Vous êtes sur la page 1sur 3

FLYOVERS PACKAGE VII

PAKHTUNKHWA HIGHWAYS AUTHORITY


PESHAWAR
F LYOVE R S PAC K A GE V I I
Project Name

Construction of Haripur Bypass Road


(Km. 0+000 to Km. 24+480 = 24.480 Km)

Package VII

Construction of 05 Nos. Flyovers

Location of Bridges

Contractor

At Km. 2+135, Km. 3+070, Km. 5+295, Km.


9+017 & Km 12+323
M/s Khattak Allied Construction Co.

Contract Value (in


Millions)
Date of Commencement

Rs. 136.232

Completion Period

Date of Completion

Defect Liability Period

PROGRESS
Cash Flow (Payment)

Cash Flow (%)

Progress Achieved during


the month

Planned Progress for the


month

Progress Achieved up to
date
Planned Progress up to
date
Lag/Lead (- , +)% during
the month

Lag/Lead(- , +)% during


the Period

Time Lapsed

:
:

39 Months
12 Months

PHYSICAL PROGRESS
1. Flyover at Km.
2+135
SPT

SPT completed at RHS abutment.

Test Pile

Boring for Test Pile is in progress.

2. Flyover at Km.
3+070
SPT

SPT completed at RHS abutment.

3. Flyover/Intercha
nge at Km.
5+295
SPT

SPT completed at LHS abutment.

4. Flyover at Km.
9+017
SPT

SPT completed at 97 feet depth due to rock at LHS


abutment.

5. Flyover/Intercha
nge at Km.
12+323
SPT

Vous aimerez peut-être aussi