial
support that the project requires to make it finically viable and implementable. The
bidding parameter for financial bid should be one of these factors for simplicity of
evaluation. Normally it is either financial support (grant from the Government; there
could be a premium also offered by bidder to the Government in case revenue returns
are very healthy) or period of Concession. In case of Annuity projects, the bid
parameter is the Annuity amount quoted by bidders.
The RFP document would invariably make provision for pre-bid conference which
would provide an opportunity to the client to make assessment of the market response
and to the prospective bidders any clarification or possible suggestive modification.
The out come of this bidders conference would be the necessary written
clarifications. It would also specify the date of submission and bidding schedule; as
suggested below:
Event Description
1. Last date for receiving queries
2. Pre-Bid meeting-1
3. Client response to queries latest by
4. Bid Due Date
6. Opening of Bids
7. Letter of Award (LOA)
8. Validity of Bids
9. Signing of Concession Agreement
Date
[25 days from the date of RFP]
[To be specified]
[35 days from the date of RFP]
[To be specified]
On Bid Due Date [at least 45
days from the date of RFP]
Within 30 days of Bid Due Date
120 days of Bid Due Date
Within 30 days of award of LOA
The Concession Agreement has to be carefully drafted so that all financial, legal and
project specific technical requirements are addressed in the manner that disputes
could be eliminated.
The Draft Agreement should cover the following topics at the minimum:
scope of the project
rights and obligations of the parties;
risk allocation, right to some compensation, breaches, events of defaults and
penalties;
grant of concession
Operation & Maintenance (O&M) requirements
Standards and Specifications
service performance standards and targets, which need to be objective and
measurable;
procedure for permitted modifications, as well as their scope and nature;
12
The RFP document shall be taken to CoSI, through PPP Cell, for its approval before
the same is duly issued. Any modification in the RFP either consequent to pre- bid
conference or otherwise shall also be got approved by CoSI.
6.11 Pre-bid conference
In PPP projects, pre- bid conference is desirable as it play a very useful role in
providing opportunity for clarifying the queries that prospective bidders may like to
seek in regard to the provisions of bidding documents and other details. It should
normally be held one month prior to deadline for submission of Bids. Queries raised
by various firms/ bidders shall be discussed in the Pre-Bid Conference/Clarification.
Based on those discussions, the Authority shall issue clarifications and or modify the
RFP if considered necessary. If modified RFP is issued then Authority may consider
revising the bid due date. The concerned Authority would keep on consulting PPP
Cell in the process.
6.12 Authority web site
The Authority should also host all its project advertisements, documents for RFQ,
RFP, clarifications, modifications and any project related information on bid process
on the Authoritys web site for wide dissemination and transparency. For realising the
document/ bid processing fee etc. guidance can be provided that the same shall be
payable while submitting the document, if downloaded from the website.
6.13 Award of Concession
On receipt of bids (single stage or two stage bid process), they would be evaluated by
an Evaluation Committee, constituted by the Authority, duly assisted by the TA, if
appointed. One or combination of one or more of the following criteria should be
considered for selection through competitive bidding depending upon the bid
parameter
Lowest bid in terms of the present value of user fees;
Highest revenue share to the Government
Highest up front fee offered by bidder
Shortest concession period
Lowest present value of the subsidy
13
Lowest capital cost and Operation & Management cost for Projects having a
definite scope;
Highest equity premium
Quantum of State Support solicited in present value
Such other suitable selection criteria as the CoSI/ CCI may allow or
determine.
14
to find the right balance between incentives to propose benificial projects and
incentives for third parties to submit counter proposals. One way to reduce public
sector corruption and opportunistic behaviour by private proponents of projects is to
forbid all unsolicited proposals.
Considering the risks involved in considering unsolicited proposals and doubtful
benefits as brought out above and the possibility of more time taken (resulting in
avoidable delays), to address the issues of transparency and competitiveness, it would
not be prudent to entertain unsolicited proposals till the situation gets matured.
7. MAIN FEATURES OF PPP PROJECT REQUIRING ATTENTION
7.1 Main Features of a PPP Project
PPP Project is a project based on a contract or Concession Agreement between a
Government or statutory entity and a private sector company, with the following
essential elements:
Fixed Concession period
Pre-determined user charges/tariff
Pre-determined scope of work for the Concessionaire
Pre-determined bidding parameters, i.e., VGF/ Premium/Revenue Sharing/ Lease
Rent
All conditions, specifications, and project agreements frozen prior to inviting final
bids
Key Performance Indicators and measurable parameters
Mechanism for return on investment
Dispute resolution mechanism
Independent agency for ensuring of project implementation in accordance with
agreed terms and conditions
Land required for the project available with the Implementing Agency
7.2 Implementing Agency (Authority) Support
7.2.1
Implementing Agency (Authority) will meet the cost of following items : Feasibility Study and preparation of Project Report, either in-house or through
TA.
Land for the project requirement (Right of Way) and en-route facilities.
Environmental Clearances.
Clearance of the Right of Way (land):
relocation of utility services
cutting of trees
resettlement/rehabilitation of affected establishments
Authority may, however, involve the private sector in these activities to minimize
delay in their completion.
7.2.2 Authority may provide Grant/Subsidy to the Concessionaire, depending on the
financial viability of a project, the amount of which will be determined solely on the
basis of competitive bidding. Depending on viability of the project, there may be a
negative grant /premium to be paid by the Concessionaire to the Implementing
Agency, which shall be decided on the basis of competitive bidding.
15
16
Value
Minimum 25% of project cost
Minimum 100% of project cost
These are indicative threshold conditions and may be decided on project specific case.
The Financial proposal is then evaluated on least cost basis as mentioned in the bid
documents.
7.6.2 Two Stage Two Cover System
In the case of contracts for large complex facilities or works of a special nature or
turnkey contracts or complex information and communication technology, it may be
undesirable or impractical to prepare complete technical specifications in advance. In
such cases, a two-stage bidding procedure may be used, under which first un priced
technical proposals on the basis of a conceptual design or performance specifications
are invited, subject to technical as well as commercial clarifications and adjustments,
to be followed by amended bidding documents and the submission of final technical
proposals and priced bids in the second stage.
A two stage bidding process shall broadly comprise of the following two stages:
(i) 1st Stage Bidding (Technical and financial capability assessment, without prices)
(ii) 2nd Stage Bidding (Price Bids)
In the first Stage, proposals would be invited for prequalification of bidders. Proposals
shall generally be invited through publication of the Invitation of Bids in newspaper,
at least in one National and one Regional and by hosting on relevant web site. The
Request for Qualification (RFQ) document prepared either in-house or by engaging
Transaction Advisor shall give the background of the project, bid process, criteria for
evaluation and general instructions. In the second stage, the RFP document including
the draft Concession Agreement shall be issued to those who had qualified in the first
stage.
17
18
Key
Project Identification
No Change to
Existing process
Assessment of PPP
Suitability
Changes to
Existing process
New Stage for
PPP projects
Project Appraisal
PPP Assessment
Statutory Process
Assessment
Procurement
Procedure Selection
Project Management
Stakeholders
Consultation
Statutory process risk with
contracting authority
Statutory Process
Preparation of Contract
Documentation
Elements of Statutory
Process Retained by
Public Sector
Preparation of Contract
Documentation
Tendering Process
Tendering Process
Contract and Performance
Management of
Construction and Operation
Contract Management of
Planning Phase
Elements of Statutory
Process Transferred to
Private Sector
Contract and Performance
Management of Construction
and Operation
19
20
21
It has web based Management Information System (MIS) software which allows the
user Department (Authority) to capture various aspects of data at each step of project
lifecycle and generates reports which help in decision making.
The overall goal of this comprehensive Management Information System is to enable
decision support system through complete management of information. The key
features of the computerized system, being covered by this software are mentioned
below.
Online and Real Time: All transactions are updated instantly in all pertinent
data files as soon as the data is entered by the end user. This integrated software
eliminates the need for error prone and times consuming clerical work, as all
necessary reports are available online.
Data Security: This software has been developed using MS-SQL Database.
The entire application and database resides on the server placed in NIC Data Center
with complete security features and ensures that right person has access to right
information.
22
23
Risk Identification
Risk Assessment
Risk Allocation
Risk Mitigation
24
Appendix I
PUBLIC PRIVATE PARTNERSHIP (PPP) IN INDIA
1 Government in India embarked upon the route of economic progress in early
Nineties and infrastructural deficiencies were recognised as major constraint.
Development and improvement of infrastructure therefore became a priority. The
level of efforts and investment required was quite huge and it was not possible to be
met from the normally available resources of the Government. Estimate by various
agencies had indicated the investment requirement of the order of US$ 500 (Rs.
25,00,000 cr) in XI Plan period which is expected to increase to the requirement of
US$ 1 trillion (Rs 50,00,000 cr) during XII Plan period, in order to sustain the
targeted growth rate of 9% to 10%. It was and is, therefore, necessary to involve
private sector to supplement the efforts of the Government in provision of improved
infrastructure.
2 The PPP mode of delivery public utilities and services has matured to a great extent
in India. A recent study commissioned by ADB has given fourth rank to India (Fig. 5)
after Australia,UK and Korea in South Pacific Region, in readiness and capacity to
implement and sustain PPP projects for infrastructure improvements.
Fig. 5: PPP Projects in Countries
25
and oversee the progress of key infrastructure projects. This has now been substituted,
in July 2009, by the Cabinet Committee on Infrastructure (CCI), under the
Chairmanship of the Prime Minister. The CCI approves and reviews policies and
monitors implementation of programmes and projects across infrastructure sectors.
Besides various innovative schemes have been initiated to promote PPP mode of
delivery of public services/ utilities.
3.2 Financial support to PPP in infrastructure under the Viability Gap Funding
Scheme (VGF) Scheme
3.2.1 In order to make infrastructure projects commercially viable, Government of
India has the Viability Gap Funding Scheme for providing financial support in the
form of grants, one time or deferred. The Scheme is administered by the Ministry of
Finance.
3.2.2. Government has constituted an Empowered Committee and Empowered
Institution for approving financial assistance to such projects which satisfies all the
eligibility criteria indicated in the Scheme.
The composition of Empowered Committee will be as follows:
i.
ii.
iii.
iv.
Sanction Viability Gap Funding up to Rs. 200 crore (Rs. Two hundred crore)
for each project subject to the budgetary ceilings indicated by the Finance
Ministry. Amounts exceeding Rs. 200 crore may be sanctioned by the
Empowered Committee with the approval of Finance Minister;
Determine the appropriate formula that balances needs across sectors in a
manner that broad bases the sect oral coverage and avoids pre empting, of
funds by a few large projects;
Determine the inter-se allocation between any on-going Plan Scheme
providing viability gap funding and this Scheme; and,
Provide clarifications or instructions relating to eligibility of a project for such
support as and when requested by Empowered Institution.
The Empowered Institution will sanction projects for Viability Gap Funding
upto Rs. 100 crore (Rs. One hundred crore) for each eligible project subject to
26
27
3.3
India Infrastructure Finance Company Limited (IIFCL) is the company
floated by Ministry of Finance to provide long-term capital to help finance PPPs, as
well capacity building and other forms of assistance. IIFCL renders financial
assistance through:
Loans assistance from SPV ordinarily shall not exceed 20 percent of the
project cost; the Company shall also syndicate loans, in addition to its
assistance
A project awarded to a private sector company for development, financing and
construction through PPP shall have overriding priority.
3.4
India Infrastructure Project Development Fund (IIPDF) within the
Department of Economic Affairs (DEA) is to provide financial support for quality
project development activities. Its role is to promote the development of credible and
bankable PPP projects. The proposals for assistance under the scheme would be
sponsored by Central Government Ministries/ Departments, State Governments,
Municipal or Local Bodies or any other statuary authority. IIPDF will ordinarily fund
up to 75% of the project development expenses as an interest free loan. Balance 25%
will be co-funded by the Sponsoring Authority. On successful completion of the
bidding process, the project development expenditure would be recovered from the
successful bidder. The IIPDF will be administered by the Empowered Institution. The
composition of the Empowered Institution will be as under:
a. Additional Secretary, DEA- Chairperson
b. Additional Secretary (Expenditure)
c. Representative of Planning Commission not below the rank of Joint Secretary
d. Joint Secretary in the line Ministry dealing with the subject
e. Joint Secretary, DEA Member Secretary
The Public Private Partnership (PPP) Cell of the Department of Economic Affairs
(DEA), Government of India will provide support functions to the Empowered
Institution to examine the applications received for assistance under IIPDF.
To seek financial assistance from the IIPDF it would be necessary for the Sponsoring
Authority to create and empower a PPP Cell to undertake PPP project development
activities and to address policy and regulatory issues. Assistance under IIPDF funding
will require co-funding by the Sponsoring Authority generally to the extent of 25
percent of the total project development cost, which would include the cost of prefeasibility study to determine whether a project is amenable to PPP. The assistance
from the IIPDF would ordinarily be released after the share of the Sponsoring
Authority has been released. Only in exceptional circumstances, the Empowered
Institution (EI) may relax this condition of co-funding by the Sponsoring Authority.
28
29
Annex I
Memorandum for Consideration
Under Guidelines for IIPDF
1. Introduction
The MFC is an application to be made by the Sponsoring Authority to seek project
development funding from the India Infrastructure Project Development Fund set up
by the Department of Economic Affairs, Ministry of Finance. The information sought
in the MFC and the rationale is given below. Annexure II includes an Application
Form to be completed for the MFC and Annexure III provides a typical Table of
Contents for the Preliminary Report to accompany the MFC.
2. Project Proposal
The Sponsoring Authority, with the aid of the PPP Cell or otherwise, will highlight
the broad contours of the project and issues related to its implementation framework
in the proposed PPP option. The proposed project development\ activities, budget and
time lines will form a part of the report.
a. Technical Information: The technical information will include the need for the
project, the components, their preliminary capacity/sizing and block cost estimates
for investment sought through PPP options. In case of PPP options like Service,
Management or Lease Contracts, the investment required for rehabilitation or
efficiency improvement measures need to be stated, the absence of which will
hinder structuring performance based contracts.
b. Environmental and Social Aspects: On one hand, the information must list the
applicable steps required to obtain environmental clearance under the
Environmental Rules and Regulations issued by competent authority from time to
time. On other hand, the information should also bring out if there are any
environmental or social risks that can impact/delay/ hinder the project deliverables
from considerations of efficient use of assets created under a PPP framework. This
should be addressed from an investment risk perspective.
c. Financial Analysis: Financial analysis of the investment proposed for the landed
cost of the project (see definitions given in the guidelines, the project cost to
include cost of project development funding and returns thereon) must highlight
the sources of investment, drawdown period, the revenues over the project
contract period (due to tariffs for services and/or due to savings arising out of
efficiency gains) and Internal Rate of Return (IRR) on Economic/Project/Equity
IRR considerations. In case of non-revenue generating projects, the Economic
IRR must be mentioned.
30
d. Legal Aspects: This must bring out the provisions under the relevant Acts/Rules
that grant authority to the Sponsoring Agency for developing and implementing
the project under the proposed PPP option and the proposed decision-making
steps to award the PPP contract. The objective is to ensure that the Sponsoring
Authority by itself or through an identified Competent Authority has the necessary
authority to approve the proposed project development and implementation
framework. In case of any need to amend the legal framework, the same must be
mentioned.
e. Risk Identification: A preliminary assessment of the project risks during different
phases of the project-development, construction and implementation-must be
summarized. This will form the basis for structuring possible mitigation
measures/structures in detail during project development, hence an indicative
summary is considered adequate at the preliminary stage. This is to ensure that the
cost of capital/investment sought from the private sector investor is minimal and
based on informed risk mitigation structures rather than perceived risks with
mitigation measures not mentioned.
f. Proposed PPP Implementation Structure: Typically, the intent of systematic project
development with funding support is to seek private sector investment and
management skills so that the Sponsoring Authority can structure performance
based service delivery, while allowing the private sector to recover the investment
with appropriate returns. In case of Greenfield projects, options such as Build, Own,
Operate & Transfer (BOOT), BOT and its variants or Concession or Lease
Contracts are possible. However, in case of existing projects, where significant
rehabilitation or replacement of assets is necessary for asset performance
improvement, management or service contracts (that bring in private sector
efficiency and management skills with investment mostly by the public sector) may
be the first step toward establishing efficient asset base and operational systems for
the project assets for subsequently enabling larger investments through BOOT type
contracts. Hence, the financiability of the proposed PPP option must be highlighted.
g. Regulatory Aspects: The preliminary report accompanying the MFC must mention
the existing regulatory mechanism, as applicable, in case tariffs are to be
structured in the PPP options. In the absence of regulatory mechanism, proposed
steps for regulation by contract must be indicated.
h. Project Development Cycle: The information will include the proposed project
development activities and time lines starting from the appointment of consultants
and advisors culminating in the selection of the private sector partner through a
transparent and competitive procurement process. The role of different
government agencies, role of consultants and advisors should be briefly included.
3. Budget for Project Development
The budget for project development should include an estimate of:
Annex II
Memorandum For Consideration (MFC) Application Form
Nature of Assistance
Project Name
Sector
Sponsoring Authority
Location/
(State/District/Town)
32
Item
Land
Building
Equipments
Any other (Specify)
Rs. Lakhs
Rs. lakhs
Total
IRR Estimations (as
applicable)
Estimated Project
Development Expenses
Enclosures
Economic IRR
Project IRR
Equity IRR
Item
Surveys and Investigations
Consultancy fees:
Technical
Environmental & Social
Legal
Financial
Any other
Total Consultancy Fees
Transaction Advisory Fees
Marketing and Procurement
Related Expenses
Any other
Total Estimated Project
Development Expenses
IIPDF contribution @75%
Rs. lakhs
33
Annex III
Table of Contents of the Preliminary
Report accompanying the MFC
1. Introduction
2. Existing Project Scenario
(including need for rehabilitation, up gradation, improvement and/or
incremental investments-to bring out the need of the project)
3. Project Proposal
(covering broad project concept and components, block cost estimates,
revenue structures, etc.-See Annexure I)
4. Preliminary Project Assessment
4.1 Technical feasibility
4.2 Environment and social acceptability
4.3 Financial & commercial viability
4.4 Legal framework
4.5 Risks (during development, construction and operation implementation)
4.6 Contractual & implementation structures1 5
5. Project Development Activities
5.1 Project development cycle
5.2 Timelines
5.3 Surveys and investigations
5.4 Technical/Environmental & Social/Financial/Legal consultants, their scope of
work
5.5 Transaction Advisors, their scope of work
5.6 Marketing
5.7 Procurement process
5.8 Others (Please specify)
6. Funding Requirements for Project Development
6.1 Budget for Project Development expenses
6.2 Drawdown (indicative quarterly budget and estimated milestone linked payment
for each activity)
7. Plan for Recovery
Plan for Recovery of the Project Development funding with Returns
8. Recommendations
BOT= build-operate-transfer, O&M= Operation and maintenance
Source: ADB, Public-Private-Partnership Handbook; Heather Skilling and Kathleen
Booth 2007.
34
Appendix II
HISTORICAL BACKGROUND
The beginnings of partnership between private and public sectors can be traced as far
back as the Roman Empire two thousand years ago in Europe. A network of postal
stations was developed to accompany the vast expansion of the highway system under
the Roman legions. During the 16th and 17th centuries, European sovereigns,
particularly France, began much more expansive public works concession programs
in canal construction, road paving, waste collection, public lighting, mail distribution
and public transportation. In early 20th. prior to 1982 there was very limited private
financing of transport infrastructure in developing or transition countries. Throughout
the industrialized and developing world, there has been a renewed move to
liberalization and privatization of infrastructure activities which increased
dramatically into the 1990s forging a systematic Public Private Partnership (PPP).
The United Kingdom's Private Finance Initiative (PFI), which began in 1992, had
projects in most key infrastructure areas. Other countries with significant PPP
programs include Australia, Ireland, United States, France, Italy, Spain, Finland,
Germany, Greece, the Netherlands and Portugal. Reflecting a need for infrastructure
investment on a large scale, but weak fiscal positions, a number of countries in
Central and Eastern Europe, including the Czech Republic, Hungary, and Poland,
have embarked on PPPs. There are also fledgling PPP programs in Canada and Japan.
PPPs in most of these countries are dominated by road projects. In Latin America,
Chile, Colombia, and Mexico have used PPPs to promote private sector participation
in public investment projects. In Africa, South Africa has embarked upon developing
PPPs in a number of sectors. In Asia, the use of PPPs is continuing to develop with a
well established program in South Korea, an extensive investment program in China,
although with varying degrees of implementation and success, in Indonesia, the
Philippines and Singapore. In India, PPP is now being used widely in improvement of
physical and social infrastructure.
35
Appendix III
LESSONS LEARNT FROM PPP PROGRAMS
The establishment and implementation of PPP programs worldwide has provided
several lessons, particularly from the poor performing PPP programs.
Such lessons include:
1 Countries without a proper policy and full commitment across the Ministries/
Departments involved, (Finance and Development, Planning), fail to instil confidence
in the private sector. The result is that either the private sector is not interested or
prefers to use unsolicited tenders to avoid a competitive and transparent framework.
2 Projects are often insufficiently prepared, sometimes for financial reasons,
sometimes for time reasons. Ultimately, poorly prepared projects either fail or take
much longer, sometimes years longer than the advocated PPP process or result in
financial (and political) liabilities for governments in later years.
3 Inconsistent laws and regulations can be worse than limited or no laws, where
regulation by contract can operate at least initially.
4 Even where projects are well developed and frameworks are in place, relatively
minor defects in concession contracts can lead to weak and uncompetitive tenders.
5 Without clear policy regarding unsolicited bids, the private sector may prefer this
approach, which could result in poorer deals for the government and longer time taken
to implement than the standard PPP route.
6 Ad hoc projects, rather than a properly developed pipeline of projects, may result in
difficult projects which either fail to be implemented or take years to be developed.
Difficult projects are generally those that require large subsidies, are risky, often not
ready and have too many negative impacts.
7 Consultation and explanation of PPPs is often insufficient to convince/inform public
sector officials, senior staff and general public of their advantages and how they work,
generating a lot of misunderstanding and opposition to PPPs. Many of these lessons
provide the basis for the policy and strategy development in the present section.
8 PPP is not the only method to deliver project financing and realisation. It does not
provide a miracle solution nor a quick fix and should only be used where
appropriate and where it is able to deliver clear advantages and benefits.
9 Each type of PPP has inherent strengths and weaknesses which need to be
recognized and integrated into project design.
10 One of the fundamental causes of project failure, for both traditional public sector
procurement and PPPs, is often a lack of clarity on the part of the public authority
regarding the exact scope and requirements of the project. The other reasons are
revenue or market forecasts being wrong, failure of technology, insolvency of
subcontractors, or excessive exchange rate fluctuations.
36
37
sector to transfer a portion of the risks associated with the project to a private sector
company, which will, it is assumed, have the skills and experience needed to manage
these more effectively and at a lower cost.
12.5 Legal and regulatory environment
Increasingly many countries have amended ( or are currently amending) their existing
legislation in order to clearly specify the powers of public bodies to contract out
services under PPPs. Legislation addressing PPP arrangements should identify which
sectors may make use of PPPs, how PPP tariffs are set and adjusted, the role played
by different institutions in making PPPs happen, how PPPs should be procured, and
methods for the resolution of any disputes that may arise between contracting
partners.
13 Another element of international best practice suggests that public authorities
engaged in broad based PPP programmes are increasingly making use of crosssectoral pools of expertise in dedicated PPP units. These units play a wide variety of
roles including:
Developing PPP policies and legislation;
Providing guidance about best practice and disseminating information on
PPPs;
Clearing and approving PPPs;
Providing expertise in one or more areas of PPP procurement and
management;
Assessing the direct and contingent financial costs of PPPs, and approving
PPPs developed by other government agencies.
14 Creating the Dedicated PPP Units
There are four general approaches to establishing PPP units and identifying their
core functions:
14.1 Create a unit within a ministry / department. For example PPP unit in
Department of Economic Affairs, Government of India, PPP unit in Treasury in South
Africa
14.2 Set up the unit as an autonomous entity attached to but not fully part of
government bureaucracy. For example Philippines BOT Centre
14.3 Establish a government owned company to collaborate with departments and
other agencies to indentify and procure PPPs. For example Partnerships British
Columbia in Canada.
14.4 Create a joint venture company owned in part by private sector shareholders
and acting as bridge between the public and private sectors. For example Partnership
UK
14.5 The authorities engaged in PPP programmes have established dedicated PPP
units for using cross sectoral pools of expertise. These units perform following main
functions
Developing PPP policies and legislation
38
39
contractors, project managers, actuaries and other technical professionals. They carry
out the following functions:
Define output and outcome specifications and service standards to be
provided under the PPP contract;
Evaluate proposals and bids, including the capability of the private sector
tenderers;
Conduct quality assurance during construction, ensuring contractor
compliance and assessing technical risk;
Value assets that may be sold or transferred from the public sector to the
private entity;
Develop systems for monitoring and measuring performance.
40
Appendix IV
TOP TEN FACTS ABOUT PPPS
1
Public-private
partnerships
are
just
what
the
name
implies.
Public-private partnerships are a contractual arrangement whereby the resources, risks
and rewards of both the public agency and private company are combined to provide
greater efficiency, better access to capital, and improved improved service delivery
with a range of government regulations. The public's interests are fully assured
through provisions in the contracts that provide for on-going monitoring and oversight
of the operation of a service or development of a facility. In this way, everyone wins - the government entity, the private company and the general public.
2 Public-private partnerships are more common than one may think
and have been in use in many countries. These contractual arrangements between
government entities and private companies for the delivery of services or facilities is
used for infrastructure such as roads, water/ wastewater, transportation, urban
development, and delivery of social services, to name only a few areas of application.
The use of partnerships is increasing because they provide an effective tool in meeting
public needs, maintaining a high level of public control, improving the quality of
services, and are more cost effective than traditional delivery methods.
3
They
are
essential
tools
in
challenging
economic
times.
Even in the best of times, governments at all levels are challenged to keep pace with
the demands of their constituencies. During periods of slow growth, government
revenues are frequently not sufficient to meet spending demands, necessitating painful
spending cuts or tax increases. Partnerships can provide a continued or improved level
of service, at reduced costs. And equally important, partnerships can also provide the
capital needed for construction of major facilities. By developing partnerships with
private-sector entities, governments can maintain quality services despite budget
limitations.
4
Successful
partnerships
can
lead
to
happy
employees.
In many partnerships created today, public employees are retained and usually at
equal or improved benefits. One of the greatest areas of improvement for employees
is with opportunities for career growth -- private companies spend more on training
and personnel development than their public-sector counterparts, as a way of gaining
the maximum efficiency out of every person, and the maximum amount of job
satisfaction.
5
Successful
partnerships
can
lead
to
better
public
safety.
For example, many mundane activities in Police department such as processing of
crime reports can be passed on to private-sector partners, whereby police officers can
spend more time on the streets doing the jobs for which they are trained. This has
been done in USA.
6 Partnerships give many children better educational opportunities.
Public-Private Partnerships could be instrumental in constructing new school
buildings. In US and UK, by working with a private real estate development
41
company, city and county school systems were able to build state-of-the-art facilities
with a modern computer lab, gym and library.
7 Private-sector companies are working with central, state and local governments to
build roads, making it possible to finance construction and upkeep without having to
impose general tax increases. While tolling is one of the means of generating the
revenue to cover the investment, other methods such as annuity and shadow tolling
have been successfully tried.
8 Clean, safe water is achieved through public-private partnerships.
Public-private partnerships have enabled the construction of state-of-the-art water
management facilities, while using efficient operations to hold down costs to
ratepayers and provide a way of meeting those "un-funded mandates". Many States
have successfully implemented projects for supplying 24x7 water supply with taking
care of weaker sections of society as well.
9 Partnerships make the information revolution accessible to more people.
This is the age of information technologies, but there can be a hefty cost of getting a
system operating. Through public-private partnerships, many governments are now
able to fully participate in "E-government" with their constituents, or effectively
coordinate government activities and budgets. Better service, improved tools and
saving money are exactly what public-private partnerships are all about.
10 Governments themselves are the biggest supporters of public-private partnerships.
While there can be substantial misperceptions about the value of partnerships, a look
at who endorses them should clarify the picture. Government of India, as in other
countries, has been promoting PPP for the last three decades. Numerous surveys
indicate why -- governments traditionally realize cost savings of 20 to 50 percent
when the private-sector is involved in providing services.
42
Appendix V
STRENGTHS AND WEAKNESSES OF PPP
1 Strength
One of the main strength of PPPs is their ability to deliver value for money in
public service procurement and operation by utilizing the skills, resources and
experience of each partner. Public sector provides its strength and expertise in
identifying public needs, service requirements and desired outcomes with strength of
governance and citizen support where as private sector brings in its capacity to
effectively utilize assets through better operational efficiency, innovative technology,
managerial effectiveness for better management of the construction and operation of
services.
Benefits to the Public Sector :
The Government i.e. the public sector derives fiscal, economic, technological
and social benefits from PPP. The foremost is that it allows to raise capital for higher
priority work that might otherwise not be possible due to budgetary constraints. This
also enables the optimal allocation of public resources for infrastructure development.
It entails accurate costing of the project and optimal allocation of risks. The
economic benefits are derived by way of speedy reliable and efficient delivery of the
facilities. The infrastructure development catalyses the other developmental activities
in the region there by creating a virtuous circle leading to enhance quality of life of
the people. It also provides new role for the Government and opportunities for
innovation, capacity building and technological enhancement. Additionally, it allows
public sector to realise value for money for the entire life of project or service rather
than just initial construction phase as is the case in traditional model of public
procurement. Figure 6 shows the main advantage of cost and time overrun cost risks
getting transferred to private sector in PPP.
Fig. 6: Risk Transfer Advantage in PPP Project from Conventional Procurement
43
Cost
Overrun
Construction
Phase
Time Overrun
Estimated
Capital
Cost
Running Cost
Overruns
Estimated Running
Cost
10
15
20
yrs.
0
Construction
Phase
10
15
20 yrs
44
The cost of finance in the private sector including both debt and equity is
typically between 1% and 3% higher than the public sector cost debt on a non
risk adjusted basis. This has effect of increasing the over all cost of PPP in
comparison to the traditional procurement method.
PPPs can some times be rather inflexible instruments specially given the long
term nature of most PPP contracts. There is limited potential for modifying
services or flexible spending.
Under PPP arrangements lines of accountability can be less straight forward
and transparent than under traditional methods of procurement where
accountability is more direct. This assumes more significance in these areas
of public service provision which may require greater public demand for
accountability and responsiveness than any others. This may also some times
result in public criticism and scepticism or even hostility towards PPP
arrangements.
Appendix VI
COMMON MISCONCEPTION ABOUT PPP
45
46
Appendix VII
47
In Africa, the picture is similar. PPP investments are estimated to have provided 1015% of total infrastructure investment over the past twenty years in African countries.
Moreover, whilst significant increased investments are planned in the highways
sector, the emphasis on private sector funding in the 1980s and 1990s has been
criticized as being a policy mistake.
Some countries however suggest a higher rate of PPP investments, notably India and
Chile, which may suggest that a higher role for PPP is possible to fund major highway
investment programs subject to a suitable enabling environment.
PPP programs should be seen as complementing and not replacing conventional
procurement methods.
Appendix VIII
ENABLING ENVIRONMENT FOR PPP
1 Drivers of PPP
The development of a successful PPP program requires two key drivers: political will
and bankable projects. The subsequent implementation of such projects necessitates
that an enabling environment for PPP be established for finance to be mobilized and
the partnership to work effectively and to the benefit of both parties.
1.1 Political will to introduce PPP: A state considering the launch of a PPP policy
for the provision of infrastructure facilities and/or public services must announce
firmly its intention to do so in an unequivocal manner. The government should
demonstrate strong commitment to pursue policy objectives within an evolving
political environment. Private sector partners need to understand the involvement of
the public authorities knowing what framework has been set up: strategy, means,
management process and principles are all important elements in the private
investors evaluation.
1.2 Bankable projects suitable for funding by the private sector :
The
key
issues that need to be examined in the PPP process are: the strategic justification for
the project, whether the project represents value for money, whether the project is
affordable, whether the project is commercially viable or bankable, and whether the
authority has the right resources, skills, and organization to manage the process. The
fundamental for the identification of PPP procurement options is to have projects with
sound economic and financial credentials. A thorough project preparation and the
identification of suitable procurement routes under PPP is necessary to be ensured.
The private sector should also perform rigorous project analysis and estimate the
project parameters independently. Initially, the best projects should be selected which
are of sufficient size to attract the private sector, not too complex or risky and which
48
need little government support. This reduces the exposure of the project to
inconsistent public commitment and inadequate fiscal space/financial support.
2 PPP Policy Framework
2.1 The route to an enabling environment passes through the PPP policy framework
which comprises a number of interlocking structures including legal and regulatory,
risk management, institutional, financial, private sector and other aspects. However,
this framework is established in the context of a number of constraints, the nature and
extent of which shall depend on the particular economic, social and political
conditions prevalent in the country. These constraints such as political instability or
lack of political will, underdeveloped financial markets or economic instability, lack
of transparency, weak public institutions, lack of PPP experience or low PPP skills.
Experience with PPP worldwide, suggests that it is useful, if not essential, to have a
PPP policy framework in place, to facilitate planning and implementation and instil
confidence and understanding in all participants in the PPP process. This includes
both public and private partners. Generally all countries have embarked on the PPP
process in that way. This framework provides a set of rules that gives confidence to
both the public sector which has to implement the rules and also the private sector
which has to invest time and money and aims to ensure that both will achieve, within
acceptable bounds, their objectives.
A PPP policy framework is an evolving tool; it should not be viewed as an ideal or
even something to be aimed at in total at once. Required changes will take time to
agree and implement and will only be felt in the medium- to long-term. It should thus
be developed with a long-term process in mind which would allow its progressive
adaptation and improvement in line with the experience from implementation of the
PPP program.
2.2 Constraints
Constraints to PPP policy are reflective of the specific environment and which have a
determining impact on the development and success of PPP programs. They may
hinder, delay or even prevent the establishment of the required components of the PPP
policy framework:
Political Instability
Economic Instability
Under-developed financial markets
Less number of users
Low capacity or unwillingness to pay
Popular resistance to levying of user charges
Lack of PPP experience / low PPP skills
Weak public institutions (low traffic enforcement/overloading)
Lack of transparency
2.3 Addressing the constraints
Setting up a PPP policy requires redefining the role of Government. The changing
focus should reduce the Governments functions as supplier, but increases its
functions as regulator - the enabler of competition. This means that governments need
to create the proper institutional framework for competition, set economically
efficient charges for the use of publicly provided infrastructure, carefully appraise the
allocation of scarce public resources and increase community participation in decision
49
making. Constraints limiting private sector involvement can only be removed through
long-term and in-depth reforms. Long-term reform aiming at developing and
structuring the construction industry would be appropriately required (Table 1).
Table 1: Constraints and Reform for PPP
Table below gives a gist of actions to address the cons
Types of Particular
constraints constraints
Political
constraints
Specific actions
Economic
and
financial
constraints
Economic
instability
Under-developed
financial markets
Less number of
users Low incomes
Economic development
Secure revenues
from
dedicated funds
Develop financial markets
(reform banking
system, set up infrastructure
investment
Develop methodologies
for public risk assessment
Economic
and
financial
constraints
Economic
instability
Under-developed
financial markets
Less number of
users Low incomes
Economic development
Secure revenues
from
dedicated funds
Develop financial markets
(reform banking
system, set up infrastructure
investment
Develop methodologies
for public risk assessment
Public
sector
Lack
of
experience/
50
constraints
assignment
of
responsibilities over
the various parts of the
network.
Build
up
progressive experience on
PPPs from maintenance
contracts to concessions.
PPP Develop capacity of the
low private sector (local
contractors and consultants)
Move from input (quantity)
to output
(performance) type of
contracts.
Private
sector
constraints
Lack
of
experience/
PPP skills
Appendix IX
PROJECT FINANCING
1 Infrastructure PPPs typically require financing; that is, external funds are required
for the initial investment costs that are recovered over time from future revenue
streams. The funds may be sourced from the public sector or the private sector.
Regardless of the source of finance, such funds have a cost and, therefore, impact the
projects economics and required tariffs (and thus affordability). A governments cost
of funding is typically lower than that of a private operator. Private financing may
therefore increase the financial costs of PPP. However, the efficiency gains from PPP
are expected to outweigh this additional cost and result in net savings and efficiency
gains, with an ultimate benefit to consumers. In addition, public sector financing is
usually scarce, creating one of the initial drivers for PPP. The operator will typically
establish a project company for implementing the contract, often called special
purpose vehicle (SPV). The company owners may be a consortium of companies or a
single large company. The company owners will not usually finance all project
requirements; instead, they will provide a proportion as equity and borrow the
remainder of the required financing from financial institutions or place debt securities
in the capital market. The creditworthiness (bankability) of a project depends on a
number of factors, some of which are within the control of the government when
designing PPP. They include commercially attractive project design and tariffs
(shorter payback and, hence, financing periods) as well as strong off-take
arrangements to reduce market/revenue risk (predictability of cash flows), together
with the level of certainty and transparency of regulatory settings, which affect future
cash flows. Infrastructure project financing in general, whether from banks or bond
markets, faces a number of challenges including
(i) long-term debt maturities to match project cash flows,
(ii) limits to the availability of debt financing to match revenue steams,
(iii) limited available equity and resulting high degree of leverage, and
(iv) no security/ guarantee except for project assets available (nonrecourse
financing).
Project finance, is a specialized activity and, depends on prevailing market conditions.
To make financing possible or to secure better borrowing rates, the operator may seek
51
Cost Recovery
Service
Standard
Subsidy
Tariff
Structure
Willingness/
Ability to Pay
52
53
reduce tariff levels for the purposes of helping the poor, addressing public health
issues, addressing environmental issues, and/or because of political constraints on
raising tariffs.
2.2.4 Simplicity and comprehensibility
The objective of simplicity and comprehensibility means that tariffs should be easily
accessible and understandable to employees and consumers of the utility. For
example, if a tariff structure is too complex, customers may not understand the
implication of changes in consumption for their bills or the range of options available
to them. However, over simplification may result in incentives being lost or a
negative impact on fairness.
2.2.5 Balancing the objectives
There is a need to balance these above objectives against one another. For example,
the objective of incentives may conflict with the objective of simplicity at times
because on cost grounds it may make sense to have a very complex tariff structure. A
similar conflict could arise with the fairness objective. There is a further requirement
that certain fundamentals be in place including a definition of a reasonable rate of
return, an understanding of how assets will be valued, and whether any additional
returns are to be allowed. After evaluating these factors and determining the
appropriate allocation of risks in PPP, the initial tariff rates and tariff structure are set
in place until an adjustment is warranted.
2.2.6 Tariff Adjustments
To expect one set of tariffs, or even a tariff structure or regime, to remain viable and
appropriate over the typical life of a PPP project is unrealistic. It is therefore essential
to define practical rules for adjustments. This requires defining:
The triggers or drivers for a price adjustment, such as changes in raw material prices
(such as oil prices), inflation, and exchange rate fluctuations);
The mechanisms by which the adjustment will be made, including cost plus and
price cap regulation; and
The frequency of adjustments including cost pass-through, tariff indexation, tariff
resets, and extraordinary tariff adjustments.
2.2.7 Stakeholder Involvement
The early involvement of all stakeholders in the PPP process helps develop an
enabling environment. The stakeholders provide valuable information on the points of
concern, the performance expectations, and potential risks. This input is also critical
to assess whether key business assumptions of the proposed PPP (in particular
tariffs/fees) are realistic and enforceable. Avoiding consultation invites the risk of
later opposition, which slows or derails the process. Ongoing consultation with
stakeholders is important at every stage. Consultation with potential bidders and
partners is also critical to ensure that the proposed PPP design meets their
requirements. Otherwise, there is a risk that the PPP design includes an unrealistic
combination of (politically) desirable features (high-level service, low prices, no
redundancies, no subsidies, and short concession periods) that will make the project
unattractive to bidders or unsustainable. Collecting informal feedback from the
market during the preparation stage is therefore critical.
54
Appendix X
PUBLIC PRIVATE PARTNERSHIP (PPP) MODELS
1 Forms of PPP
The forms of PPP and the extent of Private Sector participation is depicted in
following Figure 9.
Fig. 9: Public and Private Sector Participation in Various Forms of PPP
Private Sector
Public Sector
Design
Finance
Construct
O&M
Ownership
Service
Management
Contract
Contract
Lease
Concession BOT/BOO
Divest
2 The PPP models vary from short-term simple management contracts (with or
without investment requirements) to long-term and very complex BOT form, to
divestiture.
These models vary mainly by:
55
56
57
period which extends over the economic life of assets. Fixed facilities and land are
leased out for a longer period than for mobile assets. Land to be developed by the
leaseholder is usually transferred for a period of 15-30 years. It may be noted here that
if the assets transferred to the private sector under a lease agreement are constrained
in their use to a specific function or service, the value of assets is dependent upon the
revenue potential of that function or service. If assets are transferred to the private
sector without restrictions of use, the asset value is associated with the optimum use
of the assets and the revenues that they can generate. Its variants are:
5.1
Lease/Purchase
A lease/purchase is an instalment-purchase contract. Under this model, the private
sector finances and builds a new facility, which it then leases to a public agency. The
public agency makes scheduled lease payments to the private party. The public
agency accrues equity in the facility with each payment. At the end of the lease term,
the public agency owns the facility or purchases it at the cost of any remaining unpaid
balance in the lease.
Under this arrangement, the facility may be operated by either the public agency or
the private developer during the term of the lease. Lease/purchase arrangements have
been used by the General Services Administration for building federal office
buildings and by a number of states to build prisons and other correctional facilities.
5.2
Sale/Leaseback
This is a financial arrangement in which the owner of a facility sells it to another
entity, and subsequently leases it back from the new owner. Both public and private
entities may enter into sale/leaseback arrangements for a variety of reasons. An
innovative application of the sale/leaseback technique is the sale of a public facility to
a public or private holding company for the purposes of limiting governmental
liability under certain statues. Under this arrangement, the government that sold the
facility leases it back and continues to operate it.
5.3
Tax-Exempt Lease
A public partner finances capital assets or facilities by borrowing funds from a private
investor or financial institution. The private partner generally acquires title to the
asset, but then transfers it to the public partner either at the beginning or end of the
lease term. The portion of the lease payment used to pay interest on the capital
investment is tax exempt under state and federal laws. Tax-exempt leases have been
used to finance a wide variety of capital assets, ranging from computers to
telecommunication systems and municipal vehicle fleets.
5.4
LDO or BDO: Lease-Develop-Operate or Build-Develop-Operate
Under these partnerships arrangements, the private party leases or buys an existing
facility from a public agency; invests its own capital to renovate, modernize, and/or
expand the facility; and then operates it under a contract with the public agency. A
number of different types of municipal transit facilities have been leased and
developed under LDO and BDO arrangements.
6 Concessions
In this form of PPP, the Government defines and grants specific rights to an entity
(usually a private company) to build and operate a facility for a fixed period of time.
The Government may retain the ultimate ownership of the facility and/or right to
58
supply the services. In concessions, payments can take place both ways:
concessionaire pays to government for the concession rights and the government may
also pay the concessionaire, which it provides under the agreement to meet certain
specific conditions. Usually such payments by government may be necessary to make
projects commercially\ viable and/or reduce the level of commercial risk taken by the
private sector, particularly in the initial years of a PPP programme in a country when
the private sector may not have enough confidence in undertaking such a commercial
venture. Typical concession periods range between 5 to 50 years. It may be noted that
in a concession model of PPP, an SPV may not always be necessary. Concessions
may be awarded to a concessionaire under two types of contractual arrangements:
Franchise
BOT type of contracts
6.1 Franchise
Under a franchise arrangement the concessionaire provide services that are fully
specified by the franchising authority. The private sector carries commercial risks and
may be required to make investments. This form of private sector participation is
historically popular in providing urban bus or rail services. Franchise can be used for
routes or groups of routes over a contiguous area.
6.2 Build-Operate-Transfer (BOT)
In a Build-Operate-Transfer or its other variants type of arrangement, the
concessionaire undertakes investments and operates the facility for a fixed period of
time after which the ownership reverts back to the public sector. In this type of
arrangement, operating and investment risks are substantially transferred to the
concessionaire. However, in a BOT type of model the government has explicit and
implicit contingent liabilities that may arise due to loan guarantees provided and
default of a sub-sovereign government and public or private entity on non-guaranteed
loans. By retaining ultimate ownership, the government controls policy and can
allocate risks to those parties best suited to bear them or remove them. In a BOT
concession, often the concessionaire may be required to establish a special purpose
vehicle (SPV) for implementing and operating the project. The SPV may be formed as
a joint venture company with equity participation from multiple private sector parties
and the public sector. In addition to equity participation, the government may also
provide capital grants or other financial incentives to a BOT project. BOT is a
common form of PPP in most of sectors in India and other Asian countries. A key
distinction between a franchise and BOT type of concession is that, in a franchise the
authority is in the lead in specifying the level of service and is prepared to make
payments for doing so, whilst in the BOT type the authority imposes a few basic
requirements and may have no direct financial responsibility. A typical structure for
BOT project is indicated in Fig. 10.
59
Concession
Shareholders
Agreement
Agreement
Shareholders
Concessionaires
Users/
Special Purpose
Customers
Company
(SPC)
Lenders
Loan
Agreement
Turnkey
Contract
Designer, Contractor
And Supplier
Operation &
maintenance
Agreement
Operator and
Maintenance Holder
60
61
62
operate the facility under the oversight of the government. The developer gains the
right to use the facility and may receive future income from user fees.
While developers may in rare cases build a facility, more typically they are charged a
fee or required to purchase capacity in an existing facility. This payment is used to
expand or upgrade the facility. Developer financing arrangements are often called
capacity credits, impact fees, or extractions. Developer financing may be voluntary or
involuntary depending on the specific local circumstances
6.3 Private Ownership of Assets
In this form of participation, the private sector remains responsible for design,
construction and operation of an infrastructure facility and in some cases the public
sector may relinquish the right of ownership of assets to the private sector. It is argued
that by aggregating design, construction and operation of infrastructure services into
one contract, important benefits could be achieved through creation of synergies. As
the same entity builds and operates the services, and is only paid for the successful
supply of services at a pre-defined standard, it has no incentive to reduce the quality
or quantity of services. Compared with the traditional public sector procurement
model, where design, construction and operation aspects are usually separated, this
form of contractual agreement reduces the risks of cost overruns during the design
and construction phases or of choosing an inefficient technology, since the operators
future earnings depend on controlling costs. The public sectors main advantages lie
in the relief from bearing the costs of design and construction, the transfer of certain
risks to the private sector and the promise of better project design, construction and
operation.
There can be three main types under this form:
Build-Own-Operate type of arrangement
Private Finance Initiative (a more recent innovation)
Divestiture by license or sale
6.3.1 Build-Own-Operate
In the Build-Own-Operate (BOO) type, the private sector builds, owns and operates a
facility, and sells the product/service to its users or beneficiaries. This is the most
common form of private participation in the power sector in many countries. For a
BOO power project, the Government (or a power distribution company) may or may
not have a long-term power purchase agreement (commonly known as off-take
agreement) at an agreed price from the project operator. In many respects, licensing
may be considered as a variant of the BOO model of private participation. The
Government grants licences to private undertakings to provide services such as fixed
line and mobile telephony, Internet service, television and radio broadcast, public
transport, and catering services on the railways. However, licensing may also be
considered as a form of concession with private ownership of assets. Licensing
allows competitive pressure in the market by allowing multiple operators, such as in
mobile telephony, to provide competing services. There are two types of licensing:
quantity licensing and quality licensing. By setting limits through quantity licensing,
the government is able to moderate competition between service providers and adjust
supply between one area and other. Quality licensing however, does not place any
restriction on number of providers or the amount of service produced but specifies the
63
quality of service that needs to be provided. The government may get a fee and a
small share of the revenue earned by the private sector under the licensing
arrangement.
6.3.2 Private Finance Initiative
In the Private Finance Initiative (PFI) model, the private sector similar to the BOO
model builds, owns and operates a facility. However, the public sector (unlike the
users in a BOO model) purchases the services from the private sector through a longterm agreement. PFI projects therefore, bear direct financial obligations to
government in any event. In addition, explicit and implicit contingent liabilities may
also arise due to loan guarantees provided to lenders and default of a public or private
entity on non-guaranteed loans. In the PFI model, asset ownership at the end of the
contract period may or may not be transferred to the public sector. The PFI model also
has many variants. The annuity model for financing of national highways in India is
an example of the PFI model. Under this arrangement a selected private bidder is
awarded a contract to develop a section of the highway and to maintain it over the
whole contract period. The private bidder is compensated with fixed semi-annual
payments for his investments in the project. In this approach the concessionaire does
not need to bear the commercial risks involved with project operation. Apart from
building economic infrastructure, the PFI model has been used also for developing
social infrastructure such as school and hospital buildings, which do not generate
direct revenues.
6.3.3 Divestiture
This third type of privatization is clear from its very name. In this form a private
entity buys an equity stake in a state-owned enterprise. However, the private stake
may or may not imply private management of the enterprise. True privatization,
however, involves a transfer of deed of title from the public sector to a private
undertaking. This may be done either through outright sale or through public
floatation of shares of a previously corporatised state enterprise. Full divestiture of
existing infrastructure assets is not very common. However, there are many examples
of partial divestiture.
6.4 Joint Venture
Joint ventures are alternatives to full privatization in which the infrastructure is coowned and operated by the public sector and private operators. Under a joint venture,
the public and private sector partners can either form a new company or assume joint
ownership of an existing company through a sale of shares to one or several private
investors. The company may also be listed on the stock exchange. A key requirement
of this structure is good corporate governance, in particular the ability of the company
to maintain independence from the government. This is important because the
government is both part owner and regulator, and officials may be tempted to meddle
in the companys business to achieve political goals. From its position as shareholder,
however, the government has an interest in the profitability and sustainability of the
company and can work to smooth political hurdles. The private partner assumes the
operational role and a board of directors generally reflects the shareholding
composition or expert representation. Requirements of PPP Partners under Different
PPP Arrangements are given in following Table 2.
64
Service
Contracts
Required
Management
Contracts
Required
Leases
Required
BOT
Agreements
Required
DBFO
Concessions
Required
Partial
Divestiture
Required
Full
Divestiture
Required
Desirable
Desirable
Required
Required
Automatic
Required
Required
Required
Required
Required
Desirable
Desirable
Desirable
Desirable
Political Support
Desirable
Required
Required
Required
Political Stability
Desirable
Desirable
Desirable
Desirable
Government
Requirements
Leveraging
Funding
Accelerating
Project
Implementation
Improving
Service Levels
Improving
Service
Coverage
Efficiency Gains
Ease
of
Implementation
Maximizing
Societal Benefits
Transparency /
Open
Competition
Yes
Important
Important
Important
Important
Important
Important
Important
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Important
Yes
Yes
Yes
Important
Important
Important
Desirable
Important
Desirable
Important
Desirable
Important
Desirable
Important
Desirable
Relevant
Relevant
Relevant
Important
Important
Important
Important
Relevant
Relevant
Relevant
Important
Important
Important
Important
Reasonable
Control of Grant
Funds
Required
Required
Required
Required
Avoiding Undue
Private Profit
Required
Required
Required
Required
Efficiency Gains
Desirable
Important
Important
Important
Important
Yes
Yes
Yes
Required
Required
Required
Leveraging
Private Funds
Lender
Requirements
Rigorous
Desirable
Desirable
Yes
65
Financial
Analysis
Conservative
Cost/Revenue
Assumptions
Required
Required
Required
Certainty of
Grant and State
funding
Required
Required
Required
Clear
Legal
regulator
structure
Technical
Ability of
Owner/
Operator
Required
Required
Required
Required
Required
Required
Political Stability
Desirable
Desirable
Desirable
Improve
efficiency
Transferring
Risk
Improving
Service
Quality
Maintaining
control of
service
provision
Forms of PPP
Service Management Lease
Concessions Build
Contract Contract
Contract Contract
Operate
Transfer
p
p
p
n
n
Divesture
n
p or n
6.6 The key features of main forms of PPP are given in Annex IV
66
Annex IV
SERVICE
CONTRACT
MANAGEMENT
CONTRACTS
LEASE
CONTRACTS
CONCESSIONS
BUILD-OPERATETRANSFER (BOT)
Scope
Multiple contracts
for a variety of
support
services
such as meter
reading, billing etc.
Management
of
entire operation of a
major component
Responsibility for
management,
operations
and
specific renewals
Responsibility for
all operations and
for financing and
execution
of
specific\investments
Investment in and
operations
of
a
specific
major
component, such as a
treatment plant
Asset Ownership
Public
Public
Public
Public/Private
Public/Private
Duration
Operation
&
Maintenance
Responsibility
Capital Investment
Commercial Risk
Overall Level of
Risk Assumed by
Private Sector
Compensation
Terms
1-3 years
Public
2-5 years
Private
10-15 years
Private
25-30 years
Private
Varies
Private
Public
Public
Minimal
Public
Public
Minimal/moderate
Public
Shared
Moderate
Private
Private
High
Private
Private
High
Unit prices
Portion of tariff
revenues
High
Competition
Intense
ongoing
Useful as part of
strategy
for
improving
efficiency
of
public company;
Promotes
local
private
sector
development
Requires ability to
administer multiple
contracts
and
strong enforcement
of contract laws
Special Features
Initial
contract
only, sub-sequent
contracts usually
negotiated
Improve
operational
and
commercial
efficiency;
Develops
local
staff
Problems
Challenges
and
and
Interim
solution
during
preparation
for more intense
private participation
Mobilizes investment
finance;
Develops
local staff
67