Doc. No:
ICC-MOS-El-001
Rev 1
Page 1 of 7
ICC-MOS-El-001
Issue Date:
Doc. No:
ICC-MOS-El-001
Rev 1
Page 2 of 7
TABLE OF CONTENTS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
1.
SCOPE...................................................................................................................... 3
PURPOSE.................................................................................................................. 3
DEFINITION.............................................................................................................. 3
REFERENCES............................................................................................................ 3
RESPONSIBILITIES.................................................................................................... 3
STORAGE & HANDLING............................................................................................ 6
PREPARATION & INSATLLATION................................................................................ 6
CLEANING................................................................................................................ 7
EQUIPMENTS REQUIREMENT.................................................................................... 7
SAFETY..................................................................................................................... 7
DOCUMENTATION..................................................................................................... 7
SCOPE
Doc. No:
ICC-MOS-El-001
Rev 1
Page 3 of 7
This Method of Statement specifies the detailed requirements for Cable trays & cable
ladders installation.
2.
PURPOSE
The purpose of this method statement is to ensure that PROJECT NAME team is
familiar with the minimum guidelines and measures to be followed during
construction and installation in the PROJECT NAME.
3.
DEFINITION
Client
Subcontractor
Project
4.
:
:
:
REFERENCES
Drawings
5.
RESPONSIBILITIES
The following are job description of the principle Project Field Staff personnel
utilized construction of the PROJECT NAME.
5.1.
His specific duties including planning, organizing and direction all field work
to a successful conclusion of the project, meeting contractual obligations and
the Client's expectations while maintaining the company's best interests. He
will establish a site office, personal camps and any additional structures
required to accomplish project goals and administer all field activities in
accordance with company and departmental policies and procedures and
project specifications. He will direct material control activities and all QA/QC
and survey activities. He will administer all subcontractors and participate in
all subcontract negotiations and submit subcontractors, including any third
party companies for approval to the Client prior to signing contract with
subcontractors. Additionally, he will provide job site interface with the Client,
Doc. No:
ICC-MOS-El-001
Rev 1
Page 4 of 7
maintain close liaison in all times and attend project meetings with the Client
on a regular basis.
5.2.
Construction Supervisor
Specific duties includes but not limited to organizing and directing all
construction activities, supervising assigned staff personnel and establish
daily productivity goals, monitor productivity and initiate remedial action
where required. He will assist in preparation of reports; participate in all
coordination, scheduling, safety and progress review meeting. He is
responsible for interfacing with engineering and assuring that the latest
drawing and document revisions are circulated to project personnel. He will
also be responsible for interpreting drawings and specifications for field
personnel and subcontractors and coordinate resolution of engineering
problems with the appropriate engineering sttaff and the Client. He will also
notify QA/QC personnel in all QA/QC activities including any deficiencies
found during construction. He is also responsible for development of field
test data and punch lists.
5.3.
Doc. No:
ICC-MOS-El-001
Rev 1
Page 5 of 7
6.
Doc. No:
ICC-MOS-El-001
Rev 1
Page 6 of 7
7.
7.2. Installation
Install cable trays / ladders with sufficient space to permit access for installing
cables. Minimum clearance of 250 mm is to be maintained between top of
tray / ladder and ceiling, beams and other services and between tray /
ladders in multi-tier formation.
Mark out the location of hangers & supports for cable tray and cable ladder
installation as per the approved construction drawings.
Drill the marked position for hangers and supports by using the drill bit of
appropriate size.
Fix the flush anchor at drilled position by gentle and uniform hammering.
During hammering use the approved "Setting Tool" of appropriate size for
proper grip of the anchor in concrete. Care should be taken to avoid
damaging the thread of the rod
Fix the threaded rod by twisting. For easy and balance twisting of the rod use
any clamping tool like pliers etc. Care should be exercised to avoid any
damage to the threads.
The hanging supports for cable tray/ladder will be cut in the required size,
reamed properly and galvafroid paint will applied on cut edges.
After fixing the threading rod and hanging supports and prior to fixing the
tray/ladder at its location. Cut the required length (If not available in the
required size). Apply galvafroid on all cut edges.
Doc. No:
ICC-MOS-El-001
Rev 1
Page 7 of 7
After cutting ladder and tray should reamed properly to remove burr and
sharp edges to minimize the danger and treat cut edges.
Place the cable tray/ladder in the support with expansion connectors, if length
is more than 27 mtr.
Install connectors and earth links at the bottom of all cable tray/ladder joints.
In case of change in direction/elevation use standard fittings and specials of
the approved manufacturer.
Additional support shall be provided where cable tray/ladder changes direction
or cables drop outs.
Install covers after installation of cable is completed.
Seal penetrations through fire and smoke barriers with appropriate material.
For grounding connect trays / ladders by flexible tinned copper straps to
nearest bare earthing conductor and at maximum 30-m spacing.
8.
CLEANING
After completion of installation, remove burrs, dirt, and construction debris
and repair any damages, scratches and abrasion.
9.
EQUIPMENTS REQUIREMENT
The equipment that will be required in the installation works of cable tray/ladder
will be as follows:
High-up truck
Drill machine
Step ladder
Electrical cutting machine
Screw drivers
Measuring tape
10. SAFETY
All personnel involved in Cable tray/ladder installation shall follow the
requirements of the HSE Plan. All works HAZARDS shall be identified prior to
the start of the activity. safety coordinator shall insure that all operations are
carried out in accordance with Project Safety Procedures.
11. DOCUMENTATION
Quality Control department shall retain all Material Certificates, tests, and
inspection records.