Vous êtes sur la page 1sur 40

DATE

COMM NO.
APPROVED
APPROVED AS NOTE
NOT APPROVED
INFORMATION

APPROVAL DOES NOT RELIEVE CONTRACTOR


FROM RESPONSIBLE FOR ERROR OR
DEVIATIONS FROM CONTRACT REQUIREMENTS

BY :
LO
DATE
G
OU COMM
T
NO.

DATE :

IFA

Re ISSUED FOR
APPROVAL

IFA

ISSUED FOR APPROVAL

RE
V

STATUS

ISSUE DESCRIPTION

REVIEW

LO
G
IN
A
B
C
I

DISTRIBUTION

PLTU BUNTOK 2x7 MW


CONTRACTOR DOCUMENT REVIEW

13 - 072011
04- 042011
DATE

CIVIL
MECH
ELECT
I&C
SUPPORT
CONTRACTOR
RECORD
WORKING DOCUMENT

EDT

HRD

SGN

HPS

EDT

HRD

SGN

HPS

PREPAR
ED

CHECKE
D

REVIEW
ED

APPROV
ED

PT PERUSAHAAN LISTRIK NEGARA (PERSERO)


UNIT INDUK PEMBANGUNAN PEMBANGKIT DAN JARINGAN
KALIMANTAN
PLTU BUNTOK 2x7 MW KALIMANTAN TENGAH
CONTRACT NO. : 24.PJ/121/PIKITRINGKAL/2010

PT PLN (PERSERO) PUSAT ENJINIRING KETENAGALISTRIKAN


PLN NO.

CONTRACTOR :

PT. TRUBA JAYA ENGINEERING

SUBCONTRACTORJAKARTA,
/ DESIGN
INSTITUTE :
INDONESIA
PLTU BUNTOK 2x7 MW KALIMANTAN TENGAH
JOB NO. T3125

SUBCONTRACTOR DOCUMENT NO :

DOCUMENT NO.

PLTU BUNTOK 2x7 MW KALIMANTAN


TENGAH

T3125-T01-01
ISSUED DATE :
13 July 11

CIVIL ARCHITECTURE & STRUCTURE


JOB NO.

CONTRACT NO.

T3125

PAGE

24. PJ/121/PIKITRINGKAL/2010

REVISIO
N

2 Of 41

SIGNATU
RE

TITLE :

DATE

EPC APPD
APPROVED
REVEIWED
CHECKED
PREPARED

STAGE :

VOLUME 10
CIVIL ARCHITECTURE AND STRUCTURE

2011.7.13
2011.7.13
2011.7.13
2011.7.13

BASIC
DESIGN

DOCUMENT NO :

REV.
T3125-T01-01

TABULATION OF REVISED SHEETS


REVISIONS

SHEET
0

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33

X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

REVISIONS

SHEET
A

41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73

PLTU BUNTOK 2x7 MW KALIMANTAN


TENGAH

CIVIL ARCHITECTURE & STRUCTURE


JOB NO.

T3125

CONTRACT NO.

DOCUMENT NO.

T3125-T01-01
ISSUED DATE :
13 July 11
PAGE

24. PJ/121/PIKITRINGKAL/2010

3 Of 41

REVISIO
N
1

34
35
36
37
38
39
40

74
75
76
77
78
79
80

PLTU BUNTOK 2x7 MW KALIMANTAN


TENGAH

CIVIL ARCHITECTURE & STRUCTURE


JOB NO.

T3125

CONTRACT NO.

24. PJ/121/PIKITRINGKAL/2010

DOCUMENT NO.

T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
4 Of 41

REVISIO
N
1

Contents
Volume No.
Volume 1
Volume 2
Volume 3
Volume 4
Volume 5
Volume 6
Volume 7
Volume 8
Volume 9
Volume 10
Volume 11
Volume 12
Volume 13
Volume 14

Designation
General
Electric Power System
General Layout and Transportation
Thermal Mechanical
Coal Handling System
Ash Handling System
Water Treatment
Electrical
Instrument and Control
Civil Architecture and Structure
HVAC
Hydraulic
Fire Protection
Outline of Construction and Erection

Remarks

DOCUMENT NO.

PLTU BUNTOK 2x7 MW KALIMANTAN


T3125-T01-01
TENGAH
Item no.
Description
No. of
Drawing no.
Item no.
Description
No.
of
Drawing no.
drawing
ISSUED DATE :
CIVIL
ARCHITECTURE
& STRUCTURE
48
Workshop, storage and
laboratory
floor plan drawing
1
T3125-T01-46
24
Coal
shed
structural
1
T3125-T01-2413 July 11
and
section
1/2 column/roof plan
JOB
NO.
CONTRACT
NO.
PAGE
REVISIO
25 49 Coal
shed structural
elevation
axis 1~6floor plan
1 1
T3125-T01-25
Workshop,
storage
and laboratory
T3125-T01-46
N
T3125
24.
PJ/121/PIKITRINGKAL/2010
5
Of
41
26
Coal
shed
structural
1
T3125-T01-26
and
section
2/2 elevation axis A&B
1
Item
Description
No. of
Drawing no.
27no.
floor
plan and elevation
1 1
T3125-T01-27
50 Administration
Gate housebuilding
floor
plan
section
T3125-T01-47
drawing
28 51 Administration
building
and elevation
1 1
T3125-T01-28
Car park shelter
floorsection
plan, section
and
T3125-T01-48
1
Preliminary
Design
Description
11
T3125-T01-01
29
Cooling
tower structural plan and section
T3125-T01-29
elevation
2 52 Main
building
Floor
plan
+0.00
Floor
plan
1
T3125-T01-02
30
Coal
MCC
room
floor
plan,
section
and
1 1
T3125-T01-30
Coal
handling
system
plan
and
section
T3125-T01-49
+3.70
elevation
53
Coal handling system plan and section
1
T3125-T01-49
3
Main building
plan elevation
+11.50 Floor
plan
1
T3125-T01-03
31
tower Floor
structural
plan#1
1
T3125-T01-31
54 Cooling
Motorcycle
shelter floor
plan and
section
1
T3125-T01-50
+7.00
32 55 Complex
housefloor
floorplan,
plan section and
1 1
T3125-T01-32
20 KV pump
switchgear
T3125-T01-51
4
Main building
section
elevation
1
T3125-T01-04
33
Complex
pump
houseand
section
and elevation
1
T3125-T01-32
elevation
5
Main building
column
plan
T3125-T01-05
34
tower structural
structural
elevation
plan#2
11 1
T3125-T01-33
56 Cooling
Emergency
diesel generator
floor
plan section
T3125-T01-52
6
Main
building
structural
beam
plan
TOS
1
T3125-T01-06
35
Cooling
tower
floor
plan
and
elevation
1/2
1
T3125-T01-34
& elevation
EL+3.550
36
Cooling
tower section and elevation 2/2
1
T3125-T01-34
7
Mainfighting
buildingstation
structural
TOS
1
T3125-T01-07
37
Fire
floorbeam
plan, plan
section
and
1
T3125-T01-35
EL+6.850 & EL.+11.350
elevation
8
Main building structural elevation axis 1~8
1
T3125-T01-08
38
Spare
1
T3125-T01-36
9
Mainwater
building
roof plan
and
elevation
axis A
1
T3125-T01-09
39
DM
treatment
plant
floor
plan section
1
T3125-T01-38
10
Mainelevation
building elevation axis B-C
1
T3125-T01-10
and
11
Spare
40
DM
water treatment plant elevation and roof
1
T3125-T01-39
12
Raw water Reservoir & Complex Pump
1
T3125-T01-12
plan
House-Structural
Plan
41
DM water treatment
plant structural floor plan
1
T3125-T01-40
13
Raw
watertreatment
Reservoirplant
& Complex
Pump
1
T3125-T01-13
42
DM water
structural
roof plan
1
T3125-T01-41
House-Structural
Section
(EL +4.00& EL.7.80)
14
Coal
crusher
house plant structural elevation
1
T3125-T01-14
43
DM water
treatment
1
T3125-T01-42
15
Spare
line
16
Spare
44
Workshop and storage structural column and
1
T3125-T01-43
17
Spare
roof plan 1/2
18
Air
compressor
house structural
and2/2
1
T3125-T01-18
45
Workshop
and storage
structuralplan
section
T3125-T01-43
section
46
Weighing bridge floor plan, section and
1
T3125-T01-44
19
Air
compressor house floor plan, section and
1
T3125-T01-19
elevation
elevation
47
Mosque floor plan, section and elevation
1
T3125-T01-45
20
Chimney (chimney is Boiler scope)
21
Dry coal shed floor plan and elevation
1
T3125-T01-21
22
Dry coal shed section and elevation
1
T3125-T01-22
23
Administration building roof plan,
1
T3125-T01-23

VOL 10
Civil Architecture and Structure

PLTU BUNTOK 2x7 MW KALIMANTAN


TENGAH

CIVIL ARCHITECTURE & STRUCTURE


JOB NO.

T3125

CONTRACT NO.

24. PJ/121/PIKITRINGKAL/2010

DOCUMENT NO.

T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
6 Of 41

REVISIO
N
1

Table of Contents
1General .. 1
2Natural condition for setting and main technical data for design .2
3Foundation ...8
4Architectural and structural design for the main building.. 9
5Building (structure) behind the boiler..14
6Electrical building (structure) .. 16
7Building (structure) for conveying coal16
8Building (structure) for ash and slag 17
9Chemical water building (structure) 19
10Hydraulic building (structure) .. .19
11Administration office and other structures

20

PLTU BUNTOK 2x7 MW KALIMANTAN


TENGAH

CIVIL ARCHITECTURE & STRUCTURE


JOB NO.

CONTRACT NO.

T3125

24. PJ/121/PIKITRINGKAL/2010

DOCUMENT NO.

T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
7 Of 41

REVISIO
N
1

12List of main building (structure) for production.22


13Structural design software .28
14. Remain issue

..28

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

General
1.1

Project description
To fulfill the electric energy demand in Central Kalimantan, PT Perusahaan Listrik
Negara (Persero) has planned to build for supplying the electric power for industrial
and public use. The plant will consist of two (2) units, having turbine generator net
output of single figure in the range of 7 MW each. This project is located at Sanggu
Village, Buntok Regency, Central Kalimantan Province. The site area is bordered by
Wendo River in the South, Sanggu Lake in the West, Pematang Kayu River in the
North and forest in the East, approximately 11 KM away from Buntok City. The
geographical coordinate is at S 013949.63.and E 1145484. Topography area,
which will be proposed for power plant is approximately 23.54 hectares developed at
13.67 Ha.
The project site area is hill need cut and fill soil to achieve design ground level,
proposed ground level with height 10.5m from mean river surface. Land
transportation can be done through the main road which are consist of two lane public
traffic, connected from Buntok City to Sanggu Village, as far as 11 km..
No railroad close to the Site area, the nearest airport located at Buntok City for local
Airport and the National Airport located in Banjarmasin and Palangkaraya City.
No dedicated harbor or equipment unloading facilities at the Site, The closest
available commercial Sea Port is at Banjarmasin Capital City.

1.2

Design basis

1.1.1 Information provided by the owner


The contract agreement no.24.PJ/121/PIKITRINGKAL/2010 for coal-fired steam
1. Power plant project PLTU Buntok 2x 7MW (net) Central Kalimantan
2. The contract discussion agreement (CDA)
1.1.2 Standard and criteria
Related standard, code, criteria and regulation as below:
Ite
m
no.
1
2
3

Standard no.
ACI 318
ACI 350
AISC

ASTM

AASHTO

Name of standard
Building Code For Reinforced Concrete
Concrete Sanitary Engineering Structures
American Institute of Steel Construction
American Society for Testing and Material
ASTM Standard and Specification s for Various
Construction Materials
American Association of State Highways and
Transportation Officials

Page 1

Remar
k

PLTU Buntok 2X7MW

Ite
m
no.
6
7
8
9
10
11
12

Vol. 10. Civil Architecture and Structure

Standard no.
ASCE
AWS
JIS
SNI 03 1726 2003
SKBI-1.3.53.1987
UDC 624.042
SNI 03-17292002
SNI 03-28472002

Name of standard

Remar
k

American Society of Civil Engineers


American Welding Society
Japan International Standard
Standard Nasional Indonesia
Tata Cara Perencanaan Ketahanan Gempa Untuk
Bangunan Gedung
Pedoman Perencanaan Pembebanan Untuk Rumah
& Gedung
Tata Cara Perencanaan Struktur Baja Untuk
Bangunan Gedung
Tata Cara Perhitungan Struktur Beton Untuk
Bangunan Gedung

Note: There are some standard and code will follow to China standard (GB standard,
Where applicable)

1.3

Design principle

1.1.3 Building and structure shall have structural design in accordance with the appropriate
type of structure being selected to ensure the availability of advanced technology,
safety and applicability, economy and quality.
1.1.4 With process production being guaranteed, the type of structure shall take into
account the painting, fire-resistance, vibration resistance, explosion resistance,
geological condition, construction technology, etc. and shall meet the requirements
on structural intensity, rigidity and durability.

Page 2

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Natural condition for setting and main technical data for design
2.1

Location

Page 3

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

This project is located at Sanggu Village, Buntok Regency, Central Kalimantan


Province. The site area is bordered by Wendu River in the South, Sanggu Lake in the
West, Pematang Kayu River in the North and forest in the East, approximately 11 KM
away from Buntok City. The geographical coordinate is at S 013949.63.and E
1145484. Topography area, which will be proposed for power plant is approximately
23.54 hectares.
.
2.2

Hydrometeorology
Indonesia falls into typical tropical rainforest climate, characterized by high
temperature, much rain, low wind, big humidity, with cumulative annual temperature
of 25~270C

on an average and annual rainfall of over 2000mm. Generally, dry

season falls on April to September while rainy season falls on October to March in the
following year.
The project area, as part of Central Kalimantan Province, has a tropical climate
characteristic, where rainy season and dry season continuously change every six
months. Average temperature is 26C 29C and average rainfall is 2.826 mm/yr.
Maximum wind speed 6 knot = 11,2 m/s with dominant wind blows is 34.4% from
west
2.3

Engineering geology

1.1.5 Soil Investigation


The project site is hill and elevation varies +100.0m to +120.0m above local reference
elevation need cut and fill soil to achieve Design Ground Level.
Pre Soil Investigation Report:
The soil investigation consisted of 2 (two) points boring machine of 20m depth each,
6 (six) points hand boring (SPT) of 10 m depth each and 15 (fifteen) points of Cone
Penetration Tests (CPT) with capacity 250 kg/cm2. For ensure the soil characteristic
there are additional soil investigation with consist of 3 points depth boring until SPT
N>=50 and 3 points of cone penetration test (CPT) with capacity 2,5 ton
Final Report Soil Investigation (part of Site Investigation Report submitted)
The soil investigation consisted of 12 (twelve) point drill holes (SPT) of 20m 40 m
depth each, 3 hand bores and 8 ( eight ) point of Cone Penetration Test (CPT) with
capacity 250 kg/cm2.,refer table-2 and the recommendation and analysis of results
are inclusive on the report.
1.1.6 Bearing layer
According to the pre investigation report, the hard soil between 5m~25m depth with

Page 4

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

N >50.
1.1.7 Soil characteristics.
According to the site investigation at 2 location (DH1 at BOP and DH2 at Power
Block), the SPT test result, laboratory test result, the soil bearing layer have
significant different. The physical character and engineering character explained as
following:

Table 1 Soil Properties


Unit

Depth

Soil Description

DH1
.

20m

Depth until 9m composed Fine Sand with SPT-N 8~24; depth


until 15m is stiff clay with SPT-N 9~11; depth until 20m silty sand
with SPT-N 50

DH2
.

20m

Depth until 4m composed Fine Sand with SPT-N 19 and below


4m depth composed sand with SPT-N >30~50

Table 2 According to the Final Soil Investigation:


Unit

Depth

Soil Description

DH3.

34m

Depth until 2.5m very dense fine sand with SPT-N 51~53; depth
2.5 ~ 4m is very dense silty sand with SPT-N 51; depth 28~34m
very dense fine sand with SPT-N 50

DH4.

20m

Depth 3.3 ~ 3.7 very dense silty fine sand with SPT-N 50,
3.7~3.8 m is dense fine sand with SPT N40; depth 12.5-17
very dense to coarse sand with SPT-N >50

DH5.

44m

Depth 4.3~8.4 very dense silty fine sand with SPT-N 41; depth
40 ~ 42m is very dense fine sand with SPT-N 51; depth 42~44m
very dense coal with SPT-N 50

DH6.

36m

Depth 2 ~ 4 dense fine sand with SPT-N 44, 30~36 m is very


dense fine sand with SPT N40; depth 12.5-17 very dense fine
to medium sand with SPT-N 50

DH7.

36m

Depth until 4 ~ 8 very dense fine sand with SPT-N 44; depth 32 ~
36m is very dense fine to medium sand with SPT>N 50

DH8.

40m

Depth 6 ~ 8 very dense silty fine sand with SPT-N 44, 18~22 m is
dense medium sand with SPT N36; depth 32-40 dense fine to
medium with SPT-N 50

DH9.

30m

Depth 12 ~ 14 dense silty fine sand with SPT-N 41; depth 24 ~


30 m is very dense sand with SPT-N 50

DH11
.

38m

Depth 32 ~ 38 dense to very dense sand with SPT >N 50

DH12
.

20m

Depth 16 ~ 20m very dense to medium sand with SPT-N 51

DH13

38m

Depth 4 ~ 8 dense medium to coarse sand with SPT-N 51,


Page 5

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

34~38 m is very dense medium sand with SPT-N 50

DH14
.

44m

Depth 40 ~ 44 very dense fine to medium sand with SPT-N 51

DH15
.

32m

Depth 26 ~ 32 very dense fine to medium sand with SPT-N 51

1.1.8 Condition of underground water


The elevation of ground water level in the bore holes varies from 7.00~8.00 m below
the existing ground surface.
The corrosive character of underground water to concrete and steel in concrete base
on the experience used special portland cement for underground water level.
1.1.9 Background on earthquake and geology ( Peraturan Gempa SNI 03-1726-2003 )
Base on Indonesia earthquake zone divided, Zone = 1
Earthquake acceleration, G = 0.03g
Important factor for building structure, I = 1.5 (Faktor Keutamaan untuk Pembangkit
tenaga listrik)
1.1.10 Judgment on liquid faction
The occurrence is mainly due to soil layer of plant site is good. In pre investigation
report, it seems it will not liquid faction.
1.1.11 DATA SUMMARY
DESCRIPTION
1. height above sea level (MSL)

VALUE
10.5
m

2. Rainfall (for last 10 years)


a. Maximum
b. Average
3. Wind Data (for last 10 years)
a. Maximum Velocity
b. Design wind velocity
c. Direction (dominant)
4. Relative humidity (for last 10 years)
a. Maximum
b. Average
c. Minimum
d. Relative Humidity for design propose
5. Ambient air temperature (for last 10 years)
a. Average dry bulb
Page 6

481mm/month
140.5mm/month
11.2m/s (6 knots)
120 km/hours
W
98.3 %
84.3 %
63.8%
85 %
23~30 C

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

DESCRIPTION
b. Ambient temperature for design propose
6. River water tidal
a. High Water Level (HWL) at 100 year
rainfal
b. Mean Sea Level (MSL)
c. Low Water Level (LWL)
2.4 Main design parameters

VALUE
30 C
+97.87.m
+94.5 m
+94.15 m

Life limit by design: 20 years


Basic wind pressure: 0.64kN/m2 (Basic wind velocity -120km/h)
Seismic design grade, Zone ; 1
Basic seismic acceleration by design: 0.03g
2.5

Material

1.1.12 Concrete intensity class


For pre-stress concrete structures ( e.g spun pile, sheet pile )

: C60

For important structures (steel liner foundation, Turbine

: C30

Generator Pedestal, Steam Turbine Building & foundation,


Boiler Structure Foundation, Stack Foundation and CW
Pump House, Cooling Tower Structure and Foundation
For all concrete work in common buildings and structures of

: C25

Power Plant, unless otherwise specified


For lean concrete as specified and for un-reinforced concrete

: C15

or otherwise noted
a) Impermeable concrete: C30 class, mixed with expanding agent of 10% in cement
usage, which could be appropriately selected according to structural stress and
characteristics.
b) Secondary grouting: utilized shrinkage grouting material, fine gravel concrete with
one intensity grade higher than major concrete.
c) Structural durability of concrete:
Cement type - I shall be used for above grade work
Cement type - II for cooling tower and basin , foundation, structures below grade
Cement type - V for all structures direct contact with sea water (NA)
1.1.13 Reinforced bar
a) Common reinforcement (non pre-stressed reinforcement) used in concrete structure
shall comply with the requirement of ASTM A615 or SNI Standard.
b) Pre-stressed reinforcement: it is appropriate to utilize stress-relief steel wire, steel
strand and heat treatment reinforcement as well .
Page 7

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

c) Unless otherwise specified, reinforced bar with diameter <12mm utilize Grade BJTP
24 and for diameter 12mm utilize Grade BJTD 40.

1.1.14 Steel
a) ASTM A36

use for all structural steel , which quality shall comply with the

requirements of Carbon Steel for Structural SS400 and Low-alloy High-tensile Steel
for Structural SM490 respectively that cover the light roof structure and other lattice
structure .
b) Section steel will be selected for the steel structure in priority. For hot-rolled H
section steel, which is not applicable, welded H section may be considered. Hotrolled section shall have the cross-section characteristics in accordance with JIS G3192 and BS 4360 GR 43A.
1.1.15 Cement
Generally, ordinary Portland cement will be used or slag Portland cement and
sulphate resistant cement with intensity class of I , II and V(NA)
1.1.16 Aggregate
Utilize medium coarse sand and crushed gravel.
1.1.17 Wall
Red bricks with size of 110mmx55mmx230mm or concrete hollow with dimension
390 x 190x100 may be considered.
1.1.18 Mortar
Mortar shall conform to the applicable requirements of ASTM C270.
1.1.19 Welding
The codes and standards of the following organizations, Subsection "Codes and
Standards" are specifically applicable to the design, manufacture and testing of the
work included in this Specification:
ASTM

American Society for Testing and Materials.

AWS

American Welding Society.

ELECTRODES
Except as otherwise specified, all welding electrodes shall conform to the applicable
provisions of the AWS Structural Welding Code AWS D1.1 For steels with special
properties, such as resistance to brittle fracture, corrosion resistant steels, stainless
lad steels and stainless steels, the recommendations of both the steel and electrode
manufacturers shall be secured for each specified steel and each specific use.

Page 8

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

1.1.20 Bolt
a) Ordinary bolt
The Ordinary bolt should have the performance to ASTM A36, washer should follow
to ASTM F436 one washer under the bolts head and one under the nut.
b) High-strength bolt
The High-strength bolt should have performed to AISC specification for structural
joints using ASTM A325. Bolts and nuts use the following materials unless otherwide
indicated for bolts sizes use A325, Type 1 steel, one washer under the head and one
under the nut, whichever it the element turned in tightening.
c) Anchor bolt
ASTM A36 for threaded rods and ASTM A307 for headed bolt and for all nuts. Anchor
Bolt should be adopted to the foundation of heavy loading or heavy dynamic loading.
The material of anchor bolt for equipment shall be determined by the related
discipline. Anchor bolt shall be provided with double nuts and washer.
1.1.21

Anti-corrosive measure of building (structure)


Located at the coastal region, the proposed plant is exposed to considerable saltmist corrosion. Exposed steel structure is advised to be applied with such treatment
as hot galvanizing, zinc spraying + sealing paint, application of epoxy zinc rich paint.
For reinforced concrete structure, it is required to increase the thickness for
reinforcement cover, enhance the concrete intensity grade, inrease the antipenatrative capability, ensure the construction quality for the proposed durability. The
foundation shall be properly painted at the area exposed to underground water
change. Foundation surface may be applied with high build epoxy bituminous paint
in two coatings.

2.6

Earthquake-resistant design
Construction field for the project is defined as Base on Indonesia earthquake zone
divided, Zone = 1, the basic seismic acceleration design is 0.03g. Earthquakeresistant design is carried out according to the above parameters plus Guideline of
seismic restrain for building construction, Indonesian standard (SNI.03-1726 2003).

Page 9

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Foundation
Main Power building for this phase of project 0.00m is equal to absolute altitude
103.3m average
According to the geological survey information in feasible study report, the field
ground, the ground foundation plan is initially prepared below.
Due to the ground up level is filled with medium dense sand soil, the estimate support
force is about 160kPa. Consider MW main equipment load is not too big, to use
nature foundation should be enough to meet the requirement. So the nature
foundation is first to be considered and it will save the cost.
The soil character is good, and mainly makeup by the sand soil, under the preliminary
analyze, it does not need to do the soil improvement, use backfill the soil according to
the requirement.
If part the ground can not meet the requirement, strong rammer method could be
used to stronger the ground with little cost.
Main buildings/structures of whole plant adopt natural ground and independent
reinforced concrete foundation. Over excavation is strictly prohibited for foundation pit
and bearing layer is strictly prohibited to disturb when foundation trench is excavated
for buildings/structures in plant area based on natural ground. Soil analysis for trench
bottom shall be intensified when foundation trench is excavated to design altitude.
Careful study shall be given to the difference between soil qualities of trench bottom
and bearing layer suggested by investigation report, and section of foundation trench
with irregular soil quality, the proper measurements should be taken. Over-excavated
foundation layer shall be filled with graded sand-gravel or site undisturbed sand
without organic substance.
Main workshop foundation is considered to adopt independent reinforced concrete
foundation. Most of wall foundation adopts ground beam, few of them adopt concrete
foundation. Other buildings/structures adopt independent foundation or strip
foundation. Other foundation treatment measures could be adopted if the
requirements of construction drawing could not be met.
Piling foundation are advised to adopt for boiler & stack foundation due to larger load.
According to actual situation, further foundation treatment measures shall be taken
for area of coal yard & oil tank where larger and concentrated heaped-load has.
Before construction drawing is began to designed, it is advised to compile proper plan
of foundation treatment and style of foundation according to load distribution in each
unit engineering.

Page 10

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Architectural and structural design on the main building


4.1

Architectural design for the main building

1.1.22 Layout of the main building


Main Power building may be arranged in sequential configuration, i.e. Steam turbine
house Boiler Island (boiler house to be separately designed by the manufacturer).
a

Turbine house
Turbine house may have a lateral span of 22.00m and total longitudinal length of
49.0m (to be made of steel structure and no expansion joint), with pillar spaced in
7.0m and two steam turbosets inside. Steam turbine house is divided into ground
floor and operation floor with vertical elevation of 0.00m, 7.00m floors respectively.
0.00m floor is provided to setup thermal machine and auxiliary machine, etc.
Maintenance space is provided between two machines to satisfy the need for
maintenance of steam turbine. (A), (B) shaft at 7.00m floors may allocate a portion of
platform to facilitate the maintenance and traffic. Island platform is considered for the
foundation of steam turbine generator and heater platform so as to prevent vibration
load from transferring to the factory building. Steam turbine is oriented in longitudinal
arrangement with the machine head toward the extension end. Inside the steam
turbine house, there is a bridge crane with lifting capacity of 20t or 10t, span of
15.00m (, and elevation for crane beam-rail roof being 14.50m. Crane driver room is
located at the side of (B) row of pillar. The crane may travel freely within the operation
area.

Deaerating bay
Deaerating may have a span of 7.0m 3 stories vertically, elevation of 0.00m, 3.70m,
7.00m (operation floor), 11.50m (deaerating tank); pipe layer room may be
considered at local 3.70m .
0.00m may setup Electric distribution room and Battery room, staircase, etc 7.00
floor may include the central control building (shift change room and field house)
between (3)-(9) shaft ,toilet,Instrument rack room, etc. between (1)-(2) and (9)-(12)
shaft11.50 floor may consider two deaerators floor.

Boiler house
Boiler Island is arranged in two islands pattern with unequal distance of columns,
longitudinal length of 17.8m and lateral length of 9.75m. Boiler frame is formed in
steel structure. Boiler frame, boiler top cover and steel beam for boiler operation
platform shall be designed by the boiler manufacturer.
Pathway in front of the boiler shall have a span of 3.9 m. At elevation 7.00m, there
are platform connecting the boiler to deaerating bay.

Page 11

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

1.1.23 Traffic arrangement


a

Horizontal traffic
At the side of B row of pillar in deaerating room, there will be main longitudinal
pathway with width bigger than 1,6m. At A row of pillar side in steam turbine house
and in front of the boiler platform, there is a secondary longitudinal pathway with
width bigger than 1,8m. Both ends of main longitudinal pathway is accessed to the
outer exit of power building or staircase. At both ends 0.00m, 7.00m, there are
lateral pathways in place to allow easy access from steam turbine house to
deaerating and boiler house. Access of main equipment to steam turbine house may
pass through the maintenance yard in the middle of steam turbine house and fall way
at each floor in the top. Access to maintenance yard may be equipped with electric
rolling-opening steel door.
In front of the boiler platform 0.00m , there is longitudinal pathway with width 4.0m .

Vertical traffic
At fixed end and extension end, there are ladders/stair connecting to each platform,
which are provide to meet the requirement on production and safe evacuation in case
of fire. In steam turbine house, there are steel ladders for site inspection tour installed
at the heater platform for each turbine, via which you may go to the middle floor and
operation floor.

All entrances/exits, ladders and walkway for platform connecting each floor are equipped with
conspicuous signs showing the direction and guidance of evacuation. Turbine house
and Boiler house will each have an elevator
1.1.24 Day lighting and ventilation
Lighting in steam turbine house and deaerating shall be made available in a
combined way of natural and manual lighting. The whole factory building may be
equipped with rectangular windows in dot arrangement. Roofing for steam turbine
house may be provided with light-absorpting shade in the top to increase the
illumination over the operation floor in steam turbine house. Mechanical ventilation
may be enough for steam turbine house. Mechanical exhaust blower may be installed
at the roofing. Natural ventilation is provided across the deaerating with properly
distributed air flow.
1.1.25 Water-proof, drain and thermal insulation
Roofing is properly inclined toward roof gutter to facilitate the collection of rainwater.

Page 12

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Via rainwater pipe, rainwater is routed to the drainage system in the plant. Synthetic
polymeric water-proof coiled material made of chlorinated polyethylene (CPE) may be
applied for roof and floor against water ingress. Polystyrene insulation board or local
insulation material may be applied for thermal insulation at roof and floor.
1.1.26 Fire- and explosion-resistance
Ladder and pathway shall be properly arranged. Each structural element for main
power building shall be delivered in compliance with fire-proof criteria:
Main power building (including steam turbine house, deaerating, boiler island) shall
have Class II fire-resistance. Fire hazard is classified as IV.
Fire door shall be installed for pathway door between steam turbine house and
deaerating that for distribution room in main power building, cable sandwich,
enclosed staircase.
Fire wall shall be installed between steam turbine house and deaerating with fireresisting limit of 1 hour, while all other non load-carrying wall shall have fire-resisting
limit of 0, 25 hour.
Steel elements around oil tank or oil pipe in steam turbine house shall be painted with
fire-retardant coating. Load-carrying steel structure shall have fire-resisting limit of
1.0h and non load-carrying structure 0.5h. Fire-retardant paint shall be applied on
steel roof truss above oil tank in steam turbine house, with fire-resisting limit of 0.5h.
1.1.27 Housekeeping and sanitary facilities
Since housekeeping and sanitary measure are designed for the designated purpose
and the technicians often appear at main factory building and operation floor, the
toilets for man and woman could be considered at fixed end of deaerating, staircase,
and zero meter and operation floor so as to be used for maintenance technicians.
Water flushing may be provided zero meter of main power building, ditch may be
provided to access to outside coal-water treatment unit.
1.1.28 Building enclosure
Outer wall for steam turbine house and deaerating may be covered with laminboard
(for the purpose of insulation, heat resistance, reduction of noise, etc.). The
framework may contain filler wall filled with light partition wall (light building blocks of
aerated concrete or equivalent local light building blocks). All doors and windows are
made of aluminium alloy or plastic-steel. Distribution room may have door and
window of louver and PVC door is applied to the toilet.
1.1.29 Architectural style

Page 13

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

For the purpose of safety, applicability, economy, with adoption of architectural design
philosophy and in conjunction with local style of building, we are commit to create and
build an elegant and practical main factory building with the taste of the times and in
line with the local culture of architecture.
Fixed end is properly staggered with defined zoning. Adoption of substantiality and
virtuality design, material application, colorful decoration, etc., will create an art
background for architectural composition for the whole plant.
Outer vertical view and color for main factory building has fully taken into account the
proper consistency of environment in the vicinity. Lucid and lively color may be
painted on main factory building. Main color prefers light-color with color strip in some
areas to make the vertical view vivid.
Outer wall may be applied with washable hydrophobic paint to ensure the outer wall
clean.
1.1.30 Arrangement and planning for underground facility
Boiler house0.00m may consider water flushing to be drained to the ditch nearby.
Underground ditch for main factory building and equipment foundation shall be
arranged according to the process requirement, with channel and pit poured with
waterproof concrete and damp-proof course to eliminate or reduce the ingress of
underground water. Industrial pit and ditch are formed without interference. In case of
meeting together, the principle to be observed is wet one before dry one, hard one
before soft one, natural flow before pressure one. And, drainage system is isolated
each other to prevent leak. Waterproof measure shall be put in place at ditch
intersection, expansion joint to ensure no water accumulation in the ditch.
4.2

Structure design for the main building

1.1.31 Structural system for the main building


a

Lateral vertical view system


Main factory building shall be laterally arranged with steam turbine house deaerating boiler house. Framework system is formed with A row of pillar roofing
beam for steam turbine house - deaerating. Main framework is connected to the
foundation in rigid manner.
Boiler frame and boiler top cover shall be designed by the boiler manufacturer.
Platform structure in front of the boiler will be overlapped with C row of pillar and side
pillar of boiler frame, with the base utilizing sliding connection. Sufficient vibrationproof slipping clearance shall be provided.

Longitudinal vertical view system


Longitudinal vertical view for main power building may utilize framework support

Page 14

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

system, which will be equipped with rigid compression bar at the top of pillar and
crane beam. Cross beam for other floors shall be subject to framework structural
element control, ie. to be calculated based on bending, that is rigid bar structural
control.
End support shall be installed at the 1st pillar at both ends of main power building,
which shall be through up and down and work together with lateral support of lower
chord below the roof truss.
c

Plane system
Platform for each floor and roof for deaerating may be structured in combined steel
beam cast-in-place concrete slab, and in checkered steel plate or steel grating plate
for some areas. Roofing will be formed in structural sloping. Use lateral framework
beam as main beam with secondary beam arranged longitudinally (basic distance of
2m).
Platform in front of the boiler is structured in combined steel beam cast-in-place
concrete slab.
All steel secondary beams and cast-in-place slab may be connected with peg or
shear nail.

1.1.32 Gable wall for steam turbine house


Gable wall end for steam turbine house are all made of steel and enclosed with light
structure. Connection of gable wall to outer pillar of steam turbine house, framework
of deaerating coal bunker to roof truss shall be made available in a manner able to
transfer the horizontal loading and enable free settlement.
1.1.33 Roofing system of steam turbine house
With colourful roofing, steam turbine house is built in mono steel beam roof with span
of 15m with support arrangement in compliance with related criteria.
1.1.34 Crane beam system
Crane beam in steam turbine house is provided with H steel section beam with a
span of 7.0m and crane load of 20t or 10t, which is defined as light-duty system. With
flat plate or extended flange girth as base, there is no auxiliary girder. Lateral stress is
met by strengthening the upper flange girth.
1.1.35 Structure of coal bunker
According to process design, the coal bunker is including in the boiler system.
1.1.36 Support for steam-turbine generator
The support for steam-turbine generator is built in cast-in-place reinforced concrete
framework with concrete block foundation.
1.1.37 Miscellaneous

Page 15

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Heater platform shall be structured in steel framework. Settlement joint shall be


considered between main framework and Steam Turbine Island. RC Foundation for
plate-type is proposed.
1.1.38 Design on earthquake resistance
According to Section 2.6, main power building is classified as Important building, with
calculation on earthquake influence and measure on earthquake resistance to be
considered as per seismic design intensity (Zone =1,G= 0.03g).
Main power building is formed laterally in framework in rows and some axis are
provided with inter column support. Longitudinal ABC 3 rows of pillar are provided
with longitudinal inter column support in 2 rows at the appropriate position at both
ends. For roofing, there are lateral and longitudinal supports in response to inter
column support. Floor system is formed with combined structure of reinforced
concrete cast-in-place floor with steel beam via peg. Nodes for lateral and longitudinal
beam/pillar frame shall be rigidly designed, forming the 2 nd earthquake-resistant
structure in addition to inter column support. All these measures are made available
to enable the building complete in structure, excellent in ductility, uniform in stiffness.
At the connection of platform structure in front of the boiler and coal conveying trestle
and deaerating, leg and sliding connection are considered at C row of pillar so as to
setup sufficient sliding clearance for earthquake resistance and reduce the influence
from the earthquake.
1.1.39 Measure to avoid heterogeneous settlement
Since the soil up level is make up medium sand soil, the support force is about
180kPa, The site is flat and average, soil condition is good.
In order to prevent heterogeneous settlement in structure, settlement joints are
provided at areas between main framework structures, foundation of Steam Turbine
Island, steel structure of platform for heater (considerable difference on counterforce
at foundation base). For those unable to be disconnected, in addition to measures
taken to increase the structural rigidity in the top, you shall try to maintain the same
counterforce at foundation base or utilize the combined foundation.

Page 16

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Building (structure) behind the boiler


5.1

Stack
Two boilers may share a steel stack with outlet inside diameter of 2.5m and 40.0m
high. The stack is structured in single-drum steel structure and the foundation is
adopted piling foundation, but the final will be determined after soil investigation
report. Flue outlet shall be provided each at both sides of chimney. Heat insulation
and antisepsis on inner wall method : Brush coal-asphalt anti-corrosion dope on
the inner wall of steel. The inner liner adopts anti-acid terra-cotta and anti-acid
puddle, and perlite plate for heat insulation method : liner of chimney is design
according to electronic power industry standard and code, using light dense anti-acid
lining material, corruption-proof paint will be painted to inner wall of the chimney.

5.2

Flue
Reinforced concrete structural support and steel flue are proposed. Fire-retardant
bricks are used inside. Air thermal buffer is applied. On the top of flue, there is cast-inplace acid-proof and thermal-proof concrete corrosion resistant coating.

5.3

Support for steel flue, support of maintenance induced draft fan, foundation of ESP
Support for steel flue and support for maintenance of induced draft fan are structured
in cast-in-place reinforced concrete framework or steel framework, with independent
foundation. Support for ESP will be steel structure to be supplied by the manufacturer,
with independent foundation in reinforced concrete.

5.4

Fuel pump house


Fuel pump house is a reinforced concrete frame, with strip foundation in reinforced
concrete. Oil tank is laid on the ground and protected with sand nearby. Oil tank farm
is baffled with brick wall to meet the requirement on fire criteria.
Oil pit for accident is built in a structure of cast-in-place reinforced concrete.
Foundations for drain tank and drain pump are built in a structure of reinforced
concrete.

5.5

Pipe rack
Pipe rack support across the plant may be built in H steel column, beam or steel
truss. The support over the road is built in steel truss, with independent foundation in
reinforced concrete.

Page 17

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Page 18

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Electrical building (structure)


6.1

Central control room


Not specifically set up a separate. The control building but is the arrangement in
Deaerating bay.
Central control room shall have Class II fire resistance and Category IV fire hazard.
Distribution room shall have Class II fire resistance and Category III fire hazard.
Transformer room shall have Class I fire resistance and Category III fire hazard.
As per the related requirements, central control building shall be equipped with antisliding and anti-electrostatic ground tile. Anti-electrostatic free access floor shall be
installed in electronic device room, with 300mm beyond the floor.

6.2

Building and structure beyond Column A in the main building


Beyond Column A in main factory building, there is Electric-net Control Building,
which is reinforced concrete structural house of single storey with plain dimension of
24,7mX6.5m. The rest is foundations for switch station and transformer, structured in
reinforced concrete. According to the electrical discipline, it is required to leave such
facilities for maintenance purpose as rail, oil drain.

Page 19

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Building (structure) for conveying coal


7.1

Building (structure) for conveying coal include general building for conveying coal,
trestle for conveying coal, crushing building, Transferring station and dry coal shed,
etc.

7.2

Control room for coal conveying


There are distribution room, program-controlled room for conveying coal, etc.
It is steel framework or concrete structure with support. There are girt + colourful
board for roofing and external protections, and light partition for internal partition, with
independent foundation in reinforced concrete.

7.3

Trestle for conveying coal


Coal-transferring trestle: the long span trestle is steel structure framework supporting
and the upper part is steel truss with no enclosed. The short span trestle adopts steel
framework and no closed upon the bridge face.
According to process requirements, the trestle shall not be closed for both sides
except for electronic belt scale. Belt conveyer itself shall be equipped with belt cover.
Protections may choose colour profiled steel sheet. Walkway may be made of angle
walkway beam + grating.

7.4

Transferring tower
Each transferring station is made in structure of steel structure framework and
cladding walls and pile foundation.

7.5

Coal crusher house


For the purpose of process requirement, drainage for floor and roof and fireresistance for the building shall be made available to satisfy the related criteria and
regulation. It is structured in site-casting concrete framework and walls with concrete
hollow brick and independent foundation. Coal crusher may be based on independent
reinforced concrete platform to eliminate the influence of vibration on main structure.
Each arrangement shall meet the process requirement and drainage for floor and roof
and fire-resistance for the building shall be made available to satisfy the related
criteria and regulation.

7.6

Dry coal shed


The Coal shed is design to accommodate the coal live storage for 30 days.

Page 20

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Concrete frame structures for dry coal shed with lipped channel girt and corrugated
steel as roofing. Wall and roof above the lateral beam are baffled with single-layer
colour board. Pile foundation is shaped in independent foundation in reinforcement
concrete.
On the both sides of coal pile, there is barrel-drain.

Page 21

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Building (structure) for ash and slag


8.1

Air compressor house


Combined design shall be applied to air compressor house, electrostatic precipitator
and control room for ash removal system (including electrical distribution room and
ash net precipitator control room) with plan dimension of 1015m in 2 parts. A part is
air compressor house and another part is electrostatic precipitator and control room
for ash removal system.
It is structured in Cast-in-place concrete structure, which is equipped with girt +
colourful board for roofing and external protections, and light partition for internal
partition and independent pile foundation.

8.2

Ash silo and slag silo


Ash silo, slag silo and related brackets are all in steel structure. Taking the driveway
into account, it will install vertical supports for some inter columns. There is one ash
bin, which is designed with max. I.D. of 4.0m and volume of 25m 3. max loading of 20t
during operation. There is one slag bin, which is designed with max. I.D. of 4m and
volume of 25m3, max loading of 24t during the operation.

8.3

Transferring bracket for ash and slag


Scraping plate type conveyor and its bracket shall be designed by the manufacturer
with the bracket adopting independent foundation.

8.4

Ash yard and slag yard


According to the owners request, it is required to arrange a temporary ash and slag
stockpile at the east and north end of the plant each. In conjunction with general
utilization of ash, the stockpile shall be built in a size big enough to store ash and slag
for 5 years and area is 5.950.

1.1.40 Ash and slag dam


The dam, designed based on rammed-earth wall , may function as the fence as well.
The top of dam is plastered with cement grout for sloping and installed chunk glass,
which will be covered with five-wire net of 6 m high.
Drain ditch for ash and slag shall be considered one meter outside the dam, which
will be transferred to the wastewater treatment station before discharge on
specification.
1.1.41 Ash yard and slag yard

Page 22

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Ash and slag stockpile shall be first cleanout according to the strike of land
configuration, followed by excavation up to the clay layer for levelling and tamping
and then installation of HDPE geomembrane. Geomembrane shall be placed properly
with joint generally adopting adhesion and hot welding and being width not less than
100mm for water resistance. Geomembrane shall be covered with sand and gravel
protection on the surface.
Main blind ditch shall be arranged longitudinally along the dam with cross section of
ditch of 600400mm. Secondary blind ditch may be arranged vertically along the dam
with cross section of ditch of 500400mm and distance of 50~70m. Crushed gravel
with diameter of 20-50mm shall be filled in blind ditch and reversed filter of sand and
gravel with 300mm in thickness may be applied on the back of wall and blind ditch.
Loading capacity for the ground of ash and slag stockpile shall be considered based
on fak=160kPa.

Page 23

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Chemical building (structure)


9.1

Chemical Water Building


Chemical water building will be provided with 1 storey floor. Chemical water building
shall be designed with proper anti-corrosion measures in place.
It is structured in Cast-in-place concrete structure in masonry structure, exhibiting
reinforced concrete floor, color profiled steel plate for roofing, light partition for
partition inside, independent reinforced concrete foundation with pile, strip foundation
at the bottom of wall.

9.2

Steam-water sampling room


Steam-water sampling room is arranged in deaerating bay.

9.3

Dosing room
Dosing room is arranged in deaerating bay 3.70m floor, between (1)-(3) shaft.

Page 24

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

10 Hydraulic building (structure)


10.1 Circulating water pump house
Water supply to the power plant will be provided, which is located south of the plant,
flow from north to south. According to the process arrangement, the project will build
a water intake pump house on the river bank. The structure is formed in cast-in-place
reinforced concrete. The pump house will be equipped with small crane and electrical
hoist. Roofing and external protections will be covered with girt + colour board while
internal partition with light partition.
10.2 Cooling tower
The cooling water is concrete structure with height 11m, length 43.510 and width
13.14m connected with concrete pump house dimension length 18.8 and with 13.34
height 10m included chemical dozing, storage room, power distribution room
10.3 Drainage system
Drainage open channel, drain outlet are included, which are all built in reinforced
concrete structure.
10.4 Complex water pump house
General water pump house may have a dimension of 29.66.0m, with net height of
4.8m for single storey. The pump house is built in light steel structure with girt +
colour corrugated steel adopted for roofing and external protections, light partition for
internal partition (strip foundation at the bottom of wall), independent reinforced
concrete foundation with pile.
10.5 Wastewater treatment workshop
Wastewater treatment workshop may include wastewater regulating reservoir, effluent
regulating reservoir, slurry concentrated pit, settling pond and shift-on-duty room,
distribution room, equipment room, and other single-storey room, covering a total
area of about 230 m2. The foundations for the pit and equipment are built in reinforced
concrete in raft foundation. Single-storey room is built in light steel structure with
purlin + color corrugated steel adopted for roofing and external protections, light
partition for internal partition (strip foundation at the bottom of wall), independent
reinforced concrete foundation with pile.
10.6 Other hydraulic facility

Page 25

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

Other hydraulic facility may include water reservoir for operation and firing, coal water
and ash water treatment pit, siphon well, drain open channel, drain outlet, etc. There
may be cast-in-place reinforced concrete framework and bent structure, reinforced
concrete box-type pit structure to be taken according to the process arrangement.
According to process requirements, underground ditch, pit will take appropriate
measures against spill and corrosion.

Page 26

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

11 Administration office and other structures


11.1 Administration office building & Canteen
Administration office building shall be designed based on the owners requirement
and management functions for those in the domestic power plant of the similar size.
The building is sized 31.0 13.5m in 1 storey and has construction area of 418.50m2.
Rev 1
It is structured in reinforced concrete framework, which contains reinforced concrete
floor and girt + colourful board for roofing and external protections, and light partition
for internal partition. There are independent reinforced concrete foundation with pile
and strip foundation at the bottom of wall.
11.2 Gate and security guard room
The main gate and security room operates plot area is 5.0 m x 5.0 m, which is
concrete framework and walls with concrete hollow block.
11.3 Storage & Workshop & Laboratory
Storage & Workshop, located at the East of Chemical Water Building. Warehouse
covers an area of 12.0 m X 9.0 m. The workshop adjacent with warehouse covers an
area of 18x9 m, which is built in steel structure with natural ground and independent
reinforced concrete foundation.
The Laboratory is located adjacent with workshop covers an area of 7.0 m x 9.0 m
11.4 Mosque
The building area of the mosque is 9.0m x 9.0 m, which is a single-story building.
Adopt casting concrete framework and walls with concrete hollow block

Page 27

PLTU Buntok 2X7MW

Vol. 10. Civil Architecture and Structure

12 List of main building (structure) for production


12.1 List of building (structure)

1
2
3
4

Steam turbine house


Deaerating
Chimney
Oil storage tank

Floor
space
m2
1764
616
55
180

Air compressor house

114

6
7

Ash silo
Slag silo

30
8

DM water treatment plant

Coal water treatment plant.

190

10

Cooling tower

602

11

Complex water pump house

12

Item

Description

734.40

Construction
area
m2
3234
3080

308

Volume
m3
40910
20944

1656
80
15

1466

7076

1280

177.60

144

780

Circulating cooling water pump


station

506

506

7371

13

Siphon well

38

38

160

14

Drainage channel

340

15

Drain outlet

600

16

Ash water clarifier

198

762
Page 28

Structural pattern
Steel structure
Steel
Steel Structure
RC structure
Reinforced
concrete structure
Steel structure
Steel structure
cast-in-place
reinforced
concrete
Reinforced
concrete structure
Reinforced
concrete structure
Light steel
construction
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure

Remark

40m in height and 2.42 m of outlet I.D.


Electrostatic precipitator and ash
removal control room included
Operation load of 20t each max. 1 bins.
Operation load of 20t each max. 1 bins.
Single storey

Single storey
Steel structure on the ground

PLTU Buntok 2X7MW

Item
17

Vol. 10. Civil Architecture and Structure

Description
Coal shed

Floor
space

Construction
area

Volume

2835

2835

39100

18

Coal transfer tower

25

50

150

19

Coal crusher house

345

240

3480

20

coal-conveying gantry #1

21

coal-conveying gantry #2

22

coal-conveying gantry #3

23

20 KV switchgear room

178

24

Emergency oil basin

12

25

Foundation for main transformer

48

26

Foundation for ESP

170

27

Coal MCC room

42

168

560

28

Administration building

418.50

900

7650

29

Warehouse

108

108

900

30

Workshop + Laboratory

225

270

1620

31

Gate house

12.25

24

72

32

Mosque

146

81

960

50.5m
(length)
75.8m
(length)
(length)
220

880
30

Page 29

Structural pattern
RC & Steel
structure
Steel Structure
Reinforced
concrete structure

Remark
Gantry frame with span of 22.5m

Steel Structure

From coal crusher to coal bunker

Steel Structure

From coal shed to coal crusher

Steel Structure

From coal shed to Coal crusher room

Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
steel structure
Reinforced
concrete structure
Reinforced
concrete structure

GIS equipment foundation, relay room,


intercarrier machine room
One
Two
Two

one

PLTU Buntok 2X7MW

Item
33

Vol. 10. Civil Architecture and Structure

Description
Ash Pond

Floor
space
55565

Construction
area

Volume

Structural pattern

Remark

12.2 List of decoration


Ite
m
I.
1

Room or location
Main building
Steam turbine house
0.00m floor
7.00m operation floor
Platform rail

Deaerating Bay
Room at 0.00m floor
Cable sandwich for
3.70m pipe
Prayer room at 7.00m
floor
Others at 7.00m floor
11.50m floor

Central control room


Instrument room
Electronic
equipment
room
Central control room

Floor or ground

Wall (dado)

Ceiling

Fine gravel concrete


Ceramic floor tile
Handrail for operation floor in steam
turbine house will be galvanized

Plaster, local paint


Plaster, local paint

Plaster, local paint


Plaster, local paint

Fine gravel concrete


Plaster, local paint
Fine gravel concrete (damp-proof
Plaster, local paint
course inclusive)

Plaster, local paint

Ceramic floor tile

Plaster, local paint

Plaster, local paint

Ceramic floor tile


Plaster, local paint
Fine gravel concrete (damp-proof
Plaster, local paint
course inclusive)

Plaster, local paint

Fine gravel concrete


Plaster, local paint
Free access floor against electrostatic
Plaster, local paint
(raised floor)
Ground tile against sliding and Plaster, local paint

Plaster, local paint

Page 30

Plaster, local paint

Plaster, local paint

Acoustic/gypsum board painted


Acoustic/gypsum board painted

Remar
k

PLTU Buntok 2X7MW

Ite
m

Room or location

Vol. 10. Civil Architecture and Structure

Floor or ground

Wall (dado)

Ceiling

Ceramic wall tile

GRC board painted, suspended

electrostatics
4
5
6
II.

Boiler house
0.00m floor
Staircase
Toilet
Other building

Staircase

2
3

4
5
6
7
8

Concrete floor
Steel staircase
Anti slip ceramic tile

Except for anti-skid tile for office


building, the rest will use cement Plaster, local paint Plaster, local paint
grout or steel
Toilet
Anti slip ceramic tile
Ceramic Wall tile
GRC board painted, suspended
Plaster, acid-proof
Room requiring acid
paint (wall dado
Acid-proof coating
Plaster, acid-proof paint
resistance chemically
applied with acidproof tile)
Electrical
distribution
room,
water
pump Concrete floor
Plaster, local paint Plaster, local paint
house
Air compressor house,
water treatment room Concrete floor
Plaster, local paint Plaster, local paint
,etc.
Coal-conveying building Checkered steel plate or grating
Plaster, local paint Plaster, local paint
Plaster, local paint, ceiling with
Ceramic tile
Ground tile
Plaster, local paint
gypsum board for office building
General position
Cement grout
Plaster, local paint Plaster, local paint

Page 31

Remar
k

CP BAHARI 230MW COAL FIRED POWER

PLANTVolume Ten Architectural /Construction Description

13 Structural design software


13.1 STAAD
Steel structures for main power building framework, Complex Water Pump
House Workshop and others complicated structure facility shall be subject to three
dimensional space analysis and design with STAAD-PRO 2007 structural analysis.

Page 32

CP BAHARI 230MW COAL FIRED POWER

PLANTVolume Ten Architectural /Construction Description

14 Remain issue
The preliminary design made based on the geological survey information in the
absence of information. After additional geological survey report complete if have any
different data with prior survey information the related foundation or foundation plan will
be revise according to the updated geological survey report.

Page 33

Vous aimerez peut-être aussi