Vous êtes sur la page 1sur 14

CTIVITY

1-2
2-3
2-4
2-5
3-5
4-5

DURATION
DAYS
1
2
5
2
6
10

4-7
3-6
5-6
5-7
5-8

0
12
9
5
8

6-8
6-9
7-8
7-10
8-10

0
2
1
12
7

8-9
8-11
9-11
10-11
10-13
11-12
9-14
12-14
12-13
13-15

0
8
4
2
12
2
3
2
3
8

JOB DESCRIPTION
Relocation of boundaries-cleaning
Construction of field office
Delivery of materials
Staking and batter boards
Digging/excavation
Cutting and assembling of steel
reinforcements
Dummy
Making of forms and door jambs
Positioning steel reinforcement
Forms and scaffoldings
Electrical, plumbing and water pipe
connections
Dummy
Pouring of footings and columns
Removal of forms
CHB laying and backfilling
Beams and slab forms, reinf. And various
piping installations
Dummy
Roof framing and roofing sheet
Pouring of beam and slabs
Construction of stairways
Plastering and tile works
Installation of doors and windows
Plumbing & drainage system
Installation of plumbing fixtures
Install electrical wiring & fixtures
Painting and varnishing

14-15

Final work and cleaning

1
0

1
2

1
4

1
6

1
8

2
0

2
2

2
4

2
6

2
8

3
0

3
2

3
4

36

38

40 42

4
4

4
6

4
8

5
0

914
23
3-6

5-6
69

3-5

9-11

25

5-8
12
14

8-11

14
15
1
2

78

8-10
10
11

2-4

11
12

4-5

1213

5-7
7-10

10-13
13-15

5
2

54

DATA SHEET
DURATIO
JOB DESCRIPTION
ES
EXCAVAITION N
1-2
1
Relocation of boundaries-cleaning
0
2-3
2
Construction of field office
1
60 sq. m. X 434.27 Pesos / sqm =
26,056.00
2-4
5
Delivery of materials
1
2-5
2
Staking and batter boards
1
3-5
6
Digging/excavation
3
4-5
10
Cutting and assembling of steel reinforcements
6
ROOFING
WORKS
4-7
0
Dummy
6
3-6
12
Making of forms and door jambs
3
Roof9= 1.2 x 500 =
5-6
Positioning 60,000.00
steel reinforcement
16
5-7
5
Forms and scaffoldings
16
5-8
plumbing
and
water pipe connections
16
Steel8Deck CapElectrical,
= 12 x 750
=
9,000.00
6-8
0
Dummy
25
6-9
2
Pouring
of
footings
and
columns
25
Roofing Nails= 2.4 x 250 =
600.00
7-8
1
Removal of forms
21
7-10
12
CHB laying and backfilling
TOTAL
69,600.00 21
Beams and slab forms, reinf. and various piping
8-10
7
25
installations
8-9
0
Dummy
25
8-11
8
Roof framing and roofing sheet
25
9-11
4
Pouring of beam and slabs
27
10-11
2
Construction of stairways
33
ROOF
FRAMING
10-13
12
Plastering and tile works
33
11-12
2
Installations of doors and windows
35
Angle
Bar
=
60
x
450
=
27,000.00
9-14
3
Plumbing and drainage system
27
12-14
2
Installation
of
plumbing
fixtures
37
Purlins = 60 x 350=
21,000.00
12-13
3 Bolt = 60 x 50=
Install electrical and wiring3,000.00
fixtures
37
Anchor
13-15
8
Painting and varnishing
45
(Welding Services) = 333.33333 x 20000=
20,000.00
14-15
2
Final work and cleaning
39
ACTIVITY

EF

LS

LF

TF

FF

C.A

1
3
6
3
9
16
6
15
25
21
24
25
27
22
33

0
8
1
14
10
6
21
14
17
16
18
26
34
25
21

1
10
6
16
16
16
21
26
26
21
26
26
36
26
33

0
7
0
13
7
0
15
11
1
0
2
1
9
4
0

0
0
0
13
7
0
15
10
0
0
1
0
0
3
0

32

26

33

25
33
31
35
45
37
30
39
40
53
41

36
32
36
38
33
40
48
49
42
45
51

36
40
40
40
45
42
51
51
45
53
53

11
7
9
5
0
5
21
12
5
0
12

2
2
4
0
0
0
9
0
5
0
12

TOTAL =

71,000.00

FLOOR WORKS
1st Floor
Tiles =
Adhesive =
Cement =

200 x 280 =
12 x 220 =
12 x 230 =

56,000.00
2,640.00
2,760.00

TOTAL =

61,400.00

REINFORECMENT
Footings
Rebar 12mm Type 1 (Long Bars) = 8 x 325 =
Rebar 12mm Type 2 (Long Bars) = 8 x 325 =
Rebar 10mm Type 1 (Alternating Bars) = 5 x 135=
Rebar 10mm Type 2 (Alternating Bars) = 5 x 135=

2,600.00
2,600.00
675.00
675.00

TOTAL =

6,550.00

Column
Rebar 12mm Type 1 (Long Bars) = 32 x 325 =
10,400.00
Rebar 16mm Type 2 (Long Bars) = 13 x 340=
4,200.00
Tie Wire
= 13 x 90=
1,170.00

TOTAL =

143,910.00

Beam
Rebar 12mm Type 1 (Long Bars) = 24x 325 =
7,800.00
Rebar 16mm Type 2 (Long Bars) = 10x 340=
3,400.00
Tie Wire
= 10x 90=
900.00

TOTAL =

108,900.00

FORMWORKS (1st Floor)


Column
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
6,557.24

TOTAL =

Beam
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
19,906.15

TOTAL =

Slab
Plywood

Cocolumber
Ordinary Nails
Tie wire #16
24,857.12

TOTAL =

FORMWORKS (2nd Floor)


Column
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
6,557.24

TOTAL =

Beam
Plywood
Cocolumber
Ordinary Nails
Tie wire #16

19,906.15

TOTAL =

Slab
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
TOTAL =

24,857.12

CONCRETING
1st Floor
Ready Mix Concrete (7days curing, 3500 psi)
Pumpcrete
Consumables
TOTAL
MASONRY WORKS
1st Floor External Wall

80,235.00

6" CHB
Sand
Gravel
10 mm rebar
Cement
TOTAL

49,059.58

1st Floor Internal Wall


4" CHB
Sand
Cement
Gypsum Board
Metal Studs & Tracks
Gypsum Screw
Gypsum Patty
Gypsum Tape
TOTAL

Total Cost for BOM & BOQ : 1,000,000.00 Php


CONTRACTORS MARK UP 25%: 250,000.00 Php

24,047.83

Value Added Tax (VAT 12%) : 120,000.00 Php

GRAND TOTAL = 1,370,000.00 Pesos

ACTIVITY
1-2

TIME IN DAYS
NORMAL CRASH
1
1

COST
CRASH
25,000

COST TO
EXPEDITE
300

NORMAL
20,000

2-3

5000

10,000

300

2-4

10,000

15,000

300

2-5

5000

12,000

300

3-5

3000

6,000

300

4-5

11,500

20,000

300

4-7

50,000

65,000

300

3-6

300

5-6

30,000

50,000

300

5-7

10

30,000

45,000

300

5-8

70,000

100,000

300

6-8

10

58,000

90,000

300

6-9

300

7-8

26,000

27,000

300

7-10

10,000

15,000

300

8-10

14

10

60,000

80,000

300

8-9

50,000

95,000

300

8-11

300

9-11

150,000

200,000

300

10-11

40,000

55,000

300

10-13

14

14

50,000

70,000

300

11-12

120,000

130,000

300

9-14

30,000

50,000

300

12-14

15,000

30,000

300

12-13

15,000

30,000

300

13-15

90,000

130,000

300

14-15

6,000

7000

300

TOTAL

994,500

1,370,000

8,400

Vous aimerez peut-être aussi