Académique Documents
Professionnel Documents
Culture Documents
COMM NO.
APPROVED
APPROVED AS NOTE
NOT APPROVED
INFORMATION
BY :
LO
DATE
G
OU COMM
T
NO.
DATE :
IFA
Re ISSUED FOR
APPROVAL
IFA
RE
V
STATUS
ISSUE DESCRIPTION
REVIEW
LO
G
IN
A
B
C
I
DISTRIBUTION
13 - 072011
04- 042011
DATE
CIVIL
MECH
ELECT
I&C
SUPPORT
CONTRACTOR
RECORD
WORKING DOCUMENT
EDT
HRD
SGN
HPS
EDT
HRD
SGN
HPS
PREPAR
ED
CHECKE
D
REVIEW
ED
APPROV
ED
CONTRACTOR :
SUBCONTRACTORJAKARTA,
/ DESIGN
INSTITUTE :
INDONESIA
PLTU BUNTOK 2x7 MW KALIMANTAN TENGAH
JOB NO. T3125
SUBCONTRACTOR DOCUMENT NO :
DOCUMENT NO.
T3125-T01-01
ISSUED DATE :
13 July 11
CONTRACT NO.
T3125
PAGE
24. PJ/121/PIKITRINGKAL/2010
REVISIO
N
2 Of 41
SIGNATU
RE
TITLE :
DATE
EPC APPD
APPROVED
REVEIWED
CHECKED
PREPARED
STAGE :
VOLUME 10
CIVIL ARCHITECTURE AND STRUCTURE
2011.7.13
2011.7.13
2011.7.13
2011.7.13
BASIC
DESIGN
DOCUMENT NO :
REV.
T3125-T01-01
SHEET
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
REVISIONS
SHEET
A
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
T3125
CONTRACT NO.
DOCUMENT NO.
T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
24. PJ/121/PIKITRINGKAL/2010
3 Of 41
REVISIO
N
1
34
35
36
37
38
39
40
74
75
76
77
78
79
80
T3125
CONTRACT NO.
24. PJ/121/PIKITRINGKAL/2010
DOCUMENT NO.
T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
4 Of 41
REVISIO
N
1
Contents
Volume No.
Volume 1
Volume 2
Volume 3
Volume 4
Volume 5
Volume 6
Volume 7
Volume 8
Volume 9
Volume 10
Volume 11
Volume 12
Volume 13
Volume 14
Designation
General
Electric Power System
General Layout and Transportation
Thermal Mechanical
Coal Handling System
Ash Handling System
Water Treatment
Electrical
Instrument and Control
Civil Architecture and Structure
HVAC
Hydraulic
Fire Protection
Outline of Construction and Erection
Remarks
DOCUMENT NO.
VOL 10
Civil Architecture and Structure
T3125
CONTRACT NO.
24. PJ/121/PIKITRINGKAL/2010
DOCUMENT NO.
T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
6 Of 41
REVISIO
N
1
Table of Contents
1General .. 1
2Natural condition for setting and main technical data for design .2
3Foundation ...8
4Architectural and structural design for the main building.. 9
5Building (structure) behind the boiler..14
6Electrical building (structure) .. 16
7Building (structure) for conveying coal16
8Building (structure) for ash and slag 17
9Chemical water building (structure) 19
10Hydraulic building (structure) .. .19
11Administration office and other structures
20
CONTRACT NO.
T3125
24. PJ/121/PIKITRINGKAL/2010
DOCUMENT NO.
T3125-T01-01
ISSUED DATE :
13 July 11
PAGE
7 Of 41
REVISIO
N
1
..28
General
1.1
Project description
To fulfill the electric energy demand in Central Kalimantan, PT Perusahaan Listrik
Negara (Persero) has planned to build for supplying the electric power for industrial
and public use. The plant will consist of two (2) units, having turbine generator net
output of single figure in the range of 7 MW each. This project is located at Sanggu
Village, Buntok Regency, Central Kalimantan Province. The site area is bordered by
Wendo River in the South, Sanggu Lake in the West, Pematang Kayu River in the
North and forest in the East, approximately 11 KM away from Buntok City. The
geographical coordinate is at S 013949.63.and E 1145484. Topography area,
which will be proposed for power plant is approximately 23.54 hectares developed at
13.67 Ha.
The project site area is hill need cut and fill soil to achieve design ground level,
proposed ground level with height 10.5m from mean river surface. Land
transportation can be done through the main road which are consist of two lane public
traffic, connected from Buntok City to Sanggu Village, as far as 11 km..
No railroad close to the Site area, the nearest airport located at Buntok City for local
Airport and the National Airport located in Banjarmasin and Palangkaraya City.
No dedicated harbor or equipment unloading facilities at the Site, The closest
available commercial Sea Port is at Banjarmasin Capital City.
1.2
Design basis
Standard no.
ACI 318
ACI 350
AISC
ASTM
AASHTO
Name of standard
Building Code For Reinforced Concrete
Concrete Sanitary Engineering Structures
American Institute of Steel Construction
American Society for Testing and Material
ASTM Standard and Specification s for Various
Construction Materials
American Association of State Highways and
Transportation Officials
Page 1
Remar
k
Ite
m
no.
6
7
8
9
10
11
12
Standard no.
ASCE
AWS
JIS
SNI 03 1726 2003
SKBI-1.3.53.1987
UDC 624.042
SNI 03-17292002
SNI 03-28472002
Name of standard
Remar
k
Note: There are some standard and code will follow to China standard (GB standard,
Where applicable)
1.3
Design principle
1.1.3 Building and structure shall have structural design in accordance with the appropriate
type of structure being selected to ensure the availability of advanced technology,
safety and applicability, economy and quality.
1.1.4 With process production being guaranteed, the type of structure shall take into
account the painting, fire-resistance, vibration resistance, explosion resistance,
geological condition, construction technology, etc. and shall meet the requirements
on structural intensity, rigidity and durability.
Page 2
Natural condition for setting and main technical data for design
2.1
Location
Page 3
Hydrometeorology
Indonesia falls into typical tropical rainforest climate, characterized by high
temperature, much rain, low wind, big humidity, with cumulative annual temperature
of 25~270C
season falls on April to September while rainy season falls on October to March in the
following year.
The project area, as part of Central Kalimantan Province, has a tropical climate
characteristic, where rainy season and dry season continuously change every six
months. Average temperature is 26C 29C and average rainfall is 2.826 mm/yr.
Maximum wind speed 6 knot = 11,2 m/s with dominant wind blows is 34.4% from
west
2.3
Engineering geology
Page 4
N >50.
1.1.7 Soil characteristics.
According to the site investigation at 2 location (DH1 at BOP and DH2 at Power
Block), the SPT test result, laboratory test result, the soil bearing layer have
significant different. The physical character and engineering character explained as
following:
Depth
Soil Description
DH1
.
20m
DH2
.
20m
Depth
Soil Description
DH3.
34m
Depth until 2.5m very dense fine sand with SPT-N 51~53; depth
2.5 ~ 4m is very dense silty sand with SPT-N 51; depth 28~34m
very dense fine sand with SPT-N 50
DH4.
20m
Depth 3.3 ~ 3.7 very dense silty fine sand with SPT-N 50,
3.7~3.8 m is dense fine sand with SPT N40; depth 12.5-17
very dense to coarse sand with SPT-N >50
DH5.
44m
Depth 4.3~8.4 very dense silty fine sand with SPT-N 41; depth
40 ~ 42m is very dense fine sand with SPT-N 51; depth 42~44m
very dense coal with SPT-N 50
DH6.
36m
DH7.
36m
Depth until 4 ~ 8 very dense fine sand with SPT-N 44; depth 32 ~
36m is very dense fine to medium sand with SPT>N 50
DH8.
40m
Depth 6 ~ 8 very dense silty fine sand with SPT-N 44, 18~22 m is
dense medium sand with SPT N36; depth 32-40 dense fine to
medium with SPT-N 50
DH9.
30m
DH11
.
38m
DH12
.
20m
DH13
38m
DH14
.
44m
DH15
.
32m
VALUE
10.5
m
481mm/month
140.5mm/month
11.2m/s (6 knots)
120 km/hours
W
98.3 %
84.3 %
63.8%
85 %
23~30 C
DESCRIPTION
b. Ambient temperature for design propose
6. River water tidal
a. High Water Level (HWL) at 100 year
rainfal
b. Mean Sea Level (MSL)
c. Low Water Level (LWL)
2.4 Main design parameters
VALUE
30 C
+97.87.m
+94.5 m
+94.15 m
Material
: C60
: C30
: C25
: C15
or otherwise noted
a) Impermeable concrete: C30 class, mixed with expanding agent of 10% in cement
usage, which could be appropriately selected according to structural stress and
characteristics.
b) Secondary grouting: utilized shrinkage grouting material, fine gravel concrete with
one intensity grade higher than major concrete.
c) Structural durability of concrete:
Cement type - I shall be used for above grade work
Cement type - II for cooling tower and basin , foundation, structures below grade
Cement type - V for all structures direct contact with sea water (NA)
1.1.13 Reinforced bar
a) Common reinforcement (non pre-stressed reinforcement) used in concrete structure
shall comply with the requirement of ASTM A615 or SNI Standard.
b) Pre-stressed reinforcement: it is appropriate to utilize stress-relief steel wire, steel
strand and heat treatment reinforcement as well .
Page 7
c) Unless otherwise specified, reinforced bar with diameter <12mm utilize Grade BJTP
24 and for diameter 12mm utilize Grade BJTD 40.
1.1.14 Steel
a) ASTM A36
use for all structural steel , which quality shall comply with the
requirements of Carbon Steel for Structural SS400 and Low-alloy High-tensile Steel
for Structural SM490 respectively that cover the light roof structure and other lattice
structure .
b) Section steel will be selected for the steel structure in priority. For hot-rolled H
section steel, which is not applicable, welded H section may be considered. Hotrolled section shall have the cross-section characteristics in accordance with JIS G3192 and BS 4360 GR 43A.
1.1.15 Cement
Generally, ordinary Portland cement will be used or slag Portland cement and
sulphate resistant cement with intensity class of I , II and V(NA)
1.1.16 Aggregate
Utilize medium coarse sand and crushed gravel.
1.1.17 Wall
Red bricks with size of 110mmx55mmx230mm or concrete hollow with dimension
390 x 190x100 may be considered.
1.1.18 Mortar
Mortar shall conform to the applicable requirements of ASTM C270.
1.1.19 Welding
The codes and standards of the following organizations, Subsection "Codes and
Standards" are specifically applicable to the design, manufacture and testing of the
work included in this Specification:
ASTM
AWS
ELECTRODES
Except as otherwise specified, all welding electrodes shall conform to the applicable
provisions of the AWS Structural Welding Code AWS D1.1 For steels with special
properties, such as resistance to brittle fracture, corrosion resistant steels, stainless
lad steels and stainless steels, the recommendations of both the steel and electrode
manufacturers shall be secured for each specified steel and each specific use.
Page 8
1.1.20 Bolt
a) Ordinary bolt
The Ordinary bolt should have the performance to ASTM A36, washer should follow
to ASTM F436 one washer under the bolts head and one under the nut.
b) High-strength bolt
The High-strength bolt should have performed to AISC specification for structural
joints using ASTM A325. Bolts and nuts use the following materials unless otherwide
indicated for bolts sizes use A325, Type 1 steel, one washer under the head and one
under the nut, whichever it the element turned in tightening.
c) Anchor bolt
ASTM A36 for threaded rods and ASTM A307 for headed bolt and for all nuts. Anchor
Bolt should be adopted to the foundation of heavy loading or heavy dynamic loading.
The material of anchor bolt for equipment shall be determined by the related
discipline. Anchor bolt shall be provided with double nuts and washer.
1.1.21
2.6
Earthquake-resistant design
Construction field for the project is defined as Base on Indonesia earthquake zone
divided, Zone = 1, the basic seismic acceleration design is 0.03g. Earthquakeresistant design is carried out according to the above parameters plus Guideline of
seismic restrain for building construction, Indonesian standard (SNI.03-1726 2003).
Page 9
Foundation
Main Power building for this phase of project 0.00m is equal to absolute altitude
103.3m average
According to the geological survey information in feasible study report, the field
ground, the ground foundation plan is initially prepared below.
Due to the ground up level is filled with medium dense sand soil, the estimate support
force is about 160kPa. Consider MW main equipment load is not too big, to use
nature foundation should be enough to meet the requirement. So the nature
foundation is first to be considered and it will save the cost.
The soil character is good, and mainly makeup by the sand soil, under the preliminary
analyze, it does not need to do the soil improvement, use backfill the soil according to
the requirement.
If part the ground can not meet the requirement, strong rammer method could be
used to stronger the ground with little cost.
Main buildings/structures of whole plant adopt natural ground and independent
reinforced concrete foundation. Over excavation is strictly prohibited for foundation pit
and bearing layer is strictly prohibited to disturb when foundation trench is excavated
for buildings/structures in plant area based on natural ground. Soil analysis for trench
bottom shall be intensified when foundation trench is excavated to design altitude.
Careful study shall be given to the difference between soil qualities of trench bottom
and bearing layer suggested by investigation report, and section of foundation trench
with irregular soil quality, the proper measurements should be taken. Over-excavated
foundation layer shall be filled with graded sand-gravel or site undisturbed sand
without organic substance.
Main workshop foundation is considered to adopt independent reinforced concrete
foundation. Most of wall foundation adopts ground beam, few of them adopt concrete
foundation. Other buildings/structures adopt independent foundation or strip
foundation. Other foundation treatment measures could be adopted if the
requirements of construction drawing could not be met.
Piling foundation are advised to adopt for boiler & stack foundation due to larger load.
According to actual situation, further foundation treatment measures shall be taken
for area of coal yard & oil tank where larger and concentrated heaped-load has.
Before construction drawing is began to designed, it is advised to compile proper plan
of foundation treatment and style of foundation according to load distribution in each
unit engineering.
Page 10
Turbine house
Turbine house may have a lateral span of 22.00m and total longitudinal length of
49.0m (to be made of steel structure and no expansion joint), with pillar spaced in
7.0m and two steam turbosets inside. Steam turbine house is divided into ground
floor and operation floor with vertical elevation of 0.00m, 7.00m floors respectively.
0.00m floor is provided to setup thermal machine and auxiliary machine, etc.
Maintenance space is provided between two machines to satisfy the need for
maintenance of steam turbine. (A), (B) shaft at 7.00m floors may allocate a portion of
platform to facilitate the maintenance and traffic. Island platform is considered for the
foundation of steam turbine generator and heater platform so as to prevent vibration
load from transferring to the factory building. Steam turbine is oriented in longitudinal
arrangement with the machine head toward the extension end. Inside the steam
turbine house, there is a bridge crane with lifting capacity of 20t or 10t, span of
15.00m (, and elevation for crane beam-rail roof being 14.50m. Crane driver room is
located at the side of (B) row of pillar. The crane may travel freely within the operation
area.
Deaerating bay
Deaerating may have a span of 7.0m 3 stories vertically, elevation of 0.00m, 3.70m,
7.00m (operation floor), 11.50m (deaerating tank); pipe layer room may be
considered at local 3.70m .
0.00m may setup Electric distribution room and Battery room, staircase, etc 7.00
floor may include the central control building (shift change room and field house)
between (3)-(9) shaft ,toilet,Instrument rack room, etc. between (1)-(2) and (9)-(12)
shaft11.50 floor may consider two deaerators floor.
Boiler house
Boiler Island is arranged in two islands pattern with unequal distance of columns,
longitudinal length of 17.8m and lateral length of 9.75m. Boiler frame is formed in
steel structure. Boiler frame, boiler top cover and steel beam for boiler operation
platform shall be designed by the boiler manufacturer.
Pathway in front of the boiler shall have a span of 3.9 m. At elevation 7.00m, there
are platform connecting the boiler to deaerating bay.
Page 11
Horizontal traffic
At the side of B row of pillar in deaerating room, there will be main longitudinal
pathway with width bigger than 1,6m. At A row of pillar side in steam turbine house
and in front of the boiler platform, there is a secondary longitudinal pathway with
width bigger than 1,8m. Both ends of main longitudinal pathway is accessed to the
outer exit of power building or staircase. At both ends 0.00m, 7.00m, there are
lateral pathways in place to allow easy access from steam turbine house to
deaerating and boiler house. Access of main equipment to steam turbine house may
pass through the maintenance yard in the middle of steam turbine house and fall way
at each floor in the top. Access to maintenance yard may be equipped with electric
rolling-opening steel door.
In front of the boiler platform 0.00m , there is longitudinal pathway with width 4.0m .
Vertical traffic
At fixed end and extension end, there are ladders/stair connecting to each platform,
which are provide to meet the requirement on production and safe evacuation in case
of fire. In steam turbine house, there are steel ladders for site inspection tour installed
at the heater platform for each turbine, via which you may go to the middle floor and
operation floor.
All entrances/exits, ladders and walkway for platform connecting each floor are equipped with
conspicuous signs showing the direction and guidance of evacuation. Turbine house
and Boiler house will each have an elevator
1.1.24 Day lighting and ventilation
Lighting in steam turbine house and deaerating shall be made available in a
combined way of natural and manual lighting. The whole factory building may be
equipped with rectangular windows in dot arrangement. Roofing for steam turbine
house may be provided with light-absorpting shade in the top to increase the
illumination over the operation floor in steam turbine house. Mechanical ventilation
may be enough for steam turbine house. Mechanical exhaust blower may be installed
at the roofing. Natural ventilation is provided across the deaerating with properly
distributed air flow.
1.1.25 Water-proof, drain and thermal insulation
Roofing is properly inclined toward roof gutter to facilitate the collection of rainwater.
Page 12
Via rainwater pipe, rainwater is routed to the drainage system in the plant. Synthetic
polymeric water-proof coiled material made of chlorinated polyethylene (CPE) may be
applied for roof and floor against water ingress. Polystyrene insulation board or local
insulation material may be applied for thermal insulation at roof and floor.
1.1.26 Fire- and explosion-resistance
Ladder and pathway shall be properly arranged. Each structural element for main
power building shall be delivered in compliance with fire-proof criteria:
Main power building (including steam turbine house, deaerating, boiler island) shall
have Class II fire-resistance. Fire hazard is classified as IV.
Fire door shall be installed for pathway door between steam turbine house and
deaerating that for distribution room in main power building, cable sandwich,
enclosed staircase.
Fire wall shall be installed between steam turbine house and deaerating with fireresisting limit of 1 hour, while all other non load-carrying wall shall have fire-resisting
limit of 0, 25 hour.
Steel elements around oil tank or oil pipe in steam turbine house shall be painted with
fire-retardant coating. Load-carrying steel structure shall have fire-resisting limit of
1.0h and non load-carrying structure 0.5h. Fire-retardant paint shall be applied on
steel roof truss above oil tank in steam turbine house, with fire-resisting limit of 0.5h.
1.1.27 Housekeeping and sanitary facilities
Since housekeeping and sanitary measure are designed for the designated purpose
and the technicians often appear at main factory building and operation floor, the
toilets for man and woman could be considered at fixed end of deaerating, staircase,
and zero meter and operation floor so as to be used for maintenance technicians.
Water flushing may be provided zero meter of main power building, ditch may be
provided to access to outside coal-water treatment unit.
1.1.28 Building enclosure
Outer wall for steam turbine house and deaerating may be covered with laminboard
(for the purpose of insulation, heat resistance, reduction of noise, etc.). The
framework may contain filler wall filled with light partition wall (light building blocks of
aerated concrete or equivalent local light building blocks). All doors and windows are
made of aluminium alloy or plastic-steel. Distribution room may have door and
window of louver and PVC door is applied to the toilet.
1.1.29 Architectural style
Page 13
For the purpose of safety, applicability, economy, with adoption of architectural design
philosophy and in conjunction with local style of building, we are commit to create and
build an elegant and practical main factory building with the taste of the times and in
line with the local culture of architecture.
Fixed end is properly staggered with defined zoning. Adoption of substantiality and
virtuality design, material application, colorful decoration, etc., will create an art
background for architectural composition for the whole plant.
Outer vertical view and color for main factory building has fully taken into account the
proper consistency of environment in the vicinity. Lucid and lively color may be
painted on main factory building. Main color prefers light-color with color strip in some
areas to make the vertical view vivid.
Outer wall may be applied with washable hydrophobic paint to ensure the outer wall
clean.
1.1.30 Arrangement and planning for underground facility
Boiler house0.00m may consider water flushing to be drained to the ditch nearby.
Underground ditch for main factory building and equipment foundation shall be
arranged according to the process requirement, with channel and pit poured with
waterproof concrete and damp-proof course to eliminate or reduce the ingress of
underground water. Industrial pit and ditch are formed without interference. In case of
meeting together, the principle to be observed is wet one before dry one, hard one
before soft one, natural flow before pressure one. And, drainage system is isolated
each other to prevent leak. Waterproof measure shall be put in place at ditch
intersection, expansion joint to ensure no water accumulation in the ditch.
4.2
Page 14
system, which will be equipped with rigid compression bar at the top of pillar and
crane beam. Cross beam for other floors shall be subject to framework structural
element control, ie. to be calculated based on bending, that is rigid bar structural
control.
End support shall be installed at the 1st pillar at both ends of main power building,
which shall be through up and down and work together with lateral support of lower
chord below the roof truss.
c
Plane system
Platform for each floor and roof for deaerating may be structured in combined steel
beam cast-in-place concrete slab, and in checkered steel plate or steel grating plate
for some areas. Roofing will be formed in structural sloping. Use lateral framework
beam as main beam with secondary beam arranged longitudinally (basic distance of
2m).
Platform in front of the boiler is structured in combined steel beam cast-in-place
concrete slab.
All steel secondary beams and cast-in-place slab may be connected with peg or
shear nail.
Page 15
Page 16
Stack
Two boilers may share a steel stack with outlet inside diameter of 2.5m and 40.0m
high. The stack is structured in single-drum steel structure and the foundation is
adopted piling foundation, but the final will be determined after soil investigation
report. Flue outlet shall be provided each at both sides of chimney. Heat insulation
and antisepsis on inner wall method : Brush coal-asphalt anti-corrosion dope on
the inner wall of steel. The inner liner adopts anti-acid terra-cotta and anti-acid
puddle, and perlite plate for heat insulation method : liner of chimney is design
according to electronic power industry standard and code, using light dense anti-acid
lining material, corruption-proof paint will be painted to inner wall of the chimney.
5.2
Flue
Reinforced concrete structural support and steel flue are proposed. Fire-retardant
bricks are used inside. Air thermal buffer is applied. On the top of flue, there is cast-inplace acid-proof and thermal-proof concrete corrosion resistant coating.
5.3
Support for steel flue, support of maintenance induced draft fan, foundation of ESP
Support for steel flue and support for maintenance of induced draft fan are structured
in cast-in-place reinforced concrete framework or steel framework, with independent
foundation. Support for ESP will be steel structure to be supplied by the manufacturer,
with independent foundation in reinforced concrete.
5.4
5.5
Pipe rack
Pipe rack support across the plant may be built in H steel column, beam or steel
truss. The support over the road is built in steel truss, with independent foundation in
reinforced concrete.
Page 17
Page 18
6.2
Page 19
Building (structure) for conveying coal include general building for conveying coal,
trestle for conveying coal, crushing building, Transferring station and dry coal shed,
etc.
7.2
7.3
7.4
Transferring tower
Each transferring station is made in structure of steel structure framework and
cladding walls and pile foundation.
7.5
7.6
Page 20
Concrete frame structures for dry coal shed with lipped channel girt and corrugated
steel as roofing. Wall and roof above the lateral beam are baffled with single-layer
colour board. Pile foundation is shaped in independent foundation in reinforcement
concrete.
On the both sides of coal pile, there is barrel-drain.
Page 21
8.2
8.3
8.4
Page 22
Ash and slag stockpile shall be first cleanout according to the strike of land
configuration, followed by excavation up to the clay layer for levelling and tamping
and then installation of HDPE geomembrane. Geomembrane shall be placed properly
with joint generally adopting adhesion and hot welding and being width not less than
100mm for water resistance. Geomembrane shall be covered with sand and gravel
protection on the surface.
Main blind ditch shall be arranged longitudinally along the dam with cross section of
ditch of 600400mm. Secondary blind ditch may be arranged vertically along the dam
with cross section of ditch of 500400mm and distance of 50~70m. Crushed gravel
with diameter of 20-50mm shall be filled in blind ditch and reversed filter of sand and
gravel with 300mm in thickness may be applied on the back of wall and blind ditch.
Loading capacity for the ground of ash and slag stockpile shall be considered based
on fak=160kPa.
Page 23
9.2
9.3
Dosing room
Dosing room is arranged in deaerating bay 3.70m floor, between (1)-(3) shaft.
Page 24
Page 25
Other hydraulic facility may include water reservoir for operation and firing, coal water
and ash water treatment pit, siphon well, drain open channel, drain outlet, etc. There
may be cast-in-place reinforced concrete framework and bent structure, reinforced
concrete box-type pit structure to be taken according to the process arrangement.
According to process requirements, underground ditch, pit will take appropriate
measures against spill and corrosion.
Page 26
Page 27
1
2
3
4
Floor
space
m2
1764
616
55
180
114
6
7
Ash silo
Slag silo
30
8
190
10
Cooling tower
602
11
12
Item
Description
734.40
Construction
area
m2
3234
3080
308
Volume
m3
40910
20944
1656
80
15
1466
7076
1280
177.60
144
780
506
506
7371
13
Siphon well
38
38
160
14
Drainage channel
340
15
Drain outlet
600
16
198
762
Page 28
Structural pattern
Steel structure
Steel
Steel Structure
RC structure
Reinforced
concrete structure
Steel structure
Steel structure
cast-in-place
reinforced
concrete
Reinforced
concrete structure
Reinforced
concrete structure
Light steel
construction
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Remark
Single storey
Steel structure on the ground
Item
17
Description
Coal shed
Floor
space
Construction
area
Volume
2835
2835
39100
18
25
50
150
19
345
240
3480
20
coal-conveying gantry #1
21
coal-conveying gantry #2
22
coal-conveying gantry #3
23
20 KV switchgear room
178
24
12
25
48
26
170
27
42
168
560
28
Administration building
418.50
900
7650
29
Warehouse
108
108
900
30
Workshop + Laboratory
225
270
1620
31
Gate house
12.25
24
72
32
Mosque
146
81
960
50.5m
(length)
75.8m
(length)
(length)
220
880
30
Page 29
Structural pattern
RC & Steel
structure
Steel Structure
Reinforced
concrete structure
Remark
Gantry frame with span of 22.5m
Steel Structure
Steel Structure
Steel Structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
Reinforced
concrete structure
steel structure
Reinforced
concrete structure
Reinforced
concrete structure
one
Item
33
Description
Ash Pond
Floor
space
55565
Construction
area
Volume
Structural pattern
Remark
Room or location
Main building
Steam turbine house
0.00m floor
7.00m operation floor
Platform rail
Deaerating Bay
Room at 0.00m floor
Cable sandwich for
3.70m pipe
Prayer room at 7.00m
floor
Others at 7.00m floor
11.50m floor
Floor or ground
Wall (dado)
Ceiling
Page 30
Remar
k
Ite
m
Room or location
Floor or ground
Wall (dado)
Ceiling
electrostatics
4
5
6
II.
Boiler house
0.00m floor
Staircase
Toilet
Other building
Staircase
2
3
4
5
6
7
8
Concrete floor
Steel staircase
Anti slip ceramic tile
Page 31
Remar
k
Page 32
14 Remain issue
The preliminary design made based on the geological survey information in the
absence of information. After additional geological survey report complete if have any
different data with prior survey information the related foundation or foundation plan will
be revise according to the updated geological survey report.
Page 33