This letter from the Deputy Director (East) of the Pakhtunkhwa Highways Authority discusses issues with excavation work carried out by a contractor for an optical fiber cable project along the Maqsood - Lora – Ghoragali Road. Specifically, the letter notes that the excavation and backfilling was not done properly, resulting in settlement of loose areas and water damage to the road. Open trenches were also left near the road surface, damaging it. As no work plan was shared with the Authority, routine road maintenance cannot be carried out, deteriorating the road condition. The letter requests a joint meeting to discuss obtaining proper approval and coordinating work more closely with the Authority's field office going forward.
This letter from the Deputy Director (East) of the Pakhtunkhwa Highways Authority discusses issues with excavation work carried out by a contractor for an optical fiber cable project along the Maqsood - Lora – Ghoragali Road. Specifically, the letter notes that the excavation and backfilling was not done properly, resulting in settlement of loose areas and water damage to the road. Open trenches were also left near the road surface, damaging it. As no work plan was shared with the Authority, routine road maintenance cannot be carried out, deteriorating the road condition. The letter requests a joint meeting to discuss obtaining proper approval and coordinating work more closely with the Authority's field office going forward.
This letter from the Deputy Director (East) of the Pakhtunkhwa Highways Authority discusses issues with excavation work carried out by a contractor for an optical fiber cable project along the Maqsood - Lora – Ghoragali Road. Specifically, the letter notes that the excavation and backfilling was not done properly, resulting in settlement of loose areas and water damage to the road. Open trenches were also left near the road surface, damaging it. As no work plan was shared with the Authority, routine road maintenance cannot be carried out, deteriorating the road condition. The letter requests a joint meeting to discuss obtaining proper approval and coordinating work more closely with the Authority's field office going forward.
OFFICE OF THE DEPUTY DIRECTOR (EAST) ABBOTTABAD Ph No. 0992-382607, E-mail: ddeastpkha@gmail.com Street No. 03 House No. 417, Jinnah Abad Abbottabad
No. _
/07/ DD (E) / PKHA
Dated Abbottabad the __ _/11/2015
To Lt: Col. Sarwar Muhammad Butt (Retired) General Manager (Technical) FWO Communication Project Post Box No. 1073 Rawalpindi Subject: Reference:
RIGHT OF WAY (ROW) OPTICAL FIBER CABLE NETWORK (OFC)
1. Director (Maintenance) letter No. 2115/17-W/PKHA, dated 27-10-2015 2. Telephonic discussion of the undersigned with Col. Munsif Project Director OFC Project on 06-11-2015 and 08-11-2015
In continuation to above, this is to state again that the excavation works in
shoulders of Maqsood - Lora Ghoragali Road have been done by your Contractor under the above Project for laying of Optical Fiber Cable without obtaining any NOC from our Competent Authority and no work-plan has been shared with this office for the activities being carried out by your Contractor. The undersigned has visited the road and this is to state with concern that the excavation work and back filling along the road in which has so far been carried out in approx 25 Kms from Ghora Gali end, has not been done in appropriate manner. The back filling has been done without any leveling / dressing and compaction and residual excavated earth is found lying as heaps along the road. The loose back-filled shoulder areas have shown settlement and water is easily seeping into the shoulders and under the Asphalt Wearing course and causing damages. Open trenches have been left at numerous locations which are touching the edge of the asphalt surface and causing damage to it. The surface has also been cut and damaged where cable has crossed the road from one side to other. Due to above, and having no work plan shared with this office, this office cannot carry out the routine maintenance activities on the road, resulting in deterioration in the road condition. In light of the glimpses of the road condition presented above, it is suggested that a joint meeting may be conducted in the office of undersigned at an early date to discuss the issue of obtaining proper NOC in line with the SOPs of this Authority and carrying out the work accordingly in close liaison with this field office in the best interest of the Government and the public. An early response from your end is requested. DEPUTY DIRECTOR (EAST) Copy to:1) The Managing Director Pakhtunkhwa Highways Authority Peshawar for information please. 2) The Director (Maintenance) Pakhtunkhwa Highways Authority Peshawar with reference to above quoted letter for information. 2) The Assistant Director (East) PKHA, Haripur for information, report and to put up detailed cost estimate for restoration of damages caused to the road, within a week time.