INSPECTION TEST PLAN

ITP TITLE: TILE WORKS

ITP No.

Project

Issue No. :

Location

Date

Doc. Ref

Inspection Keys: W-Witness, H-Hold, S-Surveilance, R- Record Review


Item
No.
1

Description of Work

Controlling Specification
and Acceptance Criteria

Verifying Document

Frequency of Testing and


Inspection

Inspection Parties
Contractor

ITL

ALARGAN/
CONSULTANT

Delivery, Storage and


Handling

1.1

Delivery of materials at
site

Technical
specification/Approved
method statement

Upon arrival at site

1.2

Storage of materials at
site

Technical
specification/Approved
method statement

Regular inspection and


monitoring

Technical specification

As per required by
Engineer

H/S

Mandatory at all time

S/R

H/S

Sampling and Testing

2.1 Testing of materials


3
3.1
4

Remarks

Health and Safety


All safety concern shall
be observed at all time.

Technical specification

Health and safety


requirements

Inspection

4.1 Surface preparation

4.2 Backfilling for floor tiles

4.3 Layout

Visual inspection, checklist,


approved drawings and
approved method
statement
Visual inspection, checklist,
approved drawings and
approved method
statement
Visual inspection, checklist,
approved drawings and
approved method
statement

Before and after


preparation

W/R

After backfilling

S/R

During and after layout

H/W/R

Compulsory

INSPECTION TEST PLAN


ITP TITLE: TILE WORKS

ITP No.

Project

Issue No. :

Location

Date

Doc. Ref

Inspection Keys: W-Witness, H-Hold, S-Surveilance, R- Record/Review


Item
No.

Description of Work

Controlling Specification
and Acceptance Criteria

Verifying Document

Frequency of Testing and


Inspection

Inspection Parties
Contractor

ITL

ALARGAN/
CONSULTANT

Remarks

4.4 Installation of floor tiles

Visual inspection,
checklist, approved
drawings and approved
method statement

During installation

H/S/R

Method statement and


manufacturer's written
instruction

4.5 Installation of wall tiles

Visual inspection,
checklist, approved
drawings and approved
method statement

During installation

H/S/R

Method statement and


manufacturer's written
instruction

4.6 Wall skirting

Visual inspection,
checklist, approved
drawings and approved
method statement

During installation

H/S/R

Method statement and


manufacturer's written
instruction

4.7 Grouting

Visual inspection,
checklist, approved
drawings and approved
method statement

During and after


application

H/S/R

4.8 Protection

Visual inspection,
checklist, approved
drawings and approved
method statement

During the curing period

H/S

S/W/R

Approved method
statement and Technical
specification

As per specification
requirement

H/W/R

Project specification and


Construction waste
Approved method
management disposal
statement

During construction and


at work completion

S/R

Field Quality Control

Waste Disposal

Remove excess
materials and waste
6.1
after completion of
work