LEAN MANUFACTURING
IN MICROSOFT DYNAMICS AX
Table of Contents
Introduction
0-1
Welcome ...........................................................................................................0-1
Microsoft Dynamics Courseware Contents........................................................0-2
Documentation Conventions .............................................................................0-3
Student Objectives ............................................................................................0-4
1-1
Objectives .........................................................................................................1-1
Introduction .......................................................................................................1-1
Core Concepts ..................................................................................................1-2
The Value Stream ...........................................................................................1-12
Introduction to Production Flows .....................................................................1-14
Introduction to Kanbans ..................................................................................1-16
Simple Production Flow ..................................................................................1-22
High Level Production Flow ............................................................................1-24
Setup and Interconnectivity .............................................................................1-28
Summary ........................................................................................................1-38
Test Your Knowledge ......................................................................................1-39
Quick Interaction: Lessons Learned ................................................................1-41
Solutions .........................................................................................................1-42
2-1
Objectives .........................................................................................................2-1
Introduction .......................................................................................................2-1
Production Flow Versions .................................................................................2-3
Takt and Cycle Times .......................................................................................2-4
Activities Setup .................................................................................................2-9
Lab 2.1 - Creating a Single Process Activity Production Flow .........................2-14
Single Transfer Activity Production Flow .........................................................2-20
Two Activity Production Flow: Process and Transfer.......................................2-22
Activity Relations.............................................................................................2-23
Lab 2.2 - Multiple Activity Production Flow ......................................................2-26
Multiple Activity Scenarios ..............................................................................2-29
Inventory Integration .......................................................................................2-34
Semi-Finished .................................................................................................2-41
Costing Implications ........................................................................................2-51
Summary ........................................................................................................2-53
Test Your Knowledge ......................................................................................2-54
Quick Interaction: Lessons Learned ................................................................2-56
Solutions .........................................................................................................2-57
3-1
Objectives .........................................................................................................3-1
Introduction .......................................................................................................3-1
Kanban Types ...................................................................................................3-2
Kanban Replenishment Strategies ....................................................................3-5
Subcontracting Activities and Manufacturing Kanbans ....................................3-22
Summary ........................................................................................................3-26
Quick Interaction: Lessons Learned ................................................................3-29
4-1
Objectives .........................................................................................................4-1
Introduction .......................................................................................................4-1
Kanban Rule Setup ...........................................................................................4-2
Lab 4.1 - Configure a Fixed Quantity Kanban Rule .........................................4-26
Kanban Job Planning ......................................................................................4-29
Lab 4.2 - Planning a Kanban on the Kanban Board ........................................4-39
Kanban Printing ..............................................................................................4-40
Kanban Processing - Process Jobs ................................................................4-42
Lab 4.3 - Kanban Processing on the Kanban Board for Process Jobs ............4-54
Kanban Processing - Transfer Jobs ................................................................4-55
Lab 4.4 - Kanban Processing on the Kanban Board for Transfer Jobs ............4-58
Summary ........................................................................................................4-59
Test Your Knowledge ......................................................................................4-60
Quick Interaction: Lessons Learned ................................................................4-63
Solutions .........................................................................................................4-64
5-1
Objectives .........................................................................................................5-1
Introduction .......................................................................................................5-1
Kanban Rule Setup ...........................................................................................5-2
Lab 5.1: Configure an Event Kanban Rule ......................................................5-17
Sales Line Events ...........................................................................................5-20
Lab 5.2 - Process a Sales Line Event .............................................................5-26
Capable to Promise ........................................................................................5-28
Lab 5.3 - Process a Sales Line Event with CTP ..............................................5-31
Kanban Line Event..........................................................................................5-34
Lab 5.4 - Kanban Line Event ...........................................................................5-38
BOM Line Event ..............................................................................................5-41
Lab 5.5 - Set up a BOM Line Event Kanban Rule ...........................................5-43
Lab 5.6 - Process a BOM Line Event ..............................................................5-45
Stock Replenishment Event ............................................................................5-46
Lab 5.7 - Set up a Stock Replenishment Event Kanban Rule ..........................5-50
Lab 5.8 - Process a Stock Replenishment Event ............................................5-52
Summary ........................................................................................................5-54
Test Your Knowledge ......................................................................................5-55
Quick Interaction: Lessons Learned ................................................................5-58
Solutions .........................................................................................................5-59
6-1
Objectives .........................................................................................................6-1
Introduction .......................................................................................................6-1
Planned Orders of Type Kanban .......................................................................6-2
Supply Schedule ...............................................................................................6-3
Kanban Rule Setup ...........................................................................................6-8
Lab 6.1 - Scheduled Kanban Rule Setup ........................................................6-24
Planning Scheduled Kanbans .........................................................................6-28
Lab 6.2 - Scheduled Kanban ...........................................................................6-31
ii
Table of Contents
Summary ........................................................................................................6-34
Test Your Knowledge ......................................................................................6-35
Quick Interaction: Lessons Learned ................................................................6-37
Solutions .........................................................................................................6-38
7-1
Objectives .........................................................................................................7-1
Introduction .......................................................................................................7-1
Subcontracting Vendor Payments .....................................................................7-3
Resource Group/Work Cell ...............................................................................7-6
Production Flow with Subcontracting Activities .................................................7-8
Lab 7.1 - Process a Subcontract Activity .........................................................7-21
Subcontracting as an Alternate Resource .......................................................7-26
Lab 7.2 - Using an Alternate Subcontractor.....................................................7-29
Cost Accounting of Subcontracted Services....................................................7-31
Summary ........................................................................................................7-36
Test Your Knowledge ......................................................................................7-37
Quick Interaction: Lessons Learned ................................................................7-39
Solutions .........................................................................................................7-40
8-1
Objectives .........................................................................................................8-1
Introduction .......................................................................................................8-1
Backflush Costing .............................................................................................8-2
Standard Cost Requirement ..............................................................................8-3
Components for Lean Manufacturing ................................................................8-4
Lab 8.1 - Configure Standard Costing in Microsoft Dynamics AX 2012 ...........8-13
Lab 8.2 - Calculation of Standard Cost Based on a Production Flow...............8-20
Reporting Production Flow Activities ...............................................................8-22
Lab 8.3 - End a Kanban Process Job and Observe Posted Costs...................8-29
Subcontracting ................................................................................................8-31
Lab 8.4 - Costing for a Subcontracted Activity.................................................8-32
Backflush Costing ...........................................................................................8-35
Lab 8.5 - Perform Periodic Backflush Costing .................................................8-42
Summary ........................................................................................................8-44
Test Your Knowledge ......................................................................................8-45
Quick Interaction: Lessons Learned ................................................................8-47
Solutions .........................................................................................................8-48
9-1
Objectives .........................................................................................................9-1
Introduction .......................................................................................................9-1
Kanban Quantity Calculation Policies................................................................9-2
Calculating Kanban Quantities ..........................................................................9-9
Lab 9.1 - Calculating Kanban Quantities .........................................................9-18
Summary ........................................................................................................9-21
Test Your Knowledge ......................................................................................9-22
Quick Interaction: Lessons Learned ................................................................9-24
Solutions .........................................................................................................9-25
iii
iv
Introduction
INTRODUCTION
Welcome
We know training is a vital component of retaining the value of your Microsoft
Dynamics AX 2012. investment. Our quality training from industry experts
keeps you up-to-date on your solution and helps you develop the skills necessary
for fully maximizing the value of your solution. Whether you choose Online
Training, Classroom Training, or Training Materials; there is a type of training to
meet everyone's needs. Choose the training type that best suits you so you can
stay ahead of the competition.
Online Training
Online Training delivers convenient, in-depth training to you in the comfort of
your own home or office. Online training provides immediate access to training
24 hours-a-day. It is perfect for the customer who does not have the time or
budget to travel. Our newest online training option, eCourses, combine the
efficiency of online training with the in-depth product coverage of classroom
training, with at least two weeks to complete each course.
Classroom Training
Classroom Training provides serious, in-depth learning through hands-on
interaction. From demonstrations to presentations to classroom activities, you
receive hands-on experience with instruction from our certified staff of experts.
Regularly scheduled throughout North America, you can be sure you will find a
class convenient for you.
Training Materials
Training Materials enable you to learn at your own pace, on your own time with
information-packed training manuals. Our wide variety of training manuals
feature an abundance of tips, tricks, and insights you can refer to again and again:
0-1
Challenge Yourself!
Level 3 exercises are the most challenging. These exercises are designed for the
experienced student who requires little instruction to complete the required task.
Step by Step
Level 1 exercises are geared towards new users who require detailed instructions
and explanations to complete the exercise. Level 1 exercises guide you through
the task, step by step, including navigation.
0-2
Introduction
Documentation Conventions
The following conventions and icons are used throughout this documentation to
help you quickly and effectively navigate through the information.
CAUTION: Cautions are found throughout the training manual and are preceded by
the word CAUTION in bold. Cautions are used to remind you of a specific result of a
specific action which may be undesirable.
HINT: Hints are found throughout the training manual and are preceded by the word
HINT in bold. Hints are used to suggest time-saving features or alternative methods for
accomplishing a specific task.
NOTE: Notes are found throughout the training manual and are preceded by the word
NOTE in bold. Notes are used to provide information which, while not critical, may be
valuable to an end user.
BEYOND THE BASICS: Advanced information found throughout the training manual
is preceded by the words BEYOND THE BASICS in bold. Beyond the Basics provides
additional detail, outside of standard functionality, that may help you to more optimally
use the application.
EXAMPLE: Examples are found throughout the training manual and are preceded by
the word EXAMPLE in bold. Examples bring to light business scenarios that may better
explain how an application can be used to address a business problem.
0-3
Student Objectives
What do you hope to learn by participating in this course?
List three main objectives below.
1.
2.
3.
0-4
Describe the High Level Production Flow example and introduce the
Contoso scenario.
Set up the production flow model and explain the capacity settings.
Describe standard costing and backflush costing and how they are
used for Lean manufacturing in Microsoft Dynamics AX 2012.
Introduction
Lean Manufacturing Concepts and Overview is designed to introduce students
to Lean principles and how Lean manufacturing for Microsoft Dynamics AX
2012 can be implemented to support those principles. The topics discussed are:
Introduction to Kanbans
1-1
Core Concepts
The core concepts for Lean manufacturing in Microsoft Dynamics AX 2012
provide a base level understanding of Lean concepts necessary to understand the
system functionality within Microsoft Dynamics AX 2012.
Customer Value
Flow
Pull
Perfection
1-2
Using one piece flow by linking all the activities and processes into
the most efficient combinations to maximize value-added content
while minimizing waste.
1-3
Cellular manufacturing
Flow manufacturing
Six Sigma
1-4
Paper kaizen
Cardboard simulation
Operator balancing
Workstation ergonomics
Lean Terminology
There are ten basic Lean core elements that will be used throughout the training
course. These are:
Value Stream
Kaizen
(Work) Cell
Cycle time
Takt time
Supermarket
Production flow
Backflush costing
Kanban
Heijunka leveling
1-5
1-6
Core elements
Definition
Value Stream
Kaizen
(Work) Cell
Definition
Cycle time
Takt time
1-7
Definition
Supermarket
1-8
Definition
Backflush
costing
Kanban
Heijunka
leveling
1-9
1-10
Kanban schedules
Delivery date control CTP: The CTP delivery date control helps in
verifying the requested ship date and potential of updating the
confirmed ship date on a sales line.
This is enabled by extending the existing delivery control with a CTP
option that will trigger a Master Scheduling explosion and the
returned futures date is used as the suggested ship date.
Sales event Kanbans with CTP check on the work cell schedule:
In Lean manufacturing, the availability of resources can be
determined by loading the Kanban jobs on the Kanban job schedule
that are related to a work cell. The availability of material is
determined by explosion and pegging within Microsoft Dynamics
AX 2012.
1-11
Support of Operations
In Microsoft Dynamics AX 2012, the Value Stream is used to support these
operations of the Lean Enterprise:
1-12
Cellular manufacturing
Flow manufacturing
Six Sigma
1-13
1-14
Continuous Improvement
To support continuous improvement, the production flows are implemented in
time-effective versions. This allows you to copy an existing production flow
versionincluding all related Kanban rulesto a draft version of the production
flow, and model the future-state production flow before validating and activating
it for production.
1-15
Introduction to Kanbans
The word Kanban means visible record in Japanese. Kanban has been
adopted by many industries as a method of controlling production and internal
supply.
Kanban is an essential part of a pull system of supply, which is a critical element
of Lean production/supply. When a Kanban has been consumed, it should be
passed (triggered) to the source of supply to replenish it. This source of supply is
defined through the production flow activities that the Kanban is linked to,
providing the definition of how the Kanban is filled. Kanban rules in Microsoft
Dynamics AX 2012 are essential to production flows, as they define the activities
that a Kanban rule goes through.
Kanban Types
Lean manufacturing in Microsoft Dynamics AX provides two Kanban types that
are used to define how the empty signal is filled: manufacturing and withdrawal.
Fixed quantity Kanbans to support traditional fixed card and two bin
type systems.
1-16
Scheduled Kanbans
Master Planning creates scheduled Kanbans automatically for planned Kanban
orders to cover the requirements within the firm horizon of the production
forecast. Scheduled Kanbans can also be manually created.
Event Kanbans
Event Kanbans are only created out of the related demand, so event Kanbans
belong to the category make-to-order. The creation of event Kanbans is
initiated when certain events occur. In Microsoft Dynamics AX 2012, these
events include when you create sales lines, when estimating production orders,
upon creation of upper level Kanban demand, or when reaching a certain level of
on hand inventory.
Sales line event: This event creates the pull for final assembly,
packaging, or simply shipping out of the sales orders. When a sales
order is entered, the Kanbans that are needed to produce or withdraw
the goods to satisfy the customer order are created automatically or
by the pegging event processing batch job.
1-17
1-18
1-19
The machine operator / shop floor worker is reporting the start and
end of jobs.
In the manufacturing floor, these three roles often have some overlap. Dependent
on throughput and importance, waterspiders have been found to be dedicated for
a single work cell or for a group of work cells. Some Lean organizations remove
the system interaction for the machine operators and use the waterspiders to
report the finished goods.
1-20
Production flow
Activity name
1-21
1-22
1-23
1-24
A process activity controls the packaging and a transfer activity controls the
transfer to VMI. A sales event Kanban is used to trigger the Kanban based on
sales order demand and pulls the finished good through the Packaging process to
the VMI warehouse.
1-25
1-26
1-27
Time Units
As production flow activities and resource group capacity settings require
definition in time units, these must be set up properly as a unit with a new
concept in Microsoft Dynamics AX 2012 of Unit class referring to Time.
Time units for days, hours, minutes and seconds should be present with the Unit
class of Time. Proper unit conversions should also be created for these time
units.
1-28
Hours: The capacity and load of a work cell are measured in periods
of hours and minutes.
NOTE: After you create a production flow model, you cannot change the value
of this field.
1-29
1-30
Work Cells
Lean work cells are modeled in Microsoft Dynamics AX 2012 using resource
groups, where resources are grouped to initiate a process flow. Activities within a
production flow are assigned to a work cell.
A work cell has a determined capacity that is typically expressed in throughput.
All manufactured items can be mapped to that throughput by setting a ratio
within the Lean schedule groups, which is described further in this topic.
The work cell represents the effective capability of all resources that are assigned
to the cell. It is handled as a black box, meaning that the internal structure of the
work cell is not documented in the system.
NOTE: Resource groups that are designated as work cells cannot be used for
long term capacity planning. To model long term capacity planning, a route must
be set up using resource groups that are not designated as work cells.
1-31
1-32
The Average throughput quantity defines the quantity that is produced in the
work cell during the selected Capacity period. If the capacity model is Hours, this
is not defined. The Unit of measure defines the unit of measure to use with the
Average throughput quantity.
To calculate the actual throughput of a specific day, the available working hours
of this day need to be determined out of the calendar. The actual throughput is
calculated by:
Actual throughput = Average throughput * actual working hours /
available hours (capacity period)
1-33
1-34
1-35
Warehouses
A new concept has been created within the warehouse location structure in
Microsoft Dynamics AX 2012. This concept, a Kanban supermarket, is a special
location type that has the inventory deduction policy on empty of the material
handling unit.
This type of supermarket is used for materialthat is, inventory controlled in the
supermarketbut will not be deducted by an inventory backflushing or manual
picking or transfer processes, but rather a Kanban empty signal that is registered
separately.
From a costing point of view, this behavior is similar to a supermarket in WIP,
with the exception that on-hand is shown in the supermarket.
1-36
References
Bicheno, J. (2004). The New Lean Toolbox (3rd ed.). Buckingham: Piscie
Books.
Blackstone, J., & Cox, J. (Eds.). (2005). APICS Dictionary (11th ed.).
Alexandria, VA: APICS The Association for Operations Management.
Gross J. M. & McInnis K. R. (2003). Kanban Made Simple: Demystifying and
Applying Toyotas Legendary Manufacturing Process. New York, NY:
AMAZOM, a division of American Management Association.
Rother, M. & Shook J. (2003). Learning to See: Value stream mapping to create
value and eliminate muda. Brookline, MA: The Lean Enterprise Institute, Inc.
Womack, J. P. & Jones, D. T. (2003) Lean Thinking: Banish Waste and create
Wealth in your Corporation. New York, NY: Free Press.
1-37
Summary
Lean Manufacturing Concepts and Overview provided a broad overview of
some of the main characteristics of Lean manufacturing and the functionality
within Microsoft Dynamics AX 2012 that supports Lean manufacturing. It
included these key points:
This lesson also introduced the Contoso scenario that will be used throughout the
course to help understand Lean manufacturing for Microsoft Dynamics AX 2012.
This lesson also summarized the ways in which Lean manufacturing in Microsoft
Dynamics AX 2012 supports Lean manufacturing processes.
1-38
1-39
6. Describe the two options for modeling capacity in Lean manufacturing for
Microsoft Dynamics AX 2012.
1-40
2.
3.
1-41
Solutions
Test Your Knowledge
1. List three Lean terms.
MODEL ANSWER:
Any three terms from the chapter, such as: Value Stream - the set of all
actions (both value added and non-value added) that are required to bring a
specific product(s) or service from raw material through to the customer;
Kanban - Japanese for visible record. Kanbans have been adopted by many
industries as a method of controlling production and internal supply. It can
apply to a paper ticket or a physical container; Kaizen - Japanese for
continuous improvement. Kaizen is a management philosophy, which
emphasizes employee participation, and in which every process is
continuously evaluated and re-evaluated for the elimination of waste.
2. What are the five Lean principles?
MODEL ANSWER:
1.
2.
3.
4.
5.
Identify value
Understand the Value Stream
Create flow
Introduce pull
Strive for perfection
1-42
1-43
1-44
Define predecessors/successors.
Introduction
Production Flows explains the purpose of production flows, how to set them up,
how they are vital as the foundation for the Lean manufacturing in Microsoft
Dynamics AX 2012, and the implications that the production flow has from a
costing and inventory point of view. The topics discussed are:
Takt/cycle times
Predecessors/successors
Costing implications
2-1
2-2
A unique name
A description
A production group
NOTE: The production group defines the set of accounts that are used for the
financial postings that are related to the production flow. The most important
accounts are the WIP and Offset accounts, which are the basis of variance
calculation for the production flow.
2-3
2-4
Takt unit
Fields and Definitions: Required Takt Time, Actual Takt Time, and
Period for Actual Cycle Time (Days)
Definition
Per cycle
unit of
measure
Quantity
per cycle
Takt unit
Select the unit of measure to use with takt times and cycle
times of the production flow. If the Default time unit is set
in the production parameters, the value is displayed here by
default, but you can change it.
2-5
Definition
Average
takt time
Minimum
takt time
Maximum
takt time
2-6
Field
Definition
Required
takt time
Definition
Actual takt
The takt time that is calculated based on the actual jobs that
are completed during a defined period. If the production
flow version is active, this field is calculated by using this
formula:
Actual takt = working hours of cycle time period / quantity
produced in cycle time period.
The output quantity of the production flow version is
determined from the last activity of the production flow. If
a production flow version has multiple delivery branches,
the quantities from the last activities of all branches are
summed.
Example
The working shift is eight hours, from 8:00 to 16:00. The
cycle time period is two days. The working hours of the
cycle time period are 16 hours, which is equal to 960
minutes. Assuming that 600 pieces were produced during
the last 16 hours of working time (on Wednesday at 24:00
all jobs that were completed between Monday 24:00 and
Wednesday 24:00 are included), the actual takt time is:
960 / 600 = 1.6 minutes
Period for
actual cycle
time (days)
2-7
Assume that Process D supplies pallets of 100 pieces and Process B produces
boxes of 10. The average takt of the production flow is set to be 10 minutes. As
10 activities for Process B are needed for one Process D, the cycle time ratio is
set to 10. On validation/recalculation of the production flow, the cycle time for
the process activity is calculated to one minute.
2-8
Activities Setup
The production flow is composed of a series of process and transfer activities.
Setting up these activities is described in these sections: Single Process Activity
Production Flow, Single Transfer Activity Production Flow, and Two Activity
Production Flow: Process and Transfer.
2-9
2-10
2-11
2-12
2-13
Challenge Yourself!
Use these steps to create the production flow.
1. Create a new work cell/resource group.
The resource group settings should be:
o Name: CSR_CONFIG
o Work cell: checked
o Site: 2
o Input warehouse: ElComp
o Input location: Output
o Output warehouse: SpProd
o Output location: ElPreAsm
o Cost Run time category: CS_Wrk_RA
o Calendar: Standard
o Production Flow Model: CarSpeakerModel
o Capacity period: Standard workday
o Average throughput: 250
o Unit: Pcs
o Effective: Today
o Expiration: None
2. Create a new production flow and version.
The production flow settings should be:
o Name: Remote PF
o Description: Remote Control Production Flow
o Value Stream: LeanProduction
o Production group: 10
o Effective: Today
o Expires: 31/12/2100
o Per cycle unit of measure: Pcs
o Quantity per cycle: 5
o Takt unit: min
o Average takt time: 9.6
2-14
2-15
2-16
2-17
2-18
2-19
2-20
2-21
2-22
A transfer is needed if the output warehouse and/or location of the work cell for
the process activity are not identical with the final point of consumption, which
in this example, is the location Warehouse Indock.
Activity Relations
If a production flow version has more than one activity, the sequence and
structure of the activities in the production flow version must be defined before
the production flow version can be activated. This definition is done by adding
activity relations.
2-23
2-24
2-25
Challenge Yourself!
Use these steps to perform the amendments:
1. Deactivate the current production flow version.
2. Create a new transfer activity.
The transfer activity settings should be:
o Name: RemoteTransfer
o Type: Transfer
o Replenishing Work cell: CSR_CONFIG
o Update on hand on receipt: selected
o Update on hand on pick: cleared
o Product type: Finished product
o Transfer to Warehouse: ElComp
o Transfer to Location: Output
o Freighted by: Shipper
o Runtime: 1 min per quantity 25
3. Create the predecessor/successor relationship between the process
and transfer activity with no constraints.
4. Activate the production flow version.
2-26
7. Select the New version activity > Create new plan activity button.
8. Select the Next > button.
2-27
2-28
Sequential Activities
Optional Activities
Alternative Activities
Parallel Activities
Sequential Activities
A common example of a production flow that consists of sequential activities is
the classic production or assembly line. It applies to any product that is built
activity by activity. These can be process and transfer activities performed in
sequence, as shown in this diagram.
To build a finished product for a customer, all activities must be processed and
completed. The production flow requires a fixed sequence.
A production flow would not be a flow if it contains activities that are not related
to the flow. This is why all activities of a production flow version must be related
to be able to validate and activate the version.
Optional Activities
Optional activities are activities that are only needed for specific products, but
need a considerable amount of time or specific and limited resources. Therefore,
these activities cannot be grouped into a single activity, but rather are
accommodated with optional activities that form a branch in the production flow.
2-29
2-30
Alternative Activities
Alternative activities are activities that can supply the same product by using
different activities. In this common example, the coating of the products can be
done in an internal work cell or by a subcontractor. As the subcontractor needs to
be supplied with the output of the milling activity, an additional transfer activity
is modeled. This illustrates that in many cases, an alternative activity is not the
same activity that is performed with a different resource.
The resulting activity flows for the alternative branches from milling to
supermarket would be:
Parallel Activities
Parallel activities in a production flow are different activities that provide
different outputs that are processed at the same point in time and contribute to the
same finished product.
2-31
This latter case is better known in the process industries, where processes can
have main products, co-products and by-products. Production orders and process
Kanbans have only one main output product. Co-products and by-products can be
modeled with a negative BOM quantity. It is not possible to create a pull for a
co-product, but it is possible to create flow.
A new option for Lean manufacturing for Microsoft Dynamics AX would be
modeling process A to output either semi-finished goods or products in WIP. The
concept of semi-finished is expanded further under Chapter 2: Production
Flows: Inventory Integration".
2-32
2-33
Inventory Integration
With the new production flow backbone within Lean manufacturing in Microsoft
Dynamics AX 2012, there have been several improvements to the way that Lean
functionality has been integrated with the inventory module, providing flexibility
in configuration of Lean scenarios. The main improvements are:
2-34
Production flow activities and Kanbans modeled against WMSLocations to match the physical flow without adding more WMSWarehouses.
Material warehouses
Supermarkets
The implications of the six WMS location elements are described in these
sections:
2-35
Implication
Material
warehouses
Supermarkets
A supermarket usually consists of a single WMSLocation. Because supermarkets are usually physically
placed on the shop floor and are to be replenished by
withdrawal Kanbans or transfer orders, the
supermarkets of a production flow should be grouped
within their own warehouse for each site.
2-36
WMS Element
Implication
Input location of
a work cell
Output location
of a work cell
Implication
Finished goods
warehouses
Outdocks and
shipments to
customers or
cross site
NOTE: In Microsoft Dynamics AX 2012, the cost context for an item is always
established by site.
2-37
Update on Hand
The default behavior of an activity is to update on hand. For each job related to
this activity, an inventory transaction is created.
The creation of these related transactions gives master scheduling full visibility
of the Kanban jobs based on activities that update on hand.
Because these transactions are also used within a costing context, activities
within a production flow must have update on hand activated when they are
supplying material to or consuming material from a costing boundary:
These conditions are validated either at the creation of the activity or at the
validation of the production flow.
2-38
WMS Integration
Integration into WMS functionality, output orders, and shipments are restricted to
Kanban jobs that update inventory.
2-39
2-40
Register scrap - when selected, the scrap factor set on the BOM
lines is applied on backflushing. This is only applicable if the update
on hand is selected for the picking activity.
Semi-Finished
A new concept of semi-finished activities has been introduced to support Lean
manufacturing operations. In traditional manufacturing within Microsoft
Dynamics AX 2012, production orders allow users to report jobs on an operation
level. With each finished operation, the product reaches a different state of semifinished product; however, this status is not registered on inventory unless the
last operation of a production order has been completed and the next BOM-Level
is reached. Semi-finished products that do not represent a BOM-Level are usually
identified by the product ID of the next BOM Level and the last completed
operation.
With Lean manufacturing for Microsoft Dynamics AX, this concept can now be
applied to production with the manufacturing Kanbans through the underlying
production flow activities.
Semi-Finished: Activities
In this figure, three activities are needed to assemble material from the BOM
lines to a finished product:
These activities use the activity settings that control product picking and receipt
in the production flow. An activity that outputs semi-finished (as Activity 1 and 2
in the figure show) in a production flow shows this behavior for all products,
independent of its BOM structures.
2-41
Semi-Finished: Settings
This figure shows semi-finished settings on a process activity.
Semi-Finished: Options
This table describes the options on production flow activities that affect pick and
receipt.
2-42
Option
Description
Update on
hand receipt
Description
Pick up
Select this check box if the activity consumes semifinished products. A semi-finished product is any
intermediate state of a product that is between two BOM
levels.
An activity that consumes semi-finished products cannot
be the first activity in a production flow.
Receive
Activities can only be related if the receipt and pick properties of the activities
match to the same product type. During entry of the activities, the product type is
checked against all of the related activities, and if it does not match, an error
message is displayed. Once an activity is related to another activity, the product
properties are read only and cannot be changed.
2-43
In this figure, Activity 1 supplies the supermarket for semi-finished products with
Kanban Rule1.
The Kanban job for Activity 1 has Kanban line transactions for the material, but
no receipt transaction of producing the semi-finished product. Semi-finished
products are by definition accounted in WIP, but not visible in inventory. They
are not visible in inventory; therefore, they are also not visible to master
scheduling.
WIP
A production flow must be related to a production group. In the production
group, the Work in Process (WIP) accounts for the production flow are specified.
We recommend that you create a single WIP account for each production flow,
because the backflush costing functionality that closes the costing period for all
production flows calculates the variances as the difference of the WIP value
before and after backflush costing for each single production flow.
2-44
2-45
2-46
The transfer activity needs a predecessor (in this case Blanking) with
update on hand on receipt = no. This implies that any products
received from Blanking stay in WIP. If the Blanks need to be booked
to inventory, an additional transfer is needed to move the products
out of WIP.
2-47
2-48
2-49
Kanban Supermarkets
The two possibilities to register material consumption related to Lean
manufacturing from inventory are:
2-50
Variable Consumption
For Kanban jobs that are based on process activities, the picking list lines are
created based on the active or the selected BOM on the creation of the Kanban
jobs. The BOM version cannot be replaced unless the job is unplanned.
So far, the possibility of variable consumption is limited in Lean manufacturing.
These are approaches to enable variable consumption:
When the Flushing principle is set to "finish" on the BOM line: the
actual consumption of Kanban picking lines is re-calculated when
the job is complete, calculating the total consumption needed for the
actual reported good and in addition the error quantity of the finished
product.
Costing Implications
The Microsoft Dynamics AX 2012 backflushing cost model streamlines
processes by reducing the number of inventory transactions that need to be
tracked on the production floor. A key feature is the ability to track Kanban
requirements without the need for levels in the bills of materials or placing
inventory on hand.
2-51
The update on hand activated flag must be selected when you are
supplying or consuming materials for activities at the start or end of
a production flow or if transferring materials between sites. This
relieves inventory of the components at their standard cost and
places the finished item in inventory at its standard cost.
Periodic costing computes the total cost of resource use for the
period and clears work in progress. The system computes variances
to standard cost for the period and production flow by comparing
total cost of resource use against the total completed goods for the
period at standard cost.
References
Rother, M. & Shook J. (2003). Learning to See: Value stream mapping to create
value and eliminate muda. Brookline, MA: The Lean Enterprise Institute, Inc.
Womack, J. P. & Jones, D. T. (2003) Lean Thinking: Banish Waste and create
Wealth in your Corporation. New York, NY: Free Press.
2-52
Summary
Production Flows provided setup and configuration scenarios for how
production flows, the mainstay of the Lean functionality, are implemented in
Microsoft Dynamics AX 2012. It included these key points:
This lesson also introduced various labs that provided instruction on creating new
production flows and activities in Lean manufacturing for Microsoft Dynamics
AX 2012.
2-53
2. Explain how minimum, maximum, average, and actual takt time is used.
3. What is meant by the term activity relation and how does it apply to process
activities?
2-54
2-55
2.
3.
2-56
Solutions
Test Your Knowledge
1. Explain what is meant by the term production flow version.
MODEL ANSWER:
The futures state value stream can be modeled in Microsoft Dynamics AX
2012 as a production flow version. All processes of the value stream are
modeled as process activities. Movements or transfers can be modeled as
transfer activities, if the transfer status has to be registered or if an integration
to inventory picking or consolidated shipments is required. Production flow
versions can have an effective and expiry date and must be activated prior to
use.
2. Explain how minimum, maximum, average, and actual takt time is used.
MODEL ANSWER:
The Average takt time for a production flow is the target takt time for a
production flow version and is used to monitor and analyze performance of
the work cell. The Minimum takt time is the minimum acceptable takt time
for a production flow. A warning message is displayed in the Cycle time
performance indicator of the Kanban board if the actual cycle time is less
than the minimum takt time. The takt time is calculated based on actual
production in a work cell that is completed during a defined period. The takt
time is calculated using this formula: actual takt = working hours of cycle
time period / quantity produced in the cycle time period.
3. What is meant by the term activity relation and how does it apply to process
activities?
MODEL ANSWER:
Activity relation as it applies to process activities allows process sequencing
by using predecessors and successor relationships that must be defined when
there is more than one activity in a production flow. Predecessor activities
are the upstream activities that are defined for a selected activity. Successor
activities are the downstream activity or activities that are defined for the
activity. When defining Predecessors and Successors, you only need to
define the predecessor or the successor and the other relationship will be
created automatically.
2-57
2-58
Define withdrawal Kanbans and explain how they are used to move
materials.
Describe fixed quantity Kanbans and how they compare to fixed bin
and fixed card Kanban systems.
Define event Kanbans and describe how they can be used to trigger
pull events.
Introduction
Use and Manage Kanbans provides a base level introduction into the various
types of Kanbans and where they are best suited to be used in Lean
manufacturing for Microsoft Dynamics AX 2012. The topics discussed are:
Manufacturing Kanbans
Withdrawal Kanbans
Event Kanbans
Scheduled Kanbans
3-1
Kanban Types
The two Kanban types within Microsoft Dynamics AX 2012 are: manufacturing
and withdrawal. These Kanban types are used to manufacture and transfer
materials in the production process.
Manufacturing Kanban
A Kanban of the type manufacturing is assigned to a process that adds value.
The Kanban is linked to a production flow activity and thus a resource group
with the role of a work cell. Manufacturing Kanbans relate to at least one process
activity. The first activity of a manufacturing Kanban must be a process activity.
A process activity can be followed by a transfer or another process activity,
allowing a Kanban to span multiple activities.
Subcontracting activities are also modeled as activities and use manufacturing
Kanbans for the processing that occurs at the vendor.
3-2
3-3
Withdrawal Kanban
A Kanban with the type withdrawal creates a transfer job that is based on a
transfer activity. Withdrawal Kanbans are used to move a Kanban of a specific
item between supermarkets, warehouses, and production locations. Withdrawal
Kanbans do not add value and do not get planned as manufacturing Kanbans do.
3-4
3-5
3-6
3-7
3-8
Scheduled Kanban
Master planning creates scheduled Kanbans automatically for planned Kanban
orders to cover the requirements within the firm horizon of the production
forecast. Scheduled Kanbans can also be manually created.
The behavior of scheduled Kanbans in master scheduling is similar to production
orders. Kanbans are created by firming planned Kanbans manually or using a
firming fence. The scheduled principle is used for items or variants that are
produced in a Lean work cell, but demand is created from forecast, customer, or
dependent demand, without being explicitly built to order.
The scheduled replenishment strategy should be applied when items are not
supposed to be produced without explicit demand, but the minimum batch sizes
cannot be lowered to a single piece flow. Examples of this being where the
minimum order size is greater than a quantity of one, or where multiple
requirements need to be grouped into a single planned supply, and the coverage
group in Master Planning is set to that of period.
3-9
3-10
3-11
Event Kanban
Event Kanbans are only created out of the related demand, so event Kanbans
belong to the make-to-order category. Event Kanbans are triggered and create
related issues when you create sales lines, estimate production orders, create
Kanbans that are supplied through event Kanban rules, or run the pegging event
processing where inventory has hit a minimum quantity.
3-12
3-13
3-14
3-15
3-16
3-17
3-18
Pierre has set up the production flow activities and Kanban rules for this
scenario. Eduardo creates and plans the Kanbans for the Process B on Site 2
which automatically creates and updates the dates for the withdrawal Kanbans to
bring the components to Site 2. Sammy, who is in charge of Shipping and
Receiving, processes the withdrawal Kanbans to move the components from Site
1 to Site 2.
3-19
3-20
Pierre has set up the production flow activities and Kanban rules for this
scenario. Eduardo defines the safety stock levels for the items and the forecast
schedules. MRP then creates the scheduled Kanbans where required. Susan then
enters many small orders that reduce inventory of the product and violates the
safety stock levels. This then creates event Kanbans that Lars notices on the Final
Assembly work cell and expresses for Susan.
3-21
8.
3-22
3-23
3-24
3-25
Summary
Use and Manage Kanbans provided an overview of the Kanban types and
replenishment strategies within Microsoft Dynamics AX 2012 that support Lean
manufacturing. It included these key points:
3-26
Fixed quantity Kanbans can be used to model fixed bin and fixed
card Kanban systems.
2. What is the difference between fixed and scheduled Kanbans and when
would each be used?
3. What are sales line events and how are they triggered?
3-27
5. How can an exceptional customer demand be handled so that all of the buffer
stock is not depleted if a customer places an exceptionally large sales order?
3-28
2.
3.
3-29
Solutions
Test Your Knowledge
1. Define the two types of Kanbans that are available in Microsoft Dynamics
AX 2012 and how they are used.
MODEL ANSWER:
The two types of Kanbans are withdrawal Kanbans and manufacturing
Kanbans. The first activity of a manufacturing Kanban must be a process
activity. A process activity can be followed by a transfer or another process
activity, allowing a Kanban to span multiple activities. A Kanban with the
type withdrawal creates a transfer job that is based on a transfer activity.
Withdrawal Kanbans are used to move a Kanban of a specific item between
supermarkets, warehouses, and production locations. Withdrawal Kanbans
do not add value. Withdrawal Kanbans are not planned as manufacturing
Kanbans are.
2. What is the difference between fixed and scheduled Kanbans and when
would each be used?
MODEL ANSWER:
Fixed quantity Kanbans: A fixed quantity Kanban rule relates to a fixed
Number of bins, meaning that the number of active Kanbans is constant.
Whenever a Kanban is consumed (emptied), a new Kanban of the same type
is recreated. Fixed quantity Kanbans are typically used in environments
where demand is somewhat constant. Kanban calculations can be run
periodically to recalculate Kanban quantities from Master Planning data.
Scheduled Kanbans: Master Planning creates scheduled Kanbans
automatically for planned Kanban orders to cover the requirements within
the firm horizon of the production forecast. Scheduled Kanbans can also be
manually created. The scheduled replenishment strategy should be applied
when items are not supposed to be produced without explicit demand, but the
minimum batch sizes cannot be lowered to a single piece flow. Examples of
this being where the minimum order size is greater than a quantity of one, or
where multiple requirements need to be grouped into a single planned
supply, and the coverage group in Master Planning is set to that of period.
3. What are sales line events and how are they triggered?
MODEL ANSWER:
This event creates the pull for final assembly, packaging, or simply shipping
out of the sales orders. When a sales order is entered, the Kanbans needed to
produce or withdraw the goods to satisfy the customer order are created.
Sales line events can be triggered at the time an order line is entered, and the
Kanban creation can occur automatically, in batch periodically, or manually.
3-30
3-31
3-32
Explain how to use printing pick lists and Kanban cards to signal
processes on the shop floor.
Describe how to use the Kanban board for process jobs when using
fixed quantity Kanbans.
Introduction
Fixed Quantity Kanbans covers how to set up and process fixed quantity
Kanbans in Microsoft Dynamics AX 2012.
The topics discussed are:
4-1
4-2
4-3
Type
Replenishment strategy
Kanban rule
Product selection
Multiple activities
Descriptions of the fields on the main form are presented in these sections:
4-4
Field
Description
Type
Replenishment
strategy
Kanban rule
Product selection
Description
Multiple activity
4-5
Product selection
Product
Product family
Replaced rule
Lead time
Unit of measure
Descriptions of the fields on the Details FastTab are presented in these sections:
4-6
Description
Product
selection
Product
Product
family
Description
Valid Effective
and
Expires
Select the dates when the Kanban rule becomes effective and
when it expires.
For Kanban rules that are expired and not replaced with an
updated rule, these conditions are true:
A Kanban job cannot be started.
Replaced
rule
The rule used when a Kanban rule expires. The rule can
belong to the same version or a new version of the same
production flow and needs to have the same item relation and
last activity of the Kanban flow.
4-7
Description
Lead time
Unit of
measure
4-8
Jobs that are scheduled for a period that ends after the due
date.
Default quantity
Minimum quantity
Maximum quantity
Variance below
Variance above
4-9
Description
Default
quantity
Minimum
quantity
Maximum
quantity
4-10
Field
Description
Product
quantity
variance
Variance
below
Variance
above
Description
Fixed kanban
quantity
Description
Alert
boundary
minimum
4-11
4-12
Field
Description
Automatic
planning
quantity
Maximum
planned jobs
Automatic printing
Circulating cards
Card assignment
4-13
4-14
Field
Description
Card number
sequence
Automatic
printing
Description
Print picking
list with card
Select this check box to print the picking list with the
Kanban card.
Kanban print
instructions
Circulating
cards
Number of
active cards
4-15
Description
Card
assignment
Single use
kanbans use
circulating
cards
4-16
First activity
Last activity
Register as empty
Inventory transactions
Financial transactions
Warehouse
Location
4-17
Description
First
activity
View the production flow and version that the first activity
references. If there are no Kanbans created for this rule, you
can edit this field in the activity lookup form.
Last
Activity
View the production flow and version that the last activity
references. If there are no Kanbans created for this rule, you
can edit this field in the activity lookup form.
Register
as empty
4-18
Description
Inventory
transactions
Financial
transactions
Description
Kanban flow
defined
Warehouse
Location
4-19
Kanban
Item number
Kanban quantity
4-20
Description
Kanban
Item
Number
Description
Kanban
quantity
Handling
unit status
4-21
4-22
4-23
4-24
4-25
4-26
4-27
4-28
When the process job is not planned, the estimated start date and time of the job
is determined out of the due date of the Kanban based on the Kanban flow entries
that describe the various activities that the Kanban goes through.
The Due Date of the process job = Due date of the Kanban sum of all
the lead times of all activities of the Kanban flow after the process.
The planned period date of the job is set when the job is planned; it holds the
start of the planning period.
4-29
Not planned
Planned
Prepared
In progress
Completed
On the Kanban board for process jobs and the Kanban schedule board, the
buttons for processing certain activities for that Kanban job (example
Prepare/Start) are activated depending on the Kanban job status.
4-30
4-31
4-32
4-33
4-34
Create kanban
Plan
Cancel
Descriptions of the buttons on the Kanban schedule board that are used for
planning are presented in these sections:
4-35
Description
Create
kanban
Plan
Cancel
Revert job
status
Description
Pegging
tree supply
status
Use
alternative
kanban
rule
Plan entire
pegging
tree
4-36
Pre-Conditions
Result
Completed to
in progress
In progress to
prepared
None
Prepared to
planned
None
Planned to not
planned
4-37
4-38
Challenge Yourself!
Use these steps to plan the process Kanbans created in "Lab 4.1: Configure a
Fixed Quantity Kanban Rule":
1. Open the Kanban schedule board.
2. Locate the schedule for work cell CSR_CONFIG.
3. Schedule the unplanned Kanbans for item CSS_Rem to a day with
available capacity.
Step by Step
Use these steps to plan the process Kanbans created in "Lab 4.1: Configure a
Fixed Quantity Kanban Rule":
1. To plan the Kanban, select Production control > Common > Lean
manufacturing > Kanban schedule board.
2. Select the View > Options > Change work cell button.
3. Change Work cell to "CSR_CONFIG.
4. Select the OK button.
5. Switch to the Unplanned tab on the Kanban schedule board.
6. Select a Kanban job from the unplanned Kanban jobs, and then drag
and drop onto a schedule period. Repeat for the remaining Kanban
jobs.
4-39
Kanban Printing
The printing of Kanban cards and pick lists is not required but can be used to
signal processes on the production floor. Microsoft Dynamics AX 2012 offers
several scenarios of printing pick lists and Kanban cards, including:
Use the printed Kanban cards to scan and report the progress of a Kanban using
the Kanban boards.
This figure is an example of a printed Kanban card.
4-40
The Kanban print button is available to print the Kanbans. On the Kanban
schedule board, right-click on the Kanban and select Print Kanban to print the
card.
None
Creation
Plan
Prepare
Start
Receive
When a Kanban reaches the specified status as set up in the Kanban rule, the
Kanban card will automatically print. If desired, a pick list could print at the
same time.
4-41
4-42
Description
Prepare
Empty
Update
picking list
Description
Start
transfer
Complete
transfer
4-43
Description
Prepare
Empty
Select kanban
Start transfer
Complete transfer
4-44
Button
Description
Pick list
Kanban
Description
Start
Complete
Complete
(details)
Update
registration
4-45
Description
Start
Complete
Select kanban
4-46
Button
Description
Refresh
Refresh cycle
Description
Job details
Dimensions
display
Description
Details
Production
instructions
Picking list
Pegging
4-47
Registration
Messages
Transfer jobs
4-48
Description
Registration
Cycle time
performance indicator
Description
Messages
4-49
Description
Transfer jobs
Description
Kanban quantity
overview finished
goods
4-50
Description
Kanban quantity
overview materials
Prepare Kanban
Prepare is an optional status update performed with the Prepare button. The
prepare function picks materials and prepares jobs to be in process. Materials
with the flushing principle set to Start are physically posted when the prepare
method is processed. A Kanban job that has components that are pulled through
an event Kanban can only be prepared if the component Kanbans have been
received.
Start Kanban
Start is an optional status updateperformed with the Start buttonthat starts
one or multiple selected Kanban jobs. The start update sets the realized start date
and time of the Kanban process job. If the Kanban job has not been through the
prepare status, the start update will also prepare the Kanban job.
Complete Kanban
Complete must be performed to update the selected jobs and complete the
Kanban process jobs with the requested quantity. The complete update sets the
realized end date and time of the Kanban process job. If the Kanban job has not
been through the prepare or start statuses, the complete update will also prepare
and start the Kanban job.
4-51
4-52
4-53
Challenge Yourself!
Use these steps to process the scheduled Kanbans from "Lab 4.2: Planning a
Kanban on the Kanban Board":
1.
2.
3.
4.
5.
Step by Step
Use these steps to process the scheduled Kanbans from "Lab 4.2: Planning a
Kanban on the Kanban Board":
1. To prepare the Kanban, select Production control > Common >
Lean manufacturing > Kanban board for process jobs.
2. If entering the board for the first time, select the CSR_CONFIG
work cell using the infolog. Otherwise, select the View > Options >
Change work cell button.
3. Change the Work cell to "CSR_CONFIG".
4. Select the OK button.
5. Select the appropriate Kanbans to prepare.
6. Select the Pick > Production > Prepare button.
7. To start the Kanbans, select the Manufacture > Production > Start
button.
8. To complete the Kanbans, select the Manufacture > Production >
Complete button
4-54
4-55
Description
Update picking
list
Start
Update
registration
Complete
Description
Start
Complete
Empty
Select
4-56
Button
Description
Pick list
Kanban card
Not planned
Started
Completed
When the transfer job is not planned, the due date and time of the job is
determined out of the due date of the Kanban based on the Kanban flow entries:
Due date of transfer job = due date (Kanban) sum of all the activity
times of all activities of the Kanban flow after the transfer
When a transfer job is started, the status is changed to "In progress"; when a
transfer job is completed, the status is changed to "Completed".
The inventory transaction of the job is physically posted (if any) upon either
status depending on the activity settings in the production flow.
4-57
Challenge Yourself!
Go to the Kanban board for transfer jobs and use these steps to transfer the
manufacturing Kanban from "Lab 4.3: Kanban Processing on the Kanban Board
for Process Jobs" to its final location:
1.
2.
3.
4.
Step by Step
Use these steps to transfer the manufacturing Kanban from Lab 4.3: Kanban
Processing on the Kanban Board for Process Jobs to its final location:
1. To begin the transfer process, select Production control >
Common > Lean manufacturing > Kanban board for transfer
jobs.
2. If entering the board for the first time, select Production flow
RemotePF using the infolog. Otherwise, select the View >
Options > Change Filtering options button and change Production
flow to RemotePF. Select the OK button.
3. Select the Kanbans.
4. To start the transfer, select the Transfer tab > Transfer > Start
button.
5. To complete the transfer, select the Transfer tab > Transfer >
Complete button.
4-58
Summary
Fixed Quantity Kanbans provided an overview of the setup, planning, and
processing of fixed quantity Kanbans in Microsoft Dynamics AX 2012. It
included these key points:
Kanban rules are supply policies that govern process and transfer
activities that are based on Kanbans. The Kanban rule for fixed
quantity Kanbans defines the replenishment strategy as fixed
quantity.
This lesson also included several labs to set up, plan, and process against Kanban
jobs using the Kanban schedule board, the Kanban board for process jobs, and
the Kanban board for transfer jobs.
4-59
4-60
5. What is the function of the Complete button on the Kanban board for
process jobs?
4-61
7. How are batch and serial numbers entered for product and materials of
Kanbans in Microsoft Dynamics AX 2012?
4-62
2.
3.
4-63
Solutions
Test Your Knowledge
1. Define fixed quantity Kanbans and describe how they are used in Microsoft
Dynamics AX 2012.
MODEL ANSWER:
A fixed quantity Kanban relates to a fixed number of handling units;
meaning that the numbers of active Kanbans are constant. Whenever the
products for a Kanban are consumed (handling unit is emptied), a new
Kanban of the same type is created. Fixed quantity Kanbans are often used
with fixed circulating cards, but can also be used with single use cards. A
fixed quantity Kanban is a make-to-stock scenario.
2. Describe what a Kanban rule is in Microsoft Dynamics AX 2012.
MODEL ANSWER:
Kanban rules are a supply policy that governs process and transfer activities
that are based on Kanbans. The Kanban rule defines the way in which an
item is produced or transferred, and links the item to the activities within the
production flow. Kanban rules are linked to a specific version of a production
flow, because the Kanban rules are linked to these activities to define how
they produce or transfer the various items.
3. Describe the three ways to plan or prioritize Kanban jobs.
MODEL ANSWER:
There are three ways to plan or prioritize Kanban jobs: 1. Plan manually in
the Kanban schedule board: the Kanban schedule board allows leveling and
planning for a number of days or weeks ahead (depending on the period type
related to the Lean production flow model); 2. Automatic planning based on
the automatic planning quantity: whenever the number of unplanned jobs
corresponds to this quantity, the automatic planning is called for that exact
number of Kanbans; 3. Denote a Kanban as a priority Kanban on the Kanban
board for process jobs.
4. What is the function of the Prepare button on the Kanban board for process
jobs?
MODEL ANSWER:
Prepare is an optional status update performed when the Prepare button is
selected. The prepare function picks materials and prepares the job. Materials
with the flushing principle set to Start and no flushing principle are
physically posted when the prepare method is selected.
4-64
4-65
4-66
Define how to set up and configure event Kanban rules and the
corresponding event types.
Describe how to use the Kanban board for process jobs when you
use event Kanbans.
Introduction
Event Kanbans covers how to set up and process event Kanbans in Microsoft
Dynamics AX 2012.
The topics discussed are:
Event Kanbans are only created out of related demand, so event Kanbans belong
to the category of make-to-order. Event Kanbans are created when certain
events occur. In Microsoft Dynamics AX 2012, these events include when you
create sales lines, estimate production orders, create upper level Kanban demand,
or when you reach a certain level of on hand inventory.
5-1
5-2
Type
Replenishment strategy
Kanban rule
Product selection
Multiple activities
Descriptions of the fields on the Kanban rules form that are specific to event
Kanbans are presented in these sections:
Description
Type
Replenishme
nt strategy
Kanban rule
Product
selection
Description
First plan
activity
Select the Kanban rules first activity. This links the Kanban
to the production flow version activity. A manufacturing
Kanban rules first activity must be a process activity. The
first and only activity of a withdrawal Kanban rule must be
a transfer activity.
Multiple
activities
5-3
Description
Last plan
activity
5-4
Field
Description
Product
selection
All: The Kanban rule is valid for all products that are
supplied by the Kanban rules last activity.
Description
Product
Product
family
Description
Maximum
quantity
5-5
Description
Automatic
planning
quantity
Maximum
planned jobs
5-6
Automatic printing
Descriptions of the fields on the Kanban and cards FastTab on the Kanban
rules form are presented in these sections:
Description
Card
number
sequence
5-7
Description
Automatic
printing
Description
Print
picking list
with card
Select this check box to print the picking list with the Kanban
card.
Kanban
print
instructions
5-8
Sales event
Never
Always
Sales lines
BOM lines
Descriptions of the fields on the Events FastTab on the Kanban rules form are
presented in these sections:
Kanban Rules Events FastTab: Fields: Sales Event and BOM Line
Event
5-9
Description
Sales event
BOM line
event
5-10
Description
Kanban
line event
Stock
replenish
ment
event
Description
Minimum
event quantity
5-11
Description
Event Kanban
handling unit
must be
received on
5-12
Field
Description
Delete unused
event Kanbans
Source
requirement
reservation
Description
Never
Always
Sales lines
BOM lines
5-13
5-14
Field
Description
Register
as empty
5-15
5-16
Challenge Yourself!
To perform this setup, follow these steps:
1. Create a new color Platinum as a dimension for product
SCPS_PSCL and release it into the company CEU.
2. Create a new Lean schedule group for the platinum color and
associate the new Platinum color to the group with these settings:
o Color: Platinum (C0C0C0)
o Throughput Ratio: 1
3. Create a Kanban rule for the process activity with these settings:
o Product: SCPS_PSCL
o Product dimension Color: Platinum
o Type: Manufacturing
o Replenishment strategy: Event
o First plan activity: PaintSpeakerCovers
o Maximum quantity: 5
o Alert boundary minimum: 0
o Alert boundary maximum: 10
o Automatic planning quantity: 1
o Sales event: Automatic
o Minimum event quantity: 1
o Source requirement reservation: Always; Sales order Always
o Register as empty: When source requirement is registered
5-17
8.
9.
10.
11.
5-18
5-19
Pegging Tree
The pegging tree form can be used from the sales order to provide a quick
inquiry of the availability of Kanbans. To view the pegging tree from the sales
order line, select the Product and supply > Requirements > View pegging tree
button.
5-20
5-21
5-22
5-23
5-24
Susan views the pegging tree and determines that the delivery date
is possible for the sales order by following the Sales order line >
Product and Supply > Requirement > View pegging tree
navigation.
5-25
Challenge Yourself!
To process the sales line event, follow these steps:
1. Enter a sales order with these settings:
o Customer: 2001
o Product: SCPS_PSCL
o Color: Platinum
o Site: 2
o Warehouse: PaCovers
o Quantity: 5
o Price: 10
2. View the pegging tree for the sales order.
3. Produce the quantity signaled by the Kanban on the Kanban board
for process jobs.
4. View the sales order pegging tree and the sales order reservation
status.
5-26
5-27
Capable to Promise
An important company objective in the Lean transformation process is improving
the ability to deliver a product that is assembled to order or built to order with a
competitive lead time.
The Capable to Promise (CTP) functionality provides the order takers with
accurate information at the point of order entry about the availability of products,
material, and resources that are needed to satisfy a specific customer demand.
This functionality can occur automatically at order entry time or in a batch job
after the sales order has been entered. The availability of resources for Lean
manufacturing can be determined by loading the Kanban jobs on the Kanban job
schedule that are related to a work cell. The availability of material is determined
by explosion and pegging, similar to manufacturing with production orders.
Where CTP is used for a given product, these prerequisites are suggested:
5-28
Susan creates a sales order and selects the delivery date control type
of CTP. A specific requested ship date from the customers is entered
and a requested receipt date is calculated through the transport
settings.
Susan creates a sales order line that defaults with the dates and the
delivery date control type of the sales order.
Susan selects an item, sets site, and warehouse quantity, and fills in
all requested data that is related to the sales line. Finally, she saves
the line.
System: this creates any sales event Kanbans that are set to
Automatic in the Kanban rule Sales line setting. These Kanbans
are also automatically planned if Automatic planning is set on the
Kanban rules. These Kanbans are planned according to the
Capacity shortage reaction settings on the production flow model.
System: scheduled Kanbans are created and the related jobs are
planned if Automatic planning is set on the Kanban rules and the
firming fence is set.
From the sales order header, select Sell > Generate > Calculate
confirmed delivery dates.
Run the CTP check for the sales orders without the Update
confirmed dates option selected.
The batch job will run the CTP explosion for all sales order lines and
provide an infolog with the resulting confirmed ship dates, but
without updating the sales line.
5-29
If the proposed ship dates are acceptable, the calculation is run again
with the Update delivery dates on sales lines option selected. This
runs the CTP explosion and updates the confirmed ship dates and
confirmed receipt dates on the sales lines.
5-30
Challenge Yourself!
To process the sales line event, follow these steps:
1. Configure the coverage group and default coverage settings to enable
CTP:
o On the Lean_Cover coverage group, turn on Futures messages
with a Futures time fence of 100.
o On the Default order settings for SCPS_PSCL, override the
sales lead time and set to 0 days, override the delivery date
control and set to CTP.
o In the Item coverage for SCPS_PSCL, override the firming
fence for the color Platinum to zero.
2. Enter a sales order with these settings:
o Customer: 2001
o Delivery date control: CTP
o Product: SCPS_PSCL
o Color: Platinum
o Site: 2
o Warehouse: PaCovers
o Quantity: 5
o Price: 10
3. View the Kanbans that were automatically created on the sales order
pegging tree.
5-31
5-32
5-33
5-34
Pierre has set up the production flow activities and Kanban rules for this
scenario. Susan enters the sales order for the product CSS_SS1G, speaker set 1
green. Eduardo plans the Kanbans for the speaker assembly and packaging work
cell. Lars uses the Kanban board for process jobs to produce the speaker kit on
the speaker assembly work cell. Ahmed views the pegging tree on the packaging
work cell to view the status of the speaker assembly Kanbans.
5-35
5-36
Navigation
Procedure
Kanban
details
Kanban
schedule
board
Kanban
board for
process
jobs
Navigation
Procedure
Sales order
line
5-37
Challenge Yourself!
To process the sales line event follow these steps:
1. Enter a sales order with these settings:
o Customer: 2002
o Product: CSS_SS1G
o Site: 2
o Warehouse: VMIW
o Location: Supermarke
o Quantity: 1
View the pegging tree for the sales order.
2. Plan the Kanbans on the packaging and speaker assembly work cells.
3. Produce the Kanban line events for the four speaker kits on the
Kanban board for process jobs speaker assembly work cell. Produce
the speaker set on the Kanban board for process jobs packaging work
cell.
4. Transfer the speaker set to the VMIW warehouse.
5-38
5-39
5-40
5-41
5-42
Challenge Yourself!
Use this procedure to set up the BOM line event scenario.
1. Create, approve and activate a BOM for the home theatre
entertainment system product 11001 for Site 2, with these
components:
o Product: 1201
o Warehouse: 21
o Quantity: 1
o Line type: Pegged supply
2. Activate production flow PF1.
3. Create a Kanban rule for the process activity with these settings:
o Product: 1102
o Type: Manufacturing
o Replenishment strategy: Event
o First plan activity: Assembly (PF1 production flow)
o Maximum quantity: 40
o BOM Line event: Automatic
5-43
5-44
Challenge Yourself!
To process the BOM line event follow these steps:
1. Create a new production order with these settings:
o Product: 11001
o Site: 2
o Quantity: 5
2. Estimate the production order.
3. View the Kanban that was created based on the BOM line event.
Step by Step
Use these steps to create a new production, estimate the production order, and
view the Kanban created based upon the BOM line event.
1. Navigate to Production control > Common > Production orders >
All production orders.
2. Select the New > Production order button.
3. Enter Item number 11001.
4. Change Site from 1 to 2.
5. Select Yes to the Insert the active versions for bill of materials and
route? question.
6. Enter a Quantity of 5.
7. Select the Create button.
8. In the production order, select the Estimate button.
9. Select the OK button.
10. Navigate to: Production control > Setup > Lean manufacturing >
Kanban rules.
11. Highlight the event Kanban for 1102 and view the created Kanban
based on the BOM line event.
5-45
The Pegging event processing can be filtered by the production flow, activity, or
Kanban rule for which to create the event Kanbans. It can also be filtered to
create event Kanbans only for a certain upper level source requirement, for
example, a sales order or Kanban. The stock replenishment event requires the
pegging event processing to create the event Kanbans.
5-46
5-47
5-48
5-49
Challenge Yourself!
These steps show how to set up the stock replenishment event scenario.
1. Set the item coverage settings with these settings:
o Product: SCPS_PSCL
o Color: Magenta
o Warehouse: PaCovers
o Location: Supermarke
o Minimum: 5
2. Create a Kanban rule for the process activity with these settings:
o Product: SCPS_PSCL
o Product dimension Color: Magenta
o Type: Manufacturing
o Replenishment strategy: Event
o First plan activity: PaintSpeakerCovers
o Maximum quantity: 5
o Stock replenishment event: Batch
5-50
5-51
Challenge Yourself!
Use this procedure to process the sales line event.
1. Enter a sales order with these settings:
o Customer: 2003
o Product: SCPS_PSCL
o Color: Magenta
o Site: 2
o Warehouse: PaCovers
o Location: Supermarke
o Quantity: 6
2. Ship the sales order.
3. Run the pegging event processing job and then prioritize and plan the
Kanban on the speaker cover painting work cell.
5-52
Select the Pick and pack > Generate > Packing slip button.
Change Quantity from Picked to All.
Select the OK button.
Select the OK button.
Select the Inventory button.
Select the On-hand inventory button and view the on-hand stock of
4 pieces, which has breached the minimum stock settings.
5-53
Summary
Event Kanbans provided an overview of the setup and processing of event
Kanbans in Microsoft Dynamics AX 2012. It included these key points:
Kanban rules for event Kanbans define the type of event that triggers
the Kanban to be created. These triggers can occur automatically,
upon running of a batch job, or manually depending on the type of
event and the Kanban creation policy of the event.
Sales line events are triggered based off of a sales line and can
include the use of CTP to provide more accurate delivery dates to the
customer.
Kanban line events are triggered based off of upper level Kanbans
and can be automatically or triggered using batch processing.
BOM line events are triggered based off of upper level production
order demand and are used in mixed mode environments where
traditional production orders are used for the downstream process.
This lesson included several labs to setup and process against Kanban jobs that
are triggered off of the various event types.
5-54
2. Describe sales line events and how they are used in Microsoft Dynamics AX
2012.
3. What is CTP?
5-55
5-56
7. Describe stock replenishment events and how they are used in Microsoft
Dynamics AX 2012.
5-57
2.
3.
5-58
Solutions
Test Your Knowledge
1. Define event Kanbans in Microsoft Dynamics AX 2012.
MODEL ANSWER:
Event Kanbans are only created out of the related demand, so event Kanbans
belong to the category make-to-order. The creation of event Kanbans is
initiated when certain events occur. In Microsoft Dynamics AX 2012, these
events include when you create sales lines, when estimating production
orders, upon creation of upper level Kanban demand, or when reaching a
certain level of on-hand inventory.
2. Describe sales line events and how they are used in Microsoft Dynamics AX
2012.
MODEL ANSWER:
The sales event is triggered by the creation or a change of a sales line,
regardless of where the sales line was created. The sales line event is used in
manufacturing environments where production is directly against the sales
order. The sales line event can also be used in the scenario where
exceptionally large orders are placed and instead of depleting the buffer, the
large order is made to order against an event Kanban.
3. What is CTP?
MODEL ANSWER:
Capable to Promise provides the order takers with accurate information at the
point of order entry about the availability of products, material and resources
that are needed to satisfy a specific customer demand. This functionality can
occur automatically at order entry time or in a batch job.
4. Describe Kanban line events and how they are used in Microsoft Dynamics
AX 2012.
MODEL ANSWER:
Kanban line events are used to pull the required material to a downstream
manufacturing process. Kanban line events are used to supply components
that are not stored in a supermarket by the line side because they are not used
frequently. These Kanbans (manufacturing or withdrawal) are created
automatically or manually by the upper level Kanban.
5-59
5-60
Introduction
In Microsoft Dynamics AX 2012, scheduled Kanbans can be created by Master
Planning based on requirements from demand forecast, supply forecast, or from
any other demand, for example sales orders, transfer orders or production orders.
The planned orders of type Kanban are created based on the Kanban rule and
follow the standard Master Planning logic and horizons. Master Planning item
coverage settings determine how the planned orders are created and whether they
are automatically or manually firmed.
Scheduled Kanbans are used for items that are not typically suited for fixed
quantity Kanban rules. These products are not as frequently used and one would
only want to base the production of these items on a schedule. The schedule will
be analyzed and updated weekly based on the customer sending their forecast. By
doing this, the planner can ensure that he or she can level production to meet the
schedule without building inventory.
Scheduled Kanbans can be used by a company where these scenarios are
required:
6-1
NOTE: Kanbans that are supplied on fixed quantity or event Kanban rules also
should have the planned order type Kanban. The related items should have a
firming fence of 0 days, else master planning might create warnings or errors
when trying to firm.
6-2
Supply Schedule
The Supply schedule form, new in Microsoft Dynamics AX 2012, provides a
comprehensive view of supply and demand. The supply schedule is displayed for
a specific plan and can be filtered to show the supply and demand for a specific
item and item dimension, a generic item with the item dimension left blank, or
for a product family. A period template allows the supply schedule to be viewed
by a configurable range of periods.
Navigation
Result
Main menu
Planned
order
Net
requirements
Product
information
management >
Common >
Released products
Select the Inquires
> Supply Schedule
button.
6-3
Navigation
Result
Released
products
Product
information
management >
Common >
Released products
Select the Plan >
Supply Schedule
button.
Item
allocation
key
Inventory and
warehouse
management >
Setup > Forecast
> Item allocation
keys
Select the Supply
Schedule button.
6-4
6-5
6-6
6-7
6-8
Type
Replenishment strategy
Kanban rule
Product selection
Multiple activities
Descriptions of the fields on the Kanban rules form that are specific to
scheduled Kanbans are presented in these sections:
Description
Type
Replenishment
strategy
Kanban rule
Product
selection
6-9
6-10
Field
Description
First plan
activity
Multiple
activities
Last plan
activity
Product selection
Product
Product family
Descriptions of the fields on the Details FastTab in the Kanban rules form are
presented in these sections:
6-11
Description
Product
selection
6-12
Field
Description
Product
Product
family
Default quantity
Minimum quantity
Maximum quantity
Variance below
Variance above
Descriptions of the fields on the Quantities FastTab in the Kanban rules form
are presented in these sections:
6-13
Description
Default
quantity
Minimum
quantity
Maximum
quantity
6-14
Field
Description
Product
quantity
variance
Variance
below
Variance
above
Description
Alert
boundary
minimum
6-15
Description
Automatic
planning
quantity
Maximum
planned jobs
6-16
Automatic printing
Description
Card number
sequence
6-17
Description
Automatic printing
6-18
Field
Description
Kanban print
instructions
Description
Register as
empty
Receipt
warehouse
6-19
Add
Remove
Details
Dimensions display
Filter
Descriptions of the fields on the Kanbans FastTab in the Kanban rules form are
presented in these sections:
6-20
Button
Description
Add
Remove
Description
Details
Description
Dimensions
display
Filter
Allows the user to filter and display Kanbans that have the
handling unit status of Empty.
For use in daily work routines, we recommend that you do
not select the Show empty check box. This setting keeps
the focus on active Kanbans.
6-21
6-22
6-23
Challenge Yourself!
To perform this setup, follow these steps:
1. Create a new color Orange as a dimension for product
SCPS_PSCL and SCPS_PSCR, and release them into the company
CEU.
2. Add the orange color to the product family IAK_SCSS and associate
10 percent to the orange color, deducting 10 percent from the yellow
color for items SCPS_PSCL and SCPS_PSCR.
3. Create a new Lean schedule group for the orange color and associate
the new orange color to the group with these settings:
o Color: Orange
o Throughput Ratio: 1
4. Ensure the default order settings for SCPS_PSCL and SCPS_PSCR
are set to Kanban.
5. Ensure the Scheduled Kanban rule exists for the speaker covers paint
shop scenario with these settings:
o Product Family: IAK_SCSS
o Type: Manufacturing
o Replenishment strategy: Scheduled
o First plan activity: PaintSpeakerCovers
o Default quantity: 5
o Maximum quantity: 5
6-24
6-25
6-26
6-27
6-28
6-29
MRP Considerations
If an item can be supplied by an event rule with a Kanban creation method of
batch, and a scheduled Kanban rule, the event processing for the item must be
finished before Master Planning can be progressed for that item. This creates a
dependency between the event batch processing and Master Planning. The user
should make sure that the pegging event processing job is run before Master
Planning.
6-30
Challenge Yourself!
Perform these steps:
1. Enter weekly demand forecast lines going out six months for product
SCPS_PSCR with these settings:
o Item allocation key: IAK_SCSS.
o Model: 100
o Monthly Quantity: 100
2. Run master planning.
3. Review the supply schedule board for the orange color and static
plan 10.
4. Plan a Kanban for SCPS_PSCR on the Kanban schedule board.
5. Process the Kanban on the Kanban board for process jobs.
For an additional challenge, repeat the process with the product SCPS_ PSCL.
6-31
6-32
6-33
Summary
Scheduled Kanbans provided an overview of the setup, planning, and
processing of scheduled Kanbans in Microsoft Dynamics AX 2012. It included
these key points:
Item coverage settings and coverage group settings are used when
you create planned Kanbans.
You can use item allocation keys to create scheduled Kanban rules
for product families.
Master Planning creates planned Kanbans that are firmed and create
scheduled Kanbans.
The two labs in this chapter helped you to set up, plan, and process Kanban jobs
using the supply schedule, Kanban scheduling board, and the Kanban board for
process jobs.
6-34
6-35
5. What is the supply schedule and how does it relate to scheduled Kanbans?
6-36
2.
3.
6-37
Solutions
Test Your Knowledge
1. Describe what settings control the quantities of the planned order of type
Kanban for an item.
MODEL ANSWER:
Planned orders of type Kanban can accumulate issues. The quantities that
are created in the planned orders of type Kanban are controlled through the
default order setting inventory quantities. For scheduled Kanbans, the
minimum and maximum inventory settings in the default order settings are
an important instrument to control the planned supply. Upon creation of the
scheduled Kanban, however, the default quantity on the Kanban rule is used.
2. How is a scheduled Kanban rule set up against a product family?
MODEL ANSWER:
Kanban rules can be set up against product families, such that those items
within the product family that are represented by the Kanban rule. The
product family is created as an item allocation key and associated with the
Kanban rule.
3. What are the ways that scheduled Kanbans can be created?
MODEL ANSWER:
Scheduled Kanbans are created by Master Planning based on requirements
from demand forecast, supply forecast, or from actual demand coming from
sales orders or production orders. The Kanbans are created based on the
Kanban rule and follow the standard Master Planning logic and firming
fences. Master Planning item coverage settings determine how the planned
orders are created and whether they are automatically or manually firmed
into scheduled Kanbans. Scheduled Kanbans can also be created manually by
the planner from the Kanban rule form, the Kanban schedule board and the
supply schedule.
6-38
6-39
6-40
Describe how to use the Kanban board for process jobs for
subcontracting activities.
Introduction
Microsoft Dynamics AX 2012 provides a company with flexibility to subcontract
activities that are not seen as core competencies. The subcontracting functionality
offers visibility of the components provided to the subcontractor, and also, if
required, capacity visibility at the subcontractor. Additionally, working with the
Kanban planning and process boards allows companies to make quick, informed
decisions to effectively manage demand variations.
7-1
7-2
Create the purchase agreement and agreement line for the vendor by
using the service item.
Create a resource group with the role of a work cell for the
subcontractor that provides the service.
Create a new production flow activity and relate the agreement to the
activity.
Purchase Agreements
You can locate the Purchase agreements form by navigating to Accounts
payable > Common > Purchase orders > Purchase agreements.
To create a new agreement, select the New > Purchase agreement button and
use the Purchase agreements form to create and define a new payment
agreement. The settings for subcontracting agreements are described in this topic.
The payment item that is used in activity-based subcontracting has to be a
product with the following properties:
For cost calculation of the products, a standard cost of the service has to be
defined.
To be available for use with activity-based subcontracting, a purchase agreement
with the vendor is needed.
7-3
7-4
Field
Description
Vendor account
Status
Effective date
Expiration date
Purchase
agreement
classification
Description
Item number
Quantity
This is the total quantity contracted with the vendor for this
subcontracting agreement line.
Unit
Price
Effective date
Expiration
date
7-5
7-6
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Select the Resource group > New > Resource group button.
Create a new record in the Resource groups form.
Name the Resource group (for example, enter SUB).
Enter a Description for the Work cell (for example, enter
Subcontracting Work cell).
Select the Site (for example, select 2).
Switch to the General FastTab.
Select the Work cell field.
Select the Input warehouse the vendors warehouse (for example,
select SCC_SC1).
Select the Input location the vendors location (for example, select
material).
Select the Output warehouse (for example, select PaCovers).
Select the Output location (for example, select Supermarke).
Switch to the Calendars FastTab.
Select the Add button.
Select the Calendar (for example, select SubK).
Switch to the Resources FastTab.
7-7
7-8
7-9
Product dimensions
Service ratio
Service unit
Descriptions of the fields for these four options are presented in these sections:
7-10
Description
Product
dimensions
Service ratio
Service unit
Description
Service
quantity base
7-11
Description
Based on the product quantity:
The service quantity is relative to the
scheduled/supplied product quantity. The supplied
product quantity can be calculated including or
excluding error quantities. This calculation method is
applied for all cases where the service price for each
unit of processed product is agreed upon.
Product quantity good:
Service quantity = Delivered product quantity good
(period) * Service ratio
Product quantity all:
Service quantity = Delivered product quantity (good +
error) (period) * Service ratio
Activity time:
The theoretical activity times are calculated based on
the processing time of the activity, the total processed
quantity, and the throughput ratio of the processed
product. This calculation method is applied for
services that are pay-by-the-hour and have a variance
in time for each processed product.
Activity time:Service quantity = Number of jobs
(period) * Activity run time * Service ratio
7-12
7-13
7-14
Description
Transfer from
location
warehouse
Vendor
7-15
Description
Transfer to
location
warehouse
Vendor
Freighted by
7-16
7-17
Production flow
Plan activity
Kanban rule
Vendor account
From date
To date
Receipt advices
7-18
Field
Description
Production
flow
Description
Plan activity
Kanban rule
Description
Vendor
account
From date
Select only jobs with the job date equal to or after this date.
To date
Select only jobs with the job date equal to or before this
date. For planned jobs the planned period date is used. For
completed jobs the actual completion date is used.
Description
Minimum
job status
Release
purchase
orders
7-19
Description
Aggregate
purchase
lines by
Receipt
advices
7-20
Day: creates one purchase order for each vendor for all
Kanbans that are scheduled for an individual day
Purchase agreements and an agreement line for the vendor using the
service item are configured.
Challenge Yourself!
Follow these steps to process the Kanban jobs with subcontracting activities.
1. Create Kanban jobs using the existing Kanban rules for material to
be transferred to the subcontractor.
o Kanban rule: 000044_1015
o Product: SCPS_UPSCR
o Type: Withdrawal
o Replenishment strategy: Scheduled
o Kanban Rule: 000043_1015
o Product: SCPS_UPSCL
o Type: Withdrawal
o Replenishment strategy: Scheduled
2. Create Kanban jobs using the existing Kanban rules for material to
be received from the subcontractor.
o Kanban rule: 000040_1015
o Product: SCPS_CSCR
o Type: Manufacturing
o Replenishment strategy: Scheduled
o Kanban rule: 000039_1015
o Product: SCPS_CSCL
o Type: Manufacturing
o Replenishment strategy: Scheduled
7-21
7-22
7-23
7-24
7-25
7-26
7-27
7-28
Challenge Yourself!
Use these steps to create the Kanban jobs and reschedule the Kanban jobs to an
alternate subcontractor.
1. Create Kanban jobs using the existing Kanban rules for material to
be received from the subcontractor.
o Kanban rule: 000039_1015
o Product: SCPS_CSCL
o Type: Manufacturing
o Replenishment strategy: Scheduled
7-29
7-30
Cost Calculation
When calculating the item cost based on the production flow, Microsoft
Dynamics AX 2012 uses the subcontracting service activity settings to define the
item cost. The cost breakdown shows the service item instead of the work cell as
a resource.
7-31
7-32
The backflush costing for Lean manufacturing at the end of a costing period
calculates the actual variances of the products to standard cost for products that
are produced out of the production flow during the costing period.
Currently, two Kanbans for 50 units each have been initiated, one Kanban of 50
units have been produced, and three Kanbans of 50 units of raw materials have
been replenished into the production flow. One hundred (100) units of service for
the subcontracting chroming process have been received at $0.65 for every unit.
7-33
7-34
Realized direct material cost for the period = $5.50; calculated at 150
units at $ 0.10 $9.50 =$5.50
Realized indirect cost for the period = $11; calculated at 200 percent
of $15 $19 = $11
The output of the period is $45, calculated at the 50 units of chrome cover left
received out of the production flow at $.90 standard cost for each unit.
The resulting variance to standard cost is then $9.
7-35
Summary
Activity Based Subcontracting included set up and configuration of
subcontracting activities in production flows, how to use alternate process flows
with subcontracting activities, how to use the Kanban board for process jobs for
subcontracting activities, subcontracting cost flow scenarios for Microsoft
Dynamics.
This lesson included several labs to set up, plan, and implement against
subcontracting Kanban jobs by using the Kanban schedule board, the Kanban
board for process jobs, and the Kanban board for transfer jobs.
7-36
2. Describe how the contract details for a subcontractor are stored with
Dynamics AX?
7-37
5. On which form would you find the function that allows you to switch to an
alternate subcontractor Kanban rule?
6. What new cost group type was introduced in Microsoft Dynamics AX 2012?
7-38
2.
3.
7-39
Solutions
Test Your Knowledge
1. What are the steps that are required to configure the system for
subcontracting Kanbans after negotiating with the vendor?
MODEL ANSWER:
Create the service item (product)
Create the agreement and agreement line for the vendor by using the service
item
If the subcontracted activity is taken place at a location that is provided by
the vendor, create a resource group with the role of a work cell for the vendor
facility that provides the service
Create a new version of a production flow (or a new production flow)
Create a new production flow activity and relate the agreement to the
activity
Connect the subcontracted activity to the other activities of the production
flow, and then validate and activate the flow
Validate and activate flow
2. Describe how the contract details for a subcontractor are stored with
Dynamics AX?
MODEL ANSWER:
The purchase agreement contains all the pricing information for the
associated service, which is provided by the subcontractor.
3. Describe how you link a vendor to the work cell?
MODEL ANSWER:
Link the vendor as a resource and then link the resource to a resource group
type work cell.
4. What periodic process do you use to generate purchase orders for
subcontracting?
MODEL ANSWER:
Create purchase documents for subcontracting. Navigate to Production
control > Periodic > Lean manufacturing > subcontracting documents.
7-40
7-41
7-42
Introduction
Production Flow Costing explains the costing setup required for production
flows in Microsoft Dynamics AX 2012 and the subsequent flow of costs
originating from transactions used to process Kanbans within those production
flows.
The topics discussed are:
Backflush costing
8-1
Backflush Costing
Backflush costing in Microsoft Dynamics AX 2012 can be defined by:
Cost accounts the direct material cost resulting from products, whose
physical flow in the production flow is maintained through on-hand
inventory (no backflush).
8-2
8-3
Material costs
Indirect costs
Outsourcing costs
A costing version, cost categories, cost groups and the costing sheet must be set
up prior to calculating the item's cost and activating that into a standard cost
which is required to create Kanban rules.
8-4
8-5
Production Group
The production group associated to the production flow defines the work in
progress related ledger accounts. The production group setup is used to resolve
the ledger accounts for posting in general ledger posting originating from the
production flow for these posting types:
Ledger - Items
Ledger - Resources
Ledger - Indirect
The Production groups form can be accessed from Production Control >
Setup > Production > Production groups.
8-6
8-7
8-8
BOM
Calculation for
Single or
Multiple Items
Coverage Settings
Run for a
single item
Not Applicable.
Run for a
single item
Not Applicable.
BOM
calculation is
run on a range
of products
Item coverage or
default order settings
for the site are set with
planned order type =
Kanban.
BOM
calculation is
run on a range
of products
Item coverage or
default order settings
for the site are set with
planned order type =
Production.
BOM
calculation is
run on a range
of products
8-9
The cost calculation will use the default production flow to determine the cost
when the cost calculation is run for a range of products and the item coverage
setting is set to a Planned order type of Kanban or when there is not a route
defined for the item.
8-10
8-11
The setting for Update on hand inventory can significantly change the financial
postings as described in the section "Reporting Production Flow Activities:
Variations When Reporting Production Flow Activities" within this chapter.
When this flag is unchecked, the items are considered as not inventory
controlled.
8-12
NOTE: This exercise is not specific to Lean manufacturing, but describes the
configuration of standard costing in general.
8-13
8-14
Challenge Yourself!
Use these steps to create a new costing version for calculating standard costs for
products manufacturing using a production flow.
1. Create a new standard cost type Costing version LeanStd.
2. Create new Cost groups for material costs, labor costs, indirect costs
and outsourcing costs.
3. Create a new Cost category and activate a price of 10.0.
4. Assign the Cost category to the Work cell SCPS_Cover.
5. (Optional) Set up the costing sheet set overhead of 5% over
material costs and a rate of $1 over manufacturing costs.
6. Assign the material cost group to items SCPS_UPSCR and
SCPS_PSCR.
8-15
8-16
8-17
8-18
8-19
Challenge Yourself!
Use these steps to activate the standard cost and calculate the standard cost for
the produced product.
1. Activate standard cost of 7.00 for Item number SCPS_UPSCR.
2. Calculate and activate standard cost for Item number SCPS_PSCR
based on Production flow Speaker covers coating.
3. View the detailed cost calculation with breakdown per cost group.
Step by Step
Use these steps to activate the standard cost and calculate the standard cost for
the produced product.
1. Navigate to Product information management > Common >
Released products.
2. Find Item number SCPS_UPSCR.
3. Select the Manage costs button.
4. Select Set up > Item price button.
5. Create a new record.
6. Select Version LeanStd.
7. Select Site 2.
8. Enter the Price as "7.00".
9. Select Incl. in unit price as yes.
10. Select File and then select Save.
11. Select the Activate button.
12. Close the Item price form.
13. Select Item number SCPS_PSCR.
14. Select the Manage costs > Set up > Item price button.
15. Select the Calculation button.
16. Select Costing version as LeanStd.
17. Select Color as Blue.
18. Select Site as 2.
8-20
8-21
8-22
Scenario Description
Result
Result
Transaction is cost
accounted as picking list and
costing sheet is set to apply
to production flow.
8-23
Debit
Product - Inventory
Product - Inventory
Credit
Debit
Quantity *
standard cost
emitting
organization
Product Inventory
or WIP, Shipping
Organization
Product Inventory
or WIP, Receiving
Organization
8-24
Credit
Debit
Cost Change
Variance, Receiving
Organization
Credit
Debit
Quantity *
standard cost
Product Inventory
Production Flow
Direct Material Period - WIP
Credit
Debit
Quantity *
standard cost
Product Inventory
Production Flow
Direct Material Period - WIP
Credit
NOTE: Emptying Kanban handling units for any other type of location but
Kanban supermarket will have no inventory transaction and thus not create the
transaction described in this section. Emptying handling units on Kanbans that
are posted to WIP (update on-hand on receipt = no) will cause backflush costing
to consider the material as consumed from WIP. Kanbans that are not empty will
be considered as remaining in WIP at backflush costing.
8-25
Debit
Product Inventory
Credit
Products standard
cost
Debit
Quantity *
standard cost
Product Inventory
Production Flow Direct Material Period - WIP
8-26
Credit
8-27
8-28
Challenge Yourself!
Use these steps to end a Kanban process job and observe posted costs:
1. Create a new fixed Kanban for Item number SCPS_PSCR in Color
Blue.
2. Complete the Kanban process job of the newly created Kanban.
3. View the production flow's current WIP balance, standard cost
transactions, labor transactions and indirect fixed cost transactions.
4. View corresponding ledger vouchers and observe postings that have
been made.
Step by Step
Use these steps to end a Kanban process job and observe posted costs:
1. Navigate to Production control > Setup > Lean manufacturing >
Kanban rules.
2. Right-click on the Kanban rule field and select Filter by field.
3. Enter the Kanban rule 000034_1015 to find the Kanban rule for
product SCPS_PSCR Blue.
4. Select the OK button.
5. Switch to the Kanbans FastTab.
6. Select the Add button.
7. Enter Number of new kanbans as "1".
8. Select the Create button.
9. Select the Close button.
10. Close the Kanban rules form.
11. Navigate to Production control > Common > Lean
manufacturing > Kanban board for process jobs.
12. Select the Change cell button.
13. Select Work Cell SCPS_Cover.
14. Select the OK button.
8-29
8-30
Subcontracting
Lean manufacturing for Microsoft Dynamics AX 2012 provides a new
architecture to control subcontracting work and the related purchase and receipt
process.
Earlier versions of Microsoft Dynamics AX modeled subcontracting of
operations for production orders based on a service item that had to be put into
the BOM. The effect on costing is that subcontracted services are accounted in
the cost category for material, not labor. In addition, a service is booked to
inventory and deducted to support the process.
As part of Lean manufacturing for Microsoft Dynamics AX 2012, an alternative
solution for subcontracting is implemented. The solution models the
subcontracting work as a service that is related to an activity of a production
flow. A new cost category of subcontracting is introduced and the subcontracting
services are no longer part of a BOM. The cost accounting of subcontracted work
is completely integrated in the new costing for a Lean manufacturing solution of
Microsoft Dynamics AX 2012.
8-31
Challenge Yourself!
Use these steps to view the costing for a Kanban job based on a subcontracted
activity.
1. Create a scheduled Kanban for Kanban rule transfer to 4101 for
Item number SCPS_UPSCR.
2. Create a scheduled Kanban for Kanban rule coating 4101 for Item
number SCPS_CSCR.
3. Complete the Kanban transfer job to transfer the materials to the
subcontractor.
4. Complete the Kanban process job.
5. View the current WIP balance for the production flow.
6. Run subcontracted documents creation to create a purchase order for
the subcontracted service.
7. Post a receipt for that purchase order.
8. Again view the current WIP balance for the production flow.
8-32
8-33
8-34
Backflush Costing
The periodic consolidation of the cost for a production flow or "backflush
costing" re-calculates the actual cost of material and products in WIP based on
the status of Kanban jobs and handling units in the production flow and
determines variances for the products supplied by the production flow.
8-35
Component
Quantity
Equivalent Quantity
FG_B
20
SF_01
40
SF_02
20
MAT_01
100
MAT_02
120
8-36
Debit
Production,
Report as Finished
Credit
Period quantity
completed @ standard
cost
Production Offset
Report as Finished
Period quantity
completed @ standard
cost
Production Receipt
Period quantity
completed @ standard
cost
Production Offset,
Receipt
Period quantity
completed @ standard
cost
Debit
Production,
Picking List
Credit
Production Offset
Account Picking
list
Production Issue
8-37
Debit
Production Offset
Account Issue
Credit
Debit
Applied direct
manufacturing
conversion cost.
Production WIP
Production WIP
Issue
Applied direct
manufacturing
conversion cost.
Applied direct
manufacturing
conversion cost.
Production Offset
Account Work
Center Issue
Production Work
Center Issue
Credit
Applied direct
manufacturing
conversion cost.
Debit
Applied direct
manufacturing
conversion cost.
Production
Indirect WIP
Offset
Production
Indirect WIP Issue
Production
Indirect
Absorption
8-38
Credit
Applied direct
manufacturing
conversion cost.
Applied direct
manufacturing
conversion cost.
Debit
Production
Indirect
Absorption Offset
Applied direct
manufacturing
conversion cost.
Credit
NOTE: The indirect manufacturing cost, accumulated over the period are all
cleared from WIP. The indirect cost for unused materials will need to be reinstated.
Insert a new conversion cost transaction (of type indirect cost) in the
physically updated stage for the calculated indirect cost. This
example shows the voucher entries that are created from this
calculation.
Posting Type
Debit
Production
Indirect WIP
Offset
Production
Indirect WIP Issue
Credit
Posting type
Debit
Production
Indirect
Absorption
Production
Indirect
Absorption Offset
Credit
8-39
The net realized usage over the period calculated by the aggregate of
material quantities whose inventory transactions have been
financially updated, at their respective standard cost roll up, and the
aggregate of conversion cost having been financially updated minus
the conversion cost transactions physically updated for the unused
materials.
Debit
Unused + in process
materials by end date @
standard cost.
Period balance on direct
material.
Credit
Period
balance on
direct
material.
8-40
Debit
Quantity in
WIP * Old
standard cost
Credit
8-41
Challenge Yourself!
Use these steps to perform periodic backflush costing.
1.
2.
3.
4.
Step by Step
Use these steps to create a Kanban for the item, start the Kanban, run periodic
backflush costing and analyze the variances and unused quantities.
1. Navigate to Production control > Setup > Lean manufacturing >
Kanban rules.
2. Right-click on the Kanban rule field and select Filter by field.
3. Enter the Kanban rule 000034_1015 to find the Kanban rule for
product SCPS_PSCR Blue.
4. Select the OK button.
5. Switch to the Kanbans FastTab.
6. Select the Add button.
7. Enter Number of new kanbans as 1.
8. Select the Create button.
9. Select the Close button for the Infolog.
10. Close the Kanban rules form.
11. Navigate to Production control > Common > Lean
manufacturing > Kanban board for process jobs.
12. Select the Change cell button.
13. Select Work cell SCPS_Cover.
8-42
22.
23.
24.
25.
26.
27.
28.
8-43
Summary
Production Flow Costing provided an overview of how costs flow to the ledger
when processing Kanbans and performing end of period backflush costing in
Microsoft Dynamics AX 2012. It included these key points:
Each production flow's current WIP value can be viewed from the
production flow Costing button.
This lesson included several labs to set up costing, execute Kanban jobs and view
the transactions flowing to the ledger. Also included was a description of how
the end of period backflush job relieves WIP and creates variances for a
production flow.
8-44
8-45
8-46
2.
3.
8-47
Solutions
Test Your Knowledge
1. Define backflush costing and describe how it is used in Microsoft Dynamics
AX 2012.
MODEL ANSWER:
Backflush costing is defined by: accumulates cost for resource usage by
production flow over period; allows simplified reporting of material and
operation resource usages within the production flow; accounts for direct
material cost to work in progress, for products supplied to production flow,
but whose physical flow in the production flow is not reported or maintained
(simplified backflush costing journal entries) and accounts for the direct
material cost resulting from products, whose physical flow in the production
flow is maintained through on-hand inventory (no backflush); values
production flow output (quantities produced) at the products standard cost;
absorbs and applies to production flows WIP account, the standard
conversions costs (direct and indirect manufacturing cost) for the production
outputs from a production flow; and allows an end of period backflush
costing process for computing variances to realized costs of quantities
produced for the period, and the correction of the financial situation
(relatively to the omitted journal entries for the product cycle).
2. Define which Kanban types do not require standard cost in Microsoft
Dynamics AX 2012.
MODEL ANSWER:
Withdrawal Kanbans for non-standard cost products may be created if the
update on-hand pick and update receipt are both set to yes. This will allow
moving a non-standard cost product from one inventory location into another
but will not allow movement of a non-standard cost product into or out of
WIP.
3. Define the four types of cost components of Lean manufacturing.
MODEL ANSWER:
The four types of costs for Lean manufacturing are: material costs,
manufacturing costs (also called "labor costs"), indirect costs and outsourcing
costs.
8-48
8-49
8-50
Introduction
Kanban Quantity Calculations covers the setup and process of calculating
Kanban quantities in Microsoft Dynamics AX 2012.
The topics discussed are:
Determining the Kanban quantity is one of the most important tasks of Kanban
planning. Microsoft Dynamics AX 2012 provides the capability to calculate the
Kanban quantity by taking forecast, actual demand from open orders, lead time to
replenish the item and historical demands into account. Kanban calculations can
be used with Kanban rules of replenishment strategy "fixed.
9-1
Once you have entered the parameters for the Kanban quantity calculation policy,
the formula created using this policy can be previewed in the Formula section of
the form.
9-2
Name
Description
Master plan
Safety factor
Service level
Period
Season
Descriptions of the fields on the Kanban quantity calculation policies form are
presented in these sections:
Description
Name
Description
Master plan
Minimum
kanban quantity
9-3
Description
Safety factor
Include safety
stock
Service level
9-4
Field
Description
Period
Description
Period: Days
behind
Period: Days
ahead
Description
Season
Season: start
day and month
9-5
9-6
9-7
9-8
9-9
Name
Policy
Status
9-10
Description
Name
Policy
Status
Description
Rule
effective
date
Rule
active as
of date
9-11
Description
Fulfilled
demand
period start
date
Fulfilled
demand
period end
date
Description
Demand
period start
date
Demand
period end
date
9-12
The Kanban rules must have an active date before or on the Rule
active as of date field on the Kanban quantity calculation. Only
rules that are active on this date will be selected.
Additional Kanban rules can be added to the Kanban calculation by selecting the
Add button. Kanban rules can be removed from the Kanban calculation by
selecting the Remove button.
Description
Kanban rule
Item number
Product
quantity
Kanban
quantity
Fulfilled demand
Demand
Safety stock
9-13
Product quantity
Kanban quantity
Unrounded
Description
Fulfilled
demand
Demand
Safety
stock
9-14
Field
Description
Product
quantity
Kanban
quantity
Description
Unrounded
The service factor is calculated from a chosen cycle service level that is
designated on the Kanban quantity calculation policy. For example, a 90%
service level results in a service factor (z) of 1.29. The higher z is, the lower the
risk of stocking out, but the higher the average inventory level is.
9-15
Demand is calculated from Kanban jobs where the job status is less
than Completed.
9-16
9-17
Challenge Yourself!
Pierre is now ready to run the Kanban quantity calculation to calculate the
Kanban quantities for the speaker covers. Follow these steps to calculate the
Kanban quantities:
1. Review the Speaker Covers Kanban quantity calculation policy and
ensure these settings:
o Master plan: 20
o Minimum kanban quantity: 1
o Safety factor: 2.0
o Period: checked
o Days behind: 5
o Days ahead: 30
2. Create 5 sales order lines to create sales order demand with these
settings:
o Item number: SCPS_PSCR
o Color: Blue
o Quantity: 500
o Site: 2
o Warehouse: PaCovers
o Requested ship dates: Starting today with each line one week in
the future.
3. Create a new Kanban quantity calculation against the Painted
Covers Kanban quantity calculation policy, generate, calculate and
update the Kanban rules.
9-18
9-19
9-20
Summary
Kanban Quantity Calculations provided an overview of the setup and process
of calculating Kanban quantities in Microsoft Dynamics AX 2012.
This lesson also included a lab on calculating Kanban quantities for the Contoso
speaker cover scenario.
9-21
3. How are Kanban quantity calculation policies associated with Kanban rules?
9-22
6. How is the average daily demand calculated for inventory controlled Kanban
rules?
9-23
2.
3.
9-24
Solutions
Test Your Knowledge
1. What does the Kanban quantity calculation policy control?
MODEL ANSWER:
The Kanban quantity calculation policy controls the parameters used for the
Kanban quantity calculation. The Kanban quantity calculation policy is
associated with the Kanban rule and used to perform the Kanban
calculations. It defines the formula to be used in the calculation, and the
horizons to be considered for fulfilled and future demand.
2. What is the formula used when Include safety stock is selected?
MODEL ANSWER:
Kanban quantity = (Average daily demand * Product lead time + Safety
stock) (Product quantity per handling unit) + Minimum Kanban Qty
3. How are Kanban quantity calculation policies associated with Kanban rules?
MODEL ANSWER:
The Kanban quantity calculation policy is associated with the Kanban rule.
One rule can have multiple calculations associated with it. This is done on
the Kanban quantity calculation policies FastTab on the Kanban rule.
4. Describe the process of running the Kanban quantity calculation.
MODEL ANSWER:
To calculate the Kanban quantity for Kanban rules, a Kanban quantity
calculation is created and associated with the Kanban quantity calculation
policy. The process of running the calculation includes generating the list of
Kanban rules associated with the Kanban quantity calculation policy,
calculating the Kanban rules, and updating the Kanban rules.
9-25
9-26
COURSE: 80310
LEAN MANUFACTURING
IN MICROSOFT DYNAMICS AX2012
INSTRUCTOR NOTES
10
12
13
14
15
16
17
18
Page
Timeline
Total Class Presentation: 24 hours
Chapter Description
Page
Number
Presentation 20 minutes
Presentation:120 minutes
10
Presentation: 60 minutes
12
13
14
15
16
17
Presentation: 90 minutes
18
Page
ii
Instructor Notes
Introduction
This chapter serves as introductory guidance to instructors teaching Microsoft
Dynamics class. The purpose of this chapter is to create consistency between all
classes. A participant attending a development class for software solution A
should experience the same class beginning as a participant attending an
application class for software solution B.
This chapter provides the following information:
Pre-class tasks
Post-class tasks
Page
Pre-Class Tasks
There are several tasks that instructors should take care of to ensure a smooth
start-up to the class. These include, but are not limited to:
o
o
o
Arrive early the first day of class leave yourself time to take
care of last minute details. Give yourself time to start up your
instructor machine, open your PowerPoint slide deck, and ready
your notes.
Display the Welcome slide the Welcome slide is the first slide
in each class slide deck. This slide should be on display as
participants enter the room.
Page
Instructor Notes
Class Logistics
Display the next slide and go through the logistics of times, breaks, and
bathrooms. This is also a good time to start setting expectations for participation:
class will start on time and participants are expected to shut off mobile phones
and email at that time.
Give the participants time to write down their objectives for the class. This will
help them focus on the information and skills they wish to learn during the class.
Page
Instructor notes do not have to be followed verbatim. They are suggestions for
how to present the material included in the training manual and must be adapted
to the individual skills and knowledge of the instructor.
However, the instructor notes are written by seasoned training professionals that
are themselves trained on the best practices in classroom training presentation.
Also the content developers have tapped into the various expert resources of
Microsoft Business Solutions consulting, development, and support professionals
as well as Microsoft Business Solutions Partner professionals to include the most
relevant information possible for instructors to use in their presentations.
Therefore it is important for instructors to incorporate the guidance provided by
the instructor notes into their presentations.
Page
Instructor Notes
Using Callouts
Callouts are used to draw attention to useful information. During class, consider
highlighting call-outs as appropriate. Below is an example of how callouts are
used throughout the training material.
CAUTION: Cautions are found throughout the training courseware and are preceded by
the word CAUTION in bold. Cautions are used to remind you of a specific result of a
specific action which may be undesirable.
HINT: Hints are found throughout the training courseware and are preceded by the
word HINT in bold. Hints are used to suggest time-saving features or alternative
methods for accomplishing a specific task.
NOTE: Notes are found throughout the training courseware and are preceded by the
word NOTE in bold. Notes are used to provide information which, while not critical, may
be valuable to an end user.
EXAMPLE: Examples are found throughout the training courseware and are preceded
by the word EXAMPLE in bold. Examples bring to light business scenarios that may
better explain how an application can be used to address a business problem.
BEST PRACTICES: Best Practices call out background information and best practices
about security, where appropriate, so that users can judge risks and benefits and make
informed choices (used to emphasize the secure choice over the insecure choice when
coding, installing, upgrading, configuration, and set up of the system.) As the instructor
make sure you call out these things as part of Best practices when implementing an ERP
system.
Page
Post-Class Tasks
Post-class tasks can vary depending on the class delivered and the training center
used, but generally include the following:
Page
Parking lot take down any remaining parking lot issues and
determine how answers will be distributed to participants.
Obtaining participant email addresses and sending out a group
email with follow-up answers is often a simple solution.
Instructor Notes
o
o
o
o
Timeline
Presentation: 20 minutes
Page
Timeline
Presentation: 120 minutes
Page
Instructor Notes
Set up production flow models, work cells as resource groups, Lean
scheduled groups and explain the capacity settings.
Describe the new warehouse concept for Lean manufacturing in Microsoft
Dynamics AX 2012.
Page
Define predecessors/successors.
Timeline
Presentation: 180 minutes
Page
10
Instructor Notes
Complete all demonstrations and labs to teach the concepts of production
flows, activities and how they are linked. Discuss the scenarios to show
the various elements of semi-finished activities in production flows.
Page
11
Timeline
Presentation: 60 minutes
Page
12
Instructor Notes
Explain how to use printing pick lists and Kanban cards to signal
processes on the shop floor.
Describe how to use the Kanban board for process jobs when
using fixed quantity Kanbans.
Timeline
Presentation: 240 minutes
Page
13
Define how to set up and configure event Kanban rules and the
corresponding event types.
Describe how to use the Kanban board for process jobs when
you use event Kanbans.
Timeline
Presentation: 240 minutes
Complete all demonstrations and labs to teach the concepts of Kanban line
events, sales line events, BOM line events and minimum stock events,
how they are set up and how they are processed.
Page
14
Instructor Notes
Timeline
Presentation: 150 minutes
Page
15
Describe how to use the Kanban board for process jobs for
subcontracting activities.
Timeline
Presentation: 180 minutes
Page
16
Instructor Notes
Timeline
Presentation: 180 minutes
Page
17
Timeline
Presentation: 90 minutes
Page
18