Académique Documents
Professionnel Documents
Culture Documents
1-2
2-3
2-4
2-5
3-5
4-5
DURATION
DAYS
1
2
5
2
6
10
4-7
3-6
5-6
5-7
5-8
0
12
9
5
8
6-8
6-9
7-8
7-10
8-10
0
2
1
12
7
8-9
8-11
9-11
10-11
10-13
11-12
9-14
12-14
12-13
13-15
0
8
4
2
12
2
3
2
3
8
JOB DESCRIPTION
Relocation of boundaries-cleaning
Construction of field office
Delivery of materials
Staking and batter boards
Digging/excavation
Cutting and assembling of steel
reinforcements
Dummy
Making of forms and door jambs
Positioning steel reinforcement
Forms and scaffoldings
Electrical, plumbing and water pipe
connections
Dummy
Pouring of footings and columns
Removal of forms
CHB laying and backfilling
Beams and slab forms, reinf. And various
piping installations
Dummy
Roof framing and roofing sheet
Pouring of beam and slabs
Construction of stairways
Plastering and tile works
Installation of doors and windows
Plumbing & drainage system
Installation of plumbing fixtures
Install electrical wiring & fixtures
Painting and varnishing
14-15
1
0
1
2
1
4
1
6
1
8
2
0
2
2
2
4
2
6
2
8
3
0
3
2
3
4
36
38
40 42
4
4
4
6
4
8
5
0
914
23
3-6
5-6
69
3-5
9-11
25
5-8
12
14
8-11
14
15
1
2
78
8-10
10
11
2-4
11
12
4-5
1213
5-7
7-10
10-13
13-15
5
2
54
DATA SHEET
DURATIO
JOB DESCRIPTION
ES
EXCAVAITION N
1-2
1
Relocation of boundaries-cleaning
0
2-3
2
Construction of field office
1
60 sq. m. X 434.27 Pesos / sqm =
26,056.00
2-4
5
Delivery of materials
1
2-5
2
Staking and batter boards
1
3-5
6
Digging/excavation
3
4-5
10
Cutting and assembling of steel reinforcements
6
ROOFING
WORKS
4-7
0
Dummy
6
3-6
12
Making of forms and door jambs
3
Roof9= 1.2 x 500 =
5-6
Positioning 60,000.00
steel reinforcement
16
5-7
5
Forms and scaffoldings
16
5-8
plumbing
and
water pipe connections
16
Steel8Deck CapElectrical,
= 12 x 750
=
9,000.00
6-8
0
Dummy
25
6-9
2
Pouring
of
footings
and
columns
25
Roofing Nails= 2.4 x 250 =
600.00
7-8
1
Removal of forms
21
7-10
12
CHB laying and backfilling
TOTAL
69,600.00 21
Beams and slab forms, reinf. and various piping
8-10
7
25
installations
8-9
0
Dummy
25
8-11
8
Roof framing and roofing sheet
25
9-11
4
Pouring of beam and slabs
27
10-11
2
Construction of stairways
33
ROOF
FRAMING
10-13
12
Plastering and tile works
33
11-12
2
Installations of doors and windows
35
Angle
Bar
=
60
x
450
=
27,000.00
9-14
3
Plumbing and drainage system
27
12-14
2
Installation
of
plumbing
fixtures
37
Purlins = 60 x 350=
21,000.00
12-13
3 Bolt = 60 x 50=
Install electrical and wiring3,000.00
fixtures
37
Anchor
13-15
8
Painting and varnishing
45
(Welding Services) = 333.33333 x 20000=
20,000.00
14-15
2
Final work and cleaning
39
ACTIVITY
EF
LS
LF
TF
FF
C.A
1
3
6
3
9
16
6
15
25
21
24
25
27
22
33
0
8
1
14
10
6
21
14
17
16
18
26
34
25
21
1
10
6
16
16
16
21
26
26
21
26
26
36
26
33
0
7
0
13
7
0
15
11
1
0
2
1
9
4
0
0
0
0
13
7
0
15
10
0
0
1
0
0
3
0
32
26
33
25
33
31
35
45
37
30
39
40
53
41
36
32
36
38
33
40
48
49
42
45
51
36
40
40
40
45
42
51
51
45
53
53
11
7
9
5
0
5
21
12
5
0
12
2
2
4
0
0
0
9
0
5
0
12
TOTAL =
71,000.00
FLOOR WORKS
1st Floor
Tiles =
Adhesive =
Cement =
200 x 280 =
12 x 220 =
12 x 230 =
56,000.00
2,640.00
2,760.00
TOTAL =
61,400.00
REINFORECMENT
Footings
Rebar 12mm Type 1 (Long Bars) = 8 x 325 =
Rebar 12mm Type 2 (Long Bars) = 8 x 325 =
Rebar 10mm Type 1 (Alternating Bars) = 5 x 135=
Rebar 10mm Type 2 (Alternating Bars) = 5 x 135=
2,600.00
2,600.00
675.00
675.00
TOTAL =
6,550.00
Column
Rebar 12mm Type 1 (Long Bars) = 32 x 325 =
10,400.00
Rebar 16mm Type 2 (Long Bars) = 13 x 340=
4,200.00
Tie Wire
= 13 x 90=
1,170.00
TOTAL =
143,910.00
Beam
Rebar 12mm Type 1 (Long Bars) = 24x 325 =
7,800.00
Rebar 16mm Type 2 (Long Bars) = 10x 340=
3,400.00
Tie Wire
= 10x 90=
900.00
TOTAL =
108,900.00
TOTAL =
Beam
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
19,906.15
TOTAL =
Slab
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
24,857.12
TOTAL =
TOTAL =
Beam
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
19,906.15
TOTAL =
Slab
Plywood
Cocolumber
Ordinary Nails
Tie wire #16
TOTAL =
24,857.12
CONCRETING
1st Floor
Ready Mix Concrete (7days curing, 3500 psi)
Pumpcrete
Consumables
TOTAL
MASONRY WORKS
1st Floor External Wall
80,235.00
6" CHB
Sand
Gravel
10 mm rebar
Cement
TOTAL
49,059.58
24,047.83
ACTIVITY
1-2
TIME IN DAYS
NORMAL CRASH
1
1
COST
CRASH
25,000
COST TO
EXPEDITE
300
NORMAL
20,000
2-3
5000
10,000
300
2-4
10,000
15,000
300
2-5
5000
12,000
300
3-5
3000
6,000
300
4-5
11,500
20,000
300
4-7
50,000
65,000
300
3-6
300
5-6
30,000
50,000
300
5-7
10
30,000
45,000
300
5-8
70,000
100,000
300
6-8
10
58,000
90,000
300
6-9
300
7-8
26,000
27,000
300
7-10
10,000
15,000
300
8-10
14
10
60,000
80,000
300
8-9
50,000
95,000
300
8-11
300
9-11
150,000
200,000
300
10-11
40,000
55,000
300
10-13
14
14
50,000
70,000
300
11-12
120,000
130,000
300
9-14
30,000
50,000
300
12-14
15,000
30,000
300
12-13
15,000
30,000
300
13-15
90,000
130,000
300
14-15
6,000
7000
300
TOTAL
994,500
1,370,000
8,400