Académique Documents
Professionnel Documents
Culture Documents
Sector Director:
Appraisal
Team
Team Leader:
OITC DEPARTMENT
July 2013
TABLE OF CONTENTS
Currency Equivalents ............................................................................................................................... i
Acronyms and Abbreviations ................................................................................................................... i
Loan Information..................................................................................................................................... ii
Project Summary .................................................................................................................................... iii
Results Based Logical Framework ......................................................................................................... iv
Project Timeframe ................................................................................................................................... v
I - STRATEGIC THRUST & RATIONALE ....................................................................................... 1
1.1 PROJECT BACKGROUND ............................................................................................................. 1
1.2 PROJECT LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES ............................................. 2
1.3 RATIONALE FOR BANKS INVOLVEMENT ................................................................................... 2
1.4 DONORS COORDINATION ............................................................................................................ 3
II - PROJECT DESCRIPTION ............................................................................................................. 4
2.1 PROJECT DEVELOPMENT OBJECTIVES ......................................................................................... 4
2.2 PROJECT DESCRIPTION AND COMPONENTS ................................................................................. 4
2.3 TECHNICAL SOLUTION RETAINED AND OTHER ALTERNATIVES EXPLORED ................................ 4
2.4 PROJECT TYPE............................................................................................................................. 5
2.5 PROJECT COST AND FINANCING ARRANGEMENTS ...................................................................... 5
2.6 PROJECTS TARGET AREA AND BENEFICIARIES .......................................................................... 7
2.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION .................................. 7
2.8 BANK GROUP EXPERIENCE, LESSONS REFLECTED IN PROJECT DESIGN ...................................... 8
2.9 KEY PERFORMANCE INDICATORS ............................................................................................... 8
III - PROJECT FEASIBILITY ............................................................................................................... 8
3.1 ECONOMIC AND FINANCIAL PERFORMANCE ............................................................................... 8
3.2 ENVIRONMENTAL AND SOCIAL IMPACTS ................................................................................. 11
IV - IMPLEMENTATION ................................................................................................................... 12
4.1 IMPLEMENTATION ARRANGEMENTS ......................................................................................... 12
4.2 MONITORING ............................................................................................................................ 15
4.3 GOVERNANCE ........................................................................................................................... 16
4.4 SUSTAINABILITY....................................................................................................................... 16
4.5 RISK MANAGEMENT.................................................................................................................. 17
4.6 KNOWLEDGE BUILDING ............................................................................................................ 17
V - LEGAL INSTRUMENTS AND AUTHORITY ........................................................................... 18
5.1 LEGAL INSTRUMENT ................................................................................................................. 18
5.2 CONDITIONS ASSOCIATED WITH BANKS INTERVENTION ........................................................ 18
5.3 COMPLIANCE WITH BANK POLICIES ......................................................................................... 19
VI - RECOMMENDATION ................................................................................................................. 19
Appendix I. Countrys Comparative Socio-Economic Indicators
Appendix II. Table of ADBs Portfolio in the Country
Appendix III. Key Projects Financed by the Bank and other DP in the Country
Appendix IV. Map of the Project Area
Currency Equivalents
March 2013
Fiscal Year
01 April 31 March
=
=
=
=
=
=
NDP
NPV
PCR
PESC
LOAN INFORMATION
Clients information
BORROWER:
Amount (ZAR)
2,982 million (87.2%)
14.00 million (0.4%)
173 million (5.1%)
250 million (7.3%)
3,419.00 million
Amount (UA)
219.91 million
1.00 million
12.77 million
18.44 million
252.12 million
Instrument
Project Loan
Technical Assistance
Counterpart Funding
Counterpart Funding
Loan
South African Rand (ZAR)
Enhanced Variable Spread Loan
Base Rate + Funding Cost Margin +
Lending Base
Spread
Floating
rate based on 3 month Jibar
with free option to fix the Base rate.
*1
60 basis points (0.60%)
N/A
N/A
Semi-Annual
Up to 20 years
Up to 5 years
15%, NAD216 million
14.6%
Grant
UA
MIC TA Grant
NA
NA
NA
NA
NA
NA
NA
NA
NA
March 2013
July 2013
January 2014
June 2019
December 2017
December 2019
August 2019
August 2033
The six-month adjusted average of the difference between (i) the refinancing rate of the Bank as to the
borrowings linked to 3-month JIBAR and allocated to all its floating interest loans denominated in ZAR and (ii)
3-month JIBAR ending on 30 June and on 31 December. This spread shall apply to 3-month JIBAR which resets
on 1 February, 1 May, 1 August and 1 November. The Funding Cost Margin shall be determined twice per year
on 1 July for the semester ending on 30 June and on 1 January for the semester ending on 31 December.
ii
PROJECT SUMMARY
Project Overview
The Port of Walvis Bay is operated by the Namibian Port Authority (Namport) and serves as a
gateway linking some of southern Africas major trading regions to international markets. In
response to increased trade-related traffic volumes, Namport is embarking on an expansion
program to raise the container throughput capacity from 355,000 TEUs to 1,005,000 TEUs.
The project scope comprises the construction of a new container terminal on reclaimed land
from the Walvis Bay channel supported by complementary initiatives on logistics and
capacity building. The total project cost estimate is ZAR3,419 million (UA252.12 million),
with 87.6% financed by the Bank through an ADB Sovereign Guarantee Loan of ZAR2,982
million (UA219.91 million) and a MIC TA Grant of UA1.00 million (ZAR14 million). The
remaining 12.4% of the total project estimate, or ZAR423 million (UA31.21) will be financed
by Namport including a grant from the Government of Namibia of ZAR250 million (7.3%).
The project implementation is over a period of three (3) years. The expected project outcomes
include improved efficiency of the port and increase in cargo volumes as a result of increased
trade in the region, spurring inter regional trade and regional integration, private sector
development, employment creation and promotion of inclusion, economic growth and poverty
reduction. The projects beneficiaries are extensive, ranging from the populations and
governments of Namibia and the SADC countries, the trade and logistics industry, consumers
and exporters at national, regional and international level.
Needs Assessment
The necessity to expand the container terminal at the Port of Walvis Bay arises from the
significant growth in freight traffic in recent years and increasing demand for port capacity
due to increasing economic activities and trade in the SADC region and in Africa in general.
This trend is expected to continue and Namibia aims to maximise its potential and strategic
location to become a trade hub for the region thereby enhancing trade and regional integration
and yielding high and sustained economic growth; alleviating poverty in the country and the
SADC region as a whole. The port is currently operating at capacity and timing and urgency
are of the essence to take advantage of the opportunities on offer before this is lost to
competing ports / countries in the region.
Banks Added Value
The rationale for the Banks involvement is multifaceted: i) the Bank is proactive in the
development of major regional trade corridors, and brings to the project a wealth of
experience, providing a holistic outlook and wider reach in connecting the continents key
infrastructure and missing links; ii) the Bank is assisting in the diversification and distribution
of port facilities on the southern-west coast of Africa and provides the much needed
alternative (to South African ports) for the SADC landlocked countries to access international
markets; iii) the project is potentially serving up to seven major economies in the SADC
region influencing increased inter-regional and international trade and related activities.
Through this project, the Bank is promoting regional integration, private sector development
and jobs creation leading to significant economic development in the SADC region.
Knowledge Management
The project provides an excellent opportunity for new skills to be developed both within the
Bank and in Namibia. Within the Bank, it is an opportunity to further strengthen its
knowledge on ports and regional integration which will feed into the Banks knowledge
series. In Namibia, the project provides opportunities for trainings, skills transfers and
capacity building which help to increase the skills base in the country, help create sustainable
employment and reduce poverty.
iii
KEY ACTIAVITIES
OUTPUTS
OUTCOMES
IMPACT
RESULTS CHAIN
Indicator
Baseline
Target
Improved economic
performance
3.8% (2011)
5% - 6% (2020)
COMPONENTS
Component A: Terminal construction
Component B: Equipment
Component C: Ancillary Activities
Component D: Logistics & Capacity Building
(2012)
Costs
( UA million)
Terminal Construction
179.32
Equipment
12.84
Ancillary Activities
20.51
Logistics & Trade Facilitation
0.83
Base Cost
213.50
Physical Contingency (10%)
21.35
Price Contingency (2%FE, 5%LC) 17.27
Total
252.12
(2020)
( ZAR million)
2,431.00
174.00
278.00
12.00
2,895.00
290.00
234.00
3,419.00
iv
MEANS OF
VERIFICATION
RISKS/MITIGATION MEASURES
African Economic
Outlook database
Outcome Risks
i) Competing routes/ ports take over trade volumes;
ii) Government fails to implement its plans
iii) Regional logistics environment gets worse
Mitigation measures
Port Statistics
i) sound strategies/ business plan; complementary
Corridor Group Data
infrastructure; promote port and corridor use
ii) implement NDP4 action plan, develop and
World Bank Data
implement logistics master plan.
iii) strengthen capacity on advocacy tackling regional
non-tariff barriers on corridors
Progress reports,
Bank supervision
reports,
Audit reports,
Midterm review
reports,
Namport quarterly
reports
Output Risks
i) Procurement delays and late project start up; ii)
Construction risks; iii) Environmental risks
Mitigation measures
i) Use of Advanced Contracting reduces procurement
delays; ii) Use of EPC fixed price lump-sum and
time certain contract plus effective project and risk
management mitigates against construction risks; iii)
Close supervision and effective implementation of
ESMP & E&S action plan mitigates against
environmental risks. (refer to section 4.5 for more
details)
INPUTS
Sources of financing:
ADB loan
ADB MIC Grant
Namport
Government Grant
Total
%
[87.2%]
[0.4%]
[5.1%]
[7.3%]
[100%]
UA million
219.91
1.00
12.77
18.44
252.12
ZAR million
2,982.00
14.00
173.00
250.00
3,419.00
PROJECT TIMEFRAME
Management submits the following Report and Recommendation on a proposed loan for ZAR
2,982 million (UA219.91 million) to the Namibian Ports Authority (Namport) to finance the
New Port of Walvis Bay Container Terminal Project in Namibia and a proposed MIC
Technical Assistance Fund Grant for UA1.00 million to the Republic of Namibia to finance
Logistics and Capacity Building activities complementing the Port Project.
I-
ii) Regional integration: the project is potentially serving up to seven major economies
(Namibia, Angola, DRC, Zambia, Botswana, Zimbabwe and South Africa), each of
trade significance to the economy of the sub-Saharan sub-continent. One of the
rationales for the Banks involvement is geographical coverage of the economic
developmental impact that the project brings to the region through trade activities and
spill overs on business and jobs creation. The project also serves to foster South-South
cooperation, and provides the opportunity to strengthen commercial linkages and
promote new trading partners for the region.
iii) Private sector development: the spillover effects of this intervention are private sector
development and employment creation principally in the trade and logistics industry but
also in tourism. The project promotes the emergence of small to medium size
enterprises, scaling up of private investments, increasing productivity and
competitiveness, creation of employment opportunities and promotion of inclusion and
economic transformation.
1.3.2 Apart from the Banks ten year strategy, the project also aligns with the Southern
Africa Regional Integration Strategy Paper (RISP) 2011-2015 and the CSP 2009-2013,
through increased competitiveness and promoting intra and inter-regional trade. It is amongst
the PIDA priorities responding to Southern Africas challenge in developing sufficient port
capacity to handle future demand from both coastal and landlocked countries under the
Southern Africa Hub Port and Rail Programme.
II -
PROJECT DESCRIPTION
C. Ancillary
activities
328
24.22
D. Logistics and
Capacity
Building
14
1.00
3,419
252.12
Total Project
Cost
Component Description
Construction of a modern container terminal consisting of quay
walls, STS (ship-to-shore) cranes, paved areas, buildings, roads,
railway lines and services reticulation.
Supply and installation of RTG (rubber tired gantry) cranes and
relocation of the existing from the current container terminal.
Supply and installation of terminal operating system, communication
system, workstations, electricity supply upgrade, pilot and operator
trainings, etc. to complete the terminal expansion project
The component includes i) developing a national logistics master
plan, ii) a road safety program on transit corridors, iii) capacity
building for the Walvis Bay Corridor Group and the Walvis BayNdola-Lubumbashi Development Corridor Management Committee
and iv) a specialised training for freight forwarders (FIATA training)
Local
Currency
69.61
Total
2,431
Foreign
Exchange
109.71
Foreign
Exchange
%
179.32
61%
20
160
174
278
11.36
8.71
1.48
11.80
12.84
20.51
89%
42%
12
0.31
0.52
0.83
37%
1,764
176
143
1,131
114
91
2,895
290
234
130.10
13.01
10.52
83.41
8.34
6.75
213.50
21.35
17.27
61%
2,083
1,336
3,419
153.63
98.50
252.12
61%
Foreign
Exchange
1,487
Local
Currency
944
154
118
UA (million)
Total
2.5.3 The expansion of the port will be co-financed by the Bank, Namport and the
Government of Namibia. The Bank will finance 87.6% of the total project cost amounting to
ZAR 2,996 million or UA220.91 million. The Banks financing will be in the form of an ADB
Sovereign Guarantee Loan of ZAR 2,982 million (UA219.91 million) and MIC TA Grant of
UA1.00 million (ZAR14 million). Namports counterpart contribution is 12.4% of total
project cost estimate, comprising a grant from the Government of Namibia of ZAR250
million (UA18.44million) or 7.3% of total project cost estimate and Namport contribution of
ZAR173 million (UA12.77 million). Namport has indicated that there are other project
activities up to a total of ZAR300 million which will be financed by Namport. The source of
financing and the project expenditure schedule are summarised in table 2.4 and 2.5
respectively and justification of the Banks contribution of more than 50% of total project cost
estimate is provided in annex I.
Table 2.4: Sources of financing
ZAR (million)
Source
ADB (Loan )
ADB (MIC Grant)
Namport
Government Grant
Total Project Cost
Foreign
Exchange
1,839.00
5.00
98.16.
141.84
2,083.00
Local
Currency
1,143.00
9.00
74.84
108.16
1,336.00
UA (million)
Total
2,982.00
14.00
173.00
250.00
3,419.00
Foreign
Exchange
135.60
0.40
7.21
10.42
153.63
Local
Currency
84.31
0.60
5.56
8.02
98.50
Total
Total
Project
(%)
219.91
1.00
12.77
18.44
252.12
87.2%
0.4%
5.1%
7.3%
100%
Total
Cost
2,431
174
278
12
2,895
290
234
3,419
ZAR (million)
ADB
MIC TA
Loan
Grant
2,236
171
118
12
2,525
253
204
2,982
12
1
1
14
% Bank
% Namport
contribution
& GON
Namport
contribution
& GON
195
92%
8%
3
98%
2%
160
42%
58%
100%
0%
358
36
29
423
87.6%
12.4%
87.6%
12.4%
ZAR (million)
Foreign
Local
Total
Exchange Currency
191.00
59.00
250.00
1,487.00
1,031.00 2,518.00
86.00
41.00
127.00
1,764.00
1,131.00 2,895.00
UA (million)
Foreign
Local
Exchange Currency
14.06
4.33
109.71
76.04
6.33
3.03
130.10
83.41
18.39
185.75
9.36
213.50
% of
total base
cost
9%
87%
4%
100%
Total
176.00
114.00
290.00
13.01
8.34
21.35
10%
143.00
2,083.00
91.00
1,336.00
234.00
3,419.00
10.52
153.63
6.75
98.50
17.27
252.12
7%
3.1.2 The consultant prepared traffic forecasts that are disaggregated by three submarkets:
domestic, transit and transhipment. Transhipment accounts for a major share of the traffic
(60% of container traffic) and has increased rapidly in recent years with an average annual
growth of 55%. In the base case, Namibia is expected to have a compounded GDP growth
rate of 6% from 2014 to 2030. Without the expansion project, Namport will be constrained by
its maximum capacity of 355k TEU.
Table 3.1 : Base Case Volume Traffic Projections (kTEU)
Import
Export
Transhipment
Total
2013
2014
2015
2016
2017
2018
2019
2020
2025
2030
78
62
186
327
80
69
190
339
110
95
223
428
125
114
254
493
142
134
284
561
159
151
315
625
171
161
346
678
183
172
377
732
230
230
369
829
230
230
403
863
Economic Analysis
3.1.3 Three major sources of direct economic benefits have been identified: i) time costs
savings for vessels calling at the port; ii) new employment opportunities for nationals; iii)
time costs savings for freight trucks that transport cargo from and to the port. Estimation of
the third benefit is constrained by the scarcity of relevant statistics and is therefore omitted.
However, given that 50% of the total traffic is transshipment that requires no intermodal
operations, the omission of the time savings to trucks is unlikely to lead to a significant
underestimation of the total economic benefits.
3.1.4 Time costs savings is expected to be shared by Namibian and regional consumers and
exporters, and by international shipping lines. Additional traffic translates into higher earnings
for Namport and its staff, which contribute to additional corporate income tax and labour
income tax for the government. The government will also collect more value added tax
revenue from traffic, and indirect taxes, that would otherwise not materialize in the projects
absence. While taxes are transfers and should not be counted as an economic benefit, they
have a distributional impact and are thus captured in the stakeholder analysis, to explore how
the economic benefits are distributed among stakeholders. These are summarized in table 3.2.
Table 3.2 : Allocation of Projected Benefits among Stakeholders (Present Value, million NAD)
2,839
Namibia
Government
323
Additional labour income
12
Consumers
1,503
Exporters
1,002
1,252
Southern African Region
Consumers
877
Exporters
376
1,252
International shipping lines
3.1.5 The expansion will attract new customers and greater volume from existing ones,
further strengthening Namports role as a transshipment hub and spurring economic activities
in related industries. While the foregoing is important in its own right, the benefits identified
in the previous paragraphs are the most immediate, and can be reasonably well quantified. In
this analysis, additional benefits are omitted thus yielding a more conservative estimate. In
general, the expansion project is estimated to generate for Namibia externalities equivalent to
NAD2,839 million with an economic NPV of NAD498 million and EIRR of 14.6%.
Financial Analysis
3.1.6 From Namports recent audited financial statements, revenues show the impact of the
world trade slow-down owing to the financial crisis. Thus, revenues decreased from NAD 616
million in 2009 to NAD566 million in 2010, but bounced up to NAD755 million in 2012. The
EBITDA exhibited a similar pattern. For the past several years, the debt-equity ratio has been
at low healthy levels and dropped to 0.21 in 2012, indicating strong capacity for additional
borrowing. Since 2011, Namport has been assigned a long term credit rating at A- by Fitch
Ratings and in May 2013, Fitch Ratings reaffirmed Namports credit rating and further
upgraded their outlook from Stable to Positive on account of strong government support and
Namports strategic importance in the Namibian economy. The company has maintained a
high level of liquidity; on average, cash or cash equivalent has been 61% of sales. The
following table presents Namports historical financial indicators and their forecasts.
Table 3.3 : Namport Selected Financial Indicators (million NAD)
TEU (000s)
Total Revenue
EBITDA
Debt to Equity Ratio
CF available for debt service
Total debt service
DSCR
2009
266
616
342
0.31
N/A
75
N/A
Actual
2010 2011
256
224
566
647
241
119
0.35 0.34
N/A N/A
113
171
N/A N/A
2012
292
755
423
0.21
N/A
205
N/A
2014
339
856
687
0.19
622
254
2.45
Forecast
2016 2018 2020 2022 2024
493
625
732
779
822
1,046 1,622 2,030 2,449 2,917
259
671
737 1,175 1,494
1.50 1.61 1.04 0.63 0.35
435
586
619 1,036 1,328
253
228
281
441
407
1.72 2.57 2.21 2.35 3.27
3.1.7 A detailed financial model for Namport corporate financial flows was developed by
their financial advisor for this project. Cash flows of the expansion project were integrated
into the corporate financials. The key indicators for financial and economic performance are
derived from the consolidated corporate model of Namport. The average DSCR, based on
consolidated cash flows and both existing and new debt, is estimated to be 2.02x and the
minimum DSCR is 1.30x in 2015. The second debt service period starts with the first
principal repayment of the new loan in 2019, until 2034. Overall, the projections confirm the
strong debt service capacity of Namport.
3.1.8 While debt service capacity has been evaluated based on overall Namport financials,
the investment viability of the expansion plan is assessed on incremental basis, ensuring that
the expansion decision is judged on its own merit, independently from the existing operations
of the port. Under the base case scenario, the Equity NPV for the expansion project is
NAD216 million at a 12% discount rate (real). The Project IRR for the expansion project is
calculated to be 8.5% while the Equity IRR is estimated to be 15.0% in real terms.
3.1.9 Table 3.4 summarises the key financial and economic indicators for the expansion
project confirming that the new terminal expansion is economically and financially viable.
The forecasts indicate that the project generates sufficient operating cash flow to recoup initial
investment costs and to service debt. The project will also bring additional benefits to other
stakeholders. Furthermore, sensitivity analysis results presented in the technical annex shows
that the project is viable despite adverse shocks.
Table 3.4 : Key Financial Performance Indicators
Economic NPV at 12% EOCK (real)
Economic IRR (real)
Equity NPV at 12% ROE (real)
Equity IRR (real)
Project IRR (real)
10
11
transport, hospitality and tourism industries; a growth in new small and medium size
enterprises; and an increased scope for the marina development.
3.2.6 The project will also result in social risks, such as an influx of workers, truckers and
sailors which would add pressure on available resources and infrastructure; an increased risk
of communicable diseases like HIV/AIDS; behavioural changes leading to greater theft,
prostitution and alcoholism; road safety concerns due to increased traffic; and an inability of
local businesses, with leases in the area being targeted for the marina development, to realize
the full value of their recent investments. Through the comprehensive ESMP it is developing
and the CSR initiatives initiated through Namports Social Investment Fund, Namport will
work to address and diminish the impact of these social risks.
Involuntary Resettlement
3.2.7 The project will not involve either the physical or economic displacement of any
project affected persons. The expansion works will be undertaken on land belonging to the
Government of Namibia with the terminal facility built on reclaimed land inside current port
limits.
IV - IMPLEMENTATION
4.1 Implementation arrangements
Borrower and Executing Agencies
4.1.1 Namport, a body corporate established under the Namibian Ports Authority Act, 1994
(Act No. 2 of 1994) and operating under the State-owned Enterprises Governance Act, 2006
(Act No. 2 of 2006), will be the sole beneficiary of the loan. Namport has operated as the
National Port Authority in Namibia since 1994, and manages the Port of Walvis Bay, the Port
of Lderitz, and a Syncrolift (dry dock facility). Under the terms of the Namibian Ports
Authority Act, 1994, Namport has, in addition to the specific powers vested in it under the
Act, all the powers that may be exercised by a company under Namibias Companies Act.
These powers include, among others, the power to enter into contracts, including contracts
outside of Namibia, and the power to borrow.
4.1.2 Namport has a two-tier governance structure consisting of the Board of Directors and
the executive management. The Minister of Works and Transport appoints Namportss Board
of Directors. The Board of Directors has overall responsibility for the affairs of Namport. The
Board comprises five independent non-executive directors whose terms of office are three
years each. The Board of Directors appoints a Chief Executive Officer (CEO) on a five-year
contract that is renewable at the discretion of the Board. The CEO is responsible for the
execution of strategy and management at Namport, and is assisted by members of senior
management. Under the State-owned Enterprises Governance Act, the Minister of Works and
Transport must enter into a Governance Agreement with Namports Board of Directors that
sets out the roles, responsibilities and obligations of the Ministry and Namport; the latest such
Governance Agreement was entered into on 20th May 2010 for a period of five years.
4.1.3 The implementation arrangements for the Loan and the MIC TA Grant would be
separated whereby Namport would be the executing agency for all the project components
financed under the ADB Loan and the Walvis Bay Corridor Group (WBCG) would be the
executive agency for the component on logistics and capacity building financed under the
MIC TA Grant.
4.1.4 Namport has an existing structure comprising a Project Executive Steering Committee
(PESC) chaired by Namports CEO who oversee strategic decision making and report to the
Board of Directors. The Project Implementation Committee (PIC), headed by the Port
12
Engineer and Projects Manager is responsible for the day to day management and supervision
of project activities and report to the PESC. The PIC comprises Namport experts in all
disciplines for the projects activities, supported by external consultants providing specialist
advisory service. The PESC and PIC already exist and most key appointments have been
made with the remaining positions expected to be filled prior to project commencement. The
Walvis Bay Corridor Group has experience in the implementation of DFI financed projects
and the Project Manager for Spatial Development Initiatives will head the implementation
unit for supervision of this project. The Ministry of Works and Transport and the Ministry of
Finance have identified focal persons who will be responsible for ministerial oversight and
support for this project.
Procurement
4.1.5 Procurement activities will be carried out by Namport and by the WBCG for project
components financed under the ADB Loan and the MIC TA Grant respectively.
4.1.6 The Procurement Unit in Namport is still in the formative stage as it is only 3 years
old and Namport is in the process of filling up the vacant positions. Given the complexity of
the current EPC tender for the port expansion project (detailed below), a specialized team of
consultants have helped Namport to design the EPC procurement process and is currently
carrying out the evaluation. The consultants work under the supervision of the Project
Executive Steering Committee with recommendations presented to the Namport Board for
final decision at each stage.
Procurement for the EPC Works Contract to Construct the New Container Port Terminal
4.1.7 The procurement action for the expansion of the container terminal was initiated in
September 2012. At that time, Namport and the Government of Namibia expected project
financing to be arranged by the bidders though finance from development financial
institutions was also being contemplated. It did not appear that, at that time Namport had any
intention of seeking financing from the African Development Bank and therefore had no
reason to follow the Banks procurement policies and procedures. The situation changed when
the identification mission from the Bank visited them in December 2012 and they were made
aware of the more attractive conditions (including loans in ZAR) that the Bank was offering.
Namport and the Government of Namibia then approached the Bank to provide finance to the
extent of almost 87.6% of the cost of the project.
4.1.8 Invitations to bid for this procurement were locally and internationally advertised in
the print media and online on the Namport website. The bids were received on 18th February
2013 and are under evaluation. The bidding process has gone through stringent diligence
including a mandatory pre-bid meeting and site-inspection by the bidders. The questions from
the bidders were promptly answered.
4.1.9 The current situation that Namport is facing is unprecedented- the Banks support has
been requested for an important para-statal midway through a large and nationally (and
regionally) critical project and the Bank has had no major previous engagement in the country
for large investment lending in this sub-sector. The project is already delayed and the
Authorities have made a compelling case that re-launching of the tender will be very costly
for Namport and Namibia.
4.1.10 As the GoN and Namport have requested the Bank to finance a procurement that has
not been conducted using the Banks Procurement Rules, the Bank undertook independent
reviews and due diligence of the procurement process to ascertain if the procurement is likely
to meet global industry standards and the Banks procurement principles. For this purpose, the
Bank commissioned two independent procurement consultants to support Bank Procurement
Specialists in carrying out the due diligence. The review has concluded that while the
13
procurement process was rigorous and detailed, and did not appear to deliberately favor any
bidder or set of bidders, there were departures from the Banks procurement principles. (Some
of the deviations included (i) Namibian dollars as the payment currency irrespective of the
nationality of the bidder;(ii) the contract prices being fixed despite the contract period being
three years; (iii) bid-evaluation that allowed Namport to use unspecified criteria if it felt it was
in its best interest; (iv) bespoke contract provisions that transferred significant risks to
contractors; (v) commercial arbitration to take place in Namibia and not in a neutral place.
4.1.11 The Walvis Bay expansion project has evident economic benefits for the region and
timely completion of the project is key for such benefits to be realized. The preferred
alternative (of the Bank) of rebidding of this procurement would mean a delay of many
months in the commissioning schedule for the project. This would have serious and
unacceptable impact on the economy of Namibia and the region and is not acceptable to
Namport and the Government of Namibia. A flexible and pragmatic approach, may therefore,
be necessary for this first time engagement with Namport. It would, therefore, appear that
there might be merit to allow the present process to be completed as started and to ask for
modifications in some key contractual provisions to include Banks rights with respect to
Fraud and Corruption and for the Banks right to audit.
4.1.12 Given on the need to speedily execute the above project and the diligence to ensure
that the contractors and subcontractors who would be awarded the contracts are not debarred
or suspended at the time of contract award or signing, and the incorporation of F&C and
Audit Rights provisions in the contracts before signature, Board approval is sought to grant a
waiver from the application of the Banks Procurement Rules and to approve to finance the
EPC works contract for construction of the new container terminal at Walvis-Bay to be
awarded by Namport using a bespoke procurement process and contract. This waiver is being
sought only for the EPC works contract.
Procurement of equipment, ancillary services and logistics and capacity building
4.1.13 With the exception of the EPC main works contract, the procurement of all project
components namely: equipment, ancillary services and logistics and capacity building support
will be done in accordance with the applicable Banks Rules and Procedures for the
procurement of Goods and Works and the Banks Rules for the use of Consultants. The
details of the procurement arrangements are summarised in the technical annex.
Financial Management
4.1.14 The Project loans financial management will be implemented by Namport within its
existing set-up for project implementation under the overall management of the Board of
Directors whereas WBCG will be responsible for the Grant. An assessment of Namports and
WBCGs financial management arrangements for the implementation of the project (which
included a review of the budgeting, accounting, internal controls, flow of funds, financial
reporting and auditing arrangements) indicates that they satisfy the Banks minimum
requirements to ensure that the funds made available for the financing of the project are used
economically and efficiently and for the purpose intended. In addition, internal and external
audit requirements are further measures towards effective corporate governance.
4.1.15 In accordance with the Banks reporting and auditing requirements, Namport and
WBCG will be required to submit Quarterly Progress Reports (within 30 days after the end of
each quarter) and annual audit reports with financial information for the Loan and Grant
respectively. Furthermore, separate annual audit reports with financial information (with the
audit done in accordance with a Bank approved audit ToR) will be prepared by the respective
implementing entities in compliance with their internal legal requirements. The audit costs
will be borne by the respective implementing entity and the audit reports together with the
14
auditors management letter indicating any weakness in internal control including the
responses from management will be sent to the Bank within six (6) months of the end of the
respective fiscal year. (A draft audit TOR that can be used as a guide has been availed to
Namport). In addition, Namports annual audited financial statements will also be submitted
together with the project audit report and the project management letter.
Disbursement Arrangements
4.1.16 The Loan will be disbursed for two categories of expenditure including Works and
Goods with a provision for future consulting services, if any. The MIC TA Grant will be
disbursed for two categories of expenditure including Goods and Services. The Direct
Payment and Reimbursement Guarantee Methods will be used as payment method under the
ADB loan and the Special Account method will be applied for the MIC TA Grant.
Disbursements under the Loan and Grant would be made in accordance with the list of goods,
works and services and the Banks rules and procedures as laid-out in the Disbursement
Handbook insofar as may be applicable.
4.2 Monitoring
4.2.1 The outline of the project implementation schedule takes into account the relevant
experience of the PIC and WBCG in managing works implementation deadlines and that of
the Bank in processing previous similar projects. According to the estimates, project activities
will start (upon approval of the loan and grant) in the last quarter of 2013 and end towards the
end of 2016. The grant and loan closing dates are scheduled for end of 2017 and 2019
respectively. At the level of the Bank, the activities planned following loan and grant approval
will be closely monitored, in accordance with the schedule in Table 4.1 below.
Table 4.1 : Schedule for Project Monitoring
Timeframe
Milestone
Q4 2013
Q2 2014
Q4 2014
Q2 2015
Q4 2015
Q2 2016
Q4 2016
Q4 2017
Project Launching
Construction start + 6 months
Construction + 14 months
Construction start + 20 months
Construction start + 26 months
Construction start + 32 months
Construction start + 36 months
Defects Liability and end of 1st yr
Field Mission,
Field Mission,
Field Mission,
Mid-Term Review,
Field Mission,
Field Mission,
Project Completion,
Project Evaluation,
Progress Reporting
Progress Reporting
Progress Reporting
Progress Reporting
Progress Reporting
Progress Reporting
Completion Report
M & E Report
4.2.2 Apart from the schedule for monitoring activities, the PIC will regularly provide the
Bank with quarterly project progress reports covering all project activities including
implementation of the ESMP and the status of the log-frame indicators, annual audit reports
as well as the final project report; all in the Banks standard format. The comprehensive
ESMP and other actions in the E&S Action Plan will be implemented by Namport (by the
Environmental Manager and Officer) and the selected contractor (by Environment, Health and
Safety, Fire and Waste Management Officers). The Ministry of Environment and Tourism as
the ESIA licencing authority will monitor environmental and social performance on the basis
of the required ESMP compliance reports. Project monitoring will be carried out by the
Banks supervision missions, in line with the Banks Operations Manual.
15
4.3 Governance
4.3.1 Namibia has consistently ranked among the top African countries on good
governance. The country has consistently scored at least 4 out of 5 in all the categories of
Bank Groups Country Policy and Institutional Assessment (CPIA), with the exception of
property rights and rule based governance. In addition, Namibia has been ranked: i) between
the 50th-75th percentile out of the 212 countries by the World Banks 2011 Worldwide
Governance Indicators; ii) 6th out of 53 African countries, with an overall score of 67.3 out of
100, by the 2010 Mo Ibrahim Index of African Governance; and iii) 4th and 5th least corrupt
country in Southern Africa and SSA, respectively, by the 2010 Corruption Perception Index
by Transparency International.
4.3.2 Namport has adopted the principles of good corporate governance as contained in the
King Report 2009 (King III). The Authority is overseen, managed and controlled by a
Board of Directors on behalf of the government and has overall responsibility and
accountability for the affairs and performance of the Authority. The Authoritys Board is
appointed by the portfolio Minister of Works and Transport (MWT) who has the overall
responsibility for policy and regulation, and the Ministry of Finance who has an oversight role
in Namports financial and project development activities. The specific governance risk
mitigation measures of the present project include: (i) the appointment of financial and
technical audit firms to ensure that funds are used efficiently and for the intended purposes;
(ii) Bank prior review and approval of all project procurement activities; and (iii) the use of
direct disbursement methods to channel project funds to contractors and service providers.
4.4 Sustainability
The expansion of the port is expected to be a long-term self-sustaining economic
activity that generates sufficient financial return to cover all operating costs, taxes,
maintenance expenses, and repayment of debt and recovery of capital costs. While regular
maintenance costs for both terminals are planned to be funded by operating cash flows, the
business plan for the new terminal explicitly makes a provision for a Maintenance Reserve
Account (MRA) that will be accumulating the necessary amount of funds for equipment
replacement and purchases of additional equipment. The accumulation of funds will be spread
over five years prior to the expected time of maintenance activities, which minimizes the risk
of dependency on cash flows of a single year. Table 4.2 presents the actual, past and projected
maintenance costs, for the existing and the new terminal. It is noted that the same trend of
maintenance expenditures is expected to continue.
Table 4.2 : Historic and Projected Terminal Maintenance Costs
Maintenance costs
2009
Actual
2010
2011
2012
2016
2017
Existing terminal
New terminal
Revenue
Operating costs
Assets
As % of revenue
As % of operating
costs
As % of assets
24
N/A
616
280
2,031
3.8%
34
N/A
566
344
2,288
6.0%
29
N/A
647
362
2,879
4.5%
32
N/A
755
465
2,606
4.3%
42
27
1,046
701
5,553
6.6%
44
114
1,418
865
5,355
11.2%
53
137
2,030
1,063
6,002
9.3%
71
214
3,118
1,447
9,395
9.1%
95
286
4,239
1,909
16,372
9.0%
8.4%
10.0%
8.1%
6.9%
6.0%
5.1%
5.0%
4.9%
5.0%
1.2%
1.5%
1.0%
1.2%
0.8%
0.8%
0.9%
0.8%
0.6%
16
Projection
2020
2025
2030
4.6.2 The logistics master plan will provide a comprehensive logistics policy and system
development plan for Namibia with the target year of 2030 that will be a shared vision and
common implementation platform for the public and private sectors. Freight forwarders are
often the one-stop-shop interface between shipping lines, customs and road carriers. It is
therefore important to ensure that the professional competence of the industry is up-to-date
and meets customers requirements. The Project will address this by organizing FIATA
training particularly for female in-service freight forwarders and persons who intend to enter
this business.
V-
VI - RECOMMENDATION
6.1.1 Management recommends that the Board of Directors approve:
(i) the proposed loan of ZAR 2,982 million to Namibia Ports Authority (Namport), with
the guarantee of the Republic of Namibia for the purposes and subject to the
conditions stipulated in this report; and
(ii) the proposed MIC Technical Assistance Fund grant of UA 1.00 million to the
Republic of Namibia for the purposes and subject to the conditions stipulated in this
report; and
(iii) a waiver from application of the Bank Groups Rules and Procedures for Procurement
of Goods and Works solely with respect to the EPC main works contract for the
construction of the new terminal which was procured using a bespoke procurement
process and contract adopted by the Borrower.
19
Year
Namibia
Developing
Countries
Africa
Developed
Countries
Charts
Basic Indicators
Area ('000 Km)
824.3
30,046.4
80,976.0
54,658.4
2012
2.4
1,068.4
5,628.5
1,068.7
2012
39.2
40.8
44.8
77.7
4000
2012
2.8
34.5
66.6
23.1
3000
2010
4,500.0
1,548.9
2,780.3
39,688.1
2000
2012
40.3
37.8
0.0
0.0
1000
2012
46.2
42.5
39.8
43.3
2007
0.7
0.5
..
0.9
2012
128.0
3,972.0
..
..
2004
31.9
158.1
25.0
..
2012
1.7
2.3
1.4
0.7
2012
3.3
3.4
2.4
1.0
2012
35.5
40.0
29.2
17.7
2012
3.8
3.6
6.0
15.3
2012
64.8
77.3
52.8
..
2012
98.9
100.0
934.9
948.3
2012
26.0
48.6
53.3
47.2
2012
62.6
58.1
65.7
79.8
2012
63.0
59.4
68.9
82.7
2012
25.4
34.2
21.5
12.0
2012
8.2
10.9
8.2
8.3
2012
30.4
70.8
53.1
5.8
2012
40.6
111.3
51.4
6.3
2012
3.1
4.3
2.7
1.8
2010
200.0
402.3
440.0
10.0
2012
57.1
31.6
61.0
75.0
5000
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
Namib ia
Africa
Demographic Indicators
1.5
0.5
0
2012
2011
2010
Namib ia
Africa
2010
37.4
53.6
77.0
287.0
2007
277.5
905.0
98.0
782.0
2007
81.4
1,472.2
39.0
99.3
2010
93.0
65.7
84.0
99.6
2000
59.0
65.2
80.0
100.0
2010
32.0
39.8
54.6
99.8
2011
13.4
4.6
161.9
14.1
2011
723.0
234.6
..
..
2011
89.0
81.7
89.0
99.0
2011
74.0
76.6
76.0
92.6
2007
17.5
63.6
27.0
0.1
2009
2,151.0
2,568.8
2,675.2
3,284.7
2010
6.8
5.9
4.0
6.9
..
..
..
..
2010
106.8
101.9
106.0
101.5
2010
106.1
98.1
104.6
101.2
140
2007
64.0
42.3
62.3
100.3
120
2007
69.3
38.5
60.7
100.0
2010
68.2
43.7
..
..
2010
88.8
67.0
19.0
..
80
2010
88.5
58.3
..
..
60
2010
89.0
75.8
..
..
2010
8.3
5.3
..
5.4
100
90
80
70
60
50
40
30
20
10
0
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
Namib ia
Africa
Education Indicators
Gross Enrolment Ratio (%)
100
40
20
Environmental Indicators
0.9
0.6
0.4
-0.2
..
..
..
..
1.6
1.2
..
..
2009
Sources : ADB Statistics Department Databases; World Bank: World Development Indicators
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
Note :
Namib ia
2007
2000
2006
2005
11.6
2004
9.9
2003
8.4
2002
1.0
2001
2011
2000
Africa
Support to Aquaculture
Development
Namibia Airport Study
Human Resources
Development Plan
Statistical Capacity Building
(SCB-II)
TRUSTCO Finance
Main
Sector
Window Approval
Date
Disburse
Deadline
Amount
Approved
(UA m)
Amount
Disbursed
(UAm)
Disbursed
Rate
(%)
05.06.09
30.05.12
0.26
0.26
99.2
20.07.10
31.12.12
0.59
0.08
13.1
MIC
Fund
09.10.09
31.03.12
0.60
0.54
89.5
MIC
Fund
07.07.11
31.12.13
0.49
0.00
0.00
Agriculture
(OSAN)
Transport
(OITC)
Institutional
Support
(OSHD)
Institutional
Support
(ESTA)
Private
Sector
(OPSM)
MIC
Fund
MIC
Fund
Private
Sector
07.12.12
TBD
4.8
3.29
68.5
Health
(OSHD)
MIC
Fund
12.03.12
31.12.13
0.50
0.00
7.24
4.16
57.5%
Appendix III. Key Projects financed by the Bank and other DP in the country
Table Summarising Grants
Development
Partner
Subsectors/Programmes
China
132,752,400.00
France
Germany
5,374,469.38
425,014,800.00
Spain
Sweden
USA
Multilateral UN
European
Union
World Bank
GRAND TOTAL
Development
Partner
Commitments for
2011/2012 (N$)
55,216,179.00
35,790,045.69
401,808,861.00
91,685,175.00
256,161,168.00
20,130,273.09
1,423,933,371.16
Commitments for
2011/2012 (N$)
China
Construction
177,680,000.00
Finland
Fisheries
320,000,000.00
Germany
285,207,300.00
Japan
Transport
343,096,716.53
TOTAL
1,125,984,016.53
Annex I
I. REVIEW OF COUNTRY PARAMETERS FOR ELIGIBILITY FOR BANK FINANCING
1.1 Countrys Commitment
Has the Government demonstrated willingness to participate in project financing by efficiently
mobilizing Counterpart Funding?
Yes. The Government is providing: i) a Sovereign Guarantee against the ADB loan to Namport and
ii) providing a grant to the project of 250 million NAD (7.3% of total project cost).
Is the Government interested and actively involved in the implementation of the project?
Yes. Namport is under the purview of the Ministry of Works and Transport and its board is
appointed by the Minister and regularly reports to him. The project also includes a component on
logistics and trade facilitation funded by a Bank MIC TA Grant. This activity will involve different
government stakeholders including the National Planning Commission and Ministry of Works and
Transport during project implementation.
Is the project in a sector of priority under the Poverty Reduction Strategy?
Yes. The development agenda of the Government is contained in the Fourth National Development
Plan (NDP4), covering the period 2012/13-2016/17. NDP4 has identified logistics, as one of the
economic priorities and the Walvis Bay Port Expansion Project is clearly identified as one of the
national priorities under the Logistics pillar.
Has there been progress in achieving the Poverty Reduction Strategy objectives?
Yes. Namibia has made significant progress in addressing many development challenges. Access to
basic education, primary health care services, and safe water is high and growing. Sound public
policies are helping to lay the foundation for gender equality. Namibia maintains social safety net
programs for the elderly, disabled, orphans, vulnerable children, and war veterans, and has enacted a
Social Security Act that provides for maternity leave, sick leave, and medical benefits to Namibians.
Although Namibia is on track to meet the Millennium Development Goals on education,
environment and gender, the severity of the HIV/AIDS epidemic is frustrating efforts to meet the
Millennium Development Goals (MDGs) to reduce child mortality (MDG4), improve maternal
health (MDG5), and combat HIV/AIDS, malaria and other diseases (MDG6).
1.2 Countrys Financial Allocation to Sector
Is the countrys public expenditure allocation giving high priority to the sector concerned?
Yes. The Government has in the past few years allocated between 8%-10% of the national budget to
the transport sector. The sector is allocated NAD8.2 billion over the Medium-Term Expenditure
Framework covering the period 2011/12-2013/14 for, among others:- expansion of the port of
Walvis Bay, rehabilitation and railway infrastructure management, and development and
maintenance of national roads infrastructure.
1.3 Countrys Debt Level and Budget Situation
Can the country sustain additional debt and how is the current debt being managed?
The authorities project total debt stock to remain at about 27% of GDP in 2012, below Namibias
35% statutory debt-to-GDP threshold. Namibias debt levels remain sustainable, and can therefore
sustain additional debt. For Namport, an analysis on its capacity to borrow for this project shows
high debt service coverage ratios (DSCRs). For the existing loans that fully mature in 2018, the
average DSCR is 2.02x while the minimum is 1.30x. For the new loan, the average DSCR is 3.55x
and the minimum is 1.82x. The project is self-sufficient in debt servicing and no additional debt
burden is expected to fall on the government.
To what extent is the Government receiving co-financing from other donors?
Many bilateral donors scaled down their support to the country following its classification as an
upper MIC. The level of co-financing from donors is not significant relative to the national budget.
Annex II
II. NAMIBIA - COUNTRY OUTLOOK
General Overview
Namibia is a middle income country that has enjoyed considerable successes since it gained independence
from South Africa in 1990 resulting from sound economic management, good governance, basic civic
freedoms, and respect for human rights. Namibia inherited a well-functioning physical infrastructure, a
market economy, rich natural resources, and a relatively strong public administration. The country also
inherited extreme social and economic inequities, however, which have left Namibia with a highly dualistic
society. Namibias per capita income of US$4,700 (2011, Atlas method) places it in the World Banks
upper-middle income grouping. However income distribution is among the most unequal in the world, with
a Gini coefficient estimated at 0.5971 by the latest (2009/10) household survey. Poverty incidence is high,
although it has declined somewhat during the past decade: 29% of individuals had consumption below the
national poverty line in 2009, compared to 69% in 1993.2
Economic Overview
Namibias economy is closely linked to South Africas economy through trade, investment, and common
monetary policies. The Namibian dollar is pegged to the South African rand, making economic trends
(including inflation) closely follow those in South Africa. The Namibian economy slowed down in 2011
with a GDP growth rate of 3.8%3, down from 6.6% in 2010, reflecting modest performances in mining and
agricultural activities. Prospects for the medium-term remain favourable with GDP growth projected to
continue on its path of recovery to an average of 4.2 percent for the years 2012 and 2013, driven by
construction, livestock and crop farming, manufacturing and mining. After years of fiscal surpluses arising
from prudent macroeconomic policies, the fiscal situation has deteriorated substantially, reflecting the
global economic crisis and expansionary policies to support growth. The budget for 2011/12 provides for
the continuation of the expansionary fiscal policy for the fourth successive year as the Government
commences the implementation of the three-year Targeted Intervention Programme for Employment and
Economic Growth (TIPEEG), totaling 14.7 billion Namibian dollars (NAD), aimed at creating and retaining
104, 000 jobs. As a result, the fiscal deficit is expected to widen, averaging nearly 6.5% of GDP between
2011/12 and 2012/13. The deficit is financed by domestic borrowing and foreign debt. Namibias debt
levels have risen in recent years, but remain sustainable and below the 30% threshold, despite the
expansionary fiscal policy.
Development Plans
In July 2012, the GRN launched the Fourth National Development Plan (NDP4), which will guide policies
through 2017. Economic growth, job creation, and increased income equality are the three overarching
objectives of NDP4. It proposes to achieve these objectives through industrial policies to stimulate growth
in tourism, regional trade logistics, agriculture and manufacturing (primarily through greater processing of
primary commodities). Reducing extreme poverty and improving education, health, infrastructure, and the
business environment enter into NDP4 as basic enablers that support the economic priorities. NDP4
presents ten desired outcomes, each accompanied by an indicator for measuring attainment of the
outcome, broad strategies expected to achieve the outcome, and a ministry that will serve as the champion.
This selectivity stands are in stark contrast to previous NDPs, whose agendas spanned the entire public
policy space.
2
3
Annex III
III. THE WALVIS BAY PORT
Ports and maritime in Namibia
Namport operates as the National Port Authority in Namibia since 1994 and manages both the Port of
Walvis Bay and the Port of Lderitz in Namibia. The Port of Walvis Bay is situated at the west Coast of
Africa and provides an easier and much faster transit route between Southern Africa, Europe and the
Americas. The Port of Walvis Bay is Namibia's largest commercial port, receiving approximately 3,000
vessel calls each year and handling about 5 million tonnes of cargo. The port has good port infrastructures
which can be ranked among the best in Africa; together with tariffs which are still competitive compared
with their main competitors. These enable Walvis Bay to take advantage of the congestion and poor
productivity in Eastern and Southern African Ports (Tanzania, Mozambique, Angola and to a lesser extent
South Africa).
Recent performance
Namport achieved a record throughput of containers in 2012 of more than 337,000 TEUs4 and overall
cargo volumes exceeding the 6 million ton mark for the first time ever. Revenue concomitantly also
exceeded N$700 million. Namport has regained higher volumes per vessel and the number of container
vessels has plateaued at around 46 per month on average (annualised at 560). This is the maximum number
of vessels that can be handled at present.
Namports opportunity and key differentiator remains in the SADC region. The economic growth in the
region exceeds that of most traditional markets and is the key to the companys sustainability. The
opportunity remains in expanding intra-regional trade which is currently well below potential due to poor
infrastructure, lack of harmonisation of trade policies and cumbersome border procedures. The appointment
of the Walvis Bay Corridor Group to spearhead the recently established tri-partite Walvis Bay Ndola
Lubumbashi Development Corridor is testimony to the commitment of Namibias neighbouring countries to
regional integration.
Nature of the Transhipment Business at Namport
A significant share of the traffic in Walvis Bay is transhipment traffic (constituting 60% of container traffic)
particularly to / from ports in western and central Africa (including Angola) and transit traffic to/from
neighbouring countries (mainly South Africa and Angola) constitutes 34% of total shipments. The main
trading partner for imports are China (34%), Germany (16%) and USA (4%) and exports Spain (27%),
4
-1-
China (11%), Germany and UK (7% each). Transshipment traffic has grown from 92,000 TEUs in 2006 to
218,000 TEUs in 2012 with an average annual growth rate (AAGR) of 55%. Transit traffic has also grown
over the same period from 25,000 TEUs to 65,000TEUs with AAGR of 25%. Some of the capacity issues
that Namport experience are largely a result of the increasing transhipment business. Transhipment demand
relates to a broader, regional market and in Namports case to the development of the countries to the north
of Namibia, right up to Ghana in West Africa. It is a function of the hub-and-spoke distribution model,
employed increasingly by the large international shipping lines.
African Shipping Activity
There are 24 container liner shipping operators in the West Coast of Africa region. This trade is dominated
by 3 large shipping lines: Maersk, CMA CGM and MSC in order of their respective share of trade capacity.
Combined, they offer 73% of all trade capacity in this region with Maersk and CMA CGM being the most
dominant. These 24 shipping lines operate 71 services to-and-from the region with a calculated trade
capacity of 3 656 000 TEUs annually. The largest carrier by trade capacity is Maersk with 38% market
share.
i) This region is further separated into service types of:
ii) West Africa Far East
iii) West Africa Middle East / Indian Subcontinent
iv) West Africa Southern Africa
It is in the latter region that Walvis Bay dominates. Walvis Bay and Cape Town account for 80% of the
regions trade capacity. This goes some way towards explaining Namport and Walvis Bays rapid
improvement in another important shipping index: Liner Shipping Connectivity Index. In the past 7 years,
Namibia has improved from position 102 (out of 148 countries surveyed) to position 75. That is the same
positioning as countries like Kenya and Tanzania that enjoy centuries old trade routes
Competing Ports
Walvis Bay port has good port infrastructures which can be ranked among the best in Africa together with
tariffs which are still competitive compared with their main competitors. This enables the port to take
advantage of the congestion and poor productivity in Eastern and Southern African Ports (Mozambique,
Angola and to a lesser extent South Africa) and position itself as a transhipment port whilst also competing
for transit traffic with the other ports in the region. Out of South Africas eight ports, two are likely
competitors for Namibian ports, namely, Durban (for the traffic generated by the Gauteng province via the
trans-Kalahari) and Cogea for the transhipment traffic. The ports of Luanda, Lobito and Namib are
Angolas main ports but considered not to pose significant threat in the short term due to its obsolete
infrastructure and inefficiencies (40 days waiting before berthing has been reported). A market study
conducted by Nathan Associates on the competing ports in the region has shown Walvis Bays potential to
become a regional hub port if it takes advantage of its current window of opportunity to expand and capture
the rising market demand whilst the government provides the complementary support of hard and soft
infrastructure. Other ports considered include the ports of Lagos/Apapa, Dar es Salaam Port, Port of Cape
Town, Port Elizabeth and Port of East London. Whereas some of these ports mostly serve local
import/export or transit, Walvis Bay is mainly focusing on transhipment cargo whilst also promoting the use
of its transport corridors to transit cargo for its landlocked neighbours and including the hinterlands of
Angola though the transcunene corridor. Although Cape Town is the closest South African port to Walvis
Bay and therefore could be considered its main competitor, it handles a very small volume of transshipment
and its capacity is limited.
The Walvis Bay Corridors and Group
The Walvis Bay Corridor Group is a public-private partnership established to promote the utilisation of the
Walvis Bay Corridors. This allows it to pool resources and authorities of both transport regulators and
transport operators, thus effectively serving as a facilitation center and one-stop shop coordinating trade
along the Walvis Bay Corridors and linking Namibia and its ports to the rest of the Southern African region.
-2-
The Walvis Bay Corridor Group, is governed by a Board of Directors drawn from the different public and
private stakeholders within the transport and logistics sector. The Strategic focus and mandate of the WBCG
is: Business Development, Trade Facilitation, Infrastructure Development, Wellness service and Spatial
Development Initiatives (SDIS) for the Walvis Bay Corridors
Logistics and Trade Facilitation
International comparisons show that, Namibia is one of the most efficient logistic environments of southern
Africa ranked 89th worldwide (and 3rd position in the SADC region in 2012) after South-Africa (ranked
24th) and Botswana (ranked 68th)). Many improvements have been made in the last few years on
infrastructures, logistics competences and customs facilitation. Logistics issues in Namibia relate more with
international than with domestic traffics. In this regard, Namibia promotes several international transport
corridors crossing the country mainly from the port of Walvis Bay. Since Namibian roads along these
transport corridors are still in relatively good condition, in particular as compared with African standards,
the main challenge is the improvement of cross-border facilitation procedures. Namibian authorities are
very proactive and significant progresses have been made to simplify and harmonize custom procedures.
The following main achievements and on-going projects must be mentioned:
A Single Administrative Document (SAD) has been adopted and is used on the trans-Kalahari corridor.
The development of a One-Stop Border Post (OSBP) is on-going on the main corridor (trans-Kalahari) as
a pilot project. It is planned to be operational in 2013 and it is contemplated that this system is
extended in the future to other border crossing on the trans-Cunene and trans- Caprivi.
Implementation of an electronic data exchange system between countries is under discussion and is
planned to be operational in 2013 at the OSBP between Namibia and Botswana.
The development of dry ports has started within the port of Walvis Bay. Even though the opportunity of
developing such dry ports within the perimeter of the port where there is a serious shortage of storage
areas, in particular for dry cargo, may be questionable, it is time now to take full benefit of these
facilities and to optimize their functioning.
Creation of the Walvis Bay Corridor Group (WBCG), a public and private sector collaboration, is aimed
to promote development of corridor infrastructure, businesses and trade facilitation, corridor best
practices and safe trade and transport corridors is continuing to yield results
Increasing presence in the region and internationally through WBCG regional offices in Lusaka,
Johannesburg, Lubumbashi and Sao Paulo is increasingly drawing businesses through the Walvis Bay
corridors;
Formulation of formal tripartite MoUs and partnerships on the Trans-Kalahari and Trans-Caprivi
corridors
The next steps forward include the following:
i) Increase volume and speed to maximize advantage:
Port of Walvis Bay becomes a regional hub port
Increase transportation capacity to inland (strengthen resource based bulk cargo)
Better trade facilitation (set up OSBP at all borders)
ii) Preparation for Strategic Master Plans for Logistics and Regional Urban Centres
iii) Global promotion of Walvis Bay to attract logistics/ distribution companies.
iv) Implementation of Development of Strategic Hubs
Development of logistics hubs based upon National Logistics Master Plan, further promotion of
trade facilitation (Single Window & Port Community System).
Development of regional urban centres based upon Master plan on development of regional urban
centres (Land Use Plan, Urban Infrastructure).
v) Diversification of Industries
Attract diverse industries due to excellent position as an international logistics hub.
Optimise growth of transit as well as transhipment traffic via the Port of Walvis Bay.
-3-
Annex IV
IV. PROJECT DESCRIPTION
New Terminal Construction:
The proposed project is the strategic expansion of the Walvis Bay Container Terminal that will see the
creation of 30 hectares of new land reclaimed from channel at Walvis Bay. The new reclaimed land will be
created by dredging/deepening the port and using the sand obtained from deepening to form the new land.
The reclaimed land will be linked to the existing port land by a causeway. A new modern container terminal
will then be built on top of the newly reclaimed land and will consist of quay walls, paved areas, buildings,
roads, railway lines, ship to shore quay cranes, rubber tired gantry cranes, etc. The new container terminal
will have a capacity of 650,000TEU p.a. to complement the 355,000TEU p.a. capacity of the existing
container terminal, giving the Port a total capacity of 1,050,000TEUs with adequate space for optimisation
and future expansion. The project will not only provide increased container handling capacity in Walvis
Bay, but will also increase the ports bulk and break handling capacity by freeing up the existing container
terminal to become a multi-purpose terminal. Once built, the conversion of the existing container berths into
a multipurpose terminal would open the port up for increased scope to accommodate a wide range of
additional bulk cargo vessels and even passenger liners.
Most of the quay wall infrastructure in the Port of Walvis Bay is very old and some of these reinforced
concrete structures have already reached the end of their design life. Namport has thus scheduled major
rehabilitation of these structures to occur within the next 10 years. The new container terminal project will
add an additional 600m of quay wall length to the existing 1800m and this will enable major rehabilitation
of existing quay walls to occur with minimal disruption to normal operations. The business case for the
project has been proven in a number of comprehensive studies that were undertaken as far back as 1980 and
of which the last of these preparatory studies were completed in November 2011. To date more than N$60
million has been committed to this project in conducting preparatory studies and investigations. The project
implementation period is three years
Logistics and Capacity Building financed by the Banks MIC TA Grant:
National Logistics Master Plan: The study will provide a comprehensive logistics policy and a system
development plan for Namibia with the target year of 2030. The activity includes amongst others: 1)
review of current situation of logistics; 2) analysis on prevailing business models of international logistics in
SADC; 3) analysis of commodity flow service in Namibia; 4) analysis of potential industries and business
models; 5) prefeasibility study on inland logistics park and on One Stop Border Post; 6) Integration of
ICT to facilitate and accelerate the growth in the transport and logistics sector and 7) Formulation of an
Action Plan for implementation and monitoring of the Logistics Master plan. The period of implementation
is 9 months.
Road Safety Program in SADC: The road safety program will replicate the Safe Trade and Transport
Corridors Project (executed on the Trans-Kalahari and Trans-Caprivi Corridors) on the Trans-Cunene
Corridor (TCuC) between Namibia and Angola. The activity will include: 1) support WBCG for the design
and implementation of a road safety action plan; 2) design and implementation of a road safety
assessments/audits; 3) design and implement a monitoring system to measure the impact of the road safety
action plan in the TCuC; 4) organize meetings with the authorities concerned and the public parties involved
to ensure adequate cooperation; and 5) disseminate information about the road safety action plans. The
project implementation is 9 months spread over a period of three years.
Capacity & Institutional Building for Walvis Bay-Ndola-Lubumbashi Corridor Management Committee
(WBNLD CMC): The WBNL or Trans Caprivi Corridor via Namibia is important for the Democratic
Republic of the Congo and Zambia. The Walvis Bay Corridor Group (WBCG) serve as the secretariat for
this corridor co-operation and hosts dialogue and meetings among the three countries based on a trilateral
Memorandum of Understanding. The Interim Secretariat hosted by the WBCG will be supported by
providing technical assistance over a period of three years. This activity will also cover coordination,
hosting of meetings, travel and procurement of Information Technology Equipment and Software, Digital
Cameras, Scanners, Data Projectors and DVD Player / Recorders for the Committee.
Capacity and Institutional Building for WBCG Projects Development & Funding Department: This activity
builds capacity and support to the Walvis Bay Corridor Group Projects Development & Funding
Department to ensure ongoing transport facilitation advocacy activities on the countrys regional corridors.
The activity includes: 1) Technical assistance during three years, 2) travel & lodging, 3) organizing and
participating in conferences / Workshops / Seminars to present WBCG project portfolio, 4) Short-term
trainings and 5) Procurement of Information Technology Equipment and Project Management Software,
and Digital Cameras, Scanners, Data Projectors and DVD Player / Recorders. The implementation is over a
period of 3 years.
FIATA Training Program for Freight Forwarders: This activity will strengthen the professional competence
of Namibian freight forwarders in order to ensure that affordable and high-quality logistics services are
available for the needs of the users of the Walvis Bay corridors. The activity will: 1) assess detailed training
needs of registered freight forwarders in Namibia, 2) provide minimum 70 freight forwarders with FIATA
certified training, 3) compile a report for future actions in promoting logistics competence among freight
forwarders in Namibia. Priority in access to the training will be given to (i) female in-service freight
forwarders, (ii) female persons in related industries that are likely to benefit from the FIATA training and
(iii) female persons who intend to enter freight forwarding business. The target number of women to receive
the FIATA training is 40 out of the 70 trainees.
Annex V
V. ENVIRONMENT AND SOCIAL
Environment and Social Action Plan (to be fulfilled before 30th September 2013 as a condition of the
Loan):
i)
ii)
A report on the analysis of the impacts of the project on services such as water, electricity, health
services.
A plan of how the inclusion of the projects workforce will be serviced by the currently existing
HIV/AIDS programs.
An comprehensive Environmental and Social Management Plan (ESMP), that must among others
entail a detailed waste management plan; a business continuity plan; a hazards (especially
technological) management plan; and a detailed plan for better assessing and monitoring the socioeconomic impacts of the project.
A report on the cumulative impact assessment for the project considering all other developments
planned for the foreseeable future.
A report on gender analysis and a plan in order to align with the countrys gender equality plans and
if none exist in the country, the regional or international best standards to be applied.
A climate change adaptation plan for the project that is in line with the National Climate Change
Action Plan.
iii)
iv)
v)
vi)
vii)