Académique Documents
Professionnel Documents
Culture Documents
upgrudc.
PE-809-PWRD-0-O6-1997 A paper recommended and approved by
the lEEE Transmission and Distribution Committee of the IEEE Power
Engineering Society for publication in the IEEE Transactions on Power
Delivery. Manuscript submitted December 26, 1996; made availabie for
printing June 11, 1997.
a sectionalizing switch S12 and closing the tie switch SI5. That
is, closing a switch should always be followed by the opening of
a switch.
From [15], the power loss in the line section between two
where
AVn : the voltage drop between two terminis of Branch N
AV2av : the mean square voltage drop of all branches for a
chosen loop co
: weighing factor
The voltage ndex \^ is depicted in Figure 2 to show the
degree of each branch voltage drop.
where
Start
Weighing factor co
For a loop created by closing a specific lie switch, a weighing
factor co is defined for each sectionalizing switch according to its
distance to this specific tie switch. If there are m number of switches
in a loop as shown in Figure 4. The weighing factor for the tie
switch and two neighboring switches are assigned the valu 1/m.
Branches b2, b2', and b3, b3' are 3/m. All the rest can be assigned in
a similar manner.
loop i
Open the selected loop
switch, starting from the
source loop
Constraint
-^violation ?
Yes
No
Branch
bo bi br
b2 te1 bj te'
b4 br te te'
te te' te t>?.
co
1/m
3/m
5/m
7/m
^ Stop J
Loss reduction
Figure 5 is the flowcliart of the overall reconllguration
process in the nonnal operational stalc.
Reconllguration should start from the upstream loops, that
is, according to the order of the mximum power flow calculated
for each loop. If a switch has already been selected in the previous
loop, it will be eliminated from searching in the next loop.
Example 1: Three-feeder system[9].
The sample distribution system in Figure 1 is used for
example. Tablc I shows the line data.
Closing all tie switches will crate a meshed network as
shown in Figure 6. Three loops are created in this network. The
switching ndices V, L and ) are computed and shown in Table n.
Fig. 5 Normal Loss Minimization Scheme
Resistance
(p.u.)
0.075
4-5
0.080
0.11
3.0
15
1.1
4-6
0.090
0.18
2.0
08
1.2
6-7
0.040
0.04
1.5
1.2
2-8
8-9
S-10
9-11
9-12
3-13
13-14
0.110
0.080
0.110
0.110
0.080
0.110
0.090
0.11
0.11
0.11
0.11
0.11
0.11
0.12
40
5.0
1.0
0.6
4.5
1.0
1.0
2.7
30
0.9
0.1
2.0
0.9
0.7
13-15
15-16
5-11
0.080
0.040
0.040
0.11
0.04
0.04
1.0
2.1
0.9
1.0
10-14
0.040
0.04
7-16
0.090
0.12
Reactance
(p.u.)
0.10
Cap.(MVAR)
(End Bus)
1.2
0.6
3.7
1.8
1.8
*V
Loop 3
sil
0.39753
0.71479
0.28416
sl2
0.64733
0.85964
0.55647
sl2
sl5
0.93953
0.99702
0.90409
0.74718
0.84942
0.74495
sl3
si 4
1
0.993S4
0.92522
0.86440
0.92522
0.85907
sl9*
si
sl6
Loop 2
0.97931
0.79692
0.20357
0.89944
0.73899
0,72764
0.88083
0.58891
0.14813
063256
0.76232
0.20518
0.60177
0.68281
0.88057
0.64585
0.76723
0.70264
0.76724
0.12376
0.99927
0.97941
0.99359
0.29202
0.78434
sl6
si 7*
sl5
sl7
si 8
sl9
0.08450
0.87994
s21
s23
0.97568
0.35179
0.64585
0.85964
0.63015
0.30241
s21
s24
0.99722
0.91905
0.70487
0.89412
0.70291
0,82174
s24
s25
0.63867
0.99824
0.86944
0.86439
0.55529
0.86287
s22
0.52372
0.68281
0.35760
s26*
0.99992
0.95444
0.95437
From Table II, we can see that the switches to be opened are
si9, si7, and s26 for the three loops respectively. The switching
operations are thus (sl5,s19) and (s21,sl7). Since s26 is already
opened, there is no need to change. For this particular example,
the power loss is 8.86% less than the original network as those
derived by other methods|2, 8-14] as shown in Table TTT.
Table III Loss analysis of the sample system
Loss (p.u.) Afier-
switchmg
0.005115
8.86
0.004662
Service restoration
Identify all the Ns
switches for restoration. i =
1
Constramt
violation ?
No
Yes
i >Ns
Yes
No
Abort the selected switch
Load shedding
Stop
Switch to be closed
1 (Group 1- Group 2)
2 (Group 3- Group 2)
sl9
sl7
Example 2.
The same system in Figure 1 is used again. Note that the
sample system is now a "better" network after the
reconfguration. A fault is assumed on component sl6. After fault
isolation, the system will be divided into four groups. As shown
in Figure 8, Group 2 has load points without sources. Group 2 is
the affected group. On the other hand, Group 1 and 3 have source
points, . so there are two paths for service restoration. Table IV
shows the two paths. From Table IV, we can see that Switch si7
should be chosen to cise. Running Load Flow shows that the
switching could crate a voltage violation. The next search si9
will also crate a voltage violation. Assuming that Load 12 is a
low priority load, Load 12 has to be shed to relieve the low
voltage violation on node 9. Service of Group 2 can now be
restored, satisfying the voltage and current constraints.
D
0.88083
0.87994*
are {s~, s9, sl4, s37, s32} for each loop. In loop 3, although
Switch s9 has the largest index x ~ t has already been selected
by the previous loop. Switch s 14 with second largest u. - will be
chosen mstead. Switch s37 is a tie switch and is
^D
IX b
D
0.6662
s3
0.3809
s9
0.86S9
s4
0 6647
slO
s5
0.5502
loop 3
switch
ti f
D
^D
s9
loop 4
switch
0.9591
s3
loop 5
switch
0 5104
s25
0.3694
slO
0.4476
s4
0 5333
s26
0.5459
0.3762
sil
0.654S
s5
0.3260
s27
0.1911
sil
0.8426
sl2
0.3973
s22
0 6274
s28
0.5473
s6
0.9270
s21
0.8597
si 3
0.7988
s23
0.32S5
s29
0.5320
s7
0.9471
s35
0.6130
sl4
0.9434
s24
0 8267
s30
0.7523
sl8
0.3200
s33
0.2186
s34
0.5024
s25
0.4214
s31
0.8916
sl9
s20
s33
0.1928
0.9272
0,8796
s26
s27
s28
s37
0 6850
0 7367
0.9353
0.9397
s32
s36
si 5
sl6
s!7
s34
s6
s7
0.9774
0.9724
0.8601
0.7149
0.9681
0 3052
0.8715
0.7369
s8
0.5830
loop 2
switch
0.0818
s8
Path
Switch to be closed
s9
1 (Group 1- Group 2)
2 (Group 1- Group 2)
3 (Group 1- Group 3)
4 (Group 1- Group 3)
5 (Group 1- Group 3)
b
0.8689*
0.9591
0.9395
0.7369*
0.9774
sl4
s37
s7
s32
Service restoration
Performance test
Switching
times
Goswami
Metlicd 1
Goswami
Method 2
Goswami
Method 3
Baran
Method 1
Baran
Method2,3
Proposed
Method
(35,8)
(37,28)
(33,7)
(33,6)
(33,6)
(33,7)
(37,28)
(33,7)
(34,9)
(35.11)
(35,11)
(35,9)
(36,32)
(35,11)
(35,14)
(36,31)
(36,31)
(34,14)
4
5
6
7
(34,! 4)
(8.9)
(33,7)
(28,37)
31.148
(34,14)
(36,32)
(28,37)
(11,9)
31.148
(36,32)
(37,28)
(6,33)
31 148
27.83
Total loss
reduction(%)
(36,32)
23.826
31.148
VII. REFERENCES
[1] Y. H. Tsai, "Fault processng of feeder dispalch control
system for Taipei South District Office", Taipower Monthly
Joumal, Vol. 567, 1995, pp. 11-25.
[2] K. Aoki, T. Ichimori, M. Kanezashi, "Nonrial state optimal